Upload
erika-hilda-simon
View
215
Download
0
Tags:
Embed Size (px)
Citation preview
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 11
October 20 , 2007October 20 , 2007
LUCID* - LUCID* - A Cherenkov tubes A Cherenkov tubes based detector for monitoring based detector for monitoring
the ATLAS luminositythe ATLAS luminosity
Antonio Zoccoli – University & INFN - BolognaAntonio Zoccoli – University & INFN - Bologna For the LUCID collaboration (Alberta, Bologna, For the LUCID collaboration (Alberta, Bologna,
CERN, LUND)CERN, LUND)
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 22
October 20 , 2007October 20 , 2007
Detectors requirements Detectors requirements Test beam results & Rad. Hard. Test beam results & Rad. Hard.
MeasurementsMeasurements Detector design and installation Detector design and installation
strategystrategy Present status of the detector Present status of the detector ConclusionsConclusions
OutlineOutline
• Outline• Forward
ATLAS• LUCID the
basic concept
• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID Design • LUCID under
construction• LUCID
assembled• The
alignment system
• LUCID: the electronics
• Installation• Conclusion
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 33
October 20 , 2007October 20 , 2007
Forward detectors in AtlasForward detectors in Atlas
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 44
October 20 , 2007October 20 , 2007
LUCID is an array of Cerenkov tubes (length ~1.5m) LUCID is an array of Cerenkov tubes (length ~1.5m) made of polished aluminium using C4F10 gas as a made of polished aluminium using C4F10 gas as a radiatorradiator
The Cerenkov threshold (10 MeV for e’s 2.8 GeV for The Cerenkov threshold (10 MeV for e’s 2.8 GeV for ’s) + the pointing of the tube to the IP suppresses ’s) + the pointing of the tube to the IP suppresses background from non-pointing soft secondaries and background from non-pointing soft secondaries and scattersscatters
It is possible to count multiple particles traversing the It is possible to count multiple particles traversing the length of the same tube (no Landau Fluctuations)length of the same tube (no Landau Fluctuations)
A good time resolution ( ~2ns) allows individual beam A good time resolution ( ~2ns) allows individual beam crossings to be studiedcrossings to be studied
This technique was first used at CDF (the CLC)This technique was first used at CDF (the CLC)
LUCID – The Basic ConceptLUCID – The Basic Concept
The Cerenkov light is The Cerenkov light is produced at ~3produced at ~3oo making ~ 3 reflectionsmaking ~ 3 reflectionsas it passes down the as it passes down the length of the tube length of the tube
• Forward ATLAS
• LUCID the basic concept
• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID readout • LUCID under
construction• LUCID
assembled• The alignment
system• LUCID: the
electronics• Installation• Conclusion
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 55
October 20 , 2007October 20 , 2007
Front face of each end LUCID is ~17m from the IPPHASE 1 6.0 > |η| > 5.6
The Location of LUCID The Location of LUCID • Forward
ATLAS• LUCID the
basic concept• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID design • LUCID under
construction• LUCID
assembled• The alignment
system• LUCID: the
electronics• Installation• Conclusion
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 66
October 20 , 2007October 20 , 2007
LUCID has to count the number of particles hitting the LUCID has to count the number of particles hitting the detector that are consistent with originating from the IPdetector that are consistent with originating from the IP
There is a linear relationship between the number of There is a linear relationship between the number of particles detected and the luminosityparticles detected and the luminosity
The detector has to cope to high radiation levels The detector has to cope to high radiation levels All All parts (especially PMTs) must be rad. hard.parts (especially PMTs) must be rad. hard.
