52
BASIC ASSESSMENT REPORT 1 (For official use only) File Reference Number: 14/12/16/3/2/48 Application Number: Date Received: Basic assessment report in terms of the Environmental Impact Assessment Regulations, 2010, promulgated in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998), as amended. Kindly note that: 1. This basic assessment report is a standard report that may be required by a competent authority in terms of the EIA Regulations, 2010 and is meant to streamline applications. Please make sure that it is the report used by the particular competent authority for the activity that is being applied for. 2. This report format is current as of 1 September 2012. It is the responsibility of the applicant to ascertain whether subsequent versions of the form have been published or produced by the competent authority 3. The report must be typed within the spaces provided in the form. The size of the spaces provided is not necessarily indicative of the amount of information to be provided. The report is in the form of a table that can extend itself as each space is filled with typing. 4. Where applicable tick the boxes that are applicable in the report. 5. An incomplete report may be returned to the applicant for revision. 6. The use of “not applicable” in the report must be done with circumspection because if it is used in respect of material information that is required by the competent authority for assessing the application, it may result in the rejection of the application as provided for in the regulations. 7. This report must be handed in at offices of the relevant competent authority as determined by each authority. 8. No faxed or e-mailed reports will be accepted. 9. The signature of the EAP on the report must be an original signature. 10. The report must be compiled by an independent environmental assessment practitioner. 11. Unless protected by law, all information in the report will become public information on receipt by the competent authority. Any interested and affected party should be provided with the information contained in this report on request, during any stage of the application process. 12. A competent authority may require that for specified types of activities in defined situations only parts of this report need to be completed. 13. Should a specialist report or report on a specialised process be submitted at any stage for any part of this application, the terms of reference for such report must also be submitted.

BASIC ASSESSMENT REPORT - GIBB

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

Page 1: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

1

(For official use only)

File Reference Number: 14/12/16/3/2/48

Application Number:

Date Received:

Basic assessment report in terms of the Environmental Impact Assessment Regulations, 2010, promulgated in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998), as amended.

Kindly note that: 1. This basic assessment report is a standard report that may be required by a competent authority

in terms of the EIA Regulations, 2010 and is meant to streamline applications. Please make sure that it is the report used by the particular competent authority for the activity that is being applied for.

2. This report format is current as of 1 September 2012. It is the responsibility of the applicant to ascertain whether subsequent versions of the form have been published or produced by the competent authority

3. The report must be typed within the spaces provided in the form. The size of the spaces provided is not necessarily indicative of the amount of information to be provided. The report is in the form of a table that can extend itself as each space is filled with typing.

4. Where applicable tick the boxes that are applicable in the report.

5. An incomplete report may be returned to the applicant for revision.

6. The use of “not applicable” in the report must be done with circumspection because if it is used in respect of material information that is required by the competent authority for assessing the application, it may result in the rejection of the application as provided for in the regulations.

7. This report must be handed in at offices of the relevant competent authority as determined by each authority.

8. No faxed or e-mailed reports will be accepted.

9. The signature of the EAP on the report must be an original signature.

10. The report must be compiled by an independent environmental assessment practitioner.

11. Unless protected by law, all information in the report will become public information on receipt by the competent authority. Any interested and affected party should be provided with the information contained in this report on request, during any stage of the application process.

12. A competent authority may require that for specified types of activities in defined situations only parts of this report need to be completed.

13. Should a specialist report or report on a specialised process be submitted at any stage for any part of this application, the terms of reference for such report must also be submitted.

Page 2: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

2

14. Two (2) colour hard copies and one (1) electronic copy of the report must be submitted to the competent authority.

15. Shape files (.shp) for maps must be included on the electronic copy of the report submitted to the competent authority.

Page 3: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

3

TABLE OF CONTENTS __________________________________________________ Section A: Activity information ................................................................................................................................. 4 1. Project Description ........................................................................................................................ 4 2. Feasible and Reasonable Alternatives .......................................................................................... 9 3. Physical size of the activity.......................................................................................................... 12 4. Site Access ................................................................................................................................. 13 5. Locality Map ................................................................................................................................ 13 6. Layout/ Route Plan ...................................................................................................................... 13 7. Sensitivity Map ............................................................................................................................ 14 8. Site Photographs ......................................................................................................................... 14 9. Facility Illustration ........................................................................................................................ 14 11. Applicable legislation, policies and/or guidelines ........................................................................ 22 12. Waste, effluent, emission and noise management ...................................................................... 25 13. Water Use ................................................................................................................................... 27 14. Energy efficiency ......................................................................................................................... 27 Section C: Public Participation .............................................................................................................................. 35 Section D: Impact Assessment ............................................................................................................................. 38

Methodology for Impact Significance Scoring .............................................................................. 38 SECTION E. Recommendation of practitioner ................................................................................................. 51 Section F: Appendices .......................................................................................................................................... 52

Page 4: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

4

SECTION A: ACTIVITY INFORMATION

Has a specialist been consulted to assist with the completion of this section? YES NO

If YES, please complete the form entitled “Details of specialist and declaration of interest” for the specialist appointed and attach in Appendix I. 1. PROJECT DESCRIPTION a) Describe the project associated with the listed activities applied for

Background Information The Applicant, Transnet Pipelines (TPL), was established in 1965 to address the need for a liquid fuels and gas transportation entity. The liquid fuels pipeline network traverses five (5) provinces, KwaZulu-Natal, Free State, Gauteng, North West and Mpumalanga and includes a section of the liquid fuels pipeline from the O.R. Tambo International Airport in Johannesburg to Waltloo in Pretoria which was constructed in 1973. This section of the pipeline has however been exposed at the stream crossings in the Moreleta Spruit in Pretoria, Tshwane Municipality, due to erosion in those areas. In response to the impact of erosion on the pipeline TPL undertook the construction of gabions to protect the exposed liquid fuels pipeline at the stream crossings. The gabions are located on two sites: Site 1 – located in Moreleta Park adjacent to Garsfontein Road; Site 2 – located between Garsfontein and Pretorius Park adjacent to Garsfontein Road (see Appendix A). Although construction of gabions (the activity) requires approval in terms of the Government Notice Regulation (GNR) No. 544 (activity number 11 and 18) and GNR 546 (activity number 16 (b)) of 2nd August 2010 of the National Environmental Management Act No. 107 of 1998 (NEMA) , work commenced on site prior to obtaining the approval as required in terms of the above mentioned legislation. This was mainly due to the potential risk to infrastructure and human life associated with an exposed petroleum pipe. Also as this activity has the potential to impede the stream bed and flow during and post construction , other applicable legislative requirements include the General Authorisations or Water Use License applications in terms of Section 21 (c) of the National Water Act. TPL has since engaged with the Department of Environmental Affairs (DEA), Department of Water Affairs (DWA), City of Tshwane Nature Conservation and the Gauteng Department of Agriculture and Rural Development (GDARD), to give a detailed account of the need and desirability of the work and to ensure that all requirements are met in terms of the information requested by and placed before the Competent Authority for decision making. An Environmental Management Plan (EMP) including a letter of motivation for the commencement of construction was submitted to the DEA on 15 May 2012, and the EMP was subsequently approved. The DEA however also requested that a formal NEMA Section 24G application form for the rectification of unlawful commencement or continuation of a listed activity be lodged. The Section 24G application form was submitted to the DEA on 13 June 2012 (attached in Appendix E), and the DEA responded in a letter dated 13 August 2012 requesting further information (Appendix E). Transnet Pipelines (TPL) has therefore appointed GIBB (Pty) Ltd (GIBB) as the Environmental Assessment Practitioner (EAP) to undertake the relevant environmental authorisation processes for the Moreleta Spruit Gabions Construction Project.

Page 5: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

5

This Draft Basic Environmental Assessment Report (BAR) has been compiled in support of the application for Environmental Authorisation, as required by the NEMA and associated EIA Regulations. Technical Activity Description: The Construction of Gabions along the Moreleta Spruit During routine maintenance, TPL identified two (2) sites along the Moreleta Spruit where the erosion of the channel bottom and banks has resulted in the exposure of the high pressure petroleum fuel pipeline. The sites are in close proximity to each other (approximately 200m apart). Site 1 The site is located adjacent to the East Side Church, on the northern side of Garsfontein Road in Moreleta Park. Construction activities that already commenced in May 2012 include:

Excavation of a river diversion of the Moreleta Spruit (approximately 20m in length) from its original alignment to an alignment approximately 5m to the West to facilitate construction works. The new channel through which the river is being diverted is approximately 0.6m from natural ground level.

An excavation of approximately 5m x 5m within the initial alignment of the Moreleta Spruit, indicating the start of construction for placement of the founding mater ial for the Reno-mattress (Appendix C).

Importing and offloading of the rock material to be used in the Reno-mattress to be constructed in the original alignment of the Moreleta Spruit.

Excavation of the foundation area for the Reno-mattress.

Stockpiling of excavated soil.

Placement of two portable chemical toilets to the East approximately 50m from the Moreleta Spruit.

Site establishment, including placement of a container, to be used for construction personnel on site, for site meeting and as an on-site office.

Limited vegetation cutting and exotic vegetation clearing.

Construction of Reno-mattress including the laying of the geotextile layer.

Install dewatering points and construct silt traps to filter water prior to it filtering back into the wetland system.

Reinstate wetland including but not limited to the following: o Ensure subsoil is at correct levels as per pre-construction survey; o Ensure adequate topsoil is present; o Establish indigenous vegetation with hydroseeding (if required); and o Ensure Moreleta Spruit runs as per original alignment.

General reinstatement and clean-up, including disposing of waste at the nearest licensed landfill site.

Site 2 The site is located on the southern side of Garsfontein Road, between the suburbs of Pretorius Park and Garsfontein. Physical construction works at the time of submission of the Section 24G application form included the offloading of rock material for the gabions to be constructed at the site to arrest the erosion channel that is exposing the petroleum pipeline. Subsequent work needed includes but is not limited to:

Site establishment.

Vegetation cutting and exotic vegetation clearing.

Stripping and stockpiling of soil material in separate stockpiles (topsoil versus subsoils).

Construction of works access to the working area, which may require the cutting back of the banks of the Moreleta Spruit to allow the placement of the gabions.

Damming up of the upstream section of the Moreleta Spruit just below the Garsfontein Road

Page 6: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

6

crossing using sandbags.

Creating an area for 2 bunded 0.10 or 0.15 metres high volume pumps to stand in. these pumps will facilitate the cross-pumping of water from above the works area to a point below the works area to ensure a continuous flow of water, that will be unaffected by the cons truction works. Prior to release, the water will pass through a silt trap that will filter any excess silt. The silt will be disposed of at a licensed landfill site.

Excavation in the Moreleta Spruit river bed to construct the foundation which will support the new gabions.

