Aupl Bbp Draft v2 0

Embed Size (px)

Citation preview

  • 8/13/2019 Aupl Bbp Draft v2 0

    1/45

    Business Blue Print Document

    Submitted to

    Aichelin Unitherm Heat Treatment Systems India

    Pvt. Ltd. (AUPL)

    By

    Praxis Info Solutions Pvt. Ltd.

    Version 1.1

  • 8/13/2019 Aupl Bbp Draft v2 0

    2/45

    AUPL

    Business Blueprint Document Confidential Page 2 of 45

    Table of Contents

    1. Executive Summary ................................................................................................................... 4

    2. Set-up of Basic Data and Parameters ......................................................................................... 5

    2.1 Master Data ....................................................................................................................... 5

    2.1.1 Item Master ............................................................................................................... 5

    2.1.2 Bill of Material ............................................................................................................ 5

    2.1.3 Vendor Master ........................................................................................................... 5

    2.1.4 Customer Master........................................................................................................ 5

    2.1.5 Chart of Accounts ....................................................................................................... 5

    2.1.6 Quality Plans .............................................................................................................. 5

    3. Main Process - Sales .................................................................................................................. 6

    3.1 Sales Overall Process Flow Chart ..................................................................................... 6

    3.2 Sub Process - Enquiry ......................................................................................................... 7

    3.3 Sub Process Quotations ................................................................................................... 7

    3.4 Sub Process Negotiations with customers........................................................................ 8

    3.5 Sub Process - Sales Order ................................................................................................... 8

    3.6 Sub Process Delivery...................................................................................................... 10

    3.7 Sub Process Invoice ....................................................................................................... 10

    3.8 Sub Process Erection and Commissioning ...................................................................... 11

    3.9 Sub Process After Sales Service ...................................................................................... 11

    4. Main Process - Planning ........................................................................................................... 12

    4.1 Planning Overall Process Flow Chart .............................................................................. 12

    4.2 Process Mapping .............................................................................................................. 13

    5. Main Process Purchase ......................................................................................................... 15

    5.1 Purchase Overall Process Chart ..................................................................................... 15

    5.2 Domestic Purchase Process Flow Chart .......................................................................... 16

    5.3 Import Purchase Process Flow Chart .............................................................................. 17

    5.4 Sub Process Indent for Materials ................................................................................... 18

    5.5 Sub Process Floating Enquiries for proposals ................... ....................................... ....... 18

    5.6 Sub Process Quotations ................................................................................................. 18

    5.7 Sub Process Purchase Order (All scenarios)........... ..................... ........ ....... ..................... 18

    6. Main Process - Production ....................................................................................................... 21

    6.1 Production Overall Process Flow Chart .......................................................................... 21

  • 8/13/2019 Aupl Bbp Draft v2 0

    3/45

    AUPL

    Business Blueprint Document Confidential Page 3 of 45

    6.2 Process Mapping Production ......................................................................................... 21

    7. Main Process Stores and Inventory Management.................................................................. 25

    7.1 Stores Process Flow Chart ............................................................................................. 25

    7.2 Sub Process Good Receipt against PO ............................................................................ 25

    7.3 Sub Process Goods Issue for Production Order .............................................................. 26

    7.4 Sub Process Goods Return from Production .................................................................. 27

    7.5 Sub Process - Goods Returned to vendor .......................................................................... 27

    7.6 Sub Process Sub Contracting Material ........................................................................... 27

    7.7 Sub Process - Miscellaneous Receipts and Issues ................... ........ ....... ..................... ....... 28

    7.8 Sub Process - Customer Supplied Material .............. ............................................... .......... 28

    8. Main Process - Quality Management ....................................................................................... 29

    8.1 Quality Management Overall Process Flow Chart .......................... ....... ............... .......... 29

    8.2 Sub Process Inward Material Inspection .......................................................... .............. 30

    8.3 Sub Process QA in Production ........................................................................................ 31

    8.4 Sub Process Outdoor Inspection .................................................................................... 31

    8.5 Sub Process Material Returned from Site.............. ............................................... .......... 32

    8.6 Sub Process Material Transferred to another Job...... ..................... ....... ...................... ... 32

    9. Main Process Commercial Cell .............................................................................................. 33

    9.1 Commercial Cell - Overall Process Flow Chart .............. ....... .............................................. 33

    9.2 Commercial Cell - Process Mapping .................................................................................. 33

    10. Main Process Accounts...................................................................................................... 36

    11. Main Process Design ......................................................................................................... 40

    11.1 Design Process Flow Chart ............................................................................................. 40

    11.2 Process Mapping - Design................................................................................................. 41

    12. Main Process HRMS .......................................................................................................... 42

    12.1 HRMS Reports ............................................................................................................... 43

    13. Main Process Payroll ......................................................................................................... 45

  • 8/13/2019 Aupl Bbp Draft v2 0

    4/45

    AUPL

    Business Blueprint Document Confidential Page 4 of 45

    1. Executive Summary

    The purpose of this document is to capture the process flow in detail for various functions. At the

    same time, an attempt has been made to map the process with functionalities in the software

    application (whether it is SAP B1, or Payroll or HRMS). This document is expected to serve as the

    guideline for this implementation project.

  • 8/13/2019 Aupl Bbp Draft v2 0

    5/45

    AUPL

    Business Blueprint Document Confidential Page 5 of 45

    2. Set-up of Basic Data and Parameters

    2.1 Master Data

    2.1.1 Item Master

    Item master is the fundamental element of this system. Hence, it is important that this data be

    created with maximum attention to detail and accuracy. An excel template will be provided for

    capturing this data. In addition to this, a guideline document for item master has also been provided.

