208
AUBURN UNIVERSITY STUDENT LAUNCH Project Nova 211 Davis Hall AUBURN, AL 36849 FLIGHT READINESS REVIEW MARCH 5, 2018

Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

AUBURN UNIVERSITY STUDENT LAUNCH

Project Nova

211 Davis Hall

AUBURN, AL 36849

FLIGHT READINESS REVIEW

MARCH 5, 2018

Page 2: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

2

Table of Contents

Table of Contents ...........................................................................................................................2

List of Figures .................................................................................................................................8

List of Tables ................................................................................................................................12

Section 1: General Information ..............................................................................................14

Section 1.1: Team Information .............................................................................................14

Section 1.2: Adult Educators ................................................................................................14

Section 1.3: Safety Officer ...................................................................................................15

Section 1.4: Team Leader .....................................................................................................16

Section 1.5: Project Organization .........................................................................................16

Section 1.6: NAR/TRA Sections ..........................................................................................19

Section 2: Summary of FRR Report ......................................................................................19

Section 2.1: Team Summary.................................................................................................19

Section 2.2: Launch Vehicle Summary ................................................................................20

Section 2.3: Payload Summary .............................................................................................21

Section 3: Changes Made Since CDR ....................................................................................21

Section 3.1: Vehicle Changes ...............................................................................................21

Section 3.2: Payload Changes...............................................................................................21

Section 3.3: Project Plan Changes ........................................................................................22

Section 4: Launch Vehicle .......................................................................................................22

Section 4.1: Vehicle Changes ...............................................................................................22

Section 4.1.1: Since CDR ......................................................................................................22

Page 3: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

3

Section 4.1.2: During Construction .......................................................................................23

Section 4.2: Systems Component Analysis ..........................................................................23

Section 4.2.1: Structure ..........................................................................................................23

Section 4.2.2: Propulsion .......................................................................................................26

Section 4.2.3: Aerodynamics .................................................................................................29

Section 4.2.4: Schematics ......................................................................................................32

Section 4.3: Flight Reliability Confidence ...........................................................................40

Section 4.3.1: Fin Shape and Style ........................................................................................40

Section 4.3.2: Materials .........................................................................................................42

Section 4.3.3: Assembly Procedures ......................................................................................42

Section 4.4: Mass Statement .................................................................................................44

Section 4.5: Manufacturing Process .....................................................................................44

Section 5: Recovery System Design ........................................................................................49

Section 5.1: Structural Elements...........................................................................................50

Section 5.2: Materials ...........................................................................................................51

Section 5.3: Ejection .............................................................................................................55

Section 5.4: Parachutes .........................................................................................................59

Section 5.5: Altimeters .........................................................................................................63

Section 5.6: Recovery System Technical Drawings .............................................................66

Section 6: Mission Performance Predictions .........................................................................68

Section 6.1: Simulations .......................................................................................................68

Section 6.1.1: Motor Thrust Curve ........................................................................................71

Page 4: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

4

Section 6.1.2: Component Weights .......................................................................................71

Section 6.1.3: Stability ...........................................................................................................72

Section 6.1.4: Computational Fluid Dynamics ......................................................................73

Section 6.2: Kinetic Energy ..................................................................................................76

Section 6.3: Drift ..................................................................................................................77

Section 6.4: Simulation Verification ....................................................................................80

Section 7: Full-Scale Flight Results ........................................................................................81

Section 7.1: Flight Data ........................................................................................................81

Section 7.2: Launch Day Simulation and Analysis ..............................................................81

Section 7.3: Full-scale Analysis ...........................................................................................82

Section 7.3.1: Post-Launch Simulation ..................................................................................83

Section 7.4: Full-Scale and Subscale Comparison ...............................................................83

Section 8: Rover .......................................................................................................................84

Section 8.1: Design Changes ................................................................................................84

Section 8.1.1: Since CDR ......................................................................................................84

Section 8.1.2: During the Construction Process ....................................................................88

Section 8.2: Structural Elements...........................................................................................89

Section 8.3: Electrical Elements ...........................................................................................97

Section 8.4: Drawings and Schematics ...............................................................................102

Section 8.5: Flight Reliability Confidence .........................................................................104

Section 8.5.1: Deployment ...................................................................................................104

Section 8.5.2: Navigation .....................................................................................................104

Page 5: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

5

Section 8.5.3: Communication .............................................................................................104

Section 9: Altitude Control Module .....................................................................................105

Section 9.1: Design Changes ..............................................................................................105

Section 9.1.1: Since CDR ....................................................................................................105

Section 9.1.2: During the Construction Process ..................................................................105

Section 9.2: Design .............................................................................................................106

Section 9.2.1: Structural Elements .......................................................................................106

Section 9.2.2: Electrical Elements .......................................................................................107

Section 9.2.3: Drawings and Schematics .............................................................................108

Section 9.3: Flight Reliability Confidence .........................................................................110

Section 10: Safety .....................................................................................................................113

Section 10.1: Personnel Hazard Analysis .............................................................................113

Section 10.2: Failure Modes and Effects Analysis ...............................................................116

Section 10.3: Environmental Hazard Analysis .....................................................................126

Section 10.3.1: Rocket Effects on Environment ..................................................................126

Section 10.3.2: Environmental Effects on Rocket ...............................................................127

Section 11: Launch Operations Procedures ..........................................................................130

Section 11.1: Preassembly Checklists ..................................................................................130

Section 11.1.1: Recovery .....................................................................................................130

Section 11.1.2: Altitude Control ..........................................................................................131

Section 11.1.3: Body ............................................................................................................132

Section 11.1.4: Rover ...........................................................................................................132

Page 6: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

6

Section 11.1.5: Engine .........................................................................................................133

Section 11.2: Launch Vehicle Assembly and Check ............................................................133

Section 11.3: Launcher Setup and Launch Procedure ..........................................................135

Section 11.3.1: Launcher Setup ...........................................................................................135

Section 11.3.2: Launch Procedure .......................................................................................136

Section 11.4: Post-flight Inspection ......................................................................................136

Section 12: Testing ...................................................................................................................138

Section 12.1: Rover Battery and Motor Test (AU 4.4, 4.5) ..................................................138

Section 12.1.1: Results .........................................................................................................139

Section 12.2: Recovery and Altitude Control Battery Tests (AU 3.1, 6.9) ..........................141

Section 12.2.1: Results .........................................................................................................142

Section 12.3: Full-Scale and Subscale Separation Test (AU 3.2) ........................................142

Section 12.3.1: Results .........................................................................................................144

Section 12.4: Tension Testing of Composite and 3D Printed Material (AU 2.1, 2.2) .........146

Section 12.4.1: Results .........................................................................................................147

Section 12.5: 3-Point Bend Testing of Composite and 3D Printed Material (AU 2.1, 2.2, 6.7)

149

Section 12.5.1: Results .........................................................................................................151

Section 12.6: Compression Testing of Composite and 3D Printed Material (AU 2.1, 2.2, 6.7)

153

Section 12.6.1: Results .........................................................................................................154

Section 12.7: Rover Maneuverability (AU 4.2, 4.3, 4.6, 4.7)...............................................156

Page 7: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

7

Section 12.7.1: Results .........................................................................................................157

Section 12.8: Altitude Control System (AU 6.4 – 6.8) .........................................................158

Section 12.8.1: Results .........................................................................................................160

Section 13: Project Plan ..........................................................................................................160

Section 13.1: Requirements Verification ..............................................................................160

Section 13.1.1: General Requirements .................................................................................160

Section 1.1.1: Vehicle Requirements ................................................................................166

Section 1.1.2: Recovery Requirements .............................................................................180

Section 13.1.2: Deployable Rover Requirements ................................................................186

Section 13.1.3: Safety Requirements ...................................................................................188

Section 13.2: Team Requirements ........................................................................................189

Section 13.2.1: General Requirements .................................................................................189

Section 13.2.2: Vehicle Requirements .................................................................................190

Section 13.2.3: Recovery Requirements ..............................................................................191

Section 13.2.4: Deployable Rover Requirements ................................................................192

Section 13.2.5: Safety Requirements ...................................................................................195

Section 13.2.6: Altitude Control Requirements ...................................................................196

Section 13.3: Budget .............................................................................................................199

Section 13.4: Funding Plan ...................................................................................................206

Section 13.5: Timeline ..........................................................................................................207

Page 8: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

8

List of Figures

Figure 1.1: Team Organization Chart ........................................................................................... 17

Figure 4.1: Motor Thrust Curve .................................................................................................... 27

Figure 4.2: Motor Retention ......................................................................................................... 29

Figure 4.3: Fin Rendering ............................................................................................................. 30

Figure 4.4: Lower Booster Section Dimensional Drawing ........................................................... 35

Figure 4.5: Upper Body Tube Dimensional Drawing ................................................................... 36

Figure 4.6: Upper Section Assembly Dimensional Drawing........................................................ 37

Figure 4.7: Centering Ring Dimensional Drawing ....................................................................... 38

Figure 4.8: Bulkhead Dimensional Drawing ................................................................................ 39

Figure 4.9: Fin Dimensional Drawing .......................................................................................... 40

Figure 4.10: Fin Shapes ................................................................................................................ 41

Figure 4.11: Booster Section Diagram.......................................................................................... 45

Figure 4.12: Fin-Jig ....................................................................................................................... 47

Figure 4.13: Isogrid Manufacturing Process ................................................................................. 48

Figure 4.14: Isogrid Manufacturing Process – Filament Winding ............................................... 49

Figure 5.1: Redundant Jolly Logic System ................................................................................... 57

Figure 5.2: Jolly Logic Chute Release .......................................................................................... 58

Figure 5.3: Gore Template ............................................................................................................ 61

Figure 5.4: Parachute Template .................................................................................................... 61

Figure 5.5: Altus Metrum TeleMega Altimeter ............................................................................ 64

Page 9: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

9

Figure 5.6: Altus Metrum TeleMetrum Altimeter ........................................................................ 64

Figure 5.7: Altimeter Block Diagram ........................................................................................... 65

Figure 6.1: OpenRocket Model..................................................................................................... 68

Figure 6.2: Altitude Vs. Time ....................................................................................................... 69

Figure 6.3: Velocity Vs. Time ...................................................................................................... 70

Figure 6.4: Acceleration Vs. Time ................................................................................................ 70

Figure 6.5: Motor Thrust Curve .................................................................................................... 71

Figure 6.6: Stability Vs. Time....................................................................................................... 73

Figure 6.7: Nosecone Meshing ..................................................................................................... 75

Figure 6.8: Tail-fin Meshing ......................................................................................................... 75

Figure 7.1: Full-scale Flight Data ................................................................................................. 81

Figure 8.1: Rover Coupler Bay ..................................................................................................... 85

Figure 8.2: Servo System .............................................................................................................. 86

Figure 8.3: Bulbous Rover Drive Wheels ..................................................................................... 87

Figure 8.4: Communication Schematic......................................................................................... 88

Figure 8.5: I-beam Rover Body – Top .......................................................................................... 89

Figure 8.6: I-beam Rover Body – Bottom .................................................................................... 90

Figure 8.7: Dual Tread System ..................................................................................................... 91

Figure 8.8: Exploded Dual Tread System ..................................................................................... 92

Figure 8.9: SPDS – Folded ........................................................................................................... 93

Figure 8.10: SPDS - Unfolded ...................................................................................................... 93

Figure 8.11: Solar Panel Deployment Tray .................................................................................. 94

Page 10: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

10

Figure 8.12: Servo Arm/Jaw ......................................................................................................... 95

Figure 8.13: Open Servo Arm/Jaw ............................................................................................... 96

Figure 8.14: Closed Servo Arm/Jaw ............................................................................................. 96

Figure 8.15: Sample Orientation Check........................................................................................ 97

Figure 8.16: Electrical Schematic ................................................................................................. 98

Figure 8.17: 1000:1 12V Pololu Micro Metal Gearmotors........................................................... 98

Figure 8.18: XCTU Interface ........................................................................................................ 99

Figure 8.19: Arduino Wiring ...................................................................................................... 100

Figure 8.20: Motor Shield Wiring .............................................................................................. 101

Figure 8.21: Rover CONOPS ..................................................................................................... 102

Figure 8.22: Assembled Rover ................................................................................................... 103

Figure 8.23: Rover Dimensions .................................................................................................. 103

Figure 9.1: Bottom-Up view of plates and arms ......................................................................... 109

Figure 9.2:Side View of assembled module ............................................................................... 109

Figure 9.3: IPDS Dimensions ..................................................................................................... 110

Figure 12.1: Subscale Separation Test ........................................................................................ 144

Figure 12.2: Full-Scale Separation Test of the Upper Section ................................................... 145

Figure 12.4: Epoxy - Carbon Fiber Tension Test Results .......................................................... 147

Figure 12.5: Epoxy - Fiberglass Tension Test Results ............................................................... 148

Figure 12.6: Onyx Tension Test Results..................................................................................... 149

Figure 12.7: Epoxy - Carbon Fiber Bend Test Results ............................................................... 151

Figure 12.8: Epoxy - Fiberglass Bend Test Results .................................................................... 152

Page 11: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

11

Figure 12.9: Onyx Bend Test Results ......................................................................................... 152

Figure 13.1: Spending Comparison ............................................................................................ 206

Figure 13.2: Fall Timeline .......................................................................................................... 207

Figure 13.3: Spring Timeline ...................................................................................................... 208

Page 12: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

12

List of Tables

Table 1.1: Team Members ............................................................................................................ 17

Table 2.1: Team Information ........................................................................................................ 19

Table 2.2: Mentor Information ..................................................................................................... 20

Table 2.3: Launch Vehicle Information ........................................................................................ 20

Table 4.1: Section Lengths ........................................................................................................... 24

Table 4.2: Motor Specifications .................................................................................................... 28

Table 4.3: Fin Dimensions ............................................................................................................ 31

Table 4.4: Manufacturing Schedule .............................................................................................. 43

Table 4.5: Mass Estimations ......................................................................................................... 44

Table 5.1: Pugh Chart of Carbon Fiber vs. Fiberglass Material for the BAE............................... 50

Table 5.2: Parachute Materials Pugh Chart .................................................................................. 52

Table 5.3: Comparison of Paracord, Tubular Nylon, Kevlar ........................................................ 53

Table 5.4: Comparison of U-bolts and Eye-bolts ......................................................................... 54

Table 5.5: Comparison of Black Powder and CO2 ....................................................................... 55

Table 5.6: Parachute Shape Pugh Chart ........................................................................................ 60

Table 5.7: Parachute Dimensions ................................................................................................. 62

Table 6.1: Flight Simulation Data (Wind = 0 mph) ...................................................................... 68

Table 6.2: Component Weights .................................................................................................... 71

Table 6.3: CFD Drag Coefficient Results ..................................................................................... 76

Table 6.4: Drift Calculations for Upper Section ........................................................................... 79

Table 6.5: Drift Calculations for Lower Section .......................................................................... 79

Page 13: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

13

Table 9.1: Physical Components................................................................................................. 106

Table 9.2: Electrical Components ............................................................................................... 107

Table 9.3: Mission Success Criteria............................................................................................ 110

Table 13.1: Deployable Rover Requirements Verification ......................................................... 186

Table 13.2: AU General Requirements ....................................................................................... 189

Table 13.3: AU Vehicle Requirements ....................................................................................... 190

Table 13.4: AU Recovery Requirements .................................................................................... 191

Table 13.5: AU Rover Requirements.......................................................................................... 192

Table 13.6: AU Altitude Control Requirements ......................................................................... 196

Table 13.7: Vehicle Costs ........................................................................................................... 199

Table 13.8: Recovery Costs ........................................................................................................ 200

Table 13.9: Budget Allocation .................................................................................................... 205

Table 13.10: Funding Sources .................................................................................................... 206

Page 14: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

14

Section 1: General Information

Section 1.1: Team Information

General Team Information

Team Affiliation Auburn University

Mailing Address 211 Engineering Drive

Auburn, AL 36849

Title of Project Project Nova

Date of FRR March 5th, 2018

Experiment Option 2: Deployable Rover

Section 1.2: Adult Educators

Contact Information

Name Dr. Brian Thurow

Title Aerospace Engineering Department Chair, Faculty

Advisor

Email [email protected]

Phone 334-844-4874

Address 211 Davis Hall

Auburn, AL 36849

Page 15: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

15

Contact Information

Name Dr. Eldon Triggs

Title Lecturer, Aerospace Engineering, Mentor

Email [email protected]

Phone 334-844-6809

Address 211 Davis Hall

Auburn, AL 36849

Section 1.3: Safety Officer

Safety Officer – Contact Information

Name Corey Ratchick

Title Senior in Aerospace Engineering

Auburn University

Email [email protected]

Corey Ratchick will be the Safety Officer for the Auburn Student Launch team this year. It is his

third year on the team. His goal for the year is to provide more exhaustive checklists than the team

has had access to in the past in an attempt to minimize human error.

Page 16: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

16

Section 1.4: Team Leader

Student Team Lead – Contact Information

Name Tanner Straker

Title Senior in Aerospace Engineering

Auburn University

Email [email protected]

Phone 847-507-1193

Address 211 Engineering Dr.

Auburn, AL 36849

Tanner Straker will be the student team leader for this year’s competition team. This is Tanner’s

third year on the team. In the previous year, Tanner served as the Recovery team leader and

oversaw the successful recovery of the team’s rocket throughout the year and during the

competition flight. He enjoys long walks across launch sites and sewing parachutes. Tanner is level

one high power rocket certified through Tripoli Rocketry Association.

Section 1.5: Project Organization

The Auburn Student Launch team is broken into five major sub-teams: vehicle body design,

payload, electronic systems, testing, and recovery. Safety and educational engagement also exist

as sub-teams composed of students from the five primary groups. Each sub-team has at least one

member dedicated to identifying safety concerns and acting as the point of contact (POC) for the

safety officer. In addition, all members of the Auburn Student Launch Team are required to

participate in at least one educational engagement event and each event has its own coordinator,

Page 17: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

17

all of whom are working members of other sub-teams. Figure 1.1: Team Organization Chart shows

the hierarchy of project management with all teams reporting to their team leads, the student

project manager, and the safety officer, who in turn report to the adult educators.

Figure 1.1: Team Organization Chart

Table 1.1: Team Members

Name Role Team

Dr. Eldon Triggs Adult Educator Overall Management

Dr. Brian Thurow Adult Educator Overall Management

Tanner Straker Project Manager Overall Management

Corey Ratchick Safety Officer Overall Management/Safety

Reilly B. Team Lead Vehicle Body

Tanner O. Team Lead Electronic Systems

David T. Team Lead Payload

Page 18: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

18

Ben C. Team Lead Recovery

Bryce G. Team Lead Testing

Kate M. Team Lead Education

Nick R. Team Member Testing

Zac B. Team Member Education

Icis M. Team Member Education

Jaylene A. Team Member Education

Jake R. Team Member Safety

Rhett R. Team Member Safety

Ruth A. Team Member Safety

Sydney F. Team Member Safety

Zach W. Team Member Recovery

Paul L. Team Member Recovery

Omkar M. Team Member Recovery

Jaysal S. Team Member Recovery

Bill M. Team Member Vehicle Body

Adam B. Team Member Vehicle Body

CJ L. Team Member Vehicle Body

Matthew D. Team Member Vehicle Body

Logan J. Team Member Vehicle Body

Anthony G. Team Member Vehicle Body

Victor D. Team Member Vehicle Body

Rhett R. Team Member Payload

Stephen S. Team Member Payload

Zach S. Team Member Payload

Kevin H. Team Member Payload

Page 19: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

19

Matthew W. Team Member Payload

Landon B. Team Member Payload

Salaar K. Team Member Electronic Systems

Andrew R. Team Member Electronic Systems

Ruth A. Team Member Electronic Systems

Michael C. Team Member Electronic Systems

Austen L. Team Member Electronic Systems

Matthew H. Team Member Electronic Systems

Section 1.6: NAR/TRA Sections

The Auburn Student Launch team is planning on attending launches hosted by Southern Area

Rocketry (SoAR) at Phoenix Missile Works (PMW) in Sylacauga Alabama (NAR Section #571).

The team also occasionally attends launches with the Music City Missile Club (MC2) in

Manchester, Tennessee (NAR Section #589) and the South Eastern Alabama Rocket Society

(SEARS) in Samson, Alabama (NAR Section #572/TRA Prefect 38). We will also be partnering

with SEARS through Christopher Short. Chris provides technical experience and serves as a

reliable rocketry vendor for the team.

Section 2: Summary of FRR Report

Section 2.1: Team Summary

Table 2.1: Team Information

Team Information

Team Name Auburn University Student Launch (AUSL)

Page 20: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

20

Mailing Address 211 Engineering Drive

Auburn, AL 36849

Project Name Project Nova

Table 2.2: Mentor Information

Mentor Information

Mentor Name Eldon Triggs

TRA Number 12159

Certification Level 2

Contact Information Email: [email protected]

Phone: 334-844-6809

Section 2.2: Launch Vehicle Summary

Table 2.3: Launch Vehicle Information gives the basic details of the launch vehicle. More

information regarding the launch vehicle can be found in Section 4: Launch Vehicle of this report.

Table 2.3: Launch Vehicle Information

Launch Vehicle Information

Total Length 113 in.

Estimated Mass 38.4 lbm

Motor Selection Aerotech L1420R

Recovery System Double Separation, Dual Deployment

Page 21: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

21

Rail Size 12 ft. 1515

Section 2.3: Payload Summary

Auburn University's Student Launch team will be completing the deployable rover experiment.

The rover has been named Monica. After landing under parachute, Monica will be completely

housed inside the rocket will be remotely deployed from the rocket. She will autonomously travel

at least five feet from the rover and deploy foldable solar panels. A dual-tread design deployed

from an orientation-independent containment bay has been chosen to minimize the possibility of

error and risk within the system

Section 3: Changes Made Since CDR

Section 3.1: Vehicle Changes

The team has decided not to continue with braided carbon fiber as a body tube material for this

year. The team successfully built and flew a braided carbon fiber rocket, but the weight reduction

of the structure was minimal and the rugged shape of the skin overlaying the braid induced

additional drag. With additional research, this construction style could improve rocket

performance, but given time constraints the team constructed and flew a solid carbon fiber airframe

rocket for competition purposes.

Section 3.2: Payload Changes

The rover design has not changed significantly. Domed wheels are being used in place of flat

wheels, and the body of the rover has been modularized for ease of interaction. These changes

Page 22: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

22

came as a result of experience gained during the construction process. More information on the

rover changes can be seen in Section 8.1: Design Changes.

The larger change to the payloads is the decision not to fly at competition with the airbrake system.

The system was constructed and functioned, but due to an unavailability of larger motors could

not be tested in flight as the full-scale flights never flew above 5280 feet. Since the airbrakes

modify the external flight profile of the vehicle, the team understands this means the system cannot

be used at the competition. The data tracking components of the system will still be flown to assess

how the algorithm would function at the competition, as they have been flown with the full-scale

vehicle and do not affect the external aerodynamics of the rocket.

Section 3.3: Project Plan Changes

The project plan has been updated to account for the completion of the full-scale rocket and

completion of the Flight Readiness Review. The final hurdle for the team is the competition itself.

The team has also come in under budget, and has reflected that in the budget portion of the report.

Spare funds will be allocated to supporting materials for launch week and the Rocket Fair.

Section 4: Launch Vehicle

Section 4.1: Vehicle Changes

Section 4.1.1: Since CDR

The vehicle design has not changed substantially since CDR. Minor length additions have been

added to accommodate unexpected length in the motor tube section. Additionally, the team has

decided to not pursue the isogrid structure for the competition vehicle. This is mainly due to the

initial structure having a much higher weight than expected. This problem was compounded by

Page 23: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

23

approaching due dates which made analysis and implementing a solution infeasible. Mass

estimates have also been adjusted due to final construction weights

Section 4.1.2: During Construction

Upon completion of construction of an isogrid tube, the team realized that the design did not afford

the performance improvements expected. For this reason, the team decided to default to standard,

rolled carbon fiber tubes as these have a lower coefficient of drag.