Two readout schemes investigated and studied in beam Two readout schemes investigated and studied in beam tests:tests:
PMT directly coupled to the Cherenkov tubes (PMT directly coupled to the Cherenkov tubes (rad rad hard tests neededhard tests needed))
and fused-silica fibre readout to remote MaPMTs (and fused-silica fibre readout to remote MaPMTs (No No rad hard problemsrad hard problems))
LUCID – The readoutLUCID – The readout• Forward
ATLAS• LUCID the
basic concept• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID design • LUCID under
construction• LUCID
assembled• The alignment
system• LUCID: the
electronics• Installation• Conclusion
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 77
October 20 , 2007October 20 , 2007
Test Beam Studies - 1Test Beam Studies - 1
Test beam at DESY Test beam at DESY (electron beam) :(electron beam) :– Nov. `05, Nov. `05,
– Aug. `06,Aug. `06,
– Dec. `06.Dec. `06.
μμ = < = <# of # of photoelectrons> from photoelectrons> from spectra fitspectra fitμ
nn n
n 0
eS(x) μ G (Q , )
n!
Gas Vessel
Tubes read outS1 S3
S2
T1 T2
BEAM PMTPMT
MAPMT
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 88
October 20 , 2007October 20 , 2007
Test Beam Studies – PMT readoutTest Beam Studies – PMT readout #Photoelectrons #Photoelectrons
using PMT using PMT readout:readout:– ~70 pe’s/tube~70 pe’s/tube from from
gas at 1 bargas at 1 bar
– ~50~50 pe’s/tubepe’s/tube from from PMT windowPMT window
– ~120 pe’s/tube~120 pe’s/tube TOTALTOTAL
P1
P0P2
Npe- (P1)~70
Npe- (P2)~120
Pressure scan: Pressure scan: #Photoelectrons#Photoelectrons vs gas pressurevs gas pressure
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 99
October 20 , 2007October 20 , 2007
#Photoelectrons #Photoelectrons using fibre using fibre readout via readout via Winston cone to Winston cone to remote MaPMT, remote MaPMT, summing up summing up single fibre yieldssingle fibre yields– ~12-15 pe’s/tube ~12-15 pe’s/tube
at 1.25 barat 1.25 bar
Test Beam Studies – fibre readoutTest Beam Studies – fibre readout
Central fibres Lateral fibres
Middle fibres
• Forward ATLAS
• LUCID the basic concept
• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID design • LUCID under
construction• LUCID
assembled• The alignment
system• LUCID: the
electronics• Installation• Conclusion
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 1010
October 20 , 2007October 20 , 2007
Rad hard tests on PMT Rad hard tests on PMT HAMAMATSU R762:HAMAMATSU R762:– gammagamma: : 6060Co source, ECo source, EMM=1.22=1.22 MeV MeV
dose: (20dose: (20±1)MRad ±1)MRad 3 year LUCID phase 2 3 year LUCID phase 2– neutronneutron: ENEA-Casaccia reactor <E>: ENEA-Casaccia reactor <E>~100 KeV~100 KeV
dose: dose: ~5x10~5x103434 ncm ncm-2-2 1 year LUCID phase 2 1 year LUCID phase 2
LUCID: PMT rad. hard. testsLUCID: PMT rad. hard. tests
• Forward ATLAS
• LUCID the basic concept
• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID design • LUCID under
construction• LUCID
assembled• The alignment
system• LUCID: the
electronics• Installation• Conclusion No relevant effects for LUCID phase 1 No relevant effects for LUCID phase 1
(10 times less than phase 2)(10 times less than phase 2)
gammagamma
neutronneutron
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 1111
October 20 , 2007October 20 , 2007
PHASE 1 - Low lumi L < ~ 1033 cm-2 s-1 ends 2009Dominating sys Final goal ~4-5% + pp (CDF:~4% )
PHASE 2 – High lumi L ~ 1034 cm-2 s-1 after 2009Final goal ~ 2-3% +pp
New project approved. Two different detectors: New project approved. Two different detectors: phase 1 (low lumi) + phase 2 (high lumi)phase 1 (low lumi) + phase 2 (high lumi)
Main goal: end of construction in July 2007Main goal: end of construction in July 2007
LUCID review: installation strategyLUCID review: installation strategy
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 1212
October 20 , 2007October 20 , 2007
The Design Approved in JanuaryThe Design Approved in January
Fibre RO (4)
PMT RO(16)
Outer layer ~115 mm rad.Inner layer ~96 mm rad.
