Project Update
September 20, 2010
Roadway Projects
• Approximately 80% of NB lanes poured• Piers and Bents completed for northbound
bridge, waiting on cure time to set beams• Work continuing on Retaining Wall south
side of Hickory Slough bridge
Cullen Parkway
Cullen Parkway
Cullen Parkway
Construction phase II – Veterans Dr to Pearland Parkway
• Completed interlocking block placement in Magnolia Outfall and Independence Park Outfall
• BNSF initiated removal of at-grade RR crossing by removing concrete panels
• Completed pavement marking adjustments on Overpass
• Completed irrigation and planting on Magnolia Rd. medians
Magnolia Road
Construction Phase III – Morgan to Harkey and CR 89
• Enterprise Pipeline completed work in easement west of Harkey
• Initiated sealing of manholes in preparation for televising sanitary line
• Completed investigations of settlement issue by coring, boring and hand augers to determine areas of concern
• Initiated waterline testing on Cullen Parkway and portions of Magnolia water line
• Completed traffic switch on Cullen
Magnolia Road
Phase I - Beamer to FM518
• TxDOT is near closing out the project• Preliminary calculation is that we will be refunded
$869,525.67
Dixie Farm Road
Phase II – Mary’s Creek Bypass to SH35
• Continued excavation activities and lime stabilization in future southbound main lane area
• CenterPoint completed one phase of relocation to remove gas line in conflict
• Working on intersections of Tall Oaks, Bestin Oaks, and Willow Lake
• Preparing for intersection work at Inverness
Dixie Farm Road
Detention – East Mary’s Creek• Completed excavation activities• Completed pilot channels in pond• Working on project cleanup and closeout
Dixie Farm Road
• The jack and bore started August 10, 2010 with a duration of 20 days for each of three runs
• Mykawa-Orange Intersection closure began September 13th
• The railroad shut down the project due to rail deflection issues. These have been abated by slowing the train speed down to 25mph
• Overhead utilities along Mykawa were raised to alleviate a clearance issue for the trucks entering and leaving Pipe and tube Supply’s yard.
Town Ditch Phase III
• TxDOT has verbally agreed to adjust their design to match the Orange Street design
• Engineer is working with AT&T to solve issues that arose as a result of line and equipment relocation
• Bidding scheduled for September 2010
Orange Street
• Coordinating work with TxDOT and BNSF• One parcel remains but we have a ROE• Utilities continuing relocation• LJA has incorporated an add alternate to include
asphalt overlay of the road between Old Alvin and Grand; also between McLean and Austin
• Working with BDD4 to address their concerns with lowering Walnut Street
• Negotiating Construction Management services
Walnut Reconstruction
• 100% plans currently under review• Finalized negotiations on RFP sent to engineer for
amendment to the design contract for plan changes associated with revisions to the Bailey drainage.
• $1.2M overall savings by upsizing the trunkline and taking additional flows to the Cowart Creek Diversion Ditch
• Preparing contract for Noise Impact Analysis services. City requested that services not begin until school returned to session so conditions would be closer to normal
• ROW acquisition underway – 55 of 65 parcels acquired
Bailey Road (Veterans to FM1128)
• Sidewalk, fine grading and sod placement continued• Bridge railings placed, striping completed• Continued work with Centerpoint to install
streetlights along the new roadway• Soundwall contract awarded to John Reed & Co. • Continued to work with design team to resolve
conflicts with utilities• Reconstruction lanes have been opened to traffic
McHard Road (Country Place to Cullen)
McHard Road (Country Place to Cullen)
• Awaiting letter from TxDOT for balance of City’s cost of the utilities based on the AFA (est. $400,000)
• City and TxDOT projects underway• Working with TxDOT to address local business
concerns• Submitted for USACE permit for low water crossing• Mitigation plans completed; waiting on permit and
TxDOT approval
SH35 – BW8 to FM518
Drainage Projects
Detention Pond• Pond A approximately 84% excavated• Hauling activities and fill placement at second fill
site continued• JKC continued working with Public Works to
finalize the electrical design for the pump station• ESPA has been authorized to continue their design
based on the revised Bailey drainage plan
Cowart Creek Diversion
Diversion Ditch• East – West corridor acquisition complete• Conoco Phillips pipeline agreement
approved by Council• Dannenbaum optimization study found
overall cost savings of $1.2M by upsizing the Bailey trunkline and sending additional flows to the diversion ditch
Cowart Creek Diversion
• Contractor completing punch list items• Harris completed work at the Bailey pond to
fill in washed out area under pilot channel at outfall to Cowart’s Creek, low spots were also filled in
Bailey & Veterans Regional Detention
Facility Projects
Old PD Renovations
• Met with the architect to further address the revised scope of the project
• Received the asbestos and lead reports of the jail area which will be used for on-site storage for several City Departments. Asbestos is present in the flooring tile mastic.