Construction of the gabions.

Backfilling of the area behind the gabions and compacting.

Reinstating the wetland including but not limited to the following: o Ensure subsoil is at correct levels as per pre-construction survey; o Ensure adequate topsoil is present; o Establish indigenous vegetation with hydroseeding (if required); and o Ensure Moreleta Spruit runs as per original alignment.

General reinstatement and clean-up, including disposing of waste at the nearest licensed landfill site.

Activity Need and Desirability: The Construction of Gabions along the Moreleta Spruit The gabions are required to protect the high pressure petroleum fuel pipeline that was constructed in 1973 in order to ensure its safety and security. Exposure of the pipeline occurred due to channel erosion taking place in the Moreleta Spruit. Development that has taken place in the area post -1973 has led to increased impermeable surfaces which in turn have increased flow and velocity of run-off from storm water entering this river system. This has exacerbated the natural erosive pattern of the watercourse. With the pipeline being exposed (as was the case) it was also susceptible to vandalism and/or damage by rocks, boulders, etc. that have been swept downstream during high rainfall events. Should the pipeline have ruptured as a result of either of the scenarios above, thousands of litres of hydrocarbons (fuel) could potentially have contaminated the water in the river which would have an impact on flora and fauna downstream, as well as any other downstream users of the stream, thus leading to both negative ecological and social impacts. The fuel leakage and spillage would also have resulted in volatile organic carbon emissions to the atmosphere. Thus, it is imperative that th e pipeline remain protected from damage, that the stability of the banks of the Moreleta Spruit be reinstated and that erosion is minimised and further scouring of the river banks prevented.

b) Provide a detailed description of the listed activities associated with the project as

applied for

Listed activity as described in GN R.544, 545 and 546

Description of project activity

GN R.544 Activity 11: The construction of: (i) canals; (ii) channels; (iii) bridges; (iv) dams; (v) weirs; (vi) bulk storm water outlet structures; (vii) marinas; (viii) jetties exceeding 50 square metres in size; (ix) slipways exceeding 50 square metres in size; (x) buildings exceeding 50 square metres in size; (xi) infrastructure or structures covering 50 square

The construction of gabions as erosion mitigation and protection of the fuel pipeline occurs within 32m of the Moreleta Spruit and therefore requires a Basic Assessment.

Page 7: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

7

metres or more where such construction occurs within a watercourse or within 32 metres of a watercourse, measured from the edge of a watercourse, excluding where such construction will occur behind the development setback line.

GN R.544 Activity 18: The infilling or depositing of any material of more than 5 cubic metres into, or the dredging, excavation, removal or moving of soil, sand, shells, shell grit, pebbles or more than 5 cubic rock from (i) a watercourse; (ii) the sea; (iii) the seashore; (iv) the littoral active zone, an estuary or a distance of 100 metres inland of the high-water mark of the sea or an estuary, whichever distance is the greater-but excluding where such infilling, depositing, dredging, excavation, removal or moving; (a) is for maintenance purposes undertaken in accordance with a management plan agreed to by the relevant environmental authority; or (b) occurs behind the development setback line

The excavation of soil within 32m of the watercourse for construction of the gabions will require a Basic Assessment.

GN R.546 Activity 16 (b): The construction of:

(i) jetties exceeding 10 square metres in size;

(ii) slipways exceeding 10 square metres in size;

(iii) buildings with a footprint exceeding 10 square metres in size; or

(iv) infrastructure covering 10 square metres or more where such construction occurs within a watercourse or within 32 metres of a watercourse, measured from the edge of a watercourse, excluding where such construction will occur behind the development setback line.

(b) In Gauteng: i. A protected area identified in terms of

NEMPAA, excluding conservancies; ii. National Protected Area Expansion

Strategy Focus areas; iii. Sensitive areas as identified in an

environmental management framework as contemplated in chapter 5 of the Act and as adopted by the competent authority;

iv. Sites or areas identified in terms of the International Convention;

v. Sites identified as irreplaceable or important in the Gauteng Conservation

The proposed activity takes place within an environmentally sensitive (wetland) area, and involves infrastructure within 32m of a watercourse.

Page 8: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

8

plan; vi. Any declared protected area including

Municipal or Provincial Nature Reserves as contemplated by the Environment Conservation Act, 1989 (Act No. 73 of 1989) and the Nature Conservation Ordinance (Ordinance 12 of 1983)

vii. Areas zoned for a conservation purpose.

Page 9: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

9

2. FEASIBLE AND REASONABLE ALTERNATIVES “alternatives”, in relation to a proposed activity, means different means of meeting the general purpose and requirements of the activity, which may include alternatives to— (a) the property on which or location where it is proposed to undertake the activity; (b) the type of activity to be undertaken; (c) the design or layout of the activity; (d) the technology to be used in the activity; (e) the operational aspects of the activity; and (f) the option of not implementing the activity. Describe alternatives that are considered in this application as required by Regulation 22(2)(h) of GN R.543. Alternatives should include a consideration of all possible means by which the purpose and need of the proposed activity (NOT PROJECT) could be accomplished in the specific instance taking account of the interest of the applicant in the activity. The no-go alternative must in all cases be included in the assessment phase as the baseline against which the impacts of the other alternatives are assessed. The determination of whether site or activity alternatives (including different processes, etc.) or both are appropriate needs to be informed by the specific circumstances of the activity and its environment. Upon receipt of this report, the competent authority may also request the applicant to assess additional alternatives that could possibly accomplish the purpose and need of the proposed activity if it is clear that realistic alternatives have not been considered to a reasonable extent. The identification of alternatives should be in line with the Integrated Environmental Assessment Guideline Series 11, published by the DEA in 2004. Should the alternatives include different locations and lay-outs, the co-ordinates of the different alternatives must be provided. The co-ordinates should be in degrees, minutes and seconds. The projection that must be used in all cases is the WGS84 spheroid in a national or local projection. a) Site alternatives According to the regulations GNR543 27(e), the applicant must identify feasible and reasonable alternatives for the proposed activity. The most feasible alternatives identified for the current activity are justified below: Site alternatives: there are no feasible site alternatives for the construction of the gabions, as the fuel

pipeline is exposed at the two specific sites where the activity has commenced. Attempting to minimize erosion further up- or downstream would not necessarily address the issue of the exposed pipeline and the associated environmental and safety risks.

Layout alternatives: layout alternatives are also limited to the two affected sites of erosion and pipeline exposure, and the layout of the gabions will be limited to ensuring that the pipeline is sufficiently protected.

Design Alternatives: there are no applicable technology alternatives as the gabions have already been

constructed, however there are suggested alternatives in terms of the design of the structures that would enhance their ability to perform the erosion control function as well as protecting the fuel pipeline. Section 6.4 of the wetland assessment report and section 4.3 of the aquatic impact assessment report (Specialist reports attached in Appendix D) indicates that subsequent to construction of the gabions, structural damage already occurred. One of the most frequent causes of failure of these structures is the erosion of the gully banks associated with the hydraulic jump that forms downstream of the toe of the step or chute. It is therefore suggested that the design of the erosion control structures must ensure that the

Page 10: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

10

jump remains in the protected reach and does not extend downstream. Such design may include end sills, cut-off sills, stilling basins, stepped gabions etc. Figure 1 indicates a typical stepped gabion structure that can address the issue of erosion at the point of the change in hydraulic head. A Reno-mattress is made of woven mesh and filled with rocks, and is used for river bank and channel erosion control and embankment stability. The wetland impact assessment further indicates that the Reno-mattresses below the gabion at site 1 ends abruptly and are not keyed in, and erosion is already evident. It is therefore suggested that the Reno-mattresses be extended and keyed into the ground, thus reducing the concentration of flow at their edges. The binding of the gabions is done with only single strand wire, which will not be strong enough to withstand high flow situations, resulting in gabion failure. It is suggested that the holding structure be improved to maintain integrity. Erosion evident at site 2 is due to the gabion positioned at a sharp angle to the water flow, which results in a buildup of water at one edge and may lead to gabion failure. Alternatives include rebuilding and redesign of the gabion, or extending the problematic wing back so that water builds up equally on either side of the gabion. The bank stabilizing and downstream Reno-mattresses are too short and not keyed into the soil. It is suggested that these Reno-mattresses be extended and keyed into the ground.

Figure 1: Stepped gabion design to reduce erosion at the toe of the gabion

Implementation alternatives: there are no feasible implementation alternatives as the gabions have already been constructed. It is however suggested that remedial work and alterations be undertaken as soon as possible in order to minimize any long term effects of the gabion design on the river system as follows: Phase 1: this phase should involve the redesign of the gabions with the consultation of a wetland

rehabilitation specialist to ensure that the gabions are designed with minimal impact on the river system. Phase 2: implementation of the suggested improvements Phase 3: monitoring of the installation to ensure effective functioning of the system

The No Go Alternative relates to the proposed gabions not being constructed. As such, the fuel pipeline which is the main concern, will remain exposed and could pose both environmental and safety risks. The preferred and only alternative is detailed in the Table below.

Alternative 1 (preferred alternative)

Description Lat (DDMMSS) Long (DDMMSS)

Construction of erosion control measures (gabions) at the two sites along the Moreleta Spruit where the Transnet fuel pipeline has been exposed due to erosion.

Site 1: 250 48’ 643” S Site 2: 250 48’ 475” S

280 18’ 060” E 280 18’ 125” E

Page 11: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

11

Alternative 2

Description Lat (DDMMSS) Long (DDMMSS)

Alternative 3

Description Lat (DDMMSS) Long (DDMMSS)

In the case of linear activities: (The proposed development is not a linear activity) Alternative: Latitude (S): Longitude (E): Alternative S1 (preferred)

Starting point of the activity

Middle/Additional point of the activity

End point of the activity

Alternative S2 (if any)

Starting point of the activity

Middle/Additional point of the activity

End point of the activity

Alternative S3 (if any)

Starting point of the activity

Middle/Additional point of the activity

End point of the activity

For route alternatives that are longer than 500m, please provide an addendum with co-ordinates taken every 250 meters along the route for each alternative alignment. In the case of an area being under application, please provide the co-ordinates of the corners of the site as indicated on the lay-out map provided in Appendix A. b) Lay-out alternatives (Layout Alternatives are unfeasible due to the requirement for ensuring

adequate protection of the fuel pipeline) Alternative 1 (preferred alternative)

Description Lat (DDMMSS) Long (DDMMSS)

Alternative 2

Description Lat (DDMMSS) Long (DDMMSS)

Alternative 3

Description Lat (DDMMSS) Long (DDMMSS)

c) Technology alternatives: Technology & Operational Alternatives are limited to the redesign of

the gabion structures to reduce the impact of erosion and the impact of the structure on the functioning of the watercourse.

