Click here to load reader
Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
NSF MPS/AST
BPA MeetingApril 23, 2010
Jim UlvestadDivision Director, MPS/AST
2
Outline
Science and Programmatic Accomplishments Facilities Budget Outlook and Astro2010 Issues and Challenges
4/23/2010 BPA-MPS/AST
Programmatic Accomplishments New Division Director, Jim Ulvestad
Deputy D.D. position still unfilled
Program officer staff nearing full allocation Short-handed to meet new facility challenges
ATST Record of Decision NAIC competition solicitation to be released by
end of April New activity: Enhancing Access to Radio
Spectrum34/23/2010 BPA-MPS/AST
Storm Clouds over Titan
Gemini-North adaptive optics image of Titan at 2 microns
First clouds over tropical region in 8 yr
Liquid methane rainstorm?
4
0.8 arcsec
4/23/2010 BPA-MPS/AST
New Rotating Radio Transient
GBT Pulsar Search Collaboratory
High school student Lucas Bolyard found one of ~30 known rotating radio transients Neutron stars with
sporadic pulsation
54/23/2010 BPA-MPS/AST
Image credit: Chuck Kennedy, the White House
Shredded Companions of M31
Guhathakurta et al. surveyed red giants with Subaru, spectroscopic follow-up with Keck II Two coherent tidal
streams to NW of M31
Andromeda growing with dwarf galaxy cannibalism
64/23/2010 BPA-MPS/AST
Image credit: Mikito Tanaka, Tohoku University, and Subaru Observatory
Facilities
Detailed information is provided in backup slides for future reference or questions
4/23/2010 7BPA-MPS/AST
Facilities-1 ALMA
Proposal for 4 yr O&M received New North American Project Manager European antennas behind schedule; aggressive
catch-up efforts
EVLA: New correlator on line, shared risk observing under way
ATST: Record of Decision signed Ramp up to replace current NSO facilities
4/23/2010 8BPA-MPS/AST
Facilities-2 Gemini
UK will withdraw at end of 2012 Budget and partnership reworks under way
NAIC/Arecibo Recompetition solicitation out this month Funding decrease and shift from AST-dominated
NOAO Dark energy survey at CTIO starts in 2012 TSIP ongoing; ReSTAR post-2010 under discussion
4/23/2010 9BPA-MPS/AST
Budget Outlook & Astro2010
4/23/2010 10BPA-MPS/AST
11
FY 2011 AST Budget Request AST Total: $251.8M (2.5% increase over FY 2010 current plan)
Facilities: $141 M (56% of total) Gemini - $19.6 M NAIC - $6.0 M (AST decrease from $8.4, also $3.0M AGS) NOAO - $28.3 M (plus TSIP $5.0M) NSO - $9.5 M NRAO - $44.4 M (down from $49.5 M; end EVLA construction) ALMA Op $23.5 M UROs - $10 M
Research and Education Grants: $111 M (44% of total) Roughly $46M for AAG; $38 M for instrumentation; $25 M for special programs (AAPF, GRF, CAREER, REU,
Cyberinfrastructure, NSF-wide, etc)
4/23/2010 BPA-MPS/AST
AST Community
From 1990 to 2006, number of AAS full members increased ~33%, but AST proposal pressure increased ~150%
124/23/2010 BPA-MPS/AST
AAS members
20061989
6000
4000
2000
Full members
13
Budget Outlook? Administration, congressional support for NSF budget
doubling over 10 years. How will AST fare in this growth?