    2.1.2 Bill of Material

    Bill of material is created using the item master data. An excel template will be provided for

    capturing this data.

    2.1.3 Vendor MasterThis data is required to maintain all transactions with vendors. An excel template will be provided for

    capturing this data.

    2.1.4 Customer Master

    This data is required to maintain all transactions with customers. An excel template will be provided

    for capturing this data.

    2.1.5 Chart of Accounts

    This is essentially a listing of all ledger accounts duly grouped under headings that are required in

    the balance sheet or P&L. An excel template will be provided for the same.

    2.1.6 Quality PlansThis will be required for Quality plans to be defined for QA transactions.

  • 8/13/2019 Aupl Bbp Draft v2 0

    6/45

    AUPL

    Business Blueprint Document Confidential Page 6 of 45

    3. Main Process - Sales

    3.1 Sales Overall Process Flow Chart

    Following are the broad steps involved in sales process.

    1. Enquiry2. Quotation3. Negotiations (Manual, outside SAP)4. Customer Order5. Delivery6. Invoice7. Installation and commissioning8. After Sales Service

  • 8/13/2019 Aupl Bbp Draft v2 0

    7/45

    AUPL

    Business Blueprint Document Confidential Page 7 of 45

    3.2 Sub Process - Enquiry

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Capturing Sales

    enquiries

    Opportunity Management Numbering will be done as per SAP

    Standard

    2 Capturing

    activities in

    relation to the

    enquiry

    Activity Tracking functionality

    will be used

    Variety of activities can be created and

    assigned, with reminders

    3 Updating

    enquiry status

    Each opportunity can be

    updated with the relevant

    down-stream document

    created in the system

    For E.g. Sales Quotation created for an

    opportunity can be updated in the

    Opportunity in Stages tab

    4 List of enquiries This will be made available

    through Opportunity Reporting

    5 Segregation of

    enquiries based

    on Main

    Equipment or

    Spares,

    Service

    This will be achieved by using

    an identifier in the Opportunity

    Report will be built to deliver the

    segregation. Various mappings

    provided by AUPL will be referred

    while generating these reports (like

    state-zone etc.)

    6 Additional

    Header level

    parameters like

    North, East,

    West, South,

    Export

    Based on the reporting formats

    required we need to capture

    the fields during Enquiry

    3.3 Sub Process QuotationsSL

    NO

    Description Mapping in SAP B1 Remarks

    1 Creating Quotations Quotation Functionality

    2 Quotations need to be

    segregated based on region,

    This will be achieved using a

    combination of numbering series,

    AUPL needs to

    finalize item code

  • 8/13/2019 Aupl Bbp Draft v2 0

    8/45

    AUPL

    Business Blueprint Document Confidential Page 8 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    Year and type of item (Main

    Equipment or Spares)quoted

    identifier fields and reporting

    capabilities

    creation process for

    Quotation process

    3 Capturing activities in

    relation to the quotation

    Activity Tracking functionality will be

    used

    Variety of activities

    can be created and

    assigned, with

    reminders

    4 Budgetary Quotations need

    to be marked separately

    This will be explored with the usage of

    an identifier field

    5 Quotation Printout Main quotation document that has all

    technical details etc. will continue to be

    done in word format. SAP will capture

    only the commercial part (price,

    payment terms etc.).

    6 Revisions to Quotations Existing quotation can be edited and

    changes can be done. System will show

    the latest version of the document by

    default.

    Note: Revisions are not maintained if

    the we activate the Quotation approvalprocess in SAP

    3.4 Sub Process Negotiations with customers

    This activity will be done as a normal business process, without any active entries/updates in the SAP

    system, except the ones related to making modifications to the quotations, which is already covered

    earlier.

    3.5 Sub Process - Sales Order

    SLNO

    Description Mapping in SAP B1 Remarks

    1 Entry of

    customer PO

    Sales Order functionality will be used. Currently,

    sales orders are classified as follows

    Main Equipment Spares Erection and Commissioning

    AUPL will revert with a

    check list for SO

    creation. This will

    enable setting up

    variety of checks at the

  • 8/13/2019 Aupl Bbp Draft v2 0

    9/45

    AUPL

    Business Blueprint Document Confidential Page 9 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    Repair & Services

    AMC Free Supply

    time of SO creation.

    2 Order

    Acceptance

    Once the pre-requisite steps are carried out

    manually outside of SAP, user can generate an

    order acceptance documents from SAP system..

    OA document will be

    printed based on the

    sales order entered in

    the system

    3 Changes to

    orders by

    customer

    If customer makes a small change then the same

    can be reflected in the existing Sales Order

    document if the sales order is not closed.

    If customer makes a major amendment to the

    order leading to additional supplies and if the

    original sales order is closed then user will have to

    create a new sales order and while doing so, user

    has to maintain the same customer reference

    number if applicable.

    If customer releases a new order and cancels old

    one, then user will have to create a new sales order

    and cancel the one that was previously created.

