AFRICAN DEVELOPMENT BANK EMERGENCY POWER INFRASTRUCTURE REHABILITATION PROJECT - PHASE I SUPPLEMENTARY GRANT PROPOSAL COUNTRY : ZIMBABWE APPRAISAL REPORT ONEC DEPARTMENT December 2013

AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

AFRICAN DEVELOPMENT BANK

EMERGENCY POWER INFRASTRUCTURE REHABILITATION PROJECT - PHASE I

SUPPLEMENTARY GRANT PROPOSAL

COUNTRY : ZIMBABWE

APPRAISAL REPORT

ONEC DEPARTMENT

December 2013

Page 2: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

Table of Contents

Grant Information .................................................................................................................................. i

Currency Equivalents ........................................................................................................................... ii

Acronyms and Abbreviations ............................................................................................................... ii

RESULT MATRIX ............................................................................................................................ iii

EXECUTIVE SUMMARY .................................................................................................................. v

1 INTRODUCTION ................................................................................................................................ 1

2 ORIGINAL PROJECT ......................................................................................................................... 1

2.1 Project Background and Origin ........................................................................................................... 1

2.2 Project Objective .................................................................................................................................. 1

2.3 Project Components ............................................................................................................................. 2

2.4 Project Costs and Financing Arrangements ......................................................................................... 2

2.5 Project Implementation Status .............................................................................................................. 3

2.5.4 Rehabilitation of the Ash Plant at Hwange Power Station ........................................................... 3

2.5.5 Sub-Transmission and Distribution System Reinforcement .......................................................... 3

2.5.6 Consultancy for Environmental and Social Audit ........................................................................ 4

2.5.7 Consultancy for Project Supervision ............................................................................................ 4

2.5.8 Consultancy for Project Accounts Audit....................................................................................... 4

2.5.9 Environmental Monitoring and Capacity Building ...................................................................... 4

3 REVISED PROJECT FINANCING..................................................................................................... 5

3.1 Objectives and Description .................................................................................................................. 5

3.2 Revised Project Cost estimates ............................................................................................................. 5

3.3 Revised Implementation Schedule ........................................................................................................ 6

3.4 Project Implementation ........................................................................................................................ 6

3.4.2 Institutional Arrangement ............................................................................................................. 6

3.4.3 Monitoring and Evaluation ........................................................................................................... 6

3.4.4 Social and Environmental Management Plan ............................................................................... 6

4 JUSTIFICATION FOR SUPPLEMENTARY FINANCING .............................................................. 7

5 LEGAL INSTRUMENTS AND AUTHORITY .................................................................................. 8

5.1 Legal Instrument ................................................................................................................................... 8

5.2 Conditions Associated with Bank’s Interventions ................................................................................ 8

5.2.1 Conditions Precedent to Entry into Force of the Grant ................................................................ 8

5.2.2 Conditions Precedent to First Disbursement of the Grant ............................................................ 8

5.3 Compliance with Bank Policies ............................................................................................................ 8

6 CONCLUSION AND RECOMMENDATION ................................................................................... 8

6.1 Conclusion ............................................................................................................................................ 8

6.2 Recommendation .................................................................................................................................. 8

Annex I – Project Costs ANNEX II – Project Implementation Schedule

Page 3: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

i

Grant Information

Client’s information

RECIPIENT: Government of the Republic of Zimbabwe

Financing plan

ADB’s key financing information

Supplementary Grant

USD 4.61 million

Interest type* N/A

Interest rate spread* N/A

Commitment fee* N/A

Other fees* N/A

Tenor N/A

Grace period N/A

Timeframe - Main Milestones (expected)

Approval of Supplementary Financing by Zim-Fund POC 25/07/2013

Approval of Supplementary Financing by AfDB Board 13/11/2013

Effectiveness 25/11/2013

Last Disbursement 31/12/2014

Source Amount (USD)

million

Instrument

Zim-Fund 4.61 Grant

TOTAL COST 4.61 Grant

Page 4: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

ii

Currency Equivalents

July 2013

1UA = US Dollar (USD) 1.50396

FISCAL YEAR:

1 Jan – 31 Dec

Acronyms and Abbreviations

AfDB African Development Bank MTP Medium Term Plan

ADF African Development Fund MVA Megavolt ampere (1,000 kVA)

CAP Consolidated Appeal Framework NCB National Competitive Bidding

EIRR Economic Internal Rate of Return NGO Non-Governmental Organization

ESMP Environmental and Social Management

Plan

O&M Operation and Maintenance

EPIRP Emergency Power Infrastructure

Rehabilitation Project

PA Procurement Agency

ESIA Environmental and Social Impact

Assessment

PMT Project Management Team

GOZ Government of Zimbabwe POC Programme Oversight Committee

GPA Global Political Agreement STERP Short Term Emergency Rehabilitation

Program

HPS Hwange Power Station T&D Transmission and Distribution

IE Implementing Entity Tx Transformer

IG Inclusive Government WACC Weighted Average Cost of Capital

km Kilometer USD United States Dollar

kV Kilovolt (1,000 volts) VAR Volt-Ampere Reactive

MDTF Multi Donor Trust Fund ZEMA Zimbabwe Environmental

ManagementAuthority MMU MDTF Management Unit ZESA Zimbabwe Electricity Supply Authority

MOENRM Ministry of Environment and Natural

Resources Management

ZETDC Zimbabwe Electricity Transmission

and Distribution Company

MOEPD Ministry of Energy and Power

Development

Zim-Fund Zimbabwe Multi-Donor Trust Fund

MOF Ministry of Finance ZPC Zimbabwe Power Company

MOHCW

Ministry of Health and Child

Welfare

Page 5: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

iii

RESULT MATRIX

Country and project name: Zimbabwe, Emergency Power Infrastructure Rehabilitation Project Phase I

Purpose of the project : Improve availability and reliability of electricity supply to critical social infrastructure facilities and the people of Zimbabwe

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATION

RISKS/MITIGATION MEASURES

Indicator

(including CSI)

Baseline Target

IMP

AC

T The power production

capability of the installed

capacity fully restored

Utilised installed capacity 1237 MW in 2012 1960 MW by 2016 ZESA, ZPC

Annual Reports;

OU

TC

OM

ES

1.Improved availability

of electricity

1.1 Electrical energy production

at Hwange Power Station

3133 GWh in 2012 4800 GWh by

2016

ZPC Annual

Reports

Risk 1: Revenue risk leading to failure to

properly operate, and maintain the

rehabilitated facilities.

Mitigation Measures: (1) Ensure that the

design of the equipment installed during

the Project is robust and of low

maintenance and (2) support ZESA to

lobby for gradual tariff adjustment

towards a cost reflective tariff through

regular Bank/Government dialogue

meetings. .

Risk 2: Vandalism of rehabilitated

facilities

Mitigation Measures: Enhance security

around the refurbished installations and

Bank support ZESA to lobby for

enforcement of legislation that

criminalizes acts of vandalism and

reduction in power outages ensuring that

the system is live most of the time.

2.Access to reliable

electricity supply

2.1 Number of customers

accessing continuous electricity

supplies in selected project areas

227, 280 customers

in 2012

249,280 by 2016 ZESA and

ZETDC Annual

Reports

3.Improved

environmental quality at

HPS and surroundings

3.1 Level of air particulates in

the air at Hwange Power Station

and surroundings

273 mg/m3 in 2012 180 mg/m3 by

2016

ZPC Annual

Reports

OU

TP

UT

S

1. Distribution Network

Infrastructure upgraded

and rehabilitated

1.1 : 11/0.4kV & 33/0.4kV

distribution transformers

installed (No.)

0 in 2012 521 by 2016 Implementing

Entity Project

Progress Reports;

MMU Weekly,

Monthly &

Quarterly Reports

Risk 1: Implementation delays

Mitigation Measures: i) Engagement of

independent procurement agent; ii)

Engagement of independent

implementing entity; iii) Closer follow up

by MMU and Project Steering

Committee; iv) Effective involvement of

1.2 : Distribution lines

rehabilitated (km)

0 km in 2012 287 by 2016

1.3 Distribution cables

rehabilitated (km)

0 km in 2012 21 by 2016

Page 6: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

iv

Country and project name: Zimbabwe, Emergency Power Infrastructure Rehabilitation Project Phase I

Purpose of the project : Improve availability and reliability of electricity supply to critical social infrastructure facilities and the people of Zimbabwe

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATION

RISKS/MITIGATION MEASURES

Indicator

(including CSI)

Baseline Target

2. Sub-Transmission

Capacity Strengthened

2.1 Sub-transmission level

transformers installed (No.)