Section 4.2: Systems Component Analysis

The vehicle was designed to satisfy mission requirements set forth by NASA in the 2017-2018

NASA Student Launch Handbook, as well as requirements set by the team. The vehicle design

ensured adequate space for avionics, payload equipment, and electronics. These systems are

crucial to the success of the mission. The vehicle design was also heavily driven by manipulating

weight and length to control altitude and stability. These factors determined the success of the

flight itself. The vehicle design was separated into three major divisions: structure, propulsion and

aerodynamics. These three divisions are all vital to the success of the flight and recovery of the

launch vehicle, as well as the success of the onboard experiments.

Section 4.2.1: Structure

The structure of the launch vehicle was designed to be able to withstand the forces the rocket will

experience during operation. The launch vehicle body was strong enough to maintain stable flights,

while accommodating all other subsystems, and ensuring they had adequate space and protection.

The design of the structure requires heavy tradeoffs between strength, space, and weight.

The total length of the rocket is 113.0 inches. Component lengths are shown in Table 4.1: Section

Lengths.

Page 24: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

24

Table 4.1: Section Lengths

Body Tubes:

The body tubes house all subsystems of the launch vehicle. These tubes comprise a majority of the

vehicle body surface exposed to the airflow. Therefore, the aerodynamic properties of the body

tubes are directly related to the altitude gained by the vehicle. Additionally, as the largest structure

in the rocket, the body tubes represent the largest collection of mass in the rocket, except for the

motor. To ensure mission success, it was critical to select and design body tubes that can survive

the stresses of high-powered flight while remaining light enough to achieve the mission altitude.

Initially, it was planned that the tubes would be constructed using carbon fiber braiding, a process

that involved taking individual strands of carbon fiber and stitching them into a tightly-wound

braid. The carbon fiber braids produced, were formed into an isogrid structure around a 6-inch

mandrel, which was pre-wrapped with a layer of carbon fiber already to make bonding the internal

systems to the body tubes easier. Isogrid structures are a lighter alternative to using a solid tube

structure. For aerodynamic purposes, a thin layer of basalt fiber was filament wound around the

structure to allow for a smooth aerodynamic skin. By giving the structure this skin, the result is a

lightweight, aerodynamic body. Using this wrapped isogrid method, the mass of the body tubes

were projected to be decreased by approximately 20 to 30 percent less than if the tubes were

constructed using only filament wound carbon fiber, while also maintaining the same compressive

strength properties as a carbon fiber tube. The isogrid tubes were generously manufactured and

provided by Highland Composites.

Section Length (in.)

Nose Cone 20

Avionics Section 36

Rover Section 18

Airbrake Section 12

Booster Section 27

Total 113

Page 25: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

25

Both the isogrid and solid-tube airframes were manufactured and flown over the course of the

project, and despite promising initial estimates the isogrid structure came in at a much higher

weight than was expected. The team believes that the added weight came from issues in the method

used to wrap the airframe. Mostly due to time constraints and the end of available launch

opportunities, the team was unable to manufacture a newer iteration of the isogrid structure, but

the team feels confident that this manufacturing method will provide large weight savings for

future airframes. After much discussion, it was decided to select the solid carbon tube design due

to the simplicity of manufacturing and quickly approaching deadlines.

Couplers:

The couplers serve as a joint between two body tube sections. The couplers must be able to

withstand forces experienced during rocket ascent to keep the structure of the body attached. The

upper body tube was attached to the booster section with 3 aluminum bolts. The team has decided

to use fiber glass to create the couplers. This choice of material reduces risks which can lead to

separation of the upper body from the booster section in mid-flight. With the trade-off of an

increase in mass and more difficult construction for strength, fiber glass was considered to be a

very safe and reliable option. Fiber glass also has the additional benefit of being non-conductive,

thus it was ideal for making the coupler which was holding our electronics, the avionics bay. This

will reduce the issues the team has had in the past when it comes to being able to communicate to

the electronics inside the vehicle, such as GPS systems.

Bulkheads:

Bulkheads are typically flat plates used to increase the structural strength of a rocket. They are also

used to create airtight spaces and to divide the body into separate compartments. In rockets, they

are commonly used to separate payload bays and to mount equipment for avionics and payloads.

For rockets similar in size to the Project Nova rocket, the material used varies from fiberglass to

plywood to carbon fiber. The bulkheads for this rocket were made from pre-impregnated carbon

Page 26: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

26

fiber. This was chosen due to the simplicity of manufacturing with pre-impregnated carbon fiber.

The interior diameter for the circular cross-sectional rocket was 6 inches and the bulkheads were

designed to fit perfectly into this size. All bulkheads for this rocket was 0.25 inches thick.

Centering Rings:

The purpose of the centering rings is to center a smaller cylindrical body or tube inside a tube of a

larger diameter. In the case of high powered model rocketry, centering rings can be used as an

engine block in motor mounts. The Project Nova rocket uses three centering rings. These centering

rings are located in the engine tube and serve to attach to the fin set and to attach to the motor

retention. The centering rings are made of carbon fiber and manufactured using the Computer

Numerical Control (CNC) machine at Auburn University Aerospace Design Lab due to the

availability and the teams experience with using carbon fiber. The centering rings have an outer

diameter of 6 inches with an inner diameter of 3 inches. The thickness of each ring is approximately

0.25 inch. The centering rings have a mass of 3.65 oz., determined from sample pieces.

Section 4.2.2: Propulsion

Figure 4.3: Motor Tube Rendering

Page 27: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

27

Motor:

The motor selected for the competition is the Aerotech L1420R. This is the same motor that was

used in CDR, and after minor modifications were made to the rocket, it still gave us the needed

altitude for the rocket. The specifications are listed below in Table 4.2: Motor Specifications.

Additionally, the thrust curve for this motor is shown in Figure 4.1: Motor Thrust Curve.

Figure 4.1: Motor Thrust Curve

This motor was chosen based on OpenRocket simulations, as it provides the roughly 8-to-1 thrust-

to-weight ratio desired for stable and predictable flight.

In addition, as shown in the motor thrust curve above, the motor achieves a higher than average

thrust after approximately one-quarter second, thus reaching the required 8-to-1 thrust ratio in

about one-quarter second. Based on OpenRocket simulations, the motor provided an apogee of

5866 feet with a max acceleration of 275 ft/s^2 which delivers a max velocity of 723 ft/s or close

to Mach = 0.65.

Page 28: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

28

Table 4.2: Motor Specifications

Motor Specifications

Manufacturer Aerotech

Motor Designation L1420R

Diameter 2.95 in

Length 26.2 in

Total Impulse 1038 lb·sec

Total Motor Weight 10.1 lbm

Propellant Weight 5.69 lbm

Propellant Type Solid

Average Thrust 326 lbf

Maximum Thrust 374 lbf

Burn Time 3.18 sec

Motor Tube:

To contain the motor on the rocket, a carbon fiber motor tube is being used. The motor tube was

made by braiding carbon fiber strands and then filament winding around a mandrel that was the

same diameter of the motor. The 3D braided carbon fiber material was chosen for its strength

relative to its weight when compared to a solid tube. Basalt fiber was considered to be used for the

motor tube for its high heat resistance properties, but the team decided the weight of the basalt,

which was approximately 50% heavier when compared with the carbon fiber was not worth the

tradeoff. The tube is 0.1-inch-thick and was designed to fit around an Aerotech L1420R motor.

To mount the motor tube, three centering rings were epoxied to the outer diameter of the motor

tube and the inner diameter of the lower section tube. The epoxy was a 24-hour epoxy, which will

create a permanent bond between the components. A bulk plate was epoxied forward of the motor

tube. This is to provide extra strength to hold the motor in place as well as separate the motor from

the internal components of the rocket.

Page 29: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

29

Motor Retention:

The purpose of the motor retention system is to secure the rocket motor during launch and flight

and to be easily removable for subsequent flights. The team chose a commercially bought

Aeropack bolt-on motor retention system, as shown in Figure 4.2: Motor Retention. This is a

simple system with two components. One component was bolted directly into a centering ring,

using aluminum bolts. The other component threads onto the part that is bolted onto the structure.

This allows for a fast replacement of a used motor. The team chose a commercial motor retention

system due to past reliability and to avoid the time requirements of designing and manufacturing

a custom system.

Figure 4.2: Motor Retention

Section 4.2.3: Aerodynamics

The aerodynamics system requires the rocket remain stable during flight. The placement and

design of the aerodynamic surfaces determines the center of pressure along the length of the rocket.

Page 30: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

30

Fins:

The stability of the rocket is controlled by the fins. The primary purpose of the fins is to keep the

center of pressure aft of the center of gravity. The greater drag on the fins will keep them behind

the upper segments of the vehicle, thus allowing the rocket to fly straight along the intended flight

path. They are also helpful in minimizing the chances of weather-cocking. Fins serve as an ideal

addition to the vehicle body as they are lightweight and easy to manufacture using the CNC

machine. A clipped delta planform was selected for the fins. Four fins was machined from 0.2-

inch-thick carbon fiber flat plates. A rendering of the fin design is shown in Figure 4.3: Fin

Rendering.

When attached, the trailing edge of each fin is located slightly forward of the end of the body tube.

This design feature provides some impact protection for the fins when the rocket hits ground.

Carbon fiber of 1.03 oz/in3 density has been selected as the material due to its stiffness, strength,

and light weight. The stiffness and strength of carbon fiber reduces the chance of fin flutter which

increases the vehicles chance of success during flight. Each fin has a surface area of 54 in2

(summing both sides), making the fin surface area total equal to 216 in2. The total component mass

is 13.5 ounces. These dimensions provide the vehicle with a projected stability of 2.7 calibers. This

Figure 4.3: Fin Rendering

Page 31: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

31

level of stability is close to ideal, as it is well above stable, yet still below over-stable. Detailed fin

dimensions are provided in Table 4.3: Fin Dimensions.

Table 4.3: Fin Dimensions

Fin Dimensions

Root Chord 6.25 in

Tip Chord 2.5 in

Height 6 in

Sweep 3.68 in

Sweep Angle 31.5°

Thickness .2 in

Aero-elastic flutter has been considered as a potential failure mode for the rocket structure. At a

particularly high velocity, the air is no longer able to sufficiently dampen the vibrational energy

within the fin. At this flutter velocity, the first neutrally stable oscillations are experienced within

the wings.

The flutter velocity is directly reflective of the aero-elastic conditions of the structure/fin system.

The catastrophic flutter phenomenon results from coupling of aerodynamic forces creating a

positive feedback loop. The increase in either torsion or bending drives an infinitely looped

increase in the other motion. Since it is assumed that the fins are rigidly fixed and cantilevered to

an infinitely stiff rocket body, the fin twist (torsion) and fin plunge (bending) are the only two

degrees of freedom.

Once this flutter velocity is exceeded, the air, inversely, amplifies the oscillations and significantly

increases the energy within the respective fin. As velocity increases, the fin twist and plunge are

no longer damped. At this velocity, known as the divergent speed, one degree of freedom usually

diverges while the other remains neutral. Structural failure usually occurs at or just above this

velocity. Due to certain failure of the structure associated with potential aero-elastic flutter, the

flutter velocity is applied to the design as a “never-to-exceed” parameter.

Page 32: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

32

There are various ways to minimize the chances of experiencing fin flutter. Increasing fin retention

by strengthening the joints between the fins and rocket body is one way to supplement system

stability. Furthermore, additional layers of carbon fiber and epoxy applied to portions of the fins

as well as the joints should provide extra defense against aero-elastic flutter.

Nosecone:

The coefficient of drag affects the overall performance of the rocket in flight. The goal for the team

was to select a nose cone shape with a low drag coefficient to maximize performance. Utilizing

the software OpenRocket, the four cone types were compared using the already chosen dimensions

for the rocket. The team decided to increase the fineness ratio of the nosecone, increasing to a near

5-to-1 ratio versus the initially designed near 3-to-1 ratio. This change has been made due to the

increased stability that a 5-to-1 provides, and the team can easily acquire these nose cones by

purchasing them from several vendors. The material for the nose cone was also changed to be fiber

glass, as this is the most common material sold by these vendors.

Section 4.2.4: Schematics

Figure 4.7: Final Rocket Design

Page 33: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

33

Figure 4.7: Booster Tube Dimensional Drawing

Page 34: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

34

Figure 4.8: Engine Block Dimensional Drawing

Page 35: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

35

Figure 4.4: Lower Booster Section Dimensional Drawing

Page 36: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

36

Figure 4.5: Upper Body Tube Dimensional Drawing

Page 37: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

37

Figure 4.6: Upper Section Assembly Dimensional Drawing

Page 38: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

38

Figure 4.7: Centering Ring Dimensional Drawing

Page 39: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

39

Figure 4.8: Bulkhead Dimensional Drawing

Page 40: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

40

Figure 4.9: Fin Dimensional Drawing

Section 4.3: Flight Reliability Confidence

Section 4.3.1: Fin Shape and Style

The three most common planforms are clipped delta, trapezoidal and elliptical, as shown in Error! R

eference source not found.. In most situations, the elliptical fin design is the optimal design choice

for model rockets. This is due to their lower drag and superior lift forces compared to various other

fin designs, allowing for the highest altitudes. The downside, however is a far lower stability, and

as previously mentioned, the drag is needed for better stability and a solid flight path. Most

importantly, there is little room for error when it comes to the construction of an elliptical fin. So,

if all four fins are not identical in shape and weight then this will lead to undesirable flight results.

Page 41: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

41

Another variable the team considered while designing the fins is fin flutter. The excessive amounts

of fin flutter in elliptical shaped fins only causes more instability. So, even with the advantage of

an optimal altitude, it does not justify the several other complications that will arise during the

construction process. The clipped-delta fin, being a variation of the trapezoidal fin, gives excellent

stability, offering a slight stability advantage over the plain trapezoidal due to having more surface

area aft of the chord of the fins midpoint. The simplicity of the clipped-delta fin design also allows

for an easy and accurate construction process. Though elliptical fins do give a slight advantage

when it comes to altitude, the team has decided to implement the clipped-delta fin design due to

its increased stability.

Figure 4.10: Fin Shapes

The fins were manufactured from the same carbon fiber plates as the bulkheads and centering

rings. The same data used to verify the bulkheads and centering rings was used to ensure the fins

can withstand any inflight or landing forces.

To verify that the size and shape of the fins allows for stable flight, simulations were conducted.

There were also been two subscale flights which further verified the simulation data. Multiple full-

scale test flights were performed to visually verify no anomalies are present on the fins during

flight.

Page 42: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

42

Section 4.3.2: Materials

Body Tubes:

The structural tubes of the launch vehicle were constructed using a rolled braided carbon fiber

structure. As this is something the team has not done in past years, structural data was collected

for this structure. To do this, using the same material and manufacturing method, a test sample

was made consisting of an equal diameter of the tubes that was used on the launch vehicle. This

sample was then placed into a load cell to determine the maximum load of the structure. This

allowed us to determine that the structure is capable of safely completing the mission. The structure

experiences a maximum of 300 lbs during flight, to meet the factor of safety requirements the tube

structure must fail at or above 600 lbs of force during testing.

Bulkheads and Centering Rings:

The bulkheads and centering rings were manufactured by cutting a flat carbon fiber plate with a

CNC machine. To verify these components can handle the expected loads, sample pieces of the

carbon fiber were made. These samples were manufactured using the same material that the

bulkheads and centering rings was made of. The samples were placed in a three-point bending test

as well as a tensile stress test.

Coupler:

To verify the coupler functions correctly, ground tests of the separation was performed. Once

proven on the ground, a subscale flight test using this coupler component was used.

Section 4.3.3: Assembly Procedures

Manufacturing of the vehicle generally takes two weeks to produce and assemble the components.

To account for this the team started manufacturing three weeks prior to any scheduled launches.

Page 43: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

43

This allowed for one extra week if any problems arise during the manufacturing process. The

typical manufacturing schedule can be seen in Error! Reference source not found..

Table 4.4: Manufacturing Schedule

Week Events Percentage of

Completion

1

Manufacturing of Major

Components Such as body

tubes, fins, centering rings,

etc.

50%

2

Begin assembly of

subsystems such as the

booster section and the fin

assembly.

90%

3 Assemble completed

rocket 100%

Manufacturing body tubes using braided structures is a very time-consuming process. These tubes

are the most time-consuming component to manufacture and the event of a crash would have

negative effects on the team’s timeline. Luckily, Highland Composites generously agreed to

produce the braided carbon fiber tubes. Unfortunately, these tubes arrived far too late into the

project for in-depth analysis and revisions. To mitigate the effects of a total loss crash, multiple

tube sections were produced, which allowed for the construction of three full scale rockets, one

with braided body tubes and two with non-braided body tubes.

Several flat plates of carbon fiber were produced at various thicknesses. The plates were placed in

a CNC router to be shaped into flat components. These components include fins, bulk plates and

centering rings.

Page 44: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

44

Section 4.4: Mass Statement

The mass of the rocket and all its subsystems was calculated using optimal mass calculations from

OpenRocket. In addition to using final masses from last year as a basis, a brick sample of carbon

fiber was created to have an accurate density measurement since most of the parts was

manufactured using carbon fiber. This density test is exceedingly important given the method of

mass estimation. Since construction methods vary drastically from each manufacturer, as well as

different resin and cloth systems varying, it is highly important to get an accurate model of the

density.

Having determined an accurate density for the carbon fiber of the rocket, and the structure of the

rocket being the most significant portion of the weight of the structures of the rocket, the team

used estimates from last year’s rocket to determine the initial size estimate of the rest of the

subsystem components. The final weights of the rocket and its components are displayed in Table

4.5.

Table 4.5: Mass Estimations

Section Mass (lb) Percentage

Structure 15.4 40.10%

Motor 10.1 26.30%

Rover 3.9 10.15%

Recovery 7 18.23%

Airbrake 2 5.21%

Total 38.4 100%

Section 4.5: Manufacturing Process

With the success of subscale rocket, the team’s initial design was validated and construction on

the full sale rocket began. The primary iteration of the rocket was constructed using solid carbon

Page 45: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

45

fiber tubes in order to quickly create a rocket to test the various electrical subsystems of the rocket.

This would allow the team to validate all the sub-systems without waiting for the complex and

time-intensive isogrid airframe. These solid carbon tubes were manufactured in the student

laboratory using pre-preg carbon fiber and a steel mandrel. The team has a large wealth of

experience with this manufacturing method, so confidence was high in the quality of these tubes.

Figure 4.11: Booster Section Diagram

The most time intensive portion of the airframe to manufacture is the booster section, regardless

of whether the tube is isogrid or solid carbon. This is primarily due to the precision necessary to

align the fins and the time it takes for the 24-epoxy to set. The section must be assembled in stages

to ensure proper alignment. Small deviations in the orientation of the fins or motor tube can cause

the rocket to be unstable upon launch. The process begins with the installation of the bulkhead that

will rest at the front of the motor tube. This takes place but first using 5-minute epoxy to secure

the plate, and then adding filets of 24-hour epoxy around the edges of the bulk-plate to reinforce

Page 46: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

46

the plate and ensure stability. These filets are placed on the front and back portions of the bulk-

plate. This fileting procedure will be repeated for many of the other components of the rocket.

Next, the motor tube will be installed into the rocket. Prior to insertion into the booster section, a

centering ring was secured to the motor tube to ensure alignment. This centering ring was

positioned such that, once inserted, it will align with the leading edge of the fins. It was secured

using 5-minute epoxy and then 24-hour filets. It was checked with a level to ensure correct

orientation. Once the motor tube / centering ring assembly was inserted into the rocket, it was

secured using epoxy filets.

After the motor tube is secured in the assembly, the fins can be inserted and epoxied. This is the

most tedious and time-consuming process as each fin must be inserted and secured individually

and checked against a fin-jig that was cut out using the laser cutter and a sheet of ply-wood. The

fin-jig is used to ensure proper alignment of each fin which in turn helps guarantee the stability

of the rocket.

Each fin is secured using epoxy filets on each contact point in the rocket. For example, each fin

will have 6 epoxy filets, 2 on the motor tube, two on the interior of the airframe, and two on the

exterior of the airframe. This is to ensure the fins are locked into place and to guarantee

structural stability. This extra epoxy does cause a decent increase in weight, but the team is

confident that the added weight is worth the stability.

Page 47: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

47

Figure 4.12: Fin-Jig

Once the fins are secured, the final two centering rings were inserted and secured using epoxy

filets. One centering ring butts up against the trailing edge of the tail fins, the other is flush with

the back of the rocket.

All other sections of the rocket are fairly easy to produce as they are just tubes with minor

modifications and length differences. Any bulkhead attachments are preformed using the same

method of epoxy fileting described previously.

Page 48: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

48

Figure 4.13: Isogrid Manufacturing Process

This method is the same for the isogrid airframe, but with an initial filament winding portion.

The primary objective of the filament winding was to ensure air tightness for pressurization, as

well as for aerodynamics. For the isogrid airframe, the team decided to use basalt fiber for its

weight and strength properties. A filament winder was used to apply the fiber to the exterior of

the isogrid airframe. The individual sections of the airframe were then placed in the oven at 60°C

to accelerate the curing process. Issues were encountered with the fiber width, but due to time

constraints, no analysis or solution was able to be implemented.

Page 49: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

49

Figure 4.14: Isogrid Manufacturing Process – Filament Winding

Section 5: Recovery System Design

The overall design of the Auburn Student Launch team’s recovery system has not changed at all

since its original as it has worked as designed on the subscale flight and both full-scale test flights.

This design used an augmented dual-stage recovery system with a drogue parachute deployed at

an apogee height of 4433 ft, an upper main parachute deployed at 1000 ft. and a lower main

parachute deployed at 750 ft. At apogee, the nose cone, drogue parachute and upper main parachute

were all ejected using redundant black powder charges. When the upper main parachute was

ejected, it was held closed by the Jolly Logic Chute Release System. At 1000 ft. the Jolly Logic

System released and deployed the upper main parachute with the rocket still in one piece. After

the rocket had coasted down to 750 ft. a second set of redundant black powder charges detonated

and separated the rocket, pulling the lower main parachute from its housing. Using this

configuration, the entire rocket fell under a single drogue parachute from apogee until the second

Page 50: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

50

event occurred where the rocket separated into two separate pieces and fell under two separate

main parachutes. The nose cone and drogue parachute remained attached via shock cord to the

upper section after separation.

Section 5.1: Structural Elements

The centerpiece of Auburn's recovery system is the Barometric Avionics Enclosure (BAE). Every

recovery subsystem is either attached to or contained inside the BAE. The BAE is formed by a 12-

inch-long cylinder of fiber glass. A comparison showing why fiber glass was chosen over carbon

fiber can be seen in a Pugh chart below in Error! Reference source not found.. As for the design o

f the BAE, there is one inner bulk plate attached inside of the BAE that serves as the top cap of the

avionics bay. Inside the avionics bay there are two sets of 3D printed rails to secure the avionics

board. Both altimeters and their batteries are mounted to this board. The bottom of the BAE is

closed off by another bulk plate. The two bulk plates are linked by two rods and secured by locking

nuts on the outside of the BAE. Both bulk plates have a single open hole to allow the ejection

charge wires to run from the altimeters to their proper e-matches. Each hole has two charge wire

pairs that run through it to minimize the chance of the sensitive recovery electronics being

damaged by the pressurization that occurs when the black powder charges are deployed. This

isolation of pressure also helped to reduce the amount of black powder needed for each charge.