    4 Alerts Once the Sales order is created, system would sendthe following alerts

    - In case of advance alert to Commercial toraise Pro-forma invoice

    - Planning and design for information5 Additional

    Documents

    Additional documents related to Sales order like

    Estimation, customer drawing and other

    documents relevant to Sales order will be stored as

    attachment

    6 Approval for

    Sales Order

    This can be set-up. AUPL needs to finalize the

    approval hierarchy and rules (within the framework

    of SAP B1 Users in the system)

    Praxis recommendation Do not activate approval

    process for Sales Order as there will be changes

    (Technical and / or commercial) after order

    *Please note once we

    activate the Sales Order

    approval process,

    approved sales order

    cannot be changed

  • 8/13/2019 Aupl Bbp Draft v2 0

    10/45

    AUPL

    Business Blueprint Document Confidential Page 10 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    finalization.

    3.6 Sub Process Delivery

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Dispatch of

    items

    Delivery functionality will be used. Once the item is available in

    stock, a delivery can be created with respect to the sales order.

    Outgoing excise invoice will be created with respect to thisdelivery document for Excise related effects.

    3.7 Sub Process Invoice

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Proforma

    Invoices

    There is no out of the box mapping for

    this requirement. Sales Order

    functionality with some tweaking is likely

    to be used for this process.

    2 Final invoice AR invoice feature will be used for this

    process. Invoice formats will be mapped

    for

    Domestic Material and Service Export Material and Service

    Different numbering series will be

    maintained for Excise Invoices and non-

    Excise Invoices.

    AUPL to revert with printable

    formats indicating the different

    pieces of information that needs

    to be printed.

    The earlier these inputs are given,

    lesser will be the impact (or

    rework) on dependent masterdata like customer master, item

    master etc.

    4 Approval for

    invoice

    This can be set-up. AUPL needs to finalize

    the approval hierarchy and rules (within

    the framework of SAP B1 Users in the

  • 8/13/2019 Aupl Bbp Draft v2 0

    11/45

  • 8/13/2019 Aupl Bbp Draft v2 0

    12/45

    AUPL

    Business Blueprint Document Confidential Page 12 of 45

    4. Main Process - Planning

    4.1 Planning Overall Process Flow Chart

  • 8/13/2019 Aupl Bbp Draft v2 0

    13/45

    AUPL

    Business Blueprint Document Confidential Page 13 of 45

    4.2 Process Mapping

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Ability to viewcustomer order

    specifications

    Sales Order document in SAP willprovide all necessary information

    needed

    2 Iterative

    planning

    This will be done using MRP

    functionality.

    Care needs to be taken to ensure

    that all open documents against

    which no further supplies (or

    production for in-house activities)

    are expected are closed before

    running the MRP.

    There are several otherparameters that need to be

    maintained accurately in item

    master for the MRP to suggest

    realistic options.

    Also, MRP run should be

    performed by limited number of

    MRP- educated users, who can

    interpret MRP output accurately.

    3 Parameters in

    item master

    There are several parameters in the

    item master that need to be

    maintained as accurately as possible,

    so that MRP can give realistic results.

    E.g. Minimum, Maximum stock levels,

    lead time, Buy or Make etc.

    4 Indenting of

    material

    Items in BOM need not be indented

    since proposals will be made by the

    system automatically. These

    proposals will be for purchase orders

    or production orders.

    5 Checking stocks Variety of reports are available in the

    system that can be used for this

    purpose

    6 Planned cost Planned cost (only material) of items

    can be maintained in the BOM that

    will be created by Design

    Actual material cost will be

    managed in the system based on

    the items that are actually issued

  • 8/13/2019 Aupl Bbp Draft v2 0

    14/45

    AUPL

    Business Blueprint Document Confidential Page 14 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    department. towards any production order

    7 Decision about

    sub contracting

    This decision depends on several

    factors and dynamic variables.

    This process will have to be

    handled outside of SAP.

    In case there is a change in the

    Design BoM and production BoM,

    User will change the BoM

    accordingly to accommodate the

    requirements.

    8 Actual cost

    booked towards

    any project

    Project wise P&L can be generated

    from the system.

    However, this report is accessible

    only to accounts/ professional

    users.

  • 8/13/2019 Aupl Bbp Draft v2 0

    15/45

    5. Main Process Purchase5.1 Purchase Overall Process Chart

  • 8/13/2019 Aupl Bbp Draft v2 0

    16/45

    5.2 Domestic Purchase Process Flow Chart

  • 8/13/2019 Aupl Bbp Draft v2 0

    17/45

    AUPL

    Business Blueprint Document Confidential Page 17 of 45

    5.3 Import Purchase Process Flow Chart

    Following are the broad steps involved in purchase process.

    1. Indent for materials2. Float Enquiries3. Receive Quotations4. Negotiation/Comparison5. Vendor registration, if new6. Release PO7. Call for inspection8. QC Inspection and clearance9. Call to accounts for payment10.Give clearance to supplier to dispatch11.Receive goods12.Payment

  • 8/13/2019 Aupl Bbp Draft v2 0

    18/45

    AUPL

    Business Blueprint Document Confidential Page 18 of 45

    5.4 Sub Process Indent for Materials

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Indent formaterials

    Requirements for items that are included in BOM will begenerated by the system after running MRP. No separate indent is

    needed.

    MRP will propose the recommendations for generating either

    Purchase Order (for items that are marked as Buy in item master)

    or production order (for items that are marked as Make in item

    maser)

    Buyer/Planner will take a final call and accept/modify the

    recommendations of MRP.

    Upon acceptance, system will create Purchase Orders.

    2 Indent for

    materials

    For items that are not covered in BOM, Purchase Requisitions

    need to be created in the system

    5.5 Sub Process Floating Enquiries for proposals

    This process will be handled outside of SAP System.

