‘The Terraces’ at Paddington Welcome Welcome to the second edition of the Brookfield Multiplex ‘The Terraces’ project newsletter. With our project team commenced work on the new Aged Care Facility and Independent Living Units we will be distributing this newsletter on a regular basis to keep you informed on the project’s progress and to provide you with any other important information you may need to know as construction progresses. Construction Update #2 – December 2015 UPCOMING MILESTONES December 2015 – Commence Heritage Building Remedial Works 24 December to 3 January – Christmas Shutdown January 2016 – Commence Piling March 2016 Commence Bulk Excavation May 2016 Tower Crane Installation CONSTRUCTION PROGRESS Brookfield Multiplex commenced work on stage 1 of ‘The Terraces’ on Monday 2 November 2015. Construction activity over the coming weeks comprises early works including site security fencing and hoardings, services diversions, establishment of temporary site sheds, amenities and circulation roads, approved tree removal, scaffolding, hazmat removal, site investigations, demolition of the old operating theatre, remediation, cable bundling and piling.

‘The Terraces’ at Paddington · Building Remedial Works • 24 December to 3 January – Christmas Shutdown • January 2016 – Commence Piling • March 2016 – Commence Bulk

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ‘The Terraces’ at Paddington · Building Remedial Works • 24 December to 3 January – Christmas Shutdown • January 2016 – Commence Piling • March 2016 – Commence Bulk

‘The Terraces’ at Paddington

Welcome Welcome to the second edition of the Brookfield Multiplex ‘The Terraces’ project newsletter. With our project team commenced work on the new Aged Care Facility and Independent Living Units we will be distributing this newsletter on a regular basis to keep you informed on the project’s progress and to provide you with any other important information you may need to know as construction progresses.

Construction Update #2 – December 2015

UPCOMING MILESTONES

• December 2015 – Commence Heritage

Building Remedial Works

• 24 December to 3 January – Christmas

Shutdown

• January 2016 – Commence Piling

• March 2016 – Commence Bulk Excavation

• May 2016 – Tower Crane Installation

CONSTRUCTION PROGRESS

Brookfield Multiplex commenced work on stage 1 of ‘The Terraces’ on Monday 2 November 2015.

Construction activity over the coming weeks comprises early works including site security fencing and hoardings, services diversions, establishment of temporary site sheds, amenities and circulation roads, approved tree removal, scaffolding, hazmat removal, site investigations, demolition of the old operating theatre, remediation, cable bundling and piling.

Page 2: ‘The Terraces’ at Paddington · Building Remedial Works • 24 December to 3 January – Christmas Shutdown • January 2016 – Commence Piling • March 2016 – Commence Bulk

PROJECT STAGING

‘The Terraces’ project will be completed in 2 stages.

Stage 1 – Commenced in November 2015 and includes construction of the new 100 bed aged care facility, 18 new senior’s apartments as well as restoration and adaptive conversion of the Scottish Hospital into 9 senior’s apartments, encompassing the southern and eastern sides of the site. Stage 2 – At the completion of Stage 1 the residents of the existing aged care facility will decant and move to the new building and construction of the remaining 52 senior’s apartments will commence in place of the existing care facility on the western side of the site.

ROAD CLOSURES & DISRUPTIONS

Safe access to the existing Residential Aged Care Facility for pedestrians and vehicles throughout the project is of key importance to the project team and we have carefully considered how we will minimise disruption to current users during the planning of all stages of the works. All the current road access routes to the aged care facility will be maintained. Brookfield Multiplex will continue to provide updates on any future road closures or disruptions to surrounding neighbours through this newsletter and/or letter box drops. Power will be shut down for a few hours to complete the cable bundling works. Affected neighbours will be notified by the authorised subcontractor (Wilken) prior to the power shutdown. Materials handling will be managed within the site including concrete pumping, deliveries and logistics as far as possible.

For enquiries regarding the project please contact:

BM Site Manager Marty McCann T: (02) 9322 2000 E: [email protected] http://www.theterraces.org.au/

PROJECT OVERVIEW

The Brookfield Multiplex ‘The Terraces’ project team is excited to begin construction on the new Aged Care Facility and Independent Living Units. The project will involve the replacement of the existing 88 bed residential aged care facility with a new 100 bed facility including a 23 bed dementia unit; Construction of 70 new seniors independent living units in four buildings;

Construction of 132 car parking spaces; Adaptive conversion of the Scottish Hospital heritage building to contain 9 seniors apartments with the retention and restoration of heritage features such as the terraced gardens; Construction of a loading dock off Stephen Street; Remediation; Creation of space for future community care programs as well as a range of amenities for residents and visitors; and pocket at the corner of Brown and Cooper Streets. On completion, 1300m

2 of land will be

dedicated back to council and the community for footpath widening on Stephen St and expansion of the Dillon St reserve.