0 in 2012 7 by 2016

Bank Supervision

Mission Reports

Audit report

Project Management Teams, and v)

Better coordination through sector

governance structures;

2.2 Sub-transmission level

circuit breakers installed(No.)

0 in 2012 16 by 2016

3. Hwange Power Station

Rehabilitated:

3.1 Replace wet ash handling

system

Old ash handling

system in 2012

Completion of Ash

Dam rehabilitation

works by 2016

3.2 Construct new ash plant

control room

Old ash plant in 2012 Control room

completed by 2016

3.3 11kV transformer cable (km) Old cables in 2012 0.50 by 2016

3.4 3.3kV 3-core cables (km) Old cables in 2012 o.50 by 2016

4. Audit Services 4.1 Project Audit Produced 0 in 2012 4 by 2016

INPUTS

KE

Y

AC

TIV

ITIE

S

Component A: Rehabilitation of the Ash Handling Plant at Hwange Thermal Power Station:

Component B: Rehabilitation of sub-transmission facilities and Rehabilitation of distribution facilities

Component C : Environmental Audit

Component D: Engineering &Project Management Consultants

Component E: Audit

Component F : Environmental Monitoring and Capacity Building

Component A: USD 10.62million

Component B: USD 23.91 million

Component C: USD 0.79million

Component D: USD 1.83million

Component E: USD 0.06million

Component F: USD 2.40 million

TOTAL : USD 39.61 million

Page 7: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

v

EXECUTIVE SUMMARY

In June 2011, the Board of Directors approved a grant amounting to USD 35 million to finance

the Emergency Power Infrastructure Rehabilitation Project (EPIRP I or the Project) targeting

the power transmission and distribution facilities throughout the whole country and the

rehabilitation of the Ash Handling Plant at the Hwange Power Station in Hwange. The Protocol

of Agreement was signed in September 2011. The envisaged outcomes of the intervention

include: improved environmental management and ash handling at the Hwange Power Station,

improved reliability of sub-transmission and distribution networks, and improved electricity

supply to the water treatment plants of Harare City and other urban water supply systems.

Following the recruitment of the Implementing Entity (IE) in October 2011 and the

Procurement Agent (PA) in November 2011, the Project was launched in December 2011.

Since then, considerable progress has been achieved in the implementation of the Project. The

technical assessments, definition of scope of works and services and preparation of

procurement documents were completed followed by the launch of the procurement process.

The bid evaluation has been completed for the three packages involving physical works and

for three packages for consultancy services. The following contracts have been awarded: the

Rehabilitation of the Hwange Power Station ash dam (EPIRP/002), the Sub-transmission

Facilities reinforcements (EPIRP/003), the Distribution System Reinforcement (EPIRP/004)

the Environmental and Social Audit (EPIRP/005) and the Project Audit (EPIRP/006). The

Environmental Monitoring and Capacity Building contract requires inputs from the

Environmental and Social Audit contract and will be awarded after its commencement.

Despite the progress made in the procurement process, the prices obtained for two of the bids

have been higher than the budgeted figures in the Project Appraisal Report,

ADB/BD/WP/2011/96/Rev.1/Approved, as well as the engineer’s estimate. Generally, the

reasons for the high bid price outcomes were mainly due to: (i) negative perceptions about

Zimbabwe and its dollarized economy; (ii) lack of recent, similar projects with a similar scale

in Zimbabwe to use as references; (iii) the rehabilitation nature of the works and the lack of

sufficient documented information on the current state of the system; (iv) difficult and

unreliable cost estimating in current day Zimbabwe; and (v) the short implementation periods

required for the projects. Taking into account the concluded bidding processes and

contingencies to cater for unforeseen expenditures during the implementation process, the

expected total value of the Project is now estimated at USD 39.61 million. The additional

resources required therefore amount to USD 4.61 million.