Table 5.1: Pugh Chart of Carbon Fiber vs. Fiberglass Material for the BAE

Weight Fiberglass Carbon Fiber

Altimeter Signal

Disruption

3 3 1

Strength 2 2 3

Page 51: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

51

Ease of

Manufacturing 1 3 2

Total 16 9

The BAE served as the coupler between the upper and the lower parachute housings. Each section

was secured to the BAE with three machine bolts per section. Neither of these sections separated

once the rocket was assembled. On the outside of the BAE is a ring of the vehicle body tube taken

from the same tube the upper section is constructed from. This was done so the tube connections

between the upper parachute housing, the BAE, and the lower parachute housing were continuous

and smooth, minimizing the impact on the aerodynamic performance of the rocket. This ring is the

only surface of the BAE that is on the outside of the rocket, so two key switches and two pressure

holes are located along this ring. The key switches located on the ring allowed the team to

externally arm the altimeters while the rocket was assembled and sitting on the launch rail.

A single U-bolt was mounted to the top bulk plate of the BAE for the upper parachute assembly

to be mounted to. This location was chosen as it is the only point in the upper section where the

parachutes can be tethered to keep the rocket in an upright position and minimize the chance of

the parachute tearing when deployed. The lower main parachute was connected to a second U bolt

mounted to the bottom of the Rover section. This mounting location was chosen because it is the

only point where the lower parachutes can be mounted while also keeping the charge cups next to

the BAE, thus minimizing the potential for error with the e-matches and decreasing risk of the

rover getting stuck when it was being deployed after landing.

Section 5.2: Materials

The materials that were chosen to create the team's recovery system had a direct effect on the

success of the system. Failure of the recovery system materials to survive the ejection charges

would have caused an inadequate landing of the vehicle, and severe damage to the rover payload.

Page 52: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

52

The chosen materials for the parachute, shock cord, and bulkhead attachment were rip-stop nylon,

paracord, and U-bolts, respectively.

Ideally, the chosen material for the parachute allow it to be sturdy to be used in multiple tests and

launches. The factors that were used to assess the suitability of different parachute materials to

allow for recovery system requirement satisfaction are strength, durability, and weight. Rip-stop

nylon was chosen over cotton fabric as our parachute material for several reasons. Rip-stop nylon

weighs about 2.75 oz. per square yard while cotton fabric weighs about 4.3 oz. per square yard.

Rip-stop nylon has a tensile strength of 1500 psi while cotton fabric has a tensile strength of 400

psi. Additionally, rip-stop nylon will stretch up to 40 percent of its length before breaking while

cotton will stretch up to 10 percent. The Pugh chart shown below in Table 5.2: Parachute Materials

Pugh Chart as well as our two successful full-scale test flights confirmed the choice of rip-stop

nylon for the parachute material.

Table 5.2: Parachute Materials Pugh Chart

Rip-stop Nylon Cotton fabric

Strength 3 1

Durability 3 1

Weight 3 2

Totals 9 4

The shock cord must be able to survive the same events as the parachute. The materials that were

considered for shock cord and shroud lines are Paracord, 1-inch Tubular Nylon, and Kevlar.

Paracord is extremely light, strong for its weight, and does not take up much space. The only

possible problem with paracord was that it can only withstand 550 pounds of force before failure.

However, the other benefits of paracord made it an ideal material for the drogue shroud lines, since

the drogue did not create much drag force and did not put as much tension on the shroud lines.

Page 53: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

53

Tubular nylon consists of a nylon tube which is made from exceptionally high strength material

which is both light and strong. Tubular nylon is easy to handle and cost efficient. The wrap around

webbing increases the overall strength per inch. Tubular nylon is highly flexible and pliable. Due

to its pliability, it tends to glide better over rough or jagged surfaces preventing the wear and tear

that occurs more with Kevlar. One-inch width of tubular nylon webbing can withstand about 4000

pounds of force. For the main parachutes, which create more drag force, the shroud lines were

made from this material. Tubular nylon has a much higher strength and also allowed the team to

use a double seam across either side of the shock cord, ensuring the stitch is stronger as well.

While tubular Kevlar is stronger, the strength of tubular nylon is more than sufficient for the needs

of the mission. In addition, the pliability of nylon will allow the shock cord to better absorb the

shock of ejection and ensure smooth movement of the potentially rough surfaces inside the upper

section. By using a material known to be strong, the team ensured failure is less likely to happen

in this component. The pliability and strength of tubular nylon led to the team choosing to use it

as our material of choice for shock cords. The Pugh chart that was used to evaluate which material

was chosen for the parachute is shown in Table 5.3: Comparison of Paracord, Tubular Nylon,

Kevlar.

Table 5.3: Comparison of Paracord, Tubular Nylon, Kevlar

Paracord 1-inch Tubular Nylon Kevlar

Volume 3 1 2

Weight 3 2 2

Strength 1 2 3

Durability 1 2 1

Pliability 3 3 1

Flexibility 3 3 2

Page 54: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

54

Total 14 13 11

Nylon shear pins were used to attach the nosecone to the BAE and the lower parachute housing to

the rover section to prevent drag separation. In the team’s configuration, #4-40 nylon screws were

used to secure these sections. These machine screws have a double shear strength of 50 lbs. Ground

testing was performed on these shear pins prior to launching to ensure safety and eliminate the

possibility of manufacturing discrepancies.

The materials used to attach the shock cord to the bulk plates was chosen appropriately. The team

used U-bolts to attach the parachutes to the bulk plates, because U-bolts have proven to be more

reliable in the team’s past. Shock cord can become easily tangled, and an eye bolt is more

susceptible to failure for this reason, as the shape allows cord to wrap around it. U-bolts also

provide two points of attachment to the bulk plate while eye bolts only provide one. The factors

that were used to assess the suitability of different bulk plate attachment materials to allow for

recovery system requirement satisfaction are strength and an ability to limit cord tangles. The Pugh

chart that was used to evaluate which material was chosen for the parachute is shown in Table 5.4:

Comparison of U-bolts and Eye-bolts.

Table 5.4: Comparison of U-bolts and Eye-bolts

U-bolt Eye-bolt

Attachment Strength 3 2

Limits cord tangles 3 1

Totals 6 3

All components that were mentioned were flown on both of the teams’ full-scale test flights and

performed as designed. The three of the parachutes and their shock cord provided the drag required

Page 55: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

55

to slow down the separate sections of the rocket to put it well below the required kinetic energy

limit all while remaining usable for following launches.

Section 5.3: Ejection

4F black powder was chosen for the ejection of the team's parachutes. Black powder is an effective,

reliable means of pressurization that the team has had success with in the past and worked to a

superb level again this year. Compared to CO2 ejection, black powder can produce greater

pressures per cubic inch required to house the system. A comparison between CO2 and black

powder can be seen in Table 5.5: Comparison of Black Powder and CO2.

Table 5.5: Comparison of Black Powder and CO2

Criteria Black Powder 𝐂𝐎𝟐

Pressure Produced per

Volume 3 1

Damaging Heat Produced 1 3

Cost 3 2

Ease of Integration 3 1

Reliability 2 1

Total 12 8

For the both events, two charges were placed within 3D printed charge cups and armed with

electronic matches: the first charge is the primary means of ejection, and the other is a backup

charge for redundancy and to decrease the chances for failure of the recovery system. The

redundant apogee charge was set to fire 1 second after the first charge. The charges are not ignited

Page 56: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

56

at the same time as that has the potential to cause damage to the airframe, shock cord and

parachutes.

Black powder, when ignited, can be approximated as an ideal gas. Testing has proven to be

successful and helped guarantee the validity of the team’s calculations. The Ideal Gas Law was

used to calculate an estimate for the amount of black powder needed for ejection. The Ideal Gas

Law is as follows:

𝑃 × 𝑉 = 𝑛 × 𝑅 × 𝑇

𝑅 = 265.9𝑖𝑛 − 𝑙𝑏𝑓

𝑙𝑏𝑚 × 𝑅 𝑇 = 700R°

Ignoring the volume of the parachutes and other recovery systems contained within the upper

section, a conservative volume for the upper section can be calculated with an inner diameter of 6

inches and a length of 14 inches as:

𝑉 = 𝐴 × 𝐿 =𝜋

4× 𝑑2 ×= 395.8 𝑖𝑛3

Using this equation, the team calculated the amount of black powder needed to produce pressures

sufficient to shear the nylon screws attaching the nose-cone to the upper section. Assuming 3

nylons screwed each rated for 50 psi of shear, pressure required to shear the nylon screws is:

𝑃 =3 × 𝐹

𝜋4 × 𝑑2

= 5.3 𝑝𝑠𝑖

Which, in conjunction with the previous equations, yields a charge size for 4F black powder of:

𝑛 =𝑃 × 𝑉

𝑅 × 𝑇×

453.592𝑔

𝑙𝑏𝑚= 4.74 𝑔

Applying a factor of safety of 1.5 to the above calculations, 7 grams of black powder was estimated

as the required amount of black powder needed per charge. During testing, a 6 gram charge of

black powder separated both the upper and lower sections without any trouble so the team was

confident a 7 gram charge would be sufficient on launch day. This was confirmed through both

sections successfully separating on both full-scale test flights.

Page 57: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

57

Both charge sections were filled with fireproof cellulose insulation (colloquially known as “barf”)

to protect the parachutes from the heat of the ejection charges. The first event deployed the drogue

parachute and the rifled upper main parachute, held closed by our Jolly Logic chute release system.

The second event consisted of the second set of charges igniting to separate the rocket and deploy

the lower main parachute as well as the mechanical release of a pin in the Jolly Logic system, thus

allowing the upper main parachute to deploy.

The AUSL team utilized the Jolly Logic system in series for redundancy in the recovery systems.

It is an efficient system that doesn’t require any black powder charges and has its own self-

contained batteries which decreased amount of wires connected to the altimeter bay, as well as

reduced risk of entangled shock cord in the main body.

Figure 5.1: Redundant Jolly Logic System

The Jolly Logic system allowed for the deployment of both a drogue and main parachute

simultaneously in a single separation. This system deployed more parachutes with fewer

separations, thus reducing the chance of failure of the recovery portion of flight. The only

parachute that utilized the Jolly Logic Chute Release System was the upper main parachute.

Page 58: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

58

Figure 5.2: Jolly Logic Chute Release

The Jolly Logic system consists of an independent altimeter device which releases a mechanical

pin an altitude that is preset at (target height 1000 ft.). The pin was connected to the Jolly Logic

device via a rubber band which provided tension on the pin so that when it was released, it was

pulled from its socket. Since the Jolly Logic system consisted of rubber bands which could easily

break if put under stress, the recovery system was set up so that tension from the shock cord was

never transferred to the Jolly Logic devices. To achieve this, the main parachute was not folded

with the shock cord inside as is normal. Instead the parachute was located on the shock cord so

that the shroud lines were at full extension and so that the drogue line, which ran through the main

parachute spill hole was able to deploy to its full length during the initial separation. The main

parachutes were then carefully gathered and positioned in the body tubes so that the drogue line

pulled it out without putting any forces on the actual parachutes and Jolly Logic system.

To preserve the redundancy of the recovery system, two Jolly Logic chute releases were used in

series to gather the upper main parachute. If either of the Jolly Logic devices happened to

malfunction, the other still would have released, thus allowing the main parachutes to deploy.

Page 59: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

59

Section 5.4: Parachutes

Auburn’s augmented dual deploy recovery approach made use of three separate parachutes

designed and constructed in house by the AUSL team. The team has been constructing its own

parachutes in house for five years and has refined its manufacturing process to produce quality,

custom chutes that produce the desired drag and drift for all sections of the rocket.

The drogue parachute is a small, circular parachute constructed of rip-stop nylon with paracord

shroud lines. Following the first event at apogee, the drogue along with the upper main parachute

bundled with a jolly logic chute release system deployed from the top of the rocket. This stabilized

descent until main deployment at the second event. The drogue parachute was designed to bring

the rocket down at a velocity of approximately 100 ft/s. This velocity minimized the drift of the

rocket while still having a stable descent. The drag coefficient of 0.8 for a fully inflated circular

parachute that was determined from research was confirmed in both full-scale flights.

𝐴 = 2 × 𝐹

𝜌 × 𝐶𝐷 × 𝑉2

Where F is force, ρ is density of the air, CD is the drag coefficient and V is descent velocity. The

team used this equation to calculate an appropriate area for the drogue parachute.

𝐴 = 2 × 32𝑙𝑏𝑚 × 32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡3 × 0.8 × (100𝑓𝑡𝑠 )

2 = 3.37 ft2

These calculations yielded a circular drogue with a 24.9-inch diameter. The actual descent velocity

of the rocket under drogue for the full-scale test flight was 94.3 ft/s.

The recovery system has two main parachutes constructed of rip-stop nylon with 0.5-inch tubular

nylon shroud lines. The main parachutes are a hemispherical shape. The hemispherical shape can

be more difficult to manufacture, but produced the most drag, allowing the rocket to have

maximum drag with minimum weight. A Pugh chart comparing different parachute shapes can be

seen below in Table 5.6: Parachute Shape Pugh Chart.

Page 60: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

60

Table 5.6: Parachute Shape Pugh Chart

Baseline Square Circular Hemispherical

Drag Produced 3 1 1 2

Ease of

Manufacturing

2 1 2 1

Stability 1 2 1 1

Total 7 8 9

The shape of the main parachutes and their gores can be seen in Figure 5.3: Gore Template and

Figure 5.4: Parachute Template. When the rocket reaches 750 feet in altitude, a second charge

separates the top section of the rocket to release the lower main chute, and the jolly logic chute

release system releases the bundled upper main chute. A spill hole was added to the main

parachutes. This spill hole is necessary with our configuration of dual-deployment from the same

compartment at the top of the rocket body. The diameter of the spill holes were made to be 20%

of the total base diameters of the chutes. The 20% diameters of the spill holes are chosen because

it only reduces the areas of the parachutes by about 4%, allowing enough air to go through the spill

hole to stabilize the rocket while marginally altering the descent rate.

Page 61: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

61

Figure 5.3: Gore Template

Figure 5.4: Parachute Template

Parachute areas for hemispherical shaped chutes were determined using the following equation:

𝐴 = 2 × 𝐹

𝜌 × 𝐶𝐷 × 𝑉2

Where F is force, ρ is density of the air, CD is the drag coefficient and V is descent velocity. The

team used this equation to calculate an appropriate area for the main parachutes so that the kinetic

energy of either section of the rocket did not exceed 75 ft-lbs during recovery and remained within

safe limits.

Page 62: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

62

𝐴𝑈𝑝𝑝𝑒𝑟 =2 × 14𝑙𝑏𝑚 × 32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡3 × 1.31 × (15𝑓𝑡𝑠 )

2= 40.00 𝑓𝑡2

𝐴𝐿𝑜𝑤𝑒𝑟 =2 × 24𝑙𝑏𝑚 × 32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡3 × 1.31 × (11.5𝑓𝑡𝑠 )

2= 116.66 𝑓𝑡2

Table 5.7: Parachute Dimensions

Upper Chute Lower Chute

Area 40.00 ft2 116.66 ft2

Diameter 60.5 in 103.4 in

Diameter of Spill hole 12.1 in 20.7 in

Number of Gore 6 8

Width of Each Gore at Base 31.7 in 40.7 in

Height of Each Gore 47.5 in 81.15 in

Circumference at Base 190.1 in 27.1 ft.

The team decided to move from 6 gores to 8 gores for the lower main parachute. The main reason

for this change is that the template the team would have to print out for a 6-gore hemispherical

parachute would simply be wider than any printer available to the team would be able to print.

Moving to an 8-gore configuration also increases the accuracy of the parachute to a true

hemisphere.

Page 63: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

63

Section 5.5: Altimeters

The avionics bay houses two altimeters to satisfy redundant system requirements. Both altimeters

fired the apogee charge at the apogee height of 4433 ft to eject the nosecone and thus the drogue

and bundled upper main parachute. Then both altimeters fired the main deployment charges at an

altitude of 750 ft. Neither set of charges are fired at the exact same time. A one and three second

delay has been placed between the firing of the apogee and main charges respectively to ensure

the structural integrity of the rocket and parachutes are maintained.

The team used one Altus Metrum TeleMega as the primary altimeter and one Altus Metrum

TeleMetrum as the secondary altimeter. The TeleMega has 4 additional sets of pyro connectors,

allowing for future expansion if necessary. It can also have a second battery easily installed into

dedicated screw terminals for additional power for pyro ignition purposes. The TeleMega also has

a more advanced accelerometer for more detailed flight data acquisition. All the data gathered

from the launch was taken from this altimeter and confirmed by the secondary one. Using two

Altus Metrum altimeters made programming quick and easy, as they share an interface program.

This made any last minute or on-site adjustments across both boards simpler. Should one of the

Altus Metrum altimeters fail, the PerfectFlite Mawd or Stratologger can be used as additional

backup. All altimeters are capable of tracking in flight data, apogee and main ignition, GPS

tracking, and accurate altitude measurement up to a maximum of 25,000 feet. Figure 5.5: Altus

Metrum TeleMega Altimeter and Figure 5.6: Altus Metrum TeleMetrum Altimeter shown below

are pictures of the altimeters the team used.

Page 64: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

64

Figure 5.5: Altus Metrum TeleMega Altimeter

Figure 5.6: Altus Metrum TeleMetrum Altimeter

Another reason the Altus Metrum altimeters were used are their radio frequency (RF)

communication abilities. Both TeleMega and TeleMetrum are capable of communicating with a

Yagi-Uda antenna operated by the team at a safe distance at any point during the launch. It can be

monitored while idle on the ground or while in flight. While on the ground, referred to as “idle

mode”, the team can use the computer interface to ensure that all ejection charges are making

proper connections. Via the RF link, the main and apogee charges can be fired to verify

functionality, which was used to perform ground testing. The voltage level of the battery can also

be monitored, and should it dip below 3.8V, the launch can be aborted in order to charge the battery

to an acceptable level. Additionally, the apogee delay, main deploy height, and other pyro events

can be configured. The altimeter can even be rebooted. While in flight, referred to as “flight mode”,

the team can be constantly updated on the status of the rocket via the RF transceiver. It will report

Page 65: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

65

altitude, battery voltage, igniter status, and GPS status. However, in flight mode, settings can’t be

configured, and the communication is one way from the altimeter to the RF receiver. Figure 5.11

shown below demonstrates the process the altimeters go through to deploy the charges at each

event.

Figure 5.7: Altimeter Block Diagram

Isolating one altimeter system (altimeter, battery, and wires) from the other helped prevent any

form of coupling or cross-talk of signals. Isolation was realized via distancing the two systems,

Page 66: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

66

avoiding parallel wires, and twisting wires within the same circuit. Additionally, the most apparent

form of radio-frequency interference, the antenna, will resonate on wires any multiple of ¼ λ (1/4

of ~70cm). Avoiding resonant lengths of wire was done wherever possible. Should a wire happen

to be a resonant length and is unable to be shortened or lengthened, a low-pass filter can be

implemented to block the high frequency noise. Both altimeters and their batteries were mounted

on a carbon fiber board that slides into a set of rails. A small foam plate was placed between the

batteries and the altimeter board to ensure that the batteries did not short out. The altimeters and

batteries were mounted on opposing sides of the board, with one battery and altimeter per side.

Since carbon fiber is an effective shielding material (50dB attenuation), this board acted as

shielding between the two altimeters and minimize cross-talk as well as near-field coupling. This

board is also easily removable for connecting the altimeters to computers for configuration and for

charging the altimeters’ batteries.

Section 5.6: Recovery System Technical Drawings

Below are technical drawings of different aspects of the recovery system.

Figure 6.8: Technical Drawing of Charge Cup

Page 67: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

67

Figure 6.9: Technical Drawing of Altimeter Board Rails

Figure 6.10: CAD Model of BAE

Page 68: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

68

Section 6: Mission Performance Predictions

Section 6.1: Simulations

The launch vehicle was simulated using OpenRocket, an open source rocket simulation software.

The team is confident in this software’s ability to simulate a rockets flight due to past years success

with using OpenRocket. The rocket as it is modeled in OpenRocket is shown in Figure 6.1:

OpenRocket Model.

Figure 6.1: OpenRocket Model

The multiple runs of the simulation were conducted using various calculation methods and

assumptions such as wind speed as well as using different approximations for the earths shape.

Wind speeds were tested up to a maximum of 25 mph, which yielded only nominal changes in the

expected velocity, acceleration, or apogee. The same held for the different earth approximations.

Additionally, simulations were run where the temperature was varied between 50°F to 80° F. These

changes had no major impact on the projected values for velocity, acceleration and apogee.

Between all the different simulations the team ran, the results differed by approximately 1%.

Therefore, the following data is presented from a simulation run with 0 mph winds and standard

sea level conditions.

Table 6.1: Flight Simulation Data (Wind = 0 mph)

Old Flight Simulation Data (Wind = 0 mph)

Page 69: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

69

Maximum Velocity 739 ft./s

Maximum Acceleration 283 ft./s2

Launch Weight 38.4 lbm

Burnout Weight 32.71 lbm

Length 113 in

Maximum Diameter 6.25 in

Launch Stability 2.6 calibers

Velocity off Rod 80.9 ft/s

Figure 6.2: Altitude Vs. Time

Page 70: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

70

Figure 6.3: Velocity Vs. Time

Figure 6.4: Acceleration Vs. Time

Page 71: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

71

Section 6.1.1: Motor Thrust Curve

The simulated motor thrust curve for the selected motor can be seen below. The team is confident

that this motor selection will provide adequate thrust to propel the launch vehicle to 5280 ft.

Figure 6.5: Motor Thrust Curve

Section 6.1.2: Component Weights

Table 6.2: Component Weights

Component Weight (lbm)

Upper Body Tube 4.78

Lower Body Tube 4.64

Nose Cone 2.17

Page 72: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

72

Fins (4) .91

Centering Rings (3) .6

Motor 10.1

Motor Retention .3

Motor Tube 1

Rover and Bay 4.4

Airbrake System 2

Bulkheads .9

Electronics 1.5

Recovery Section 5

Total 38.4

Section 6.1.3: Stability

For the rocket to be stable during flight the center of pressure must be located aft of the center of

gravity. It is recommended for this size of rocket that the stability margin should be 1-2 calibers.

The stability margin for the rocket is predicted to be 2.6 calibers at the point of rail exit which is

comfortably above the minimum requirement of 2 calibers. Since the drag plate system will not be

flown, they do not factor into the stability. The team feels confident that having a stability margin

of over 2 calibers will allow the rocket to be stable without becoming overstable.

Page 73: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

73

Figure 6.6: Stability Vs. Time

Before flight, the center of pressure and the center of gravity are measured to be 89.13 inches and

72.852 inches from the top of the rocket, respectively. In Figure 6.6: Stability Vs. Time, the change

in the locations of the center of pressure and center of gravity can be seen for the entirety of the

flight. After apogee, the data for the stability drops off due to the deployment of the drogue

parachute. The increase in stability is due to the motor losing propellant mass due to motor burnout

as well as the decrease in velocity which moves the center of pressure away from the center of

gravity.

Section 6.1.4: Computational Fluid Dynamics

Computational Fluid Dynamics (CFD) is a branch of fluid mechanics that utilizes numerical

analysis methods and high-performance parallel computing to best analyze the flow properties and

fluid dynamic interactions of aerospace systems. Through CFD, the Navier-Stokes equations are

Page 74: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

74

solved numerically across a finite volume that encompasses the boundary conditions that comprise

the tested system. The finite volume is constructed through a series of successive steps, beginning

with the creation of a surface geometry through computer-aided design (CAD) software. The

surface data is then imported into mesh generation software, where domains are constructed

according to the specific boundary conditions inherent in the desired simulation. The exported grid

is then processed through a CFD software package, where flow parameters and boundary

conditions are specified, and a specific flow solution is chosen to account for various aerodynamic

phenomena (vorticity, viscosity, turbulence, and more), and numerical data approaches

convergence.

