39
CMAA-San Diego Panel: Alt Delivery Methods 5/26/11 1 CMAA Workshop May 26, 2011 Alternative Delivery Methods What do Public Owners Want? CMAA Alternative Delivery Workshop Bill Prey Principal Engineer San Diego Association of Governments (SANDAG)) 37 years civil engineering experience - public and private SANDAG LOSSAN Corridor Director – Managing 21 major capital projects valued at over $800 million SANDAG Construction Engineer - Managed the construction of seven major Light Rail Transit (LRT) with total value over $1 billion

Alternative Delivery Methods: What do Public Owners Want?

Embed Size (px)

DESCRIPTION

Over the course of the Propositions S & N construction bond program, the District has utilized various construction delivery methods. Under Design/Bid/Build, plans and specifications are completed by an architect, and then advertised for bid. CMMP provides the District greater flexibility than Design/Bid/Build in selecting the firm which is ultimately responsible for delivering the project. In a Design/Build (D/B) project, the contractor and architect form a single entity to deliver a complete project based on a conceptual plan provided by the District. Lean Construction principles, a production management-based approach to project delivery where work is structured throughout the process to maximize value and reduce waste, are integrated into all projects.

Citation preview

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

1

CMAA Workshop May 26, 2011

Alternative Delivery Methods What do Public Owners Want?

CMAA Alternative Delivery Workshop

Bill Prey Principal Engineer San Diego Association of Governments (SANDAG))

  37 years civil engineering experience - public and private   SANDAG LOSSAN Corridor Director – Managing 21

major capital projects valued at over $800 million   SANDAG Construction Engineer - Managed the

construction of seven major Light Rail Transit (LRT) with total value over $1 billion

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

2

Presentation Overview

  Alternative Delivery Methods

  DBB – Design, Bid, Build

  DB – Design Build

  CMAR – CM at Risk

  CMMP – CM Multiple Prime

  IPD – Integrated Project Delivery

  PPP – Public Private Partnerships

Presenters

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

3

CMAA Alternative Delivery Workshop

  21 years with Sundt   38 years in Alternate Project Delivery   17 years experience in Design/Build   Design-Build Institute of America, Western Pacific

Region; Director and Legislative Committee Chair   Associated General Contractors of America, San Diego

Chapter; Director

Jon Wald Senior Vice President Sundt Construction

Jim Gillie Director, Const. Services UCSD)

CMAA Alternative Delivery Workshop

  UCSD Facility Design and Construction Department since 2000

  Manages $2 billion design and construction work at main campus, east campus Health Sciences facilities, Hillcrest Hospital and Scripps Institution of Oceanography

  22 years with Blake Construction Co.

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

4

CMAA Alternative Delivery Workshop

  Oversees $1.5 billion construction bond program, facilities services, and police functions

  Executive Dir. of Facilities for SD Unified School District   Implemented $1.51 billion Proposition MM capital

construction bond program and managed $131 million annual physical plant operations

David Umstot, PE Vice Chancellor, Facilities Mgmt. SD Community College Dist.

  Manages Design Build and P3 pursuits for Flatiron in the West

  19 years experience managing heavy civil projects in the Western U.S.

  Pursuit Manager for Presidio Parkway Project, San Francisco – 1st Infrastructure P3 in Western US

CMAA Alternative Delivery Workshop

Darren Blume Business Development Mgr. Flatiron West, Inc.

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

5

CMAA Alternative Delivery Workshop

Dan Fauchier Executive Vice President The ReAlignment Group)

  35 years in design and construction project management and consulting

  Lean Construction trainer and mentor to owners, designers and builders

  Alignment Partnering / ReAlignment facilitator

Provocateurs

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

6

CMAA Alternative Delivery Workshop

Afshin Oskoui, PE City Engineer City of San Diego

  25 years civil engineering and construction experience in public works

  Responsible for the oversight of the City’s Land Development Permit Process and 10-year $7.2 Billion Capital Improvement Program

  Lead development of City’s first and most comprehensive Design-Build, and CM@R project delivery methods

