2
Unit 12 Stirling Park, Laker Road, Rochester, Kent ME1 3QR t 01634 668090 e [email protected] www.tgc.uk.com A DIVISION OF TGC INTERNATIONAL LTD case study CS-078-TGC-25724-R0 ©TGC International Ltd 2015 The Project The Generator Company were asked to supply, install and commission a generator to back up the stadium flood lights of a football club based in Hertfordshire. With recent promotion to the Premier League and directive from the Football Association, the football club needed back up power in the event of a power cut during a televised game. Premier League Football Club based in Hertfordshire SUPPLY & INSTALL OF 275kVA GENERATOR

ASE STUY SUPPLY & INSTALL OF 275kVA GENERATOR€¦ · ASE STUY CS-078-TGC-25724-R0 ©TGC International Ltd 2015 ... using the site lighting to ensure all systems performed as required

  • Upload
    buibao

  • View
    216

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ASE STUY SUPPLY & INSTALL OF 275kVA GENERATOR€¦ · ASE STUY CS-078-TGC-25724-R0 ©TGC International Ltd 2015 ... using the site lighting to ensure all systems performed as required

Unit 12 Stirling Park, Laker Road, Rochester, KentME1 3QR

t 01634 668090e [email protected] A DIVISION OF TGC INTERNATIONAL LTD

case study

CS-078-TGC-25724-R0©TGC International Ltd 2015

The Project

The Generator Company were asked to supply, install and commission a generator to back up the stadium flood lights of a football club based in Hertfordshire. With recent promotion to the Premier League and directive from the Football Association, the football club needed back up power in the event of a power cut during a televised game.

Premier League Football Club based in

Hertfordshire

SUPPLY & INSTALL OF 275kVA GENERATOR

Page 2: ASE STUY SUPPLY & INSTALL OF 275kVA GENERATOR€¦ · ASE STUY CS-078-TGC-25724-R0 ©TGC International Ltd 2015 ... using the site lighting to ensure all systems performed as required

Unit 12 Stirling Park, Laker Road, Rochester, KentME1 3QR

t 01634 668090e [email protected] A DIVISION OF TGC INTERNATIONAL LTD

case study

CS-078-TGC-25724-R0©TGC International Ltd 2015

The customer, F1 Sound Co Ltd based in Kent, who provide various services to the football club contacted The Generator Company after seeing one of our fleet of service vehicles out on the road.

It is a requirement of the Football Association for all premier league stadiums to have floodlights to allow games to be scheduled outside daylight hours. To comply with Premier League guidelines, the club were asked to install a standby generator to support LED floodlight upgrade.

On completion of a site inspection, it was discussed that the best way forward would be to provide a 275kVA Cummins C275D5 standby generator together with an ATS panel and lighting control board. Our scope of works to include full electrical installation and commissioning using the site lighting.

On commencement of the project, we delivered, offloaded with the use of our own hiab and positioned the generator on a prepared base. On completion the ATS panel and a lighting board were installed followed by connections of all cable from the generator to the ATS and lighting board.

On conclusion of the installation works, the generator set and associated equipment were commissioned using the site lighting to ensure all systems performed as required in a mains failure situation.