• Requested proposal for asbestos remediation• Received proposal for demolition
• Held interim design review meeting on July 20th
• Conducted Site/Civil plan review July 28th
• Received 90% Construction Documents and distributed for internal review
• Plans in for permitting• Scoping work for the retro-fit of the existing fuel
management system at the Orange Street facility
Hillhouse Road Service Center
• Conducted Substantial Completion inspection• Obtained Certificate of Occupancy• Held VIP Reception and Grand Opening• Scheduled TDLR inspection for September
Recreation and Natatorium Center
Recreation and Natatorium Center
• Floor Drain and reversed Holding Cell door have been installed
• Jail control and surveillance system completed and programmed
• Working towards building commissioning
Public Safety Building
• Substantial June 30th• Completed final items of punch list August 20th
• Final Completion and Acceptance issued August 24th
• Unused contingency amount $296,970
U of H Clear Lake – Pearland Campus
• Building slab foundation passed strength tests• Petrographic analysis completed• Contractor began erecting building August 28th
• Working with a vendor on a proposal to provide an alerting system for the facility that would tie into the City’s existing dispatch system
• Preparing to pour site paving
Fire Station #5
Fire Station #5
• FDC received bids• $997,000• Engineering Department’s comments were
sent back to the engineer for re-submittal
Fire Station #6
• HVAC system/insulation repairs started; sources of condensation identified and corrected
• Exhaust fan repairs completed• Kennel gate rebuilds began; working with
contractor to resolve issues with the finish• Final finish selections submitted to contractor• Furniture and equipment orders placed• TDLR ADA inspection completed
Animal Control Expansion
Parks
• New easement mapping received – moving forward with acquisition
• Property appraisals received and offers made.• Counteroffers received and are under review• Some files are being prepared for condemnation
proceedings.• City staff met with design firm to begin finalizing
construction plans in preparation for bidding
Trail Connectivity
• Reviewing scope of design contract for the Detention Pond and Sports Complex
• Schedule
Sports Complex at Max Road
Utility Projects
30” Waterline Interconnect
• Notice to Proceed issued to Huff & Mitchell, Inc. on August 23rd
• Beltway 8 crossing underway – 330 of 401 feet completed
• Approximately 500 feet south of Clear Creek completed
• CoH 72” line scheduled for completion in March 2011
City of Houston Interconnect
City of Houston Interconnect
Alice Street Water Plant
• Installation of waterlines and storm sewer lines within plant site began
• Beginning excavation for the foundation of the 5MG Ground Storage Tank
• Completed placement of clay material in Backwash Pond area
• Began placement of clay material on east and west slopes
Surface Water Reservoir
Knapp Road LS & SH35 Utilities
• PEDC Funded• 100% plans completed. • Easement donations pursued by PEDC• PEDC working with developer on
construction plan and evaluating alternatives for funding the construction
Hooper Road Utilities
• PER submitted for approval• Negotiating design contract with Malcom Pirnie;
submit for Council approval in October
Longwood WWTP Rehabilitation
• Submitted first draft of Preliminary Engineering Report
• PER completion scheduled for September 2010
Barry Rose WWTP Rehabilitation
• Held substantial walk through inspections of Knapp Road lift station and Blockbuster grinder pump station
• Punch list items noted
Knapp Road LS & SH35 Utilities
Project Update
Questions/Comments
September 20, 2010