APPEARANCE OF THE TANK BEFORE THE COATING
INSTALLATION OF THE SCAFFOLDINGS
INSTALLATION OF COMPRESSOR & PIPPING THE BLASTING POT
PREPARATION,TEST BLASTING FOR PROFILE & CHECK FOR PRESSENCE OF OIL
MATERIALS TO BE USED FOR THE INTERNAL COATING
CHECKING THE SURFACE TO A WHITE METAL FINISH
CONDUCT CHLORIDE TEST FOR SALT CONTAMINATION
TEST RESULT 1PPM (3 PPM IS THE MAXIMUM VALUE)
APPLICATION OF ENECON PUTTY TO THE JOINT & DEEPLY PITTED AREA
CONDUCT WET FILM THICKNESS DURING APPLICATION
1ST COURSE COATED WITH ENECON CHEMCLAD SC
2ND COURSE COATED WITH ENECON CHEMCLAD SC
APPLICATION FROM 3RD COURSE TO THE TOP AREA, 1ST PART
APPLICATION FROM 3RD COURSE TO THE TOP AREA, 2ND PART
APPLICATION FROM 3RD COURSE TO THE TOP AREA, 5TH PART
APPLICATION FROM 3RD COURSE TO THE TOP AREA, 3RD PART
APPLICATION FROM 3RD COURSE TO THE TOP AREA, 4TH PART
FINISHING OF THE TOP PART OF THE & THE ENTIRE 6 COURSE
BLASTING & PAINTING OF THE BOTTOM PART OF THE TANK
AREA BEING REPAIRED A 12X16 HOLE WAS MADE & DAMAGED THE COATING
FINAL APPEARANCE OF THE AREA AFTER THE REPAIR WITH ENECON PUTTY & OVERCOAT WITH CHEMCLAD SC
TANK 2 BEFORE ENECON CHEMCLAD SC APPLICATION
TANK 2 AFTER ENECON CHEMCLAD SC APPLICATION