BANNER 9 PROJECT REPORT
FY 2017 - 2018
As of January 18, 2018
1 | P a g e
ContentsGeneral Information___________________________________________________________2
Summary of Banner 9 Tasks_____________________________________________________5
Human Resources____________________________________________________________6
Student_____________________________________________________________________7
Finance_____________________________________________________________________9
Accounts Receivable__________________________________________________________10
Financial Aid________________________________________________________________11
Communication Plan__________________________________________________________12
Training Plan________________________________________________________________13
Project Timeline_____________________________________________________________14
Project Risks________________________________________________________________15
Project Information (Governance)________________________________________________16
Version 2, last updated January 18, 2018
2 | P a g e
General Information
PROJECT PURPOSE (Why are we doing this?)
Banner 9 is a mandatory vendor upgrade, which must be in place by December 2018 in order to stay on Banner support and receive federal and state regulatory patches.
Ellucian, our Enterprise Resource Planning vendor for support of Human Resources, Finance, Student, Grants, Financial Aid, and Accounts Receivable, is replacing their suite of products with new technologies. Most changes represent a new look and feel to data entry forms. However, there are new applications that provide additional functionality. For example, the way students register for classes will be greatly improved.
This paper provides an overview of the new technologies and a high-level timeline by functional area for the implementation.
Version 2, last updated January 18, 2018
This is a mandatory
vendor upgrade.
Banner 8 will reach
end of life at year
end of 2018.
Admin Applications
Banner will have a new look and feel.Navigation is similar to a web-page.Forms will be referred to as pages.Banner form names will not change.Ability to find pages by description.
Streamlined Processes
Integration of Academic Plan with registration.Employees get a dashboard view.Enhanced communication options.Streamlined upgrades.Java problems dramatically reduced.Shopping Cart.
Navigation Improvements
ADA compliant.Mobile device friendly.Improved filtering options.Easier record searching.View multiple records at a time.Expand and collapse sections in a page.Better table extraction.Modern appearance.Customized branding.
3 | P a g e
Benefits of Banner 9 – Student Registration and Admin Pages
Version 2, last updated January 18, 2018
Allows students to register faster and easier using locked Degree Plans in Degree Works designed to integrate with Banner 9.
Degree Works Integration
Allows students and advisors to create planned registration schedules. Also integrates with Degree Works Student Educational Plan (SEP).
Registration Planning
Allows students to self-select the block of classes they wish to attend. Admin users no longer have to register students into blocks.
Block Registration
Leverages Curriculum Advising & Program Planning (CAPP) (or external API to another degree audit system) to generate a projected list of student courses for selection in the next registration term.
Projected Registration
Students are guided through the selection of classes based on their academic program requirements.
Structured Registration
4 | P a g e
Group 1 Applications
The Ellucian Banner 9 environment is comprised of three application groups.
Group 2 Admin Pages
Ellucian renamed Banner “forms” to Admin “pages.” Admin “pages” replacing Oracle “forms”.Pages are equivalent to forms in the Banner 8 environment.
The current plan is to complete Banner 9 implementation no later than 07/31/2018.
Overall timelines
All go-live dates are tentative to user acceptance and based on maturity of technology.
Group 3 Self-Service Applications
Self-Service Applications are equivalent to Banner Self-Service modules currently delivered through ACES.
New Self-Service Banner functionalities are delivered in specialized “lightweight” applications. Current Self-Service will remain functional until upgraded or replaced with new technology.
Version 2, last updated January 18, 2018
Improvements for student registration (integrates with Degree Works)Optional modules for different functional areasCan be installed a la cart
Group 1 Benefits
Same functionality as Banner FormsNavigation changes (modern look & feel)Mobile friendlyTablet friendly
Group 2 Benefits
Banner General Admin 04/29/2018Human Resources Admin 04/29/2018Student Admin 04/29/2018Banner Finance Admin 06/29/2018Banner Accounts Receivable Admin 07/31/2018Banner Financial Aid Admin 07/31/2018
Group 2Admin Pages
Group 1 applications
provide additional
functionality to
Banner.
Admin (Group 2)
pages are updated
Banner forms that
require staff training.