CMAA Alternative Delivery Workshop

Mark G. Budwig Partner McKenna Long & Aldridge LLP

  Practiced exclusively construction law for 25 years   Public (Cal. & Federal) and Private Projects   Drafted, arbitrated and litigated all forms of contract

delivery methods   Former Licensed Civil Engineer (CA)

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

7

Project Delivery Methods

Design-Bid-Build

Bill Prey SANDAG

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

8

DDB Sequential Phases

OWNER

DESIGNER

OWNER

CM DESIGNER BUILDER

Construction Phase Design Phase

Summary of DBB

Construction

Time May take longer & cause late news on cost

Owner

GC

Designer

S U B S

Less Collaboration

CM

Design Bid

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

9

DBB: What’s Working, What’s Not-Working

Working:   Complete design – no surprises   Less expensive on bid day   Increased perception of fairness   Avoids preferential awards

Not-Working:   Comfort in mediocrity   Risk for builders   Provides less quality   Detracts from relationship building

Jon Wald Sundt Construction

Design-Build

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

10

Design-Build

Selection Process:   Qualifications Only (QBS)

  Requires no bridging documents   Price Only

  Requires extensive bridging documents   Best Value (BV) Combination of Technical Score and Price

  Requires limited bridging documents (primarily scope and program)

Design-Build

Qualifications Only (QBS)   Requires no bridging documents   Example: San Diego Airport Green Build Terminal

2 Expansion

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

11

Design-Build

Price Only   Requires extensive bridging documents   Example: Most Federal Projects, Warriors in

Transition, Fort Bliss, TX

Design-Build

  Best Value: Combination of Technical Score and Price   Requires limited bridging documents (primarily

scope and program)   Example: SD City College Math & Social

Sciences Building

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

12

What it takes:   Trust   Collaboration   Win-Win-Win Attitudes

Our experience: The greater trust, collaboration and win-win-win you have, the greater success you will experience.

Design-Build

Design-Build

Advantages (owner perspective):   Cost control   Schedule control   Not responsible for design Disadvantages (owner perspective):   Loss of direct design relationship   Need for early, comprehensive project definition   Re-training of staff

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

13

DB: What’s Working, What’s Not-Working

Working:   Trade contractors involved in construction drawings   Design changes are within budget   Schedule advantages   Owners must be disciplined about change

Not-Working:   Owner’s perceived loss of design control   Cost overruns   Unclear bid documents   Potential public skepticism   Some CA Public agencies do not allow qualifications-based

selection of Design-Build team

Jim Gillie University of California, San Diego

Construction Manager at Risk

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

14

CM/GC Method

OWNER

DESIGNER BUILDER (CM/GC)

DESIGN & CONSTRUCTION PHASE

CM at Risk at UCSD

  CA Department of Industrial Relations – Prequalification: a convenient coincidence?

  Prequalification is a key to the success of all our projects AND is required for alternate delivery methods

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

15

CM at Risk at UCSD

Eleanor Roosevelt College UCSD’S First CM at Risk Project

Prequalification: 3-Step Process

Level 1 Step 1: Advertisement

  RFQ   Mandatory Meeting   Submit Qualifications

Step 2: Invitation to interview   Interview Requirements

Level 2 Step 3: Prequalification Acceptance letter

  RFP   Bid

What exactly is being bid?

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

16

Prequalification: Criteria

  Certification (Pass/Fail)   Attendance at mandatory meeting – (Pass/Fail)   Surety Declaration*** - (Pass/Fail)   Insurance Declaration*** - (Pass/Fail)   Construction Experience – MAJOR

DETERMINING FACTOR!   3 – 5 comparable projects in last 10 years

  Staff Experience – MAJOR DETERMINING FACTOR!   Minimum Staff Requirements – (Basis of Bid)

Prequalification: Criteria (cont.)