Alternative 1 (preferred alternative)

Alternative 2

Page 12: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

12

Alternative 3

d) Design alternatives

Alternative 1 (preferred alternative) The design of the erosion control structures must ensure that the jump remains in the protected reach and does not extend downstream. Such design alternatives may include end sills, cut-off sills, stilling basins, stepped gabions etc. (refer to fig. 1) Structural related design alternatives include the packing of the rock material within the gabion, and reinforcing the mesh covering to further strengthen the gabion’s structural integrity.

Alternative 2

Alternative 3

e) No-go alternative

The No Go Alternative relates to the proposed gabions not being constructed. As such, the fuel pipeline which is the main concern, will remain exposed and vulnerable to erosion and could pose both environmental and safety risks. It is important to note that the proposed project was undertaken to protect a fuel pipeline that traverses a number of provinces in the country, and the integrity of this pipeline is therefore of national concern.

Paragraphs 3 – 13 below should be completed for each alternative. 3. PHYSICAL SIZE OF THE ACTIVITY a) Indicate the physical size of the preferred activity/technology as well as alternative

activities/technologies (footprints): Alternative: Size of the activity:

Alternative A11 (preferred activity alternative) 400 m2

Alternative A2 (if any) m2 Alternative A3 (if any) m2

or, for linear activities: Alternative: Length of the activity: Alternative A1 (preferred activity alternative) m Alternative A2 (if any) m Alternative A3 (if any) m b) Indicate the size of the alternative sites or servitudes (within which the above footprints

will occur): Alternative: Size of the site/servitude:

1 “Alternative A..” refer to activity, process, technology or other alternatives.

Page 13: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

13

Alternative A1 (preferred activity alternative) m2 Alternative A2 (if any) m2 Alternative A3 (if any) m2 4. SITE ACCESS

Does ready access to the site exist? YES NO

If NO, what is the distance over which a new access road will be built m

Describe the type of access road planned:

There will be no new access roads constructed for the proposed development. The site is accessible via Garsfontein Road.

Include the position of the access road on the site plan and required map, as well as an indication of the road in relation to the site. 5. LOCALITY MAP

An A3 locality map must be attached to the back of this document, as Appendix A. The scale of the locality map must be relevant to the size of the development (at least 1:50 000. For linear activities of more than 25 kilometres, a smaller scale e.g. 1:250 000 can be used. The scale must be indicated on the map.). The map must indicate the following: (Please refer to Appendix A for the attached site plan)

an accurate indication of the project site position as well as the positions of the alternative sites, if any;

indication of all the alternatives identified;

closest town(s;)

road access from all major roads in the area;

road names or numbers of all major roads as well as the roads that provide access to the site(s);

all roads within a 1km radius of the site or alternative sites; and

a north arrow;

a legend; and

locality GPS co-ordinates (Indicate the position of the activity using the latitude and longitude of the centre point of the site for each alternative site. The co-ordinates should be in degrees and decimal minutes. The minutes should have at least three decimals to ensure adequate accuracy. The projection that must be used in all cases is the WGS84 spheroid in a national or local projection).

6. LAYOUT/ROUTE PLAN A detailed site or route plan(s) must be prepared for each alternative site or alternative activity. It must be attached as Appendix A to this document. The site or route plans must indicate the following:

the property boundaries and numbers of all the properties within 50 metres of the site;

the current land use as well as the land use zoning of the site;

the current land use as well as the land use zoning each of the properties adjoining the site or sites;

Page 14: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

14

the exact position of each listed activity applied for (including alternatives);

servitude(s) indicating the purpose of the servitude;

a legend; and

a north arrow. 7. SENSITIVITY MAP The layout/route plan as indicated above must be overlain with a sensitivity map that indicates all the sensitive areas associated with the site, including, but not limited to:

watercourses;

the 1:100 year flood line (where available or where it is required by DWA);

ridges;

cultural and historical features;

areas with indigenous vegetation (even if it is degraded or infested with alien species); and

critical biodiversity areas. The sensitivity map must also cover areas within 100m of the site and must be attached in Appendix A. 8. SITE PHOTOGRAPHS Colour photographs from the centre of the site must be taken in at least the eight major compass directions with a description of each photograph. Photographs must be attached under Appendix B to this report. It must be supplemented with additional photographs of relevant features on the site, if applicable. 9. FACILITY ILLUSTRATION A detailed illustration of the activity must be provided at a scale of at least 1:200 as Appendix C for activities that include structures. The illustrations must be to scale and must represent a realistic image of the planned activity. The illustration must give a representative view of the activity. 10. ACTIVITY MOTIVATION Motivate and explain the need and desirability of the activity (including demand for the activity):

1. Is the activity permitted in terms of the property’s existing land use rights?

YES NO Please explain

The properties’ land use rights include public open space. The fuel pipeline was constructed in 1973 and Transnet has servitude rights on the property for the pipeline inside this public open space.

Page 15: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

15

2. Will the activity be in line with the following?

(a) Provincial Spatial Development Framework (PSDF) YES NO Please explain

The development promotes sustainable development by protecting and supporting the current use of the pipeline infrastructure and protecting the public environment for future generations. The pipeline is a key requirement for the transportation of fuel which serves the South African economy.

(b) Urban edge / Edge of Built environment for the area YES NO Please explain

The proposed development is located within the boundaries of the urban edge.

(c) Integrated Development Plan (IDP) and Spatial Development Framework (SDF) of the Local Municipality (e.g. would the approval of this application compromise the integrity of the existing approved and credible municipal IDP and SDF?).

YES NO Please explain

According to the IDP of the City of Tshwane, the mission of the Municipality is “To sustainably enhance the quality of life of all people in Tshwane through a developmental system of local government and by rendering efficient, effective and affordable services.”

This development and the activity aim to protect the health and safety of its residents by lowering the risk of a leaking/ rupturing of the petroleum fuel pipeline. It also aims to ensure that the integrity of the pipeline is not compromised which will enable the continued supply of petroleum fuel that is necessary for economic functioning.

The area is identified as a key open space linking the Rietvlei Nature Reserve with the Faerie Glen Nature Reserve. The importance of the area also becomes clear when viewed within the context of the planned development intensification of the Menlyn Node and Rubenstein Development Zone amongst others in the area.

The gabion construction will thus provide protection of the pipeline, which if left unprotected could result in significant impacts to the open space as well as to the Faerie Glen Nature Reserve and all fauna and flora supported in these areas. It will also stabilise the river banks from erosion.

Approval of this application would therefore not compromise the integrity of the existing municipal IDP and SDF.

(d) Approved Structure Plan of the Municipality YES NO Please explain

The Tshwane Nature Conservation Section has been engaged on the process, and has requested that an Environmental Authorisation must be obtained from the Department of Environmental Affairs (Attached in Appendix J).

Page 16: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

16

(e) An Environmental Management Framework (EMF) adopted by the Department (e.g. Would the approval of this application compromise the integrity of the existing environmental management priorities for the area and if so, can it be justified in terms of sustainability considerations?)

YES NO Please explain

The proposed development would not compromise the integrity of the existing environmental management priorities for the area as the proposed development inherently promotes the sustainability of the Transnet Petroleum fuel pipeline, as well as the safety of nearby residents and protection of the surrounding natural environment. Furthermore the existing priorities such as conservation are not in conflict considering that the development is aimed at ensuring that conservation areas are not compromised by hydrocarbon pollution.

(f) Any other Plans (e.g. Guide Plan) YES NO Please explain

Similar to the SDF, the City of Tshwane Open Space Framework identifies the area as a key corridor for species movement. The construction of the gabions protects the petroleum pipeline from damage and leakage which could have a significant impact on the flora and fauna not only within the corridor system but also to the downstream Faerie Glen Nature Reserve.

3. Is the land use (associated with the activity being applied for) considered within the timeframe intended by the existing approved SDF agreed to by the relevant environmental authority (i.e. is the proposed development in line with the projects and programmes identified as priorities within the credible IDP)?

YES NO Please explain

TPL has existing servitude rights for the maintenance and monitoring of the fuel pipeline (Appendix J).

Page 17: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

17

4. Does the community/area need the activity and the associated land use concerned (is it a societal priority)? (This refers to the strategic as well as local level (e.g. development is a national priority, but within a specific local context it could be inappropriate.)

YES NO Please explain

The area in which the pipeline was exposed due to erosion from high water flows occurs within Moreleta Park, is located in close proximity to a community church and other settlements.

The proposed construction of gabions will therefore not only protect the petroleum pipeline from becoming further exposed and leaking fuel into the surrounding natural environment, it will also minimise the associated health and safety risks to humans.

Potential impacts of liquid petroleum (if the potential structural compromise of the pipeline is not addressed through the construction of gabions) on the environment include but are not limited to:

1. The effects of liquid petroleum accidentally released into the natural environment are generally toxic and has carcinogenic (cancer causing) effects on humans and animals.

2. Liquid petroleum is a highly flammable substance, which could lead to fires or explosions if exposed to open flame.

3. Vapours released from petroleum into the atmosphere contain volatile organic compounds, many of which have short- and long-term impacts on human health and the environment due to their toxicity and carcinogenic properties.

The aforementioned impacts may not necessarily be local or immediate, or even quantifiable. However the potential health and safety risks and pollution risks to the environment can be very detrimental and the accidental release of petroleum from a leaking or broken fuel pipeline needs to be avoided. The urgency for Transnet to protect the exposed fuel pipeline can therefore be justified in light of these potential impacts.

5. Are the necessary services with adequate capacity currently available (at the time of application), or must additional capacity be created to cater for the development? (Confirmation by the relevant Municipality in this regard must be attached to the final Basic Assessment Report as Appendix I.)

YES NO Please explain

The proposed facility would be located within the Transnet Pipelines servitude. No additional services would be

required from the municipality.

6. Is this development provided for in the infrastructure planning of the municipality, and if not what will the implication be on the infrastructure planning of the municipality (priority and placement of services and opportunity costs)? (Comment by the relevant Municipality in this regard must be attached to the final Basic Assessment Report as Appendix I.)

YES NO Please explain

The construction of the gabions to protect the exposed pipeline was undertaken as part of an emergency

maintenance. There should however be no impact on the municipal infrastructure planning, as the pipeline has

been in existence since 1973.

Page 18: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

18

7. Is this project part of a national programme to address an issue of national concern or importance?

YES NO Please explain

Yes. Sustainable Development is a priority for South Africa and in July 2008, the Cabinet passed the

National Framework for Sustainable Development (NFSD). The NFSD is designed to “initiate a broad

framework for sustainable development in South Africa that can serve as a basis from which to develop

and consolidate a national strategy and action plan”. The NFSD proposes a national vision, principles,

trends, strategic priority areas, and a set of implementation measures that are intended to enable and

guide the development of the national strategy and action plan.

