    Alternate ProjectDelivery

    Opportunities

    April 21, 2010

  • 8/9/2019 Alt Proj Delivery 4-10

    2/25

    2

    Master Builder

  • 8/9/2019 Alt Proj Delivery 4-10

    3/25

  • 8/9/2019 Alt Proj Delivery 4-10

    4/25

    4

    The 60s

    Time and theHandshake

    Aerial views ofEast Los Angeles College

  • 8/9/2019 Alt Proj Delivery 4-10

    5/25

    5

    70s and 80s

    AdversarialRegulation

    Craft Talent

    Building Systems

    Users Requirements

    Edison Center for the Arts /ELAC auditorium (left) Mural by Roberto Chavez in 1970s (right)

  • 8/9/2019 Alt Proj Delivery 4-10

    6/25

    6

    The 90s and Present

    Stop the Conflicts

    Design-Build

    ConstructionManagement

  • 8/9/2019 Alt Proj Delivery 4-10

    7/25

    7

    Technological Revolution

    Communication

    Design

    Construction

  • 8/9/2019 Alt Proj Delivery 4-10

    8/25

    8

    Technological Revolution:

    SustainabilityMaterials and TechniquesCode Requirements

    Construction

  • 8/9/2019 Alt Proj Delivery 4-10

    9/25

    9

    3D Models

    Lines vs. Objects

    Technological Revolution:

    Building InformationModeling (BIM)

    Material Lists

    Cost Estimating

    Personnel Scheduling

    Funding Schedules

    Clash Detection

  • 8/9/2019 Alt Proj Delivery 4-10

    10/25

    10

    BIM Storm

    BIM

    Brain Storming

    Design Charrettes

  • 8/9/2019 Alt Proj Delivery 4-10

    11/25

    11

    Back to the Master Builder

    Eliminate Conflicts

    Changes in Designand Construction

    Technology

    Fluid Changes inOwners Needs

  • 8/9/2019 Alt Proj Delivery 4-10

    12/25

    12

    Project Delivery Methods

    Design Bid Build

    CPM-AdvisorCPM-At Risk

    Design Build

    DB

    A/E B

    CPM

    O

    A/E B

    O

    CPM

    A/E CM

    O

    Sub-contractors

    A/E CPM

    O

    Sub-contractors

  • 8/9/2019 Alt Proj Delivery 4-10

    13/25

    13

    DB

    A/E Builder

    CPM

    Owner

    CPM

    A/E Builder

    Owner

    LACCD Project Delivery Methods

    Design Bid Build Design Build

  • 8/9/2019 Alt Proj Delivery 4-10

    14/25

    14

    Design Bid Build Delivery Process

    NeedA/E TeamSelection

    Progra

    Owner

    A/E B

    O

    CPM

  • 8/9/2019 Alt Proj Delivery 4-10

    15/25

    15

    Design Bid Build

    PROS:

    Independent A/E

    Low Bid Focus

    Owner: Maximum Design Control

    CONS:

    Lengthy Linear Process

    No Pre-Qualification of BuilderExtensive finger pointing

    No constructability input by Builders

    Owner: Maximum Design Risk

    A/E B

    O

    CPM

  • 8/9/2019 Alt Proj Delivery 4-10

    16/25

    16

    Design Build Delivery ProcessDesi Buil Delivery ro ess

    Neero ra iA E Tea

    ele tio

    ro ra

    Crit

    BA/E

    O

    DB

    CPM

  • 8/9/2019 Alt Proj Delivery 4-10

    17/25

    17

    Design Build

    PROS:

    Single Sources of Responsibility

    Pre-Qualification ofENTIREENTIRE Team

    Constructability Input by Builders

    CONS:

    Independence of A/E Team

    BA/E

    O

    DB

    CPM

  • 8/9/2019 Alt Proj Delivery 4-10

    18/25

    18

    Current Design Build Process Results

    Schematic Design/ Design Development

    Fixed Price

    Design Fees

    Construction Costs

    Builders Fees

    RFP Issuance to Award: 100 120 Days

  • 8/9/2019 Alt Proj Delivery 4-10

    19/25

    19

    Construction Cost Comparison

    WLAC Parking Structure #8

    Harbor Parking Structure

    Harbor FMO

    Pierce FMO

    9/6/07 DBB $83.14/sq.ft.

    1/14/09 DB $81.50/sq.ft.

    Trade Tech South Campus

    Mission East Campus

    4/20/06 DBB $342.51/sq.ft.

    8/6/09 DB $269.27/sq.ft.

    3/22/07 DBB $658.01/sq.ft.

    1/14/09 DB $646.71/sq.ft.

  • 8/9/2019 Alt Proj Delivery 4-10

    20/25

    20

    TeamBack to the Master Builder

  • 8/9/2019 Alt Proj Delivery 4-10

    21/25

    Integrated Project Delivery

    Partnered process

    All participants

    A / E

    Contractor

    Subcontractor

    Suppliers

    Owners

    Open book

    Shared savings

    21

  • 8/9/2019 Alt Proj Delivery 4-10

    22/25

    22

    LACC Student Union

  • 8/9/2019 Alt Proj Delivery 4-10

    23/25

    23

    Current Design Build Projects

    LAPC Facilities Maintenance & Operations

    LASC Student Services Center WLAC Athletic Campus

    LAHC Science Complex

  • 8/9/2019 Alt Proj Delivery 4-10

    24/25

    24

    Current Design Build Projects

    LASC Student Services Center

    WLAC Watson Center

    LAMC East Campus

    LACC Student Union