Upload
vumien
View
214
Download
0
Embed Size (px)
Citation preview
Cape Environmental Assessment Practitioners (Pty) Ltd
Reg. No. 2008/004627/07
Telephone: (044) 874 0365 1st Floor Eagles View Building
Facsimile: (044) 874 0432 5 Progress Street, George
Web: www.cape-eaprac.co.za PO Box 2070, George 6530
D.J. Jeffery Directors L. van Zyl
BASIC ASSESSMENT REPORT
for
DYASONSKLIP 1 & 2 AND SIRIUS SOLAR PV
PROJECT 1 – GRID CONNECTION
on
RE/454,RE/638 and Agricultural Holding 1080
In terms of the
National Environmental Management Act (Act No. 107 of 1998, as amended) & 2014
Environmental Impact Regulations
Prepared for Applicant: Scatec Solar SA 163 (Pty) Ltd
By: Cape EAPrac
Report Reference: SIY231b/04
Department Reference: 14/12/16/3/3/1/1447
Case Officer: To be allocated (enquiries: Ms Salome Mambane)
Date: 24 August 2015
APPOINTED ENVIRONMENTAL ASSESSMENT PRACTITIONER:
Cape EAPrac Environmental Assessment Practitioners
PO Box 2070
George
6530
Tel: 044-874 0365
Fax: 044-874 0432
Report written & compiled by: Dale Holder(Ndip, Nat Con), who has 12 years’
experience as an environmental practitioner.
Report reviewed by: Louise-Mari van Zyl (MA Geography & Environmental Science
[US]; Registered Environmental Assessment Practitioner with the Interim Certification
Board for Environmental Assessment Practitioners of South Africa, EAPSA);
Committee Member of the Southern Cape International Association for Impact
Assessments (IAIA). Ms van Zyl has over ten years’ experience as an environmental
practitioner.
PURPOSE OF THIS REPORT:
Public Participation
APPLICANT:
Scatec Solar SA 163 (Pty) Ltd
CAPE EAPRAC REFERENCE NO:
SIY231b/04
DEPARTMENT REFERENCE:
14/12/16/3/3/1/1447
SUBMISSION DATE
24 August 2015
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac Basic Assessment Report
BASIC ASSESSMENT REPORT
in terms of the
National Environmental Management Act, 1998 (Act No. 107 of 1998), as amended &
Environmental Impact Regulations 2014
DYASONSKLIP 1 & 2 AND SIRIUS SOLAR PV
PROJECT 1 – GRID CONNECTION
RE/454,RE/638 and Agricultural Holding 1080
Submitted for:
Stakeholder Review & Comment
This report is the property of the Author/Company, who may publish it, in whole, provided
that:
Written approval is obtained from the Author and that Cape EAPrac is acknowledged in
the publication;
Cape EAPrac is indemnified against any claim for damages that may result from any
publication of specifications, recommendations or statements that is not administered or
controlled by Cape EAPrac;
The contents of this report, including specialist/consultant reports, may not be used for
purposes of sale or publicity or advertisement without the prior written approval of Cape
EAPrac;
Cape EAPrac accepts no responsibility by the Applicant/Client for failure to follow or
comply with the recommended programme, specifications or recommendations contained
in this report;
Cape EAPrac accepts no responsibility for deviation or non-compliance of any
specifications or recommendations made by specialists or consultants whose
input/reports are used to inform this report; and
All figures, plates and diagrams are copyrighted and may not be reproduced by any
means, in any form, in part or whole without prior written approved from Cape EAPrac.
Report Issued by:
Cape Environmental Assessment Practitioners
Tel: 044 874 0365 PO Box 2070
Fax: 044 874 0432 5 Progress Street
Web: www.cape-eaprac.co.za George 6530
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac Basic Assessment Report
ORDER OF REPORT
Summary
Basic Assessment Report
Appendix A : Maps
Appendix A1 : Location & Topographical Maps
Appendix A2 : Biodiversity Overlays
Appendix B : Photographs
Appendix C : Facility Illustrations
Appendix D : Specialist Reports
Appendix D1 : Ecological Specialist Assessment (Todd, 2015)
Appendix D2 : Agricultural Statement (Lubbe, 2015)
Appendix D3 : Visual Impact Statement (Stead, 2015)
Appendix D4 : Heritage Impact Statement (De Kock, 2015)
Appendix D5 : Preliminary Design Report – Power lines (TAP, 2015)
Appendix D6 : Preliminary Design Report – Dyasonsklip onsite Sub Station
(TAP,2015)
Appendix D7 : Preliminary Design Report – Sirius onsite Sub Station (TAP,2015)
Appendix E : Public Participation
Appendix E1 : Advertisements & Site Notices
Appendix E2 : Proof of written notification to stakeholders
Appendix E3 : Comments & Responses table
Appendix E4 : Proof of written notification to Authorities & Organs of State
Appendix E5 : Registered I&AP List
Appendix E6 : Copies of correspondence & Meeting minutes
Appendix F : Impact Assessment
Appendix G : Other Information
Appendix H : Details of EAP and expertise
Appendix I : Specialist’s declaration of interest
Appendix J : Additional Information
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac Basic Assessment Report
TABLE OF CONTENTS
INTRODUCTION .................................................................................................................................... I 1
TECHNICAL DETAILS AND CONSIDERATION OF ALTERNATIVE POWERLINE 2ALIGNMENTS ....................................................................................................................................... II
IMPACT ON THE BIOLOGICAL ENVIRONMENT (FAUNA AND FLORA) ....................................... IV 3
3.1 IDENTIFICATION & NATURE OF IMPACTS ........................................................................................... IV
3.1.1 Construction Phase ........................................................................................................... v
3.1.2 Operational Phase ............................................................................................................. v
3.2 ASSESSMENT OF IMPACTS............................................................................................................... VI
3.2.1 Construction Phase .......................................................................................................... vi
1.2 OPERATIONAL PHASE .................................................................................................................... VII
3.3 CONCLUSION & RECOMMENDATIONS ............................................................................................... IX
POTENTIAL IMPACTS ON HERITAGE RESOURCES ..................................................................... IX 4
4.1 DESCRIPTION OF STUDY AREA ......................................................................................................... IX
4.2 HISTORIC BACKGROUND .................................................................................................................. X
4.3 HERITAGE RESOURCES AND ISSUES ................................................................................................. XI
4.3.1 Cultural Landscape Context ............................................................................................ xi
4.3.2 Archaeology ..................................................................................................................... xii
4.3.3 Palaeontology ................................................................................................................. xiii
4.3.4 Eco-Tourism .................................................................................................................... xiii
4.4 HERITAGE INFORMANTS AND ASSESSMENT OF IMPACTS .................................................................. XIV
4.4.1 Cultural Landscape Context .......................................................................................... xiv
4.4.2 Archaeology .................................................................................................................... xiv
4.4.3 Palaeontology .................................................................................................................. xv
4.5 RECOMMENDATIONS ...................................................................................................................... XV
4.5.1 Recommended Conditions of Approval ........................................................................ xv
ASSESSMENT OF IMPACTS ON AGRICULTURAL RESOURCES ................................................ XV 5
5.1 VEGETATION .................................................................................................................................. XV
5.2 CLIMATE....................................................................................................................................... XVI
5.3 SOILS ........................................................................................................................................... XVI
5.4 LAND CAPABILITY AND SUITABILITY FOR AGRICULTURE ................................................................... XVI
5.5 EROSION POTENTIAL ..................................................................................................................... XVI
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac Basic Assessment Report
5.6 POSSIBLE IMPACTS OF GRID CONNECTION LINES ON EROSION ........................................................ XVII
5.7 POTENTIAL IMPACTS ON AGRICULTURAL RESOURCES .................................................................... XIX
5.8 MITIGATION MEASURES ................................................................................................................. XIX
5.9 CONCLUSION ................................................................................................................................. XX
ASSESSMENT OF IMPACTS ON VISUAL RESOURCES ............................................................... XX 6
6.1 PROJECT VISIBILITY ....................................................................................................................... XX
6.2 KEY LANDMARKS........................................................................................................................... XX
6.3 SUMMARY OF POTENTIAL IMPACTS ................................................................................................ XXI
6.4 PRELIMINARY FINDINGS ................................................................................................................. XXI
6.5 MITIGATIONS AND RECOMMENDATIONS ........................................................................... XXIII
6.5.1 Preferred Routing ......................................................................................................... xxiii
6.5.2 Alternative 1 Routing .................................................................................................... xxiii
6.6 CONCLUSION .............................................................................................................................. XXIII
CONCLUSION ................................................................................................................................ XXIV 7
SECTION A: ACTIVITY INFORMATION ...................................................................................................... 2
PROJECT DESCRIPTION .................................................................................................................... 2 1
FEASIBLE AND REASONABLE ALTERNATIVES ............................................................................. 3 2
PHYSICAL SIZE OF THE ACTIVITY .................................................................................................... 9 3
SITE ACCESS ..................................................................................................................................... 10 4
LOCALITY MAP .................................................................................................................................. 11 5
LAYOUT/ROUTE PLAN ...................................................................................................................... 12 6
SENSITIVITY MAP .............................................................................................................................. 12 7
SITE PHOTOGRAPHS ........................................................................................................................ 12 8
FACILITY ILLUSTRATION ................................................................................................................. 12 9
ACTIVITY MOTIVATION ..................................................................................................................... 13 10
APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES ................................................... 18 11
WASTE, EFFLUENT, EMISSION AND NOISE MANAGEMENT ....................................................... 19 12
WATER USE ....................................................................................................................................... 21 13
ENERGY EFFICIENCY ....................................................................................................................... 22 14
SECTION B: SITE/AREA/PROPERTY DESCRIPTION ............................................................................. 23
GRADIENT OF THE SITE ................................................................................................................... 25 1
LOCATION IN LANDSCAPE .............................................................................................................. 25 2
GROUNDWATER, SOIL AND GEOLOGICAL STABILITY OF THE SITE ........................................ 25 3
GROUNDCOVER ................................................................................................................................ 26 4
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac Basic Assessment Report
SURFACE WATER ............................................................................................................................. 26 5
LAND USE CHARACTER OF SURROUNDING AREA ..................................................................... 27 6
CULTURAL/HISTORICAL FEATURES .............................................................................................. 28 7
SOCIO-ECONOMIC CHARACTER .................................................................................................... 28 8
BIODIVERSITY .................................................................................................................................... 29 9
SECTION C: PUBLIC PARTICIPATION .................................................................................................... 34
ADVERTISEMENT AND NOTICE ....................................................................................................... 34 1
DETERMINATION OF APPROPRIATE MEASURES ........................................................................ 34 2
ISSUES RAISED BY INTERESTED AND AFFECTED PARTIES ..................................................... 34 3
COMMENTS AND RESPONSE REPORT .......................................................................................... 35 4
AUTHORITY PARTICIPATION ........................................................................................................... 35 5
CONSULTATION WITH OTHER STAKEHOLDERS ......................................................................... 35 6
SECTION D: IMPACT ASSESSMENT ....................................................................................................... 42
IMPACTS THAT MAY RESULT FROM THE PLANNING AND DESIGN, CONSTRUCTION, 1OPERATIONAL, DECOMMISSIONING AND CLOSURE PHASES AS WELL AS PROPOSED MANAGEMENT OF IDENTIFIED IMPACTS AND PROPOSED MITIGATION MEASURES ............ 42
ENVIRONMENTAL IMPACT STATEMENT ....................................................................................... 48 2
SECTION E. RECOMMENDATION OF PRACTITIONER .............................................................. 53
SECTION F: APPENDIXES ........................................................................................................................ 56
REFERENCES .............................................................................................................................................. 1
FIGURES
Figure 1: Preferred Layout...................................................................................................................... ii
Figure 2: Alternative Layout.................................................................................................................... iii
Figure 3: Showing proposed single grid connection corridors compared to those authorised. ............ iv
TABLES
Table 1: Assessment of ecological impacts during the construction phase. .......................................... vi
Table 2: Assessment of Ecological Impacts during the Operational Phase .......................................... vii
Table 3: Potential Erosion and Drainage Impacts of the Preferred Grid Connection .......................... xvii
Table 4: Impacts on Erosion and Drainage associated with alternative alignment ........................... xviii
Table 5: Potential Impacts during Construction .................................................................................... xxi
Table 6: Potential Impacts during Operation ........................................................................................ xxi
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac i Basic Assessment Report
REPORT SUMMARY
INTRODUCTION 1
Cape EAPrac was appointed by Scatec Solar 163 (PTY) LTD, as independent environmental
practitioner (EAP), to facilitate the Basic Assessment (BA) process required in terms of the
National Environmental Management Act (NEMA, Act 107 of 1998) for this project.
The purpose of this Basic Assessment Report is to describe the environment to be
affected, the proposed project, the process followed to date (focussing on the outcome of the
Draft Basic Assessment public participation process), to present specialist findings and
recommendations to avoid or minimise impacts, and provide a description of how the
development concept has been adjusted to consider the above.
NOTE: The RE Capital 3, RE Capital 3b and Sirius Solar PV Project 1 (all 3 projects are
DOE preferred bidders) have separate power lines and on site Sub Stations Authorised as
part of their respective EA’s. It is the intention of this project to strategically establish a single
powerline and two on site sub-stations to replace the 3 power lines and 3 on site substations
that have already been authorised. This report should therefore be considered in conjunction
with the Final Environmental Impact Assessment Reports for the RE Capital 3, RE Capital 3b
and Sirius Solar PV Project 1 (14/12/16/3/3/2/538, 14/12/16/3/3/2/538/1, 14/12/16/3/3/2/469)
This Basic Assessment Report is available for a 30 day review and comment period
extending from 31 August 2015 to 30 September 2015. All comments must be submitted to
Cape EAPrac in writing by no later than 30 September 2015 to the details below:
Cape EAPrac
Att: Dale Holder
PO Box 2070, George, 6530
Email: [email protected]
Fax: 044 874 0432.
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac ii Basic Assessment Report
TECHNICAL DETAILS AND CONSIDERATION OF ALTERNATIVE 2POWERLINE ALIGNMENTS
The applicant intends constructing two on site substations and a single 132kV line to connect
three renewable energy projects (DOE Preferred bidders) to the national grid via the Eskom
Upington MTS substation.
Trans Africa Projects were appointed as the technical specialists to provide expertise into the
power line and substation design and implementation. Please refer to Appendix D5 – D7 for
copies of the preliminary design reports. The proposal is that Dyasonsklip 1 and 2 will share
a substation, called Dyasonsklip Substation and evacuate generated power to Sirius
substation by means of a single circuit (SCt) Twin Tern line. From Sirius substation the
power shall be evacuated by means of a SCt Twin Tern line to the new Upington MTS.
Eskom planning has opted for the use of Twin Tern to accommodate future generating plants
planned in the area.
Two alternative powerline alignments are under consideration and have been assessed in
this Basic Assessment Process. These are shown in the figures and described below.
Figure 1: Preferred Layout
The preferred alignment follows the Dyasonsklip 1 and 2 and Sirius 2 solar farm boundaries,
crossing over a dirt access road, to connect to Sirius substation. From Sirius substation it
follows a straight trajectory towards McTaggerts 132kV Line where it makes an underpass
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac iii Basic Assessment Report
crossing. The line then bends in a south-east direction towards the existing Oranje-Oasis
132kV wood pole line where it crosses over at approximately midspan and heads towards its
final bend before termination at the new Upington MTS. The corridor adjacent to McTaggerts
132kV Turn-in Lines has been earmarked as a 400kV line corridor to the new Upington MTS.
In addition to this, the corridor will host a planned access road to the planned Eskom CSP
plant located on the eastern side of the Khi Solar One CSP (Concentrated Solar Power)
facility. The underpass crossing at the McTaggerts 132kV Turn-in Line will be made such
that clearance to the planned 400kV line and access road is maintained.
Figure 2: Alternative Layout
The alternative alignment follows the solar farm boundaries of Dyasonsklip 1 and 2 and
bends toward the existing Oranje-Oasis 132kV line where it runs parallel until turning into
Sirius Substation. The line exits Sirius Substation in a southern direction towards the existing
wood pole line, where it crosses over at approximately midspan and bends to again run
parallel to the existing 132kV line. The last two bends allows it to turn and terminate at the
new Upington MTS.
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac iv Basic Assessment Report
Figure 3: Showing proposed single grid connection corridors (both alternatives shown) compared to the
powerlines already authorised.
IMPACT ON THE BIOLOGICAL ENVIRONMENT (FAUNA, 3AVIFAUNA AND FLORA)
The following considerations and assessment are extracted from the Ecological Impact
Assessment report compiled by Mr Simon Todd and attached in Appendix D1.
3.1 IDENTIFICATION & NATURE OF IMPACTS
In this section, the potential impacts and associated risk factors that may be generated by
the development are identified. In order to ensure that the impacts identified are broadly
applicable and inclusive, all the likely or potential impacts that may be associated with the
development are listed. The relevance and applicability of each potential impact to the
current situation are then examined in more detail in the next section.
Potential ecological impacts resulting from the development of the Grid Connection options
for the Dyasonsklip and Sirius facilities would stem from a variety of different activities and
risk factors associated with the construction and operational phases of the project including
the following:
Planning & Construction Phase
Vegetation clearing & site preparation
Operation of heavy machinery at the site
Human presence
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac v Basic Assessment Report
Operational Phase
Servitude maintenance activities
Power line presence
Human presence
Decomissioning
Operation of heavy machinery at the site
Human presence
The above impacts would be likely to result in the following impacts which are described
briefly below and assessed for each phase of the development as appropriate thereafter:
3.1.1 Construction Phase
Impacts on vegetation and protected plant species
The abundance of protected species such as Acacia erioloba, Boscia albitrunca and Boscia
foetida is high along some parts of the power line routes and some impact on these species
is likely. Should the power line corridor be cleared of all woody vegetation, then the number
of affected trees would be high. Apart from a direct impact on protected species, the clearing
is also likely to impact the vegetation composition and diversity within the affected as well.
Direct Faunal impacts
Increased levels of noise, pollution, disturbance and human presence will be detrimental to
fauna during construction. Sensitive and shy fauna would move away from the area during
the construction phase as a result of the noise and human activities present, while some
slow-moving species would not be able to avoid the construction activities and might be
killed. Some mammals or reptiles would be vulnerable to illegal collection or poaching during
the construction phase as a result of the presence of construction personnel or greater site
access. This impact is however transient and there are not likely to be any long-term
consequences on terrestrial fauna during the operational phase.
3.1.2 Operational Phase
Avifaunal Impacts
Large raptors and many larger bird species such as cranes and bustards are vulnerable to
collisions with or electrocution from power line infrastructure. This can be a particular
problem if the power line lies within the movement or migration pathway of the birds. As
many of the vulnerable species are long-lived slow-breeding species, collisions with power
lines can be a major source of mortality for such species and may threaten the viability of
local or regional populations. Insulating electrical components and fitting bird flight diverters
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac vi Basic Assessment Report
can provide effective mitigation against such impacts and is recommended as standard
practice for new power line infrastructure. Bird flight diverters are however not 100%
effective and reductions in collisions of around 60-70% have been reported from studies
examining the effectiveness of this mitigation measure. As this represents a long-term
cumulative impact associated with the lifetime of the power lines, even relatively low levels of
mortality at any one time can generate significant long-term impacts on local populations of
affected species. Areas near to water bodies, along the tops of ridges and valley heads are
usually areas which generate a lot of collisions and which require specific attention.