If the Project goals and objectives as set out in the PAR are to be met, the Project must be

completed as per the original plan. The additional resources being requested will make it

possible for the Project to be completed as planned and achieve its goals.

Page 8: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

1

REPORT AND RECOMMENDATION OF THE MANAGEMENT TO THE BOARD

OF DIRECTORS ON A PROPOSED SUPPLEMENTARY GRANT

FROM THE RESOURCES OF THE ZIM-FUND TO ZIMBABWE FOR THE EMERGENCY

POWER INFRASTRUCTURE REHABILITATION PROJECT (EPIRP I)

Management hereby submits this proposal and recommendations concerning a proposal for a US$ 4.61

million supplementary grant to the Republic of Zimbabwe from the resources of the Zimbabwe Multi-

Donor Trust Fund (Zim-Fund) to finance the full implementation of the EPIRP I.

1 INTRODUCTION

1.1 It is to be recalled that on 30 June 2011, the Board approved on a lapse-of-time basis financing of

the EPIRP I targeting the rehabilitation of the ash handling plant at Hwange Power Station, the

sub-transmission facilities and distribution system throughout the country, and other related

activities.

1.2 The original estimated cost of the Project was USD 35 million and the disbursement rate as of 31

August 2013 was at 9.13%. The Project Protocol of Agreement was signed on 14 September 2011,

and the Project was launched on 15 December 2011 following the recruitment of the

Implementing Entity (IE) in October 2011 and the Procurement Agent (PA) in November 2011.

This was followed by technical assessments, provision of bid documents, and commencement of

the bidding process. By 31 December 2012, the tendering of the major components of the Project

was completed, except for Environmental Monitoring and Capacity Building (EPIRP/007). The

tendering for several of the Project components resulted in bid prices higher than the budgeted

amounts. Due to the importance of implementing the full scope of the Project for achieving the

Project objectives, this proposal is requesting supplementary financing in the amount of USD 4.61

million to enable the full implementation of the Project as originally envisaged.

2 ORIGINAL PROJECT

2.1 Project Background and Origin

2.1.1 The political and economic situation in Zimbabwe for the last decade has severely affected all

sectors of the economy including infrastructure. In this regard, the rehabilitation of key power

sector assets in the generation, transmission and distribution systems has been identified as the

fastest and least cost option for restoring capacity to increase electricity supply in order to meet

part of the current electricity demand and enhance system stability. Following the outbreak of

Cholera in the country in 2008, it was imperative for the water and sanitation situation to be

urgently addressed. In order to address the situation it was also observed that the reliability and

availability of power supply in the country had to be improved, hence the need for the

Emergency Power Infrastructure Rehabilitation Project.

2.2 Project Objective

2.2.1 The objective of the Project is to improve the provision of adequate and reliable power supply

in an environmentally sound manner through the rehabilitation of the ash handling plant at

Hwange Power Station and the sub-transmission and distribution facilities in the country. The

Project will also help to improve the reliability of electricity supply to the treatment plant of the

Harare city water supply and other urban water supply systems and thereby help prevent another

cholera outbreak in the country.

Page 9: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

2

2.3 Project Components

2.3.1 The Project complements the ongoing power sector infrastructure rehabilitation program

identified by ZPC and ZETDC, subsidiaries of ZESA Holdings mandated to operate and

maintain the Hwange power station and transmission & distribution networks respectively.

Components included in the project were selected from a list of critical interventions that need

to be conducted in the rehabilitation of power infrastructure to bring the power system to an

acceptable level of performance. The identification of the Project components was undertaken

by the stakeholders - ZESA, ZPC, ZETDC, the Ministry of Energy and Power Development and

the Ministry of Finance - as the priority activities to be supported by the limited funds available.

The Project comprises six components:

(A) Rehabilitation of Ash Plant at Hwange Power Station;

(B) Sub-Transmission and Distribution Reinforcement;

(C) Consultancy for Environmental and Social Audit;

(D) Consultancy for Project Supervision;

(E) Consultancy for Project Accounts Audit; and

(F) Environmental Monitoring and Capacity Building.

