Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Alexander Zlobin US Magnet Development Program
Fermi National Accelerator Laboratory
Assembly and First Test of the US-MDP
Nb3Sn Dipole Demonstrator (MDPCT1)
June 27, 2019
Acknowledgment
FNAL: I. Novitski, E. Barzi, J. Carmichael, G. Chlachidze, J. DiMarco, V.V.
Kashikhin, S. Krave, C. Orozco, S. Stoynev, T. Strauss, M. Tartaglia, D. Turrioni,
G. Velev, A. Rusy, S. Jonhson, J. Karambis, J. McQueary, L. Ruiz, E. Garcia
LBNL: S. Caspi, M. Juchno, M. Martchevskii
CERN: D. Schoerling, D. Tommasini
FEAC/UPATRAS: C. Kokkinos
US-MDP: G6 and TAC
This work was supported by Fermi Research Alliance, LLC, under contract No.
DE-AC02-07CH11359 with the U.S. Department of Energy and the US-MDP.
2
Program goals
• Demonstration of 15 T field level
o Record Nb3Sn dipole magnets:
• D20 (LBNL, 1997): Bmax=13.5 T @1.9K, 12.8 T @4.4K
• HD2 (LBNL, 2008): Bmax=13.8 T @4.5K
• FRESCA2 (CERN, 2018): Bmax=14.6 T @1.9K, 13.9 T @4.5K
• Study and optimization of
o magnet quench performance and mechanics
o quench protection
o field quality
• The development and test of the 15 T dipole demonstrator
is a key milestone of the US Magnet Development Program
o coordinated with EuroCirCol program and supported by CERN
3
15 T Dipole design
4
Innovative mechanical
structure (I. Novitski et al.): • Thin StSt coil-yoke spacer
• Vertically split iron laminations
• Aluminum I-clamps
• 12-mm thick StSt skin
• Thick end plates and StSt rods
• Cold mass OD<610 mm
Cable (E. Barzi et al.): • L1-L2: 28 strands, 1 mm RRP150/169
• L3-L4: 40 strands, 0.7 mm RRP108/127
• 0.025 mm x 11 mm SS core
• Insulation: E-glass tape
RRP-108/127
0.7 mm
RRP-150/169
1 mm
26
18
33 32
Coil (V.V. Kashikhin et al.):
• 60-mm aperture, 4-layer graded coil
• Wsc = 68 kg/m/aperture
Magnet conductor limit
5
15.0
15.5
16.0
16.5
17.0
17.5
18.0
2500 2750 3000 3250 3500 3750 4000
Bo
re f
ield
(T
)
Jc(12T, 4.2K) (A/mm2)
4.2 K
1.9 K
10% margin
Jc(12T,4.5K)~2600 A /mm2
Magnet conductor limit for the wire Jc(12T,4.2K)~2.65 kA/mm2
• Bap=15.3T @4.5K
• Bap=16.7T @1.9K
Courtesy V.V. Kashikhin
Magnet mechanical limit
• Magnet design limit is determined by the coil
maximum stress and the pole turn separation
from poles
o independent FNAL and FEAC analysis
Mechanical limit for this design is 15 T!
6
300K
Seqv=133 MPa
Limit 150 MPa
4K
Seqv=176 Mpa
Limit 200 MPa
4K+15T
Seqv=168 Mpa
Limit 200 MPa
Courtesy I. Novitski
TAC recommendations
TAC members:
• Andy Lankford (UCI, Chair), Giorgio Apollinari (Fermilab), Joe Minervini (MIT),
Mark Palmer (BNL), Davide Tommasini (CERN), Akira Yamamoto (KEK & CERN)
Report of the Technical Advisory Committee for the U.S. Magnet
Development Program
February 22, 2019
Recommendations:
• Maintain as the priority for the cos-theta approach using the clamped
mechanical structural design to realize a field of about 14 T, with special
attention to mechanical stress management and control.
• Continue with demonstration of 15 T cos-theta performance only after the
review of the 14 T magnet test results and feedback from the international
workshop.