LUCID approved for installation in ATLAS in January 2007LUCID approved for installation in ATLAS in January 2007 LUCID construction completed in July 2007LUCID construction completed in July 2007
Mass = 22 KgVolume = 54 litres
20 Cerenkov Tubes each end
• Forward ATLAS
• LUCID the basic concept
• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID design • LUCID under
construction• LUCID
assembled• The alignment
system• LUCID: the
electronics• Installation• Conclusion
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 1313
October 20 , 2007October 20 , 2007
The main elements of LUCID produced during the The main elements of LUCID produced during the construction phase of LUCIDconstruction phase of LUCID
LUCID Under ConstructionLUCID Under Construction
Gas vessel Gas vessel componentscomponents
LUCID gas vessel under LUCID gas vessel under Pressure testPressure test
PMT Test FacilityPMT Test Facility
PMT holdersPMT holders Cerenkov tube Cerenkov tube manufacturemanufacture
Fibre-optic cable Fibre-optic cable manufacturemanufacture
IINN
BBOOLLOOGGNNAA
IINN
AALLBBEERRTTAA
• Forward ATLAS
• LUCID the basic concept
• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID design • LUCID under
construction• LUCID
assembled• The alignment
system• LUCID: the
electronics• Installation• Conclusion
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 1414
October 20 , 2007October 20 , 2007
LUCID was fully assembled at CERN by an Alberta-LUCID was fully assembled at CERN by an Alberta-Bologna-CERN-Lund team in July 2007Bologna-CERN-Lund team in July 2007
Test with the LUCID LED pulser system showed all Test with the LUCID LED pulser system showed all channels were functioning correctly.channels were functioning correctly.
LUCID Assembled LUCID Assembled • Forward
ATLAS• LUCID the
basic concept• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID design • LUCID under
construction• LUCID
assembled• The alignment
system• LUCID: the
electronics• Installation• Conclusion
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 1515
October 20 , 2007October 20 , 2007
Alignment to a fraction of a degree to the beam axis requiredAlignment to a fraction of a degree to the beam axis required Test mounting of alignment system on 3Test mounting of alignment system on 3rdrd gas vessel in 10/07 gas vessel in 10/07
The Alignment SystemThe Alignment SystemRear alignment system Front alignment system
Mods to the VJ coneFor LUCID support& alignmentsystem
Alignment system piecesProduced at Alberta
• Forward ATLAS
• LUCID the basic concept
• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID design • LUCID under
construction• LUCID
assembled• The alignment
system• LUCID: the
electronics• Installation• Conclusion
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 1616
October 20 , 2007October 20 , 2007
The PMT readout is produced tested and installed (upper The PMT readout is produced tested and installed (upper photos)photos)
The MaPMT readout (lower photos) is in a advanced state of The MaPMT readout (lower photos) is in a advanced state of readiness. Final commissioning will start as soon as the MAROC3 readiness. Final commissioning will start as soon as the MAROC3 chip is available next springchip is available next spring
The main LUCID processor VME card (LUMAT) (trigger, data The main LUCID processor VME card (LUMAT) (trigger, data output, on-line lumi measure) is in an advanced state of design output, on-line lumi measure) is in an advanced state of design – estimated to be ready next spring– estimated to be ready next spring
LUCID ElectronicsLUCID Electronics
• Forward ATLAS
• LUCID the basic concept
• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID design • LUCID under
construction• LUCID
assembled• The alignment
system• LUCID: the
electronics• Installation• Conclusion
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 1717
October 20 , 2007October 20 , 2007