2.4 Project Costs and Financing Arrangements

2.4.1 The total cost of the EPIRP Phase I was estimated at USD 35.00 million, excluding the cost of

the services of a procurement agent which is being financed separately through the Fragile States

Facility (FSF). This was the amount approved respectively by the Zim-Fund Project Oversight

Committee (POC) for implementation of Phase I, and the Board. Table 1 summarizes aggregate

costs of the various project components at project appraisal stage.

Table 1: Original Project Cost Estimates by Component

Project Component Cost

(USD million)

A Rehabilitation of ash plant at Hwange power station 14.870

B Sub-Transmission and Distribution system reinforcement 14.960

C Consultancy for Environmental and Social audit 1.200

D Consultancy for Project Supervision 1.500

E Consultancy for Project Accounts Audit 0.070

F Environmental monitoring and capacity building 2.400

Total 35.000

Table 2: Original Project Cost by Category of Expenditure

Category of Expenditure USD (million)

A. Works 32.13

B Services 2.87

C Miscellaneous 0.00

TOTAL PROJECT COSTS 35.00

Page 10: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

3

2.5 Project Implementation Status

2.5.1 Despite being approved by the Board in June 2011, the conditions for the first disbursement

were fulfilled in May 2012. This resulted in the late commencement of the technical assessment

phase of the Project. The overall slippage from the indicative schedule in the PAR is estimated

at 12 months.

2.5.2 Despite the delays, the Project has made steady progress. USD3.2 million was disbursed by end

of August 2013 with the project having achieved the following milestones:

Completion of the technical assessment and definition of scope of works and services,

Preparation of procurement documents;

Launch of procurement process including prequalification process;

Completion of tender evaluation for 5 out of a total of 6 packages;

Negotiations and award of five contracts (EPIRP/002, EPIRP/003, EPIRP/004, EPIRP/005

and EPIRP/006). Only one contract (EPIRP/007) is yet to be awarded.

Implementation of the awarded contracts is progressing well.

2.5.3 The paragraphs below provide the detailed status of implementation of each component of the

Project.

2.5.4 Rehabilitation of the Ash Plant at Hwange Power Station

This component entails the replacement and refurbishment of various pumps, discharge lines,

low voltage and medium voltage cables in the ash handling plant at Hwange Power Station. The

main outcome of this will be improved environmental management at Hwange Power Station

ash plant. The Specific Procurement Notice (SPN) for the pre-qualification of bidders for this

component closed on 26th July 2012. The only one bidder that was pre-qualified for this package

pulled out on 7 November 2012. Thus it was agreed to change the mode of procurement to

Limited International Bidding and eleven bidders were pre-qualified for the bid. The bids for

this bidding process were opened on 9 April 2013. The bid evaluation for this complex

rehabilitation package was completed during the second week of July 2013. The contract was

awarded in August 2013 with an eight month contract delivery period.

2.5.5 Sub-Transmission and Distribution System Reinforcement

Sub-Transmission System Reinforcement: The sub-transmission part of this component

involves the supply, installation and commissioning of seven power transformers and

sixteen 132 kV circuit breakers at various substations throughout the country. The contract

for this package was awarded in January 2013. Orders have been placed for equipment

which is currently being manufactured. The target completion date for this contract is 4

January 2014.

Distribution System Reinforcement : The distribution part of this component consists of

the supply, installation and commissioning of 521 distribution transformers and

construction of 287 km of distribution overhead lines and 12 km of underground cables.

The contract for this package was awarded in February 2013. The equipment and materials

are at various stages of being manufactured in South Africa and India. The target completion

date for this contract is April 2014.

Page 11: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

4

2.5.6 Consultancy for Environmental and Social Audit

Consultancy has been procured to carry out an Environmental and Social Audit of the whole

Hwange power plant and its operations and a comprehensive Environmental and Social

Management Plan prepared for the plant. The contract was awarded in August 2013 and is

expected to be completed in July 2014.