A new shell was constructed in SolidWorks to simulate the exterior of the rocket body, comprised

of the revolved nose-cone, uniform cylindrical body, and trapezoidal fin control surfaces. The

SolidWorks geometry was then exported in the form of a .STP file in order to be imported into

Pointwise mesh generation software. A farfield domain, in the form of a cylinder, was constructed

around the rocket body, extending roughly five rocket-body lengths in the aft direction, and two

lengths in the forward direction, while having a diameter many multiples of the rocket-body

diameter in order to maintain a farfield condition. The connection point discontinuities, apparent

after importation into Pointwise, between the nose-cone and the cylindrical body, and between the

trapezoidal fins and the cylindrical body, were resolved and smoothed.

Page 75: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

75

Figure 6.7: Nosecone Meshing

Grid spacing on the fins was also applied more uniformly through the leverage of anisotropic

tetrahedral meshing, and is evidenced in the following figure.

Figure 6.8: Tail-fin Meshing

The entire domain was processed through an anisotropic tetrahedral mesh extrusion, with the

cylindrical farfield as a “farfield” boundary condition, and the entire rocket-body defined as a

Page 76: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

76

“wall” condition, with a ∆s value of roughly 1.0x10^-7 (a value calculated as a function of the

Reynolds number of the simulated transonic flow).

Upon exportation of the grid, the TENASI CFD software package, developed by UT Chattanooga

and used by Auburn University, was utilized to construct separate parameter and boundary

condition files to test the freshly created grid with. Current research efforts are focusing on the

comparison between the use of an arbitrary mach flow regime with the Menter Scale-Adaptive

Simulation (SAS single equation) and the Spalart-Allmaras (SA single equation) flow solution

types. Preliminary analysis of the rocket-body grid flying at roughly Mach 0.65, with a post-

burnout center of gravity occurring roughly 1.25 meters aft of the origin of the coordinate axis

defined at the center of the nose-cone connecting ring produced coefficient of drag values, and are

shown in the following table. These drag coefficients were then inputted into OpenRocket to

ensure the use of accurate drag coefficients in the team’s simulations.

Table 6.3: CFD Drag Coefficient Results

Mach Number (M) Coefficient of Drag (C_d)

0.6 .532

0.725 .5375

0.750 .5425

Section 6.2: Kinetic Energy

The kinetic energy for the rocket upon impact can be calculated using the following formula:

𝐾𝐸 =1

2𝑚 × 𝑉2

Where m is mass and V is descent velocity. With a mass of 14 lbm and a recorded velocity of 15.8

ft./s for the upper section, this equation yields:

Page 77: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

77

𝐾𝐸 =1

14𝑙𝑏𝑚

32.2𝑓𝑡𝑠2

× (15.8𝑓𝑡

𝑠)

2

= 54.3 𝑓𝑡 ∙ 𝑙𝑏

With a mass of 24 lbm and a recorded velocity of 12.2 ft/s for the lower section, this equation

yields:

𝐾𝑒 =1

24𝑙𝑏𝑚

32.2𝑓𝑡𝑠2

× (12.2𝑓𝑡

𝑠)

2

= 55.5 𝑓𝑡 ∙ 𝑙𝑏

Section 6.3: Drift

The distance the rocket will drift during descent can be estimated with the following equation.

𝐷𝑟𝑖𝑓𝑡 = 𝑊𝑖𝑛𝑑 𝑆𝑝𝑒𝑒𝑑 ×𝐴𝑙𝑡𝑖𝑡𝑢𝑑𝑒 𝐶ℎ𝑎𝑛𝑔𝑒

𝐷𝑒𝑠𝑐𝑒𝑛𝑡 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦

However, this drift estimation assumes wind speed and descent velocity are constant and does not

account for the horizontal distance the rocket travels during ascent. There will be two stages of

descent. First, the rocket will descend under the drogue parachute from an altitude of 5280 ft. to

750 ft. At 750 ft. a second black powder series will occur separating the rocket into two pieces,

and the Jolly Logic parachute release system will separate and another event will occur releasing

a lower main parachute to safely escort the rover to the ground. The rate of descent under drogue

can be calculated with the following equation:

𝐷𝑒𝑠𝑐𝑒𝑛𝑡 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦 = √2 × 𝐹𝑜𝑟𝑐𝑒

𝐴𝑖𝑟 𝐷𝑒𝑛𝑠𝑖𝑡𝑦 × 𝐷𝑟𝑎𝑔 𝐶𝑜𝑒𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑡 × 𝑃𝑎𝑟𝑎𝑐ℎ𝑢𝑡𝑒 𝐴𝑟𝑒𝑎

Since this is a variation on the formula used to calculate the parachute areas, the resulting velocities

are the team’s desired descent velocities. However, as the competition progresses, this formula can

be used to update our predicted velocities with different drag coefficients, weights, or parachute

areas. This descent velocity will then be used to ensure drift is kept to a reasonable amount. An

assumed drag coefficient of 0.8 was estimated from research. Testing confirmed this as a

Page 78: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

78

reasonable value for the coefficient of drag. Assuming a total rocket weight after burnout of 32

lbm and a drogue diameter of 12.43 inches (3.37 ft2), the descent velocity under drogue is:

𝐷𝑒𝑠𝑐𝑒𝑛𝑡 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦 = √2 × 32𝑙𝑏𝑚 × 32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡2 × 0.8 × 3.37 𝑓𝑡2= 100

𝑓𝑡

𝑠

Assuming a total rocket weight of 32 lbm and an upper main parachute area of 40.00 ft2, the descent

velocity of the entire rocket before separation is:

𝐷𝑒𝑠𝑐𝑒𝑛𝑡 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦 = √2 × 32𝑙𝑏𝑚 × 32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡2 × 1.31 × 12.86 𝑓𝑡2= 22.7

𝑓𝑡

𝑠

Assuming a total upper rocket weight after burnout of 14 lbm and an upper main parachute area

of 40.00 ft2, the descent velocity of the upper section after separation is:

𝐷𝑒𝑠𝑐𝑒𝑛𝑡 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦 = √2 × 8𝑙𝑏𝑚 × 32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡2 × 1.31 × 12.86 𝑓𝑡2= 15.0

𝑓𝑡

𝑠

Assuming a total lower rocket weight after burnout of 24 lbm and a main parachute area of 116.66

ft2, the descent velocity of the lower section after separation is:

𝐷𝑒𝑠𝑐𝑒𝑛𝑡 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦 = √2 × 24𝑙𝑏𝑚 × 32.2

𝑓𝑡𝑠2

0.076474𝑙𝑏𝑚

𝑓𝑡2 × 1.31 × 116.66 𝑓𝑡2= 11.5

𝑓𝑡

𝑠

Estimated drift distances for a variety of wind speeds are shown below in Table 6.4: Drift

Calculations for Upper Section and Table 6.5: Drift Calculations for Lower Section. These tables

contain the total and the broken-down drift at each wind speed. The drift is broken down into three

Page 79: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

79

separate sections: Drift under drogue (5280 – 1000 ft), drift under upper main before separation

(1000 – 750 ft) and drift under each respective main after to separation (750 – 0 ft).

Table 6.4: Drift Calculations for Upper Section

Wind Speed

(mph)

Wind

Speed

(ft./s)

Drift Under

Drogue (ft.)

Drift Before

Separation

(ft.)

Drift Under

Upper (ft.)

Total Drift

of Upper

Rocket (ft.)

5 7.33 313.72 80.70 366.50 760.92

7.5 11.00 470.80 121.11 550.00 1,141.91

10 14.67 627.88 161.52 733.50 1,522.9

12.5 18.33 784.52 201.81 916.50 1,902.83

15 22.00 941.60 242.22 1,100.00 2,283.82

17.5 25.67 1,098.68 282.63 1,283.50 2,664.81

20 29.33 1,255.32 322.92 1,466.50 3,044.74

Table 6.5: Drift Calculations for Lower Section

Wind Speed

(mph)

Wind Speed

(ft./s)

Drift Under

Drogue (ft.)

Drift

Before

Separation

(ft.)

Drift Under

Lower (ft.)

Total Drift of

Lower Rocket

(ft.)

5 7.33 313.72 80.70 478.04 872.46

7.5 11.00 470.80 121.11 717.42 1,309.33

10 14.67 627.88 161.52 956.78 1,746.18

Page 80: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

80

12.5 18.33 784.52 201.81 1,195.48 2,181.81

15 22.00 941.60 242.22 1,434.84 2,618.66

17.5 25.67 1,098.68 282.63 1,674.20 3,055.49

20 29.33 1,255.32 322.92 1,912.90 3,491.14

The team understands that these are only predictions and not representative of how the rocket will

actually drift. The team also understands that recovery of our rocket can only be guaranteed up to

3500 ft. at the competition. However, the approximate reported wind conditions for the team’s

final launch at Sylacauga were 50 mph at a height of 1000 ft. Under these conditions, neither piece

of the rocket drifted farther than a mile from the launch pad. Given this data, and the fact that these

calculations were made on an assumption of an apogee of 5280 ft when the true apogee was 4433

ft the team must assume that the rough estimates we have tabulated are rougher than initially

supposed. Unless there is a significant amount of wind, the team believes that the rocket will stay

within the drift limits despite the rough calculations to the contrary.

Section 6.4: Simulation Verification

Multiple instances of the simulation, although not shown, were ran to verify the accuracy of the

simulation. Variables such as ambient temperature and wind speed changed the results by

approximately 1% and so were kept fixed. In addition, the simulation data was compared to the

subscale flight, full-scale flight, and CFD results to ensure an accurate drag coefficient for the

model. The team is confident that the simulation is accurate, yet understands that the model slightly

overestimates flight characteristics.

Page 81: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

81

Section 7: Full-Scale Flight Results

Section 7.1: Flight Data

Flight data for the subscale launch can be seen below in Figure 7.1: Full-scale Flight Data. The

flight occurred on the 17th of February 2018. The airframe was made of a solid carbon fiber tube

and flew on an Aerotech L1520T motor. We flew on this motor due to the lack of availability of

our desired motor, the L1420R. This figure represents the launch data of the full rocket and the

recovery data of the upper section of the rocket. The rocket reached an apogee of 4433 feet, had a

maximum acceleration of 350 ft/s2. The data verifies that the vehicle and recovery designs are safe

and within the limits of the competition.

Figure 7.1: Full-scale Flight Data

Section 7.2: Launch Day Simulation and Analysis

The following data is the OpenRocket simulation using the motor that was flown on the day of,

the L1520T. The data is quite similar to the flight results achieved at the launch. The team believes

Page 82: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

82

that the differences had to due to inaccurate weights obtained during the pre-launch checks and a

faulty scale. We believe that the current simulations will be valid for the competition providing we

ensure that the weights of each component are accurate prior to launch.

OpenRocket

Simulation

Recorded Flight

Data

Apogee (ft) 4552 4433

Max Velocity (ft/s) 620 567

Section 7.3: Full-scale Analysis

The full-scale flight characteristics are very similar to what the simulation model predicted.

Although the values are slightly off, the pre-launch weight values did not match the simulation

weights exactly. The team believes this accounts for the variation in flight data from predicted

data.

The physical subsystems of the vehicle all performed to expectations. The airframe handled all the

experienced loads, and the launch was stable. The winds at the launch were exceeding 50 mph

above the ground, yet the vehicle was neither under- nor over-stable. The vehicle was angled

slightly into the wind to mitigate drift, but flew straight otherwise.

The recovery system performed as intended, safely landing the vehicle. Despite the high winds,

the recovery system did not drift excessively. This leads the team to believe that the calculations

for drift may not be as accurate for a vehicle of this size as expected, and that they are an

overestimation of actual drift. The team decided this is acceptable, as it introduces a factor of

safety.

Page 83: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

83

The rover retainment system functioned, but the rover was unable to be deployed after landing due

to terrain that was more treacherous than could be expected at the competition. However, ground

tests confirm that Monica is able to traverse the obstacles that she will experience.

Section 7.3.1: Post-Launch Simulation

Using the data from the full-scale launch, the team estimated a coefficient of drag for the rocket of

.53. This value is very similar to the values obtained from CFD and from the subscale flight. A

simulation was performed after the launch with updated coefficient of drag and weight values. The

comparison of these results with the flight data can be seen below.

Updated

OpenRocket

Simulation

Recorded Flight

Data

Apogee (ft) 4489 4433

Max Velocity (ft/s) 586 567

These values more closely approximate the flight data. The team is confident this final simulation

model can accurately simulate the flight of the rocket. Additionally, the team would prefer these

values to overestimate apogee due to the importance of not exceeding the altitude limit.

Section 7.4: Full-Scale and Subscale Comparison

The full-scale rocket performed very similarly to the subscale rocket. Both of these test flights

have assisted the team in improving the simulation model for the competition flight. The most

important lesson learned from these flights is that the team must be careful when estimating the

Page 84: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

84

mass of different sections of the vehicle. Components tend to weight more than expected, most

likely due to additional weight from the epoxy bonding the carbon fiber composite material.

Both flights, however, did demonstrate the stability and safety of the design. The recovery and

ascent of both flights went perfectly. This is a boon, as it allows the team to iterate and improve

upon designs as often as the team has launch opportunities.

Section 8: Rover

Section 8.1: Design Changes

Section 8.1.1: Since CDR

Design changes to the rover since CDR are reflective of shortcomings noticed during testing; most

are minor tweaks to pre-existing subsystems/components.

The rover bay has been redesigned to be completely modular for ease of access and transportation.

The rover will be housed inside of a coupler with an extension (Figure 8.1: Rover Coupler Bay).

Two slats of wood will act as the platforms for the rover to rest on inside of the coupler. The bay

was changed from 3D printed nylon to wood for cost and time savings. The back of the rover

coupler bay has an eye bolt installed in it that will be used to secure the rover in the bay. Until tests

were performed, the rover was expected to stay in the bay as no forces would be acting on it to

eject it from the bay; the eye bolt acts as an anchor for the rover to latch onto.

Page 85: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

85

Figure 8.1: Rover Coupler Bay

A number of changes were made to the rover body. Holes were 3D printed into the body of the

rover for ease of component attachment. A panel was added in between the main motor housings

in order to prevent shorting of the motor leads. The solar panel deployment system was moved

closer to the end of the rover to allow for maximum solar exposure of the panels once deployed.

The length of the body was changed from 6.71 in. to 7.51 in. to incorporate a servo that is needed

to the hold the rover into the bay. Attached to the servo is an L-shaped bracket that will clamp

down on the eye-bolt in the back of the rover coupler bay. An arm was added to the back of the

rover for the L-shaped bracket to make a complete closure around the eye-bolt. A detail of the

servo system on the rover can be seen in Figure 8.2: Servo System.

Page 86: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

86

Figure 8.2: Servo System

After maneuverability tests, the team was satisfied with the tread design. However, the orientation

of the rover and it being able to right itself into a drivable position did present a problem. Going

back to a very early team design idea, bulbous wheels are being used to aid in the “righting” of the

rover after deployment. A top-down view of the wheels can be seen in Figure 8.3: Bulbous Rover

Drive Wheels. These wheels act as a see-saw for the rover so that after deployment, the rover does

not tip onto its side.

Page 87: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

87

Figure 8.3: Bulbous Rover Drive Wheels

Electrically, there were a number of changes. A new set of communication devices was chosen

after further range testing deemed the XBee Pro 60mW antennas to not perform as well as

expected. To replace the 60mW version (effective communication range of 1 mile), the XBee Pro

900 devices (effective communication range of 6 miles) were selected and have been deemed to

consistently communicate at the maximum expected range of half a mile. Since the new more

powerful XBees did not have antennas built onto them, an antenna system was developed.

Connected to the transmitting XBee is a Yagi-Uda directional antenna. On the rover, an internal

laptop antenna is connected to the XBee and has been proven to successfully receive the

transmitted signal. A communication schematic is shown in Figure 8.4: Communication

Page 88: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

88

Schematic. For determining the rover orientation in the rocket, the Adafruit 9DOF Breakout board

was deemed too big and was replaced with a Pololu AltIMU-10 v5 inertial measurement unit.

Figure 8.4: Communication Schematic

Section 8.1.2: During the Construction Process

There were unforeseen challenges that we faced during rover manufacturing since CDR. Most of

these challenges were design flaws with tolerances. During assembly, short term fixes included

dremeling/wrapping tape around the component to size it properly. At the first chance, whatever

change needed to be made to the print was updated in SolidWorks.

Page 89: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

89

Section 8.2: Structural Elements

Auburn University’s deployable rover has been designed to be housed inside of the rocket during

flight and deploy from the rocket after landing, whereupon it will travel at least five feet from the

rocket and deploy solar panels. All parts of this section (minus the solar panels) have been designed

using SolidWorks and then 3D printed with either nylon or onyx, a chopped-carbon-fiber-infused

nylon composite. Due to its impressive strength properties, onyx was used in parts such as the

rover chassis and the wheels. The only thing not printed with onyx are the treads, which need to

be flexible enough to deform over the wheels of the rover.

During the design process, size was the biggest limiting factor the team faced. An I-beam structure

(Figure 8.5: I-beam Rover Body – Top) was chosen as the frame to support components on

Figure 8.5: I-beam Rover Body – Top

Page 90: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

90

both sides of the web while keeping height to a minimum. Over the course of the design process,

multiple 3D printed compartments were added to the body to allow for placement of individual

components. In Figure 8.5: I-beam Rover Body – Top, two motor sections and a servo

compartment can be seen. The wall towards the front of the rover allows placement of a 9V battery,

which is friction fit between the wall and the motor housing. In Figure 8.6: I-beam Rover Body –

Bottom, (a bottom-up view of the rover, “Monica”) the solar

Figure 8.6: I-beam Rover Body – Bottom

panel deployment system (SPDS) motor compartment and another 9V battery station are visible.

The use of friction fitting for the batteries allows for easy removal and replacement.

In both figures, holes can be seen on the web of the body. The holes mark the mounting location

of the Arduino UNO in Figure 8.5: I-beam Rover Body – Top and the Adafruit motor shield in

Figure 8.6: I-beam Rover Body – Bottom.

Page 91: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

91

A dual tread system was selected as the best way to maneuver across the unknown terrain of the

launch field. The system, Figure 8.7: Dual Tread System, not only allows for impeccable traction

on most surfaces

Figure 8.7: Dual Tread System

that we have tested on, but also acts as a guide for placement of components inside the structure;

anything outside of the treads will be dragging on the ground. The treads are 3D printed nylon.

The bulbous wheels prevent the rover from tipping onto its side and resting there. If tipped upon

deployment or during the travel to reach five feet from the rocket, the wheels act as a pivot point

for the rover, which will right itself; “righting” tests have been successfully performed on the rover

to confirm this passive orientation correction method. The drive wheels are secured to the body

directly through the drive motors’ shafts while the idle wheels on the rear of the rover spin freely

around separate bolts. The idle wheels are secured with nuts. An exploded view of this setup is in

Page 92: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

92

Figure 8.8: Exploded Dual Tread System. Once the wheels are attached, the treads are stretched

trightly across them.

Figure 8.8: Exploded Dual Tread System

To complete the solar panel deployment aspect of the competition, an array of solar panels are

installed on the back of the rover in an accordion fashion (Figure 8.9: SPDS – Folded and Figure

8.10: SPDS - Unfolded). After the rover reaches

Page 93: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

93

Figure 8.9: SPDS – Folded

Figure 8.10: SPDS - Unfolded

Page 94: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

94

five feet from the rocket, a rack and pinion system is utilized to deploy the solar panels. Attached

to the motor is a gear that spins to deploy a tray (Figure 8.11: Solar Panel Deployment Tray) out

of the

Figure 8.11: Solar Panel Deployment Tray

back of the rover. The solar panels, which are anchored to the rover and attached to the front of

the solar panel depolyment tray, are unfolded and held in place.

To secure the rover into the rover coupler bay, a jaw was designed to fit onto a servo arm. When

the servo arm/jaw (Figure 8.12: Servo Arm/Jaw) closes, it clamps onto an eyebolt in the back of

the rover

Page 95: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

95

Figure 8.12: Servo Arm/Jaw

coupler bay and is supported undereneath by an arm that protrudes from the back of the rover. To

allow for proper pressurization of the recovery section directly above the rover, a carbon fiber door

covers the rover bay. However, it does nothing to prevent the rover from prematurely deploying

from the rocket; it is simply pulled from the bay when the second main parachute deploys. That is

solely resting on the jaw-like servo. The open and closed servo jaw can be seen in Figure 8.13:

Open Servo Arm/Jaw and Figure 8.14: Closed Servo Arm/Jaw.

Page 96: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

96

Figure 8.13: Open Servo Arm/Jaw

Figure 8.14: Closed Servo Arm/Jaw

Page 97: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

97

Section 8.3: Electrical Elements

The electrical elements of the rover include everything that does not provide a structural purpose.

This includes the motors/servos, circuit boards, communication and power that ensure the rover

operates as designed. Once the rocket lands under parachute, the team will send a signal to the

rover via XBee modules; this signal will initialize the deployment sequence. First, the Pololu

Altimu-10 v5 will determine the rover orientation in the rocket based on the z-axis of the

Altimu/rover. This is a critical step as an improper orientation detection will send the rover

backwards into the rocket. A sample of orientation detection code is seen in Figure P. Once the

Figure 8.15: Sample Orientation Check

orientation is determined, the servo unclamps to allow the rover to deploy. The drive motors then

spin the direction determined by the uploaded script for a predetermined amount of time. Once the

rover exits the rocket (after that predetermined amount of time) one motor will stop spinning while

the other continues, turning the rover perpendicular to the rocket. This is done to avoid running

into the parachute that might be directly in front of the open rover bay. At this point, both motors

will spin another predetermined amount of time, driving the rover forward. Upon reaching that

time, the drive motors will stop and the solar panel motor will engage the solar panel tray to deploy

the foldable panels. At various times throughout this process, the Arduino pulls the orientation

from the AltIMU to ensure that the rover has not flipped over, thus ensuring the rover travels the

Page 98: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

98

same direction throughout the course of the deployment. An electrical schematic is shown in

Figure 8.16: Electrical Schematic.

Figure 8.16: Electrical Schematic

The motors used for driving the rover and for the SPDS are 1000:1 12V Pololu Micro Metal

Gearmotors. These motors (Figure 8.17: 1000:1 12V Pololu Micro Metal Gearmotors) provide 125

oz.-in. of torque and have a cross-sectional

Figure 8.17: 1000:1 12V Pololu Micro Metal Gearmotors

Page 99: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

99

area of 0.4 in. x 0.45 in., small enough to fit on the rover, but strong enough to provide enough

torque to overcome difficult obstacles once deployed. The wheels were designed so that the keyed

shaft of these motors would fit snuggly into the wheel holes.

The servo used for securing the rover into the coupler bay is an Adafruit TowerPro SG-5010. Since

the jaw of the servo will not be experiencing much lateral force during the flight (only longitudinal

due to the nature of the servo orientation) the strength of the servo was not critical. After several

successful shake tests and a successful flight using the servo-secured method, the team has proven

the feasibility of this servo.

To communicate with the rover, XBEE Pro 900s were selected. Previous models of the XBees did

not provide the communication range required, so the 900s, a more powerful model that has an

effective range up to six miles, was chosen instead. On the transmitting side, one XBee is

connected to a laptop via USB dongle. Through a software called XCTU, the XBees can be

programmed and a team member can communicate with the other paired XBee through a serial

monitor (Figure 8.18: XCTU Interface). The transmitting antenna is connected to the XBee

through a series of connections from the U.Fl antenna on

Figure 8.18: XCTU Interface

wires from the U.Fl antenna on the XBee to a male N-type connection on a Yagi-Uda directional

antenna. The Yagi’s transmitting frequency is 900 MHz as is the XBee Pro 900. The rover antenna

is an internal Bluetooth laptop antenna that sticks through a hole in the body of the rocket and

wraps around the outside of the rocket. The team decided to have the antenna on the outside of the

Page 100: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

100

rocket in order to avoid attenuation problems from the electrically conductive carbon fiber body.