So far the move towards So far the move towards installation is on schedule installation is on schedule
After the final beam test, presently ongoing @ CERN, After the final beam test, presently ongoing @ CERN, we plan to move the LUCID modules into the cavern we plan to move the LUCID modules into the cavern and test connect them to the available services and test connect them to the available services
The final installation of LUCID in the ATLAS forward The final installation of LUCID in the ATLAS forward region is slated for the end of February 2008region is slated for the end of February 2008
Towards the Installation of LUCID Towards the Installation of LUCID
Connect Connect to theseto these
resourcesresources
• Forward ATLAS
• LUCID the basic concept
• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID design • LUCID under
construction• LUCID
assembled• The alignment
system• LUCID: the
electronics• Installation• Conclusion
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 1818
October 20 , 2007October 20 , 2007
The LUCID design approved at the ATLAS review in January The LUCID design approved at the ATLAS review in January 2007 has been successfully realized2007 has been successfully realized
LUCID was assembled in July 2007 according to schedule LUCID was assembled in July 2007 according to schedule The gas system, the cooling vessel and the alignment The gas system, the cooling vessel and the alignment
system have been designed and are being assembledsystem have been designed and are being assembled The electronics is in an advanced state of readiness and is The electronics is in an advanced state of readiness and is
envisaged to be completely available by Spring 2008envisaged to be completely available by Spring 2008 Extensive beam tests have been performed successfully at Extensive beam tests have been performed successfully at
DESY. A final test beam at CERN is ongoing, that will DESY. A final test beam at CERN is ongoing, that will enable us to calibrate the LUCID detector(s)enable us to calibrate the LUCID detector(s)
Rad. Hard. Studies have been carried out on the PMT to be Rad. Hard. Studies have been carried out on the PMT to be installed installed
The software necessary for the LUCID detector integration The software necessary for the LUCID detector integration in the general MC and for the luminosity monitor is moving in the general MC and for the luminosity monitor is moving on schedule on schedule
Remaining – important - detector studies (systematic Remaining – important - detector studies (systematic effects etc.) are in an advanced phaseeffects etc.) are in an advanced phase
We are progressing on schedule and will be ready for We are progressing on schedule and will be ready for installation by December 2007.installation by December 2007.
Conclusion Conclusion • Forward
ATLAS• LUCID the
basic concept• Location • LUCID the
readout• Test beam
studies• LUCID: rad.
hard. tests• Installation
strategy• LUCID design • LUCID under
construction• LUCID
assembled• The alignment
system• LUCID: the
electronics• Installation• Conclusion
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 1919
October 20 , 2007October 20 , 2007
EXTRA SLIDESEXTRA SLIDES
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 2020
October 20 , 2007October 20 , 2007
• Use a relatively well Use a relatively well known, copious, known, copious, process:process:
•Inclusive inelastic pp cross-Inclusive inelastic pp cross-sectionsection
• large acceptance at small angleslarge acceptance at small angles
• µ = µ = avg. # of interactions/b.cavg. # of interactions/b.c..
• f = f = frequency of bunch crossingsfrequency of bunch crossings
• inin = = tot inelastic cross-sectiontot inelastic cross-section
• L = L = inst. luminosityinst. luminosity
• Use a good estimatorUse a good estimator•Measure the fraction of crossings with pp interactions
•Use: prob. of no int.