2.5.7 Consultancy for Project Supervision

The GOZ, with the assistance of the Zim-Fund Management Unit (MMU), procured the services

of Parsons Brinkerhoff as an Implementing Entity for the Project through advance contracting

procedures. The IE provides project management, coordination, technical assessment,

preparation provision of technical documents for tenders and supervision services. The IE is also

responsible for project financial management including accounting and financial reporting. The

IE and GOZ signed the Implementing Entity Agreement in October 2011, with the IE

mobilization commencing in December 2011.

To date, the IE has completed technical assessments, provided technical inputs for tender

bidding documents preparation, prequalification, bidding and evaluation process and contract

award negotiations. With the technical input from the IE, the Procurement Agent is effectively

leading and administering the procurement process. The procurement process for most of the

packages has been completed and the next phase of the PA’s role is now administering the

contracts on behalf of the GOZ. The IE will play the role of Engineer to supervise the works and

services to be provided.

2.5.8 Consultancy for Project Accounts Audit

The project audit for year ending 2012 is being finalized. The Project audit contract was awarded

in May 2013, and the auditor is working on the report for the period ending 2012. The audit

services will include both the EPIRP I and the Zim-Fund Urgent Water Supply and Sanitation

Rehabilitation Project I.

2.5.9 Environmental Monitoring and Capacity Building

This package is made up of an environmental consultancy services to provide Capacity Building

of the Environmental Monitoring Unit at Hwange Power Station and works for the procurement

of Air Quality Monitoring Equipment for the station. The procurement of this component will

be initiated after the completion of the environmental and social audit.

Page 12: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

5

3 REVISED PROJECT FINANCING

3.1 Objectives and Description

3.1.1 The project objectives have not changed and remain as described in the PAR, as set out in section

2.2 above.

3.2 Revised Project Cost estimates

3.2.1 The bidding process for all the items in the Project except for one (Environmental Monitoring

and Capacity Building) has been completed and the comparison between the cost estimates by

the IE after the scoping exercise and the costs from the bidders is shown in Table 3. The bid

prices for the Sub-transmission and Distribution System Reinforcement component of the

Project were substantially higher than the revised cost estimate.

3.2.2 The reasons for the high bid prices were mainly due to:

Negative perceptions about Zimbabwe and its dollarized economy;

Lack of recent, similar projects with a similar scale in Zimbabwe to use as references;

The rehabilitation nature of the works and the lack of sufficient documented information on

the current state of the system;

Difficult and unreliable cost estimation in current day Zimbabwe; and

The short implementation periods.

The inclusion of some items that were considered to be essential in addressing the further

deterioration of the distribution network in Harare.

The Project Appraisal cost estimates were not based on a detailed feasibility study.

Table 3 – Comparison between cost estimates and contract prices

Project Packages

Cost estimates

at PAR

(USD million)

Actual bid

prices

(USD million)

Difference

between PAR

and actual

costs

(USD million)

Comments

A Rehabilitation of Ash Plant

at Hwange Power Station 14.87 10.62 -4.25

B

Sub-Transmission &

Distribution System

Reinforcement

14.96 23.92

8.96

Increase in

scope and

bid price

C

Consultancy for

Environmental and Social

Audit

1.2 0.79

-0.41

D Consultancy for Project

Supervision 1.50 1.83 0.33

Increase in

bid price

E Consultancy for Project

Accounts Audit 0.07 0.06 -0.01

F Environmental Monitoring

and Capacity Building 2.40 2.401 0.00

Total 35.00 39.61 4.61

Additional Resources above approved amount 4.61

1 Tender price not yet known hence estimated cost used.

Page 13: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

6

Table 4: Supplementary Financing Categories of Expenditure

Categories of Expenditure Amount (USD million)

A Works 4.61

B Services 0.0

C Miscellaneous 0

TOTAL 4.610

3.2.3 Considering the concluded bidding process and making estimates for outstanding contracts and

a contingency, the expected total cost of the Project is estimated at the revised amount of USD

39.61 million as shown in Table 3. Additional resources amounting to USD 4.61 million are

therefore required for the Project to achieve its original goals and objectives.

3.3 Revised Implementation Schedule

3.3.1 The Project was originally planned to be implemented over a period of 21 months. The contracts

for the various project components were originally expected to have been signed by late

November 2011. However, due to the various delays experienced in the implementation process,

the first contracts were signed in March 2013. Project completion for all packages is now

targeted at the end of 2014. The revised implementation schedule is shown in Annex II.