Must accommodate additional ALMA ramp-up of ~$10-15M Traditional AST strengths do not align well with current
Administration priorities: “Green” energy Climate change Short term economic recovery
FY2011 budget request gives MPS a 4.3% increase relative to FY 2010 current plan, compared to 8.0% NSF-wide AST (2.5%) and PHY (2.8%) were two lowest MPS divisions
4/23/2010 BPA-MPS/AST
Budget Scenarios, FY 2011-2016
Four sample scenarios for FY2016 (FY16 $$) 0% per year increase; flat discretionary spending. FY
2016 budget=$252M 2.5% per year increase; consistent with FY 2011
request, near inflation. FY 2016 budget=$286M 4.5% per year increase; near MPS average, slightly
above inflation. FY 2016=$314M 7.0% per year increase; 10-yr doubling. FY
2016=$353M
144/23/2010 BPA-MPS/AST
Potential Spending Increases Potential (FY16-FY11) differences are quantized
in units of $30M-$40M Predicted facilities increase: $32M 5%/yr individual investigator increase: $31M 10%/yr individual investigator increase: $68M
Possible MREFC operations in FY17-FY18 50%-75% LSST operations: $20-30M 50% GSMT ops (or 25% each for two): ~$40M
Goal: Accommodate up to 5 quanta of increase, totaling $160M
154/23/2010 BPA-MPS/AST
Budget Shortfalls Relative to Desires
Increase Δ (2016-2011) Available Comment0%/yr $0.0 ($160M) 0/5 possible2.5%/yr $34M ($126M) 1/5 possible4.5% /yr $62M ($98M) 2/5 possible7.0%/yr $101M ($59M) 3/5 possible
164/23/2010 BPA-MPS/AST
Sample Choices in Budget Scenarios
17
At 7.0%/yr increase, can start GSMT and LSST ops, and increase grants by 5%/yr, only by substantial divestiture of operating facilities
At 4.5%/yr, can start GSMT and LSST ops only by flat-funding grants and significant facility divestiture
At 2.5%/yr, can start ops for one of GSMT and LSST only by flat-funding grants and divesting facilities
4/23/2010 BPA-MPS/AST
0
50
100
150
200
250
300
350
400
0
50
100
150
200
250
300
350
400
FY2011 FY2016
Mill
ions
AST Budget Scenarios
Midsize projects
Grants
Facilities
Grants +5%
Grants +10%
GSMT ops
LSST ops
0%
3.5%
AST annual growth of 7%
Fac. growth
4/23/2010 18BPA-MPS/AST
19
Primary Issues & Concerns
Long-term funding trends for AST Balance of facilities (“missions”) and grants
Low grants success rate—increasing demand/astronomer Will Astro2010 recommendations be outside funding envelope?
Competitiveness of US in ground-based optical astronomy Federal investment strategy for GSMT and LSST? Balance among large/medium/small telescopes
MREFC investments, and operating funds Rebalancing of Gemini partnership, operational model Near- and mid-term status of Arecibo, VLBA Lack of funding line for mid-size “projects” Long-term facility stewardship (infrastructure maintenance)
4/23/2010 BPA-MPS/AST
Overall AST Status Core priorities supported at healthy levels
ARRA funding is providing benefits to the community and to facility infrastructure
ALMA and EVLA are succeeding ATST is poised for construction
AST is preparing to respond to Astro2010 Strategic planning under way for most likely options
We expect AST to share in a healthy growth of basic research in the U.S. Difficult choices will be needed
204/23/2010 BPA-MPS/AST
Backups Follow
214/23/2010 BPA-MPS/AST
ALMA-1
Major milestone of “closure phase” achieved 3rd ALMA antenna moved to high-altitude
(16,500’) site in November, followed a few days later by phase closure Significant demonstration of hardware and software
Commissioning and Science Verification phase started in Jan 2010
Six (of 66) antennas (one Japanese, five North American) now accepted 23 antennas at various stages of assembly
and test in Chile (12 NA, 2 European, 4 Japanese)
224/23/2010 BPA-MPS/AST
23
ALMA Antenna Assembly Line
4/23/2010 BPA-MPS/AST
ALMA-2 New NA Project Manager—Mark McKinnon replaced Adrian Russell in March Challenges/risks:
Schedule remains very tight Production of receivers on critical path to Early Science (forecast 2011Q3) and
antennas on critical path to completion First European antenna delayed by another 3 months, pushes current forecast of completion
into 2013
Cost-to-complete assessment due to conclude in April; contingency expected to be at acceptable level (~15% of CtC)
Proposal for next 4 years of NSF-funded ALMA operations submitted by AUI/NRAO in March External review mid-2010 NSB action in early 2011
244/23/2010 BPA-MPS/AST
EVLA Old correlator turned off in January; first science with new
correlator occurred on schedule in early March Detected 3.3 GHz CH line at z=0.886, for study of evolution of
fundamental physical constants 27-antenna fringes this month
Currently mix of Open Shared Risk Observing and science commissioning
Five visiting scientists present in Socorro in Resident Shared Risk Observing program
Project contingency remains at 30% of cost to complete; on schedule for completion in 2012 EVLA dedication scheduled for August 12, 2010
Bob Dickman is interim project manager, replacing Mark McKinnon (to ALMA)
254/23/2010 BPA-MPS/AST
26
ATST Environmental Review and Permitting process for site:
Final EIS submitted to EPA on July 24, 2009; published on July 31. Application for building permit (state of Hawaii process) underway;
University of Hawaii leads. More than thirty National Historic Preservation Act Section 106
consultations resulted in fully-executed programmatic agreement detailing the required mitigation.