Degradation of ecosystems
Maintenance activities such as vegetation clearing as well as the large amount of
disturbance created during construction will leave the site vulnerable to degradation through
alien plant invasion and soil erosion. Areas near to wetlands and watercourses are usually
particularly vulnerable to alien plant invasion and disturbance in these areas should be kept
to a minimum to reduce this risk.
3.2 ASSESSMENT OF IMPACTS
3.2.1 Construction Phase
Table 1: Assessment of ecological impacts during the construction phase.
Nature of impact: Impacts on vegetation and listed or protected plant species resulting from construction activities
Alternative Spatial
Extent Duration Intensity Probability Reversibility
Significance and
Status Confidence
level Without
Mitigation
With
Mitigation
Alternative 1 Local Long-
Term Moderate High Low
Medium
Negative
Low
Negative
High
Alternative 2 Local Long-
Term Moderate High Low
Medium
Negative
Low
Negative
High
No-Go
Alternative Local
Long-
Term
Moderate-
High High Low
Medium-
High
Negative
Low
Negative
High
Mitigation/Management Actions
Preconstruction walk-through of the power line route in order to locate species of conservation concern that can be
translocated as well as comply with the Northern Cape Nature Conservation Act and DENC/DAFF permit conditions.
Construction and vegetation clearing to commence only after walk through has been conducted and necessary permits
obtained.
No large woody species should be cleared from the power line servitude. It may be necessary to remove some individuals
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac vii Basic Assessment Report
Nature of impact: Impacts on vegetation and listed or protected plant species resulting from construction activities
Alternative Spatial
Extent Duration Intensity Probability Reversibility
Significance and
Status Confidence
level Without
Mitigation
With
Mitigation
from the area directly beneath the power line due to safety concerns, however, within the wider servitude the presence of
large woody species does not increase the fire risk and so there are no valid reasons to remove such trees. If these are too
tall and cause safety problems, they can be cut to a lower height rather than removed and, as growth rate in arid areas is
slow, it would take many years before such trees would need to be trimmed again. Such trees can be trimmed to 1m height
if necessary.
Preconstruction environmental induction for all construction staff to ensure that basic environmental principles are adhered
to. This includes awareness as to no littering, appropriate handling of pollution and chemical spills, avoiding fire hazards,
minimizing wildlife interactions, remaining within demarcated construction areas etc.
Vegetation clearing along the power line corridor should only be conducted where necessary and should not be cleared
using herbicides or with a bulldozer. Vegetation can be cleared manually with bush cutters to 0.5m height where
necessary.
Temporary lay-down areas should be located within previously transformed areas or areas that have been identified as
being of low sensitivity.
Nature of impact: Direct Faunal Impacts During Construction
Alternative Spatial
Extent Duration Intensity Probability Reversibility
Significance and
Status Confidence
level Without
Mitigation
With
Mitigation
Local Short-
Term Medium High High
Medium
Negative
Low
Negative
High
Local Short-
Term Medium High High
Medium
Negative
Low
Negative
High
Local Short-
Term Medium High High
Medium
Negative
Low
Negative
High
Mitigation/Management Actions
All personnel should undergo environmental induction with regards to fauna and in particular awareness about not harming
or collecting species such as snakes, tortoises and owls, which are often persecuted out of superstition.
Any fauna threatened by the construction activities should be removed to safety by the ECO or appropriately qualified
environmental officer.
All construction vehicles should adhere to a low speed limit to avoid collisions with susceptible species such as snakes and
tortoises.
All hazardous materials should be stored in the appropriate manner to prevent contamination of the site. Any accidental
chemical, fuel and oil spills that occur at the site should be cleaned up in the appropriate manner as related to the nature of
the spill.
If holes or trenches need to be dug, these should not be left open for extended periods of time as fauna may fall in and
become trapped in them. Holes should only be dug when they are required and should be used and filled shortly thereafter.
1.2 OPERATIONAL PHASE
Table 2: Assessment of Ecological Impacts during the Operational Phase
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac viii Basic Assessment Report
Nature of impact: Avifaunal impact due to collision or electrocution from power line.
Alternative Spatial
Extent Duration Intensity Probability Reversibility
Significance and Status
Confidence
level Without
Mitigation
With
Mitigation
Alternative 1 Local Long-term Medium High Low Medium
Negative
Low
Negative High
Alternative 2 Local Long-term Medium High Low Medium
Negative
Low
Negative High
No-Go
Alternative Local Long-term Medium High Low
Medium
Negative
Low
Negative High
Mitigation/Management Actions
All new power line infrastructure should be bird-friendly in configuration and adequately insulated (Lehman et al. 2007).
The sections of the line over ridges and near drainage lines should be fitted with bird flight diverters (flappers) and the live
components should be insulated to reduce electrocution problems. Sections to be fitted with flappers should be identified
during the walk-through of the final route and informed by bird movements in the area.
Surveys along the power line for dead birds should be conducted monthly for a year after construction to ascertain if there
are any sections present which are generating a high impact on avifauna and where additional mitigation is necessary.
Nature of impact: Ecosystem degradation along the power line route due to erosion and alien plant invasion.
Alternative Spatial
Extent Duration Intensity Probability
Reversibi
lity
Significance and Status
Confidence
level Without
Mitigation
With
Mitigation
Alternative 1 Local Long-term Medium High Low
Medium-
Low
Negative
Low
Negative High
Alternative 2 Local Long-term Medium High Low
Medium-
Low
Negative
Low
Negative High
No-Go
Alternative Local Long-term Medium High Low
Medium-
Low
Negative
Low
Negative High
Mitigation/Management Actions
Regular erosion and alien plant management along the power line servitude.
Herbicides should only be used on alien species and should not be broadcast or sprayed and should only be used on cut-
stump type applications where it is applied by hand to specific plants.
During operation and maintenance of the power line servitudes, alien species especially large woody species such as
Prosopis glandulosa should be cleared from the power line servitudes.
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac ix Basic Assessment Report
3.3 CONCLUSION & RECOMMENDATIONS
The integrated, combined grid connection for the Dyasonsklip and Sirius PV facilities would
generate a lower overall impact than the original 3 grid connections. The main benefit would
be the need for a single line from the Dyasonsklip facilities compared to the current double
line.
In terms of the two alternatives considered for the combined grid connection, the main
difference between the two alternatives is that the Alternative 2, the southern route runs
adjacent to the existing Oranje-Oasis 132kV power line for a large proportion of the route.
This reduces the potential impact of this alternative as the same access route can be used
and some potentially important impacts such as avifaunal collisions may be significantly
lower as a result of the proximity to the existing line. However, this alternative also has
significant sections away from the existing Oranje-Oasis 132kV line, especially the section
looping in and out of the Sirius substation. Consequently, this difference is not considered
significant. As a result, there is not a significant difference between the two proposed
alternatives and both are considered acceptable alternatives from a terrestrial ecology point
of view.
The conclusion of this study is that either or the proposed alternatives would be acceptable
ecologically and that with reasonable mitigation applied, there would be no highly significant
long-term impacts associated with the grid connection. The current preferred alternative
from a technical perspective is Alternative 1 and there are no reasons that this alternative
should not be authorised in favour of Alternative 2.
POTENTIAL IMPACTS ON HERITAGE RESOURCES 4
Mr Stephan de Kock of Perception heritage planning provided an Intergrated Heritage Impact
Statement for this proposed development, from which the following summary is drawn.
Please refer to the Heritage Impact statement attached in Appendix D4 for further information
in this regard.
4.1 DESCRIPTION OF STUDY AREA
From a regional perspective the study area is situated ±28km southwest of Upington, ±25km
northeast of Keimoes and northwest of the Orange River (Figure 1). It is ±1.7km northwest of
the N14 National Road and adjoins the Khi Solar One CSP (Concentrated Solar Power)
facility currently under construction (see Figure 2). The study area is located within the ZF
Mgcawu district of the Northern Cape Province and jurisdiction area of the Khai Garib Local
Municipality.
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac x Basic Assessment Report
Morris (2013) describes the environment of the farm as an arid, gently sloping plain with
shallow drainage lines running through it. The landscape is very sparsely vegetated. Higher
ground drains towards multiple depressions (seasonal washes), forming waterways towards
the river corridor. No structures or ruins were noted along the proposed transmission line
alignments.
4.2 HISTORIC BACKGROUND
From a colonial perspective, early travellers such as Wikar and Gordon travelled along the
Orange River in the 1770s and described various communities living along the river (Penn
1995). By the mid-19th century the stretch of the Orange River to the west of Upington was
settled by the Korana, a Khoekhoen group whose origins are still unclear (Strauss 1979).
With increasing Trekboer encroachment from the south, the Korana became involved in a
struggle to maintain an independent existence. The attempt by the Korana to resist resulted
in two wars, that of 1868-9 and 1878-9.
According to Morris (2013), the name Dyason’s Klip is derived from events which occurred
during the Korana War of 1879-1880. Apparently a certain Captain Dyason of the Northern
Border Police was killed by Korana adversaries while walking between two rocks at this
place in 1880. However, it is not recorded exactly where these stones are situated. The
adjoining property of McTaggarts Camp also derives its name from events during the Korana
War when Captain McTaggart set up his military camp here. It is assumed that the camp was
located close to the river and that it is unlikely to have left much of an archaeological trace.
In his assessment of the farm Olyvenhout’s Drift, Dreyer (2006) reported finding a heavily
soldered food tin resembling British rations from the Anglo-Boer War (1899-1902). He
considered it possible that a British camp may have existed in the area. Van der Walt (2011)
reported the presence of a sandy track marking an old wagon-track on the farm Geel Kop to
the west of Dyason’s Klip. The wagon road between Keimoes and Upington crossed the farm
and is marked on maps dating to 1908 (Van der Walt 2011). To the north of the farm Geel
Kop, on the farm Van Rooi’s Vley 443, is the Rebellion Tree monument (Van der Walt 2011).
It marks the Rebellion of 1914 in which many Afrikaners opposed the plan of the South
African government to invade German South-West Africa at the commencement of World
War I (Van Vollenhoven 2012). The site is a Provincial Heritage site.
Van der Walt (2011) mentions the presence of mining exploration trenches on the farm Geel
Kop dating to 1929 and Morris (2013) also reports on tungsten mining on the north-western
portion of the farm McTaggarts Camp dating to the early 1930s. Morris (2013) identified two
ruined mud-brick structure, presumably that of 19th/20th century farm workers, on the farm
Dyason’s Klip.
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xi Basic Assessment Report
Early mapping (1906-1914) shows the location of former farmsteads on early farms in
relation to the proposed site boundary. The mapping highlights the alignment of several
historic roads through the area, including that of the current N14, which remains roughly
unchanged. Mapping furthermore emphasises use of the area for sheep farming and
describes soil conditions as sandy, with several pans and dams within the proximity
Dyason’s Klip.
Basic historic background research did not identify or highlight any significant historic or
other heritage-related themes, which may be negatively impacted through the proposed
development.
4.3 HERITAGE RESOURCES AND ISSUES
4.3.1 Cultural Landscape Context
The term “cultural landscape” refers to the imprint created on a natural landscape through
human habitation and cultivation over an extended period of time. While the Cape has been
inhabited for many hundreds of thousands of years (pre-colonial history) prior to Western
settlement (colonial history), the nomadic lifestyles of early inhabitants are rarely as evident
within the landscape as the imprints made by humans during the last two – three hundred
years and more. Unlike ancient landscapes in parts of the world where intensive cultivation
over periods much longer than locally have allowed natural and cultural components of the
landscape to become interwoven, landscape components along the Southern Cape have not
yet developed in such a manner. The fact that natural and cultural landscape components in
the region is therefore more distinguished means that the cultural landscape tends to be very
vulnerable to the cumulative impact of inappropriate large-scale development.
“The concept of landscape gives expression to the products and processes of the spatial and
temporal interaction of people with the environment. It may thus be conceived as a particular
configuration of topography, vegetation cover, land use and settlement pattern which
establishes some coherence of natural and cultural processes and activities.” (Green,
B.H.1995).
Taken in conjunction of the above the study area therefore forms part of a cultural landscape,
which by itself, as well as within a broader context, provides a more lasting framework for the
understanding and management of heritage resources. While it itself a heritage resource,
cultural landscape could in a sense the cultural regarded as a “patchwork” within which all
other heritage resources are embedded and which adds to their meaning and sense of place.
While the NHRA does not clearly define the term “cultural landscape”, it is briefly referred to
in the schedule of definitions. Based on local and international best-practice and within the
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xii Basic Assessment Report
context of definitions assigned to the terms heritage resource, place and cultural significance,
cultural landscape can be defined as “A place of cultural significance, which engenders
qualities relating to its aesthetic, architectural, historical, scientific, social, spiritual, linguistic,
technological, archaeological or palaeontological value ”.
The site may be described as forming part of a typical Kalahari landscape and defined by flat
and wide open spaces overgrown by sparse, low-growing vegetation. From a Pre-Modern
perspective, the site formed part of an area mostly used for small stock farming and so,
modern man-made features noted on the site included e.g. shallow pans, fences, wind
pumps and cement water reservoirs related to said land use. The study area is north of the
Orange/ Gariep River Corridor, which is characterised by intensive agricultural farming,
including vineyards. The landscape within the direct proximity of the study area is visually
dominated by the 200m high CSP structure, directly east of the subject site. Of further
relevance is the fact that several other solar energy facilities had already been authorised
within the study area. From a cultural landscape perspective therefore, the study area is
considered to be of no local cultural significance.
4.3.2 Archaeology
Findings from archaeological impact assessments undertaken with relation to the already-
authorised solar energy facilities to which this proposal relate, did not identify or highlight any
archaeological resources considered of high or moderate cultural significance. These
findings may be summarised as outlined below:
While Morris (July 2013) identifies vleis as potential areas of interest from archaeological
perspective, none of these features occur along the proposed transmission line alignments.
Morris did not identify any archaeological resources of significance and did not recommend
any mitigation or archaeological monitoring to be undertaken.
During field work, ACO Associates (November 2014) identified, “Very ephemeral scatters of
ESA and MSA material; Some stone cairns which are unlikely to represent graves; A ruined
mud brick shepherd’s hut and Evidence for 20th century mining, possibly of tungsten”. The
report concludes that potential impacts of the proposal are likely to be limited and
controllable and does not recommend any mitigation or the need for archaeological
monitoring during the construction phase. The report recommends that:
- If any human remains are uncovered during construction, the ECO should have the
area fenced off and contact SAHRA (Tel: 021 462 4502) immediately;
- If there are any significant changes to the layout of the facility, the new design should
be assessed by a heritage practitioner.
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xiii Basic Assessment Report
GA Heritage (October 2013) identified scatterings of Stone Age archaeological occurrences,
most of which were likely to be of Later Stone Age origin and one of Middle Stone Age origin.
The report indicates that finds were not concentrated or unique but recommends that
archaeological monitoring of construction excavations be undertaken.
4.3.3 Palaeontology
The findings and recommendations of three desktop palaeontological studies for each of the
already-permitted solar energy facilities, all of which were compiled by Natura Viva (Dr. John
Almond) conclude that no further related studies or mitigation were required for any of said
facilities. With relation to the Dyasonsklip area, the reports all indicate that, “The igneous
and metamorphic Precambrian basement rocks underlying the Dyasonsklip study area at
depth are entirely unfossiliferous. The overlying aeolian sands and stream gravels of the
Kalahari Group mantling the older bedrocks are generally of low palaeontological sensitivity”
and concludes that, “the proposed Dyasonsklip Solar Energy Facility 1 near Upington,
including the associated transmission line, is unlikely to have significant impacts on local
palaeontological heritage resources”.
The reports furthermore recommends that, pending the discovery of significant new fossils
remains before or during construction, exemption from further specialist palaeontological
studies and mitigation be granted” but that, “Should any substantial fossil remains (e.g.
mammalian bones and teeth) be encountered during excavation, however, these should be
safeguarded, preferably in situ, and reported by the ECO to SAHRA, i.e. The South African
Heritage Resources Authority, as soon as possible (Contact details: Mrs Colette
Scheermeyer, P.O. Box 4637, Cape Town 8000. Tel: 021 462 4502 (Email:
[email protected]), so that appropriate action can be taken by a professional
palaeontologist, at the developer’s expense. Mitigation would normally involve the scientific
recording and judicious sampling or collection of fossil material as well as associated
geological data (e.g. stratigraphy, sedimentology, taphonomy) by a professional
palaeontologist.”
4.3.4 Eco-Tourism
One of the goals of ecotourism is to offer tourists insight into the impact of human beings on
the environment, and to foster a greater appreciation of our natural habitats and from an
economic perspective, heritage resources may prove to be valuable resources when used in
sustainable manner through eco-tourism. This may for example include investment in
adaptive reuse of historic buildings so as to conserve and enhance the unique character and
historic themes pertinent to this area. Heritage tourism can therefore serve as a driver for
economic development, including infrastructure development and poverty alleviation through
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xiv Basic Assessment Report
job creation. The broader region’s rich archaeological, palaeontological, historical and natural
heritage has the potential to provide unique tourism opportunities when developed and used
in responsible and sustainable ways.
Given the location as well as pattern of existing land use in and within the proximity of the
study area and furthermore, the very low density of heritage resources considered of cultural
significance noted as part of this assessment, we do not consider that the proposed
development would offer significant heritage-related eco-tourism opportunities.
4.4 HERITAGE INFORMANTS AND ASSESSMENT OF IMPACTS
According to the requirements of Section 38(3) of the NHRA it is crucial that the land use
planning and EIA processes be informed by and incorporate heritage informants and
indicators as done through mapping and grading of relevant heritage resources identified as
part of a HIA. It is the purpose of this Section to summarise heritage informants and
indicators and the manner in which heritage resources should be incorporated into the
overall design of the proposed development.
4.4.1 Cultural Landscape Context
From a regional and natural landscape perspective, the proposed development site forms
part of a highly-transformed landscape that has already been altered through mining
activities as well as high concentration of proposals for development of renewable energy
(solar) facilities. The proposal put forward in this report would relate to a significant reduction
in the total distance of transmission lines required to be installed for the Sirius 1 and
Dyasonsklip 1 & 2 solar energy facilities by combining the three already approved
transmission line alignments into a single route alignment.
While the proposal would relate to a landscape modification, we are of the view that this
proposal would significantly reduce the overall visual impact of the proposal. Even if not the
case, we are of the view that none of the two route alignment alternatives would materially
alter any natural or cultural landscape of cultural significance.
4.4.2 Archaeology
Findings and recommendations from archaeological impact assessments undertaken with
relation to the already-authorised solar energy facilities to which this proposal relate, did not
identify or highlight any archaeological resources considered of high or moderate cultural
significance. Given the nature of the proposal, which would not traverse any archaeological
occurrences identified, it is the specialists view that none of the two route alignment
alternatives as put forward herewith would warrant any further archaeological investigation,
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xv Basic Assessment Report
subject to the recommendations set out in Section 7.2 of the Heritage Report attached in
Appendix D4.