  Safety Program   Quality Control Program   Business Construction Revenue – (Formula)   Mediation, Arbitration, Litigation, Disciplinary

Record   Preconstruction Services Requirements

  And non-scored estimate of Precon. Services

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

17

Preconstruction Services

  Estimates – DD, 50% CD, & 100% CD   Preliminary Schedule – for sub-Bids also   Constructability Review   Bid package strategy   Bidding sub-trades   General Requirements

Approval for Construction

CM @ Risk Contract: A Two-Part Contract

Part 1 – CM (Consulting) Contract

Part 2 – Construction Contract

Cal IT²

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

18

The CM @ Risk Contract

The CM @ Risk Contract: Part 1   Consulting agreement to perform the specified

preconstruction services

The CM @ Risk Contract: Part 2   General construction contract   Plans and specs

Computer Science Engineering Building

CM @ Risk

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

19

Basis of Award of CM @ Risk Contract

  Prequalified firms bid the Fee & GC to manage the construction

  This includes every cost the firm will incur to schedule, coordinate, manage, and administer the construction contract, i.e.:   All field and office overhead & profit, staff, and

whatever supplies, materials, equipment, and utilities needed by general contractor to perform its work.

Basis of Award of CM @ Risk Contract

  The bids do not include the following costs:   The cost of the actual construction work.   The General Requirements needed by the project

or the trade contractors

  Examples:   Do include in bid general contractor’s trailer   Do not include project fence or dumpsters   Do include all utility costs for GC’s trailer   Do not include utility costs for project

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

20

Transition from CM to Construction Contract

If the sum of the general contractor’s bid Fee & GC plus the sum of the trade bids plus the cost of General Requirements is within the budget and the project is scheduled to complete within the Contract Time, then…..

The construction “option” in the agreement is exercised, the costs of the trade bids and General Requirements are added to the agreement by Contract Amendment, (the Fee and GC bid amount are specified in the agreement) and the general contractor has a complete contract.

  The amount paid for preconstruction services is established by UCSD and known by the General Contractors prior to bidding the Fee & GC

  This amount is fixed and will not change unless the scope of the preconstruction services are changed by the University

  If the established amount is insufficient then bidder should consider increasing Fee & GC bid to cover it

  Preconstruction Cost Formula

Payment for Preconstruction Services

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

21

CM @ Risk

Moores Cancer Center

CMAR: What’s Working, What’s Not-Working

Working:   Qualifications-based selection allows contractor to

collaborate with subs   Assembles team of experts   Owner maintains control over design   True cost known up front

Not-Working:   Doesn’t guarantee project completed within budget   Requires owner discipline

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

22

Dave Umstot, PE San Diego Community College District

CM Multi-Prime

  Owner retains CM based on qualifications to act as builder

  Owner holds all trade contracts

  Typically 20-40 trade contracts

  The CM coordinates with project manager, superintendent and provides General Conditions

CMMP – What is it?

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

23

  Match builder to project

  Factor past performance into selection

  Select best management team available

  Reduce redundant management costs

  CM fee is typically equal to GC OH&P at bid

  Change order rates typically trend 50% lower than traditional delivery

CMMP – Why Do It?

Program  Level   Sum  of  Contract   Sum  of  Approved  Changes   Percentage  

CM  Mul&-­‐Prime   $    125,859,889  $    2,683,649  

2.13%  

Hard  Bid   $    125,976,590   $    10,575,169   8.39%  

Change Orders by Delivery Method

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

24

   

  Consider delivery of complicated MEP or skin systems via design/build as part of larger projects

  Integrate shop and fabrication drawings into the final design

  Resolve any spatial conflicts in model prior to construction

Design/Build of Systems with CMMP

City  College   Mesa  College   Miramar  College   Con;nuing  Ed.  Career  Technology  Center  Rudolph  &  SleAen  $55.7M        (Completed)  

Science  Building  Rudolph  &  SleAen  $47.6M  

Arts/Humani;es  and  Business  Tech  Bldgs.  Turner  Construc;on  $78.3M  

Allied  Health  Educa;on  &  Training  Facility  McCarthy  Builders  $24.9M  (Completed)  

Student  Services  Center  PCL  Construc;on  $38.5M  

Math  and  Science  Building  McCarthy  Builders  $105.2M  

Humani;es  &  Arts  and  Math  &  Business  Buildings  Sundt  Construc;on  $29.4M  (Completed)  