    5.6 Sub Process Quotations

    SLNO

    Description Mapping in SAP B1 Remarks

    1 Quotation entry Purchase Quotation functionality can be used for this

    2 Comparison of

    Quotations

    Quotations submitted by different vendors can be

    compared in the system

    5.7 Sub Process Purchase Order (All scenarios)

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Purchase Order Purchase Order functionality will be used

    2 Tax structure,

    freight

    Quotations

    These can be entered in the PO

  • 8/13/2019 Aupl Bbp Draft v2 0

    19/45

    AUPL

    Business Blueprint Document Confidential Page 19 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    3 Terms of

    Payment (ToP)

    ToP gets defaulted based on the vendor

    master. However user can change this at thePO stage

    4 Standard Terms

    and conditions

    Standard T&C can be created at pre-defined

    texts and can be copied into every purchase

    order

    5 Follow up

    activities for PO

    Activity Tracking functionality will be used Variety of activities can be

    created and assigned, with

    reminders

    6 PO for Sub

    contracting

    PO will be raised for labor charges (Service PO

    in SAP)

    Material will be sent to the

    processor with respect to

    this PO using the Sub

    Contracting Module.

    7 Call for

    Inspection alerts

    This will be used primarily in Sub-contracting

    POs. Provision will be made at the PO header

    level where user can enter Call for

    Inspection dates for

    1. RM inspection2. Tag-Weld Inspection3. Final Inspection

    Daily alert will be

    generated for calls for

    inspection that are due in

    next 8 days (with reference

    to the dates entered for

    these three stages)

    8 PO for capital

    goods

    General process of creating PO will remain

    the same as normal PO

    There may be some additional identifiers that

    need to be populated if the PO is for capital

    goods

    9 PO for imports General process of creating PO will remain

    the same as normal PO.

    There may be some additional identifiers thatneed to be populated if the PO is for imports

    Provision will be made for following

    1. OA received?2. Committed deliver date

    If committed delivery date is beyond the

    Alert will be generated

    every day, which will

    identify all such Pos, where

    delivery is due in next 10

    days (as per the

    requirement date

    mentioned in the PO

    header).

    This alert will be sent to

    Buyer and commercial

  • 8/13/2019 Aupl Bbp Draft v2 0

    20/45

  • 8/13/2019 Aupl Bbp Draft v2 0

    21/45

    AUPL

    Business Blueprint Document Confidential Page 21 of 45

    6. Main Process - Production

    6.1 Production Overall Process Flow Chart

    6.2 Process Mapping Production

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Ability to viewcustomer order

    specifications

    Sales Order document in SAPwill provide all necessary

    information needed

    2 Project wise

    micro planning

    This will be in the form of

    creating production orders

    (items to be produced, there

    quantities, dates of delivery)

    Stocks can be checked for all child items for

    any stage based on the BOM.

    In addition to this, there are several other

    reports in inventory management module

  • 8/13/2019 Aupl Bbp Draft v2 0

    22/45

    AUPL

    Business Blueprint Document Confidential Page 22 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    for various sub-assemblies

    or stages

    that will assist the planning department in

    making their decisions.

    3 Material

    availability for

    an order

    When the user views the

    production order and refers

    to the bill of material,

    system also shows current

    stock of that item.

    In addition a report will be generated that

    will list out the position of various items

    needed to complete that production order

    4 Production Production order

    functionality will be used.

    Whenever a production

    order is created, system will

    copy the bill of material

    (from master data), into the

    production order.

    Any further changes that

    may happen to the bill of

    material have to be made

    directly in the production

    order, if the change is very

    specific to that order.

    5 Drawing

    availability

    Design department will

    upload the drawing files for

    each item whether it is

    Finished Goods, Sub-

    Assemblies, Sub-

    Components or Parts i.e

    Sub-components and Parts.

    A report will be developed that will show the

    availability of drawing for that sub-

    assembly/component. This report will refer

    to the item master fields where the design

    department will be updating the status of

    drawing number, revision number or any

    other reference information like GOD or

    LOD, Engineering notes, List of loose items

    etc.

    6 Alert for

    receipt of

    materials

    Daily alert will be set that

    will list out the items

    received on that day for

    respective projects

    Alert will also be set for QC

    clearance of items.

  • 8/13/2019 Aupl Bbp Draft v2 0

    23/45

    AUPL

    Business Blueprint Document Confidential Page 23 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    7 Pending items

    for an order

    This information will be

    available in the productionorder itself. In fact the

    production order displays

    planned quantity and actual

    quantity for each of the

    items/sub-assemblies listed

    in the production BOM.

    Report/Alert will be developed that will help

    the planning department to find out list ofitems that are not yet received for a

    particular order.

    8 Completion of

    production

    Production declaration

    functionality will be used

    9 Call for

    inspection

    This will be handled through

    activity management

    functionality.

    Inspection calls will be raised using activity

    management for checking of any sub

    assembly, parts, main assembly, process etc.

    which are those of running production

    activity.

    10 List of items to

    be supplied

    loose

    This will be available in the

    sales order, if items were to

    be supplied loose

    contractually.

    In case, the equipment was dispatched with

    short supplies list of items that were not

    used up as per planned quantity in the BOM

    are visible in the production order itself. If

    needed, an additional report may have to be

    developed for this purpose. Ownership offinal shortage list lies with QC, as per AUPLs

    current process.

    11 Returning extra

    items to stores

    Any items that need to be

    returned back to main stores

    will be done so using

    inventory transfer

    transaction

    Return of material will be prepared by

    production. An appropriate format for MRN

    would be developed.