4.4.3 Palaeontology
It is concluded that none of the two route alignment alternatives are likely to have any
significant impacts on local palaeontological heritage resources. However, the
recommendations reflected in the desktop palaeontological study, shall be adhered to.
4.5 RECOMMENDATIONS
Based on the information submitted and the findings of this assessment it is recommended
that the recommendations below be incorporated into the proposed development and that
the Department of Environmental Affairs be informed accordingly:
4.5.1 Recommended Conditions of Approval
- If any human remains are uncovered during construction, the ECO should have the
area fenced off and contact SAHRA (Tel: 021 462 4502) immediately
- Should any substantial fossil remains (e.g. mammalian bones and teeth) be
encountered during excavation, however, these should be safeguarded, preferably in
situ, and reported by the ECO to SAHRA, i.e. The South African Heritage Resources
Authority, as soon as possible (Contact details: Mrs Colette Scheermeyer, P.O. Box
4637, Cape Town 8000. Tel: 021 462 4502 (Email: [email protected]), so
that appropriate action can be taken by a professional palaeontologist, at the
developer’s expense. Mitigation would normally involve the scientific recording and
judicious sampling or collection of fossil material as well as associated geological
data (e.g. stratigraphy, sedimentology, taphonomy) by a professional palaeontologist.
ASSESSMENT OF IMPACTS ON AGRICULTURAL RESOURCES 5
Mr Christo Lubbe compiled an agricultural Impact Statement from which the following is
drawn. Please refer to the Agricultural Impact Statement Attached in Appendix D2 for further
information in this regard.
5.1 VEGETATION
All three projects and this grid connection are situated in the Nama Karoo Bushmanland Eco
zone. The region is marked by Karoo and Karroid veld types. Sweet grass and shrub veld
occur, while tree density is less than 5%. The Normalised Difference Vegetation Index
(NDVI) is low. Grazing capacity is low at 31 to 40 hectares per large stock unit (LSU).
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xvi Basic Assessment Report
5.2 CLIMATE
This is an arid zone with few perennial rivers. Summers are hot to extremely hot, while
winters may cool down to -5°C. Frost occurs from late April through to October, thus
rendering is a very short growing season for frost–sensitive crops. Summer rainfall peaks in
March, ranging between 0-200mm in this specific area. Unpredictable drought is a feature of
the entire Eco zone.
5.3 SOILS
Soils associated with arid landscapes and mineral composition presence in this area, are
Silicic soils - soils that have a subsurface horizon cemented by silica. The hard set
subsurface layer (known as Dorbank) limits rooting depth. Calcium is another dissolved
product of rock weathering that, like silica, remains behind to form a cemented soil as a
result of water evaporation in arid environments. The two layers formed as such ((i) soft and
(ii) hardpan carbonate horizons) also acts as depth limiting factor.
5.4 LAND CAPABILITY AND SUITABILITY FOR AGRICULTURE
Land capability involves the consideration of the risk of land damage from erosion and other
causes and the difficulties in land use owing to physical land characteristics, including
climate.
The potential agricultural capability of the project based on the natural resources identified
shows that the site is largely unsuitable for cultivation due to the following limiting factors:
Low annual rainfall, high evaporation and extreme temperatures restrict dry land cultivation.
The very shallow soil depth with its limited water holding capacity that restricts root development
The very fine sand grade of top soil influences the stability and increases erodibility potential.
Low clay percentage results in low water holding capacity and low nutrient availability, resulting in low soil fertility.
5.5 EROSION POTENTIAL
In this arid climate, the erosivity (the potential ability of rain to cause erosion) is low, but the
erodability (vulnerability of the soil to erosion) is high due to the low clay percentage and
shallow soil depth. Possible erosion caused by water is low, due to the characteristics of the
terrain, i.e.:
Low annual rainfall
Regular slope of 1.6%
Length of slope is short
Small catchment area, because water drain naturally away from the ridge.
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xvii Basic Assessment Report
The risk of erosion caused by wind is high, due to the low clay percentage of the soil and the
fact that the soil is usually dry - therefore prone to blow away. To combat this erosion,
vegetation is needed, but the severe climatic conditions prevent possible mechanical
conservation measures. However, this erosion risk already exists and the proposed grid
connection lines will have a low impact.
5.6 POSSIBLE IMPACTS OF GRID CONNECTION LINES ON EROSION
The Tables below show the routes of the alternatives ant their potential impacts on erosion
and drainage patterns.
Table 3: Potential Erosion and Drainage Impacts of the Preferred Grid Connection
Stretch Remarks
1-2 Low influence on down flow because it lies on the ridge and water will drain outwards
2-3 Will catch down flow and provision for diversion drains. The specialist has recommended
that provision for low water bridge must be made to cross the main drain. The project
engineers have however confirmed that it will not be necessary to construct formal
maintenance tracks across this watercourse. Furthermore, Pylons will be constructed
outside of the watercourses.
3-5 In the valley, it will have a low influence on run-off. The specialist recommended that
where the road crosses the main drainage line, provision for a low water bridge must be
made to ensure that no blockages occur in the down flow. The project engineers have
however confirmed that it will not be necessary to construct formal maintenance tracks
Main drainage
Ridge
Concrete Furrow
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xviii Basic Assessment Report
across this watercourse. Furthermore, Pylons will be constructed outside of the
watercourses. Provision for diversion drains must be made.
4-5 On both sides of the ridge, it will have a low influence on down flow. Water will drain away
from the road naturally.
5-10 Provision for diversion drains should be made as the road lies perpendicular on the flow
direction.
Table 4: Impacts on Erosion and Drainage associated with alternative alignment
Stretch Remarks
1-2 Low influence on down flow because it lies on the ridge and water will drain
outwards
2-4 Will catch down flow and provision for diversion drains must be made. The
specialist confirmed that where the road crosses main drainage lines, provision
for low water bridges must be made to ensure that no blockages occur in down
flow.
The project engineers have however confirmed that it will not be necessary to
construct formal maintenance tracks across this watercourse. Furthermore,
Pylons will be constructed outside of the watercourses.
3-4 Provision for diversion drains must be made.
4-5 On both sides of the ridge, it will have a low influence on down flow. Water will
Main drainage
Ridge
Concrete furrow
Main drainage
Ridge
Concrete furrow
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xix Basic Assessment Report
drain away from the road naturally.
5-10 Provision for diversion drains should be made as the road lies perpendicular on
the flow direction.
5.7 POTENTIAL IMPACTS ON AGRICULTURAL RESOURCES
Potential impacts of the proposed project on agriculture were identified and considered, with
particular attention to the following aspects:
The possibility of permanent loss of high potential agricultural land;
Impairment of land capability due to construction;
Veld conditions for grazing may deteriorate.
Analysis of erosion risk because of altered drainage patterns and poor rehabilitation in erosion-sensitive areas.
Positive impacts are the following:
The single line would be more beneficial to the environment because two instead of three substations will be constructed.
The preferred alignment would have the least effect on the drainage because of the shorter distance spent in valley and longer on ridge.
The entrance into the drainage channel is with a wider angle and less obstructive to run off water.
The preferred alternative is closer to the PV station, resulting in a smaller area of the farm occupied, leaving bigger uninterrupted grazing space.
5.8 MITIGATION MEASURES
The following measures are recommended:
- Make use of veld strips to combat wind erosion. Carbonate is a very fine material for
road building, increasing cohesion, thus improving resistance to wind erosion. Ridge
left by grader that is perpendicular to the direction of the prevailing wind increase
roughness of soil surface combat erosion. Ridges must not be higher than 40cm or
the wind will lop off the tops and speed up the erosion.
- Provide effective waterways to channel run-off water as part of its road network.
- Place diversion channels in the road to divert water out of the road. Place on intervals
of 40-50m and ensure that outflow is not deposited on the one beneath.
- Due to the flat topography, the gullys are not deep, but usually have a high
percentage of silt and sand washed or wind blown in its basin, making crossing
difficult. Low water bridges could overcome this problem. NB: It is not neccesary to
impliment this reccomendation, as the project engineers have confirmed that it is not
neccesary to include formal access tracks across the watercourses.
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xx Basic Assessment Report
5.9 CONCLUSION
The Agricultural Specialist has concluded that it is his opinion that a single power line and
two on site substations to serve all three proposed PV Power plants, will have less impacts
on agriculture on site than the three separate grid connections and substations as authorised
during the previous EIAs of the three projects.
However, drainage patterns may be disturbed by construction of the grid line and poor
rehabilitation may increase erosion risks. These can be mitigated/avoided by following the
recommendations stated.
ASSESSMENT OF IMPACTS ON VISUAL RESOURCES 6
The following was extracted from the Visual Impact Assessment Compiled by Mr Stephen
Stead as attached in Appendix D5.
6.1 PROJECT VISIBILITY
The visible extent, or viewshed, is ‘the outer boundary defining a view catchment area,
usually along crests and ridgelines’ (Oberholzer, 2005). This reflects the area, or extent,
where a landscape modification of a specified height would probably be seen. As the
viewsheds were undertaken for both the previous project transmission lines, indicating a
localised extent, a viewshed analysis was not undertaken for this transmission line.
However, an approximate zone of visual influence (ZVI) of the proposed activities was
defined. The ZVI was restricted to 4km as the monopoles have a relatively small visual
footprint, which dissipates in the surrounding middle ground areas. In addition, visibility
tends to diminish exponentially with distance, which is well recognised in visual analysis
literature ((Hull, R.B. and Bishop, I.E., 1988).
6.2 KEY LANDMARKS
Based on the 4km ZVI defined above, the following landmarks were identified as significant
in defining the surrounding areas characteristic landscape:
• Orange River
• Khi Solar One CSP Facility and Other Solar Energy Facilities
• Existing 132 kv Transmission Line
• Higher VAC levels along certain sections of the N14 National Road
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xxi Basic Assessment Report
6.3 SUMMARY OF POTENTIAL VISUAL IMPACTS
Table 5: Potential Visual Impacts during Construction
Alternative Nature Extent Duration Intensity Probability Status Degree of
confidence
Level of
Significance
Significance
after
Mitigation
Status
Quo
Degradation
of scenic
resources
Local Short
Term Medium Likely Negative High Medium Medium
Preferred
Alternative
Degradation
of scenic
resources
Site Short
Term Low Likely Negative High Low Low
Alternative
1
Degradation
of scenic
resources
Site Short
Term
Medium
to Low Likely Negative High Low Low
Table 6: Potential Impacts during Operation
Alternative Nature of
Impact
Extent of
Impact
Duration of
Impact Intensity Probability
Status of
Impact
Degree of
confidence
Level of
Significance
Significance
after
Mitigation
Status
Quo
Degradation
of scenic
resources
Local Permanent Medium
to High
Distinctly
Possible Negative High
Medium
to High
(Cumul.)
Medium
to High
(Cumul.)
Preferred
Alternative
Degradation
of scenic
resources
Local Permanent Low Likely Negative High Low Low
Alternative
1
Degradation
of scenic
resources
Local Permanent Medium Distinctly
Possible Negative Medium
Medium
to High
(Cumul.)
Medium
to High
(Cumul.)
6.4 PRELIMINARY FINDINGS
The nature of the impact was defined as negative due the potential degradation of local
scenic resources, which includes open and undulating Kalahari landscapes, as well as
drainage lines. Topographically, both routes have similar spatial statistics, but with the
Preferred Alternative routed over a small rise between two river valleys, but not to the degree
where it becomes prominent to the surrounding areas. Due to the closer proximity of
Alternative 1 to the N14 National Road, which falls within the route ZVI, the routing is slightly
more visually prominent.
The construction phase extent of the visual impact (zone of visual influence) would be
contained on site for the two new routing alternatives, but the status quo is rated local due to
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xxii Basic Assessment Report
the larger coverage of the multiple routes. Operation phase extent was rated local for all
routings, it is unlikely that the negative effects of the proposed power line routings would
extend beyond the local extent due to the small visual footprint of the proposed landscape
modification. The duration of the impact was rated short term for the construction phase, and
permanent for the operation, as it is likely that the proposed power lines will remain in the
landscape for longer than 20 years.
The intensity of the construction phase was rated medium for the Status Quo, low for the
Preferred Alternative and medium to low for the Alternative 1. This is due to the higher visual
absorption capacity of the landscape for all routes. The Status Quo and Preferred
Alternative would be routed adjacent to the authorized SEF’s, and the Alternative 1 would be
routed adjacent the existing Eskom 132kV power line. Operational phase intensity was rated
medium to high for the Status Quo, low for the Preferred, and medium for Alternative 1. The
higher ratings for the Status Quo relate to the wider distribution of the impact, which like the
Alternative 1 Routings, also falls within the N14 National Highway zone of visual influence
(hence rated higher than the Preferred which is located further away from the N14 National
Road).
Construction phase impacts are likely to take place, but there is a distinct possibility of the
Status Quo operational impacts taking place due to the wider visual distribution, and lack of
coordinated alignment to existing cadastral or infrastructure in the landscape, creating a
cluttered landscape effect. It is also distinctly possible for the Alternative 1 Routings impacts
to take place, which falls within the N14 zone of visual influence. Due to the background
position of the Preferred Routing, which is routed adjacent the authorized SEF projects, the
impact is likely on the small area of slightly raised ground between the two river valleys.
Construction phase visual impact significance was rated medium for the Status Quo, due to
the medium intensity and local extent, and low for both the new routing options (due the
small visual footprint of the construction phase impacts). Operation phase visual impact
significance was rated medium to high for the Status Quo, due to the cumulative visual
impacts from the cluttering of the landscapes, setting a precedent for un-aligned routing
corridors taking place in the future. Alternative 1 significance was also rated medium to high
due to the north-south section of the line (Sirius SS LILO), creating a structure barrier that
would force any future power line routings to follow the same route, crossing over the
existing Eskom 132kV line, and creating a power line corridor to the south of the existing line
that is in close visual proximity to the N14 National Road. This barrier effect is not apparent
for the Preferred Alternative, which would allow for a new power line corridor, running parallel
to the existing Eskom 132kV line, but with a suitable gap and with the routing corridor
location outside of the ZVI of the N14 National Road (hence the Preferred Routing was rated
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xxiii Basic Assessment Report
low). As mitigation would not likely reduce the resultant visual impacts, significance for all
the routings was rated the same as without mitigation. However, mitigations in terms of best
practice are recommended.
6.5 MITIGATIONS AND RECOMMENDATIONS
6.5.1 Preferred Routing
It is the recommendation of the study that the Preferred Routing Alternative is visually
preferred, with the following mitigations:
- Utilisation of existing northsouth access roads to access the corridor;
- Location of the pylons outside of drainage lines, or significant biodiversity areas (as
per the ecology specialists findings);
- Soil erosion management along the maintenance road along the proposed corridor.
- The Preferred Alternative makes a kink to follow the Sirius SEF footprint areas. If
possible, it is recommended that the route be aligned as straight as possible, so that
any further power lines from future SEF projects to the west, will also be routed in a
straight line (adjacent the proposed routing).
6.5.2 Alternative 1 Routing
It is the recommendation of the study that Alternative 1 Routing is not implemented, due to
the higher visual impacts associated with cumulative degradation of the landscapes falling
within the N14 National Road. Should this alternative be implemented, the following
mitigations are proposed:
- Future power lines should be routed to the north of the authorised;
- Utilisation of existing northsouth access roads to access the corridor;
- Location of the pylons outside of drainage lines, or significant biodiversity areas (as
per the ecology specialists findings);
- Soil erosion management along the maintenance road along the proposed corridor.
6.6 CONCLUSION
It is the recommendation of the study that the Preferred Routing Alternative is visually
preferred. Operation phase visual impact significance was rated medium to high for the
Status Quo option, due to the cumulative visual impacts from the cluttering of the
landscapes, setting a precedent for un-aligned routing corridors taking place in the future.
Alternative 1 significance was also rated medium to high due to the north-south section of the
line (Sirius SS LILO), creating a structure barrier that would force any future power line
routings to follow the same alignment, crossing over the existing Eskom 132kV line,
essentially setting a precedent for a power line corridor to the south of the existing line. This
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xxiv Basic Assessment Report
routing corridor is in close visual proximity to the N14 National Road, which carries tourist
traffic and should be recognised as a tourist view corridor. This barrier effect is not apparent
for the Preferred Alternative, which would allow for a new power line corridor, running parallel
to the existing Eskom 132kV line, but with a suitable gap and with the routing corridor
location outside of the ZVI of the N14 National Road (hence the Preferred Routing was rated
low). As mitigation would not have a major reduction in the resultant visual impacts,
significance for all the routings was rated the same as without mitigation. Mitigations in
terms of best practice were recommended, to straighten the proposed routing and much as
possible, setting in place a precedent for a future power line corridor running parallel, but
further to the north, of the existing Eskom 132kV power line.
CONCLUSION 7
Cape EAPrac is of the opinion that the information contained in this Draft Basic Assessment
Report and the documentation attached hereto is sufficient to allow the general public and
key stakeholders to apply their minds to the potential negative and positive impacts
associated with the development of the Dyasonsklip 1 & 2 and Sirius Solar PV Project 1 Grid
Connection.
All participating specialists have confirmed that both the preferred alignment as well as the
alternative alignment (including sub-station positions) will result in an overall lower impact
that of the substations and powerlines that are already authorised.
The proposed powerline alignment alternatives were assessed in this environmental process
as corridors (300m wide) to allow for minor adjustments / flexibility during the final design /
micro-siting phase post environmental decision, and to avoid protracted administrative
amendment processes as a result of these potential minor adjustments.
Aside from potential negative impacts, it is submitted that the this proposed Grid Connection
has notable positive impacts, in that it aligns with, and is in furtherance of, international,
national, regional and local strategies to support alternative / renewable energy projects.
These include the distribution of much-needed ‘clean’ electricity into the national grid,
provision of local electrical infrastructure for use in long-term, and the provision of
employment opportunities during the construction and operation phases for members of local
communities.
Sufficient mitigation has been recommended to reduce potential negative impacts to an
acceptable level. It is submitted that the proposed installation of the preferred overhead
powerline alternatives will be sustainable in the long term and the preferred alternative can
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xxv Basic Assessment Report
be considered to be the most feasible / viable option, from environmental and practical
perspectives.