The NFSD discusses the various environmental and social risk areas facing South Africa and maps out

five strategic priority areas.

1. Enhancing systems for integrated planning and implementation.

2. Sustaining our ecosystems and using resources sustainably.

3. Investing in sustainable economic development and infrastructure.

4. Creating sustainable human settlements.

5. Responding appropriately to emerging human development, economic and environmental challenges.

This proposed development falls directly in line with the point two and three above. By protecting the

exposed petroleum pipeline, Transnet has ensured that the fuel resources would not be compromised in

any way, thus securing the supply of fuel to the various end users.

The South African Designated National Authority (DNA) further evaluates sustainability in three categories:

Economic, environmental and social. The contribution of the project towards sustainable development is

discussed in terms of these three categories:

Economic: The project will ensure the continued and smooth functioning of fuel supply to other

businesses and end users thus supporting economic operations.

Environmental: At a regional level, the project will have a positive impact on the environment. This

positive impact relates to a reduction in the potential of fuel leakage into the receiving wetland

environment and its associated environmental impacts. As a result the project would reduce the

possibility of water pollution, as well as to mitigate against erosion of the river banks and promote the

conservation of the wetland system, if the proposed design improvements are effected.

Social: The project will contribute to ensuring the safety and health of the nearby residents and

community.

Page 19: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

19

8. Do location factors favour this land use (associated with the activity applied for) at this place? (This relates to the contextualisation of the proposed land use on this site within its broader context.)

YES NO Please explain

The proposed development and activity is located within the existing Transnet Pipeline servitude (refer to

Appendix I for the servitude registration)

9. Is the development the best practicable environmental option for this land/site?

YES NO Please explain

The preferred option to construct erosion control gabions is the best practicable environmental option as

the area the two sites where the fuel pipeline has been exposed has been caused by erosion of the river

banks during high water flow events. While gabions are effective in mitigating the effects of erosion as well

as protecting the fuel pipeline, it is suggested that the proposed improvements and redesign of the gabion

installations be implemented in order to ensure that the environmental impacts of the project are minimised

(please refer to Section 2: Alternatives as well as specialist studies attached as Appendix D).

10. Will the benefits of the proposed land use/development outweigh the negative impacts of it?

YES NO Please explain

The infrastructure is aimed at protecting the fuel pipeline from being exposed and susceptible to damage

which may lead to environmental pollution and health and safety risks.

11. Will the proposed land use/development set a precedent for similar activities in the area (local municipality)?

YES NO Please explain

The proposed development was undertaken under emergency conditions and to protect the exposed fuel

pipeline. It is not anticipated that similar activities will be undertaken in the area, unless the mitigation of

erosion of river banks and bank stabilisation becomes a prioritised municipal project.

12. Will any person’s rights be negatively affected by the proposed activity/ies?

YES NO Please explain

To date no person’s rights have been negatively affected by the proposed development.

Page 20: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

20

13. Will the proposed activity/ies compromise the “urban edge” as defined by the local municipality?

YES NO Please explain

The proposed activity occurs within the Moreleta Park, which is within the urban boundaries of the

municipality.

14. Will the proposed activity/ies contribute to any of the 17 Strategic Integrated Projects (SIPS)?

YES NO Please explain

This proposed development is aligned with the SIP 2.

SIP 2: Durban-Free State-Gauteng Logistics and Industrial Corridor

The Transnet high pressure liquid petroleum pipeline traverses through 5 provinces, 3 of which are

KwaZulu-Natal, Free State and Gauteng. This pipeline therefore supplies fuel to various industries and

businesses located along the identified corridor, and are aligned to promoting the industrial corridor.

15. What will the benefits be to society in general and to the local communities?

Please explain

The reduction in potential environmental, health and safety risks should the exposed pipeline be

vandalised or damaged will benefit neighbouring property owners as well as properties downstream of the

pipeline exposure. The Moreleta Spruit which falls within the Faerie Glen Nature Reserve will continue to

support the ecological functioning of the wetland system, and therefore benefit society in general in terms

of the intrinsic value of conservation areas and urban “green lungs”.

16. Any other need and desirability considerations related to the proposed activity?

Please explain

No.

17. How does the project fit into the National Development Plan for 2030? Please explain

The National Development Plan (NDP) speaks to South African goals in terms of economic infrastructure development. One of the Enabling milestones of the plan is to:

“Upgrade fuel refineries to ensure they meet new fuel quality standards and insist on larger strategic fuel stocks to ensure security of supply.”

As such, the development is aligned to the NDP, as it the fuel pipeline will perform the function of supporting infrastructure to transport the liquid fuel and ensure the security of fuel supply to various provinces.

Page 21: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

21

18. Please describe how the general objectives of Integrated Environmental Management as set out in section 23 of NEMA have been taken into account. The principles and objectives of Integrated Environmental Management are closely linked and a discussion on the one inherently involves reference to the other. As such and as per NEMA the general objectives of integrated environmental management are included in the section below in italics. A description of how each objective is related to and has been taken into account in this application for Environmental Authorisation is noted in red script below the statement in italics.

(a) promote the integration of the principles of environmental management set out in section 2 into the making of all decisions which may have a significant effect on the environment; The decision to undertake the development arose out of the need to minimise the potential impact of the environmental, health and safety risks associated with an exposed fuel pipeline on people and ecosystems in vicinity of the pipeline. The gabion construction project (as an example) integrates the principle that environmental management must place people and their needs at the forefront of its concern, and serve their physical, psychological, developmental, cultural and social interests equitably into the decision making process. Please also refer to 19 below for a discussion in terms of the principles of Environmental Management and Appendix J for an excerpt from NEMA in terms of the principles of Integrated Environmental Management.

(b) identify, predict and evaluate the actual and potential impact on the environment, socio-economic conditions and cultural

heritage, the risks and consequences and alternatives and options for mitigation of activities, with a view to minimising negative impacts, maximising benefits, and promoting compliance with the principles of environmental management set out in section 2; The key issues, potential impacts of the proposed facility and recommended mitigation measures have been identified and evaluated by the EAP and appointed specialists and detailed in the sections that follow. Please refer to Section D of this report which includes a description of the Methodology used for Impact Significance Scoring.

(c) ensure that the effects of activities on the environment receive adequate consideration before actions are taken in connection

with them; Yes, potential effects/ impacts of installing the gabions as erosion control measures and protection for the Transnet fuel pipeline have been considered in this Basic Assessment Process. As stated above each impact on the environment was identified and assessed by the EAP and the specialist team and mitigation measures recommended where possible and required. An Environmental Management Programme (EMP) has been compiled and attached to this document as Appendix G to ensure that these mitigation measures are implemented during the construction and operational phases of the proposed development.

(d) ensure adequate and appropriate opportunity for public participation in decisions that may affect the environment;

An equitable public participation process/ stakeholder engagement was undertaken in terms of Best Practise Public Participation Guidelines and principles. Key Stakeholders were identified through a focussed process (by identifying relevant authorities, organisations operating within Moreleta Park, and neighbouring property owners), and were notified of the project via e-mailed letters. The general public were notified in a local newspaper, in the predominant languages (English and Afrikaans) of the local community. Interested and affected parties were afforded the opportunity to comment and request additional information in any form of written communication acceptable to them. Site notices were also placed at the fences in close vicinity to the sites of construction, providing details of the public participation process, project background and contact details for further communication. Details of the public participation process will be included in Appendix E. A register will be kept of all Interested and Affected parties and the details will be used in all future communication in terms of the process and application for Environmental Authorisation. A public meeting is scheduled for 16 January 2013, at the Eastside Community Church in Moreleta Park.

(e) ensure the consideration of environmental attributes in management and decision-making which may have a significant effect

on the environment; and Wetland and Aquatic Specialist studies have been undertaken to assess the effects of the gabion construction on the wetland system function, and have identified mitigation measures and proposed methods to enhance the functioning of the gabion structures. The implementation of these measures will ensure that the impact on environmental attributes will be managed and minimised.

(f) identify and employ the modes of environmental management best suited to ensuring that a particular activity is pursued in accordance with the principles of environmental management set out in section 2.” The development has followed the modes outlined below to ensure that the activity is in accordance with the principles of environmental management: o Aligned to relevant municipal and district by-laws, spatial planning and environmental frameworks for the

proposed development area; o Ensure equitable public participation process was undertaken. o The adherence to the all the principles of NEMA, which would be implemented by the Environment

Management Programme (EMP) during construction and operation of the proposed facility. Refer to Appendix G for the Draft EMP for the proposed facility.

Lastly is it is assumed that the template for a Basic Assessment Report, as prepared by the Department, adheres to all provisions of the National Environmental Management Act in terms of Integrated Environmental Management (including the objectives and principles of NEMA) and the EAP has therefore endeavoured to provide as much detailed information as possible in the sections above and below.

Page 22: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

22

19. Please describe how the principles of environmental management as set out in section 2 of NEMA have been taken into account.

The development involves the construction of gabions at two sites along the Moreleta Spruit to protect an exposed fuel pipeline from erosion.

The following points demonstrate how the principles in Section 2 of NEMA have been applied:

The potential pollution or degradation to the environment has been minimised through the proposed mitigation measures detailed in the EMP.

Although the site serves as an ecological corridor, it is already somewhat disturbed with some alien invasive vegetation and no cultural or heritage resources are present on the site.

Any general waste generated from the development during the construction phase was disposed of at the relevant registered waste facility.

The potential risks to human health have been considered and included in the assessment of impacts.

The construction of the gabions was undertaken as emergency measures to the fuel pipeline, and all applicable environmental and international legislation/standards and any other applicable legislation or standards will be adhered to and authorisation applied for retrospectively.

Throughout the Basic Assessment process information has been made freely available to any Interested and Affected Party requesting information ensuring transparency in the process.

11. APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES List all legislation, policies and/or guidelines of any sphere of government that are applicable to the application as contemplated in the EIA regulations, if applicable:

Title of legislation, policy or guideline

Applicability to the project Administering authority

Date

The Constitution of the Republic of South Africa, Section 24 (Environmental Right)

1) Everyone has the right;

a) to an environment that is not harmful to their health or well-being; and

b) to have the environment protected, for the benefit of present and future generations, through reasonable legislative and other measures that:

i) prevent pollution and ecological degradation;

ii) promote conservation; and

iii) secure ecologically sustainable development and use of natural resources while promoting justifiable economic and social development.”

National Government 1996

National Environmental Management Act (Act No. 107 of 1998) (NEMA)

In terms of NEMA and associated Environmental Impact Assessment (EIA) Regulations published in August 2010, an Environmental Authorisation (Basic Assessment)

Department of Environmental Affairs

1998

Page 23: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

23

must be obtained from the relevant decision-making authority, to rectify the illegal commencement of certain listed activities that may result in potential negative impacts on the environment.