    12 Daily man hour

    logging

    In SAP manufacturing, user

    can enter the hours

    consumed for that particular

    order.

    Further classification of skills

    and their rates can be

    maintained as well.

    User will have to make

    It is not possible to link attendance system

    with SAP for this purpose. Man hours

    available on a particular date cannot be

    generated in SAP.

    However, user can enter the actual hours

    spent on the order (for various levels of

    skills).

    Attendance related emails, if needed, will

  • 8/13/2019 Aupl Bbp Draft v2 0

    24/45

    AUPL

    Business Blueprint Document Confidential Page 24 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    entries as per actual hours

    spent on that productionorder

    have to be triggered from the attendance

    tracking system (not a part of SAP) that youhave already deployed.

    13 Project

    progress

    AUPL will revert with a

    business logic that can be

    used to deduce the progress

    of any production order.

    It may be noted that the parameters to be

    used for this report, will necessarily have to

    be fields based in SAP system. Report output

    format will be kept as close as possible to the

    current format (excel), subject to technical

    feasibility.

    Full-fledged project progress tracking will

    have to be done using MS Project software

    and will be completely outside of SAP.

  • 8/13/2019 Aupl Bbp Draft v2 0

    25/45

    AUPL

    Business Blueprint Document Confidential Page 25 of 45

    7. Main Process Stores and Inventory Management

    7.1 Stores Process Flow Chart

    7.2 Sub Process Good Receipt against PO

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Goods Inward GRPO functionality will be used. AUPL to provide list

    of checks or locks

    that they need at

    the GRPO stage so

  • 8/13/2019 Aupl Bbp Draft v2 0

    26/45

    AUPL

    Business Blueprint Document Confidential Page 26 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    that they can be set-

    up

    2 Serial number

    tracking

    Movement of items that are marked as Serial

    Number Managed in item master can be

    tracked. System will ask for serial number while

    performing any transaction that has an effect

    on the stored quantities

    3 Location of storage

    needs to be visible

    This will be achieved with the help of the

    location that is mapped to the item in item

    master

    AUPL to provide

    location in item

    master

    4 Bar code label

    printing AUPL is

    yet to finalize their

    own requirements

    Once the requirements are finalized, solution

    options can be discussed

    5 Non moving item A report will be generated that will show all

    items where no inventory transaction has been

    posted since last XYZ months.

    6 Check points for

    incoming invoice

    Certain fields will be provided that can be used

    for positive confirmation about receiving

    concerned documents/information at the timeof making goods receipt

    AUPL to provide a

    list of these check

    points

    7.3 Sub Process Goods Issue for Production Order

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 List of items to be

    issues for

    production order

    This list is available in the production order

    document.

    If needed a report

    will be developed

    to address specificneeds

    2 Issue of material

    for production

    order

    This will be achieved in two steps

    Step 1:Inventory transfer transaction will be used

    to transfer material from main production store to

    Production Store

  • 8/13/2019 Aupl Bbp Draft v2 0

    27/45

    AUPL

    Business Blueprint Document Confidential Page 27 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    Step 2: As and when the production department

    actually consumes the material, Issue toProduction transaction will be used. This step will

    result in reducing the stock of the items and

    posting a consumption entry.

    7.4 Sub Process Goods Return from Production

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Receipt of material

    returned by

    production

    This will be handled via inventory transfer functionality

    and the requisite item quantities will be moved from

    production stores to main stores.

    7.5 Sub Process - Goods Returned to vendor

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Material is sent back

    to vendor

    This will be handled via Goods Return functionality in

    Purchase module

    2 POD for vendor

    returns

    Field will be provided in the goods return document,

    where the user can updated once the POD is received.

    3 Debit Memo on

    vendor

    This will be created using AP Credit Memo functionality

    7.6 Sub Process Sub Contracting Material

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Sending material to

    sub-contractor

    This will be achieved using

    the sub-contracting

    module using 4 (5) challan

    transaction

    Reference of the sub-contracting PO

    will be provided

    2 Reconciliation of Complete reporting will be

    provided in the sub-

    Reports will be available item wise,

  • 8/13/2019 Aupl Bbp Draft v2 0

    28/45

    AUPL

    Business Blueprint Document Confidential Page 28 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    material/challan contracting module challan wise, processor wise

    3 Receipt of processed

    goods sent by

    processor

    This will be handled via

    goods receipt transaction

    in sub-contracting module

    Based on the balance quantity the

    challan will be closed/or continue to

    remain open so that it can be used for

    receiving balance material.

    7.7 Sub Process - Miscellaneous Receipts and Issues

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 MiscellaneousGR

    This will be achieved using GoodsReceipt transaction in Inventory

    module

    This transaction has to be doneby a highly responsible user

    2 Miscellaneous

    GI

    This will be achieved using Goods Issue

    transaction in Inventory module

    This transaction has to be done

    by a highly responsible user

    7.8 Sub Process - Customer Supplied Material

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Receiving

    customer

    supplied material

    for trials

    These items need to be created as zero value

    item masters.

    Another identifier flag will be used to indicate

    that the item is supplier by customer.

    Additionally, item code for such items should be

    designed in such a way that user can easily

    identify that it is a customer supplier item.

    On receipt of such items, a goods receipt entry

    will be posted.

    Report will be

    developed to show all

    customer supplied

    items lying in AUPL

    premises.