Mobile responsive.
Tablet friendly. Functional Area Launch Date
5 | P a g e
Summary of Banner 9 Tasks
Banner 9 Upgrade Tasks (In Process):
Version 2, last updated January 18, 2018
Determine scope for Banner 9 upgrade and what will be part of post-Banner 9 upgrade.Install and review Banner 9 Applications in test environment.Complete technical environment requirements (includes new hardware, new software and new skills).Develop Banner 9 upgrade test schedule.Build Banner 9 demo environment.Determine which modifications & customizations are candidates for re-baselining to Banner 9 as delivered.Determine upgrade timelines.Implement the Banner 9 test upgrade.Complete upgrades to latest available versions.
Technical
Establish upgrade organizational structure.Determine and establish upgrade teams.Review and utilize available Ellucian resources, including recordings, training workshops and documentation.Review the three groups that make up the Banner 9 upgrade.Determine functional areas needs.Send demo site invitations to campus groups.Training, including documentation and hands-on training.Functional area preparation for Banner 9 upgrade.
Functional
These tasks are in
process.
Banner 9 can be
introduced in steps
while the existing
ERP system is up
and running.
Steering Committee
Linda Boyer-OwensMichelle Wilson
Integration Team
Alicia ReyesCindy MunozErlinda YbarraAllen HimeJerry Botello
Project Sub-Team
Andrea ArenasGeena JohnsonMaria Limon-MontalvoAnnette Sanchez
6 | P a g e
Human Resources
Timeline
Month Task StatusResponsible Party
Sep 2017 Schedule online Admin Pages navigation training for Integration and Project teams. District IT &
Integration Team
Sep 2017 Admin Pages navigation training for Human Resource teams. District IT &
Integration Team
Sep 2017 Coordinate with Finance Process Functional Manager testing schedule. Integration Team
Sep – Oct 2017 Update training materials. Integration Team
Sep 2017 Communicate and provide test plans for project teams with deadlines. District IT &
Integration Team
Oct 2017 Begin Banner 8 patch testing and Banner 9 testing. District IT &
Integration Team
Oct 2017 Communication – schedules, setup in Alamo Learn. District IT &
Integration Team
Nov 2017 – Feb 2018
Banner 9 Human Resources Admin Pages training. Integration Team
Feb 2018 Begin Banner 8 patch testing and Banner 9 testing.
District IT & Integration Team
Apr 2018 User acceptance testing and sign off. Integration Team
April 29, 2018 Banner 9 Human Resources go-live. District IT & Integration Team
Version 2, last updated January 18, 2018
Improved usability, a modern look and feel.Seasoned users can continue to leverage their specific business rules.New users will have a more intuitive experience requiring less training.
Human Resources Admin Pages (Group 2)
Admin Pages have
the same business
rules and similar
shortcut keys, but
better navigation.
7 | P a g e
Student
Month Task Status Responsible Party
May 2017 Begin meeting with Banner 9 Steering Committee. Integration Team
Aug 2017 Banner 9 Overview Training for Center for Student Information (CSI) staff. District IT &
Integration Team
Aug 2017 Banner 9 Student "Sneak Peek" with functional users. District IT &
Integration Team
Aug 2017 Development of first draft of timeline for Banner 9 implementation. District IT &
Integration Team
Sep – Oct 2017 Update training materials. District IT & Integration Team
Sep 2017 Communicate and provide test plans for project teams with deadlines. District IT &
Integration Team
Oct 2017 Begin Banner 8 patch testing and Banner 9 testing. District IT &
Integration Team
Nov 2017 Communication – schedules, setup in Alamo Learn. District IT &
Integration Team
Jan 2018 College Super Users begin training on Student Admin pages with appropriate college staff. Steering Committee
Feb 2018 Determine pilot college and host Banner 9 Student Registration focus group.
District IT &Integration Team
Feb 2018 Begin Banner 8 patch testing and Banner 9 Admin Page testing.
District IT &Integration TeamProject Sub-Team
Apr 2018 Admin pages user acceptance testing and sign off. Integration Team
Apr 2018 Admin pages acceptance for production. Steering Committee
Version 2, last updated January 18, 2018
Fresh and improved user-interface.Enhances navigation with built-in industry-standard web controls.Consistency from page to page.Secure access for staff.