The environmental principles and requirements of NEMA were considered during the assessment of impacts and development of mitigation measures and the EMP.

Occupational Health and Safety Act (Act No.85 of 1993)

A number of OHSA requirements are also relevant to environmental control and were as such considered in the identified mitigation and the EMP (e.g. bunding for flammable substances, Material Safety Data Sheets).

Department of Labour 1993

Hazardous Substances Act (Act No. 15 of 1973)

Use and or handling of any hazardous substances.

Department of Environmental Affairs

1973

National Water Act (Act No. 36 of 1998)

Impeding or diverting the flow of water in a watercourse

Department of Water Affairs

1998

Listed Activities requiring environmental authorisation

Listed activity as described in GN R.544, 545 and 546

Description of project activity

GN R.544 Activity 11: The construction of: (i) canals; (ii) channels; (iii) bridges; (iv) dams; (v) weirs; (vi) bulk storm water outlet structures; (vii) marinas; (viii) jetties exceeding 50 square metres in size; (ix) slipways exceeding 50 square metres in size; (x) buildings exceeding 50 square metres in size; (xi) infrastructure or structures covering 50 square metres or more where such construction occurs within a watercourse or within 32 metres of a watercourse, measured from the edge of a watercourse, excluding where such construction will occur behind the development setback line.

The construction of gabions as erosion mitigation and protection of the fuel pipeline occurs within 32m of the Moreleta Spruit and therefore requires a Basic Assessment.

GN R.544 Activity 18: The infilling or depositing of any material of more than 5 cubic metres into, or the dredging, excavation, removal or moving of soil, sand, shells, shell grit, pebbles or more than 5 cubic rock from (i) a watercourse; (ii) the sea; (iii) the seashore;

The excavation of soil within 32m of the watercourse for construction of the gabions will require a Basic Assessment.

Page 24: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

24

(iv) the littoral active zone, an estuary or a distance of 100 metres inland of the high-water mark of the sea or an estuary, whichever distance is the greater-but excluding where such infilling, depositing, dredging, excavation, removal or moving; (a) is for maintenance purposes undertaken in accordance with a management plan agreed to by the relevant environmental authority; or (b) occurs behind the development setback line

GN R.546 Activity 16 (b): The construction of:

(v) jetties exceeding 10 square metres in size;

(vi) slipways exceeding 10 square metres in size;

(vii) buildings with a footprint exceeding 10 square metres in size; or

(viii) infrastructure covering 10 square metres or more where such construction occurs within a watercourse or within 32 metres of a watercourse, measured from the edge of a watercourse, excluding where such construction will occur behind the development setback line.

(b) In Gauteng: viii. A protected area identified in terms of

NEMPAA, excluding conservancies; ix. National Protected Area Expansion

Strategy Focus areas; x. Sensitive areas as identified in an

environmental management framework as contemplated in chapter 5 of the Act and as adopted by the competent authority;

xi. Sites or areas identified in terms of the International Convention;

xii. Sites identified as irreplaceable or important in the Gauteng Conservation plan;

xiii. Any declared protected area including Municipal or Provincial Nature Reserves as contemplated by the Environment Conservation Act, 1989 (Act No. 73 of 1989) and the Nature Conservation Ordinance (Ordinance 12 of 1983)

xiv. Areas zoned for a conservation purpose.

The proposed activity takes place within an environmentally sensitive (wetland) area, and involves infrastructure within 32m of a watercourse.

Page 25: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

25

12. WASTE, EFFLUENT, EMISSION AND NOISE MANAGEMENT a) Solid waste management There will be minimal on-site construction. The construction activities would consist of excavation and installation of the reno-mattresses and packed gabions.

Will the activity produce solid construction waste during the construction/initiation phase?

YES NO

If YES, what estimated quantity will be produced per month? 1 m3

How will the construction solid waste be disposed of (describe)?

The domestic waste and building rubble from construction activities was disposed of at a registered landfill site.

Where will the construction solid waste be disposed of (describe)?

The Garstkloof Landfill Site, Delmas Road, Pretoria

Will the activity produce solid waste during its operational phase? YES NO If YES, what estimated quantity will be produced per month? m3 How will the solid waste be disposed of (describe)?

If the solid waste will be disposed of into a municipal waste stream, indicate which registered landfill site will be used.

Where will the solid waste be disposed of if it does not feed into a municipal waste stream (describe)?

If the solid waste (construction or operational phases) will not be disposed of in a registered landfill site or be taken up in a municipal waste stream, then the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA. N/A

Can any part of the solid waste be classified as hazardous in terms of the NEM:WA? YES NO

If YES, inform the competent authority and request a change to an application for scoping and EIA. An application for a waste permit in terms of the NEM:WA must also be submitted with this application.

Is the activity that is being applied for a solid waste handling or treatment facility? YES NO

If YES, then the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA. An application for a waste permit in terms of the NEM:WA must also be submitted with this application. b) Liquid effluent

Will the activity produce effluent, other than normal sewage, that will be disposed of in a municipal sewage system?

YES NO

If YES, what estimated quantity will be produced per month? 1 m3

Will the activity produce any effluent that will be treated and/or disposed of on site? YES NO

Page 26: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

26

If YES, the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA.

Will the activity produce effluent that will be treated and/or disposed of at another facility?

YES NO

If YES, provide the particulars of the facility:

Facility name:

Contact person:

Postal address:

Postal code:

Telephone: Cell:

E-mail: Fax:

Describe the measures that will be taken to ensure the optimal reuse or recycling of waste water, if any:

Chemical toilets were provided for construction staff during the construction phase of the project and were maintained by a specialist contractor.

c) Emissions into the atmosphere

Will the activity release emissions into the atmosphere other that exhaust emissions and dust associated with construction phase activities?

YES NO

If YES, is it controlled by any legislation of any sphere of government? YES NO

If YES, the applicant must consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA. If NO, describe the emissions in terms of type and concentration:

Emissions generated during construction activities would have been limited to dust generated from moving vehicles and excavation activities. Concentration levels cannot be determined.

d) Waste permit

Will any aspect of the activity produce waste that will require a waste permit in terms of the NEM:WA?

YES NO

If YES, please submit evidence that an application for a waste permit has been submitted to the competent authority e) Generation of noise

Will the activity generate noise? YES NO

If YES, is it controlled by any legislation of any sphere of government? YES NO

If YES, the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA. If NO, describe the noise in terms of type and level:

Page 27: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

27

The noise impacts were generated by construction vehicles, generators and water pumps. Construction activities were limited to daylight hours, between 07h00-17h00 to avoid disturbance to surrounding residents. Noise levels during construction activities would have ranged between 60-80 dB, although these are estimated and not measured levels.

13. WATER USE Please indicate the source(s) of water that will be used for the activity by ticking the appropriate box(es):

Municipal Water board Groundwater River, stream, dam or lake

Other The activity will not use water

If water is to be extracted from groundwater, river, stream, dam, lake or any other natural feature, please indicate the volume that will be extracted per month:

litres

Does the activity require a water use authorisation (general authorisation or water use license) from the Department of Water Affairs?

YES NO

If YES, please provide proof that the application has been submitted to the Department of Water Affairs (To be included in Appendix J of the Final Basic Assessment Report).

14. ENERGY EFFICIENCY Describe the design measures, if any that have been taken to ensure that the activity is energy efficient:

N/A

Describe how alternative energy sources have been taken into account or been built into the design of the activity, if any:

N/A

Page 28: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

28

SECTION B: SITE/AREA/PROPERTY DESCRIPTION Important notes: 1. For linear activities (pipelines, etc) as well as activities that cover very large sites, it may be

necessary to complete this section for each part of the site that has a significantly different environment. In such cases please complete copies of Section B and indicate the area, which is covered by each copy No. on the Site Plan.

Section B Copy No. (e.g. A):

2. Paragraphs 1 - 6 below must be completed for each alternative.

3. Has a specialist been consulted to assist with the completion of this section? YES NO

If YES, please complete the form entitled “Details of specialist and declaration of interest” for each specialist thus appointed and attach it in Appendix I. All specialist reports must be contained in Appendix D. Property description/physical address:

Province Gauteng

District Municipality

City of Tshwane Metropolitan Municipality

Local Municipality City of Tshwane Metropolitan Municipality

Ward Number(s) 91

Farm name and number

Site 1: Erf 492 Moreleta Park Ext 3 Site 2: Erf 3823 Garsfontein Ext 15 and Erf 925 Pretorius Park Ext 1

Portion number

SG Code Site 1: T0JR01760000049200000 Site 2: T0JR00880000382300000 and T0JR02050000009200000

Where a large number of properties are involved (e.g. linear activities), please attach a full list to this application including the same information as indicated above.

Current land-use zoning as per local municipality IDP/records:

Public Open Space/ Park

In instances where there is more than one current land-use zoning, please attach a list of current land use zonings that also indicate which portions each use pertains to, to this application.

Is a change of land-use or a consent use application required? YES NO

Page 29: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

29

1. GRADIENT OF THE SITE Indicate the general gradient of the site. Alternative S1:

Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

Alternative S2 (if any):

Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

Alternative S3 (if any):

Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

2. LOCATION IN LANDSCAPE Indicate the landform(s) that best describes the site:

2.1 Ridgeline 2.4 Closed valley 2.7 Undulating plain / low hills

2.2 Plateau 2.5 Open valley x 2.8 Dune

2.3 Side slope of hill/mountain 2.6 Plain 2.9 Seafront

3. GROUNDWATER, SOIL AND GEOLOGICAL STABILITY OF THE SITE Is the site(s) located on any of the following? Alternative S1: Alternative S2

(if any): Alternative S3

(if any):

Shallow water table (less than 1.5m deep) YES NO YES NO YES NO

Dolomite, sinkhole or doline areas YES NO YES NO YES NO

Seasonally wet soils (often close to water bodies)

YES NO

YES NO

YES NO

Unstable rocky slopes or steep slopes with loose soil

YES NO

YES NO

YES NO

Dispersive soils (soils that dissolve in water) YES NO YES NO YES NO

Soils with high clay content (clay fraction more than 40%)

YES NO

YES NO

YES NO

Any other unstable soil or geological feature YES NO YES NO YES NO

An area sensitive to erosion YES NO YES NO YES NO

If you are unsure about any of the above or if you are concerned that any of the above aspects may be an issue of concern in the application, an appropriate specialist should be appointed to assist in the completion of this section. Information in respect of the above will often be available as part of the project information or at the planning sections of local authorities. Where it exists, the 1:50 000 scale Regional Geotechnical Maps prepared by the Council for Geo Science may also be consulted.

Page 30: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

30

4. GROUNDCOVER Indicate the types of groundcover present on the site. The location of all identified rare or endangered species or other elements should be accurately indicated on the site plan(s).