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xxvi Basic Assessment Report
ABBREVIATIONS
AIA Archaeological Impact Assessment
BGIS Biodiversity Geographic Information System
BID Background Information Document
CBD Central Business District
ACMP Archaeological Conservation Management Plan
CDSM Chief Directorate Surveys and Mapping
CEMP Construction Environmental Management Plan
dBA Decibel (measurement of sound)
DEA Department of Environmental Affairs
DEA&DP Department of Environmental Affairs and Development Planning
DEIR Draft Environmental Impact Report
DME Department of Minerals and Energy
DSR Draft Scoping Report
FEIR Final Environmental Impact Report
EAP Environmental Impact Practitioner
EHS Environmental, Health & Safety
EIA Environmental Impact Assessment
EIR Environmental Impact Report
EMP Environmental Management Programme
GPS Global Positioning System
GWh Giga Watt hour
HIA Heritage Impact Assessment
HWC Heritage Western Cape
I&APs Interested and Affected Parties
IDP Integrated Development Plan
IFC International Finance Corporation
IPP Independent Power Producer
KNP Karoo National Park
KOP Key Observation Point
kV Kilo Volt
LAeq,T Time interval to which an equivalent continuous A-weighted sound level
LLRC Low Level River Crossing
LUDS Land Use Decision Support
LUPO Land Use Planning Ordinance
MW Mega Watt
NEMA National Environmental Management Act
NEMAA National Environmental Management Amendment Act
NEMBA National Environmental Management: Biodiversity Act
NERSA National Energy Regulator of South Africa
NHRA National Heritage Resources Act
NID Notice of Intent to Develop
NSBA National Spatial Biodiversity Assessment
NWA National Water Act
PIA Paleontological Impact Assessment
DK1&2 and Sirius Grid Connection SIY231b/04
Cape EAPrac xxvii Basic Assessment Report
PM Post Meridiem; “Afternoon”
SACAA South African Civil Aviation Authority
SAHRA South African National Heritage Resources Agency
SANBI South Africa National Biodiversity Institute
SANS South Africa National Standards
SDF Spatial Development Framework
SMME Small, Medium and Micro Enterprise
SAPD South Africa Police Department
TIA Traffic Impact Assessment
VIA Visual Impact Assessment
DK1&2 and Sirius Grid Connection BASIC ASSESSMENT REPORT SIY231b/04
Cape EAPrac Basic Assessment Report
SECTION 1:
BASIC ASSESSMENT
REPORT
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 1 Basic Assessment Report
(For official use only)
File Reference Number:
Application Number:
Date Received:
Basic assessment report in terms of the Environmental Impact Assessment Regulations, 2014, promulgated in
terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998), as amended.
Kindly note that:
1. This basic assessment report is a standard report that may be required by a competent authority in terms of the EIA Regulations, 2014 and is meant to streamline applications. Please make sure that it is the report used by the particular competent authority for the activity that is being applied for.
2. This report format is current as of 08 December 2014. It is the responsibility of the applicant to ascertain whether subsequent versions of the form have been published or produced by the competent authority
3. The report must be typed within the spaces provided in the form. The size of the spaces provided is not necessarily indicative of the amount of information to be provided. The report is in the form of a table that can extend itself as each space is filled with typing.
4. Where applicable tick the boxes that are applicable in the report.
5. An incomplete report may be returned to the applicant for revision.
6. The use of “not applicable” in the report must be done with circumspection because if it is used in respect of material information that is required by the competent authority for assessing the application, it may result in the rejection of the application as provided for in the regulations.
7. This report must be handed in at offices of the relevant competent authority as determined by each authority.
8. No faxed or e-mailed reports will be accepted.
9. The signature of the EAP on the report must be an original signature.
10. The report must be compiled by an independent environmental assessment practitioner.
11. Unless protected by law, all information in the report will become public information on receipt by the competent authority. Any interested and affected party should be provided with the information contained in this report on request, during any stage of the application process.
12. A competent authority may require that for specified types of activities in defined situations only parts of this report need to be completed.
13. Should a specialist report or report on a specialised process be submitted at any stage for any part of this application, the terms of reference for such report must also be submitted.
14. Two (2) colour hard copies and one (1) electronic copy of the report must be submitted to the competent authority.
15. Shape files (.shp) for maps must be included in the electronic copy of the report submitted to the competent authority.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 2 Basic Assessment Report
SECTION A: ACTIVITY INFORMATION
Has a specialist been consulted to assist with the completion of this section? YES NO
If YES, please complete the form entitled “Details of specialist and declaration of interest” for the specialist
appointed and attach in Appendix I.
PROJECT DESCRIPTION 1
a) Describe the project associated with the listed activities applied for
Three adjacent renewable energy projects situated West of Upington in the Northern Cape have been selected as
preferred bidders by the Department Of Energy, these are:
Dyasonsklip 1 (RE Capital 3 Pty (Ltd))
Dyasonsklip 2 (RE Capital 3B (Pty) Ltd)
Sirius Solar PV Project 1 (Sirius Solar PV Project One (Pty) Ltd)
Each one of these three projects have an authorised on-site substation and an authorised 132 kV powerline from
the on-site substation to the ESKOM Upington MTS substation.
In order to reduce the cumulative impacts of having 3 separate power lines (already authorised) and 3 separate on-
site substations (already authorised) evacuating power to the same ESKOM substation, the proposal is to construct
a single power line to evacuate power from all three power generators.
The proposal is that Dyasonsklip 1 and 2 will share a substation, called Dyasonsklip Substation and evacuate
generated power to Sirius substation by means of a single circuit (SCt) Twin Tern line. From Sirius substation the
power shall be evacuated by means of a SCt Twin Tern line to the new Upington MTS. Eskom planning has opted
for the use of Twin Tern to accommodate future generating plants planned in the area.
From economic and environmental perspectives, replacement of these various transmission lines by a single
alignment, designed to evacuate generated electricity through a single transmission line, would therefore make
sense. The proposal is therefore that Dyasonsklip 1 and 2 will share a substation, called Dyasonsklip Substation
and evacuate generated power to Sirius substation by means of a single circuit (SCt) Twin Tern line. From Sirius
substation the power shall be evacuated by means of a SCt Twin Tern line to the new Upington MTS. Eskom
planning has opted for the use of Twin Tern to accommodate future generating plants planned in the area.
Please refer to the preliminary design reports compiled by Trans Africa Projects, attached in Annexure D5 – D7 for
detailed description of the project components.
Two power line corridor alternatives of approximately 300m wide have been assessed as part of the Basic
Assessment Process.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 3 Basic Assessment Report
b) Provide a detailed description of the listed activities associated with the project as applied for
Listed activity as described in GN 734, 735 and 736 Description of project activity
Example:
GN 734 Item xx xx): The construction of a bridge
where such construction occurs within a
watercourse or within 32 metres of a
watercourse, measured from the edge of a
watercourse, excluding where such construction
will occur behind the development setback line.
A bridge measuring 5 m in height and 10m in
length, no wider than 8 meters will be built over
the Orange river
GN983 Item 11(i): The development of facilities or
infrastructure for the transmission and distribution of
electricity (i) outside urban areas or industrial
complexes with a capacity of more than 33 but less
than 275 kilovolts.
Construction of a 132Kv powerline and two on site
substations to connect three renewable energy
generation facilities (PV) to the National Grid.
These facilities include:
- Dyasonsklip 1 (RE Capital 3)
- Dyasonsklip 2 (RE Capital 3b); and
- Sirius Solar PV Project 1
FEASIBLE AND REASONABLE ALTERNATIVES 2
“alternatives”, in relation to a proposed activity, means different means of meeting the general purpose and requirements
of the activity, which may include alternatives to—
(a) the property on which or location where it is proposed to undertake the activity;
(b) the type of activity to be undertaken;
(c) the design or layout of the activity;
(d) the technology to be used in the activity;
(e) the operational aspects of the activity; and
(f) the option of not implementing the activity.
Describe alternatives that are considered in this application as required by Appendix 1 (3)(h), Regulation 2014. Alternatives
should include a consideration of all possible means by which the purpose and need of the proposed activity
(NOT PROJECT) could be accomplished in the specific instance taking account of the interest of the applicant in the activity.
The no-go alternative must in all cases be included in the assessment phase as the baseline against which the impacts of
the other alternatives are assessed.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 4 Basic Assessment Report
The determination of whether site or activity (including different processes, etc.) or both is appropriate needs to be informed
by the specific circumstances of the activity and its environment. After receipt of this report the, competent authority may
also request the applicant to assess additional alternatives that could possibly accomplish the purpose and need of the
proposed activity if it is clear that realistic alternatives have not been considered to a reasonable extent.
The identification of alternatives should be in line with the Integrated Environmental Assessment Guideline Series 11,
published by the DEA in 2004. Should the alternatives include different locations and lay-outs, the co-ordinates of the
different alternatives must be provided. The co-ordinates should be in degrees, minutes and seconds. The projection that
must be used in all cases is the WGS84 spheroid in a national or local projection.
a) Site alternatives
Alternative 1 (preferred alternative)
Description Lat
(DDMMSS)
Long
(DDMMSS)
Two powerline routes have been proposed for the line connections
between the three substations. The figure below shows the
preferred route (line in green, corridor in maroon).
The route follow Dyasonsklip 1 and 2 and Sirius 2 solar farm
boundaries, crossing over a dirt access road, to connect to Sirius
substation. From Sirius substation it follows a straight trajectory
towards McTaggerts 132kV Line where it makes an underpass
crossing. The line then bends in a south-east direction towards the
existing Oranje-Oasis 132kV wood pole line where it crosses over
at approximately midspan and heads towards its final bend before
termination at the new Upington MTS.
Linear
Activity –
see below
Linear
Activity –
see below
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 5 Basic Assessment Report
Alternative 2
Description Lat
(DDMMSS)
Long
(DDMMSS)
The second route option Alternative, (line marked in yellow, corridor
in green) is depicted in the image below
This alternative also follows the solar farm boundaries of
Dyasonsklip 1 and 2 and bends toward the existing Oranje-Oasis
132kV line where is runs parallel until turning into Sirius 1
substation. The line exists Sirius 1 substation in a southernly
direction towards the existing wood pole line, where it crosses over
at approximately midspan and bends to again follow parallel to the
existing 132kV line. The last two bends allows it to turn and
terminate at the new Upington MTS.
Linear
Activity –
see below
Linear
Activity –
see below
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 6 Basic Assessment Report
Alternative 3
Description Lat
(DDMMSS)
Long
(DDMMSS)
In the case of linear activities:
Alternative: Latitude (S): Longitude (E):
Alternative S1 (preferred)
Starting point of the activity 28°34’34” 21°03’45”
Middle/Additional point of the activity 28°33’29” 21°06’03”
End point of the activity 28°32’44” 21°08’06”
Alternative S2 (if any)
Starting point of the activity 28°34’34” 21°03’45”
Middle/Additional point of the activity 28°33’57” 21°06’41”
End point of the activity 28°32’44” 21°08’06”
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 7 Basic Assessment Report
Alternative S3 (if any)
Starting point of the activity
Middle/Additional point of the activity
End point of the activity
For route alternatives that are longer than 500m, please provide an addendum with co-ordinates taken every 250 meters
along the route for each alternative alignment.
In the case of an area being under application, please provide the co-ordinates of the corners of the site as indicated on the
lay-out map provided in Appendix A of this form.
b) Lay-out alternatives
The different alignments and as discussed above could be considered as both site and layout alternatives. For the
purpose of this basis Assessment Report, they have been discussed and considered as Site Alternatives, rather
than layout alternatives.
Alternative 1 (preferred alternative)
Description Lat (DDMMSS) Long (DDMMSS)
Alternative 2
Description Lat (DDMMSS) Long (DDMMSS)
Alternative 3
Description Lat (DDMMSS) Long (DDMMSS)
c) Technology alternatives
Alternative 1 (preferred alternative)
Conductor: Twin Tern Conductors (ungreased)
Shield wire: OPGW with 2 X 48-cores rated for 20kA at 0.5 second fault withstand (or equivalent). (Total rating
40kA)
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 8 Basic Assessment Report
Insulators: Insulator type to be used on this line shall be as per IEC 60815 specifications. Composite long rod
insulators for 132kV applications shall be used. The creepage shall be 20mm/kV as specified for inland regions.
Earthing: Footing resistance values shall be adopted from the Eskom Distribution (DX) Earthing standard
(SCSASABF9 - line earthing) where earthing is necessary. For 132kV lines the maximum acceptable footing
resistance is 20Ù. These values shall be measured during construction and additional earthing installed if
required.
Corona & Audible Noise: The selected conductor, Tern, satisfies Eskom’s requirements in terms of corona and
noise parameters with sufficient margin of safety.
Hardware: Standard hardware components have been used.
Towers : Self-supporting monopoles and guyed monopoles.
Foundations: Standard pad and plinth foundations for the self-supporting towers. Dead-man anchor/stay plate
anchor foundations for stays and a central plinth for tower mast will be used for the guyed monopoles.
Corrosion protection: Standard galvanizing as per SANS 121 and ISO 9223 for C2 corrosion categories.
Length: Dyasonsklip - Sirius 132kV line is approximately 6km and Sirius - new Upington MTS is approximately
3km.
Line Profile: Lines templated at 70°C maximum operating temperature.
Furthermore the project will entail the construction of 2 on site-substations:
- Dyasonsklip Sub Station
- Sirius Substation
Alternative 2
No additional technology alternatives are under investigation as part of this environmental
process.
Alternative 3
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 9 Basic Assessment Report
d) Other alternatives (e.g. scheduling, demand, input, scale and design alternatives)
Alternative 1 (preferred alternative)
Alternative 2
Alternative 3
e) No-go alternative
The no go alternative is the option of not commencing with the activity, which in this case is
deemed to be continuation with three separate powerline and three separate on site sub
stations as already authorised by the respective project EA’s. Implementation of the no go
alternative in this case is not preferred, as the reduced impacts associated with the
construction of a single power line (as opposed to three separate power lines) will not be
realised.
Paragraphs 3 – 13 below should be completed for each alternative.
PHYSICAL SIZE OF THE ACTIVITY 3
a) Indicate the physical size of the preferred activity/technology as well as alternative activities/technologies
(footprints):
Alternative: Size of the activity:
Alternative A11 (preferred activity alternative) m2
Alternative A2 (if any) m2
Alternative A3 (if any) m2
1 “Alternative A..” refer to activity, process, technology or other alternatives.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 10 Basic Assessment Report
or, for linear activities:
Alternative: Length of the activity:
Alternative A1 (preferred activity alternative) Approx 8880 m
Alternative A2 (if any) Approx 11740 m
Alternative A3 (if any) m
b) Indicate the size of the alternative sites or servitudes (within which the above footprints will occur):
Alternative: Size of the site/servitude:
Alternative A1 (preferred activity alternative) m2
Alternative A2 (if any) m2
Alternative A3 (if any) m2
SITE ACCESS 4
Does ready access to the site exist? YES NO
If NO, what is the distance over which a new access road will be built m
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 11 Basic Assessment Report
Describe the type of access road planned:
There are numerous existing roads in close vicinity that will be used to access the power line corridor for construction. These are indicated in the figure below:
Apart from these existing roads, all three of the solar facilities have authorised access roads (authorised as part of their respective EIA’s) that can also be used to access the site. Formal roads will not be constructed underneath the powerlines for maintenance purposes. Access for maintenance purposes will be limited to jeep tracks.
Include the position of the access road on the site plan and required map, as well as an indication of the road in relation to the site.
LOCALITY MAP 5
An A3 locality map must be attached to the back of this document, as Appendix A. The scale of the locality map must be relevant to the size of the development (at least 1:50 000. For linear activities of more than 25 kilometres, a smaller scale e.g. 1:250 000 can be used. The scale must be indicated on the map.). The map must indicate the following:
an accurate indication of the project site position as well as the positions of the alternative sites, if any;
indication of all the alternatives identified;
closest town(s;)
road access from all major roads in the area;
road names or numbers of all major roads as well as the roads that provide access to the site(s);
all roads within a 1km radius of the site or alternative sites; and
a north arrow;
a legend; and
locality GPS co-ordinates (Indicate the position of the activity using the latitude and longitude of the centre point of the site for each alternative site. The co-ordinates should be in degrees and decimal minutes. The minutes should have at least three decimals to ensure adequate accuracy. The projection that must be used in all cases is the WGS84 spheroid in a national or local projection).
A locality map complying to the above criteria is attached in Appendix A1.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 12 Basic Assessment Report
LAYOUT/ROUTE PLAN 6
A detailed site or route plan(s) must be prepared for each alternative site or alternative activity. It must be attached as Appendix A to
this document.
The site or route plans must indicate the following:
the property boundaries and numbers of all the properties within 50 metres of the site;
the current land use as well as the land use zoning of the site;
the current land use as well as the land use zoning each of the properties adjoining the site or sites;
the exact position of each listed activity applied for (including alternatives);
servitude(s) indicating the purpose of the servitude;
a legend; and
a north arrow.
The Route Plans for the proposed powerline (both preferred and alternative layouts) are attached in Appendix A1 and Appendix C. Detailed design reports are also included in Appendices D5, D6 and D7
SENSITIVITY MAP 7
The layout/route plan as indicated above must be overlain with a sensitivity map that indicates all the sensitive areas associated
with the site, including, but not limited to:
watercourses;
the 1:100 year flood line (where available or where it is required by DWS);
ridges;
cultural and historical features;
areas with indigenous vegetation (even if it is degraded or infested with alien species); and
critical biodiversity areas.
The sensitivity map must also cover areas within 100m of the site and must be attached in Appendix A.
All Biodiversity maps are attached in Appendix A2 to this report. Please also refer to the discipline
specific sensitivity mapping included in the respective specialist reports contained in Appendix D1
– D7.
SITE PHOTOGRAPHS 8
Colour photographs from the centre of the site must be taken in at least the eight major compass directions with a
description of each photograph. Photographs must be attached under Appendix B to this report. It must be supplemented
with additional photographs of relevant features on the site, if applicable.
The required photographic plates are attached in Appendix B.
FACILITY ILLUSTRATION 9
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 13 Basic Assessment Report
A detailed illustration of the activity must be provided at a scale of at least 1:200 as Appendix C for activities that include structures. The illustrations must be to scale and must represent a realistic image of the planned activity. The illustration must give a representative view of the activity.
These are included in Appendix C as well as in the preliminary design reports attached in Appendix D5 – D7.
ACTIVITY MOTIVATION 10
Motivate and explain the need and desirability of the activity (including demand for the activity):
1. Is the activity permitted in terms of the property’s existing land use rights? YES NO Please explain
The Applicant have engaged with landowners of the farms to be traversed by the preferred powerline alignment, as well as the alternative route considered. The applicant is engaging directly with landowners regarding the option agreements and servitudes.
2. Will the activity be in line with the following?
(a) Provincial Spatial Development Framework (PSDF) YES NO Please explain
In terms of Electricity infrastructure related to forms of renewable energy, the spatial distribution of supply should aim be follow clearly defined corridors, with electricity services being highly concentrated close to the major routes and high capacity electricity infrastructure (PSDF, 2011). This project aims to link to existing and approved electrical infrastructure associated with renewable energy projects (Solar PV Developments) and the Eskom national grid network (via the Upington MTS substation).
This grid connection is associated with three renewable energy projects that are all preferred bidders in term of the Department of Energy REIPPP.
One of the sustainable development objectives of the PSDF is to utilize renewable resources as opposed to non-renewable resources. This grid connection is associated with the generation of electricity from a renewable resource. It also promotes the concept of Bioregionalism as enshrined in the PSDF.
(b) Urban edge / Edge of Built environment for the area YES NO Please explain
The nature of Power lines dictates that they need not be situated within an urban edge or within the edge of built up areas.
(c) Integrated Development Plan (IDP) and Spatial Development Framework (SDF) of the Local Municipality (e.g. would the approval of this application compromise the integrity of the existing approved and credible municipal IDP and SDF?).