    2 Return of

    customer

    supplied material

    for trials

    When the item is returned, a goods issue

    transaction will be posted

  • 8/13/2019 Aupl Bbp Draft v2 0

    29/45

    8. Main Process - Quality Management8.1 Quality Management Overall Process Flow Chart

  • 8/13/2019 Aupl Bbp Draft v2 0

    30/45

    8.2 Sub Process Inward Material Inspection

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Incoming inspection Pre-requisites

    Item master should indicate thatQM is applicable for that item

    Inspection plan has to be

    maintained for the item

    2 Listing of pending

    inspection activity

    for incoming

    material

    As soon as the user opens up the

    QM application and refreshes the

    screen, system will display a list of

    all GRs for which the incoming

    inspection activity is still pending.

    3 Entering the values

    observed

    This will be handled using

    Inspection transaction.

    4 Deciding on accept

    or reject

    This is handled by entering

    quantities in respective fields in the

    module

    5 Inspection report This will be generated from the

    system, which can be converted

    into a PDF document.

    Emailing of documents will have

    to be handled outside of SAP.

    6 Documents record All documents that are receivedwith the supply can be uploaded in

    the Goods Receipt document.

    QA team can refer to these

    documents while in the process of

    performing quality inspection

    7 Rework items QA user will move the goods to a

    rework stores and hold the final

    usage decision till the items are

    reoffered and the results aresatisfactory

    8 Rejected items QA user will move rejected items to

    a rejection store

    Once the final decision is made

    about such items, they will be

    either reworked and reoffered or

    sent back to supplier. Debit note

  • 8/13/2019 Aupl Bbp Draft v2 0

    31/45

    AUPL

    Business Blueprint Document Confidential Page 31 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    will be created separately.

    9 Consolidated view

    of all inspection

    calls made for a

    project

    Custom report will be developed to

    manage this

    8.3 Sub Process QA in Production

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 QA Inspection ofin house

    produced items

    Whenever a sub-assembly or stage isdeclared as produced and if the item code

    is marked as relevant to QA, then the item

    stock will be available in QA stores for

    inspection.

    Processes related toentering values, usage

    decision etc. will be same as

    that of Inward Inspection

    2 Stage wise

    inspection

    Whenever a sub-assembly or stage is

    declared as produced and if the item code

    is marked as relevant to QA, then the item

    stock will be available in QA stores for

    inspection.

    Processes related to

    entering values, usage

    decision etc. will be same as

    that of Inward Inspection

    3 Final Inspection

    of equipment

    This will be handed through pre-dispatch

    inspection

    Processes related to

    entering values, usage

    decision etc. will be same as

    that of Inward Inspection

    8.4 Sub Process Outdoor Inspection

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Call for

    inspection

    Provision will be made at the

    PO header level where user

    can enter Call for Inspection

    dates for

    1. RM inspection2. Tag-Weld Inspection

    Daily alert will be generated for calls for

    inspection that are due in next 8 days (with

    reference to the dates entered for these three

    stages)

  • 8/13/2019 Aupl Bbp Draft v2 0

    32/45

  • 8/13/2019 Aupl Bbp Draft v2 0

    33/45

  • 8/13/2019 Aupl Bbp Draft v2 0

    34/45

    AUPL

    Business Blueprint Document Confidential Page 34 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    2 Tracking validity

    of BankGuarantees

    Alerts will be set in the system

    based on business rules providedby AUPL

    List of alerts is mentioned in the

    subsequent sections. System will beset-up in such a way that alerts can be

    set for most (if not all) triggers.

    Note: Praxis Recommendation is to

    set only most critical alerts in the first

    go, till the users get accustomed to it.

    Else, there is a risk of too many alert

    messages coming up and user

    ignoring them.

    3 Insurance

    related tracking

    Alerts will be set in the system

    based on business rules provided

    by AUPL

    4 Invoicing to

    customer

    Please refer Sub process Invoicing

    under main process Sales

    5 Landed cost Landed cost functionality will be

    used

    Report will be developed that will

    make it easier to track the mapping of

    landed cost booked in clearing

    account and actual bills bookedtowards those expenses.

    6 Availing Excise

    credit for

    regular invoices

    This will be done using the

    incoming excise invoice transaction

    in the system

    7 Availing Excise

    credit for

    Dealer invoices

    Since the value of excise credit

    passed on by the dealer does not

    follow a fixed formula, special tax

    code called Manual Excise will be

    provided. User will have to enterall necessary information manually

    in this tax code including

    assessable value, ED, ECESS,

    HECESS etc.

    8 Excise reports RG registers, PLA, DSA will be There are a bunch of other excise

    related reports or formats, for which

  • 8/13/2019 Aupl Bbp Draft v2 0

    35/45

  • 8/13/2019 Aupl Bbp Draft v2 0

    36/45

    AUPL

    Business Blueprint Document Confidential Page 36 of 45

    10.Main Process Accounts

    SLNO

    Description Mapping in SAP B1 Remarks

    1 Listing of

    ledgers

    Chart of Accounts (CoA) - CoA

    provided and approved by AUPL will

    be loaded in SAP system with the

    required grouping and automated

    posting

    Accounts that will be posted automatically

    will be finalized and included the existing

    list of accounts as a part of finalizing CoA in

    SAP. AUPL will provide the CoA with the

    required Schedule grouping as per the

    Government requirements.

