STUDY ON REPAIR AND MAINTENANCE OF LPG STORAGE BULLET

PROJECT GUIDES TEAM MEMBERS

INTERNAL GUIDE

Mr.S.KANNAN, M.E., (Ph.D),ASSOCIATE PROFESSOR,

AVC COLLEGE OF ENGG.

EXTERNAL GUIDE

Mr.S.DEEPAK,B.Tech,(MAINT/PLANNING-PROJECTS),

CPCL PANNANGUDI.

M.ANAND (80107144005)

P.SENTHILKUMAR (80107144045)

S.SUDHARSANAN (80107144048)

G.PRABHU (80107144504)FINAL MECHANICAL

April 19, 20232

Page 3: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

OBJECTIVE

To study about the Maintenance and Repair of the LPG bullets in Chennai Petroleum Corporation Ltd (CPCL).

To make recommendations for the recurring problem.

April 19, 20233

Page 4: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

BULLET

Bullet is a LPG storage unit used in the oil refinery Industries.

It is look like in the shape of diesel or petrol tankers in the lorries.

April 19, 20234

Page 5: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

LPG STORAGE BULLET

April 19, 20235

Page 6: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

BULLET SPECIFICATIONS

Diameter : 4m

Length : 16m

Wall Thickness : 28 mm to 32 mm

Material : SA 516 Gr70(high quality

carbon steel)

Design code : ASME sec 8 div1-1989

Operating temp : 450c Hydrostatic pressure : 22.5 Kg/cm2April 19, 20236

Page 7: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

2D VIEW OF LPG STORAGE BULLET

April 19, 20237

Page 8: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

BULLET DIAGRAMS

April 19, 20238

Page 9: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

SECTIONAL VIEW OF THE BULLET

April 19, 20239

Page 10: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

BULLET MATERIALMATERIAL SA 516 GR 70

It is a high quality carbon steel plate for boiler and pressure vessel.

Carbon : 0.27-0.31% Manganese : 0.79-1.3% Phosphorous : 0.035%max Sulphur : 0.035%max Silicon : 0.13-0.45%

April 19, 202310

Page 11: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

Maintenance methodology (Existing)

De commissioning Erection of scaffolding Cleaning inside the bullet for NDT tests Ultrasonic Flaw Detection Testing Ultrasonic thickness measurement Hardness testing Spot Radiography tests Cleaning outside the bullet for NDT tests Nozzle replacement Stress relieving process Hydro testing of bullets Box up the nozzles

April 19, 202311

Page 12: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

After studying about the existing maintenance methodology the frequently faced problems were found out.

April 19, 202312

Page 13: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

PROBLEMS FACED:

It was observed that shell external, shell nozzles, nozzles flanges were found heavily corroded.

Therefore nozzles and nozzle flanges were replaced with approval from Chief controller of Explosives, Nagpur.

Maintenance cost was increased due to replacement of nozzles.

Downtime is also increased.April 19, 202313

Page 14: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

RECOMMENDATION

Insulation to be provided and aluminium sheet to be covered over the insulation (or) to reduce the external corrosion around the bullet every year it should be painted.

April 19, 202314

Page 15: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

April 19, 202315

Page 16: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

April 19, 202316

Page 17: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

April 19, 202317

Page 18: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

Existing maintenance cost

For 40 years (the life time of the plant)

Total maintenance action – 8 timesTotal maintenance cost – 2 croresi.e.8times X 25 lakhs = 2 crores.

April 19, 202318

Page 19: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

According to our recommendations

Total cost for insulation material with Aluminium cover plate Rs.100000.

Total cost for water sealing compounds with shed arrangement is Rs.20000.

(including labour cost)

April 19, 202319

Page 20: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

LIFE TIME OF THE BULLET AND SAVING COST NOZZLES. By providing the insulation with Aluminium cover

plate we can increase the life from 5 years to 8 years.

The capacity of the plant is 40 years.

i.e. for 8 times X 5 years = 2 crores. (25 lakhs per time)

for 5 times X 8 years = 1.25 crores. (25 lakhs per time)

So that the maintenance cost is reduced up to 75 lakhs

April 19, 202320

Page 21: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

For providing Aluminium plate covering with insulation

April 19, 202321

Page 22: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

By providing the water sealing compounds with the shed type arrangement we can increase the life time of the nozzle form 5 to 6 years.

The capacity of the plant is 40 years.

i.e. for 8 times X 5 years = 2 crores. (25 lakhs per time)

for 7 times X 8 years = 1.75 crores. (25 lakhs per time)

So that the maintenance cost is reduced up to 25 lakhs (approximately.)

April 19, 202322

Page 23: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

For providing water sealing compound

April 19, 202323

Page 24: AVC COLLEGE OF ENGINEERING MANNAMPANDAL MAYILADUTHURAI REVIEW 2 3 September 20151

ADVANTAGES Maintenance cost is reduced. Life time of the nozzle is increased. Downtime is also decreased. It is one of the method to avoid the major LPG

tank accident

April 19, 202324