AMC Process in Plant Maintenance
Purpose: - In any SAP Plant Maintenance implementation, customer will ask about how to handle the AnnualMaintenance Contract Process (AMC Process) in SAP. People might follow different procedures, here I havedocumented one process and this might be useful for the freshers.
AMC Process for Preventive Maintenance :
1. Create Service Master.2. Create Outline Agreement3. Create General Maintenance Task list4. Create Maintenance Plan5. Schedule Maintenance Plan6. Release Maintenance Order7. Create Purchase Order against the Purchase Requisition8. Create Service Entry sheet against the Purchase Order9. Perform TECO for the Maintenance Order
Step 1:- Create Service Master by using the transaction code AC01.
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:002
Step 2:- Create Outline Agreement / Service Contract for AMC by using the Transaction Code ME31KEnter necessary data like Vendor, Agreement Type, Item Category as D and Acct AssignmentCat. as F
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:003
Enter the service short text, here I have taken 4 visits for Preventive and two visits for Free Break Down.Since system will not allow zero price, entered minimum amount as 0.01 USD for Free Break Down Services.
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:004
Details of Service specifications for Preventive Maintenance are as below
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:005
Details of Service specifications for Free Break down Services.
SAVE the Outline Agreement after entering all the details. System will generate Outline agreement number.
Step 3:- Create General Maintenance Task List by using the transaction Code IA05 and enter the control keyas PM03 and enter the Outline agreement number as shown below.
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:006
By using the service specifications button copy the services from the agreement
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:007
Step 4:- Create single cycle maintenance plan by using the transaction code IP41 and enter the Task Listwhich was created earlier.
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:008
Step 5:- Schedule Maintenance Plan and Release Maintenance Order1. Maintenance Plan can be scheduled manually by using the Transaction IP10, in regular practice these
maintenance plans will be run on batch job in background.2. Upon scheduling , Maintenance Orders will be triggered with reference to the intervals maintained in
Maintenance Plan 3. The Maintenance Orders (Preventive) called will be released to process further4. Purchase requisition will be triggered on release of Maintenance Order.
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:009
Step 6:- Process of Purchase Requisition to Purchase OrdersUse the transaction ME21n, Create Purchase Order with reference to the Purchase Requisition numberwhich was created in the Maintenance Order.
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:0010
Step 7:-Use the transaction ML81n, Create service entry sheet with reference to the Purchase Order whichwas created from Purchase Requisition shown in the earlier screen shot.
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:0011
After completion of the Service entry sheet service cost will reflect in the Maintenance Order and do the TECOand other normal PM process like settlement and business completion of the order.
AMC for Breakdown Maintenance Process
Use the Transaction IW31 and create Break down Maintenance Order as like normal PM Process.Enter the Control Key as PM03 for the Operation which is to be done by the vendor as per the OutlineAgreement and enter the Outline Agreement number with Item number 0020
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:0012
Process of Breakdown Maintenance Order similar to Preventive Maintenance Order
1. Release the Maintenance Order2. Purchase Requisition created from Maintenance Order is further processed to Purchase Order.
3. Create a Service Entry Sheet against the Purchase Order. 4. Accept the Service Entry Sheet.5. Perform Maintenance Order for Technical Completion and Settlement.
6. Perform Business Completion
Upon releasing of the Break Down Order system will create Purchase Requisition and with reference to PR,PO has ben created.
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:0013
Create Service Entry Sheet with reference to Purchase Order
AMC Process in Plant Maintenance
Generated by Jive on 2015-08-27+02:0014
Similarly for any Paid Break Down Services, we can create one more line item in the Outline Agreement andprocess the same like Break Down Order.
Hope this will be useful....