24
Analysing the stability of an islanded hydro-electric power system The American Modelica Conference 2018 Dietmar Winkler Kindly presented by Prof. Luigi Vanfre, ALSETLab ż th October ŵųŴŻ

Analysing the stability of an islanded hydro-electric power ......Contents Introduction Projectbackground Projectobjectives Modelling TheOpenIPSLlibrary Transmissionsystemmodel Three-generatormodel

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • Analysing the stability of an islandedhydro-electric power system

    The American Modelica Conference 2018

    Dietmar Winkler

    Kindly presented by Prof. Luigi Vanfretti, ALSETLab

    th October

  • Contents

    Introduction

    • Project background• Project objectives

    Modelling

    • The OpenIPSL library• Transmission system model

    Three-generator model

    Four-generator model

    Simulation

    • Results of two different load scenariotypes

    Active and reactive load changes

    Active load changes only

    Conclusions

    • Summary• Modelling challenges

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • Contents

    Introduction

    • Project background• Project objectives

    Modelling

    • The OpenIPSL library• Transmission system model

    Three-generator model

    Four-generator model

    Simulation

    • Results of two different load scenariotypes

    Active and reactive load changes

    Active load changes only

    Conclusions

    • Summary• Modelling challenges

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • Contents

    Introduction

    • Project background• Project objectives

    Modelling

    • The OpenIPSL library• Transmission system model

    Three-generator model

    Four-generator model

    Simulation

    • Results of two different load scenariotypes

    Active and reactive load changes

    Active load changes only

    Conclusions

    • Summary• Modelling challenges

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • Contents

    Introduction

    • Project background• Project objectives

    Modelling

    • The OpenIPSL library• Transmission system model

    Three-generator model

    Four-generator model

    Simulation

    • Results of two different load scenariotypes

    Active and reactive load changes

    Active load changes only

    Conclusions

    • Summary• Modelling challenges

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • IntroductionProject background

    The Westfjords

    • Low reliability of power supplyin this area

    • Consumption is larger thanarea’s local production

    • If connection to central grid islost loads need to be reduced

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • IntroductionProject objectives

    Goal

    • Determine optimaldisconnection sequence of

    loads

    • Effect of additional productionof Hvesta power station

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • IntroductionThe transmission system

    • transmission linesOperating at

    132kV 66kV 33kV 11kV• load centres

    Bíldudalur

    Patreksfjörður

    Tálknafjörður

    • generating unitsMjólká , &

    Hvesta

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • IntroductionThe power stations

    Mjólká

    • Largest power station in the Westfjords• Total capacity of 13.25MVA• Generating units

    Mjólká (Francis turbine, 3.4MVA)Mjólká (Pelton turbine, 8.5MVA)Mjólká (Francis turbine, 1.35MVA)

    Hvesta

    • Pelton turbine, 1.7MVAFigure: Power house of Mjólká and Mjólká

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • ModellingThe Open Instance Power System Library

    OpenIPSL

    • open-source library for modelling of electrical powersystems

    • developed as an continuation of the iTesla project and ismaintained by the ALSETLab research group

    • components are based on and validated against modelsfrom the existing power system software such as “Power

    System Simulator for Engineering (PSS/E)” and “Power

    System Analysis Toolbox (PSAT)”

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • ModellingThree-generator model

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • ModellingFour-generator model

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • SimulationsScenario 1: Active and reactive loads

    • Connection to the national grid is lostat 20s

    • Loads are partially disconnected if thefrequency drops below a specified limit

    • Loads remain disconnected• Quality requirements:

    Frequency

    Voltage

    Initial loads

    Load name Active load Reactive load

    [MW] [Mvar]

    LoadTAL . .

    LoadBIL . .

    LoadPAT . .

    Total loads . .

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • SimulationsLoad Scenario 1.1: Disconnection of LoadPAT and LoadTAL

    • % of LoadTAL and LoadPAT are disconnected• System stabilises s after the disconnection from the national grid

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • SimulationsLoad Scenario 1.2: Disconnection of LoadBIL

    • % of LoadBIL is disconnected• System stabilises s after the disconnection from the national grid

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • SimulationsLoad Scenario 1: Additional production, four-generator model

    • The increased production of Hvesta stabilises the system• System stabilises s after the disconnection from the national grid

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • SimulationsScenario 2: Active loads

    • Connection to the national grid is lostat 20s

    • Loads are partially disconnected if thefrequency drops below a specified limit

    • Loads remain disconnected• Quality requirements:

    Frequency

    Voltage

    Initial loads

    Load name Active load [MW]

    LoadTAL .

    LoadBIL .

    LoadPAT .

    Total loads .

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • SimulationsLoad Scenario 2.1 (3G): Disconnection of LoadPAT and LoadTAL (Three-generator)

    • % of LoadPAT and LoadTAL are disconnected• System stabilises s after the disconnection from the national grid

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • SimulationsLoad Scenario 2.1 (4G): Disconnection of LoadPAT and LoadTAL (Four-generator)

    • % of LoadPAT is disconnected (LoadTAL stays connected)• System stabilises s after the disconnection from the national grid

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • SimulationsLoad Scenario 2.2 (3G): Disconnection of LoadBIL (Three-generator)

    • % of LoadBIL is disconnected• System stabilises s after the disconnection from the national grid

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • SimulationsLoad Scenario 2.2 (4G): Disconnection of LoadBIL (Four-generator)

    • % of LoadBIL is disconnected• System stabilises s after the disconnection from the national grid

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • Conclusions

    LoadBIL

    • Disconnection of LoadBIL gives fasteststabilisation for both scenarios

    Additional production from Hvesta

    • Grid is not overloaded in scenario• Gives better voltage stability at all buses• System stabilises slower

    Modelling Challenges

    • For numerical reasons parameters hadto be adjusted away from original PSS/E

    values

    • Reduced load values→ simulatedvoltage levels lower than in reality

    • Sub-optimal turbine governorparameters lead to frequency offset

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • Conclusions

    LoadBIL

    • Disconnection of LoadBIL gives fasteststabilisation for both scenarios

    Additional production from Hvesta

    • Grid is not overloaded in scenario• Gives better voltage stability at all buses• System stabilises slower

    Modelling Challenges

    • For numerical reasons parameters hadto be adjusted away from original PSS/E

    values

    • Reduced load values→ simulatedvoltage levels lower than in reality

    • Sub-optimal turbine governorparameters lead to frequency offset

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

  • Thank you!Acknowledgement and Contact

    Acknowledgement

    This paper is based on the work executed by Kim Aars

    as part of his Master’s Thesis in with the title:

    “Simulation of load and fault scenarios in a hydro

    power system with island grid” in cooperation with

    Verkís Consulting Engineers, Iceland

    Contact

    [email protected]

    Analysing the stability of an islanded hydro-electric power system – The American Modelica Conference /

    mailto:[email protected]