3.4 Project Implementation

3.4.1 Implementation Arrangement

The Project will continue to be implemented within the framework of the instrument establishing

the Zim-Fund and its Operations Manual. In this regard, an independent Project Implementation

Entity (IE) will be responsible for implementation coordination, and monitoring while the

procurement services will be provided by an experienced independent Procurement Agent (PA)

already appointed for the project.

3.4.2 Institutional Arrangement

There will be no change to the institutional arrangements. That is to say, the IE will be assisted

by Project Management Teams (PMTs) that have been set up within ZPC and ZETDC for

general coordination. The already set up Project Steering Committee (PSC) comprising

representatives from ZPC, ZETDC, Ministry of Energy and Power Development, and Zim-Fund

MMU will continue to address all major issues in connection with the Project, and will provide

overall guidance during project implementation.

3.4.3 Monitoring and Evaluation

Zim-Fund is developing a Monitoring and Evaluation (M&E) framework to support the

project.The logframe was retrofitted into the new format and in the process the outcome

indicators revised in line with the requirements for M&E.

3.4.4 Social and Environmental Management Plan

An Environmental and Social Management Plan for Hwange Power Station was developed by

ZPC, and an independent environmental and social audit is being done under the Project

(Contract No. EPIRP/005) which will be followed by the Environmental Monitoring and

Capacity Building component (Contract No. EPIRP/007). The Environmental and Social

Management Plans for the sub-transmission and distribution packages have been systematically

Page 14: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

7

included in the works packages for implementation by the contractor, and its implementation

will be monitored and supervised by the current IE ( Parsons Brinkerhoff).

4 JUSTIFICATION FOR SUPPLEMENTARY FINANCING

4.1 The supplementary financing proposal was approved on 25 July 2013 by the POC of the Zim-

Fund, which is composed of the Zim-Fund donors and GOZ representatives, after consideration

of the importance of achieving the original objectives of the Project. The Project is in alignment

with the Bank Group’s 2011-2013 Zimbabwe Country Brief (as well as the draft 2013 – 2015

version) and the Bank’s Strategy (2013-2022) focus on infrastructure development. The

inadequate provision or lack of reliable power supply services has affected the people of

Zimbabwe more so the poor. It therefore significantly responds to the inclusive agenda and should

be supported for the achievement of the full Project objective which is also in line with GOZ

Medium Term Plan for 2011 - 2015.

4.2 This supplementary financing proposal meets the applicable general conditions and specific

conditions for supplementary financing set out in the Bank Group Policy and Procedures for

Supplementary Financing (ADB/BD/WP/97/83). The following factors have been considered in

submitting this proposal:

(i) The execution of the Project has commenced and is progressing satisfactorily from the

technical perspective but will require additional resources to achieve its objectives.

(ii) The cost increases are beyond the control of the GOZ, and the GOZ is not in a position to

provide additional financing.

(iii) There is need to build upon the recent power sector interventions so as to improve the

deteriorated power supply infrastructure in the country. A delay in improvement of power

supply services has high tangible and nontangible economic and social costs.

(iv) It has not been possible to reduce the total cost of the project through changes of

specifications or scope of work or services without significantly affecting the objective of

the Project

(v) The project is technically and economically viable even with the cost overruns.

(vi) The Project cannot be reduced in size without damaging its ability to achieve the set

objectives or its sustainability.

(vii) There are no exogenous constraints: financial, managerial, or technical – that would hinder

the completion of the Project

Page 15: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

8

5 LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal Instrument

5.1.1 The legal instrument to finance the supplementary grant will be a Protocol of Agreement

between the Republic of Zimbabwe (the Recipient) and the Bank, in its capacity as the

administrator of the Zimbabwe Multi-Donor Trust Fund (Zim-Fund), for a grant from the

resources of the Zim-Fund.

5.2 Conditions Associated with Bank’s Interventions

5.2.1 Conditions Precedent to Entry into Force of the Grant

The Protocol of Agreement will enter into force on its date of signature by the Recipient and

the Bank.

