CBG Mine Expansion Project: Annexes – Chapter 6 A6-1 6 ANNEXES – CHAPTER 6 Annexe 6-5 Chronology of Consultations Conducted to Date by the Community

ANNEXES – CHAPTER 6 · Baseline study 4/2/2014 Madina Dian - Baseline study Baseline study 16/1/2014 M'Bouroré - Archeological study Baseline study 16/1/2014 Fassaly Foutabhé

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

  • CBG Mine Expansion Project: Annexes – Chapter 6

    A6-1

    6 ANNEXES – CHAPTER 6

    Annexe 6-5 Chronology of Consultations Conducted to Date by the Community

  • CBG Mine Expansion Project: Annexes – Chapter 6

    A6-2

    Mission Date Subject

    Assessment of social impacts 8/3/2014 Impact study consultation - Kamsar-Centre Assessment of social impacts 8/3/2014 Impact study consultation - Kourawel Assessment of social impacts 7/3/2014 Impact study consultation - Sangarédi - CBG Mine Assessment of social impacts 7/3/2014 Impact study consultation - Parawol Aliou Assessment of social impacts 7/3/2014 Impact study consultation - Madina Dian Assessment of social impacts 6/3/2014 Impact study consultation - Cogon Lengué Assessment of social impacts 6/3/2014 Impact study consultation - Sangarédi - Health center Assessment of social impacts 6/3/2014 Impact study consultation - Dian Assessment of social impacts 5/3/2014 Impact study consultation - Boundou Wandé Assessment of social impacts 5/3/2014 Impact study consultation - Fassely Foutabhé Assessment of social impacts 5/3/2014 Impact study consultation - Parawol Malassi Assessment of social impacts 4/3/2014 Impact study consultation - Horé Lafou Assessment of social impacts 4/3/2014 Impact study consultation - Ndanta Fongné Ley Assessment of social impacts 3/3/2014 Impact study consultation - Parawi Assessment of social impacts 1/3/2014 Impact study consultation - Hamdallaye Assessment of social impacts 1/3/2014 Impact study consultation - Guéguérré Assessment of social impacts 28/2/2014 Impact study consultation - Sangarédi - Women Assessment of social impacts 28/2/2014 Impact study consultation - Sangarédi - Youth Assessment of social impacts 28/2/2014 Impact study consultation - Boulléré Assessment of social impacts 28/2/2014 Impact study consultation - Sangarédi - Thiankounaye district Assessment of social impacts 27/2/2014 Impact study consultation - Sangarédi - CBG Human Rights Assessment of social impacts 27/2/2014 Impact study consultation - Sangarédi - Improved health center Assessment of social impacts 27/2/2014 Impact study consultation - Sangarédi - Territorial gendarmerie Assessment of social impacts 27/2/2014 Impact study consultation - Sangarédi - CECIDE Assessment of social impacts 27/2/2014 Impact study consultation - Sangarédi - Daramagnaki Assessment of social impacts 27/2/2014 Impact study consultation - Sangarédi - Subprefecture Assessment of social impacts 27/2/2014 Impact study consultation - Sangarédi - City hall Assessment of social impacts 27/2/2014 Impact study consultation - Sangarédi - Lavage district Assessment of social impacts 27/2/2014 Impact study consultation - Sangarédi - Spontaneous interview Assessment of social impacts 26/2/2014 Impact study consultation - Sangarédi - Bappa Sargent district Assessment of social impacts 26/2/2014 Impact study consultation - Sangarédi - Sidilara district Assessment of social impacts 26/2/2014 Impact study consultation - Corrérah Assessment of social impacts 26/2/2014 Impact study consultation - Kafelè Assessment of social impacts 25/2/2014 Impact study consultation - Boké city hall Assessment of social impacts 25/2/2014 Impact study consultation - Tanéné Assessment of social impacts 25/2/2014 Impact study consultation - Taytotte Assessment of social impacts 25/2/2014 Impact study consultation - Dabaya Assessment of social impacts 25/2/2014 Impact study consultation - Dakoultou Assessment of social impacts 25/2/2014 Impact study consultation - Boké prefecture Assessment of social impacts 24/2/2014 Impact study consultation - Kolaboui Assessment of social impacts 24/2/2014 Impact study consultation - Kalakouloun (railroad zone) Assessment of social impacts 24/2/2014 Impact study consultation - Diassia - Villager impacted by Kolaboui siding Assessment of social impacts 23/2/2014 Impact study consultation - Kamsar - Kamsar subprefecture (teachers) Assessment of social impacts 23/2/2014 Impact study consultation - Kamsar - fishers - Port Néné Assessment of social impacts 23/2/2014 Impact study consultation - Kamsar-Cité Assessment of social impacts 22/2/2014 Impact study consultation - Kamsar - Aigles NGO Assessment of social impacts 22/2/2014 Impact study consultation - Kamsar - Youth Assessment of social impacts 22/2/2014 Impact study consultation - Kamsar - Kawass Assessment of social impacts 22/2/2014 Impact study consultation - Kamsar - Madina Borbof