Banner Student Admin Pages (Group 2)
Registration Planning.Integrates with Degree Works.Block Registration and Projected Registration.Structured Registration.
Student Registration(Group 1)
8 | P a g e
Apr 2018 Begin Banner 9 Student Registration testing.District IT &
Integration TeamProject Sub-Team
Apr 2018 Banner 9 Student Registration user acceptance testing and sign off for pilot. Integration Team
TBD Banner 9 Student Registration acceptance for rollout to other campuses. Steering Committee
April 29, 2018 Banner 9 Admin Pages go-live. Steering Committee
TBD Banner 9 Registration rollout to all campuses. Steering Committee
Version 2, last updated January 18, 2018
Steering Committee
Dr. Cindy Mendiola-PerezDr. Liz GarzaDr. Christa Emig
Integration Team
Delia MurairaAngie GuillenSusan EspinozaAna GarciaLenny Arredondo
Project Sub-Team
Velia TovarRoxanne StratmannMyrella GonzalezJennifer ZamarippaEd DiazJonathon Marin
9 | P a g e
Finance Banner Finance Admin (Group 2)
Timeline
Month Task Status Responsible PartySep 2017 Demo Banner 9 Finance. District IT
Jan – Feb 2018 Review Admin (Group 2) Pages. Integration Team
Jan – Feb 2018 Review Finance background processes. Integration Team
Jan – Jun 2018 Develop Admin (Group 2) training. Integration Team
Jan – Jun 2018 Admin (Group 2) training. Integration Team
Feb 2018 Begin Banner 8 patch testing and Banner 9 testing.
District IT &Integration TeamProject Sub-Team
Apr 2018 Admin pages user acceptance testing and sign off. Integration Team
May 2018 Admin pages acceptance for production. Steering Committee
Jun – Jul 2018 Banner 9 Admin Pages go-live. Steering Committee
Version 2, last updated January 18, 2018
Offers improved usability, a modern look and feel.Easier accessibility of the Banner administrative experience.Seasoned users can continue to leverage their specific business rules.New users will have a more intuitive experience with less training.
Banner Finance Admin (Group 2)
Banner General Admin (Group 2)
Steering Committee
Gettie Moreno
Integration Team
Mark MartinezLinda GarzaGrace VillarealJose Rodriquez
Project Sub-Team
Rosa BertranAracely FloresMarvel BaileyRebecca CortezCecila MartinezAmy Guerra
10 | P a g e
Accounts Receivable
Timeline
Month Task Status Responsible PartyAug 2017 Demo Banner 9 Accounts Receivable. District IT
Nov – Dec 2017 Review admin (group 2) Pages. Integration Team
Nov – Dec 2017 Review Accounts Receivable background processes. Integration Team
Feb – April 2017 Develop Admin (Group 2) training. Integration Team
Jan – Jun 2018 Admin (Group 2) training. Integration Team
Feb 2018 Begin Banner 8 patch testing and Banner 9 testing.
District IT &Integration TeamProject Sub-Team
Feb – April 2018 Develop Admin (Group 2) training. Integration Team
Feb – Jun 2018 Admin (Group 2) training. Integration Team
Jun – July 2018 Admin pages user acceptance testing and sign off. Integration Team
Jun – July 2018 Admin pages acceptance for production. Steering Committee
Jun – July 2018 Banner 9 Accounts Receivable Admin Pages go-live. Steering Committee
Version 2, last updated January 18, 2018
Provides a full range of functions and data management.Record processing with a central repository for critical student information. Provides an integrated foundation for consolidating transactions and reporting.
Banner Accounts Receivable Admin Pages
(Group 2)
Steering Committee
Sue Swan
Integration Team
Aide Contreras
Project Sub-Team
Jennifer CastroCarmen MorinHelen BealerDaniel Rocha
11 | P a g e
Financial Aid
Timeline
Month Task Status Responsible PartyOct 2017 Move to test environment. District IT
Oct 2017 Demo Financial Aid Admin pages. District IT
Oct 2017 Review Financial Aid admin (group 2) pages. Integration Team
Oct 2017 – Jan 2018 Workflow updates. Integration Team
Nov – Dec 2017 Review Financial Aid background processes. Integration Team
Feb 2018 Develop admin pages (Group 1) training. Integration Team
Feb 2018 Begin Banner 8 patch testing and Banner 9 testing.