Natural veld - good conditionE

Natural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens

Sport field Cultivated land Paved surface Building or other structure

Bare soil

If any of the boxes marked with an “E “is ticked, please consult an appropriate specialist to assist in the completion of this section if the environmental assessment practitioner doesn’t have the necessary expertise. 5. SURFACE WATER Indicate the surface water present on and or adjacent to the site and alternative sites?

Perennial River YES NO UNSURE

Non-Perennial River YES NO UNSURE

Permanent Wetland YES NO UNSURE

Seasonal Wetland YES NO UNSURE

Artificial Wetland YES NO UNSURE

Estuarine / Lagoonal wetland YES NO UNSURE

If any of the boxes marked YES or UNSURE is ticked, please provide a description of the relevant watercourse.

The site is located in the Crocodile West and Marico Water Management Area in quaternary catchment A23A. The stream is classified as the Moretele River according to the DWA 1:500 000 rivers layers, and drains into the Pienaars River and into the Crocodile River, which drains into the Limpopo River. The stream also forms part of the Western Bankenveld Ecoregion. The wetland is an unchannelled valley bottom wetland, with some artificial channels present.

6. LAND USE CHARACTER OF SURROUNDING AREA Indicate land uses and/or prominent features that currently occur within a 500m radius of the site and give description of how this influences the application or may be impacted upon by the application:

Natural area Dam or reservoir Polo fields

Low density residential Hospital/medical centre Filling station H

Medium density residential School Landfill or waste treatment site

High density residential Tertiary education facility Plantation

Informal residentialA Church Agriculture

Page 31: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

31

Retail commercial & warehousing Old age home River, stream or wetland

Light industrial Sewage treatment plantA Nature conservation area

Medium industrial AN Train station or shunting yard N Mountain, koppie or ridge

Heavy industrial AN Railway line N Museum

Power station Major road (4 lanes or more) N Historical building

Office/consulting room Airport N Protected Area

Military or police base/station/compound

Harbour Graveyard

Spoil heap or slimes damA Sport facilities Archaeological site

Quarry, sand or borrow pit Golf course Other land uses (describe)

If any of the boxes marked with an “N “are ticked, how will this impact / be impacted upon by the proposed activity?

N/A

If any of the boxes marked with an "An" are ticked, how will this impact / be impacted upon by the proposed activity? Specify and explain:

N/A

If any of the boxes marked with an "H" are ticked, how will this impact / be impacted upon by the proposed activity? Specify and explain:

N/A

Does the proposed site (including any alternative sites) fall within any of the following:

Critical Biodiversity Area (as per provincial conservation plan) YES NO

Core area of a protected area? YES NO

Buffer area of a protected area? YES NO

Planned expansion area of an existing protected area? YES NO

Existing offset area associated with a previous Environmental Authorisation? YES NO

Buffer area of the SKA? YES NO

If the answer to any of these questions was YES, a map indicating the affected area must be included in Appendix A. 7. CULTURAL/HISTORICAL FEATURES

Are there any signs of culturally or historically significant elements, as defined in section 2 of the National Heritage Resources Act, 1999, (Act No. 25 of 1999), including Archaeological or paleontological sites, on or close (within 20m) to the site? If YES, explain:

YES NO

Uncertain

If uncertain, conduct a specialist investigation by a recognised specialist in the field (archaeology or palaeontology) to establish whether there is such a feature(s) present on or close to the site. Briefly explain the findings of the specialist:

Page 32: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

32

Will any building or structure older than 60 years be affected in any way? YES NO

Is it necessary to apply for a permit in terms of the National Heritage Resources Act, 1999 (Act 25 of 1999)?

YES NO

If YES, please provide proof that this permit application has been submitted to SAHRA or the relevant provincial authority. 8. SOCIO-ECONOMIC CHARACTER a) Local Municipality Please provide details on the socio-economic character of the local municipality in which the proposed site(s) are situated. Level of unemployment:

The City of Tshwane Metropolitan Municipality indicated a 20% unemployment level in their approved 2011-2016 IDP. The City further indicated that 18% of the population earn below R 1 600 per month, and that 82 100 people were households on the indigent register (www.tshwane.gov.za). These statistics indicate that increasing employment in the area is crucial to this community in order to alleviate inequity and poverty.

Economic profile of local municipality:

According to the City of Tshwane Socio-Economic Review and Outlook 2010/11, the average economic growth rate between 2005-2007 was approximately 7%, where after a global economic recession resulted in a drop in the growth rate to 4.2% by 2010. It is anticipated however, that the economic growth for the municipality will average at around 4.5% between the period 2012-2014.

Level of education:

“The City of Tshwane’s population of over two million has, on average, the highest educational level in the country, and the CoT is a national centre of research and learning with four universities and the headquarters of both the Council for Scientific and Industrial Research and the Human Sciences Research Council” (CoT IDP 2011-2016).

b) Socio-economic value of the activity

What is the expected capital value of the activity on completion? R 1.9 million

What is the expected yearly income that will be generated by or as a result of the activity?

R 0.00

Will the activity contribute to service infrastructure? YES NO

Is the activity a public amenity? YES NO

How many new employment opportunities will be created in the development and construction phase of the activity/ies?

0

What is the expected value of the employment opportunities during the development and construction phase?

R 0.00

What percentage of this will accrue to previously disadvantaged individuals? 0%

Page 33: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

33

How many permanent new employment opportunities will be created during the operational phase of the activity?

0

What is the expected current value of the employment opportunities during the first 10 years?

R 0.00

What percentage of this will accrue to previously disadvantaged individuals? 0%

9. BIODIVERSITY Please note: The Department may request specialist input/studies depending on the nature of the biodiversity occurring on the site and potential impact(s) of the proposed activity/ies. To assist with the identification of the biodiversity occurring on site and the ecosystem status consult http://bgis.sanbi.org or [email protected]. Information is also available on compact disc (cd) from the Biodiversity-GIS Unit, Ph (021) 799 8698. This information may be updated from time to time and it is the applicant/ EAP’s responsibility to ensure that the latest version is used. A map of the relevant biodiversity information (including an indication of the habitat conditions as per (b) below) and must be provided as an overlay map to the property/site plan as Appendix D to this report. a) Indicate the applicable biodiversity planning categories of all areas on site and indicate

the reason(s) provided in the biodiversity plan for the selection of the specific area as part of the specific category)

Systematic Biodiversity Planning Category If CBA or ESA, indicate the reason(s) for its selection in biodiversity plan

Critical Biodiversity Area (CBA)

Ecological Support

Area (ESA)

Other Natural

Area (ONA)

No Natural Area

Remaining (NNR)

b) Indicate and describe the habitat condition on site

Habitat Condition

Percentage of habitat

condition class (adding up to 100%)

Description and additional Comments and Observations

(including additional insight into condition, e.g. poor land management practises, presence of quarries,

grazing, harvesting regimes etc).

Natural 40 %

The site falls within the Faerie Glen and Rietvlei Nature Reserve corridor, thus facilitating species movement and promoting species diversity, as well as providing safe breeding habitat.

Near Natural (includes areas with

low to moderate level of alien invasive

plants)

40 %

Due to the proximity to the built-up urban area and settlements, there is some disturbance of the natural habitat, allowing for alien invasive species to become established.

Degraded (includes areas

heavily invaded by alien plants)

0 %

Page 34: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

34

Transformed (includes cultivation,

dams, urban, plantation, roads, etc)

20%

The wetland habitat is in close proximity to a main road (Garsfontein Road), which supports urban development. As such, the wetland habitat has become transformed.

c) Complete the table to indicate:

(i) the type of vegetation, including its ecosystem status, present on the site; and (ii) whether an aquatic ecosystem is present on site.

Terrestrial Ecosystems Aquatic Ecosystems

Ecosystem threat status as per the

National Environmental Management:

Biodiversity Act (Act No. 10 of 2004)

Critical Wetland (including rivers, depressions, channelled and unchanneled wetlands, flats,

seeps pans, and artificial wetlands)

Estuary Coastline Endangered

Vulnerable

Least Threatened YES NO UNSURE YES NO YES NO

d) Please provide a description of the vegetation type and/or aquatic ecosystem present on

site, including any important biodiversity features/information identified on site (e.g. threatened species and special habitats)

The vegetation type on site is classified as Marikana Thornveld, and is part of the Western Bankenveld Eco

region. The watercourse is a tributary of the Moreleta River and falls within the Crocodile West and Marico

Water Management Area. Refer to Appendix D for Specialist Reports.

Page 35: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

35

SECTION C: PUBLIC PARTICIPATION 1. ADVERTISEMENT AND NOTICE

Publication name Pretoria News

Date published 16 January 2013

Site notice position Site 1 Site 2

Latitude Longitude 25°48’28.3”S 28°18’07.7”E

25°48’06.4”S 28°18’00.6”E

Date placed 11 January 2013

Include proof of the placement of the relevant advertisements and notices in Appendix E1 (Proof of advertisement to be included in the Final Basic Assessment Report). 2. DETERMINATION OF APPROPRIATE MEASURES Provide details of the measures taken to include all potential I&APs as required by Regulation 54(2)(e) and 54(7) of GN R.543. Key stakeholders (other than organs of state) identified in terms of Regulation 54(2)(b) of GN R.543:

Title, Name and Surname Affiliation/ key stakeholder status Contact details (tel number or e-mail address)

No additional key stakeholders were identified however the site notices and newspaper advertisement may result in additional stakeholders registering. Include proof that the key stakeholder received written notification of the proposed activities. (To be included in the Final Basic Assessment Report) This proof may include any of the following:

e-mail delivery reports;

registered mail receipts;

courier waybills;

signed acknowledgements of receipt; and/or

or any other proof as agreed upon by the competent authority. The aforementioned document would be included in the FINAL Basic Assessment Report.

3. ISSUES RAISED BY INTERESTED AND AFFECTED PARTIES

Summary of main issues raised by I&APs Summary of response from EAP

No comments were received to date.