Record of Decision signed by the NSF Director, Arden Bement on December 3, 2009. This completes the Federal compliance requirements. (But not the mitigation!)
First funding action for $146M (ARRA) awarded on January 15, 2010. MREFC funding for $20M (FY09+10 MREFC) followed by the end of February.
4/23/2010 BPA-MPS/AST
27
ATST
4/23/2010 BPA-MPS/AST
28
The Gemini ObservatoryThe Gemini Observatory consists of twin 8-meter optical/infrared telescopes located on two of the world’s best sites for observing the universe. Together these telescopes can access the entire sky.
“Two telescopes, one observatory.”
Gemini South – Cerro Pachon, Chile
Gemini North – Mauna Kea, HI4/23/2010 BPA-MPS/AST
29
Gemini Gemini was built and is funded by a partnership of 7 countries including the
United States, United Kingdom, Canada, Chile, Australia, Brazil and Argentina. The U.S. is the majority partner (50.4%).
NSF is Executive Agency, AURA is managing entity The UK Science & Technology Facilities Council officially communicated
their decision to withdraw on 22 December 2009. The departure of the UK will result in a ~25% cut in the annual Gemini
M&O and instrumentation budget. Other partners cannot yet commit to funding levels post-2012.
The Board instructed the observatory to prepare plans for a 7-10% cut per annum in 2011-2013 (inclusive). Plans must include consideration of operational model, staffing make-up, etc.
4/23/2010 BPA-MPS/AST
http://www.gemini.edu/index.php?q=node/12�
30
National Astronomy and Ionosphere Center (NAIC)
Recommendation to ramp budget down to $8M by 2010, and to a level not to exceed half of the expected operational cost in years following. Seek non-AST support to maintain operations or closure. NSF Atmospheric and GeospaceSciences (AGS) will be increasing contribution to operations
NSF (AST, AGS) will compete the next cooperative agreement for the management and operation of NAIC. Program solicitation in the NSF clearance process, expected out in
late April; full proposals due 5-6 months following publication. Expected to lead to the award of a single, five-year cooperative
agreement for the management and operation of NAIC for FY 2011-2015.
NASA putting in $2M in FY10 for NEO studies
4/23/2010 BPA-MPS/AST
NOAO Dark Energy Survey from CTIO 4m planned to
start in 2012 100 nights/yr for 5 yr, using wide-field camera built
by DOE
Large proposal letter of intent for “Big Boss” on KPNO 4m Earliest start of observing is in 2014
TSIP nights on private telescopes continuing Post-2010 ReSTAR plan under consideration by
NSF4/23/2010 31BPA-MPS/AST
32
FY2009 Spending(including American Reinvestment and
Recovery Act, ARRA)
4/23/2010 BPA-MPS/AST
NSF MPS/AST�OutlineProgrammatic AccomplishmentsStorm Clouds over TitanNew Rotating Radio TransientShredded Companions of M31FacilitiesFacilities-1Facilities-2Budget Outlook & Astro2010FY 2011 AST Budget Request AST CommunityBudget Outlook? Budget Scenarios, FY 2011-2016Potential Spending IncreasesBudget Shortfalls Relative to DesiresSample Choices in Budget ScenariosSlide Number 18Primary Issues & ConcernsOverall AST StatusBackups FollowALMA-1ALMA Antenna Assembly LineALMA-2EVLAATSTATSTThe Gemini ObservatoryGeminiNational Astronomy and Ionosphere Center (NAIC)NOAOFY2009 Spending�(including American Reinvestment and Recovery Act, ARRA)