District IT &Integration TeamProject Sub-Team
Mar – Jun 2018 Admin (Group 2) training. Integration Team
Jun – July 2018 Admin pages user acceptance testing and sign off. Integration Team
Jun – July 2018 Admin pages acceptance for production. Steering Committee
Jun – July 2018 Banner 9 Financial Aid Admin Pages go-live. Steering Committee
Version 2, last updated January 18, 2018
Helps handle financial aid processes efficiently, quickly, and equitably, regardless of the source or type of aid.
Banner Financial Aid Admin Pages (Group 2)
Steering Committee
Michelle Hill
Integration Team
Jennifer Tamayo
Scheduling of sneak peek sessions .Promote Banner 9 Sneak
PeeksBegin Jul 2017
Super user & train-the-trainer workshops.
Workshop notifications & follow ups
Begin Aug 2017
Conduct training of campus and DSO end-users.
Banner training notifications
Begin Oct 2017
Public facing page from alamo.edu with FAQ's.
Banner 9 websiteJan 2017
Alerts to staff about Banner 9 availability per focus area.
Banner 9 go-live datesFeb- Aug 2018
Alerts to staff regarding Banner 8 discontinuation.
Banner 8 discontinuationMar-Nov 2018
12 | P a g e
Communication PlanObjectives
Practice effective communication strategies within Steering Committee and Banner 9 teams.
Monthly status reports to all governance teams.
Conduct “sneak peek” familiarization sessions for all DSO Banner 9 user groups.
Raise awareness of the Banner 9 upgrade across the Alamo Colleges communities—faculty, staff & students.
Post and publicize self-orientation & training resources
Send heads-up notices to user communities at each milestone in the transfer from Banner 8 to Banner 9.
Version 2, last updated January 18, 2018
Weekly & bi-weekly
meetings
Digital displays
www.alamo.edu
Alamo Share &
Alamo Talent
Email notifications
Steering Committee
Project Team
Integration Team
Sub-teams
Public Relations
Students Faculty
Staff
13 | P a g e
Training PlanObjectives• Deploy standardized and structured model for training program and supplemental material
development.
• Illustrate similarities and changes between Banner 8 and Banner 9 navigation.
• Familiarize users with the benefits of Banner 9.
• Roll out a train-the-trainer plan to educate faculty, staff, and students.
Version 2, last updated January 18, 2018
Facilitate
opportunities for
collaboration.
Leverage
engagement for
training and
development.
Use Alamo Share as
a repository for
Banner 9 information.
Use Alamo Talent to
deliver series of
Banner 9 training
offerings.
14 | P a g e
Project Timeline
Version 2, last updated January 18, 2018
15 | P a g e
Project Risks
Project teams will work closely with district functional areas and leads to calculate the amount of training necessary for success with this project.
Employee understanding of the new Banner 9 interfaces is key to this project and vendor admin pages performance as expected.
Product Maturity Solution maturity.
Competing projects.
Allocation of Resources• Additional functional area resources must be committed to the Banner 9 project.• Resources must be monitored to make sure we have enough labor to complete the
project.• Adequate training and timely transfer of knowledge must be included in the project plan.
Portal or Entry Point Access• Single Sign-On (SSO) access from the new applications.
Self-Service Customizations• External support to third party applications.• Self-Service Banner modification support.
Budget / Resources (Can we find the right people?)• Department training.• Outside consulting support.
Risk Mitigation• Information Systems and all functional areas will closely monitor this project to make
sure it stays on track.
• The legacy Banner forms and Student Self-Service portal will remain open until functional areas are fully trained and comfortable with the new technologies.
Version 2, last updated January 18, 2018
Banner 9 Risks
16 | P a g e
Project Information (Governance)Roles and Responsibilities
Steering Committee The Project Steering Committee/Executive Committee provides leadership at the administrative level for the Banner 9 Upgrade.