YES NO Please explain
The IDP defines public infrastructure development such as energy generation as a critical action within the municipal area
(d) Approved Structure Plan of the Municipality YES NO Please explain
To the best of our knowledge, there is no specific structure plan adopted for the Khai Garib local municipality. The project is however compliant with other relevant planning policies.
(e) An Environmental Management Framework (EMF) adopted by the Department (e.g. Would the approval of this application compromise the integrity of the existing environmental management priorities for the area and if so, can it be justified in terms of sustainability considerations?)
YES NO Please explain
There are no specific Environmental Management Frameworks for the Khai Garib Municipal area.
(f) Any other Plans (e.g. Guide Plan) YES NO Please explain
To the best of our knowledge, there is no specific guide plan adopted for the Khai Garib local municipality. The project is however compliant with other relevant planning policies.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 14 Basic Assessment Report
3. Is the land use (associated with the activity being applied for) considered within the timeframe intended by the existing approved SDF agreed to by the relevant environmental authority (i.e. is the proposed development in line with the projects and programmes identified as priorities within the credible IDP)?
YES NO Please explain
The spatial development framework defines the renewable energy sector as a focus area for this municipal district.
4. Does the community/area need the activity and the associated land use concerned (is it a societal priority)? (This refers to the strategic as well as local level (e.g. development is a national priority, but within a specific local context it could be inappropriate.)
YES NO Please explain
This grid connection is related to three renewable energy projects that have been selected as preferred bidders under the Department of Energy’s Renewable Energy Independent Power Producers procurement programme.
The preliminary results of the Strategic Environmental Assessment for introducing renewable energy in South Africa, have identified this specific area as a renewable energy development zone.
Given the context of PV farm developments in the local context, this proposed powerline can be considered to be in-line / associated with the local investment already placed in this emerging renewable energy landscape. Care has been taken to avoid impacting on the agricultural land-use in the area, as well as the scenic / cultural landscape, by aligning the preferred powerline route along existing lines and breaks i.e. existing tracks, fences and fire-breaks etc.
On a strategic level, the proposed powerline aligns with the regional, national and international need for the distribution of ‘green electricity’ from renewable energy.
5. Are the necessary services with adequate capacity currently available (at the time of application), or must additional capacity be created to cater for the development? (Confirmation by the relevant Municipality in this regard must be attached to the final Basic Assessment Report as Appendix I.)
YES NO Please explain
The activity itself is a service that has been specifically designed for its purpose. It does
not require the availability of any ancillary services.
6. Is this development provided for in the infrastructure planning of the municipality, and if not what will the implication be on the infrastructure planning of the municipality (priority and placement of services and opportunity costs)? (Comment by the relevant Municipality in this regard must be attached to the final Basic Assessment Report as Appendix I.)
YES NO Please explain
The development does not require municipal service provision.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 15 Basic Assessment Report
7. Is this project part of a national programme to address an issue of national concern or importance?
YES NO Please explain
The generation of ‘green / clean electricity’ from a renewable energy resource (Solar)
forms part of a national programme to reduce reliance of coal-powered generation of
electricity. The proposed powerline will serve to transmit / distribute the electricity to be
generated by three renewable energy development into the national Eskom grid.
Securing renewable energy sources into the overall energy matrix has been highlighted as
a priority by the Department of Energy. The Renewable Energy Independent Power
Producers Procurement Programme was established as a result of this (The three solar
projects are preferred bidders under this programme).
This project is furthermore deemed to constitute a Strategic Infrastructure Project and
confirmation of this status has been sought from the relevant SIP coordinators.
8. Do location factors favour this land use (associated with the activity applied for) at this place? (This relates to the contextualisation of the proposed land use on this site within its broader context.)
YES NO Please explain
This powerline connects 3 renewable energy preferred bidders to the National Grid. These
projects will be generating 225MW of electricity for inclusion into the National Grid.
The proposed powerline will align as far as possible along landscape divides (i.e. farm
roads/tracks, fence lines, fire breaks) so as to avoid impacting of the agricultural landuse
and ecological sensitive areas. In addition, the pylons/towers will not be located on
prominent landscape or sensitive features, and would become a smaller component of the
greater Solar Energy Facility landscape emerging in the area.
9. Is the development the best practicable environmental option for this land/site? YES NO Please explain
This proposed powerline provides a far more environmentally sustainable option to having
three separate powerlines as already authorised. This powerline reduces cumulative
impact of facilities already authorised, by combining infrastructure across multiple projects.
10. Will the benefits of the proposed land use/development outweigh the negative impacts of it?
YES NO Please explain
The potential negative impacts associated with the preferred powerline corridor alignment
were found to be medium to low (with mitigation), and thus acceptable, given the context.
Aside from the employments benefits associated with the construction and operation /
maintenance of the powerline, the benefit of allowing the input of ‘clean electricity’ into the
national grid is considerable.
It must be further noted that the impacts of this powerline area also significantly lower than
those impacts associated with the no-go alternative. i.e. building three separate
powerlines, as has been authorised.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 16 Basic Assessment Report
11. Will the proposed land use/development set a precedent for similar activities in the area (local municipality)?
YES NO Please explain
Several solar facilities (including PV and CSP facilities) have been approved for
development in this area, which will all require connection to the national grid, via overhead
powerlines. This proposal reduces negative precident, by combining multiple into a single
powerline.
Considering the manner in which the powerline has been designed to avoid impacting on
the landuse and sensitive features (environmental and heritage/cultural) in the landscape,
as well as combining projects to reduce cumulative impact, it can be argued that it will set
a positive precedent for any future powerlines in the area.
12. Will any person’s rights be negatively affected by the proposed activity/ies? YES NO Please explain
As mentioned above, the preferred powerline alternative has been aligned / designed to
have the least possible impact on existing landuse as it has been aligned along boundaries
and existing tracks as far as possible.
Furthermore, a detailed public participation process took place as part of the previous 3
EIA’s (for the facilities and powerlies). No major concerns nor objections were raised in
these three separate environmental processes.
13. Will the proposed activity/ies compromise the “urban edge” as defined by the local municipality?
YES NO Please explain
Although falling outside of the developed areas of Upington and Keimoes, as a linear
activity, the proposed powerline will not compromise the urban edges of the Khai Garib
Municipality.
14. Will the proposed activity/ies contribute to any of the 17 Strategic Integrated Projects (SIPS)?
YES NO Please explain
SIP 8: Support sustainable green energy initiatives on a national scale through a
diverse range of clean energy options as envisaged in the IPR2010
The distribution of electricity generated from renewable resource (solar) by the three
preferred bidders that will connect to the national grid via this powerline.
SIP 9: Electricity Generation to support socio-economic development
The distribution of electricity generated from renewable resource (Solar) by the by the
three preferred bidders that will connect to the national grid via this powerline.
SIP 10: Electricity Transmission and Distribution for all.
As the proposed powerline is associated with renewable energy projects (preferred
bidders) under the Independent Power Producer (IPP) Procurement Programme, it can be
considered as a Strategically Important Development ("SID"), due to their potentially
significant contribution to the regional and national economy.
Confirmation in this regard has been sought from the relevant SIP co-ordinators.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 17 Basic Assessment Report
15. What will the benefits be to society in general and to the local communities? Please explain
Addition of much needed electricity into the national grid.
This powerline will distribute 225mw of “clean-electricity” generated by the three Solar
Developments from a renewable resource (solar) into the national electrical grid, which is
currently under enormous pressure. The national grid currently relies heavily of coal for
electricity generation, has associated pollution and climate-change repercussions, thus this
project indirectly contributes to minimising these impacts through its associated with
renewable energy generation.
16. Any other need and desirability considerations related to the proposed activity? Please explain
The studies undertaken as part of this environmental process, as well as those associated
with the solar farms in the area, contribute to a greater understanding of the landscape and
context and the sensitive elements within it (e.g. remnant natural vegetation and
watercourses, cultural heritage areas, archaeological and palaeontological resources,
avifaunal species and populations etc.), as well as the protection and rehabilitation of these
elements (e.g. implementation of buffers, removal and monitoring of alien vegetation etc.).
17. How does the project fit into the National Development Plan for 2030? Please explain
Contribution to the provision of electricity to the nation, and investment in electrical
infrastructure for its distribution (as part of the strategy to remedy the electricity crisis of
2008 and that associated with the future demands).
This powerline aligns with the one of the prioritised infrastructure investments listed in the
NDP: “Procuring at least 20 000MW of renewable electricity by 2030, importing electricity
from the region, decommissioning 11 000MW of ageing coal-fired power stations and
stepping up investments in energy-efficiency”, as well as one the key proposals to
“Implement the 2010 Integrated Resource Plan (procuring at least 20 000MW of electricity
from renewables) to reduce carbon emissions from the electricity industry from 0.9kg per
kilowatt-hour to 0.6kg per kilowatt-hour.
18. Please describe how the general objectives of Integrated Environmental Management as set out in section 23 of NEMA have been taken into account.
The investigation, assessment and communication of potential impacts of this proposal on
the receiving environment have considered alternatives (the no-go) and cumulative
impacts, and recommended mitigation and monitoring measures to ensure that potential
negative impacts are kept to a minimum and potential positive impacts are enhanced.
Among these is the recommendation for on-going monitoring of the access tracks to avoid
erosion and removal alien plants. This proposal reduces the cumulative impact of multiple
projects utilising a single grid connection option.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 18 Basic Assessment Report
19. Please describe how the principles of environmental management as set out in section 2 of NEMA have been taken into account.
It is argued that the proposed development of this integrated grid solution will be socially,
environmentally and economically sustainable, due to the following:
Further disturbance to the local ecosystems / loss of biodiversity is likely to be negligible
as the powerline, and associated access tracks and switching stations, will be positioned
along / on existing transformed / disturbed areas in the landscape i.e. the powerline and
access tracks will align as far as possible along cadastral lines, existing farm tracks, fence
lines and fire breaks, while the switching stations will be placed on disturbed areas
associated with the Substations of Solar developments in the area.
Mitigation and monitoring measures have been recommended to minimise and avoid
potential degradation of the environment, as well as rehabilitate the current disturbed
context where possible.
APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES 11
List all legislation, policies and/or guidelines of any sphere of government that are applicable to the application as
contemplated in the EIA regulations, if applicable:
Title of legislation, policy or
guideline
Applicability to the project Administering authority Date
National Environmental Management Act.
Basic Assessment Department of Environmental Affairs
Act 107 of 1998 as amended
National Environmental Management: Biodiversity Act.
Endangered / Vulnerable vegetation types and Protected Species (TOPS)
DENC Act 10 of 2004
National Spatial Biodiversity Assessment
Critical Biodiversity Areas & Ecological Support Areas across alignment
DENC
2011
Conservation of Agricultural Resources Act
Agricultural land traversed by powerline.
Alien vegetation in and surrounding site
Department of Agriculture, Forestry & Fisheries
Act 43 of 1983
National Veld and Forest Fire Act
Alien infested Thicket and Fynbos in relation to fire risk.
Department of Agriculture, Forestry & Fisheries
Act 101 of 1998
Nature & Environment Conservation Ordinance
Lists Endangered & Protected animals & plants (species) in Schedules 1-4.
DENC Ordinance 19 of 1974
National Heritage Activity on site greater than SAHRA Act 25 of
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 19 Basic Assessment Report
Resources Act 5000m² in extent.
1999
WASTE, EFFLUENT, EMISSION AND NOISE MANAGEMENT 12
a) Solid waste management
Will the activity produce solid construction waste during the construction/initiation phase? YES NO
If YES, what estimated quantity will be produced per month? 5m3
How will the construction solid waste be disposed of (describe)?
Construction waste will be stored in a skip on site and periodically removed to a licenced
landfill by a service provider. Confirmation of the capacity of the municipality to handle this
construction waste was obtained as part of the three previous environmental processes.
Where will the construction solid waste be disposed of (describe)?
Construction waste will be stored in a skip on site and periodically removed to a licenced
landfill by a service provider. Confirmation of the capacity of the municipality to handle this
construction waste was obtained as part of the three previous environmental processes.
The Khai Garib municipality has confirmed this to be in order as long as no Medical Waste
or industrial Effluent is dumped.
Will the activity produce solid waste during its operational phase? YES NO
If YES, what estimated quantity will be produced per month? 0m3
How will the solid waste be disposed of (describe)?
No Solid Waste will be generated during the operational phase of this proposal.
If the solid waste will be disposed of into a municipal waste stream, indicate which registered landfill site will be used.
No Solid Waste will be generated during the operational phase of this proposal.
Where will the solid waste be disposed of if it does not feed into a municipal waste stream (describe)?
No Solid Waste will be generated during the operational phase of this proposal.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 20 Basic Assessment Report
If the solid waste (construction or operational phases) will not be disposed of in a registered landfill site or be taken up in a
municipal waste stream, then the applicant should consult with the competent authority to determine whether it is necessary
to change to an application for scoping and EIA.
Can any part of the solid waste be classified as hazardous in terms of the NEM:WA? YES NO
If YES, inform the competent authority and request a change to an application for scoping and EIA. An application for a
waste permit in terms of the NEM:WA must also be submitted with this application.
Is the activity that is being applied for a solid waste handling or treatment facility? YES NO
If YES, then the applicant should consult with the competent authority to determine whether it is necessary to change to an
application for scoping and EIA. An application for a waste permit in terms of the NEM:WA must also be submitted with this
application.
b) Liquid effluent
Will the activity produce effluent, other than normal sewage, that will be disposed of in a municipal
sewage system? YES NO
If YES, what estimated quantity will be produced per month? 0m3
Will the activity produce any effluent that will be treated and/or disposed of on site? YES NO
If YES, the applicant should consult with the competent authority to determine whether it is necessary to change to an
application for scoping and EIA.
Will the activity produce effluent that will be treated and/or disposed of at another facility? YES NO
If YES, provide the particulars of the facility:
Facility name:
Contact person:
Postal address:
Postal code:
Telephone: Cell:
E-mail: Fax:
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 21 Basic Assessment Report
Describe the measures that will be taken to ensure the optimal reuse or recycling of waste water, if any:
Wastewater will not be generated during the construction nor operation phases of this
activity.
c) Emissions into the atmosphere
Will the activity release emissions into the atmosphere other that exhaust emissions and dust
associated with construction phase activities?
YES NO
If YES, is it controlled by any legislation of any sphere of government? YES NO
If YES, the applicant must consult with the competent authority to determine whether it is necessary to change to an
application for scoping and EIA.
If NO, describe the emissions in terms of type and concentration:
Atmospheric Emissions will not be generated during the construction nor operation phases
of this activity.
d) Waste permit
Will any aspect of the activity produce waste that will require a waste permit in terms of the NEM:WA? YES NO
If YES, please submit evidence that an application for a waste permit has been submitted to the competent authority
e) Generation of noise
Will the activity generate noise? YES NO
If YES, is it controlled by any legislation of any sphere of government? YES NO
Describe the noise in terms of type and level:
The activity will not generate any noise during the operational phases. Limited noise
associated with construction vehicles is expected during the construction phase. This will
be of a low – very low significance.
WATER USE 13
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 22 Basic Assessment Report
Please indicate the source(s) of water that will be used for the activity by ticking the appropriate box(es):
Municipal Water board Groundwater River, stream,
dam or lake Other
The activity
will not use
water
If water is to be extracted from groundwater, river, stream, dam, lake or any other natural feature,
please indicate the volume that will be extracted per month: 0 litres
Does the activity require a water use authorisation (general authorisation or water use license) from
the Department of Water Affairs? YES NO
If YES, please provide proof that the application has been submitted to the Department of Water Affairs.
It is unlikely that a Water Use Licence is required for this powerline, as all infrastructure is
to be situated outside of the watercourses (A general authorisation, may however be
relevant in this regard). Notwithstanding, SRK consulting has been appointed to compile
the Water Use Licence Application (WULA) for the PV Facilities and this will include
engagement with the Department of Water and Sanitation (DWS) regarding this powerline.
The DWS has also been given an opportunity to comment on this Basic Assessment
Process.
ENERGY EFFICIENCY 14
Describe the design measures, if any, which have been taken to ensure that the activity is energy efficient:
The activity is for the transmission of electricity generated from a renewable resource (PV)
and this will be done to Eskom Standards.
Describe how alternative energy sources have been taken into account or been built into the design of the activity, if any:
None – this activity is for the transmission of electricity generated from a renewable
resource (PV).
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 23 Basic Assessment Report
SECTION B: SITE/AREA/PROPERTY DESCRIPTION
Important notes:
1. For linear activities (pipelines, etc) as well as activities that cover very large sites, it may be necessary to complete this section for each part of the site that has a significantly different environment. In such cases please complete copies of Section B and indicate the area, which is covered by each copy No. on the Site Plan.
It is not deemed necessary to complete this section for different sections of the powerline, as the powerline is
only approximately 8.8km long and the landscape character and vegetation component remain consistent.
Section B Copy No. (e.g. A):
2. Paragraphs 1 - 6 below must be completed for each alternative.
3. Has a specialist been consulted to assist with the completion of this section? YES NO
If YES, please complete the form entitled “Details of specialist and declaration of interest” for each specialist thus appointed
and attach it in Appendix I. All specialist reports must be contained in Appendix D.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 24 Basic Assessment Report
Property
description/physica
l address:
Province Northern Cape Province
District Municipality ZF Mcgawu
Local Municipality Khai Garib
Ward Number(s) 7
Farm name and
number
Farm 454 Dyason’s Klip, Farm 638, & Agricultural
Holding 1080.
Portion number Farm 454 Dyason’s Klip, Farm 638, & Agricultural
Holding 1080.
SG Code Remainder of Dyasonsklip 454
C02800000000045400000
Remainder of Farm 638
C02800000000063800000
Agricultural Holding 1080
NO SG Number Available
Where a large number of properties are involved (e.g. linear activities), please attach a full list to
this application including the same information as indicated above.
Current land-use zoning as
per local municipality
IDP/records:
The properties are currently zoned for agricultural use. Power
distribution lines are consistent with this use. The applicant is
however in the process of registering a long term lease over
portions of the properties for the purpose of operating the PV
facilities.
In instances where there is more than one current land-use zoning, please attach a list of
current land use zonings that also indicate which portions each use pertains to, to this
application.
Is a change of land-use or a consent use application required? YES NO
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 25 Basic Assessment Report
GRADIENT OF THE SITE 1
Indicate the general gradient of the site. Alternative S1:
Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than
1:5
Alternative S2 (if any):
Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than
1:5
Alternative S3 (if any):
Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than
1:5
LOCATION IN LANDSCAPE 2
Indicate the landform(s) that best describes the site:
2.1 Ridgeline 2.4 Closed valley 2.7 Undulating plain / low hills
2.2 Plateau 2.5 Open valley 2.8 Dune
2.3 Side slope of hill/mountain 2.6 Plain 2.9 Seafront
2.10 At sea
GROUNDWATER, SOIL AND GEOLOGICAL STABILITY OF THE 3SITE
Is the site(s) located on any of the following?
