11
Helping to keep the lights on, businesses running and communities strong® ATC Project Update May 2011 Mary Carpenter ATC Customer Meeting May 24, 2011

ATC Project Update · Pleasant Prairie to Zion Project • Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

  • Upload
    others

  • View
    28

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ATC Project Update · Pleasant Prairie to Zion Project • Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

Helping to keep the lights on, businesses running and communities strong®

ATC Project UpdateMay 2011

Mary CarpenterATC Customer Meeting

May 24, 2011

Page 2: ATC Project Update · Pleasant Prairie to Zion Project • Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

2

Badger Coulee Project

Page 3: ATC Project Update · Pleasant Prairie to Zion Project • Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

www.atcllc.com

Badger Coulee Project

• Approximately 150 miles from northern Dane County to La Crosse area

• Multiple benefits– Improve reliability in Southwest WI region– Provide economic savings by improving access– Improve access to renewable energy

• Approximate cost: $425 million• In-service date: 2018

3

Page 4: ATC Project Update · Pleasant Prairie to Zion Project • Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

www.atcllc.com

Where Are We Now?

• Open houses in Sept/October 2010 introduced the project as a broad study area– Over 1800 attendees at 8 open houses

• Second round of open houses coming up last two weeks in June will identify a number of potential corridors

• Public outreach will continue through 2012• Application filing anticipated in 2013

4

Page 5: ATC Project Update · Pleasant Prairie to Zion Project • Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

5

Pleasant Prairie to

ZionProject

Page 6: ATC Project Update · Pleasant Prairie to Zion Project • Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

www.atcllc.com

Pleasant Prairie to Zion Project

• Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

• Benefits:– Relieves congestion in the region– Enables most efficient generators

to supply power– Strengthens access and market

• Approximate cost: $21 million - $25 million• In-service date: early 2014

6

Page 7: ATC Project Update · Pleasant Prairie to Zion Project • Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

www.atcllc.com

Where Are We Now?

• Introduced the project in April with two route corridor options

• Identify preferred and alternate routes to be included in regulatory filings in both Wisconsin and Illinois in late 2011

• Public outreach continues

7

Page 8: ATC Project Update · Pleasant Prairie to Zion Project • Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

Western Milwaukee County Electric Reliability Project

8

Page 9: ATC Project Update · Pleasant Prairie to Zion Project • Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

www.atcllc.com

Western Milwaukee County Electric Reliability Project

• New We Energies substation adjacent to the existing substation and plant

• Two 2-mile, 138,000-volt transmissions lines• Need:

– Addresses forecasted overloads on distribution system

– Provides critical service to medical complex– Strengthens access and market

• Approximate cost: $35 million• In-service date: Spring 2015

9

Page 10: ATC Project Update · Pleasant Prairie to Zion Project • Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

www.atcllc.com

Where Are We Now?

• Open houses held Fall 2010 and March 2011

• Finalizing routes to be included in regulatory application to be file in early 2012

• Open house in Fall 2011 to show final routes

10

Page 11: ATC Project Update · Pleasant Prairie to Zion Project • Approximately 5.3 mile, 345,000-volt transmission line from Pleasant Prairie Substation to Zion Energy Center Substation

www.atcllc.com

Questions

11