Integration Team The integration team is comprised of leads from each of the Project Sub-teams and provides leadership at the functional level for the Banner 9 Upgrade.
Project Management Team The Project Manager leads the Project Management Team, serves as the Chair of the Integration Team and sits on the Project Steering Committee.
Project Sub-Teams Project Sub-teams will be established for each Banner Lightweight Application to be implemented, and may be established as needed for functionality. The lead for each Sub-team is a member of the Integration Team. Sub-team membership consists of staff from related functional areas with expertise in the functionality being implemented.
Communication The Steering Committee will meet as needed, but not less than monthly.
Version 2, last updated January 18, 2018
Champions of ChangeLeadership
Resources
Support
Technical ExpertiseTesting
Collaboration
Training
CoordinationCommunication
Structure
17 | P a g e
Project Steering Committee
Integration Team (including but not limited to the following)
Version 2, last updated January 18, 2018
Champions of
Change
Leadership
Resources
Support
Technical Expertise
Testing
Collaboration
Training
Coordination
Communication
Structure
Name Functional AreaDr. Liz Garza Student Success
Linda Boyer-Owens Human Resources
Alicia Reyes, Backup Human ResourcesMichelle Wilson, Backup Human Resources
Gettie Moreno Finance
Dr. Christa Emig Academic Success
Sue Swan Accounts Receivable
Roger Castro Information Technology
Rick Fletcher Information Technology
Lucy Odell Information Technology
18 | P a g e
Project Management Team (including but not limited to the following)
Version 2, last updated January 18, 2018
CoordinationCommunication
Structure
Name Functional Area
Jill Weston State Reporting
Delia Muraira (Lead) Student
Angie Guillen Student
Susan Espinoza-Vargas Student
Ana Garcia Student Success
Aide Contreras Finance
Mark Martinez (Lead) Finance
Jose Rodriquez Finance
Grace Villarreal Finance
Linda Garza Finance
Carol Aguirre Information Technology
Elvira Smolik Information Technology
Jennifer Burciaga Information Technology
Vanessa Garza Information Technology
Peter Van Dusen Information Technology
Hector Hernandez Information Technology
Kin Ho Information Technology
Alicia Reyes (Lead) Human Resources
Erlinda Ybarra Human Resources
Allen Hime Human Resources
Jerry Botello Human Resources
Jennifer Tamayo (Lead) Financial Aid
Michelle Hill (Lead) Financial Aid
Lenny Arredondo Student
Cheryl Drake Information Technology
Patty Clark Information Technology
Name Functional Area
Rick Fletcher Information Technology
Lucy Odell Information Technology
Peter Van Dusen Information Technology
Cindy Munoz Human Resources
Jennifer Tamayo (Lead) Financial Aid
Michelle Hill (Lead) Financial Aid
19 | P a g e
Project Sub-Team (including but not limited to the following)
Version 2, last updated January 18, 2018
Name Functional Area
Velia Tovar Student
Roxanne Stratmann Student
Myrella Gonzalez Student
Jennifer Zamarripa Student
Ed Diaz Student
Lenny Arredondo Student
Jonathon Marin Student
Andrea Arenas (Lead) Human Resources
Geena Johnson Human Resources
Maria Limon-Montalvo Human Resources
Annette Sanchez Human Resources
Jennifer Castro Accounts Receivable
Carmen Morin Accounts Receivable
Helen Bealer Accounts Receivable
Daniel Rocha Accounts Receivable
Rosa Bertran Finance
Aracely Flores Finance
Marvel Bailey Finance
Rebecca Cortez Finance
Cecilia Martinez Finance
Amy Guerra Finance
20 | P a g e
811 W. Houston San Antonio, Texas 78207Tel 210-485-0400www.alamo.edu
Content Note:
Special thanks to Truman University and Ellucian for content added to this document.
Version 2, last updated January 18, 2018
Roger CastroDistrict Director Information TechnologyTel 210-485-0027Email [email protected]
Rick FletcherSenior Manager, Applications & SystemsTel [email protected]
Lucy OdellSenior Manager, IT Projects OfficeTel 210-485-0503Email [email protected]