    2 Accounts

    Payable

    Accounting transactions related to

    vendors will be managed using APInvoice and AP credit memo, outgoing

    payments and functionality

    Aging reports of payables: as per GRN date

    and as per due dates customer wise,invoice wise, bucket wise, currency wise

    Credit note and debit note register

    including tax details

    Party ledger in foreign currency

    Purchase return invoicing with applicable

    taxes (part of Commercial)

    O/s Reports in Foreign currency and INR

    Auto posting of exchange gain & loss

    Customized Valuation of exchange gain &

    Loss (not available in SAP B1 Standard

    Product is not in scope)

    3 Accounts

    Receivables

    Accounting transactions related to

    customers will be managed using AR

    Invoice, AR credit memo, incoming

    payments functionality

    Debtors ageing Reports 1, based on invoice

    date

    2 Based on due date (as per terms of

    orders) as per buckets of days"

    Party ledger in foreign currency

    Credit note and debit note register

    O/s Reports in Foreign currency and INR

    Auto posting of exchange gain & loss on

    actual transactions

  • 8/13/2019 Aupl Bbp Draft v2 0

    37/45

    AUPL

    Business Blueprint Document Confidential Page 37 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    Customized Valuation of exchange gain &

    Loss (not available in SAP B1 StandardProduct is not in scope)

    4 Banking Incoming payment, outgoing

    payment, bank reconciliation

    functionalities will be used. This is

    used for both Cash and Banking

    Custom report will be develop for

    RRGS/NEFT Payments as per HDFC bank

    requirement

    Automatic payment programmed for

    positing of the entry of RTGS/NEFT

    payments

    Cheque Printing with advice having the

    details of invoices including Tax deducted

    Post dated cheques accounting and

    printing

    Advance payment, part payment facilities

    Utilization details of CC limits

    Funds Transfer within bank

    Foreign currency transactions for EFC a/c

    Cash book, lock on Cash payment of Rs 20k

    and above except bank deposit.

    Actual Cash Flow statements

    5 Journal

    Vouchers

    Bank, GL, Cash, Vendor, Customer : JV

    a standard functionality in SAP to be

    used

    Printing of Journal Vouchers and JV

    Register

    Recurring entries

    Excise Jv and Excise utilization JV for

    payment of duty with effect on Exciserecords

    Cost center wise and GL wise entry

    uploading facility from excel files will be as

    per the SAP standard DTW (Data transfer

    Workbench)

  • 8/13/2019 Aupl Bbp Draft v2 0

    38/45

    AUPL

    Business Blueprint Document Confidential Page 38 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    Reversal of entries

    6 Trial

    balance,

    P&L and BS

    Standard functionalities in SAP for TB

    with Op Bal, Transactions(Dr&Cr ) &

    Cl bal

    Sub-Ledgers Employee advances and

    Loans and Inventory. Please note SAP B1

    has the sub-ledger functionality for

    Debtors and creditors only. For above

    requirements we will be using the GL

    grouping or Dimensions in SAP. Exact

    procedure will be finalized during CRP.

    7 P&L SAP Standard P&L format according

    to the CoA grouping will be

    configured

    8 Balance

    Sheet

    SAP Standard Balance sheet formats

    with CoA grouping will be configured

    9 Reports VAT computation, Sales register,

    Purchase register will be available as

    standard

    10 Inventory Inventory Valuation will be Moving

    Average Method

    Reports:

    1. Line item inventory details Qty x

    Rate & Value With the Colum Op

    Stock, Purchase, Consumption and

    Closing stock (Group wise)

    2. Inventory Aging Reports

    In addition to the mentioned report, host

    of SAP standard report will be available

    11 Cost Centers All expenses other than Raw material

    must be covered by cost centers

    We can make the cost centers mandatory

    for expense accounts.

    12 TDS All mandatory requirements of TDSwith the applicable TDS sections and

    capturing the TDS deducted during AP

    Invoices will be covered.

    SAP standard TDS reports will be

    provided

  • 8/13/2019 Aupl Bbp Draft v2 0

    39/45

    AUPL

    Business Blueprint Document Confidential Page 39 of 45

    SL

    NO

    Description Mapping in SAP B1 Remarks

    13 Service Tax Service tax codes to generate the

    liability of Service Tax on Transportersand others AP invoices according to

    SAP std processes will be configured

    14 Fixed Assets

    Fixed Assets RegisterFA register with the listing of the current

    Fixed assets will be available

    Monthly / Yearly deprecation

    calculations

    Auto calculation assets depreciation will

    not be done through system. This is not

    available in SAP B1 India version till date.

    Purchase / Sales of Fixed Assets will

    be a handled in SAP

    15 Budget SAP Budget definitions will be used

    define GL wise and Cost center wise

    Budgets.

    SAP standard report for Budget Vs Actual

    will be used

    16 Costing Project wise P&L can be generated

    from the system.

    However, this report is accessible only to

    accounts/ professional users.

    17 Year /

    Month End

    Closing

    SAP standard feature for Month /

    Year end will be used (Period Locking)

  • 8/13/2019 Aupl Bbp Draft v2 0

    40/45

    AUPL

    Business Blueprint Document Confidential Page 40 of 45

    11.Main Process Design

    11.1Design Process Flow Chart

  • 8/13/2019 Aupl Bbp Draft v2 0

    41/45

    AUPL

    Business Blueprint Document Confidential Page 41 of 45

    11.2Process Mapping - Design

    SL

    NO

    Description Mapping in SAP B1 Remarks

    1 Drawingcreation

    CAD System will handle this

    2 Assigning

    drawings

    This will be managed by attaching

    drawing files to respective item masters

    or to any other operational document

    likes sales order, purchase order etc.