Alternative S1: Alternative S2 (if
any):
Alternative S3 (if
any):
Shallow water table (less than 1.5m deep) YES NO YES NO YES NO
Dolomite, sinkhole or doline areas YES NO YES NO YES NO
Seasonally wet soils (often close to water bodies) YES NO YES NO YES NO
Unstable rocky slopes or steep slopes with loose soil YES NO YES NO YES NO
Dispersive soils (soils that dissolve in water) YES NO YES NO YES NO
Soils with high clay content (clay fraction more than
40%) YES NO
YES NO
YES NO
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 26 Basic Assessment Report
Any other unstable soil or geological feature YES NO YES NO YES NO
An area sensitive to erosion YES NO YES NO YES NO
If you are unsure about any of the above or if you are concerned that any of the above aspects may be an issue of concern in the application, an appropriate specialist should be appointed to assist in the completion of this section. Information in respect of the above will often be available as part of the project information or at the planning sections of local authorities. Where it exists, the 1:50 000 scale Regional Geotechnical Maps prepared by the Council for Geo Science may also be consulted.
An agricultural specialist has been appointed to provide input into this environmental process. Please refer to appendix D2 for a copy of this report.
GROUNDCOVER 4
Indicate the types of groundcover present on the site. The location of all identified rare or endangered species or other elements should be accurately indicated on the site plan(s).
Natural veld -
good
conditionE
Natural veld with
scattered aliensE
Natural veld with
heavy alien
infestationE
Veld dominated by
alien speciesE Gardens
Sport field Cultivated land Paved surface Building or
other structure Bare soil
If any of the boxes marked with an “E “is ticked, please consult an appropriate specialist to assist in the completion of this section if the environmental assessment practitioner doesn’t have the necessary expertise.
A botanical specialist has provided input into this Environmental Process. Please refer to appendix D1 for a copy of this report.
SURFACE WATER 5
Indicate the surface water present on and or adjacent to the site and alternative sites?
Perennial River YES NO UNSURE
Non-Perennial River YES NO UNSURE
Permanent Wetland YES NO UNSURE
Seasonal Wetland YES NO UNSURE
Artificial Wetland YES NO UNSURE
Estuarine / Lagoonal wetland YES NO UNSURE
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 27 Basic Assessment Report
If any of the boxes marked YES or UNSURE is ticked, please provide a description of the relevant watercourse.
The powerlines will cross two non-perennial rivers. The pylon infrastructure will however be situated outside of these watercourses as per the recommendation by the ecological specialist.
LAND USE CHARACTER OF SURROUNDING AREA 6
Indicate land uses and/or prominent features that currently occur within a 500m radius of the site and give description of how this influences the application or may be impacted upon by the application:
Natural area Dam or reservoir Polo fields
Low density residential Hospital/medical centre Filling station H
Medium density residential School Landfill or waste treatment site
High density residential Tertiary education facility Plantation
Informal residentialA Church Agriculture Retail commercial & warehousing Old age home River, stream or wetland Light industrial Sewage treatment plantA Nature conservation area
Medium industrial AN Train station or shunting yard N Mountain, koppie or ridge
Heavy industrial AN Railway line N Museum
Power station Major road (4 lanes or more) N Historical building
Office/consulting room Airport N Protected Area
Military or police base/station/compound Harbour Graveyard
Spoil heap or slimes damA Sport facilities Archaeological site
Quarry, sand or borrow pit Golf course Other land uses (describe)
If any of the boxes marked with an “N “are ticked, how will this impact / be impacted upon by the proposed activity? Specify and explain:
None of the specific features highlighted in this table will be impacted upon by the
powerline
If any of the boxes marked with an "An" are ticked, how will this impact / be impacted upon by the proposed activity? Specify and explain:
None of the specific features highlighted in this table will have an impact on the powerline
If any of the boxes marked with an "H" are ticked, how will this impact / be impacted upon by the proposed activity? Specify and explain:
None of the specific features highlighted in this table will have an impact on the powerline
Does the proposed site (including any alternative sites) fall within any of the following:
Critical Biodiversity Area (as per provincial conservation plan) YES NO Core area of a protected area? YES NO Buffer area of a protected area? YES NO Planned expansion area of an existing protected area? YES NO Existing offset area associated with a previous Environmental Authorisation? YES NO Buffer area of the SKA? YES NO
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 28 Basic Assessment Report
If the answer to any of these questions was YES, a map indicating the affected area must be included in Appendix A.
CULTURAL/HISTORICAL FEATURES 7
Are there any signs of culturally or historically significant elements, as defined in section 2 of the National Heritage Resources Act, 1999, (Act No. 25 of 1999), including Archaeological or paleontological sites, on or close (within 20m) to the site? If YES, explain:
YES NO
Uncertain
Not Applicable If uncertain, conduct a specialist investigation by a recognised specialist in the field (archaeology or palaeontology) to establish whether there is such a feature(s) present on or close to the site. Briefly explain the findings of the specialist:
A Heritage specialist has been appointed to provide input into this Environmental Process. Please refer to Appendix D4 for a copy of this report.
Will any building or structure older than 60 years be affected in any way? YES NO Is it necessary to apply for a permit in terms of the National Heritage Resources Act, 1999 (Act 25 of 1999)?
YES NO
If YES, please provide proof that this permit application has been submitted to SAHRA or the relevant provincial authority.
The South African Heritage Resources Authority has already authorised the three separate power lines as part of the three PV Facilities. No further approvals are needed in this regard.
SOCIO-ECONOMIC CHARACTER 8
a) Local Municipality
Please provide details on the socio-economic character of the local municipality in which the proposed site(s) are situated. Level of unemployment:
According to the Khai Garib IDP, The current official unemployment rate in Kai !Garib population is 10.0 % (In comparison to 16.1 % in 2011)
Economic profile of local municipality:
The Orange River played an enormous role in the formation of the municipal area and most of the towns and settlements are to be found close to or adjacent thereto. The economy is heavily depended on the Agricultural Sector, both intensive and extensive. However the major roads (N14, R27 and R359) assist in the growth the municipal area experience. It is important to note that new opportunities have opened up for Kai !Garib municipal area since the need to facilitate the generation of sustainable energy was introduced in South Africa by Eskom and the South African government. According to SDF, Kai!Garib Municipality immediately became a hotspot for Solar Energy developments and numerous developments are currently in process and the resulting economic spin-offs are eagerly anticipated.
Level of education:
No Schooling – 9.0 % (14.7 % in 2001 = decrease with 5%) Higher Education – 3.9 % (3.7 % in 2001 = increase with 0.2 %)
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 29 Basic Assessment Report
Matric – 15.5 % (11.2 % in 2001 = increase with 4%)
b) Socio-economic value of the activity
What is the expected capital value of the activity on completion? ~R150m –
~R200m
What is the expected yearly income that will be generated by or as a result of the activity? R0
Will the activity contribute to service infrastructure? YES NO
Is the activity a public amenity? YES NO
How many new employment opportunities will be created in the development and construction
phase of the activity/ies?
~130
What is the expected value of the employment opportunities during the development and
construction phase?
~R10m
What percentage of this will accrue to previously disadvantaged individuals? ~60%
How many permanent new employment opportunities will be created during the operational
phase of the activity?
0
What is the expected current value of the employment opportunities during the first 10 years? R0
What percentage of this will accrue to previously disadvantaged individuals? 0%
BIODIVERSITY 9
Please note: The Department may request specialist input/studies depending on the nature of the biodiversity occurring on the site and potential impact(s) of the proposed activity/ies. To assist with the identification of the biodiversity occurring on site and the ecosystem status consult http://bgis.sanbi.org or [email protected]. Information is also available on compact disc (cd) from the Biodiversity-GIS Unit, Ph (021) 799 8698. This information may be updated from time to time and it is the applicant/ EAP’s responsibility to ensure that the latest version is used. A map of the relevant biodiversity information (including an indication of the habitat conditions as per (b) below) and must be provided as an overlay map to the property/site plan as Appendix D to this report.
An ecological expert has been appointed to provide input into this environmental process. Please refer to his report attached in Appendix D1.
a) Indicate the applicable biodiversity planning categories of all areas on site and indicate the reason(s)
provided in the biodiversity plan for the selection of the specific area as part of the specific category)
Systematic Biodiversity Planning Category If CBA or ESA, indicate the reason(s) for its selection in biodiversity plan
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 30 Basic Assessment Report
Critical Biodiversity Area (CBA)
Ecological Support
Area (ESA)
Other Natural
Area (ONA)
No Natural Area
Remaining (NNR)
There is no Critical Biodiversity Planning for
this area. The Namaqua Biodiversity
sector plan indicates the area along the
Orange River as a Critical Biodiversity
Area. This proposed powerline will not
have any impact on this the Orange River
or this corridor.
b) Indicate and describe the habitat condition on site
Habitat Condition
Percentage of habitat condition class (adding up
to 100%)
Description and additional Comments and Observations (including additional insight into condition, e.g. poor land
management practises, presence of quarries, grazing, harvesting regimes etc).
Natural 30% Includes natural veld that supports very limited stock grazing
Near Natural (includes areas with low to
moderate level of alien invasive plants)
30%
Includes natural overgrazed veld with limited disturbance from Alien Vegetation.
Degraded (includes areas heavily invaded by alien plants)
10% Includes heavily overgrazed areas and limited erosion
Transformed (includes cultivation,
dams, urban, plantation, roads, etc)
30%
Includes existing tracks and firebreaks.
c) Complete the table to indicate:
(i) the type of vegetation, including its ecosystem status, present on the site; and (ii) whether an aquatic ecosystem is present on site.
Terrestrial Ecosystems Aquatic Ecosystems
Ecosystem threat status as per the National
Environmental Management: Biodiversity
Act (Act No. 10 of 2004)
Critical Wetland (including rivers, depressions, channelled and unchanneled wetlands,
flats, seeps pans, and artificial wetlands)
Estuary Coastline Endangered
Vulnerable
Least Threatened YES NO UNSURE YES NO YES NO
d) Please provide a description of the vegetation type and/or aquatic ecosystem present on site, including
any important biodiversity features/information identified on site (e.g. threatened species and special
habitats)
A desktop review of the available ecological information as well as a site visit and field
assessment of the proposed development area was conducted in order to identify and
characterize the ecological features of the site. The majority of the site consists of arid
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 31 Basic Assessment Report
grassland or grassy shrubland on open plains considered to be of moderate to low
sensitivity. A number of drainage lines of various sizes and significance are also present
and represent the major sensitive features along the power line route.
According to the national vegetation map (Mucina & Rutherford 2006), there are three
vegetation types within the boundaries of the site but only two within the current study
area. An additional two vegetation types are common in the wider area, but do not occur
in the vicinity of the affected area . In terms of the conservation status of the various
vegetation types of the area, only Lower Gariep Alluvial Vegetation is of concern and is
listed as Endangered. This vegetation type is however associated with the alluvium along
the Orange River and would not be impacted by the current development which is some
distance from the river itself.
Within the area affected by the proposed development, the two vegetation types that occur
are Kalahari Karroid Shrubland and Bushmanland Arid Grassland. Both Kalahari
Karroid Shrubland and Bushmanland Arid Grassland are classified as Least Threatened
and have been little impacted by transformation and more 99% of their original extent is
still intact. Both are considered Hardly Protected within formal conservation areas.
Mucina & Rutherford (2006), list 6 endemic species for Bushmanland Arid Grassland, while
no vegetation-type endemic species are known from Kalahari Karroid Shrubland. The
biogeographically important and endemic species known from these vegetation types tend
to be widespread within the vegetation type itself and local-level impacts are not likely to
be of significance for any of these vegetation types or species concerned. Bushmanland
Arid Grassland is widely distributed and represents one of the most extensive vegetation
types in South Africa. Kalahari Karroid Shrubland is less extensive, but represents a
transitional vegetation type between the northern Nama Karoo and Kalahari (Savannah)
vegetation types.
A number of different habitats are traversed by the power line, these have been described
in detail under the previous studies (For RE Capital 3, RE Capital 3b and Sirius Solar PV
Project 1) and are summarized here for the purposes of the current study.
Bushmanland Arid Grassland
The amount of vegetation consistent with this vegetation type is much greater than
suggested by the national vegetation map. Most areas on deeper soils are dominated by
various Stipagrostis species with a variable shrub layer. Common and dominant species
include Stipagrostis ciliata, S.obtusa, S.uniplumis and S.amabilis. Species of conservation
concern are not abundant in this habitat and the only species of concern that was
observed within this habitat type were very occasional Hoodia gordonii plants. Protected
species which occur in this habitat type include occasional individuals of Boscia foetida,
Boscia albitrunca and Acacia erioloba.
Kalahari Karroid Shrubland
Areas of shallow soils with exposed or underlying calcrete often occur on crests of hills or
on valley bottoms along drainage lines. These areas are usually shrub-dominated and
correspond loosely with the Kalahari Karroid Shrubland vegetation type. Typical species
include Leucosphaera bainesii, Hermannia spinosa, Monoechma genistifoilium, Salsola
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 32 Basic Assessment Report
rabieana, Aptosimum albomarginatum, A.spinecens, Kleinia longiflora, Limeum argute-
carinatum, Phyllanthus maderaspatensis, Zygophyllum dregeanum and grasses such as
Stipagrostis anomala, S.ciliata, S.uniplumis, S.hochstetteriana, S.uniplumis and Schmidtia
kalariensis.
Plains Wash
It is common in the area for wash areas to develop on the open plains. These are areas
where runoff may collect and flow during extreme rainfall events, but not to the extent that
that well-defined drainage lines develop. This is typical of arid areas and these areas are
not considered to be drainage lines and usually disappear or dissipate as soon as the soils
get deeper or the slope declines. As such these areas are not categorized as drainage
lines but are nevertheless considered more sensitive than the surrounding plains as these
areas are more vulnerable to disturbance and erosion. These areas are usually dominated
by perennial grasses such as Stipagrostis anomala, S.ciliata, S.uniplumis,
S.hochstetteriana, S.uniplumis and Schmidtia kalariensis. A scattered variable-density
taller woody layer is usually present, consisting of species such as Phaeoptilum spinosum,
Rhigozum trichotomum and Lycium oxycarpum, but there is often little overall
differentiation between the grass and low shrub layer of these areas and the surrounding
vegetation. Aside from Boscia foetida which is fairly common in these areas, there are few
listed or protected species which were observed in this habitat type.
Drainage Lines
There are a number of drainage lines of variable size which occur in the affected area, the
most significant of which are the Helbrandkloofspruit and the Helbrandleegte. These
represent the largest obstacles which would need to be traversed by the power line and all
options would need to traverse these these dry rivers. The drainage lines carry water only
for brief periods following heavy rainfall events and usually consist of a narrow sandy bed
flanked by tall shrubs and scattered trees. Larger drainage lines are dominated by species
such as Acacia erioloba, Boscia albitrunca, Zizyphus mucronata and Searsia lancea, while
the smaller drainage lines are typically dominated species such as Acacia mellifera, Boscia
foetida and Phaeoptilum spinosum. Due to the ecological role that drainage lines play as
well as their vulnerability to disturbance, these areas are considered sensitive and should
be avoided as much as possible. Protected tree species are concentrated along the
drainage lines with species such as Boscia foetida, Boscia albitrunca and Acacia erioloba
being found largely within this habitat type. For this reason, it is recommended that pylon
footprints and maintenance tracks be excluded from these two drainage features.
Listed And Protected Plant Species
According to the SANBI SIBIS database, 286 indigenous plant species have been
recorded from the quarter degree squares 2820 BD, DB and 2821 AC and CA. This
includes 7 species of conservation concern as listed below in Table 3. Two of these can
be confirmed present within the affected area, with Hoodia gordonii present in low numbers
and Acacia erioloba common along the larger drainage lines. There are also additional
species present which are either protected under the National Forests Act such as Boscia
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 33 Basic Assessment Report
albitrunca and Acacia erioloba or protected under the Northern Cape Nature Conservation
Act of 2009, which includes Boscia foetida, all Mesembryanthemaceae, , all species within
the Euphorbiaceae. Oxalidaceae, Iridaceae, all species within the genera Nemesia and
Jamesbrittenia. It is not likely that many Boscia albitrunca would be affected by the
development as this species is mostly restricted to the larger drainage lines at the site.
Boscia foetida is however common along the smaller drainage lines as well as in the open
veld, and it is likely that some of these would be affected. The ecological expert has been
appointed to undertake the site walk through for the biodiversity consents. The results of
this walkthrough will be submitted to DAFF and DENC in support of the Biodiversity
Consent Applications.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 34 Basic Assessment Report
SECTION C: PUBLIC PARTICIPATION
ADVERTISEMENT AND NOTICE 1
Publication name Die Gemsbok Date published 21 August 2015 Site notice position Latitude Longitude
28°36’21.1” 21°05’42.2” 28°35’47.9” 21°06’31.15” Date placed 04 August 2015
Include proof of the placement of the relevant advertisements and notices in Appendix E1.
Copies of the Newspaper Advert, Photographs of the Site Notices as well as a map indicating the position of the site notices are included in Appendix E1.
DETERMINATION OF APPROPRIATE MEASURES 2
Provide details of the measures taken to include all potential I&APs as required by Regulation 41(2)(e) and 41(6) of GN 733. Key stakeholders (other than organs of state) identified in terms of Regulation 41(2)(b) of GN 733
Title, Name and Surname Affiliation/ key stakeholder status Contact details (tel number or e-mail address)
Please refer to the Stakeholder Register attached in Appendix E5
Please refer to the Stakeholder Register attached in Appendix E5
Please refer to the Stakeholder Register attached in Appendix E5
Please refer to the Stakeholder Register attached in Appendix E5 for a full list of stakeholders, their status as well as their full contact details. Include proof that the key stakeholder received written notification of the proposed activities as Appendix E2. This proof may include any of the following:
e-mail delivery reports;
registered mail receipts;
courier waybills;
signed acknowledgements of receipt; and/or
or any other proof as agreed upon by the competent authority.
ISSUES RAISED BY INTERESTED AND AFFECTED PARTIES 3
Summary of main issues raised by I&APs Summary of response from EAP
No issues have been raised to date. This
Section will be updated on completion of
the Public Participation process.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 35 Basic Assessment Report
COMMENTS AND RESPONSE REPORT 4
The practitioner must record all comments received from I&APs and respond to each comment before the Draft BAR is submitted. The comments and responses must be captured in a comments and response report as prescribed in the EIA regulations and be attached to the Final BAR as Appendix E3.
AUTHORITY PARTICIPATION 5
Authorities and organs of state identified as key stakeholders:
Authority/Organ of
State
Contact person
(Title, Name and
Surname)
Tel No Fax No e-mail Postal
address
Please refer to
the Organ of
State Register
attached in
Appendix E5
Include proof that the Authorities and Organs of State received written notification of the proposed activities as appendix E4.
In the case of renewable energy projects, Eskom and the SKA Project Office must be included in the list of Organs of State.
Please refer to the Organ of State Register attached in Appendix E5 for a full list of Organs of State consulted, their status as well as their full contact details.
CONSULTATION WITH OTHER STAKEHOLDERS 6
Note that, for any activities (linear or other) where deviation from the public participation requirements may be appropriate,
the person conducting the public participation process may deviate from the requirements of that sub-regulation to the extent
and in the manner as may be agreed to by the competent authority.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 36 Basic Assessment Report
Proof of any such agreement must be provided, where applicable. Application for any deviation from the regulations relating
to the public participation process must be submitted prior to the commencement of the public participation process.