Once the rover receives the signal and begins the exit the coupler bay, the antenna will get pulled

off of the rover XBee, allowing the rover to proceed unhindered by the 27 in. Bluetooth antenna.

The black piece on the XBee in Figure 8.19: Arduino Wiring ensures the antenna is disconnected

when the rover starts to deploy.

The core of the rover electronics is the Arduino UNO. This was chosen due to previous experience

with Arduino Unos and to the accessibility of sample codes and libraries online. Using the Uno

also meant that we did not need a large source of power; one 9V is able to successfully power the

Arduino during the launch and deployment. The wiring for the Arduino Uno can be seen in Figure

8.19: Arduino Wiring.

Figure 8.19: Arduino Wiring

Page 101: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

101

In order to ensure proper powering of the three motors and the servo, an Adafruit Motor Shield v2

was used; this was chosen based on previous experience with the unit. Similarly to the Arduino,

there are numerous resources to aid in the utilization of this unit. It also is powered simply with a

9V battery. The motor shield wiring can be seen in Figure 8.20: Motor Shield Wiring.

Figure 8.20: Motor Shield Wiring

To determine the rover orientation in the rocket after landing under parachute, the team decided

on using a Pololu AltIMU-10 v5. This unit includes a 3-axis gyroscope, accelerometer,

magnetometer and digital barometer on a board no larger than a quarter.

Page 102: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

102

Section 8.4: Drawings and Schematics

Figure 8.21: Rover CONOPS

Page 103: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

103

Figure 8.22: Assembled Rover

Figure 8.23: Rover Dimensions

Page 104: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

104

Section 8.5: Flight Reliability Confidence

Based on ground tests and successful flight tests, Auburn University Student Launch team has high

hopes for the successful launch, deployment, and recovery of “Monica”. Ground tests have

individually validated aspects of the rover such as being able to navigate different terrains,

communicate effective and successfully up to the range specified by the competition, and right

itself in the event that the rover tips to one side during its deployment. Flight tests have given us

the opportunity to successfully demonstrate the ability to overcome all of these individual

challenges.

Section 8.5.1: Deployment

The eyebolt added to the bay introduces a static attachment point for the rover to ensure it will not

deploy during ascent. Flight tests have verified this capability, and ground tests have ensured the

clasp will separate properly after landing when the deployment signal is sent.

Section 8.5.2: Navigation

The dual-tread design has been confirmed to be able to traverse the terrain that the rover will

encounter. The treads also enable travel regardless of the landing orientation, ensuring that the

rover will be able to travel at least five feet from the rocket to deploy solar panels. The domed

wheels prevent the rover from tipping onto a side which is the only orientation that the treads

cannot function.

Section 8.5.3: Communication

The rover is required to communicate remotely with the team for a successful and safe flight. All

communication systems have been thoroughly tested and proven to function from a distance. All

Page 105: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

105

communication systems are also isolated from other transmitting devices by carbon fiber plates to

ensure there is no cross-talk between devices, leading to unsafe and unexpected events. This

shielding has been proven in flight.

Section 9: Altitude Control Module

Section 9.1: Design Changes

Section 9.1.1: Since CDR

From CDR, the Internal Plate Drag System (IPDS) has remained relatively unchanged with regard

to the module itself. A few tweaks were made to the dimensions of the support plates and arms

within the system to retrofit the module to the inside of the rocket body. Also, assumptions with

securing the module within the rocket body have changed. Due to design changes from other

systems, the module took up roughly half the space it was allotted within the body. A new direction

was then taken to secure the module within its section. Three screws are now being used to hold

the module stable during flight. In addition to this, the upper half of the module bay is being used

to hold key switches, which are able to power on the system once the rocket is mounted to the

launch rail before a flight. These changes are required both for system integrity and ease of

integration.

Section 9.1.2: During the Construction Process

As detailed in the previous section, several changes were made to the system overall since CDR.

With regard to the dimensional changes of the system, several different components had to be

resized and printed again to get a better fit for system integration. The arms that act as the interface

between the motor shaft and the drag plates had to be made longer to achieve a higher drag

coefficient during flight. Making this change results in a longer actuation from within the body.

Page 106: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

106

Also with earlier iterations, our 6-inch diameter support plates were too large to be printed with

the departmental 3D printer. In order to address this issue, we split the support plates in two within

the design in order to make the module pieces snap into place upon assembly. Also mentioned in

Section 4.1.1, the original iteration of the system was intended to be secured by the bottom bulk

plate separator of the section above it. Upon implementation the dimensions were off. This led to

the addition of securing screws with washers to hold the module down. The upper portion of the

body was then used for drilling in key switches to help power on the IPDS. This significantly cut

down on the time spent integrating and prepping the system prior to launch.

Section 9.2: Design

Section 9.2.1: Structural Elements

The concept for this design was centered on the benefits of a modular system. The housing for this

system will be able to be predominantly printed with composite materials. The team printed

components of the design in order to prove the feasibility of using additive techniques to produce

a prototype and ultimately a final product.

Table 9.1: Physical Components

Component Responsibility

(3) Drag Plates Actuate out of IPDS to produce drag on the

vehicle perpendicular to the air flow.

(3) Support Plates Form the backbone of the module. These hold

the system together.

(3) Threaded Support Rods Form the backbone of the module. These hold

the system together.

Page 107: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

107

(1) Shaft-to-Plate Interface This connects to the shaft of the motor and the

support arms that actuate the drag plates.

(3) Plate Interface Arms These connect the Shaft-to-Plate Interface to

the three drag plates to help carry out actuation.

Arms will interface with the drag plates, which revolve around the center point controlled by the

motor. These plates will be able to actuate from a completely revolved position all the way out to

a maximum determined by the controller. These plates will be actuated out a variable degree in

order to accurately bring the rocket to apogee.

The modularity of this design is a prime benefit of using this system. Preparation for launch will

be a small hassle since the housing can be dropped in with relative ease. Another benefit is the

lack of external components. This decreases drag on the system as a whole, since no fins or fairings

have to be attached. Another consideration is the ability to operate with just a single motor. This

allows for all arms to operate from a single stream of inputs.

Section 9.2.2: Electrical Elements

The electronics for this system combine to provide all of the inputs necessary to provide a continual

calculation for projected altitude. The controller will act as the decision maker for the system,

determining the rate at which the vehicle will self-correct its trajectory.

Table 9.2: Electrical Components

Component Responsibility

(1) Arduino Uno Controller for the IPDS. Responsible for

coordinating all calculations and guidance.

Page 108: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

108

(1) AndyMark NeveRest 40 DC Motor Handles uniform actuation of the drag plates.

(1) Adafruit Motor Shield v.2.3 Allows communication and power distribution

to the DC motor.

(1) Adafruit accelerometer Calculates triple-axis acceleration needed for

controls.

(1) Adafruit Micro SD card breakout Destination for importation of all flight data.

(1) Adafruit barometric pressure sensor Measures altitude needed for calculations in

controls.

(2) 9V Battery Distributes power to system.

The IPDS is completely powered via two 9V batteries. One battery pack powers the controller,

while the other powers the motor shield. Both power sources are linked to the two key switches

towards the top of the system. This circuit is completed via the switches directly prior to launch in

order to conserve battery life. This ensures the system is not in danger of losing power. All sensors

and the Micro SD card breakout are located on top of the module, soldered directly to a breadboard.

The placement and location of the sensors and breadboard allow the correct axis data to be

collected during launch.

Section 9.2.3: Drawings and Schematics

This section includes pictures, renderings, and dimensions of the Internal Plate Drag System

(IPDS).

Page 109: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

109

Figure 9.1: Bottom-Up view of plates and arms

Figure 9.2:Side View of assembled module

Page 110: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

110

Figure 9.3: IPDS Dimensions

Section 9.3: Flight Reliability Confidence

This system’s mission success criteria are listed in the table below.

Table 9.3: Mission Success Criteria

Criteria Number Criteria Method of Validation

AU1

All aerodynamic data must be

validated through analytical

and experimental testing.

An aerodynamic analysis of

the drag plates and the internal

system was conducted through

pid controller implementation

and simulations.

AU2 Drag plates must stay static

throughout launch.

Code implemented phases will

be implemented through the

controller that will prevent

Page 111: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

111

any system action prior to the

end of the boost phase.

AU3 Electronics must stay secured

throughout flight.

Proper screws and fasteners

are used to secure the system

in place.

AU4

Subsystem components must

engage accordingly after

boost phase and stay online

for the remainder of the flight.

Testing will verify that the

code implemented phases will

keep the system static until

motor burn.

AU5

Controller and IMU must be

able to correctly predict the

projected altitude of the

launch vehicle.

Test data will be logged to a

Micro SD card to review post-

launch.

AU6

Drag plates must deploy after

boost phase in order to self-

correct the trajectory of the

launch vehicle.

PID controller simulations and

test flights will validate

deployment precision.

AU7

Drag plates must be able to

withstand the perpendicular

force of the airflow.

Wind tunnel testing and

structural testing will be

conducted to ensure the

integrity of the plates and the

materials used to construct

them.

Mission success criteria 2, 4, and 6 (AU 2, 4, 6) are satisfied via the implementation of flight

phases. In the controller script, phases keep unwanted output from ever occurring in any case.

Phase 1 waits for the launch event of the launch vehicle. Phase 2 awaits the end of the motor burn

Page 112: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

112

event. Phase 3 runs all calculations and will feature action from the drag plates and self-correction

of trajectory. The last phase shuts the system down once the system has done its job. Mission

success criteria 1 and 7 (AU1 and AU7) is satisfied through simulations, computational fluid

dynamics, and wind tunnel testing. Finally, securing the module in the body with screws fulfills

criteria 3 (AU3). The system that has been implemented is extremely fault-tolerant given many

common potential circumstances and can adjust accordingly.

Page 113: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

Section 10: Safety

Section 10.1: Personnel Hazard Analysis

Hazard Cause Result Severity Probability Combined

Risk Mitigation Verification

Improper use of

small power tools

Lack of training,

improper use,

and/or improper

protection such

as a lack of

gloves or safety

glasses

Mild to severe cuts,

scrapes, and other

injuries.

Additionally,

reactions can result in

harm to rocket

components being

worked upon.

3 3 9

Demonstration of proper

use by experienced team

members, easily

accessible safety

materials and protective

wear, and securely

fastening the object being

worked upon

Trainings and safety

measures taken as

described in proposal

Soldering fumes

from heated

metals or plastics

Use soldering

tool on improper

surfaces or for

excessive time

Toxic fumes created

are inhaled and cause

the team member to

become sick from

prolonged exposure

3 3 9

Work with any soldering

tools will be done in a

ventilated area and all

unsupervised work will

be performed by trained

individuals

Trainings and safety

measures taken as

described in proposal

Improper use of

large power tools

Failure to pay

attention,

aggressive use

of the tools, lack

of proper

protective

equipment, or a

lack or training

Severe cuts, burns,

rashes, bruises, or

other harm to fingers,

hands, or arms

4 2 8

Experienced team

members will instruct

inexperienced team

members before the

newer team member is

allowed to use the tools,

and only those that

display comprehensive

and safe work may

proceed. Protective

equipment will also be

easily accessible

Trainings and safety

measures taken as

described in proposal

Page 114: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

114

Carbon fiber

particles

Sanding carbon

fiber or other

fibrous material

without using a

mask or filter

Mild coughing and

difficulty breathing,

irritation in the eyes

and skin.

2 4 8

When sanding or cutting

tools are used on carbon

fiber all members in the

lab, regardless if they are

working on the carbon

fiber or not, are required

to utilize a mask to

prevent the breathing in

of excessive particles

Trainings and safety

measures taken as

described in proposal

Burning surface

of soldering tool

Failure to pay

proper attention

to the soldering

tool or lack of

training

Mild to severe burns

on the fingers or

hands of the team

member using it.

Additionally, could

result in excessive

heat and damage to

the component being

worked on.

3 2 6

Members that use the

soldering iron are

required to give it their

full attention for the

duration of their work.

They must turn off and

stow the tool somewhere

away from the object

being worked on if they

must attend to something

else before work is

finished. Only those who

have been instructed in

the use of the soldering

iron may work with the

tool unassisted

Trainings and safety

measures taken as

described in proposal

Page 115: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

115

Noxious fumes

from body

manufacturing

Improper

ventilation of the

workstation

where curing is

taking place

Excessive exposure to

toxic fumes results in

nausea and irritation.

Reactions could

potentially damage

the component being

worked upon.

3 2 6

The workstation will be

properly vented and

members using it are

required to confirm

ventilation is functioning

periodically.

Additionally, if

ventilation is

malfunctioning, work

will not continue to avoid

a buildup of fumes and

allow dispersion of the

Trainings and safety

measures taken as

described in proposal

Insecure Tools

Tools are left

out in the lab

workspace and

not returned to a

storage space

where they

belong

Cuts, pricks, or tears

when members sort

through items or

knock loose tools

around or off tables.

2 3 6

The storage spaces for all

tools are clearly marked

and easy to find.

Members are instructed

to return tools they find

left out to their storage

spaces. A checklist must

be finished before project

members can leave the

lab or start a different

project.

Trainings and safety

measures taken as

described in proposal

Checklists shown in

Launch Operations

Procedures are

followed

Electrical

discharge from

equipment

a) Improperly

maintained

equipment

b)

Improper use of

equipment

Electric shocks could

occur to team

members handling the

equipment

4 1 4

Electrical equipment will

be maintained regularly.

Electrical equipment will

only be plugged in when

ready for immediate use

and will be promptly

unplugged afterward. All

wires will be kept out of

the path of other team

members or any other

equipment.

Trainings and safety

measures taken as

described in proposal

Page 116: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

116

Improper use of

man powered

tools

Lack of training

or discipline

with tools

Damage to sections

of the rocket or to

team members and

delays to the project

due to the need for

replacements

2 2 4

All team members will be

trained on the use and

proper educate of the lab.

If they are not followed,

members will be

reprimanded before an

incident occurs

Trainings and safety

measures taken as

described in proposal

Section 10.2: Failure Modes and Effects Analysis

Hazard Cause Result Severity Probability Combined

Risk Mitigation Verification

Improper wiring

Faulty

connections or

mistaken

placement of

connections

The electronic

payload does not

behave as expected or

does not function at

all

4 4 16

Wires will be color-coded

to communicate their

function and a specific

checklist will be used to

correct wiring. The

checklist will be doubled

checked by the systems

lead and recovery lead.

Wiring noted in

Electrical Elements

Parachute failure

after deployment

(tangled)

The parachute is

not packed

properly

The parachute

becomes tangled on

descent resulting in an

erratic and fast

moving projectile that

endangers personnel

and property below

5 3 15

Packing of the parachute

will be performed by

dedicated members of the

recovery team who will

have practiced previously.

Noted in Preassembly

Checklists

Parachute design

noted in Parachutes

Page 117: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

117

Parachute

deploys early

A faulty

altimeter fails to

detect the

altitude at which

the parachute

should deploy or

improper wiring

switches event

order

The rocket's ascent

will be compromised

and its descent will

result in the rocket

drifting for a very

long distance

3 3 9

The altimeter will be

thoroughly tested prior to

its use in a full-scale

capacity to confirm that it

will function as intended.

Safety procedures will be

followed as directed by

the USLI handbook for the

recovery of the vehicle.

Noted in

Preassembly

Checklists

Fire in recovery

system

Excessive black

powder and

insufficient

flame retardant

wadding

The descent of the

rocket is accelerated

and the external and

internal structure of

the rocket is

jeopardized. Upon

landing, a flaming

parachute or chords

could ignite brush.

4 3 12

Testing will be done to

determine the exact

amount of black powder

and wadding needed to

safely deploy the

parachute. No more than

is needed will be used. A

fire extinguisher will be

available to combat any

fires that may occur once

the rocket lands. If the fire

spreads or is significantly

large, authorities will be

contacted. Safety

procedures will be

followed as directed by

the USLI handbook for

the recovery of the

vehicle.

Proper charge size

noted in Preassembly

Checklists and

Ejection

Page 118: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

118

Rocket sections

poorly coupled

The use of weak

bolts or poorly

designed

manufactured

couplers

between sections

Sections of the rocket

may wobble and the

trajectory of the

rocket could be

affected during ascent

or during recovery.

5 2 10

Extensive testing of the

coupler will be done prior

to sub-scale and full-scale

launches. The coupler

will be visually inspected

before and after assembly

by the team leads, safety

officer, and Range Safety

Officer.

Noted in Preassembly

Checklists and

Launch Vehicle

Assembly and Check

Holes in the

airframe

Insufficient

communication

in addition to

excessive

drilling or work

on components

or failure to

notice missing

pins or screws

The hole could result

in an improper

reading of air

pressure by the

altimeter and result in

premature activation

of the recovery

system.

3 2 6

All sections of the rocket

will be visually inspected

immediately after

construction, before

transport to the launch

site, and on assembly.

Duplicates of objects such

as pins, screws, etc. will

be available to replace any

missing ones. Prelaunch

machining will be kept to

an efficient minimum with

our preflight checklists

and assembly plan.

Noted in Flight

Reliability

Confidence

Motor fails on

launch

(explosion)

Manufacturing

defect

The rocket is

destroyed on the

launch pad or shortly

after launch

5 2 10

Rocket motors will only

be purchased from a

certified source and will

be handled with extreme

care exclusively by the

team mentor or by

someone with permission

of the team mentor.

Guidelines state all

motor work is to be

done by team mentor

Page 119: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

119

Parachute failure

after deployment

(tear)

Defects in the

parachute or

parachute bay

occurred during

construction

The rocket's descent

will not be slowed as

effectively and could

endanger the rocket or

personnel

5 2 10

The parachute will be

visually inspected and

tested prior to its

utilization in a full-scale

capacity and upon

assembly on launch day.

The container holding

parachute will be

smoothed to not contain

any sharp edges. All

parachutes will be

reinforced at any potential

tear location.

Parachute materials

noted in Materials

Parachute fails

to deploy

a) A faulty

altimeter fails to

detect the

altitude at which

the parachute

should deploy

b) Not enough

black powder is

used in the

recovery system

The rocket descends

chaotically at a speed

that his extremely

dangerous to both the

rocket and personnel.

5 2 10

a) A reliable altimeter will

be selected during the

PDR phase and will be

tested prior to launch in a

full-scale capacity.

b) The amount of black

powder that will be used

will be calculated by team

members beforehand.

Calculations will include

the amount necessary and

the amount allowable with

the final amount used

lying somewhere within

the range. Use and final

preparation of black

powder charges will be

monitored by the safety

officer.

Testing – Recovery

battery tests verifies

Mitigation A

Testing – Full scale

and Subscale

separation testing

verifies Mitigation B

Page 120: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

120

Rocket blown off

course on

descent

a) Strong winds

on the day of

the launch affect

descent more

than expected

b) A premature

parachute

deployment

causes the

rocket to be

subject to more

drift

Rocket could become

lost, damaged, or

could endanger

observers.

3 3 9

The rocket will not be

launched if weather

conditions are considered

dangerous by either the

team or the range safety

officer. All parts of the

rocket will have a GPS

locater device securely

attached to facilitate

tracking during and after

descent. Safety procedures

will be followed as

directed by the USLI

handbook for the recovery

of the vehicle.

Parachute sized noted

in Parachutes

Deployment height

noted in Recovery

System Design

Insecure

aerodynamic

attachments such

as fins or brakes

a) The epoxy

was mixed or

cured

improperly

b) The epoxy

used was not

strong enough

to withstand

forces encounter

in flight

Fins may vibrate and

cause unexpected or

erratic changes to the

course of the rocket.

This could cause

mission failure and

potentially endanger

personnel

4 2 8

Proper procedures

regarding the mixing and

curing of epoxy will be

strictly followed during

construction of the rocket.

During assembly, team

members will apply

pressure to the fins to

confirm they do not move

and will not move during

flight. If the epoxy is not

sufficient, steps will be

taken to fully secure the

fins and if they cannot, the

safety officer will deem

the rocket unsafe to

launch.

All parts tested pre-

flight in Launch

Vehicle Assembly

and Check

Page 121: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

121

Improper coding

Improper coding

of the

microcontroller

controlling the

airbrake system

Airbrakes do not

actuate as expected

compromising our

maximum altitude and

overall mission

4 2 8

The code that will drive

the microcontroller will be

written and reviewed by

multiple team members

and tested on the ground

to ensure that it reacts in

ways it is meant to.

Verified in Flight

Reliability

Confidence

Improper

soldering or

board

manufacturing

Too much or too

little solder is

used when

constructing the

electrical

equipment

Electrical

malfunctions and a

loss of system

integrity leading to a

loss of whichever

system the electronics

are used in

4 2 8

The electrical equipment

will be visually inspected

by multiple team members

and tests run to ensure that

it carries electrical signals

as intended.

Tested pre-flight in

Launch Vehicle

Assembly and Check

Rocket descends

too rapidly

Design oversight

causes the

rocket to fall

faster than

desired

The body of the

rocket will be

damaged and

potentially the

internal components

damaged as well.

This could violate

vehicle requirement

1.4 and jeopardize

mission success.

4 2 8

The exact size of the

parachute needed to slow

down the descent of the

rocket and the timing of

its release will be

calculated and sufficient

leeway given to ensure

that recovery will not

threaten the rocket or

personnel. All members

and observers will remain

vigilant until the rocket is

recovered after landing.

Parachute sizes noted

in Parachutes

Kinetic energy

calculations located in

Kinetic Energy

Page 122: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

122

Payload (rover)

becomes unstable

during flight

Payload is not

properly secured

within its

compartment

With a moving

payload inside the

rocket, the center of

gravity would be

constantly changing.

This would cause the

rockets flight to

become unstable and

potentially damage

the payload and other

components within

the rocket

4 2 8

The payload will be

housed within a secure

bay inside the rocket. It

will be placed inside this

bay with a bulk plate door

and clamp to hold it in

place. The payload is also

at the bottom of the rocket

with the opening facing

upward. If the payload

dislodges, the inertial

forces of launch would

keep it in place inside the

bay.

Design changes to

maintain steadiness

noted in Rover

Structure is

dropped and

damaged during

construction,

assembly, or in

transport

Distracted or

clumsy handlers

that are not

aware of their

surroundings

The body of the

rocket or components

in the rocket may be

damaged by the

impact and may

require replacement

3 2 6

Great care will be taken

when working on

components under all

conditions. The

transportation vehicle will

have a stable carrying

structure for the launch

vehicle. During

transportation, multiple

personnel will carry the

rocket slowly and

carefully while an

additional team member

removes obstacles or

opens doors as necessary.

Replaceable parts such as

pins, screws, and the nose

cone will have duplicate

parts available during

assembly.

Testing sections on

materials testing in

Testing

Page 123: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

123

Motor fails on

launch (fails to

ignite)

a)

Manufacturing

defect

b) Failure of the

ignition system

c) Delayed

ignition

a) and b) The motor

will not fire and the

rocket will not launch

c) The motor will fire

and the rocket will

launch at an unknown

amount of time after

the button is pressed

3 2 6

In accordance with the

NAR Safety Code, the

safety interlock will be

removed or the battery

will be disconnected and

no team member will

approach the rocket for 60

seconds. After 60 seconds

without activity the safety

officer will approach and

check the ignition

systems. In the event that

the ignition systems are

not at fault, the motor will

be removed and replaced

with a spare. A second

launch will be attempted if

there is time to do so.

Servos used in

aerodynamic

systems do not

actuate smoothly

a) Internal

electrical failure

b) Worn gears

or slide rails

The science payload

may not respond as

accurately as expected

3 2 6

The servos that will be

used for flight will be

purchased at the beginning

of the project and will be

stored in a space away

from any chemicals or

excessive humidity. The

servos will be tested

before transport, before

and after assembly to

confirm that they actuate

properly. The airbrake

system will be tested

before launch to ensure

the accurate response from

our system as a whole.