Page 36: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

36

4. COMMENTS AND RESPONSE REPORT The practitioner must record all comments received from I&APs and respond to each comment before the Draft BAR is submitted. The comments and responses must be captured in a comments and response report as prescribed in the EIA regulations and be attached to the Final BAR as Appendix E5. No Comments were received to date. 5. AUTHORITY PARTICIPATION Authorities and organs of state identified as key stakeholders:

Authority/Organ of State

Contact person (Title, Name and Surname)

Tel No Fax No e-mail Postal address

Department of Water Affairs

Lillian Siwelane

012 392 1411

City of Tshwane Metropolitan Municipality (Ward Councillor)

Franscois Bekker

073 087 6999

[email protected]

City of Tshwane Metropolitan Municipality (Ward Councillor)

Nick Pascoe 083 589 2393

086 689 9914

[email protected] [email protected]

City of Tshwane Metropolitan Municipality

Adelene Marais 012 358 0598

086 587 8958

[email protected]

PO BOX 1454 Pretoria, 0001

City of Tshwane Metropolitan Municipality

Ernst Wohlitz 083 255 0090

[email protected]

Department of Environmental Affairs

Fatima Rawjee 072 667 8408

[email protected]

Gauteng Department of Agricultural and Rural Development

Andrew 011 355 1885, 011 355 1241

[email protected]

PO BOX 8769 Johannesburg 2000

Include proof that the Authorities and Organs of State received written notification of the proposed activities as Appendix E3. In the case of renewable energy projects, Eskom and the SKA Project Office must be included in the list of Organs of State. 6. CONSULTATION WITH OTHER STAKEHOLDERS Note that, for any activities (linear or other) where deviation from the public participation requirements may be appropriate, the person conducting the public participation process may deviate from the

Page 37: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

37

requirements of that sub-regulation to the extent and in the manner as may be agreed to by the competent authority. Proof of any such agreement must be provided, where applicable. Application for any deviation from the regulations relating to the public participation process must be submitted prior to the commencement of the public participation process. A list of registered I&APs must be included as appendix E4. Copies of any correspondence and minutes of any meetings held must be included in Appendix E6 (To be included in the Final BAR).

Page 38: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

38

SECTION D: IMPACT ASSESSMENT The assessment of impacts must adhere to the minimum requirements in the EIA Regulations, 2010, and should take applicable official guidelines into account. The issues raised by interested and affected parties should also be addressed in the assessment of impacts.

Methodology for Impact Significance Scoring

The significance (quantification) of potential environmental impacts identified during the Basic Assessment have been determined using a ranking scale, based on the following (terminology has been taken from the Guideline Documentation on EIA Regulations, of the Department of Environmental Affairs and Tourism, April 1998): Occurrence

Probability of occurrence (how likely is it that the impact may occur?)

Duration of occurrence (how long may it last?) Severity

Magnitude (severity) of impact (will the impact be of high, moderate or low severity?)

Scale/extent of impact (will the impact affect the national, regional or local environment, or only that of the site?) Each of these factors has been assessed for each potential impact using the following ranking scales:

The environmental significance of each potential impact is assessed using the following formula:

Significance Points (SP) = (Magnitude + Duration + Extent) x Probability

Probability Duration 1 - very improbable (probably will not happen 2 - improbable (some possibility, but low likelihood) 3 - probable (distinct possibility) 4 - highly probable (most likely) 5 - definite (impact will occur regardless of any prevention measures)

1 - of a very short duration (0–1 years) 2 - of a short duration (2-5 years) 3 - medium-term (5–15 years) 4 - long term (> 15 years) 5 - permanent

Extent Magnitude 1 - limited to the site 2 - limited to the local area 3 - limited to the region 4 - will be national 5 - will be international

0 - small and will have no effect on the environment 2 - minor and will not result in an impact on processes 4 - low and will cause a slight impact on processes 6 - moderate and will result in processes continuing but in a modified way 8 - high (processes are altered to the extent that they temporarily cease) 10 - very high and results in complete destruction of patterns and permanent cessation of processes

Page 39: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

39

The maximum value is 100 Significance Points (SP). Potential environmental impacts were rated as high, moderate or low significance on the following basis: < 30 significance points = LOW environmental significance. 31- 60 significance points = MODERATE environmental significance > 60 significance points = HIGH environmental significance

The table below summarises all the identified impacts and their significance ratings without and with mitigation, while detailed descriptions of each impact are provided there under.

Note there are no feasible alternatives for the gabion construction at the Moreleta Spruit EXCEPT the NO GO Alternative. 1. IMPACTS THAT MAY RESULT FROM THE PLANNING AND DESIGN, CONSTRUCTION,

OPERATIONAL, DECOMMISSIONING AND CLOSURE PHASES AS WELL AS PROPOSED MANAGEMENT OF IDENTIFIED IMPACTS AND PROPOSED MITIGATION MEASURES

Provide a summary and anticipated significance of the potential direct, indirect and cumulative impacts that are likely to occur as a result of the planning and design phase, construction phase, operational phase, decommissioning and closure phase, including impacts relating to the choice of site/activity/technology alternatives as well as the mitigation measures that may eliminate or reduce the potential impacts listed. This impact assessment must be applied to all the identified alternatives to the activities identified in Section A (2) of this report. Note: There are no planning and design phase impacts associated with the proposed development. Refer below for the construction phase, operational phase, decommissioning phase impacts identified and assessed.

CONSTRUCTION PHASE POTENTIAL IMPACTS Activity Impact summary Significance Proposed

mitigation

Alternative 1 (preferred alternative)

Direct impacts: Temporary Vegetation Clearing: During the installation of the gabion structures, vegetation occurring along the river banks was removed to allow for easy accessibility to the site. As a result there would be a Low significance impact (Negative).

Significance Table: Wetland Impacts

Duration Magnitude Extent Probability Significance

1 4 1 3 18

Low

Ensure that rehabilitation measures for the site include re-vegetation of stripped areas. Monitoring of the bare ground must ensure that any signs of soil erosion are immediately addressed.

Page 40: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

40

Activity Impact summary Significance Proposed mitigation

Direct impacts: Increased Traffic in the Wetland: foot and vehicle traffic through the wetland areas may result in damage to naturally occurring plant and animal species, especially smaller vertebrates. As a result there would be a Low significance impact (Negative).

Significance Table: Wetland impacts

Duration Magnitude Extent Probability Significance

1 2 1 3 12

Low

Ensure that rehabilitation measures for the site include re-vegetation and remediation of foot paths and vehicle tracks.

Direct impacts: Soil disruption: excavation activities on site will cause subsoil to become exposed, and can lead to more soil erosion and leaching of stored chemicals in the system. As a result there would be a Low significance impact (Negative).

Significance Table: Wetland Impacts

Duration Magnitude Extent Probability Significance

1 2 1 3 12

Low

Excavated soil stockpiles must be protected from wind erosion, by covering with a tarpaulin. Stockpiles should also be situated away from the watercourse so as not to be susceptible to run-off.

Page 41: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

41

Activity Impact summary Significance Proposed mitigation

Direct impacts: Hydrocarbon Spills: hydrocarbon spills can occur from machinery leaking oil onto the ground. Spillage can also occur during refuelling of equipment on-site. As a result there would be a Low significance impact (Negative).

Significance Table: Wetland Impacts

Duration Magnitude Extent Probability Significance

1 4 1 2 12

Low

Machinery should be regularly serviced and maintained to ensure that there are no oil leaks. Refuelling should be undertaken on an impermeable service and a drip tray used.

Direct impacts: Habitat disturbance: the construction of the gabions has resulted in damming of the Moreleta Spruit, and hence poses a hindrance to the free movement of aquatic species and can result in habitat fragmentation. As a result there would be a Moderate significance impact (Negative).

Significance Table: Wetland Impacts

Duration Magnitude Extent Probability Significance

4 6 2 3 36

Moderate

Gabions should be constructed in a manner that minimises the damming of water by loosely packing the material within the reno-mattress to allow permeability.

Direct impacts: Noise Impacts: heavy machinery and earthmoving machinery can cause noise disturbance to surrounding residents and businesses As a result there would be a Low significance impact (Negative).

Low

Construction activities should be limited to daylight hours (07h00 – 17h00). Further

Page 42: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

42

Activity Impact summary Significance Proposed mitigation

Significance Table: Noise Impacts

Duration Magnitude Extent Probability Significance

1 0 2 4 12

mitigation can include the installation of mufflers onto machinery.

Indirect impacts: Groundwater contamination: hydrocarbon spills can occur from machinery leaking oil onto the ground. This can permeate through to the subsurface, resulting in groundwater contamination or pollution. As a result there would be a Low significance impact (Negative).

Significance Table: Wetland Impacts

Duration Magnitude Extent Probability Significance

1 4 2 2 14

Low

Machinery should be regularly serviced and maintained to ensure that there are no oil leaks. Refuelling should be undertaken on an impermeable service and a drip tray used.

No-go option

Direct impacts: Damage to the fuel pipeline: should the fuel pipeline remain exposed, the pipeline may become damaged either by vandalism or accidental high impact to the exposed area. This will cause environmental, and health and safety impacts, as well as interruption in fuel supply. As a result there would be a Moderate significance impact (Negative).

Significance Table: Infrastructure damage

Duration Magnitude Extent Probability Significance

2 8 3 4 52

Moderate

Undertake measures to protect and prevent damage to the fuel pipeline.

Indirect impacts: Surface Water Pollution and Soil Contamination: should the

Moderate

Undertake

Page 43: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

43

Activity Impact summary Significance Proposed mitigation

fuel pipeline remain exposed, the pipeline may become damaged which could result in petroleum spills into the Moreleta Spruit and onto the ground around the pipeline, resulting in pollution and contamination of the surface water in the watercourse and the ground surface. As a result there would be a Moderate significance impact (Negative).

Significance Table: Wetland impacts

Duration Magnitude Extent Probability Significance

3 8 3 4 56

measures to protect and prevent damage to the fuel pipeline.

Indirect impacts: Fire and explosion risks: rupture of the fuel pipeline can lead to fire or explosion if the liquid petroleum is exposed to open flame or sparks. This poses a health and safety risk to residents and adjacent property owners. As a result there would be a Moderate significance impact (Negative).

Significance Table: Health and Safety

Duration Magnitude Extent Probability Significance

1 8 2 4 44

Moderate

Undertake measures to prevent damage to the fuel pipeline.

Indirect impacts: Health and safety risks: petroleum spills can result in health impacts due to the toxicity and carcinogenic properties of liquid petroleum. As a result there would be a Moderate significance impact (Negative).

Significance Table: Health and Safety

Duration Magnitude Extent Probability Significance

4 8 3 4 60

Moderate

Undertake measures to prevent damage to the fuel pipeline.

Page 44: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

44

OPERATIONAL PHASE POTENTIAL IMPACTS Activity Impact summary Significance Proposed

mitigation

Alternative 1 (preferred alternative)

Direct impacts: Habitat disturbance: the construction of the gabions has resulted in damming of the Moreleta Spruit, and hence poses a hindrance to the free movement of aquatic species and can result in habitat fragmentation. As a result there would be a Moderate significance impact (Negative).

Significance Table: Wetland Impacts

Duration Magnitude Extent Probability Significance

4 6 2 3 36

Moderate

Gabions should be constructed in a manner that minimises the damming of water by loosely packing the material within the reno-mattress to allow permeability. The design alternatives contained in section 2 of this report and the specialist reports (Appendix D) should be implemented.