    3 List of

    drawings

    available

    Custom report will be developed to

    address this requirement. Every item

    master will have fields that need to be

    updated by design department, wheneverthey create item masters.

    4 Alert for OA Whenever a sales order is created, an

    alert will be sent to design department

    user in the SAP system

    5 Check list for

    OA

    AUPL to revert with this check list Using this input certain fields will

    be provided at sales order level.

    Based on values entered in these

    fields, reports will display a

    variety of statuses

    6 Task

    assignment

    Activity Tracking functionality will be used Variety of activities can be

    created and assigned, with

    reminders

  • 8/13/2019 Aupl Bbp Draft v2 0

    42/45

    AUPL

    Business Blueprint Document Confidential Page 42 of 45

    12.Main Process HRMS

    SL

    NO

    Description Mapping in HRMS Remarks

    1 Personal

    Information

    Personal details Profile picture Contact details Leaves Other details related to the employee Reporting structure (Manager, Reportees)

    2 Employee Self

    Service

    Updating personal information Viewing leave balance Applying for new leave Viewing companys holiday list Viewing updates published by HR team

    3 Joining

    Formalities

    Offer Letter Appointment Letter Creation of New Employee master with the required

    details and Uploading of documents

    4 Publishing

    company policy

    PDF documents will be hosted like LTP, Leave Policy, Loan

    Policy, TA DA Policy, Safety policy, AUPL Holiday List, Foreign

    Travel Policy etc

    5 Time office Daily attendance will be captured from the attendance

    system and used for both HRMS and Payroll

    Leave Management with Approvals

    6 Gate Pass Dedicated Gate system will not be part of the scope

    7 Performance

    Management

    Defining KPIs grade/position wise Defining goals and objectives Entering performance achievements - by employee Performing an appraisal (KPI wise)- Manager Assigning ratings for each KPI and adding feedback Assigning overall rating for the year

    8 Training Module Identify and record training requirement Updated list of trainings available Application for attending a training Confirmation Updating information on trainings attended

  • 8/13/2019 Aupl Bbp Draft v2 0

    43/45

    AUPL

    Business Blueprint Document Confidential Page 43 of 45

    SL

    NO

    Description Mapping in HRMS Remarks

    9 Requests Material request

    HK Material, Safety Shoes, Stationery etc.. Manpower request Vehicle and Travel request

    10 Letters to

    employees

    Using predefined formats

    11 Alerts All alerts will be available in SAP system

    12.1HRMS Reports

    Please note:- AUPL needs to submit the formats for the below mentioned reports

    SL

    NO

    Group Report name Remarks

    1 Factories Act Form 20 - Maintain Register Of Leavewith Wages

    Muster roll Form 27

    2 Provident Fund Act1952

    PF Withdrawal - Form 19 & 10C (Tobe studied in detail) Statement of workers leaving the

    service - Form 10

    3 Under Contract Labour

    (Regulation &

    Abolition) Act

    Register of Workman employed bythe Contractor at AUPL

    Annual Returns (Yearly return Form -24)

    Muster roll Register of Annual Wages Paid Validity of License - Alert

    4 Under Payment of

    Bonus Act

    Form C for the year closing Form D for the year closing

    5 Maternity Benefit act Form A - Muster roll

  • 8/13/2019 Aupl Bbp Draft v2 0

    44/45

    AUPL

    Business Blueprint Document Confidential Page 44 of 45

    SL

    NO

    Group Report name Remarks

    6 HRA Form A Register to be maintainstaff

    Form I For Workmen

    7 Nominations Gratuity PF Nomination details likenominees name, DOB,

    Relationship, % of Share

    will be defined in

    Employee master

    details.

    8 Payment Of Wage Act

    1936

    FORM NO. II-A (Register of wages) FORM NO. III(Register of advances

    made to employment persons)

    FORM NO. III-A (Register of loansgranted to the employed persons for

    house building or other purposes)

    9 Minimum Wages

    (Central) Rules, 1950

    Form III Rule 21(4A) : Annual Returnof Deduction from Wages Form

    Form V Rule 26(5) : Muster Roll Form Form X Rule 26(1): Register of Wages

    Form

    Form XI Rule 26(2): Wage Slip Form10 THE EQUAL

    REMUNERATION

    RULES, 1976

    FORM D - Register to be maintainedby employer under rule 6 of the Equal

    Remuneration Act, 1976

  • 8/13/2019 Aupl Bbp Draft v2 0

    45/45

    AUPL

    13.Main Process Payroll

    SLNO

    Description Mapping in HRMS Remarks

    1 Company

    Master

    Multiple companies can bemaintained

    2 Calendars Holiday calendar Factory calendar

    3 Employee

    Master

    Detail information about eachemployee

    Employee master stored in thissystem will be used by HRMSsystem

    4 Salary Group Salary groups as perorganization structure

    Salary stack (salary heads ofearning, deduction, manual

    salary heads if applicable)

    5 Monthly

    Payroll

    Manual salary heads (ifapplicable)

    Additional deductions (ifapplicable)

    Calculation of payroll for month(for review and validation)

    Final Payroll Run Full and Final settlement

    process

    Arrears processing MLWF deduction Deductions like PF, PT, IT, ESIC

    and deduction reports

    F&F Final run Salary slips sent at attachment

    to email, at a single click

    IT calculation will be done outside the

    payroll system. However, IT deductions

    will be included in the monthly payroll

    6 Reports There are several reports available

    as standard.

    If needed, additional reports can be

    generated, provided there is a

    technical feasibility for the same.