Prelaunch checks can

be found in Launch

Vehicle Assembly

and Check

Page 124: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

124

Structural

integrity of

rocket

compromised in

flight

Excessive

aerodynamic

loading on the

airframe of the

rocket

Rocket may be

entirely lost after

flight becomes

unstable and recovery

systems may be

compromised

5 1 5

Extensive testing of the

materials and structural

architecture of the rocket

body will be done before

sub-scale and full-scale

launches to confirm that

the design will withstand

forces that it will

encounter.

Testing sections on

materials testing in

Testing

Cracked

airframe

Excessive

physical or

thermal loading

to the rocket

body during

storage or

transport

The rocket body

fractures on launch or

on ascent releasing

debris in the

immediate area

5 1 5

Sections of the rocket

body will be kept in a dry

location at room

temperature. The rocket

body will be visually

inspected before and after

transport, during

assembly, and

immediately prior to

launch to confirm that

there are no cracks. If

cracks are found, the

launch vehicle will be

deemed unsafe for launch

by the safety officer.

Testing sections on

materials testing in

Testing

Noted in Preassembly

Checklists

Center of gravity

or center of

pressure

misplaced

Rocket property

calculations

were made

incorrectly or

with improper

data

The rocket's ascent

will be unstable and

potentially dangerous

to personnel and

equipment

5 1 5

Calculations will be

checked multiple times

prior to launch. Subscale

launches will provide an

opportunity to confirm

these calculations prior to

full scale launch.

Additionally, the center of

gravity will be physically

checked prior to launch.

Noted in Preassembly

Checklists

Page 125: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

125

Misplaced or lost

components

A messy or

disorganized

work

environment

leads to poor

tracking and

storage of

pertinent rocket

components

An incomplete rocket

body is transported or

ready for assembly on

launch day. Segments

may need to be

remanufactured if

they cannot be

located.

4 1 4

Once segments of the

rocket body are completed

they will be immediately

stored in a location

exclusively for launch-

ready components. For

subscale launches, some

components will be

manufactured twice so

that one may serve as a

backup.

First step in each

preflight checklist

Rocket exceeds

Mach 1 on ascent

The rocket

motor utilized in

the design is too

powerful for the

mass of the

rocket

Vehicle requirement

1.19.7 is violated,

compromising the

validity of the mission

and an infraction of

our launch licensing

4 1 4

Team members will

analytically evaluate the

expected speed of the

rocket prior to testing and

will confirm these results

in sub-scale and full-scale

testing. In the event that

the mass of the rocket is

too low, additional mass

will be added to the inside

of the rocket to ensure it

does not exceed Mach 1.

If the mass cannot be

fixed in a safe manner, the

rocket will be deemed

unsafe to launch by the

safety officer.

Model simulation

noted in Simulations

Motor selection noted

in Propulsion

Page 126: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

126

Motor is

physically

damaged

Motor was

damaged during

handling or

transport due to

a drop or

insecure

transportation

Motor can function

improperly or

potentially explode

due to pressure forces

on damaged area

3 1 3

The motor will be

primarily handled by the

team mentor or another

member certified to do so

with the permission of the

mentor or safety officer.

The motor will be checked

multiple times before

flight to ensure no damage

has been done

Checked in Engine

Section 10.3: Environmental Hazard Analysis

Section 10.3.1: Rocket Effects on Environment

Hazard Cause Result Severity Probability Combined

Risk Mitigation Verification

Fire on ignition

Upon ignition,

the exhaust from

the rocket may

set fire to any

vegetation

beneath or

around the

launch site

Fires will destroy the

vegetation near

launch and have the

potential to spread

further from the site

4 3 12

In accordance with the

NAR guidelines, the

launch site will be placed

such that it does not

present the risk of grass

fires.

Noted in checklist in

safety section

Launcher Setup and

Launch Procedure

Page 127: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

127

Debris from

ballistic return

or explosion

A recovery

system failure

cause the rocket

to impact the

ground at high

velocity

scattering debris

or an engine

CATO forms

debris either in

the air or on the

launch pad

Heated materials are

spread on flammable

surfaces causing fires

or debris is spread as

a contaminant

4 2 8

This situations are

mitigated by other

precaution shown in

failure modes and proper

recovery techniques are

followed according to

NAR guidelines

Noted in checklist in

safety section Post-

flight Inspection

Cured epoxy in

landfill

Cups used to

cure epoxy are

thrown into

normal trash

bins and taken to

landfills

The epoxy breaks

down and releases

harmful chemicals

into the ground

2 4 8

Epoxy and epoxy stirring

cups will be disposed of

separately into a bin by

the work station. The

contents will be taken to

an approved chemical

disposal site

Trainings and safety

measures taken as

described in proposal

Epoxy gas and

chemical release

Epoxy releases

volatile

chemicals and

gasses as it cures

This small release can

be vented into the

environment causing

pollution of air or

water

1 4 5

With our rather small

scale of our construction,

the impact of our

ventilation is minimal

and all solid or liquid

contaminates are

disposed of in a proper

fashion

Trainings and safety

measures taken as

described in proposal

Section 10.3.2: Environmental Effects on Rocket

Page 128: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

128

Hazard Cause Result Severity Probability Combined

Risk Mitigation Verification

Cross winds in

flight

Rocket is

launched when

cross winds are

faster than

desired limits

Winds can cause the

rockets trajectory to

change or its flight to

become unstable.

This can further cause

the rocket to land in

an unanticipated or

unsafe location

3 4 12

In accordance with NAR

regulations, the rocket

will not be launched if

wind speeds exceed 20

miles per hour. The

safety officer and range

safety officer will

monitor the wind speed

prior to launch. The

rocket is also designed to

be stable under cross

wind conditions

Stability margin noted

in Stability

Fin design noted in

Aerodynamics

Exposure to

humidity

(electronics)

Exposure to

humidity can

cause wires or

electronic

boards to

corrode

Corroded wires can

cause electrical

signals to not be

transmitted leading to

a loss of avionics or

rover control

3 3 9

Our system components

will be kept in a

dehumidified space at

room temperature to

avoid and corrosion

Natural

environment

effects recovery

of rocket

The rocket drifts

into difficult

terrain or foliage

when landing

Finding or accessing

the rocket during

recovery is made

difficult or even

dangerous for team

members

3 3 9

The size of the main

parachutes are minimized

to prevent drift while still

ensuring the safe decent

of rocket sections. The

event heights for

separation and

deployment of parachutes

is lowered for similar

reasons

Parachute sized noted

in Parachutes

Deployment height

noted in Ejection

Page 129: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

129

Exposure to

humidity

(corrosion)

Exposure to

humidity can

cause metals

within certain

systems to

corrode

Corroded metals do

not have the same

integrity as their

original states leading

to potential damage

3 2 6

Our system components

will be kept in a

dehumidified space at

room temperature to

avoid any corrosion

Air temperature

and sun exposure

Prolonged

exposure to the

sun heats

components of

the launch

vehicle beyond

standard

temperatures for

manufactured

materials

Epoxies and other

resins may loosen or

melt causing the

separation of the

launch vehicle body

3 2 6

On-site work and

assembly of the launch

vehicle are done under a

tent or in another form of

shaded area

Unstable launch

surface

The surface,

below launch

rails, is loosely

packed or wet

The weight of the

rocket causes a tilt of

the launch rail system

resulting in a skewed

trajectory

2 2 4

All launch locations are

checked by the safety

officer, project lead, and

the RSO prior to launch

setup

Noted in safety

checklist Launcher

Setup and Launch

Procedure

Page 130: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

130

Section 11: Launch Operations Procedures

Section 11.1: Preassembly Checklists

Section 11.1.1: Recovery

Task Completed (Initialed)

Ensure all necessary items are transported

Check primary and back-up batteries

Attach RF trackers to both the upper and

lower sections with electrical tape

Open up the BAE, plug batteries into

altimeters and ensure all lead wires are

plugged into correct altimeter points

Check both altimeters and jolly logic

systems for functionality

Folded parachutes

Attach RF trackers to both the upper and

lower sections with electrical tape

Turn on both Jolly Logic Chute Releases,

ensuring that the batteries are at full

charge and have a deploy height of 1000ft

set

Page 131: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

131

Attach shock chord for nose cone, drogue

parachute and upper main parachute

Attach key switches

Secure e-match in charge cup

Fill Charge Cups (done or supervised by

authorized personnel):

Use clear and clean table surface

• Wear provided safety equipment

• Fill cups using clean funnel

• Fill to exact mass (measure with scale)

Attach key switches and e-matches to

altimeter boards

Place system in housing BAE

Section 11.1.2: Altitude Control

Task Completed (Initialed)

Ensure all necessary items are transported

Check primary and back-up batteries

Check altimeters for functionality

Check for any damage on plates or housing

Test system for functionality and smooth

extension

Page 132: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

132

Place system in housing and secure

attachment screws

Section 11.1.3: Body

Section 11.1.4: Rover

Task Completed (Initialed)

Ensure all necessary items are transported

Task Completed (Initialed)

Ensure all necessary items are transported

Check for damage to nose

Check for damage to upper section

Check for damage to lower section

Check fins for correct alignment and any

damage from transportation

Check engine housing for structural

integrity

Gather all shear pins and attachment

screws

Page 133: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

133

Check primary and back-up batteries

Test rover functionality along with engine

response and functionality

Test radio receiver

Place rover on tracks in housing bay

Secure housing bay door

Section 11.1.5: Engine

Task Completed (Initialed)

Use engine transported by team mentor or

purchase engine from authorized range

store

Engine prepared by licensed team mentor

Section 11.2: Launch Vehicle Assembly and Check

Task Completed (Initialed)

Attach lower main parachute to lower

section attachment ring

Attach upper section to avionics BAE with

screws

Page 134: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

134

Attach upper main parachute assembly to

avionics bulkhead

Ensure charge cups are in proper locations

indicated by design

Pack insulation (barf) around lower charge

cups and insert lower main parachute and

shock chord

Attach lower section to avionics BAE with

shear pins

Pack insulation (barf) around upper

charge cups and insert upper main

parachute assembly and shock chord

Attach nose cone to upper section with

shear pins

Check all connections for proper alignment

Place and secure engine in engine housing

Test center of gravity

Check key stitches to ensure functionality

of avionics

Check body for flight readiness

Check engine mount for flight readiness

Check fins for flight readiness

If any steps cannot be completed,

disassemble and correct

Page 135: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

135

Section 11.3: Launcher Setup and Launch Procedure

Section 11.3.1: Launcher Setup

Task Completed (Initialed)

Test to ensure all weather conditions are

within preset limits

With supervision of range safety officer,

place rocket on launch rail

Ensure angle launch rail is within limits

Turn on avionics

Clear surrounding area of flammable

material

Have all viewing personnel move to safe

distance

Place ignitor against engine fuel grain

Attach launch controller to ignitor

Check for proper connection

Page 136: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

136

Section 11.3.2: Launch Procedure

Task Completed (Initialed)

Move setup team to safe launch distance

Initialize mission process with range

officials

Receive all clear from range officials

Initiate motor ignition

Check for proper ignition

Section 11.4: Post-flight Inspection

Task Completed (Initialed)

Track both halves of rocket with RF

tracker

Approach the upper section of the rocket

and turn off the altimeters with the key

switches

Page 137: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

137

Check to see if all black powder charges

have detonated

Remove undeployed black powder charges

by cutting the wires to the e-match and

placing the charge in a bucket of water

Check altimeter beeps for launch altitude

Separate the upper parachute assembly

from the upper half of the rocket

Recover any vehicle components

Remove any environmental hazards

Disconnect the upper and lower parachute

housings from the BAE

Open up the BAE and remove the

altimeter board

Plug both altimeters into a laptop, read the

flight data and determine the kinetic

energy of the upper section impact

Team Lead Safety Officer

x___________________ x___________________

Page 138: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

Section 12: Testing

In addition to the creation of requirements, it is essential to verify that they are satisfied. The pre-

competition full scale launches provide a method to check the function of all components, but

testing all systems at once introduces a large degree of risk and reduces the time to make changes

if needed. Therefore, although the goal is for all requirements to be verified through launching a

full-scale rocket with fully functional payloads, when possible components should be tested

previously and separately. Each of the following tests lists first the Auburn University

requirements that the test aims to confirm compliance with, the procedure used, and then reports

whether the test was determined to be a success.

Section 12.1: Rover Battery and Motor Test (AU 4.4, 4.5)

Test Objective

This test aimed to verify the longevity of the electronics of the rover, in accordance with AU

requirements:

AU 4.4 Rover electronics must be able function after being left on for more than two hours.

AU 4.5 Rover motors must be able to function after more than two hours of battery drain.

This test was to be considered successful if the rover electronics were still functional after two or

more hours of intense battery drain.

Justification

Between time spent on the launch pad and time waiting to be deployed after landing, the rover

system will be experiencing power drain for a significant period of time. This power drain will

be less strenuous than two hours of continuous motor operation, however simply leaving the

system in its highest power consuming state provides a useful benchmark for the test. If the Rover

Page 139: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

139

system could not sustain this level of operation, the Rover would need to be redesigned to ensure

mission completion.

Test components

-Arduino Uno

-New 9V batteries

-Rover Motors

-Multimeter

Procedure

1. Assemble the motors, control circuits, and batteries into the planned launch

configuration.

2. Turn on the Arduino and the motors.

3. Measure the initial voltage from the batteries using the multimeter. Battery 1 was

connected to the Arduino, while battery 2 was providing power to the motors.

4. Take voltage measurements every thirty minutes, ending the test if any components

stopped functioning.

Section 12.1.1: Results

Voltage Reading (Volts)

Time (AM) Battery 1 Battery 2

7:45 9.2 8.8

8:15 8.4 7.6

8:45 8 7

Page 140: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

140

Although very simple, this test has provided some very important data. The motors were able to

run continuously for over three and a half hours off of a single 9V battery. This is a much higher

power drain than expected for simply standing idle in the launch configuration, so even in a case

of extreme battery usage the rover will still exceed AU requirement AU 4.5. The Arduino was

still functional after four hours, double AU 4.4 and four times NASA requirement 2.10 for vehicle

components endurance in the standby launch position.

Design Changes due to Test

None, the Rover electronics met and exceeded all requirements for the test. This confirms that the

planned electronics setup can be used in the final design.

9:15 7.8 6.8

9:45 7.6 6.5

10:15 7.4 6.2

10:45 7 5.9

11:15 7 5.4

11:45 7 5.4

Page 141: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

141

Section 12.2: Recovery and Altitude Control Battery Tests (AU 3.1, 6.9)

Test(s) Objective

Since these two tests are very similar, they have been combined here. They are both intended to

address NASA requirement 2.10, and the more strenuous AU requirements

AU 4.4 Recovery electronics must be able function after being left on for more than two hours.

AU 4.5 Altitude electronics must be able to function after more than two hours of battery drain.

These tests will be considered successful if the respective electronics are still operational after two

or more hours of intense battery drain.

Justification

Both electronics systems, like the rover, may need to standby in the on position for quite some

time on the launchpad before launch. The recovery system must still operate after this time for

mission completion. Although not as critical, the altitude control system must still operate as well

in order to not overshoot the mile altitude goal. If these systems cannot sustain this level of

operation, they will need to be redesigned to incorporate longer lasting batteries.

Test components

-Recovery altimeters

-Fully charged batteries

-Altitude control system Arduino Uno

-Multimeter

Procedure

1. Assemble the motor (in the case of the altitude control system), control circuits, and

batteries into the planned launch configuration.

2. Turn on the Arduino and the motor or the two altimeters.

3. Measure the initial voltage from the batteries using the multimeter.

Page 142: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

142

4. Take voltage measurements every thirty minutes, ending the test if any components

stopped functioning.

Section 12.2.1: Results

Due to the failure of the multimeter during the recovery test, voltage readings are not available.

Both systems outlasted the required number of hours, however.

Design Changes due to Test

No design changes were necessary, as both systems exceeded the time requirements.

Section 12.3: Full-Scale and Subscale Separation Test (AU 3.2)

Test Objective

This test is highly essential for both successful flight execution and safety. Ground Separation

testing was used to verify AU requirement

AU 3.2 Recovery system will be able to separate rocket into desired sections using the minimum

amount of black powder for reliable results, to ensure safety.

and NASA requirement

3.2 Each team must perform a successful ground ejection test for both the drogue and main

parachutes. This must be done prior to the initial subscale and full-scale launches.

Justification

Too little black powder, and the rocket will not separate, preventing parachute deployment, leading

to mission failure and more importantly a dangerous projectile. Too much black powder, however,

provides a fire and explosive hazard to team and launch personnel, and similarly can damage rocket

components. Therefore, it is important to use ground separation testing to determine the minimum

amount of black powder necessary to separate sections and eject the parachutes.

Page 143: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

143

This test must be performed for both the subscale and full-scale rocket. Although rules exist for

scaling and theoretically determining the required powder, the team prefers to use these methods

as a starting point to be checked with proper testing.

Test components

-Recovery Barometric Avionics Enclosure (BAE) structure

-Launch configuration upper or lower recovery section, secured with shear pins, including

● Main parachute (with drogue in upper section)

● Shock cord

● Recovery wadding

● Assembled black powder charges

● Nose cone or first lower body section coupler (depending on upper or lower

section)

-Electronic matches

-Ignition system

-Fire extinguisher (have not needed to use it, but always will be located beforehand)

Procedure

1. Fill charge cups according to equation established in the Recovery Section, or to

increased amount based on the result of the previous test/launch. (The equation from the

recovery section is an ideal case, and has been found from previous years to undershoot

the required amount).

2. Assemble structural components of the BAE with the electronic matches threaded

through to reach the charge cups. (Using the complete electronics system is possible but

not necessary)

3. Attach recovery section tube to the BAE, packing charges, wadding, parachutes, etc. as

they would be for a launch.

4. Seal the recovery section with the coupler or nose cone that completes the enclosure,

securing with shear pins.

5. Place the assembled system on the ground or a test stand away from all personnel.

Page 144: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

144

6. Attach the electronic matches to the power supply, and after verifying everyone is at a

safe distance, fire the charges.

7. If the components separate, record the amount of black powder used. If the charges do

not separate the components, disassemble the rocket and increase the charge.

Figure 12.1: Subscale Separation Test

Error! Reference source not found. shows the subscale lower section prior to conducting s

eparation testing. The BAE is orange, on the right, and the wires to the electronic matches can be

seen trailing off to a further distance that all members retreated to in order to conduct the test after

this photo was taken.

Section 12.3.1: Results

Separation testing was completed for the subscale rocket at the launch field in Samson, Alabama

on November 4, 2017. Through a series of tests, it was determined that both the upper and lower

sections recovery sections would require 4 grams of black powder to successfully separate the

subscale sections and deploy the parachutes. When flown in this configuration, the subscale was

successfully recovered.

Full scale separation testing was performed at an off-site testing location on February 13, 2018,

and utilized seven grams of black powder per charge cup. The amount of black powder used was

Page 145: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

145

determined via the aforementioned equations, and confirmed with estimations based on previous

projects. These determined amounts proved to be acceptable, as the separation test was completely

successful. Both the nose cone and the recovery section separated cleanly. Additionally, both

sections separated successfully during flight testing.

Figure 12.2: Full-Scale Separation Test of the Upper Section

Design Changes due to Test

For subscale, the 4 grams of black powder per charge cup determined still fit within the original

charge cup design, and all recovery components fit into the section, so no changes were necessary.

Additionally, full scale testing with seven grams per charge cup confirmed the effectiveness of the

system. The separation system will remain unchanged in the final rocket.

Page 146: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

146

Section 12.4: Tension Testing of Composite and 3D Printed Material (AU 2.1,

2.2)

Test Objective

This test aimed to verify that the characteristics of all materials used to construct any portion of

the rocket are consistent with expected values, in accordance with AU requirements:

AU 2.1 Materials used to construct any portion of the rocket will undergo testing to ensure

…………….that materials characteristics are consistent with expected values.

AU 2.2 Materials used to construct any portion of the rocket will undergo testing to ensure

…………….that materials characteristics are consistent with expected values.

This test was to be considered successful if the materials tested show consistent results with

expected values.

Justification

In order to ensure that the composite materials used in the rocket body are capable of handling the

stresses involved in the launch and recovery, the materials properties must be determined. As the

properties of composite materials vary heavily depending on such factors as matrix orientation,

number of layers, and resin type, the properties of the specific composites the team will be using

must be determined via testing.

Test components

-Onyx 3D-printed Carbon Fiber

-Epoxy Carbon Fiber

-Epoxy Fiberglass

Procedure

Page 147: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

147

1. For the tensile testing, the team took the plates of Onyx 3D-printed Carbon Fiber, Epoxy

Carbon Fiber, and Epoxy Fiberglass, and measured their length, width, and depth using

dial calipers.

2. Once in the materials testing lab, the team outfitted the Instron Multipurpose testing

machine with the hardware appropriate for the thickness of each material.

3. After proper setup of the machine, measurements were taken again to ensure absolute

accuracy.

4. The material sample dimensions were then inputted into the computer interface.

5. The material was then placed between the grips of the apparatus and the chuck was

torqued to ensure proper grip on the material being tested

6. The load and strain were then zeroed out on the computer interface, after which the test

was commenced.

7. The data was then analyzed and plotted until the max stress and load of each specimen

was reached, and the sample torn, at which point the machine automatically ended the

test.

Section 12.4.1: Results

Figure 12.3: Epoxy - Carbon Fiber Tension Test Results

Page 148: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

148

Figure 12.4: Epoxy - Fiberglass Tension Test Results

Page 149: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

149

Figure 12.5: Onyx Tension Test Results

This test provided the data that allows for the calculation of the maximum stress, modulus, tensile

strength and the tensile strain at the maximum load of all of the materials used in the structural

aspects of the rocket. This allows for the determination of the wall dimensions to allow for the

rocket to be stable in flight and during recovery. The stresses that the samples were put under were

much higher than would be seen in a normal flight/recovery pattern, proving the structural integrity

of the materials used.

Section 12.5: 3-Point Bend Testing of Composite and 3D Printed Material (AU

2.1, 2.2, 6.7)

Test Objective

This test aimed to verify that the characteristics of all materials used to construct any portion of

the rocket are consistent with expected values, in accordance with AU requirements:

AU 2.1 Materials used to construct any portion of the rocket will undergo testing to ensure

…………….that materials characteristics are consistent with expected values.

Page 150: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

150

AU 2.2 Materials used to construct any portion of the rocket will undergo testing to ensure

…………….that materials characteristics are consistent with expected values.

AU 6.7 Drag plates must be able to withstand the perpendicular force of the airflow

This test was to be considered successful if the materials tested show consistent results with

expected values.

Justification

In order to ensure that the composite materials used in the rocket body are capable of handling the

stresses involved in the launch and recovery, the materials properties must be determined. As the

properties of composite materials vary heavily depending on such factors as matrix orientation,

number of layers, and resin type, the properties of the specific composites the team will be using

must be determined via testing.

Test components

-Onyx 3D-printed Carbon Fiber

-Epoxy Carbon Fiber

-Epoxy Fiberglass

Procedure

-The machine used for this test was the Instron Multipurpose testing machine.

1. First, five samples of each type of material were constructed and their length, width, and

thickness were measured using calipers for accuracy.

2. Once in the materials lab, measurements were taken again to ensure absolute accuracy

within the machine.

3. The material sample dimensions were then input into the computer interface.

4. The material sample was then placed within the apparatus and lined up by eye to center it

between two solid contact points. The machine was then positioned with accuracy using

various dials to ensure the contact arm was slightly in contact with the material species.

Page 151: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

151

5. The load and extension were zeroed then the user began the test within the interface of

the computer.

6. The data was then analyzed and plotted until the max flexure load of each specimen was

reached, at which point the machine automatically ended the test.