Library  Learning  Resource  Center  Sundt  Construc;on  $33.9M  

Cafeteria/Bookstore  &  Student  Services  Center  CW  Driver  $30.5M  

Linda  Vista  Campus  PCL  Construc;on  $16.9M  

Cesar  Chavez  Campus  Rudolph  &  SleAen  $38M  

North  City  Campus  Barnhart  Balfour  BeaAy  $21.3M  

Educa;onal  Cultural  Complex  Wing  Expansion  CW  Driver  $14.5M  

$520 Million in CMMP Hard Cost Budgets

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

25

50,000  SF,  three-­‐story  building,  

cer&fied  LEED  Gold.    Awarded    

CMAA  2010  Project  of  the  Year  

Project  Budget:  $27.4  million  

Comple&on  Date:    Sept.  2009  

Change  Order  Rate:  8.8%  (included  owner-­‐requested  coffee  kiosk)  

Completed CMMP Projects: Allied Health Building

88,000  SF,  five-­‐story  building,  cer&fied    

LEED  Gold.    Includes  parking  structure  with  

approximately  700  spaces.  Winner  of  CA  

Higher  Educa&on  Sustainability  Conference  

award  for  Best  Overall  Sustainable  Design.  

Project  Budget:  $63.1  million  

Comple&on  Date:    April  2010  

Change  Order  Rate:  0.6%  

Completed CMMP Projects: Career Tech Center

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

26

Humani&es  &  Arts  provides  45,000  sq.  b.  of  new  classroom  and  laboratory  space.  

Math  &  Business  provides  45,000  sq.  b.  of  new  classrooms,  computer  labs,  and  a  mathema&cs  research  center.  

The  dual  classroom  building  project  was  named  CMAA  2011  Project  of  the  Year.  

Project  Budget:  $32.8  million  

Comple&on:    December  2010  

Change  Order  Rate:  3.7%  

Humanities & Arts and Math & Business Bldgs.

CM Multi-Prime: What’s Working, What’s Not-Working

Working:   Allows owner to bid out smaller components   Provides flexibility to owners   Several school districts seem to like it

Not-Working:   Larger owner administrative burden   Potential lack of single overall project manager   Multiple primes must be scheduled and coordinated   Loss of efficiency due to lack of coordination

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

27

Dave Umstot, PE San Diego Community College District

Integrated Project Delivery

•hAp://www.aia.org/ipdg  

Owner’s Perspective: IPD

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

28

IPD: What is it?

  Project  delivery  approach  that  integrates  people,  systems,  business  structures,  and  prac&ces  to  op&mize  project  results,  increase  value  to  the  owner,  reduce  waste  and  maximize  efficiency  of  project  delivery.  

  Dis&nguished  by  highly  effec&ve  collabora&on  among  the  owner,  prime  designer    and  prime  constructor  commencing  at  early  design  through  project  comple&on.  

Waste in Construction

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

29

IPD: Why do it?

Target Costing

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

30

BIM! BIM! BIM!

  Build  it  in  model  space  before  you  build  it  in  real  space  

  Reduce  conflicts  using  Revit  and  NavisWorks  clash  detec&on  

  Energy  efficiency  evalua&on  

  Walk  the  end  user  through  the  space  

  With  schedule  integra&on,  a        4-­‐D  model  can  be  developed  

  With  cost  es&mates,  a  5-­‐D  model  can  be  developed  

Builder’s Perspective: Internal Clash Survey

 Building Construction Mechanical piping hits cable tray and fire protection piping in ceiling space

  Survey Average Results  Man-hour Savings = 61  Delay Savings = 3 Days  Cost Savings = $30,349

  Number of Clashes Shown in Example = 9   Savings per Clash Resolved = $3,372

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

31

Early Attitudes Towards Lean Construction

  We’ve  tried  that.  

  We  already  do  that.  

  We  don’t  need  it.    It  won’t  work  here.    We  don’t  build  cars.  

  We’re  different.  

  The  other  guy  needs  it,  not  me.  

  We’re  doing  well,  so  why  change?  