A list of registered I&APs must be included as appendix E5.
Copies of any correspondence and minutes of any meetings held must be included in Appendix E6.
The table below indicates how the public participation has complied with the minimum
requirement contained in the regulations.
Regulated Requirement Description
(1) If the proponent is not the owner or
person in control of the land on which the
activity is to be undertaken, the proponent
must, before applying for an environmental
authorisation in respect of such activity,
obtain the written consent of the landowner
or person in control of the land to undertake
such activity on that land.
(2) Subregulation (1) does not apply in
respect of-.
(a) linear activities;
The proposed grid connection is deemed to
constitute a linear activity and as such not
required to obtain landowner consent. Proof
of Landowner notification is attached to the
application. Landowners have also been
notified of the availability of this Basic
Assessment Report for review and comment.
The person conducting a public participation process must take into account any relevant
guidelines applicable to public participation as contemplated in section 24J of the Act and
must give notice to all potential interested and affected parties of an application or proposed
application which is subjected to public participation by -
(a) fixing a notice board at a place
conspicuous to and accessible by the public
at the boundary, on the fence or along the
corridor of -
(i) the site where the activity to which the
application or proposed application relates is
or is to be undertaken; and
(ii) any alternative site;
Two site notices have been placed along the
N14 near the existing access roads.
Proof of these notices is attached in
Appendix E1.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 37 Basic Assessment Report
Regulated Requirement Description
(b) giving written notice, in any of the manners provided for in section 47D of the Act, to -
(i) the occupiers of the site and, if the
proponent or applicant is not the owner or
person in control of the site on which the
activity is to be undertaken, the owner or
person in control of the site where the
activity is or is to be undertaken or to any
alternative site where the activity is to be
undertaken;
Th owner is the only current occupier of the
site. The landowners have been notified of
this application.
(ii) owners, persons in control of, and
occupiers of land adjacent to the site where
the activity is or is to be undertaken or to
any alternative site where the activity is to
be undertaken;
Owners of adjacent properties have been
notified of this environmental process. Such
owners have been requested to inform the
occupiers of the land of this environmental
process.
(iii) the municipal councillor of the ward in
which the site or alternative site is situated
and any organisation of ratepayers that
represent the community in the area;
The ward councillor has been notified of this
environmental process.
(iv) the municipality which has jurisdiction in
the area;
The Khai Garib municipality has been notified
of this environmental process.
(v) any organ of state having jurisdiction in
respect of any aspect of the activity; and
All organs of state and state departments
agreed upon during the pre-application
meeting have been notified of this
environmental process.
(vi) any other party as required by the
competent authority;
A pre application meeting was held with the
competent authority. At this meeting the
competent authority provided input into the
proposed Stakeholder register. All additional
parties identified at this pre-application
meeting have been included in the
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 38 Basic Assessment Report
Regulated Requirement Description
stakeholder register and have received
notifications of the availability of the Basic
Assessment Report.
(c) placing an advertisement in -
(i) one local newspaper; or
(ii) any official Gazette that is published
specifically for the purpose of providing
public notice of applications or other
submissions made in terms of these
Regulations;
An advert has been placed in “Die Gemsbok”
newspaper.
There is currently no official Gazette that has
been published specifically for the purpose of
providing public notice of applications
(d) placing an advertisement in at least one
provincial newspaper or national
newspaper, if the activity has or may have
an impact that extends beyond the
boundaries of the metropolitan or district
municipality in which it is or will be
undertaken: Provided that this paragraph
need not be complied with if an
advertisement has been placed in an official
Gazette referred to in paragraph (c)(ii);and
Adverts will not be placed in provincial or
national newspapers, as the potential impacts
will not extend beyond the borders of the
municipal area.
(e) using reasonable alternative methods, as
agreed to by the competent authority, in
those instances where a person is desirous
of but unable to participate in the process
due to -
(i) illiteracy;
(ii) disability; or
(iii) any other disadvantage.
Notifications will include provision for
alternative engagement in the event of
illiteracy, disability or any other disadvantage.
In such instances, Cape EAPrac will engage
with such individuals in such a manner as
agreed on with the competent authority.
(3) A notice, notice board or advertisement
referred to in subregulation (2) must -
The notice board referred to above has
complied with these requirements.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 39 Basic Assessment Report
Regulated Requirement Description
(a) give details of the application or
proposed application which is subjected to
public participation; and
(b) state -
(i) whether basic assessment or S&EIR
procedures are being applied to the
application;
(ii) the nature and location of the activity to
which the application relates;
(iii) where further information on the
application or proposed application can be
obtained; and
(iv) the manner in which and the person to
whom representations in respect of the
application or proposed application may be
made.
(4) A notice board referred to in
subregulation (2) must -
(a) be of a size at least 60cm by 42cm; and
(b) display the required information in
lettering and in a format as may be
determined by the competent authority.
The notice board referred to above has
complied with these requirements.
(5) Where public participation is conducted
in terms of this regulation for an application
or proposed application, subregulation
(2)(a), (b), (c) and (d) need not be complied
with again during the additional public
participation process contemplated in
regulations 19(1)(b) or 23(1)(b) or the public
participation process contemplated in
regulation 21(2)(d), on condition that -
This will be complied with if final reports are
produced later on in the environmental
process.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 40 Basic Assessment Report
Regulated Requirement Description
(a) such process has been preceded by a
public participation process which included
compliance with subregulation (2)(a), (b), (c)
and (d); and
(b) written notice is given to registered
interested and affected parties regarding
where the -
(i) revised basic assessment report or, EMPr
or closure plan, as contemplated in
regulation 19(1)(b);
(ii) revised environmental impact report or
EMPr as contemplated in regulation
23(1)(b);or
(iii) environmental impact report and EMPr
as contemplated in regulation 21(2)(d);
may be obtained, the manner in which and
the person to whom representations on
these reports or plans may be made and the
date on which such representations are due.
(6) When complying with this regulation, the
person conducting the public participation
process must ensure that -
(a) information containing all relevant facts
in respect of the application or proposed
application is made available to potential
interested and affected parties; and
(b) participation by potential or registered
interested and affected parties is facilitated
in such a manner that all potential or
registered interested and affected parties
are provided with a reasonable opportunity
to comment on the application or proposed
All reports that are submitted to the
competent authority will be subject to a public
participation process. These include:
- Basic Assessment Report.
- Environmental Management
Programme.
- All Specialist Reports.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 41 Basic Assessment Report
Regulated Requirement Description
application.
(7) Where an environmental authorisation is
required in terms of these Regulations and
an authorisation, permit or licence is
required in terms of a specific environmental
management Act, the public participation
process contemplated in this Chapter may
be combined with any public participation
processes prescribed in terms of a specific
environmental management Act, on
condition that all relevant authorities agree
to such combination of processes.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 42 Basic Assessment Report
SECTION D: IMPACT ASSESSMENT
The assessment of impacts must adhere to the minimum requirements in the EIA Regulations, 2014 and should take
applicable official guidelines into account. The issues raised by interested and affected parties should also be addressed in
the assessment of impacts.
IMPACTS THAT MAY RESULT FROM THE PLANNING AND 1DESIGN, CONSTRUCTION, OPERATIONAL, DECOMMISSIONING AND CLOSURE PHASES AS WELL AS PROPOSED MANAGEMENT OF IDENTIFIED IMPACTS AND PROPOSED MITIGATION MEASURES
Provide a summary and anticipated significance of the potential direct, indirect and cumulative impacts that are likely to occur as a result of the planning and design phase, construction phase, operational phase, decommissioning and closure phase, including impacts relating to the choice of site/activity/technology alternatives as well as the mitigation measures that may eliminate or reduce the potential impacts listed. This impact assessment must be applied to all the identified alternatives to the activities identified in Section A(2) of this report.
Activity Impact summary Significance Proposed mitigation
Alternative 1 (preferred alternative)
Direct impacts: Impacts on vegetation and listed or protected plant species resulting from construction activities.
Medium Negative Low Negative with Mitigation
Preconstruction walk-through of the power line route in order to locate species of conservation concern that can be translocated as well as comply with the Northern Cape Nature Conservation Act and DENC/DAFF permit conditions. Construction and vegetation clearing to commence only after walk through has been conducted and necessary permits obtained. No large woody species should be cleared from the power line servitude. It may be necessary to remove some individuals from the area directly beneath the power line due to safety concerns, however, within the wider servitude the presence of large woody species does not increase the fire risk and so there are no valid reasons to remove such trees. If these are too tall and cause safety problems, they can be cut to a lower height rather than removed and, as growth rate in arid areas is slow, it would take many years before such trees would need to be trimmed again. Such trees can be trimmed to 1m height if necessary. Preconstruction environmental induction for all construction staff to ensure that basic environmental principles are adhered to. This includes awareness as to no littering, appropriate handling of pollution and chemical spills, avoiding fire hazards, minimizing wildlife interactions, remaining within demarcated construction areas etc. Vegetation clearing along the power line corridor should only be conducted where necessary and
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 43 Basic Assessment Report
Activity Impact summary Significance Proposed mitigation
should not be cleared using herbicides or with a bulldozer. Vegetation can be cleared manually with bush cutters to 0.5m height where necessary. Temporary lay-down areas should be located within previously transformed areas or areas that have been identified as being of low sensitivity.
Direct impacts: Direct Faunal Impacts during Construction
Medium Negative. Low negative with mitigation
All personnel should undergo environmental induction with regards to fauna and in particular awareness about not harming or collecting species such as snakes, tortoises and owls, which are often persecuted out of superstition. Any fauna threatened by the construction activities should be removed to safety by the ECO or appropriately qualified environmental officer. All construction vehicles should adhere to a low speed limit to avoid collisions with susceptible species such as snakes and tortoises. All hazardous materials should be stored in the appropriate manner to prevent contamination of the site. Any accidental chemical, fuel and oil spills that occur at the site should be cleaned up in the appropriate manner as related to the nature of the spill. If holes or trenches need to be dug, these should not be left open for extended periods of time as fauna may fall in and become trapped in them. Holes should only be dug when they are required and should be used and filled shortly thereafter.
Direct impacts: Degradation of Scenic Resources during construction
Low Utilisation of existing northsouth access roads to access the corridor; Location of the pylons outside of drainage lines, or significant biodiversity areas (as per the ecology specialists findings); Soil erosion management along the maintenance road along the proposed corridor. The Preferred Alternative makes a kink to follow the Sirius SEF footprint areas. If possible, it is recommended that the route be aligned as straigtht as possible, so that any further power lines from future SEF projects to the west, will also be routed in a straight line (adjacent the proposed routing).
Direct impacts: Degradation of Scenic Resources during operation
Low Utilisation of existing northsouth access roads to access the corridor; Location of the pylons outside of drainage lines, or significant biodiversity areas (as per the ecology specialists findings); Soil erosion management along the maintenance road along the proposed corridor.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 44 Basic Assessment Report
Activity Impact summary Significance Proposed mitigation
The Preferred Alternative makes a kink to follow the Sirius SEF footprint areas. If possible, it is recommended that the route be aligned as straigtht as possible, so that any further power lines from future SEF projects to the west, will also be routed in a straight line (adjacent the proposed routing).
Direct impacts: Impacts on Cultural Landscape Context
Low None
Direct impacts: Impacts on Archaeological Resources
Low If any human remains are uncovered during construction, the ECO should have the area fenced off and contact SAHRA (Tel: 021 462 4502) immediately; If there are any significant changes to the layout of the facility, the new design should be assessed by a heritage practitioner.
Direct impacts: Impacts on Palaeontological resources
Low Should any substantial fossil remains (e.g. mammalian bones and teeth) be encountered during excavation, however, these should be safeguarded, preferably in situ, and reported by the ECO to SAHRA, i.e. The South African Heritage Resources Authority, as soon as possible (Contact details: Mrs Colette Scheermeyer, P.O. Box 4637, Cape Town 8000. Tel: 021 462 4502 (Email: [email protected])
Indirect impacts: Avifaunal impact due to collision or electrocution from power line.
Medium Negative. Low Negative with Mitigation.
All new power line infrastructure should be bird-friendly in configuration and adequately insulated (Lehman et al. 2007). The sections of the line over ridges and near drainage lines should be fitted with bird flight diverters (flappers) and the live components should be insulated to reduce electrocution problems. Sections to be fitted with flappers should be identified during the walk-through of the final route and informed by bird movements in the area. Surveys along the power line for dead birds should be conducted monthly for a year after construction to ascertain if there are any sections present which are generating a high impact on avifauna and where additional mitigation is necessary.
Indirect impacts: Ecosystem degradation along powerline route due to erosion and alien plant invasion.
Medium-low negative. Low Negative with Mitigation.
Regular erosion and alien plant management along the power line servitude. Herbicides should only be used on alien species and should not be broadcast or sprayed and should only be used on cut-stump type applications where it is applied by hand to specific plants. During operation and maintenance of the power line servitudes, alien species especially large woody species such as Prosopis glandulosa should be cleared from the power line servitudes.
Alternative 2
Direct impacts: Impacts on vegetation and
Medium Negative
Preconstruction walk-through of the power line route in order to locate species of conservation
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 45 Basic Assessment Report
Activity Impact summary Significance Proposed mitigation
listed or protected plant species resulting from construction activities.
Low Negative with mitigation.
concern that can be translocated as well as comply with the Northern Cape Nature Conservation Act and DENC/DAFF permit conditions. Construction and vegetation clearing to commence only after walk through has been conducted and necessary permits obtained. No large woody species should be cleared from the power line servitude. It may be necessary to remove some individuals from the area directly beneath the power line due to safety concerns, however, within the wider servitude the presence of large woody species does not increase the fire risk and so there are no valid reasons to remove such trees. If these are too tall and cause safety problems, they can be cut to a lower height rather than removed and, as growth rate in arid areas is slow, it would take many years before such trees would need to be trimmed again. Such trees can be trimmed to 1m height if necessary. Preconstruction environmental induction for all construction staff to ensure that basic environmental principles are adhered to. This includes awareness as to no littering, appropriate handling of pollution and chemical spills, avoiding fire hazards, minimizing wildlife interactions, remaining within demarcated construction areas etc. Vegetation clearing along the power line corridor should only be conducted where necessary and should not be cleared using herbicides or with a bulldozer. Vegetation can be cleared manually with bush cutters to 0.5m height where necessary. Temporary lay-down areas should be located within previously transformed areas or areas that have been identified as being of low sensitivity.
Direct impacts: Direct Faunal Impacts during Construction
Medium Negative. Low negative with mitigation
All personnel should undergo environmental induction with regards to fauna and in particular awareness about not harming or collecting species such as snakes, tortoises and owls, which are often persecuted out of superstition. Any fauna threatened by the construction activities should be removed to safety by the ECO or appropriately qualified environmental officer. All construction vehicles should adhere to a low speed limit to avoid collisions with susceptible species such as snakes and tortoises. All hazardous materials should be stored in the appropriate manner to prevent contamination of the site. Any accidental chemical, fuel and oil spills that occur at the site should be cleaned up in the appropriate manner as related to the nature of the
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 46 Basic Assessment Report
Activity Impact summary Significance Proposed mitigation
spill. If holes or trenches need to be dug, these should not be left open for extended periods of time as fauna may fall in and become trapped in them. Holes should only be dug when they are required and should be used and filled shortly thereafter.
Direct impacts: Degradation of Scenic Resources during construction
Low Future power lines should be routed to the north of the authorised; Utilisation of existing north south access roads to access the corridor; Location of the pylons outside of drainage lines, or significant biodiversity areas (as per the ecology specialists findings); Soil erosion management along the maintenance road along the proposed corridor.
Direct impacts: Degradation of Scenic Resources during operation
Medium to high (As a result of cumulative impact)
the authorised; Utilisation of existing north south access roads to access the corridor; Location of the pylons outside of drainage lines, or significant biodiversity areas (as per the ecology specialists findings); Soil erosion management along the maintenance road along the proposed corridor.
Direct impacts: Impacts on Cultural Landscape Context
Low None
Direct impacts: Impacts on Archaeological Resources
Low If any human remains are uncovered during construction, the ECO should have the area fenced off and contact SAHRA (Tel: 021 462 4502) immediately; If there are any significant changes to the layout of the facility, the new design should be assessed by a heritage practitioner.
Direct impacts: Impacts on Palaeontological resources
Low Should any substantial fossil remains (e.g. mammalian bones and teeth) be encountered during excavation, however, these should be safeguarded, preferably in situ, and reported by the ECO to SAHRA, i.e. The South African Heritage Resources Authority, as soon as possible (Contact details: Mrs Colette Scheermeyer, P.O. Box 4637, Cape Town 8000. Tel: 021 462 4502 (Email: [email protected])
Indirect impacts: Avifaunal impact due to collision or electrocution from power line.
Medium Negative. Low Negative with Mitigation.
All new power line infrastructure should be bird-friendly in configuration and adequately insulated (Lehman et al. 2007). The sections of the line over ridges and near drainage lines should be fitted with bird flight diverters (flappers) and the live components should be insulated to reduce electrocution problems.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 47 Basic Assessment Report
Activity Impact summary Significance Proposed mitigation
Sections to be fitted with flappers should be identified during the walk-through of the final route and informed by bird movements in the area. Surveys along the power line for dead birds should be conducted monthly for a year after construction to ascertain if there are any sections present which are generating a high impact on avifauna and where additional mitigation is necessary.
Indirect Impacts: Ecosystem degradation along powerline route due to erosion and alien plant invasion.
Medium-low negative. Low Negative with Mitigation.
Regular erosion and alien plant management along the power line servitude. Herbicides should only be used on alien species and should not be broadcast or sprayed and should only be used on cut-stump type applications where it is applied by hand to specific plants. During operation and maintenance of the power line servitudes, alien species especially large woody species such as Prosopis glandulosa should be cleared from the power line servitudes.
Cumulative impacts:
No-go option It must be noted that the no go alternative in this case is deemed to be the continuation of constructing and operating three separate power lines as already authorised. For this reason, you will note that the significance of certain impacts associated with the No Go Alternative are higher than those of the current proposal.
Direct impacts: Impacts on vegetation and listed or protected plant species resulting from construction activities.
Medium – High Negative. Low Negative with mitigation.
None
Direct impacts: Direct Faunal Impacts during Construction
Medium Negative. Low negative with mitigation
None
Direct impacts: Degradation of Scenic Resources during construction
Medium None
Direct impacts: Degradation of Scenic Resources during operation
Medium – High (as a result of cumulative impact)
None
Direct impacts: Impacts on Cultural Landscape Context
Low None
Direct impacts: Impacts on Archaeological Resources
Low None
Direct impacts: Impacts on Palaeontological resources
Low None
Indirect impacts: Medium None
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 48 Basic Assessment Report
Activity Impact summary Significance Proposed mitigation
Avifaunal impact due to collision or electrocution from power line.
Negative. Low Negative with Mitigation.
Indirect Impacts: Ecosystem degradation along powerline route due to erosion and alien plant invasion.
Medium-low negative. Low Negative with Mitigation.
None
A complete impact assessment in terms of Regulation 19(3) of GN 733 must be included as Appendix F.