•Direct counting # of pp interactions
•Counting particles•Counting hits
• Cross-calibrateCross-calibrate•Machine information•Roman Pots •Rarer, clean, better understood physic processes
• Use dedicated detector:Use dedicated detector:
fBC in L
˜ fBC in detector L
Strategies for lumi measurementStrategies for lumi measurement
( )P e
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 2121
October 20 , 2007October 20 , 2007 [ATLAS-LUM-PUB-2006-001]
Measured by LUCID
Measured by LUCID (at low luminosity <1)
Given by calibration method
LUCID with 200 tubes(No Secondaries)
Calibration Constant: A = pp x inel
Run LUCID in parallel with calibration measurement
M
Advantage of “Parallel” Calibration
Measured:Not easy at high precision, e.g. CDF vs E811 discrepancy
Calculated:Acceptance shown at the Tevatron to be difficult to calculate in forward region
Calculated and measured tot used for consistency cross checks
LUCID calibration strategyLUCID calibration strategy
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 2222
October 20 , 2007October 20 , 2007
StartStart
up up
QEDQED: small : small QEDQED
– pp pp (p+ (p+*)+(p+*)+(p+*)*)p+(p+()+p)+p Low rate (<< 1 Hz) still at L=10Low rate (<< 1 Hz) still at L=103434 cm cm-2-2 s s-1-1
Process calculated with Process calculated with 1% accuracy 1% accuracy
EWEW: W/Z : W/Z leptons leptons – Theoretically well understood processes (calculated till NNLO)Theoretically well understood processes (calculated till NNLO)
– High rate: High rate: 6Hz for Z6Hz for Z, , 60Hz for W60Hz for Wνν at L=10 at L=103434 cm cm-2-2 s s-1-1
Online monitor at high luminosity Online monitor at high luminosity LL//LL))systsyst ~ 4-6% ~ 4-6% **; ; LL //L L ))statstat ~ 1-5% ~ 1-5% **
QCDQCD: : tottot ~ 100 mb ~ 100 mb
– Roman Pots at dedicated luminosity (L≈10Roman Pots at dedicated luminosity (L≈102727 cm cm-2-2 s s-1-1) and optic) and optic Absolute Luminosity Absolute Luminosity LL
– Counting of the number of bunch crossings with/without Counting of the number of bunch crossings with/without interactioninteraction
Online monitor Online monitor Relative Luminosity Relative Luminosity L L
No Monitor Online
* Small statistical error (<1%) homogeneous samples with at least 10K-100K ev
Physics processesPhysics processes
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 2323
October 20 , 2007October 20 , 2007
Cherenkov photons from gas + PMT window
Cherenkov photons from PMT quartz window
1 interaction per event
• Sensitive to IP-pointing tracks above threshold
• Much shorter paths for non pointing secondaries
• The response of the detector is linear with both PMT and fiber read-out
LUCID performancesLUCID performances
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 2424
October 20 , 2007October 20 , 2007
During beam pipe bake out LUCID could reach ~250 During beam pipe bake out LUCID could reach ~250 ooC C A cooling system must be employed to keep the A cooling system must be employed to keep the
temperature of LUCID well below 50temperature of LUCID well below 50ooC (PMT specs.)C (PMT specs.) This is achieved using a water cooled aluminium cylinder This is achieved using a water cooled aluminium cylinder
using 6 copper cooling loops (20 litres/hr in each loop)using 6 copper cooling loops (20 litres/hr in each loop) FEA shows that the temperature of the inner radius will be FEA shows that the temperature of the inner radius will be
maintained at a temperature of ~20maintained at a temperature of ~20ooC using this jacket C using this jacket (assuming perfect connection between cooling pipe and (assuming perfect connection between cooling pipe and AlAl))
The cooling system in currently under fabrication in Alberta The cooling system in currently under fabrication in Alberta
The LUCID Cooling SystemThe LUCID Cooling System
The cooling cylinder deployed The cooling cylinder deployed Between the beam pipe and LUCIDBetween the beam pipe and LUCID
Cooling system Cooling system under fabricationunder fabricationat Albertaat Alberta
(Heat dissipated during beam Pipe bakeout is 250 W/m)
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 2525
October 20 , 2007October 20 , 2007
No continuous flow of CNo continuous flow of C44FF1010
Pressure maintained (at 1.25/1.5 Bar by regulator) Pressure maintained (at 1.25/1.5 Bar by regulator) leak rate observed less than 10 millibar/dayleak rate observed less than 10 millibar/day
Front PanelSchematic of Gas System
The LUCID Gas SystemThe LUCID Gas System
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 2626
October 20 , 2007October 20 , 2007
Test beam venue - SPS H8 in PrevessinTest beam venue - SPS H8 in Prevessin Test Beam period 18Test Beam period 18thth 28 28thth of October 2007 of October 2007 Final assembly of additional components of LUCID Final assembly of additional components of LUCID
for beam test in b154 ( mechanical cage) from the for beam test in b154 ( mechanical cage) from the 1010thth to the 15 to the 15thth of October of October
Next – Test-Beam in Oct. 2007 (1)Next – Test-Beam in Oct. 2007 (1)
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 2727
October 20 , 2007October 20 , 2007
Next – Test-Beam in Oct. 2007 (2)Next – Test-Beam in Oct. 2007 (2)
Main goal: calibrate 40 tubes (PMT+MAMPT-with Main goal: calibrate 40 tubes (PMT+MAMPT-with DESY 12/2006 system-) i.e. # p.e./trackDESY 12/2006 system-) i.e. # p.e./track
Determine optimum gas pressure for LUCID runningDetermine optimum gas pressure for LUCID running
The moveable tableThe area in which theThe area in which the table will be placedtable will be placed
The beam dump region
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 2828
October 20 , 2007October 20 , 2007
Integration in the ATLAS MC Integration in the ATLAS MC THE
GEO
MODEL
Our stand-alone Monte Carlo predicts satisfactory LUCID performance.