Direct impacts: Health and Safety: the health and safety risks associated with exposure to liquid petroleum are minimised due to protection of the fuel pipeline. As a result there would be a Moderate significance impact (Positive).

Significance Table: Health and Safety

Duration Magnitude Extent Probability Significance

4 2 2 5 40

Moderate

Regular maintenance must ensure that the pipeline protection measures remain intact.

Page 45: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

45

Activity Impact summary Significance Proposed mitigation

Direct impacts: Soil erosion: should the gabions not be properly designed and implemented, there may be a potential to exacerbate erosion along the watercourse. As a result there would be a Low significance impact (Negative).

Significance Table: Wetland Impacts

Duration Magnitude Extent Probability Significance

2 4 2 2 16

Low

Regular maintenance must ensure that the gabions do not promote soil erosion. Design alternatives provided in section 2 of this report and the specialist reports (Appendix D) must be implemented.

Indirect impacts: Increased traffic in the system: the gabions may be used as a bridge across the watercourse, and therefore increase traffic in the system, which will impact on the surrounding vegetation. Maintenance activities required may also impact on vegetation and small animals and insects. As a result there would be a Low significance impact (Negative).

Significance Table: Wetland Impacts

Duration Magnitude Extent Probability Significance

3 4 2 2 18

Low

Maintenance operations should be limited to the gabion sites, and no unnecessary traffic outside the demarcated area should be undertaken, so as to minimise potential impacts. The use of the gabions as bridges should be restricted.

No-go option

Direct impacts:

The No Go Alternative refers to the development not occurring. As such the following positive benefits would not come to light:

- The protection of the fuel pipeline: the construction of

Moderate environmental significance (Negative)

N/A

Page 46: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

46

Activity Impact summary Significance Proposed mitigation

gabions in the Moreleta Spruit is aimed at protecting the fuel pipeline from further exposure and potential damage and leaks.

- Reduction of soil erosion: the channel erosion upstream from the gabions will be decreased, and the eroded areas will fill up again. The downstream area may also erode less.

- Water table: the water table may be lifted due to the flow

velocity reduction from the gabions, which may improve vegetation quality and wetland functioning.

As noted, the above benefits would not come to light if the project is not authorised and have to be decommissioned. As such the overall cumulative impact of not constructing gabions in the Moreleta Spruit is negative, with a moderate environmental significance.

Significance Table: Wetland Impacts

Duration Magnitude Extent Probability Significance

4 8 3 4 60

Page 47: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

47

DECOMMISSIONING PHASE POTENTIAL IMPACTS Activity Impact summary Significance Proposed

mitigation

Alternative 1 (preferred alternative)

Direct impacts: Increased traffic in the system: the demolition of the gabions will increase traffic in the system during this phase of the project, which will impact on the surrounding vegetation. As a result there would be a Low significance impact (Negative).

Significance Table: Wetland Impacts

Duration Magnitude Extent Probability Significance

3 4 2 2 18

Low

Demolition operations should be limited to the gabion sites, and no unnecessary traffic outside the demarcated area should be undertaken, so as to minimise potential impacts.

Direct impacts: Soil erosion: the demolition of the gabions will result in restoration of the site prior to construction. This implies that erosion will continue along the banks of the river, particularly at the two sites where the fuel pipeline has been exposed. As a result there would be a Moderate significance impact (Negative).

Significance Table: Wetland Impacts

Duration Magnitude Extent Probability Significance

4 6 2 4 48

Moderate

Alternative methods to protect the pipeline must be investigated.

Page 48: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

48

Activity Impact summary Significance Proposed mitigation

Direct impacts: Waste generation: the demolition of the gabions will result in the generation of building rubble, and therefore increase the volumes of waste disposed to landfill should reuse options not be available. As a result there would be a Moderate significance impact (Negative).

Significance Table: Waste Management

Duration Magnitude Extent Probability Significance

4 4 3 3 33

Moderate

Alternative uses of building rubble generated from demolition activities must be investigated.

Direct impacts: Health and Safety: the health and safety risks associated with exposure to liquid petroleum are increased due to removal of the fuel pipeline protection structures. As a result there would be a Moderate significance impact (Negaitive).

Significance Table: Health and Safety

Duration Magnitude Extent Probability Significance

4 2 2 5 40

Moderate

Regular maintenance must ensure that the pipeline protection measures remain intact.

2. ENVIRONMENTAL IMPACT STATEMENT Taking the assessment of potential impacts into account, please provide an environmental impact statement that summarises the impact that the proposed activity and its alternatives may have on the environment after the management and mitigation of impacts have been taken into account, with specific reference to types of impact, duration of impacts, likelihood of potential impacts actually occurring and the significance of impacts. As is evident from this report, the motivation for the construction and operation of the gabion structures within the Moreletta Spruit is rooted in the negative impact of uncontrolled erosion on the structural integrity of the Transnet high pressure liquid petroleum pipeline and the subsequent impact on the social and biophysical environment if said structural integrity is compromised. This assessment illustrates that there are various potential negative and positive impacts that may result from the construction and operation of the gabion infrastructure, although with the implementation of applicable mitigation measures, the negative impacts can be satisfactorily minimised.

Page 49: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

49

The alternatives proposed included design alternatives recommended by the specialist as mitigation measures in terms of the unlawful commencement of the activity. Table 1 below is a representation of all identified impacts and the assessment of significance with and without mitigation. Table 1: Potential Impact Summary Report.

ALTERNATIVES A1 (Preferred Alternative) No-Go

CONSTRUCTION PHASE IMPACTS

POTENTIAL IMPACT Without mitigation

With mitigation

Without mitigation

With mitigation

Temporary Vegetation Clearing (Direct Impact)

Low (-) Low (-)

Increased traffic in the wetland (Direct Impact)

Low (-) Low (-)

Soil disruption (Direct Impact) Low (-) Low (-)

Hydrocarbon spills (Direct Impact) Low (-) Low (-)

Habitat Disturbance (Direct Impact) Moderate (-) Low (-)

Noise impacts (Direct Impact) Low (-) Low (-)

Groundwater contamination (Indirect Impact)

Low (-) Low (-)

Damage to Infrastructure (Indirect Impact)

Moderate (-) Moderate (-)

Surface water and Soil contamination (Indirect Impact)

Moderate (-) Moderate (-)

Fire and Explosion (Indirect Impact) Moderate (-) Moderate (-)

Health and Safety (Indirect Impact) Moderate (-) Moderate (-)

OPERATIONAL PHASE IMPACTS

POTENTIAL IMPACT Without mitigation/

enhancement

With mitigation/

enhancement

Without mitigation

With mitigation

Habitat Destruction (Direct Impact) Moderate (-) Low (-) - -

Health and Safety (Direct Impact) Moderate (+) Moderate (+) - -

Soil Erosion (Direct Impact) Low (-) Low (-) - -

Protection of the fuel pipeline (Direct Impact

Moderate (-) Moderate (-)

Decreased Soil erosion Moderate (-) Moderate (-)

Increased traffic in the system (Indirect Impact)

Low (-) Low (-)

DECOMMISSIONING PHASE IMPACTS

POTENTIAL IMPACT Without mitigation/

enhancement

With mitigation/

enhancement

Without mitigation

With mitigation

Increased traffic in the system (Direct Impact)

Low (-) Low (-)

Soil erosion (Direct Impact) Moderate (-) Low (-)

Waste generation (Direct Impact) Moderate (-) Low (-)

Health and safety (Direct Impact) Moderate (-) Moderate (-)

Page 50: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

50

Key:

The table indicates that with the implementation of mitigation measures, all impacts will be of low significance to the receiving environment. However, given the ecological value and considering that the proposed site forms part of the biodiversity corridor of the Faerie Glen and Rietvlei Nature Reserves, the design alternatives suggested in section 2 of this report and the specialist reports (Appendix D) should be implemented to ensure that the positive impacts identified for the gabion structures are highlighted. Health and Safety Impacts is an important environmental aspect requiring careful mitigation and control. The danger of fire or explosion as a result of damage to the exposed fuel pipeline can have detrimental effects such as fatalities and damage to infrastructure. Ensuring that the fuel pipeline remains protected together with implementing the monitoring measures included into the Environmental Management Programme (See Appendix G) is essential to the sustainability of this project. Several mitigation measures have been proposed to minimise the anticipated environmental impacts together with an environmental management programme report to monitor the effectiveness of these mitigation measures.

Alternative A (preferred alternative)

In terms of the provisions of NEMA, the objectives and principles of Integrated Environmental Management and in the light of the potential impacts detailed above, it is the EAPs recommendation that the activity (Alternative A) be authorised with the condition that all mitigation measures recommend by the specialist be implemented. The EAP further recommends that a limited timeframe be set for the implementation of the mitigation measures.

No-go alternative (compulsory)

The “No-Go” alternative was briefly assessed and compared as shown above.

The gabion construction has positive environmental and health and safety impacts. The purpose of the gabion structure is to protect the fuel pipeline from exposure by the erosive action of the river during high flow periods. Therefore in the event that the application is not authorised the structural integrity of the pipeline will be compromised and the benefits to the receiving environment will not be realised.

High negative impact (-) Negative Impact

Moderate negative impact (+) Negative Impact

Moderate positive impact (-) Positive Impact

Low (-) Negative Impact

Page 51: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

51

SECTION E. RECOMMENDATION OF PRACTITIONER

Is the information contained in this report and the documentation attached hereto sufficient to make a decision in respect of the activity applied for (in the view of the environmental assessment practitioner)?

YES √

NO

If “NO”, indicate the aspects that should be assessed further as part of a Scoping and EIA process before a decision can be made (list the aspects that require further assessment).

If “YES”, please list any recommended conditions, including mitigation measures that should be considered for inclusion in any authorisation that may be granted by the competent authority in respect of the application.

Refer to the EMP attached in Appendix G

Is an EMPr attached? YES NO

The EMPr must be attached as Appendix G. The details of the EAP who compiled the BAR and the expertise of the EAP to perform the Basic Assessment process must be included as Appendix H. If any specialist reports were used during the compilation of this BAR, please attach the declaration of interest for each specialist in Appendix I. Any other information relevant to this application and not previously included must be attached in Appendix J. Sukendrie Paras ________________________________________ NAME OF EAP 14/01/2013 ________________________________________ _________________ SIGNATURE OF EAP DATE

Page 52: BASIC ASSESSMENT REPORT - GIBB

BASIC ASSESSMENT REPORT

52

SECTION F: APPENDICES The following appendices must be attached: Appendix A: Maps Appendix B: Photographs Appendix C: Facility illustration(s) Appendix D: Specialist reports (including terms of reference) Appendix E: Public Participation Appendix F: Impact Assessment Appendix G: Environmental Management Programme (EMPr) Appendix H: Details of EAP and expertise Appendix I: Specialist declaration forms Appendix J: Additional Information