RFI Value Stream Mapping

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

32

Cont. Education: Major Projects 2010-11

Key Points

  Reducing workflow variability   Improves total system performance   Makes project outcomes more predictable   Simplifies coordination   Reveals new opportunities for improvement

  Point speed and productivity of a single operation doesn’t matter – throughput does

  Strategy: Reduce variation then go for speed to increase throughput.

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

33

Local Optimization

Playing the Capacity Utilization Game   Workflow  losses  are  real,  lead  to  adversarial  rela&ons  and  can  not  be  demonstrated  by  delay  claims,  so…  

  Trade  contractors  protect  themselves  by  adding  con&ngency  and  holding  back  labor  to  keep  u&liza&on  high  

  This  further  reduces  workflow  predictability  and  increases  project  risk  

  By  their/our  ac&ons,  we  shib  that  risk  along.  

Why Pull Planning

  Without Pull Planning:   Only half the tasks on weekly work plans are

completed as planned   So called “project control” is after-the-fact

identification of variances, not proactive steering toward objectives

  Projects are a commitment-free zone; promises are neither requested nor made

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

34

Darren Blume Flatiron West, Inc.

Public - Private Partnership

P3 Legal Structure

P3 Delivery Model:

Owner

Designer- Builder

Operations & Maintenance

Concessionaire/ SPC

Debt Provider

Equity Provider

DBFO Contract

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

35

Payments

Payment from Owner to Concessionaire:

  25,30,50,90 year payment periods (monthly, yearly, milestones, etc.)

  Two Primary payment mechanisms….

  Availability type payments (i.e. mortgage)….only if it is “available”

  Usage/Traffic Risk (who takes the risk of ridership?)….Toll or Shadow toll

Payments (cont.)

  Any combination of the above

  Incentives/Disincentives payments….   QA/QC

  Lane Rental

  Safety performance

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

36

Cost Structure

PPP: What’s Working, What’s Not-Working

Working:   Owner doesn’t need large initial investment   Maximizes innovation and creativity   Schedule Savings   Allows the US to play catch up   All the same advantages of Design-Build

Not-Working:   Understanding of Revenue risk and that risk transfer   Must be careful about the residual value of asset after transition to

owner’s possession   Procurement documents are complicated, understanding of how to

get what you want   Requires more sophisticated owner’s representation on the legal and

commercial side

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

37

Project Delivery Methods

Summary

Advantages and Disadvantages

Advantages Disadvantages CM at Risk   CM provides preconstruction

services   Design completed prior to

  State funding excludes preconstruction services

bidding   Costs more on bid day   Sub trades prequalified   Good Owner-Architect-Contractor

relationship

Design/Build   D/B provides preconstruction services

  Design NOT completed prior to bid

  Sub trades prequalified   Cost Effective - Awarded on

Cost/ Point basis

  Exact project components loosely defined

  Good Owner-Architect-Contractor relationship

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

38

Advantages and Disadvantages

Advantages Disadvantages Bid-Build   Design completed prior to bidding   No preconstruction

services   Lowest cost on bid day   Sub trades NOT

prequalified   Owner-Architect-

Contractor relationship may be stressed

CM/ Multi-Prime

  CM provides preconstruction services

  Owner at greater risk

  Sub trades prequalified   CM Selected

Advantages and Disadvantages

Advantages Disadvantages Public Private Partnerships

  A vehicle to fund projects now   Added pursuit costs (.5 to 1%)

  Schedule Savings   Owner control is decreased

  Sole Source of Finance, Design Construct and Operate (1 stop shop)

  Complicated procurement documents, defining scope at bid time

  Claims reduced; Design Conflicts

  Lack of Legal precedence

  Major Project Efficiencies   Potential for High Risk – High Reward

CMAA-San Diego Panel: Alt Delivery Methods

5/26/11

39

Where Do We Go From Here?

  Educate ourselves on relative benefits, uses and proven “track record” of alternate delivery methods

  Educate the broader community about benefits, uses and track record

  Explore legislation to provide all public agency owners flexibility to select which method works best for each project

  Continue to educate public agencies, designers, builders in how best to collaborate on projects for the best benefit of the public

Dan Fauchier, Facilitator

Discussion