Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
© ABB Inc. June 6, 2011 | Slide 1
AWEA Windpower 2011
Wind Turbine Grid Integration Challenge
© ABB Inc. June 6, 2011 | Slide 2
Speaker name: Slavomir Seman Speaker title: Design manager - Simulations, Grid codes Company name: ABB, Drives, Wind AC
In booth theater presentationsWind Turbine Grid Integration Challenge
© ABB Inc. June 6, 2011 | Slide 3
Grid Integration Challenges
# 1: Grid integration requirements – What, Where and How ?
# 2: Fault Ride Through (FRT) – How to support the grid during fault conditions
# 3: Quick Response - Fast acting voltage control and reactive current during fault
# 4: Advanced simulation models – Important tool for compliance validation
# 5: Series compensated lines & DFIG wind farm
© ABB Inc. June 6, 2011 | Slide 4
Grid Integration Challenge #1What are the requirements? Requirements of the local grid codes are different between countries/regions.
Today's grid codes are very diverse and contain many technical “gray areas” (historicalreasons, new generation).
Common specification language, as required for global standardization, does not exist.
Grid codes are continually changing.
EXAMPLE Germany (11 Grid codes and guidelines):
© ABB Group June 6, 2011 | Slide 5
Where to Comply Defines what the performance requirement is
for power plants connected to power system Grid code reflects the structure and status of
transmission system The content of grid code depends on the
region US FERC Order 661 E.ON 2006, German R.E.E 12.3. Spain
Wind park
POINT OF COMMON COUPLING (PCC)
132 kV/20kV 20kV/690V
WTGrid
ZWP
WT Connection point
Wind turbineWind park
POINT OF COMMON COUPLING (PCC)
132 kV/20kV 20kV/690V
WTGrid
ZWP
WT Connection point
Wind turbine
Usually defined at PPC
Grid Integration Challenge #1
© ABB Inc. June 6, 2011 | Slide 6
Grid Integration Challenge #1How to validate compliance Type test of a single wind turbine – typically performed by so-called “container test”.
Wind power plant compliance assessment – performed by simulation.
Tester
Photo: E2Q
© ABB Inc. June 6, 2011 | Slide 7
Challenge #2: Fault Ride Through (FRT)
Typical FRT curve - not full consistency on how FRT profiles are to be understood and applied
Source: IEEE power and energy magazine November/December 2007
Source: European Grid Code Development – the Road towards Structural Harmonization Workshop on Integration of Wind Power, Québec/Canada, October 2010
FERC Order 661- LVRT requirements defined at HVside of the plant step-up TR. Wind generation facilityremains online during:
3-phase fault with normal clearing
1-phase to ground fault with delayed clearing
© ABB Inc. June 6, 2011 | Slide 8
Challenge #2: FRT – Example of Dynamic Performance
4900 5000 5100 5200 5300 5400 5500 56000
50
100
150
200
250
300
350
400
450
500
Time [ms]
Urms
[V]
MEASURED INSTANTANEOUS VALUES AT LV SIDE OF TR
uurmsgrid [V]
uvrmsgrid [V]
uwrmsgrid [V]
FRT 0% Un, 180 ms – DFIG ( Type 3) - LV side FRT 0% Un, 500 ms – Full Converter ( Type 4) – MV/LV side
© ABB Inc. June 6, 2011 | Slide 9
Challenge #3: Quick Response to Grid Faults/Voltage Support
Reactive Current (<100%In) injected within 30 ms during ZVRT
© ABB Inc. June 6, 2011 | Slide 10
FRT – Converter Supports Wind Turbine
© ABB Inc. June 6, 2011 | Slide 11
Challenge #4: Advanced Simulation Models
test.v_wind
v_wind
v_wind
Pref_max
dip_flag
ext_dip_flag
Tel
Uabc_lg_grid
flux_ref
Pref_dyn
Cselect
Uac-Q_ref
n_gen
Wind Turbine rev1_1(Aero+mech+wtc)
Scope20
RT
RT
test.Pref_max
Pref_max
Tel
Pref _dy n
n_gen
Tel_out
Initialization/Tel
flux_ref
Pref_dyn
Cselect
Uac-Q_ref
n_gen
Uabc_lg_grid
dip_flag
ext_dip_flag
Tel
Grid+Trafo+Conv+Gen
Generator/Converter model
Electrical Control Model
Q
P
Generic model “open source” (RMS) of WT 4 type model – Full power converterDetailed model “black box” (EMT) of WT 4
type model – Full power converter
© ABB Inc. June 6, 2011 | Slide 12
Challenge #4: Advanced Simulation Models – Validation
WT 4 model against full power test - 2,5 MW, Full converter under 3-ph dip , Generic model Ts = 5 ms
CONVERTER CTRL
MCB CTRL
WIND TURBINE CTRL
LCL=~
ISU
=~INU
WIND TURBINE CONVERTER
MAIN DISTRIBUTION TRANSFORMER FOR ABB (TKPmE M4)
MCB MCB
ABB’S TEST LABORATORY POINT OF MV CONNECTION (ASA21)
MCB
CBC
BMC
CBC
SDC
CONVERTER CTRL
MCB CTRL
LCL=~
ISU
=~INU
LOAD DRIVE CONTROL
MCB SDC
CBC
ABB’S VOLTAGE DEVIDERS
SUPPLY TRANSFORMER FOR EUT (TK29)
MCB
Z2
Z1
IG, DFIG or PMSG
INDUCTION GENERATOR
EQUIPMENT UNDER TEST
© ABB Inc. June 6, 2011 | Slide 13
0
200000
400000
600000
800000
1000000
1200000
1400000
-1000
-500
0
500
1000
1500
2000
2500
7000 7500 8000 8500 9000 9500 10000
Volt
Activ
e an
d re
activ
e po
wer
(sca
led)
time (ms)
Active Power
Reactive Power
Grid rms voltage
Challenge #5: Series compensated lines & DFIG wind farm
Voltage dip, 55 % compensated line, RSC about 1.6 at the point of connection
Stable!