7
Target coil prestress for the first assembly
8
4K+14T
Seqv=138MPa
300K
Seqv=68MPa
4K+13T
Inner Pole at 13T
Gap=0.003mm
Seqv=117MPa Seqv=143MPa
Inner Pole at 14T
Gap=0.037mm
Conservative pre-stress:
• Smax at all steps <150 MPa
Courtesy I. Novitski
9
Coil winding and
curing using ceramic
binder
Coil lead splicing and
epoxy impregnation
Coil reaction Coil instrumentation
Coil fabrication process Coil fabrication, measurements and
instrumentation
Coil size control,
accuracy ~10 microns
• Coil fabrication, measurement and instrumentation
time ~3 months • IL spare coil was wound, reacted and impregnated
• OL spare coil – the cable and coil parts are available
Witness sample data
10
• HT cycle optimized for the 28-starnd and 40-strand cable
• Witness sample data are close to the target Ic
• Good reproducibility of witness sample data for IL and OL coils
• Magnet short sample limit: 15.16 T @4.5K and 16.84 T @1.9K
Average = 601 A
Average = 583 A Average =
584 A
100
200
300
400
500
600
700
0 2 4 6 8 10 12 14 16
Cu
rre
nt,
A
Test number
Ic @ 15 T
CL1_002
CL1_003
CL1_004
IL coils
Average = 266 A
Average = 256 A
Average= 258 A
100
120
140
160
180
200
220
240
260
280
300
0 2 4 6 8 10 12 14 16 18 20 22 24
Cu
rre
nt,
A
Test number
Ic @ 15 T
CL2_002
CL2_004
CL2_005
OL coils
Courtesy E. Barzi and D. Turrioni
Coil interfaces analysis and optimization
11
HFM-CL1-002 230mm from RE
HFM-CL1-003 230mm from RE
Coil SS 230
L2 OD by 80
mic smaller
L2 OD by
96 mic
smaller HFM-CL2-004 201mm from RE
HFM-CL2-005 218mm from RE
L3 ID by 88
mic smaller
L4 OD by
80 mic
smaller
L4 OD by 187
mic smaller
Coil assembly and preload scheme
12
Yoke-Skin
Rad
interference
d Skin
Clamp-Yoke
interference
Mid-Plane shims
Shell-Yoke Rad
interference
Clamp-Skin Rad
interference
Coil-Coil Rad
interference
Yoke-Yoke
gap taper
Filler-Yoke
interference
Coil assembly, yoking and skinning
13
Magnet transportation and test preparation
14
Instrumentation
• Voltage taps on all coil layers
o one dead and one inactive (both by-passed
by using longer segments)
• Strain Gauges
o skin gauges: OK
o bullet gauges: two (on different bullets) dead
o pole gauges: layer 3 and 4 all gone or
inactive, layer 1 are OK
o coil gauges: one switched off (problems
during ramp up), another off for technical
reasons (could be recovered if needed)
• Quench antennas
o only sensitive to quenches in Layer 1 (didn’t
happen yet)
• Acoustic sensors
o not useful data (very noisy signal)
15
Magnet training
• Only 2 quenches in IL coil 2
• No quenches in coil 3
• OL quenches are equally distributed between coil 4 and coil 5
• Quenches are in both layers 3 and 4 mostly in the LE
• Highest achieved quench current 9758 A at 4.5 K
• Magnet quenching was stopped to avoid coil damage
16
Courtesy S. Stoynev
Magnetic field measurements
17
1.40
1.42
1.44
1.46
1.48
1.50
-0.3 -0.2 -0.1 0 0.1 0.2 0.3
TF
(9kA
) (T
/kA
)
Z (m)
1.460
1.462
1.464
1.466
1.468
1.470
1.472
1.474
1.476
-0.3 -0.2 -0.1 0 0.1 0.2 0.3
TF
(9kA
) (T
/kA
)
Z (m)
130 mm probe
26 mm probe
0
2
4
6
8
10
12
14
16
0 2000 4000 6000 8000 10000
B0 (
T)
Magnet current (A)
130 mm probe
26 mm probe
Courtesy J. DiMarco and T. Strauss
1.40
1.50
1.60
1.70
1.80
1.90
0 2000 4000 6000 8000 10000
TF
(T
/kA
)
Magnet current (A)
Low-order field harmonics
• Good correlation of measurements
with theoretical predictions
18
-60
-40
-20
0
20
40
60
80
0 2000 4000 6000 8000 10000
b3 (
un
its)
Magnet current (A)
-10
-5
0
5
10
15
20
0 2000 4000 6000 8000 10000
b5 (
un
its)
Magnet current (A)
-50
-40
-30
-20
-10
0
10
0 2 4 6 8 10 12 14 16b
n (
10
-4)
Bore field (T)
b3
b5
V.V. Kashikhin and A.V. Zlobin, NAPAC2016
TF analysis
• 2D analysis has been updated based
on the actual yoke material properties
and the final magnet geometry
• 3D calculations are in progress
• Measurements have been verified
with NMR probes (provided by GMW)
19
Courtesy I. Novitski Courtesy V.V. Kashikhin
Courtesy M. Tartaglia
Maximum field achieved
• First quenches above 11 T
• Maximum bore field at 4.5 K
o measured 14.10±0.04 T
o calculated (COMSOL, V.V. Kashikhin) 14.112 T
20
Summary and next steps
• 15 T cos-theta dipole is a challenging and important MDP milestone to
understand limits of Nb3Sn accelerator magnet technology
• integrated international effort with EuroCirCol
• 1-m long 15 T dipole model (MDPCT1) has been developed, fabricated
and first tested at Fermilab (June 2019)
• The goals of the first test have been achieved
o Bmax = 14.10±0.04 T at 1.9 and 4.5 K – record field at 4.5 K for accelerator
magnets!
o graded 4-layer coil design, innovative support structure and magnet
fabricated procedure tested
• Next steps
o Magnet re-assembly
• coil pre-load increase to the level sufficient to achieve the goal of 15 T
• improve instrumentation
o Magnet second test in the fall of 2019
21