Section 12.5.1: Results

Figure 12.6: Epoxy - Carbon Fiber Bend Test Results

Page 152: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

152

Figure 12.7: Epoxy - Fiberglass Bend Test Results

Figure 12.8: Onyx Bend Test Results

Page 153: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

153

This test provided the data that allows for the calculation of the maximum stress of all of the

materials used in the structural aspects of the rocket. This allows for the determination of the wall

thicknesses to allow for the rocket to be stable in flight and during recovery. The stresses that the

samples were put under were much higher than would be seen in a normal flight/recovery pattern,

proving the structural integrity of the materials used. This does not result in any design changes,

but instead was useful for design creation.

Section 12.6: Compression Testing of Composite and 3D Printed Material (AU

2.1, 2.2, 6.7)

Test Objective

This test aimed to verify that the characteristics of all materials used to construct any portion of

the rocket are consistent with expected values, in accordance with AU requirements:

AU 2.1 Materials used to construct any portion of the rocket will undergo testing to ensure

…………….that materials characteristics are consistent with expected values.

AU 2.2 Materials used to construct any portion of the rocket will undergo testing to ensure

…………….that materials characteristics are consistent with expected values.

AU 6.7 Drag plates must be able to withstand the perpendicular force of the airflow

This test was to be considered successful if the materials tested show consistent results with

expected values.

Justification

In order to ensure that the composite materials used in the rocket body are capable of handling the

stresses involved in the launch and recovery, the materials properties must be determined. As the

Page 154: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

154

properties of composite materials vary heavily depending on such factors as matrix orientation,

number of layers, and resin type, the properties of the specific composites the team will be using

must be determined via testing.

Test components

-Onyx 3D-printed Carbon Fiber

-Epoxy Carbon Fiber

-Epoxy Fiberglass

Procedure

-The machine used for this test will be the Instron Multipurpose testing machine. Due to

equipment availability restraints, these tests could not be completed this year, and instead data

from previous years were used during construction.

1. First, five samples of each type of material were constructed and their length, width, and

thickness were measured using calipers for accuracy.

2. Once in the materials lab, measurements were taken again to ensure absolute accuracy

within the machine.

3. The material sample dimensions were then input into the computer interface.

4. The material sample was then placed within the apparatus and lined up by eye to center it

between two solid contact points. The machine was then positioned with accuracy using

various dials to ensure the contact arm was slightly in contact with the material species.

5. The load and extension were zeroed then the user began the test within the interface of

the computer.

6. As the progressively larger load was applied, the data was then analyzed and plotted until

each specimen reached -30% elongation, at which point the machine automatically ended

the test.

Section 12.6.1: Results

Page 155: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

155

Onyx 3D-printed Carbon Fiber

Epoxy Carbon Fiber and Epoxy Fiberglass

After discussing testing methods with a materials testing oriented professor and consulting the

ASTM procedure for compression testing on unidirectional composites, it was determined that the

team’s home university did not have the proper equipment to conduct the test. However, based on

a combination of experience from previous projects and consultation with the assisting professor,

the team is confident in the materials’ abilities to withstand compressive forces during launch.

Potential design changes

Page 156: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

156

Although unlikely, if this year’s data did not vary significantly from the previous structural data

used to design the rocket, so no design changes will be made to reinforce vulnerable rocket

components.

Section 12.7: Rover Maneuverability (AU 4.2, 4.3, 4.6, 4.7)

Test Objective

As outlined in requirements

AU 4.2 Rover can be activated remotely from a distance

AU 4.3 Rover must be able to traverse various expected terrains

AU 4.6 Rover must be able to exit the vehicle body from any orientation

AU 4.7 Rover will successfully deploy solar panels after travelling at least 5 feet

This test will aim to determine the cross country performance of the rover, and whether it will be

able to cross the farm field after leaving the rocket from any orientation. While already on testing

all these other aspects of the rover, it makes sense to test the remote activation as well. Success

will be defined as accomplishing all mission objectives.

Justification

The competition launch will take place on a farmer’s field. Cropland, whether left fallow or

planted in, will be very rough terrain for a small rover. Tufts of grass, grooves in the dirt from the

plow, eroded paths left by water runoff, and mud are all major obstacles when compared to the

size of the rover. To reach the desired distance, however, the rover must be able to cross these

obstacles. To complete its objective, the rover must then also be communicated with and deploy

solar panels.

Test Components

-Completed Rover

Page 157: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

157

-Rocket rover bay (optional)

-Shovel

-Measuring equipment

Procedure

The expected obstacles are characteristics shared by many open fields, including those used as

extra parking on Auburn’s Campus. Therefore, the rover can simply be taken to one of these

locations and activated to see if it can cross the terrain. If the team cannot find particular terrain

features outlined in AU 4.3, the shovel will be used to construct that feature.

After finished testing that capability, the lower section of the rocket, or at least the rover bay, can

be staged on the field as if it had just landed. AU 4.2 will be tested to see if the rover can be

activated remotely while it is inside the rocket. Once remote activation has been verified, the rover

will be remotely activated while the rover bay is rotated off the horizontal at various angles to

determine if it can leave the rocket after landing in any orientation and will be commanded to

deploy solar panels to verify AU 4.6 and 4.7.

Section 12.7.1: Results

By orienting the rover bay with regards to the fins at the rocket rear, instead of needing to deploy

from any orientation the rover only needed to be able to deploy when lying at a 45-degree angle,

with either side on the top. This was them verified with a completed assembly of the entire rocket

aft of the rover bay and the rover for the four possible orientations.

Prior to the full-scale launch on February 17 in Sylacauga, the rover was placed out in the launch

field and activated remotely. Team members placed the rover in front of various terrain obstacles,

such as the aforementioned slopes, dips, mud patches, and tufts of grass. The rover was able to

contend satisfactorily with all terrain obstacles of a size similar or smaller than itself without issue.

Dried corn stalks and ruts deeper than the rover body with steep sides proved impassable, and no

attempt was made to ford deep standing water.

Page 158: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

158

Possible design impacts

As the rover was able to exit the rocket from any landed orientation, the design is considered

verified.

Section 12.8: Altitude Control System (AU 6.4 – 6.8)

Test Objective

This test aims to address several closely related team derived requirements for the altitude control

system, which are seen in the table below.

AU

Requirement Description

AU 6.4 Subsystem components must engage accordingly after boost phase and stay online

for the remainder of the flight.

AU 6.5 Controller and IMU must be able to correctly predict the projected altitude of the

launch vehicle.

AU 6.6 Drag plates must deploy after boost phase in order to self-correct the trajectory of

the launch vehicle.

AU 6.7 Drag plates must be able to withstand the perpendicular force of the airflow.

AU 6.8 The altitude control system must be able to correct the vehicles altitude from

overshoot to 5280 ft.

Page 159: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

159

To test all of these requirements at once, a special test 6” rocket will be constructed (time and

funds permitting). This rocket will be 6” diameter, like the actual full scale, but will be shorter,

possessing a weaker motor and greatly simplified recovery. The altitude control system will

control this rocket to a lower altitude of 3200 ft. The test will be considered a success if the altitude

control system can fulfill all the above requirements, albeit to a lower altitude.

If this cannot be tested in a separate rocket, these requirements will be verified by a launch of the

system inside the completed full-scale rocket.

Justification

A major component of the competition is the altitude requirement. However, an altitude control

system can also be the most dangerous aspect of a rocket, even in the case of our team’s design

where an engineering control has been applied to prevent asymmetric drag. The system is also

difficult to meaningfully ground test. Therefore, by first testing the system on an expendable

rocket with a lower apogee, the team can improve safety and avoid risking any of the other full-

scale components, such as the isogrid body tube, that are difficult to replace at short notice.

Finally, more construction will provide additional experience for the team’s junior members.

Test Components

-Completed Altitude control system (designed to be easily added and removed from the rocket,

and retargetable for different altitudes)

-6” Diameter, 88” length test rocket with recovery system

-Aerotech K560W-P Motor

Procedure

Due to the similarity of this test to a full-scale launch, the procedure for this test will be the same

as the procedure of a full scale launch, as seen in the launch checklist.

Page 160: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

160

Section 12.8.1: Results

The altitude control system was implemented on the March 3, 2018, full scale launch in Samson,

Alabama. The system was active, correctly predicted the altitude for the launch vehicle, and stood

by to deploy the altitude control surfaces to control the vehicle’s energy. However, due to other

circumstances with the launch inside the isogrid rocket, the apogee was only around 3200 feet, and

therefore the altitude control system did not actuate to control the rocket’s altitude. Therefore, AU

6.1-6.5 were verified, as they only relate to the electronics’ ability to function during a launch and

predict the altitude of the rocket, but AU 6.6 to 6.8, which relate to the performance of the drag

plates themselves were not verified.

Design Impact

The altitude control system electronics are verified, but since it did not manage the energy of the

rocket successfully (it did not get a chance to), the altitude control system will not be active at

competition. However, since the design is complete and modular, it can easily be implemented

into future Auburn designs.

Section 13: Project Plan

Section 13.1: Requirements Verification

Section 13.1.1: General Requirements

Table 10.1: General Requirements Verification

Requirement

Number Requirement Statement Verification Method

Execution of

Method

Page 161: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

161

1.1

Students on the team will do

100% of the project,

including design,

construction, written reports,

presentations, and flight

preparation with the

exception of assembling the

motors and handling black

powder or any variant of

ejection charges, or preparing

and installing electric

matches (to be done by the

team’s mentor).

Demonstration

Throughout the

competition, student

members of USLI

have handled all

tasks beyond those

specifically restricted

to the team’s mentor.

1.2

The team will provide and

maintain a project plan to

include, but not limited to the

following items: project

milestones, budget and

community support,

checklists, personnel

assigned, educational

engagement events, and risks

and mitigations.

Demonstration

The team provided

and maintained a

project plan

throughout the

duration of the

competition.

1.3

Foreign National (FN) team

members must be identified

by the Preliminary Design

Review (PDR) and may or

may not have access to

Demonstration

FN team members

were identified by the

PDR.

Page 162: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

162

certain activities during

launch week due to security

restrictions. In addition, FN’s

may be separated from their

team during these activities.

1.4

The team must identify all

team members attending

launch week activities by the

Critical Design Review

(CDR)

Demonstration

The team has

identified all

members attending

launch week by

CDR.

1.5

The team will engage a

minimum of 200 participants

in educational, hands-on

science, technology,

engineering, and mathematics

(STEM) activities, as defined

in the Educational

Engagement Activity Report,

by FRR. An educational

engagement activity report

will be completed and

submitted within two weeks

after completion of an event.

A sample of the educational

engagement activity report

can be found on page 31 of

the handbook. To satisfy this

requirement, all events must

occur between project

Demonstration

The team has

completed the

Educational

Engagement

requirements,

engaging over 400

participants on Junior

E-Day alone.

Page 163: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

163

acceptance and the FRR due

date

1.6

The team will develop and

host a Web site for project

documentation.

Demonstration

The team developed

and hosts a Web site

for project

documentation.

1.7

Teams will post, and make

available for download, the

required deliverables to the

team Web site by the due

dates specified in the project

timeline.

Demonstration

The team posted the

required deliverables

to the team Web site

by the due dates

specified.

1.8 All deliverables must be in

PDF format Demonstration

All deliverables are

in PDF format.

1.9

In every report, teams will

provide a table of contents

including major sections and

their respective sub-sections

Demonstration Every report contains

a table of contents.

1.10

In every report, the team will

include the page number at

the bottom of the page.

Demonstration Every report includes

page numbers.

1.11

The team will provide any

computer equipment

necessary to perform a video

teleconference with the

review panel. This includes,

but is not limited to, a

Demonstration

The team provided

all necessary

equipment for the

video

teleconferences.

Page 164: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

164

computer system, video

camera, speaker telephone,

and a broadband Internet

connection. Cellular phones

can be used for speakerphone

capability only as a last

resort.

1.12

All teams will be required to

use the launch pads provided

by Student Launch’s launch

service provider. No custom

pads will be permitted on the

launch field. Launch services

will have 8 ft. 1010 rails, and

8 and 12 ft. 1515 rails

available for use.

Demonstration

The team used the

launch pads

provided.

1.13

Teams must implement the

Architectural and

Transportation Barriers

Compliance Board Electronic

and Information Technology

(EIT) Accessibility Standards

(36 CFR Part 1194)

Demonstration

The team

implemented the EIT

Accessibility

Standards.

1.14

Each team must identify a

“mentor.” A mentor is

defined as an adult who is

included as a team member,

who will be supporting the

Demonstration

The team has

identified a mentor,

Dr. Eldon Triggs.

Page 165: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

165

team (or multiple teams)

throughout the project year,

and may or may not be

affiliated with the school,

institution, or organization.

The mentor must maintain a

current certification, and be in

good standing, through the

National Association of

Rocketry (NAR) or Tripoli

Rocketry Association (TRA)

for the motor impulse of the

launch vehicle and must have

flown and successfully

recovered (using electronic,

staged recovery) a minimum

of 2 flights in this or a higher

impulse class, prior to PDR.

The mentor is designated as

the individual owner of the

rocket for liability purposes

and must travel with the team

to launch week. One travel

stipend will be provided per

mentor regardless of the

number of teams he or she

supports. The stipend will

only be provided if the team

passes FRR and the team and

Page 166: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

166

mentor attends launch week

in April.

Section 1.1.1: Vehicle Requirements

Table 10.2: Vehicle Requirements Verification

Requirement

Number

Requirement

Statement

Verification

Method Execution of Method

2.1

The vehicle shall

deliver the science

or engineering

payload to an

apogee altitude of

5,280 feet above

ground level

(AGL).

Analysis

Demonstration

The vehicle has been

launched, and upon

recovery the altimeters will

be checked.

2.2

The vehicle shall

carry one

commercially

available,

barometric

altimeter for

recording the

official altitude

used in

determining the

Inspection

Demonstration

A commercially available,

barometric altimeter has

been purchased and

calibrated for the vehicle.

Page 167: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

167

altitude award

winner.

2.3

Each altimeter

will be armed by a

dedicated arming

switch that is

accessible from

the exterior of the

rocket airframe

when the rocket is

in the launch

configuration on

the launch pad.

Inspection

Demonstration

The altimeters are designed

and constructed to be armed

from outside the vehicle

2.4

Each altimeter

will have a

dedicated power

supply.

Inspection

Demonstration

Each altimeter in use on the

rocket has a dedicated

power supply.

2.5

Each arming

switch will be

capable of being

locked in the ON

position for launch

(i.e. cannot be

disarmed due to

flight forces).

Demonstration

Each arming switch cannot

be disabled by launch

forces, as seen by the

successful full scale flight.

Page 168: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

168

2.6

The launch

vehicle shall be

designed to be

recoverable and

reusable. Reusable

defined as being

able to launch

again on the same

day without

repairs or

modifications.

Testing

Analysis

Demonstration

Inspection

Trajectory simulations have

indicated that the rocket

will be reusable. Flight

testing has demonstrated the

launch vehicle is

recoverable and reusable

2.7

The launch

vehicle shall have

a maximum of

four (4)

independent

sections.

Demonstration

The team has designed a

launch vehicle that has two

independent sections.

2.8

The launch

vehicle shall be

limited to a single

stage.

Demonstration As designed, the launch

vehicle is a single stage.

2.9

The launch

vehicle shall be

capable of being

prepared for flight

at the launch site

within 3 hours,

from the time the

Demonstration

Subscale and full-scale

launches days have shown

that the rocket can be

readied for launch in the

required 3 days.

Page 169: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

169

Federal Aviation

Administration

flight waiver

opens.

2.10

The launch

vehicle shall be

capable of

remaining in

launch-ready

configuration at

the pad for a

minimum of 1

hour without

losing the

functionality of

any critical on-

board component.

Demonstration

Testing

All components of the

launch vehicle can remain

in a pad ready position for

over an hour without losing

functionality, as verified

through component testing.

2.11

The launch

vehicle shall be

capable of being

launched by a

standard 12-volt

direct current

firing system. The

firing system will

be provided by the

NASA-designated

Demonstration

The rocket can be flown

using the launch controller

provided by the Range

Services Provider, as

proven by the successful

full-scale launches.

Page 170: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

170

Range Services

Provider.

2.12

The launch

vehicle shall

require no external

circuitry or special

ground support

equipment to

initiate launch

(other than what is

provided by

Range Services).

Demonstration

The rocket, as designed,

does not require any extra

launch equation.

2.13

The launch

vehicle shall use a

commercially

available solid

motor propulsion

system using

ammonium

perchlorate

composite

propellant (APCP)

which is approved

and certified by

the National

Association of

Demonstration

Vehicle is designed around

commercially available,

certified motors

Page 171: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

171

Rocketry (NAR),

Tripoli Rocketry

Association

(TRA), and/or the

Canadian

Association of

Rocketry (CAR).

2.13.1

Final motor

choices must be

made by the

Critical Design

Review (CDR).

Demonstration

The motor used for the

competition has been

determined, an Aerotech L-

1420R

2.13.2

Any motor

changes after

CDR must be

approved by the

NASA Range

Safety Officer

(RSO), and will

only be approved

if the change is for

the sole purpose of

increasing the

safety margin.

Demonstration No change will be

necessary after CDR

2.14

Pressure vessels

on the vehicle

shall be approved

by the RSO and

Analysis

Testing

No pressure vessels were

used on the rocket this year.

Page 172: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

172

shall meet the

following criteria:

2.14.1

The minimum

factor of safety

(Burst or Ultimate

pressure versus

Max Expected

Operating

Pressure) shall be

4:1 with

supporting design

documentation

included in all

milestone reviews.

Inspection

Analysis

Testing

No pressure vessels were

used on the rocket this year.

2.14.2

Each pressure

vessel shall

include pressure

relief valve that

sees the full

pressure of the

tank.

Inspection

Analysis

Testing

No pressure vessels were

used on the rocket this year.

2.14.3

Full pedigree of

the tank shall be

described,

including the

application for

Inspection

Demonstration

No pressure vessels were

used on the rocket this year.

Page 173: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

173

which the tank

was designed, and

the history of the

tank, including the

number of

pressure cycles

put on the tank, by

whom, and when.

2.15

The total impulse

provided by a

College and/or

University launch

vehicle shall not

exceed 5,120

Newton-seconds

(L-class).

Demonstration

Analysis

The team has chosen a

motor with a total impulse

that does not exceed 5,120

Newton-seconds (L-class),

an Aerotech L-1420R with

an impulse of 4616

Newton-seconds.

2.16

The launch

vehicle shall have

a minimum static

stability margin of

2.0 at the point of

rail exit.

Testing

Demonstration

Analysis

The team designed and

tested the vehicle to ensure

that it has a stability margin

of greater than 2.0 at the

point of rail exit.

2.17

The launch

vehicle shall

accelerate to a

minimum velocity

Demonstration

Analysis

Testing

The team designed and

flight tested the vehicle to

ensure that its minimum

velocity at rail exit is at

least 52 fps.

Page 174: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

174

of 52 fps at rail

exit.

2.18

All teams shall

successfully

launch and

recover a subscale

model of their

rocket prior to

CDR.

Demonstration

Testing

A subscale model of the

rocket was flown and

recovered successfully prior

to CDR.

2.18.1

The subscale

model should

resemble and

perform as

similarly as

possible to the

full-scale model,

however, the full-

scale shall not be

used at the

subscale model.

Demonstration

The subscale model was

designed and constructed to

resemble and perform

similarly to the full-scale

model.

2.18.2

The subscale

model shall carry

an altimeter

capable of

reporting the

Demonstration

An altimeter capable of

reporting the model’s

apogee altitude was

implemented on the

subscale model.

Page 175: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

175

model’s apogee

altitude.

2.19

All teams shall

successfully

launch and

recover their full-

scale rocket prior

to FRR in its final

flight

configuration. The

rocket flown at

FRR must be the

same rocket flown

on launch day.

The following

criteria must be

met during the

full-scale

demonstration

flight:

Testing

Demonstration

Analysis

A successful launch and

recovery of a full-scale

rocket was accomplished

prior to FRR.

2.19.1

The vehicle and

recovery system

shall have

functioned as

designed.

Testing

Demonstration

The recovery system

functioned as designed.

Page 176: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

176

2.19.2.1

If the payload is

not flown, mass

simulators shall be

used to simulate

the payload mass.

Testing

Demonstration

Analysis

The rover (payload) was

flown.

2.19.2.1.1

The mass

simulators shall be

located in the

same approximate

location on the

rocket as the

missing payload

mass.

Inspection

By flying the actual

payload, the mass was

located exactly where

planned for the competition

launch.

2.19.3

If the payload

changes the

external surfaces

of the rocket (such

as with camera

housings or

external probes) or

manages the total

energy of the

vehicle, those

systems shall be

activated during

the full-scale

demonstration of

flight.

Demonstration

Testing

The rover payload does not

affect the total energy of the

vehicle.

Page 177: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

177

2.19.4

The full-scale

motor does not

have to be flown

during the full-

scale test flight.

Inspection

Demonstration

The full-scale motor was

not flown during the full-

scale test due to extremely

low availability, as only one

could be secured.

2.19.5

The vehicle shall

be flown in its

fully ballasted

configuration

during the full-

scale test flight.

Demonstration

The vehicle will be fully

ballasted during test flights.

2.19.6

After successfully

completing the

full-scale

demonstration

flight, the launch

vehicle or any of

its components

shall not be

modified without

the concurrence of

the NASA Range

Safety Officer

(RSO).

Demonstration

The team will not alter any

components or vehicle after

demonstration flight.

2.19.7

Full scale flights

must be completed

by the start of

FRRs (March 6th,

Demonstration

The full-scale flight will be

completed by March 6,

2018. If for some reason the

full-scale flight is not

Page 178: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

178

2018). If

necessary, an

extension to

March 28th, 2018

will be granted.

Only granted for

re-flights.

completed by March 6,

2018, NASA will grant an

extension to March 28,

2018 for a re-flight attempt.

2.20

Any structural

protuberance on

the rocket shall be

located aft of the

burnout center of

gravity.

Demonstration

Team designed and

constructed rocket such that

all structural protuberances

on the vehicle to be aft of

the burnout center of

gravity.

2.21 Vehicle

Prohibitions

2.21.1

The launch

vehicles shall not

utilize forward

canards.

Demonstration The Launch vehicle does

not use forward canards.

2.21.2

The launch

vehicle shall not

utilize forward

firing motors.

Demonstration

The team designed the

vehicle so that it does not

utilize forward firing

motors.

Page 179: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

179

2.21.3

The launch

vehicle shall not

utilize motors that

expel titanium

sponges (Sparky,

Skidmark,

MetalStorm, etc.)

Demonstration

The team will not utilize a

motor that expels titanium

sponges.

2.21.4

The launch

vehicle shall not

utilize hybrid

motors.

Demonstration The team will not utilize a

hybrid motor.

2.21.5

The launch

vehicles shall not

utilize a cluster of

motors.

Demonstration

A demonstration and

inspection of the launch

vehicle shall be carried out

to validate it does not use a

cluster of motors.

2.21.6

The launch

vehicle shall not

utilize friction

fitting for motors.

Demonstration

The team will design the

vehicle so that it does not

utilize friction fitting for the

motor.

2.21.7

The launch

vehicle shall not

exceed Mach 1 at

any point during

flight.

Demonstration

Testing

Analysis

The team has flight tested

the rocket to demonstrate to

ensure that the vehicle does

not exceed Mach 1 at any

point during flight

Page 180: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

180

2.21.8

Vehicle Ballast

shall not exceed

10% of the total

weight of the

rocket.

Demonstration

Testing

Analysis

The team will design ballast

so that it does not exceed

10% of the total weight of

the rocket.