ENVIRONMENTAL IMPACT STATEMENT 2
Taking the assessment of potential impacts into account, please provide an environmental impact statement that summarises the impact that the proposed activity and its alternatives may have on the environment after the management and mitigation of impacts have been taken into account, with specific reference to types of impact, duration of impacts, likelihood of potential impacts actually occurring and the significance of impacts. Alternative A (preferred alternative)
Ecological Impacts
The integrated, combined grid connection for the Dyasonsklip and Sirius PV facilities would
generate a lower overall impact than the original 3 grid connections. The main benefit
would be the need for a single line from the Dyasonsklip facilities compared to the current
double line. However, as these two lines runs adjacent to one another, this benefit is not a
large as it would be if the two lines followed different routes.
In terms of the two alternatives considered for the combined grid connection, the main
difference between the two alternatives is that the Alternative 2, the southern route runs
adjacent to the existing Oranje-Oasis 132kV power line for a large proportion of the route.
This reduces the potential impact of this alternative as the same access route can be used
and some potentially important impacts such as avifaunal collisions may be significantly
lower as a result of the proximity to the existing line. However, this alternative also has
significant sections away from the existing Oranje-Oasis 132kV line, especially the section
looping in and out of the Sirius substation. Consequently, this difference is not considered
significant. As a result, there is not a significant difference between the two proposed
alternatives and both are considered acceptable alternatives from a terrestrial ecology
point of view.
The conclusion of the ecological study is that either or the proposed alternatives would be
acceptable ecologically and that with reasonable mitigation applied, there would be no
highly significant long-term impacts associated with the grid connection. The current
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 49 Basic Assessment Report
preferred alternative from a technical perspective is Alternative 1 and there are no reasons
that this alternative should not be authorised in favour of Alternative 2.
Visual Impacts
It is the recommendation of the visual study that the Preferred Routing Alternative is also
visually preferred.
A barrier effect is not apparent for this Preferred Alternative, which would allow for a new
power line corridor, running parallel to the existing Eskom 132kV line, but with a suitable
gap and with the routing corridor location outside of the ZVI of the N14 National Road
(hence the Preferred Routing was rated low). As mitigation would not have a major
reduction in the resultant visual impacts, significance for all the routings was rated the
same as without mitigation. Mitigations in terms of best practice were recommended, to
straighten the proposed routing and much as possible, setting in place a precedent for a
future power line corridor running parallel, but further to the north, of the existing Eskom
132kV power line.
Heritage Impacts
From a regional and natural landscape perspective, the proposed development site forms
part of a highly-transformed landscape that has already been altered through mining
activities as well as high concentration of proposals for development of renewable energy
(solar) facilities. The proposal put forward in this report would relate to a significant
reduction in the total distance of transmission lines required to be installed for the Sirius 1
and Dyasonsklip 1 & 2 solar energy facilities by combining the three already approved
transmission line alignments into a single route alignment.
While the proposal would relate to a landscape modification, we are of the view that this
proposal would significantly reduce the overall visual impact of the proposal. Even if not
the case, the specialist is of the view that none of the two route alignment alternatives
would materially alter any natural or cultural landscape of cultural significance.
Findings and recommendations from archaeological impact assessments undertaken with
relation to the already-authorised solar energy facilities to which this proposal relate, did
not identify or highlight any archaeological resources considered of high or moderate
cultural significance. Given the nature of the proposal, which would not traverse any
archaeological occurrences identified, it is the specialists view that none of the two route
alignment alternatives as put forward herewith would warrant any further archaeological
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 50 Basic Assessment Report
investigation.
It is concluded that none of the two route alignment alternatives are likely to have any
significant impacts on local palaeontological heritage resources.
Alternative B
Ecological Impacts
The integrated, combined grid connection for the Dyasonsklip and Sirius PV facilities would
generate a lower overall impact than the original 3 grid connections. The main benefit
would be the need for a single line from the Dyasonsklip facilities compared to the current
double line. However, as these two lines runs adjacent to one another, this benefit is not a
large as it would be if the two lines followed different routes.
In terms of the two alternatives considered for the combined grid connection, the main
difference between the two alternatives is that the Alternative 2, the southern route runs
adjacent to the existing Oranje-Oasis 132kV power line for a large proportion of the route.
This reduces the potential impact of this alternative as the same access route can be used
and some potentially important impacts such as avifaunal collisions may be significantly
lower as a result of the proximity to the existing line. However, this alternative also has
significant sections away from the existing Oranje-Oasis 132kV line, especially the section
looping in and out of the Sirius substation. Consequently, this difference is not considered
significant. As a result, there is not a significant difference between the two proposed
alternatives and both are considered acceptable alternatives from a terrestrial ecology
point of view.
The conclusion of the ecological study is that either or the proposed alternatives would be
acceptable ecologically and that with reasonable mitigation applied, there would be no
highly significant long-term impacts associated with the grid connection.
Visual Impacts
The significance of this alternative was also rated medium to high due to the north-south
section of the line (Sirius SS LILO), creating a structure barrier that would force any future
power line routings to follow the same alignment, crossing over the existing Eskom 132kV
line, essentially setting a precedent for a power line corridor to the south of the existing
line. This routing corridor is in close visual proximity to the N14 National Road, which
carries tourist traffic and should be recognised as a tourist view corridor. As mitigation
would not have a major reduction in the resultant visual impacts, significance for all the
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 51 Basic Assessment Report
routings was rated the same as without mitigation. Mitigations in terms of best practice
were recommended, to straighten the proposed routing and much as possible, setting in
place a precedent for a future power line corridor running parallel, but further to the north,
of the existing Eskom 132kV power line.
Heritage Impacts
From a regional and natural landscape perspective, the proposed development site forms
part of a highly-transformed landscape that has already been altered through mining
activities as well as high concentration of proposals for development of renewable energy
(solar) facilities. The proposal put forward in this report would relate to a significant
reduction in the total distance of transmission lines required to be installed for the Sirius 1
and Dyasonsklip 1 & 2 solar energy facilities by combining the three already approved
transmission line alignments into a single route alignment.
While the proposal would relate to a landscape modification, the specialist is of the view
that this proposal would significantly reduce the overall visual impact (compared to the
authorised powerlines). Even if not the case, we are of the view that none of the two route
alignment alternatives would materially alter any natural or cultural landscape of cultural
significance.
Findings and recommendations from archaeological impact assessments undertaken with
relation to the already-authorised solar energy facilities to which this proposal relate, did
not identify or highlight any archaeological resources considered of high or moderate
cultural significance. Given the nature of the proposal, which would not traverse any
archaeological occurrences identified, it is the specialists view that none of the two route
alignment alternatives as put forward herewith would warrant any further archaeological
investigation.
It is concluded that none of the two route alignment alternatives are likely to have any
significant impacts on local palaeontological heritage resources.
Alternative C
No-go alternative (compulsory)
Ecological
The integrated, combined grid connection for the Dyasonsklip and Sirius PV facilities (this
proposal) would generate a lower overall impact than the No-go alternative (continuing with
the original 3 grid connections as authorised). The main benefit would be the need for a
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 52 Basic Assessment Report
single line from the Dyasonsklip facilities compared to the current double line. However,
as these two lines runs adjacent to one another, this benefit is not a large as it would be if
the two lines followed different routes.
Visual Impacts
Operation phase visual impact significance was rated medium to high for the Status Quo
option, due to the cumulative visual impacts from the cluttering of the landscapes, setting a
precedent for un-aligned routing corridors taking place in the future.
Heritage Impacts
The proposal put forward in this report would relate to a significant reduction in the total
distance of transmission lines required to be installed for the Sirius 1 and Dyasonsklip 1 &
2 solar energy facilities by combining the three already approved transmission line
alignments into a single route alignment and is thus preferred to the No Go Alternative.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 53 Basic Assessment Report
SECTION E. RECOMMENDATION OF PRACTITIONER
Is the information contained in this report and the documentation attached hereto sufficient to make
a decision in respect of the activity applied for (in the view of the environmental assessment
practitioner)?
YES NO
If “NO”, indicate the aspects that should be assessed further as part of a Scoping and EIA process before a decision can be
made (list the aspects that require further assessment).
NA
If “YES”, please list any recommended conditions, including mitigation measures that should be considered for inclusion in
any authorisation that may be granted by the competent authority in respect of the application.
- Preconstruction walk-through of the power line route in order to locate species of
conservation concern that can be translocated as well as comply with the Northern
Cape Nature Conservation Act and DENC/DAFF permit conditions.
- Construction and vegetation clearing to commence only after walk through has
been conducted and necessary permits obtained.
- No large woody species should be cleared from the power line servitude. It may be
necessary to remove some individuals from the area directly beneath the power
line due to safety concerns, however, within the wider servitude the presence of
large woody species does not increase the fire risk and so there are no valid
reasons to remove such trees. If these are too tall and cause safety problems, they
can be cut to a lower height rather than removed and, as growth rate in arid areas
is slow, it would take many years before such trees would need to be trimmed
again. Such trees can be trimmed to 1m height if necessary.
- Preconstruction environmental induction for all construction staff to ensure that
basic environmental principles are adhered to. This includes awareness as to no
littering, appropriate handling of pollution and chemical spills, avoiding fire hazards,
minimizing wildlife interactions, remaining within demarcated construction areas
etc.
- Vegetation clearing along the power line corridor should only be conducted where
necessary and should not be cleared using herbicides or with a bulldozer.
Vegetation can be cleared manually with bush cutters to 0.5m height where
necessary.
- Temporary lay-down areas should be located within previously transformed areas
or areas that have been identified as being of low sensitivity.
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 54 Basic Assessment Report
- All personnel should undergo environmental induction with regards to fauna and in
particular awareness about not harming or collecting species such as snakes,
tortoises and owls, which are often persecuted out of superstition.
- Any fauna threatened by the construction activities should be removed to safety by
the ECO or appropriately qualified environmental officer.
- All construction vehicles should adhere to a low speed limit to avoid collisions with
susceptible species such as snakes and tortoises.
- All hazardous materials should be stored in the appropriate manner to prevent
contamination of the site. Any accidental chemical, fuel and oil spills that occur at
the site should be cleaned up in the appropriate manner as related to the nature of
the spill.
- If holes or trenches need to be dug, these should not be left open for extended
periods of time as fauna may fall in and become trapped in them. Holes should
only be dug when they are required and should be used and filled shortly
thereafter.
- The contractor must utilise the existing north south access roads to access the
corridor;
- Location of the pylons to be outside of all drainage lines,
- If any human remains are uncovered during construction, the ECO should have the
area fenced off and contact SAHRA (Tel: 021 462 4502) immediately;
- If there are any significant changes to the layout of the facility, the new design
should be assessed by a heritage practitioner.
- Should any substantial fossil remains (e.g. mammalian bones and teeth) be
encountered during excavation, however, these should be safeguarded, preferably
in situ, and reported by the ECO to SAHRA, i.e. The South African Heritage
Resources Authority, as soon as possible (Contact details: Mrs Colette
Scheermeyer, P.O. Box 4637, Cape Town 8000. Tel: 021 462 4502 (Email:
- All new power line infrastructure should be bird-friendly in configuration and
adequately insulated (
- The sections of the line over ridges and near drainage lines should be fitted with
bird flight diverters (flappers) and the live components should be insulated to
reduce electrocution problems. Sections to be fitted with flappers should be
identified during the walk-through of the final route and informed by bird
movements in the area.
- Surveys along the power line for dead birds should be conducted monthly for a
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 55 Basic Assessment Report
year after construction to ascertain if there are any sections present which are
generating a high impact on avifauna and where additional mitigation is necessary.
- Regular erosion and alien plant management must take place along the power line
servitude.
- Herbicides should only be used on alien species and should not be broadcast or
sprayed and should only be used on cut-stump type applications where it is applied
by hand to specific plants.
- During operation and maintenance of the power line servitudes, alien species
especially large woody species such as Prosopis glandulosa should be cleared
from the power line servitudes.
Is an EMPr attached? YES NO
The EMPr must be attached as Appendix G.
The details of the EAP who compiled the BAR and the expertise of the EAP to perform the Basic Assessment process must
be included as Appendix H.
If any specialist reports were used during the compilation of this BAR, please attach the declaration of interest for each
specialist in Appendix I.
Any other information relevant to this application and not previously included must be attached in Appendix J.
NAME OF EAP
SIGNATURE OF EAP DATE
DK1&2 and Sirius Grid Connection SIY231/04
Cape EAPrac 56 Basic Assessment Report
SECTION F: APPENDIXES
The following appendixes must be attached:
Appendix A: Maps
Appendix B: Photographs
Appendix C: Facility illustration(s)
Appendix D: Specialist reports (including terms of reference)
Appendix E: Public Participation
Appendix F: Impact Assessment
Appendix G: Environmental Management Programme (EMPr)
Appendix H: Details of EAP and expertise
Appendix I: Specialist’s declaration of interest
Appendix J: Additional Information
DK1 & 2 and Sirius Grid Connection SIY231b/04
Cape EAPrac Basic Assessment Report
REFERENCES
DWA (2001). Generic public participation guideline. Department of Water Affairs and
Forestry.
DEAT (2002). Integrated Environmental Management Information Series 3: Stakeholder
Engagement. Department of Environmental Affairs and Tourism, Pretoria.
DEADP (2003). Waste Minimisation Guideline for Environmental Impact Assessment
reviews. NEMA EIA Regulations Guideline & Information Series, Department Environmental
Affairs & Development Planning.
DEAT (2004). Criteria for determining alternatives in EIAs, Integrated Environmental
Management, Information Series 11, Department of Environmental Affairs & Tourism,
Pretoria.
DEAT (2004). Environmental management Plans, Integrated Environmental management,
Informatino Series 12, Department Environmental Affairs & Tourism.
DEAT (2005). Assessment of Impacts and Alternatives, Integrated Environmental
Management Guideline Series, Department of Environmental Affairs & Tourism, Pretoria.
DEAT (2005). Guideline 4: Public Participation, in terms of the EIA Regulations 2005,
Integrated Environmental Management Guideline Series, Department of Environmental
Affairs and Tourism, Pretoria.
DEADP (2005). Guideline for the review of specialist input in the EIA process. NEMA EIA
Regulations Guideline & Information Document Series, Department of Environmental Affairs
& Development Planning.
DEADP (2005). Guideline for involving biodiversity specialists in the EIA process. NEMA
EIA Regulations Guideline & Information Document Series, Department of Environmental
Affairs & Development Planning.
DEADP (2005). Guideline for environmental management plans. NEMA EIA Regulations
Guideline & Information Document Series, Department of Environmental Affairs &
Development Planning.
DEADP (2005). Provincial urban edge guideline. Department Environmental Affairs &
Development Planning.
DEAT (2006). EIA Regulations in terms of the National Environmental Management Act (Act
No 107 of 1998) (Government Notice No R 385, R 386 and R 387 in Government Gazette No
28753 of 21 April 2006).
DK1 & 2 and Sirius Grid Connection SIY231b/04
Cape EAPrac Basic Assessment Report
DEADP (2006). Guideline on the Interpretation of the Listed Activities. NEMA EIA
Regulations Guidelines & Information Document Series, Department of Environmental Affairs
& Development Planning.
DEADP (2007). Guide on Alternatives, NEMA EIA Regulations Guidelines & Information
Document Series, Department of Environmental Affairs & Development Planning.
DEADP (2007). Guideline on Appeals, NEMA EIA Regulations Guidelines & Information
Document Series, Department of Environmental Affairs & Development Planning.
DEADP (2007). Guideline on Exemption Applications. NEMA EIA Regulations Guidelines &
Information Document Series, Department of Environmental Affairs & Development Planning.
DEADP (2007). Guideline on Public Participation. NEMA EIA Regulations Guidelines &
Information Document Series, Department of Environmental Affairs & Development Planning.
DEADP (2009). Guideline on Need & Desirability, NEMA EIA Regulations Guideline and
Information Document Series, Department Environmental Affairs & Development Planning.
DEADP (2009). Guideline on Alternatives, NEMA EIA Regulations Guideline and
Information Document Series, Department Environmental Affairs & Development Planning.
DEADP (2009). Guideline on Transitional Arrangements, NEMA EIA Regulations Guideline
and Information Document Series, Department Environmental Affairs & Development
Planning.
DEADP (2009). Guideline on Exemption Applications. NEMA EIA Regulations Guideline
and Information Document Series, Department Environmental Affairs & Development
Planning.
DEADP (2009). Guideline on Appeals. NEMA EIA Regulations Guideline and Information
Document Series, Department Environmental Affairs & Development Planning.
DEADP (2009). Guideline on Public Participation. NEMA EIA Regulations Guideline and
Information Document Series, Department Environmental Affairs & Development Planning.
Keatimilwe K & Ashton PJ 2005. Guideline for the review of specialist input in EIA
processes. Department Environmental Affairs & Development Planning.
Lochner P (2005). Guideline for Environmental Management Plans. Department
Environmental Affairs & Development Planning.
Münster, F. (2005). Guidelines for Determining the Scope of Specialist Involvement in EIA
Processes: Edition 1. CSIR Report No ENV-S-C 2005 053 A. Republic of South Africa,
Provincial Government of the Western Cape, Department of Environmental Affairs and
Development Planning, Cape Town.
DK1 & 2 and Sirius Grid Connection SIY231b/04
Cape EAPrac Basic Assessment Report
Oberholzer B (2005). Guideline for involving visual & aesthetic specialists. Department
Environmental Affairs & Development Planning.
Winter S & Beaumann N (2005). Guideline for involving heritage specialists in EIA
processes. Department Environmental Affairs & Development Planning.
DEA (2010). National Climate Change Response Green Paper 2010.
DEA (January 2008). National Response to South Africa’s Electricity Shortage.
Interventions to address electricity shortages.
DEA&DP. (May 2006). Strategic Initiative to Introduce Commercial Land Based Wind Energy
Development to the Western Cape: Specialist Study: Executive Summary - CNdV Africa
prepared for Provincial Government of the Western Cape.
Department of Mineral & Energy (1998). White Paper on Energy Policy of the Republic of
South Africa.
Department of Mineral & Energy (2003). The White Paper on Renewable Energy.
Hsai-Yang, F (Ed)(2006). Environmental Geotechnology Dictionary (online version).
University of North Caroline, Charlotte, USA.
Integrated Resource Plan for Electricity (Oct. 2010). Revision 2, Version8.
International Finance Corporation – World Bank Group. (April 2007). Environmental,
Health and Safety Guidelines for Electric Power Transmission and Distribution.
International Finance Corporation – World Bank Group. (April 2007). Environmental,
Health and Safety Guidelines for Wind Energy.
International Finance Corporation – World Bank Group. (April 2007). General
Environmental, Health and Safety Guidelines.
Mucina, L. & Rutherford, M.C. (eds) 2006. The Vegetation of South Africa, Lesotho and
Swaziland. Strelitzia 19. South African National Biodiversity Institute, Pretoria.
National Energy Regulator of South Africa (NERSA)(Feb.2010). Rules on selection
criteria for renewable energy projects under the REFIT Programme.
Saayman, I. (2005). Guideline for Involving Hydrogeologists in EIA Processes: Edition 1.
CSIR Report No ENV-S-C 2005 053 D. Republic of South Africa, Provincial Government of
the Western Cape, Department of Environmental Affairs and Development Planning, Cape
Town.