We have started the process of integration of the LUCID into the ATLAS MC
Our aim is to be ready for the Full Dress Rehearsal by the end of 2007
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 2929
October 20 , 2007October 20 , 2007
The LUCID Data Flow The LUCID Data Flow
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 3030
October 20 , 2007October 20 , 2007
Radiation Hardness A Hamamatsu R762 photomultiplier has been irradiated with a 60Co
source and the dark current and gain has been studied.
PMT 2: No irradiation
PMT 1: 20 MRad in 18 hours
Equivalent to 15 years at 2x1033 cm-2s-1
Equivalent to 3 years at 1x1034 cm-2s-1 The increase of the dark current is not a concern for the PMT lifetime !
V. Hedberg ATLAS Overview Week - 20.02.2007 18
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 3131
October 20 , 2007October 20 , 2007
Radiation Hardness
Before irradiation ! No irradiation !
After 20 MRad No irradiation !
V. Hedberg ATLAS Overview Week - 20.02.2007 19
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 3232
October 20 , 2007October 20 , 2007
The readout schemeThe readout scheme
PMT 1
PMT 16
MAMPTFED
MAROC
4 diff. TX lines
TRIGGER
CARD
100 m
100 m
100 m
FED USA 15
HV, LV, SLOW CONTROL
ROS
TTCRQ
To LVL1
VME IFOnLineLUMI
3
RX
BOARDS
3
CFD
BOARDS
20
20
VMEQDC/TDC
•INTEGRATED ON TDAQ •ONLINE SCALERS •DEBUGGING VIA VME•MAROC DIGITAL PART NOT AVAILABLE
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 3333
October 20 , 2007October 20 , 2007
Scalers in the Trigger Card (Firmware) Scalers in the Trigger Card (Firmware)
for Online Luminosityfor Online Luminosity
LUCID A LUCID C
II. Particle Counting
I. Collision/Zero Counting
16 tubes
1
2
3
4
4 x 3564 x 32bit ~ 60kB (1-4 x BCIDs x Scaler depth) L
R
1
2 (If LUCID A-C Coincidence)
34 (If LUCID A-C Coincidence)
4 x 3564 x 32bit ~ 60kB
III. Total Orbit Counter • For normalization (Average)
• All scalers start/stop are synchronized with the Orbit signal to scale over the same interval at a BC precision• Scalers are incremented on L1A (for dead time correction) • Scalers read-out by VME and sent to DCS (~ 120 kB for each Luminosity Block –few min-) for processing, to be published at any time
32bit
Antonio ZoccoliAntonio Zoccoli RICH 2007 – TriesteRICH 2007 – Trieste 3434
October 20 , 2007October 20 , 2007
The important steps in The important steps in the LUCID assembly the LUCID assembly sequence followed in sequence followed in July 2007July 2007
The Assembly of LUCID The Assembly of LUCID • LUCID the
basic concept• LUCID the
basic concept• Location • Test beam
studies• LUCID design• LUCID under
construction• Assembly• LUCID
assembled• The alignment
system• The cooling
system• The gas
system• Next test
beam• Next test
beam• MC
integration• Installation• Conclusion