  • CBG Mine Expansion Project: Annexes – Chapter 6

    A6-3

    Mission Date Subject

    Assessment of social impacts 21/2/2014 Impact study consultation - Kamsar - Port Néné Assessment of social impacts 21/2/2014 Impact study consultation - Kamsar - Women fish smokers - Kamsar region Assessment of social impacts 21/2/2014 Impact study consultation - Kamsar - Kassongoni district Assessment of social impacts 21/2/2014 Impact study consultation - Kamsar (city hall) Assessment of social impacts 21/2/2014 Impact study consultation - Kamsar - Port Fory Assessment of social impacts 21/2/2014 Impact study consultation - Kamsar - Port Kamsar Assessment of social impacts 21/2/2014 Impact study consultation - Kamsar - Filima Assessment of social impacts 21/2/2014 Impact study consultation - Kamsar - Kamsar subprefecture Baseline study 18/2/2014 N'Diarindé Missidé - Archeological study Baseline study 8/2/2014 Parawol Malassi - Baseline study Baseline study 7/2/2014 N'Diarindé Missidé - Baseline study Baseline study 7/2/2014 Hamdallaye - Baseline study Baseline study 7/2/2014 Boulleré - Baseline study Baseline study 6/2/2014 Kamsar - Baseline study Baseline study 6/2/2014 Paragogo - Baseline study Baseline study 6/2/2014 Sangarédi - Baseline study Baseline study 6/2/2014 Boké - Baseline study Baseline study 5/2/2014 Kourawel - Baseline study Baseline study 5/2/2014 Daramagnaki - Baseline study and PEPP Baseline study 4/2/2014 Diandian - Baseline study Baseline study 4/2/2014 Madina Dian - Baseline study Baseline study 16/1/2014 M'Bouroré - Archeological study Baseline study 16/1/2014 Fassaly Foutabhé - Archeological study Baseline study 13/1/2014 Kamsar - Baseline study Baseline study 11/1/2014 Laffou M'Baila - Archeological study Baseline study 11/1/2014 Louggal - Archeological study Baseline study 11/1/2014 Hamdallaye - Archeological study CBG public consultation 17/12/2013 Daramagnaki public consultation CBG public consultation 16/12/2013 Kamsar public consultation Baseline study 16/12/2013 Sangarédi - Baseline study CBG public consultation 11/12/2013 Tanéné public consultation CBG public consultation 10/12/2013 Sangarédi public consultation CBG public consultation 10/12/2013 Kolaboui public consultation CBG public consultation 9/12/2013 Public consultations - Boké Baseline study 9/12/2013 Sangarédi - Baseline study Baseline study 7/12/2013 Sangarédi - Baseline study Baseline study 21/11/2013 Sangarédi - Baseline study Baseline study 20/11/2013 Sangarédi - Baseline study Scoping 17/11/2013 Boké - Scoping Scoping 25/10/2013 Conakry - Scoping Scoping 23/10/2013 CBG - Scoping Scoping 23/10/2013 CBG - Scoping Scoping 23/10/2013 CBG - Scoping Scoping 23/10/2013 CBG - Scoping Scoping 23/10/2013 Kamsar - Scoping Scoping 22/10/2013 Kamsar - Scoping Scoping 22/10/2013 Daramagnaki - Scoping Scoping 21/10/2013 Diandian - Scoping Scoping 21/10/2013 Kamsar - Scoping

  • CBG Mine Expansion Project: Annexes – Chapter 6

    A6-4

    Mission Date Subject

    Scoping 21/10/2013 Karedabel - Scoping Scoping 19/10/2013 Bembeya - Scoping Scoping 19/10/2013 Guégueré - Scoping Scoping 19/10/2013 Fassaly Belenderé - Scoping Scoping 19/10/2013 Bandodji Nyalbi Scoping 19/10/2013 Bosseré - Scoping Scoping 19/10/2013 Boundy Foulasso - Scoping Scoping 19/10/2013 Madina Dian - Scoping Scoping 19/10/2013 Missira - Scoping Scoping 19/10/2013 Sangarédi - Scoping Scoping 18/10/2013 Kamsar (city hall) & CBG - Scoping Scoping 18/10/2013 CBG - Scoping Scoping 17/10/2013 Kamsar road, Kolaboui commune - Scoping Scoping 17/10/2013 Silidara - Scoping Scoping 17/10/2013 Sangarédi - Scoping Scoping 17/10/2013 Tanéné - Scoping Scoping 16/10/2013 Parawol Malassi - Scoping Scoping 16/10/2013 Kalinko Guessoré - Scoping Scoping 16/10/2013 Kourawel - Scoping Scoping 16/10/2013 Parawol Malassi - Scoping Scoping 15/10/2013 Soucka - Scoping Scoping 15/10/2013 Wossou - Scoping Scoping 14/10/2013 Tanéné - Scoping Scoping 14/10/2013 Boké commune - Scoping Scoping 14/10/2013 Kolaboui - Scoping Scoping 14/10/2013 Sangarédi - Scoping Scoping 13/10/2013 Silidara - Scoping Scoping 13/10/2013 Cogon Lengué Scoping 13/10/2013 Parawol Aliou Scoping 12/10/2013 Kagnaka - Scoping Scoping 12/10/2013 Boundou Wandé - Scoping Scoping 12/10/2013 Balandougou - Scoping Scoping 12/10/2013 Hore Iafou Scoping 12/10/2013 Sintiourou Hafia - Scoping Scoping 11/10/2013 Sangarédi - Scoping Scoping 10/10/2013 Sangarédi - Scoping Scoping 10/10/2013 Hamdallaye - Scoping Scoping 10/10/2013 Paragogo - Scoping Scoping 10/10/2013 Mbourore - Scoping Scoping 9/10/2013 Sangarédi - Scoping Scoping 8/10/2013 Boké - Scoping Scoping 8/10/2013 CBG & Sangarédi (subprefecture) - Scoping Scoping 5/10/2013 CBG - Scoping Scoping 5/10/2013 Kamsar - Scoping