Upload
dennis-griffin
View
220
Download
0
Embed Size (px)
Citation preview
All DØ Meeting, 12/01/00
Central Fiber Tracker
Light Guide Performance
Thomas Nunnemann
Fermilab
90 days before RunII …
(a.k.a. 12/01/00)
All DØ Meeting, 12/01/00
Optical Readout of Scintillating Fibers
Scintillating FiberOptical Connector
Waveguide Fiber
Mirror
Photodetector CassetteElectrical Signal Out
Cryostat
All DØ Meeting, 12/01/00
discrimination of signal from Visual Light Photon Counters (VLPC) with SIFT chip:
provides trigger information threshold of 1 photo electron (p.e.) signal anticipated (mayor
challenge) average p.e. yield measured in Lab3 cosmic ray test:
7 p.e. (with 11m light guide) contribution of 0 p.e. and 1 p.e. peak (Poisson), i.e.
inefficiency of single layer at threshold of 1.5 p.e 7 p.e. average: 0.7% 5 p.e. average: 4.0% Note: CFT has doublet layers!
We cannot afford any additional light attenuation! Optical transmission from SciFi to VLPC has to be optimal!
Light Yield and Trigger Efficiency
All DØ Meeting, 12/01/00
Central Track Trigger (CTT) requires a hit in all 8 axial CFT layers (8 out of 8)
for highest p-t bin (p-t > 10 GeV): 7 out of 8 MC simulation based on
7 p.e. yield, not including compromised fibers (Alan Bross):
CTT Single Track Efficiencies
(-0.5<<0.5)
Threshold Cut (PE) 8 out of 8 7 or 8 out of 8 1.0 100 (100) 100 (100) 2.0 97 (94) 100 (100) 2.5 95 (88) 100 (99) 3.0 90 (77) 98 (96)
But: Hit efficiency (doublet layer) in cosmic ray test was estimated to be approx. 98% (Brian Smith). Additional inefficiencies in CR test?
Some naïve estimates:
single layer eff. 98.0% 99.0% 99.5% 99.87%
8 out of 8 85.1% 92.3% 96.1% 99.00%
7 out of 8 99.0% 99.7% 99.93% 100.00%
All DØ Meeting, 12/01/00
152 Light Guides on Each Side of CFT
CFT installed in central cryostat
Light guide with curved connector
All DØ Meeting, 12/01/00
Light Guide Routing 1
2-FRONT
CFWCFE
CENTERBEAM
FORWARD DETECTORS
FORWARD PRE-SHOWERICD
LEVEL ZERO
WAVE GUIDEPATCH PANEL
VLPC CRYOSTAT INSTALLATION
SEPT 98
WAVE GUIDE FIBERBUNDLE INSTALLATION
VLPC CASSETTE
VLPC CRYOSTAT
SILICON TRACKER POWER SUPPLIES
VLPC CASSETTE
VLPC CRYOSTAT
TRACKER CABLING SLOT
ECS
All DØ Meeting, 12/01/00
Light Guide Routing 2
All DØ Meeting, 12/01/00
Light Guide Routing 3
All DØ Meeting, 12/01/00
Light Guide Testing 1
Scintillating fibers can be illuminated with LED panels. Each ribbon (256 fibers) is covered by 3 panels on both ends
respectively. LED panel designed for calibration purpose (no absolute calibration
possible, coupling LED panel – SciFi non-uniform and unknown) provides a measurement of light attenuation (LG quality)
Photo peaks in the ADC spectrum of single fibers:
Poisson fit (smeared by Gaussians) provides a measure of the average p.e. yield for a fiber channel (scintillating fiber + clear fiber + VLPC chip [quantum efficiency]).
p.e. yield with LED system: 0.5–2.5 p.e. depends on light coupling into scint. fibers
All DØ Meeting, 12/01/00
CFT Front-End: 4 production cassettes, any 2 integrated in the read-out (limited by electronics)
LED pulser data taken with primary DAQ (L3) CFT is currently primary DAQ user
hundreds of runs with millions of events provides thorough test of DAQ and data logging system
online/offline analysis using examine and stand-alone kumac/fortran code
online: direct feedback to installation team mapping SVX channels – fibers not provided in DØ offline framework
(stereo boards) LG are tested with 2-3 different LED settings.
provides a partial cancelation of LED panel effects P.e. yield can be determined with 7% accuracy on average.
But non-uniform coupling LED panel – SciFi can fake losses. classification of LGs based on uniformity of p.e. yield distributions
can be compared to ribbon and LG QC with radio-active source (Lab3)
Light Guide Testing 2
All DØ Meeting, 12/01/00
QC: Light Guide with Uniform Response
dead electronics LED panel edge
LED panel edge
All DØ Meeting, 12/01/00
QC: Light Guide with Crack Structure
The worst LG so far!
Even-odd structure indicates crack in curved connector in between doublet layer.
To minimize cracks curved connectors (LG to ribbon) are now glued with temporary clamps. Glue is strong enough to stop evolution of cracks (tested independently).
All DØ Meeting, 12/01/00
CFT Curved Connector
All DØ Meeting, 12/01/00
QC Summary: LG on Axial Ribbons
Problematic LGs were detected during QC: easy: wrong labels, wrong pinning of connectors coupled to
cassettes severe: several LG reglued, 5 LG entirely replaced (cracks)
Classification of the 152 LG (axial side), multiple class. allowed: low gain means < approx. 75%, LED effects not entirely cancelled,
performance of whole system including scintillating fibers good uniformity: 43 edge fibers with low gain: 25 drop at edge (<20%): 30 drop at edge (>20%): 16 Indication of crack: 17 several (>3) low gain fibers: 9 structure (period 32): 21 bad: 1 (shown in QC example) marginal: 20
All DØ Meeting, 12/01/00
QC Summary: LG on Stereo Ribbons
82 out of 152 LG installed and glued, QC completed for 69 LG On average LGs on stereo side have a better performance than those
on axial side: due to less handling? initial routing now close to final route only 1 replacement candidate up to now Ironically optimal performance is much more crucial for LGs on axial side,
since stereo layers are not included in CTT.
Installation and QC anticipated to be finished 12/11 2 additional checkouts of optical/electronic read-out system needed
before RunII after LG connection to final cassette after installation of AFE boards
What I haven’t mentioned: only limited QC of CPS LGs possible due to non-uniform LED response
(by design to account for large dynamic range) FPS LGs not yet produced