Section 1.1.2: Recovery Requirements

Table 10.3: Recovery Requirements Verification

Requirement

Number

Requirement

Statement Verification Method

Execution of

Method

3.1

The launch vehicle

shall stage the

deployment of its

recovery devices,

where a drogue

parachute is deployed

at apogee and a main

parachute is deployed

at a much lower

altitude. Tumble

recovery or streamer

recovery from apogee

to main parachute

deployment is also

permissible, provided

Design

Testing

The team has staged

the deployment of the

recovery devices with

a drogue parachute

deployed at apogee

(5280 ft.), and two

main parachutes

deployed at 750 ft.

Page 181: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

181

that kinetic energy

during drogue-stage

descent is reasonable,

as deemed by the

Range Safety Officer.

3.2

Each team must

perform a successful

ground ejection test

for both the drogue

and main parachutes.

This must be done

prior to the initial

subscale and full-

scale launches.

Testing

Prior to the initial

subscale and full-

scale launches, the

team has performed a

ground ejection test

for both the drogue

and upper main

parachute section as

well as the lower

main parachute

section.

3.3

At landing, each

independent sections

of the launch vehicle

shall have a

maximum kinetic

energy of 75 ft-lbf.

Design

Demonstration

The team has flight

test and calculated

both sections of our

launch vehicle to

ensure that a

maximum energy of

Page 182: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

182

75 ft-lbf at landing is

not exceeded.

3.4

The recovery system

electrical circuits

shall be completely

independent of any

payload electrical

circuits.

Design

The team has created

independent circuits

for the recovery

system so that they

are independent of all

payload electrical

circuits.

3.5

All recovery

electronics will be

powered by

commercially

available batteries.

Design

The recovery system

utitlizes

commercially

available 9V batteries

to power the two

altimeters.

3.6

The recovery system

shall contain

redundant,

commercially

available altimeters.

The term “altimeters”

includes both simple

altimeters and more

sophisticated flight

computers.

Design

The recovery system

includes a

TeleMetrum and

TeleMega altimeter

each with their own

independent set of

charges for each

section.

Page 183: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

183

3.7

Motor ejection is not

a permissible form of

primary or secondary

deployment.

Design

The team does not

use motor ejection as

a primary or

secondary

deployment. An

electronic form of

recovery deployment

is used.

3.8

Removable shear

pins will be used for

both the main

parachute

compartment and the

drogue parachute

compartment.

Design

The team will use

removable shear pins

for both the main

parachute

compartment and the

drogue parachute

compartment.

3.9

Recovery area will be

limited to a 2500 ft.

radius from the

launch pads.

Design

The main parachutes

deploy from a low

enough altitude so

that the rocket will

not drift more than

2500 ft.

3.10

An electronic

tracking device shall

be installed in the

launch vehicle and

shall transmit the

position of the

tethered vehicle or

Design

The team installs a

tracking device on

both sections of the

launch vehicle so that

the location of both

pieces can be

Page 184: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

184

any independent

section to a ground

receiver.

determined after

landing.

3.10.1

Any rocket section,

or payload

component, which

lands untethered to

the launch vehicle,

shall also carry an

active electronic

tracking device.

Design

All separating

sections of the rocket

contain their own

tracking device.

3.10.2

The electronic

tracking device shall

be fully functional

during the official

flight on launch day

Verification

The team tests and

makes sure the

electronic tracking

devices will be fully

functional during the

official flight before

each launch.

3.11

The recovery system

electronics shall not

be adversely affected

by any other on-

board electronic

devices during flight

Testing

The team has

demonstrated through

flight testing that the

recovery system will

not be adversely

affected by any other

Page 185: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

185

(from launch until

landing).

on-board electronic

devices during flight.

3.11.1

The recovery system

altimeters shall be

physically located in

a separate

compartment within

the vehicle from any

other radio frequency

transmitting device

and/or magnetic

wave producing

device.

Design

The recovery system

altimeters are located

in a separate

compartment within

the vehicle from any

radio frequency

transmitting devices,

and magnetic wave

producing devices.

3.11.2

The recovery system

electronics shall be

shielded from all

onboard transmitting

devices, to avoid

inadvertent excitation

of the recovery

system electronics.

Design

The recovery

electronics are sealed

in their own separate

compartment separate

from all other

transmitting devices

in the rocket.

3.11.3

The recovery system

electronics shall be

shielded from all

onboard devices

Design

The recovery

electronics are sealed

in their own separate

compartment separate

Page 186: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

186

which may generate

magnetic waves

(such as generators,

solenoid valves, and

Tesla coils) to avoid

inadvertent excitation

of the recovery

system.

from all other

magnetic wave

inducing devices in

the rocket.

3.11.4

The recovery system

electronics shall be

shielded from any

other onboard

devices which may

adversely affect the

proper operation of

the recovery system

electronics.

Design

The recovery

electronics are sealed

in their own separate

compartment separate

from all other devices

in the rocket which

could adversely affect

the proper operation

of the recovery

system.

Section 13.1.2: Deployable Rover Requirements

Table 13.1: Deployable Rover Requirements Verification

Page 187: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

187

Requirement

Number

Requirement

Statement

Verification

Method Execution of Method

4.5.1

Teams will design a

custom rover that will

deploy from the internal

structure of the launch

Demonstration,

test, inspection

Demonstration and testing

before the launch will ensure

the rover can fit inside the

rocket and is fit to maneuver

difficult terrain

4.5.2

At landing, the team will

remotely activate a

trigger to deploy the

rover from the rocket

Demonstration,

test, inspection

Demonstration and testing will

be done before the flight to

validate that the rover will

receive the deployment signal.

Inspection afterward will also

ensure successful rover

deployment

4.5.3

After deployment, the

rover will autonomously

move at least 5 ft from

the launch vehicle

Demonstration,

test, inspection

Demonstration and testing will

be conducted before the launch

to determine the exact distance

the rover will travel

4.5.4

Once the rover has

reached its final

destination, it will deploy

a set of foldable solar cell

panels

Demonstration,

test, inspection

Demonstration and testing will

be performed on the solar panel

deployment system (SPDS) to

ensure that the system can

successfully deploy the solar

panels

Page 188: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

188

Section 13.1.3: Safety Requirements

Requirement

Number Requirement Statement

Verification

Method Execution of Method

5.1

Each team will use a launch

and safety checklist. The final

checklists will be included in

the FRR report and used

during the Launch Readiness

Review (LRR) and any

launch day operations.

Demonstration The team will use

checklists.

5.2

Each team must identify a

student safety officer who

will be responsible for all

items in section 5.3.

Demonstration The team has identified a

safety officer.

5.3

The role and responsibilities

of each safety officer will

include, but not limited to: a

bunch of things.

Demonstration The safety officer is aware

of his responsibilities.

5.4

During test flights, teams will

abide by the rules and

guidance of the local rocketry

club’s RSO. The allowance of

certain vehicle configurations

and/or payloads at the NASA

Student Launch Initiative

Demonstration The team will follow the

rules.

Page 189: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

189

does not give explicit or

implicit authority for teams to

fly those certain vehicle

configurations and/or

payloads at other club

launches. Teams should

communicate their intentions

to the local club’s President

or Prefect and RSO before

attending any NAR or TRA

launch.

5.5 Teams will abide by all rules

set forth by the FAA. Demonstration

The team will follow the

rules.

Section 13.2: Team Requirements

Section 13.2.1: General Requirements

Table 13.2: AU General Requirements

Team

Requirement

Requirement

Statement Derivation

Verification

Method

Method of

Execution

AU 1.1

All Educational

Engagement

forms will be

submitted and

This requirement

was made

because last year

a large number

Demonstration

The team will

submit EE

reports within a

week and check

Page 190: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

190

verified to have

been received

within 1 week of

an outreach event.

of education

events where

completed, but

the forms where

not submitted on

time

that they have

been properly

received. This

procedure will

be continued to

be upheld going

forward.

Section 13.2.2: Vehicle Requirements

Table 13.3: AU Vehicle Requirements

Team

Requirement

Requirement

Statement Derivation

Verification

Method

Method of

Execution

AU 2.1

Materials used to

construct any

portion of the

rocket will

undergo testing

to ensure that

materials

characteristics

are consistent

with expected

values.

It is important to

verify the material

properties of rocket

components, and to

maintain the

knowledge base to

conduct materials

testing if new

materials are

introduced in the

future.

Test

All tests are

completed, using

Auburn

University

constructed

samples on AU

testing

equipment.

AU 2.2 3D printed

components will

It is important to

verify the material Test

All tests are

completed, using

Page 191: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

191

have strength

comparable to

alternatives and

appropriate for

their role

properties of rocket

components, and to

maintain the

knowledge base to

conduct materials

testing if new

materials are

introduced in the

future.

Auburn

University

constructed

samples on AU

testing

equipment.

Section 13.2.3: Recovery Requirements

Table 13.4: AU Recovery Requirements

Team

Requirement

Requirement

Statement Derivation

Verification

Method Method of Execution

AU 3.1

Recovery

electronics

must be able

function after

being left on

for more than

two hours.

From team

observations of last

year’s competition,

rockets could be

on the standby for

almost an hour,

and we want our

rocket to have a

large margin of

safety over this

time.

Test

The recovery

electronics (excluding

e-matches and black

powder for safety

reasons) have been

assembled and left in

the on/standby

position until loss of

function to determine

system longevity

Page 192: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

192

AU 3.2

Recovery

system will be

able to separate

rocket into

desired

sections using

the minimum

amount of

black powder

for reliable

results, to

ensure safety.

Too much black

powder is

dangerous, but too

little is also

dangerous because

a failed ejection

can result in a

ballistic rocket.

Test

Extensive ground

separation tests were

performed before

launch for both

subscale and full scale.

Section 13.2.4: Deployable Rover Requirements

Table 13.5: AU Rover Requirements

Team

Requirement

Requirement

Statement Derivation

Verification

Method

Method of

Execution

AU 4.1

With the

exception of

electronic parts,

the rover will be

3-D printed in-

house composites

Allows for cost

saving, rapid

design changes

and complex

geometries to

be created in

singular parts.

Demonstration

Rover parts are

designed and printed

in-house so that the

team can continue to

precisely

manufacture rover

parts

Page 193: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

193

AU 4.2

Rover activation

signal will

successfully reach

the rover up to a

certain distance

plus a large

tolerance distance

Activating the

rover remotely

is a

requirement,

and doing so at

an additional

distance

provides for a

margin of error

at competition.

Demonstration

Test

XBee has tested at

different distances to

ensure that the signal

will reach the rover

AU 4.3

Rover will be able

to traverse various

terrains (examples

include 45 degree

inclines and 3 inch

divots)

Launch fields

can be rough,

but the rover

must be

capable of

crossing them.

Demonstration

Test

Rover treads have

tested on various

terrains before the

launches and have

demonstrated

adequate traction

AU 4.4

Rover electronics

must be able

function after

being left on for

more than two

hours.

From team

observations of

last year’s

competition,

rockets could

be on the

standby for

almost an hour,

and we want

our rocket to

have a large

margin of

Test

The rover electronics

were run

continuously for

several hours and

have been proven to

be functional for

more than two hours.

Page 194: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

194

safety over this

time.

AU 4.5

Rover motors

must be able to

function after

more than two

hours of battery

drain.

From team

observations of

last year’s

competition,

rockets could

be on the

standby for

almost an hour,

and we want

our rocket to

have a large

margin of

safety over this

time.

Test

The rover motors

were run

continuously for

several hours and

have been proven to

be functional for

more than two hours.

AU 4.6

Rover must be

capable of exiting

rocket from any

orientation of

rocket body.

There is no

guarantee that

the rocket will

land at any

particular

orientation, but

the rover must

Test

The rover has placed

in section, rotated to

various angles in

increments of 30

degrees from

horizontal, and be

commanded to drive

out.

Page 195: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

195

still be

successful

AU 4.7

Rover will

successfully

deploy solar

panels after

travelling at least

5 feet

In order to

complete the

rover

requirements,

this must

occur.

Demonstration,

test

SPDS has been

shown to deploy after

travelling over

various terrain and

travelling varying

distances

Section 13.2.5: Safety Requirements

Team

Requireme

nt

Requirement Statement Derivation Verification

Method

Method of

Execution

AU 5.1

All team members will

work in groups of at least

two, ensuring immediate

assistance for any team

member in need.

Safety first Demonstratio

n

Team members

have not and will

not work alone.

Page 196: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

196

Section 13.2.6: Altitude Control Requirements

Table 13.6: AU Altitude Control Requirements

Team

Require

ment

Requirement

Statement Derivation

Verification

Method Method of Validation

AU 6.1

All

aerodynamic

data must be

validated

through

analytical and

experimental

testing.

In order to have an

accurate computer

model, the drag

contribution of each

plate must be

computed

Analysis

An aerodynamic analysis

of the drag plates and the

internal system was

conducted through

computational fluid

dynamics (CFD) and

sensor tests.

AU 6.2

Drag plates

must stay static

throughout

launch

Deploying the drag

plates before the

boost phase is over is

against competition

rules and is

dangerous.

Demonstration

A timer has been

implemented through the

controller that prevented

any system action prior

to the end of the boost

phase.

AU 6.3

Electronics

must stay

secured

throughout

flight.

Loose electronics,

are vulnerable to

damage from launch

forces, as learned

with previous

launches.

Demonstration

A housing was made for

all electrical components

to keep everything in

place.

Page 197: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

197

AU 6.4

Subsystem

components

must engage

accordingly

after boost

phase and stay

online for the

remainder of

the flight.

If the subsystem

components are not

engaged, they cannot

act to control the

rocket energy.

Test

Flight testing has

verified that the

behavioral integrity of

the system remains

intact.

AU 6.5

Controller and

IMU must be

able to

correctly

predict the

projected

altitude of the

launch vehicle.

The controller and

IMU must be able to

predict the max

altitude in order to

then act to control

the altitude.

Test

Flight testing has

confirmed that the IMU

can predict the projected

altitude of the launch

vehicle.

AU 6.6

Drag plates

must deploy

after boost

phase in order

to self-correct

the trajectory

of the launch

vehicle.

Deploying the drag

plates before the

boost phase is over is

against competition

rules and is

dangerous.

Test

“Hardware In-The-

Loop” testing has

occurred, but test flights

were unable to validate

deployment precision.

AU 6.7

Drag plates

must be able to

withstand the

If the drag plates

cannot withstand the

force required, they

Test

Wind tunnel testing and

structural testing has not

been able to ensure the

Page 198: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

198

perpendicular

force of the

airflow.

cannot perform the

altitude control

functions.

integrity of the plates

and the materials used to

construct them.

AU 6.8

The subsystem

must be able to

correct altitude

by at least 400

feet and be

accurate to 200

feet.

If the system is not

accurate, it could

hurt the team’s

ability to hit the

altitude requirement

instead of helping.

Analysis

Demonstration

The subsystem was

designed to conform to

accuracy requirements

and but could not be

demonstrated to be

accurate in a test flight.

AU 6.9

Altitude

control

electronics

must be able to

function after

being left on

for more than

two hours.

From team

observations of last

year’s competition,

rockets could be on

the standby for

almost an hour, and

we want our rocket

to have a large

margin of safety over

this time.

Test

The batteries, motors,

and Arduino with all

relevant electronics were

assembled and ran as

intended for several

hours, confirming the

electronics ability to

function for more than

two hours.

Page 199: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

199

Section 13.3: Budget

The budgets displayed in Table 13.9: Budget Allocation are the final costs allocated to the full-

scale vehicle, research and development, the subscale (rounded up for a factor of safety), travel,

and test flight fees. As the team will continue to perform outreach events, the educational

engagement budget is a close approximation of the expected final expenditures. Hoping to bring

a large number of students to the competition this year, the team has already reserved 6 hotel rooms

from the block. The team paid $2,200 for these rooms, and thanks to the team’s close proximity to

Huntsville, other travel costs should be negligible. Thanks to the success of the subscale on its first

flight, the team did not have to do any rebuilding, and all the electronic components are reusable.

Factoring this is to the initial estimate of $2,700 for the subscale, the actual cost of the subscale

came out to $2,000. Our educational outreach has spent $1,000 so far, and is estimated to cost

$500 more. The team has spent $3,410.67 for the rocket on the pad, $2,000 for the sub-scale

vehicle, and $2,200 for travel, $1,794 for research and development, and $600 on test flights. The

team plans to spend a total of $1,500 on educational outreach, leaving $2,995.33 for promotional

items and additional costs, based on the $16,500 amount for total funding presented in Table 13.10:

Funding Sources.

Overall, the team is quite happy with how the finances were managed this year. Thanks to the

recovery of all components from all launches this year, no additional funds had to be allocated to

replacing broken or missing materials. The additional funds will be spent on accruing materials

for level 2 certification flights, additional research for future endeavors, and updated facilities after

the competition has been completed.

Below are the budgets for the on-the-pad rocket.

Table 13.7: Vehicle Costs

Vehicle (Full Scale)

Page 200: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

200

Item Cost Per Unit Unit Quantity Total

Pre-preg Carbon

Fiber $118 Per yard 6 $708

Aerotech L1420R $259.99 Per unit 1 $259.99

RMS 75/5120

Motor Case and

Associated

Hardware

$390 Per unit 1 $390

Fiberglass

Coupler $69 Per unit 3 $207

Rail Buttons $3 Per unit 2 $6

Total $1,571

Table 13.8: Recovery Costs

Recovery (Full Scale)

Item Cost Per Unit Unit Quantity Total

Ripstop Nylon $8 Per yard 25 $200

Nylon Thread $8 Per spool 3 $24

Tubular Nylon $1 Per foot 50 $50

Paracord $5 Per roll 1 $5

Telemetrum $200 Per unit 1 $200

Telemega $300 Per unit 1 $300

Page 201: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

201

Jolly Logic $130 Per unit 2 $260

Total $1,039

Rover (Full Scale)

Item Cost Per Unit Unit Quantity Total

1000:1 Micro

Metal Gearmotor

HPCB 12V

$24.95

Per Unit 12 $299.4

2 X 6inch IPX /

U.fl to to RP-

SMA Male Plug

Straight Wifi

Antenna

Extension Cable

Pigtail Cable

1.13mm 15cm

for Wireless 6"

$9.99

Per Unit

1

$9.99

AltIMU-10 v5

Gyro,

Accelerometer,

Compass, and

Altimeter

(LSM6DS33,

LIS3MDL, and

LPS25H Carrier)

$22.95

Per Unit

1

$22.95

Page 202: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

202

Arduino

Wireless SD

shield

$17.49

Per Unit 1

$17.49

Continuous

Rotation Servo -

FeeTech

FS5103R

$11.95

Per Unit 1

$11.95

Digi

International

XBP9B-DPUT-

001

$39.99

Per Unit 2 $79.98

Elegoo UNO

project $35.00 Per Unit 1 $35.00

New Pair Laptop

Wireless Mini

PCI PCI-E WIFI

Bluetooth

Internal

$8.99 Per Unit 1 $ 8.99

Qunqui L298N

Motor Driver $7.00 Per Unit 1 $7.00

Roll of Onyx $189.00 Per Roll 1 $189.00

TRENDnet Low

Loss Reverse

SMA Female to

N-Type Male

Weatherproof

$22.99 Per Unit 1 $22.99

Page 203: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

203

Connector Cable

(8M, 26.2ft.)

TEW-L208

U.FL Mini PCI

to RP-SMA

Pigtail Antenna

WiFi Cable Pack

of 2

$4.99 Per Unit 1 $4.99

Xbee Explorer

dongle $24.95 Per Unit 2 $49.90

Xbee Pro 60 mW

Wire Antenna $37.95 Per Unit 2

$75.90

$800.67

Below are costs associated with research and development. As the altitude control module will be

unable to be on the pad, those costs are factored in here as well. The majority of the R&D expenses

went towards constructing the isogrid airframe to assess its performance compared to pre-preg

carbon fiber rolls, and the construction of a second test rocket as an asset and a new member

development tool.

Research and Development Costs

Cost of Rocket On the Pad $3,410.67

Page 204: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

204

Item Cost Per Unit Unit Quantity Total

Carbon fiber and

resin for open

weave structure.

$284 Per tube 2 $568

Fiber glass sleeve $33 Per tube 2 $66

Pre-preg Carbon

Fiber $118 Per yard 3 $354

Aerotech L1520T $199.99 Per unit 1 $199.99

RMS 75/3840

Motor Case and

Associated

Hardware

$385 Per unit 1 $385

Rail Buttons $3 Per unit 2 $6

Stratologger CF $55 Per unit 2 $110

Roll of Onyx $189.00 Per Roll 1 $189.00

Total $1,689

Altitude Control Module (R&D)

Item Cost Per Unit Unit Quantity Total

Arduino Uno $8 Per unit 1 $22

AndyMark

NeveRest 40 DC

Motor

$8 Per unit 1 $28

Page 205: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

205

Adafruit Motor

Shield v.2.3 $1 Per unit 1 $20

Adafruit

accelerometer $5 Per unit 1 $15

Adafruit Micro

SD card

breakout

$200 Per unit 1 $8

Adafruit

barometric

pressure sensor

$300 Per unit 1 $10

9V Battery $130 Per unit 2 $2

Total $105

Table 13.9: Budget Allocation

Item Cost

Full-Scale $3,410.67

Sub-Scale $2,000

Travel $2,200

Educational Outreach $1,500

Test flights (3) $600

Research and Development $1,794

Page 206: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

206

Promotional Items $1,000

Total $12,504.7

Figure 13.1: Spending Comparison

Section 13.4: Funding Plan

The team has secured funding from the sources presented in Table 13.10: Funding Sources. This

money will cover the cost of the rocket on the pad, the purchase of capital equipment as needed,

the cost of subscale and full-scale test launch motors, programming and materials for our

educational engagement events, travel and housing for the team at the competition in Huntsville,

Alabama, and any other costs associated with designing, building, and launching our competition

rocket. This funding was more than sufficient for the cost of the project, but the team hopes to

accrue additional sponsors to increase the scope of future projects.

Table 13.10: Funding Sources

Budget Breakdown

Full-Scale Sub-Scale Travel

Educational Outreach Test Flights (5) Development

Promotional Items

Page 207: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

207

Source Amount

Alabama Space Consortium $12,000

Dynetics $2,500

Lockheed Martin $2,000

Total Funding $16,500

Section 13.5: Timeline

Two Gannt charts have been created to illustrate the project timeline. They are broken up by

semester, as this separation most closely imitates how the students operate, and it helps to remove

clutter. These can be found in below in Figure 13.2: Fall Timeline and Figure 13.3: Spring

Timeline.

Figure 13.2: Fall Timeline

8/23/17 9/13/17 10/4/17 10/25/17 11/15/17 12/6/17 12/27/17 1/17/18

Conceptual Design

Proposal

Preliminary Design Review

Materials Testing

CFD Testing

Trade Studies

Detailed Design

Critical Design Review

Sub-Scale Development

Payload Development

First Subscale Launch

Junior E-Day EE Event

Detailed Design Review

Page 208: Auburn University Student Launch Project Tiger Launch · 2018. 3. 5. · Title of Project Project Nova Date of FRR March 5th, 2018 Experiment Option 2: Deployable Rover Section 1.2:

208

Figure 13.3: Spring Timeline

As seen in the timelines, the team has completed all research and construction of the full-scale

rocket. The team attended two separate launch dates and recovered the rocket at both.

Unfortunately, the dates of Rocket Week had to be pushed back to accommodate Drake Middle

School; however, the team still plans to go ahead with this outreach event even though it occurs

past the educational engagement deadline. For now, all that remains for the team is to get ready

and excited for Huntsville, and complete the Post-Launch Assessment Review afterwards.

1/10/18 1/31/18 2/21/18 3/14/18 4/4/18 4/25/18

Payload Construction

Full-Scale Development

Flight Readiness Review

Rocket Week EE Event

Auburn E-Day EE Event

Two Day Full-Scale Flight Opportunity

Emergency Full-Scale Flight

Competition Preparation

Huntsville Competition

Post-Launch Assessment Review