Applying the Espoo Convention on NPP Cernavoda units 3-4 Constantin Pulbere, legal adviser, Ministry of Environment and Sustainable Development, Romania

Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

Applying the Espoo Convention on NPP Cernavoda units 3-4

Constantin Pulbere, legal adviser, Ministry of Environment and Sustainable Development, Romania

Page 2: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

2

Law 22/2001-Romania became party to the Espoo Convention by ratifying the convention

Subsequent legislation for implementing the Convention

Romanian Ministry of Environment and Sustainable Development

Applying the Espoo Convention on NPP Cernavoda units 3-4

Page 3: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

Cernavoda NPP: site S-E Romania in Constanta county

located at 160 km east from Bucharest and about 2 km south-east from the Cernavoda town boundaryabout 1,5 km north-east from the first lock on the Danube-Black Sea Canal (DBSC). plant uses Canadian technology CANDU type 700 MWe each reactor.

Screening: Appendix 1 pt.2 Espoo ConventionProcedure started: 09.08.2006

Romanian Ministry of Environment and Sustainable Development

3

Applying the Espoo Convention on NPP Cernavoda units 3-4

Page 4: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

Countries notified: Austria, Bulgaria Hungary, Moldavia, Ukraine.

4 Romanian Ministry of Environment and Sustainable Development

Applying the Espoo Convention on NPP Cernavoda units 3-4

Page 5: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

Cernavoda view

5 Romanian Ministry of Environment and Sustainable Development

Page 6: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

6

Notification

Information on NPP: scope, scale, description, rationale for proposed activity;Information on the spatial and temporal boundaries of NPP: description of the location, rationale for location, start and duration of construction and operation;Information on expected environmental impacts and proposed mitigation measures: scope of assessment, potential sources of releases to water/of emission to air/soil pollution etc. Nature and timing of the possible decision: December 2007 for the final EIA decision

Applying the Espoo Convention on NPP Cernavoda units 3-4

Romanian Ministry of Environment and Sustainable Development

Page 7: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

7

Notification

Romanian legislation, including public participation procedures (public debate with 30 working days availability to the EIA Report)

An indication of a reasonable time within which a response is required: 4 weeks

Applying the Espoo Convention on NPP Cernavoda units 3-4

Romanian Ministry of Environment and Sustainable Development

Page 8: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

In accordance with the Romanian law and taking into account comments received the project owner elaborated the EIA documentation

EIA documentation submitted to the Romanian environmental authorities

the EIA documentation (English and Romanian language) posted on MESD and project owner websites to be consulted by the public

EIA documentation also available for consultations at Ministry of Environment headquarters.

8 Romanian Ministry of Environment and Sustainable Development

Applying the Espoo Convention on NPP Cernavoda units 3-4

Page 9: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

Romanian Ministry of Environment and Sustainable Development

9

EIA documentation transmitted (both Romanian and English languages) to the Parties Affected to provide it to national authorities and their own public

Reasonable time to answer: 8 weeks

Applying the Espoo Convention on NPP Cernavoda units 3-4

Page 10: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

10 Romanian Ministry of Environment and Sustainable Development

Applying the Espoo Convention on NPP Cernavoda units 3-4

Project owner Project owner submits EIA submits EIA

documentationdocumentation

Ministry of Ministry of EnvironmentEnvironment

Ministry of Ministry of Foreign AffairesForeign Affaires

Romania public Romania public and public and public authoritiesauthorities

Affected Affected partiesparties

Public and Public and national national

authorities of authorities of Affected PartiesAffected Parties

Page 11: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

11

In Romania:

Public debates held in 3 cities:

CernavodaConstantaBucucharest

Romanian Ministry of Environment and Sustainable Development

Applying the Espoo Convention on NPP Cernavoda units 3-4

Page 12: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

In Bulgaria:

EIA Documentation discussed in 2 public debates in Silistra and Dobrich

Project owner and Romanian Ministry of Environment present at Bulgarian public debates

Public answers: - in situ- gathered in special form

12 Romanian Ministry of Environment and Sustainable Development

Applying the Espoo Convention on NPP Cernavoda units 3-4

Page 13: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

Austria requested consultation based on art.5 of Espoo

Convention and art.7 of the EIA Directive

Day1: visit at Nuclearelectrica:training centre, main control room of unit 2, dosimetry laboratory, reactor building unit 3, environmental control laboratory, on-site emergency centre.

Day 2: consultations at MESD’s headquartersTechnical issues: discussion on items previously received from Austria: reactor core, seismic hazard etc. Procedural issues: Agreement on the timelimit for the final feedback

13 Romanian Ministry of Environment and Sustainable Development

Applying the Espoo Convention on NPP Cernavoda units 3-4

Page 14: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

14 Romanian Ministry of Environment and Sustainable Development

Consultations at MESD headquarters

Page 15: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

Final decision has not been yet taken;

Final decision will take into account Parties Affected comments and the outcome of the consultations

Will be provided to Parties Affected along with the reasons and considerations on which it was based.

15 Romanian Ministry of Environment and Sustainable Development

Applying the Espoo Convention on NPP Cernavoda units 3-4

Page 16: Applying the Espoo Convention on NPP Cernavoda units 3-4 · `Cernavoda NPP: site S-E Romania in Constanta county `located at 160 km east from Bucharest and `about 2 km south-east

16

Thank you for your attention

Contact details:Constantin Pulbere

[email protected]+4 021 316 61 54

Romanian Ministry of Environment and Sustainable Development