5.2.2 Conditions Precedent to First Disbursement of the Grant

The conditions precedent to first disbursement of the initial grant, which will be extended to

the supplementary grant, have been fulfilled. As such, disbursements may be made from the

supplementary grant upon entry into force of the Protocol of Agreement.

5.3 Compliance with Bank Policies

5.3.1 The proposed supplementary grant complies with all applicable Bank policies, including the

Bank Group Policy and Procedures for Supplementary Financing.

6 CONCLUSION AND RECOMMENDATION

6.1 Conclusion

6.1.1 Priced bids received from the tendering process have been significantly higher than the budgeted

figures from the estimates arrived at during the Project appraisal stage. Considering the

concluded bids and estimates on the outstanding packages and the requirements during

execution, the expected total value of the works is estimated at USD 39.61 million, thus

additional resources of USD 4.61 million (13.2% of the original estimated Project costs) is

needed in order to achieve the objectives of EPIRP.

6.2 Recommendation

6.2.1 Considering the many socio-economic and environmental benefits of this Project, it is

recommended that the Bank approves this supplementary grant, from the resources of the Zim-

Fund, for the amount of USD 4.61 million for the EPIRP.

Page 16: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

Annex I – Project Costs

Component Package

Number

Description Budget as

appraised

(USD)

Actual

Contract

(USD)

Additional

Resource

Required

(USD)

Rehabilitation of ash plant at

Hwange power station

EPIRP/002 Ash Plant Upgrade and Rehabilitation

14,870,000 10,615,500 -4,254,500

Sub-transmission and Distribution

Reinforcement

EPIRP/003 Sub-Transmission Facilities Reinforcement 4,960,000 8,565,535.77 3,605,535.77

EPIRP/004 Distribution System Reinforcement 10,000,000 15,352,498 5,352,498

Consultancy for Environmental

and Social Audit EPIRP/005 Consulting Services for Environmental and

Social Audit and Environmental

Management Plan 1,200,000 789,095 -410,905

Consultancy for Project

Supervision EPIRP/001 Implementing Entity Services

1,500,000 1,826,964.65 326,964.65

Consultancy for Project Accounts

Audit EPIRP/006 Consultant’s Services for External Project

Audit 70,000 58,899 -11,111

Environmental Monitoring and

Capacity Building1 EPIRP/007 Environmental Monitoring and Capacity

Building 2,400,000 2,400,000 0

Total 35,000,000 39,608,482.42 4,608,482.42

1. The contract for this package has not yet been awarded hence budget price used as contract price.

Page 17: AFRICAN DEVELOPMENT BANK · 0 in 2012 16 by 2016 3. Hwange Power Station Rehabilitated: 3.1 Replace wet ash handling system Old ash handling system in 2012 Completion of Ash Dam rehabilitation

ANNEX II – Project Implementation Schedule ZIMFUND: EMERGENCY POWER INFRASTRUCTURE REHABILITATION PROJECT SCHEDULE STATUS AND PROJECTION

WORK SCHEDULE

KEY Original Schedule Projection Reporting time original completion projected completion

Current Schedule

SR. NO.

1 EPIRP 002 - Rehab. of Ash Plant

2 EPIRP 003 - Rehab. Sub transmission

3 EPIRP 004 - Rehab. Of distribution sys.

4 EPIRP 005 - Env. and Social Audit

5 EPIRP 006 - Project Audit

Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Jul-13Feb-13 Mar-13 Apr-13 May-13 Jun-13Apr-12 May-12 Jun-12

Inception, scoping, pre-Qualif ication Process

Contract Aw ard

Preparation of Contract Documents

Inception, Technical assessment, Scoping,

Pre-Qualif ication Process

Bidding Documents

Floatation

Evaluation

Jan-12

Bidding Documents

Evaluation

Evaluation

Preparation of Contract Documents

Contract Aw ard

Inception, Scoping, Pre-Qualif ication Process

Bidding Documents

Floatation

Bidding Documents

Floatation

Works Implementation

Works Implementation

Preparation of Contract Documents

Contract Aw ard

1.5

Inception, Scoping, Pre-Qualif ication Process

1.7 Works Implementation

2.7

2.5

3.2

3.3

2.6

3.1

Floatation

Aug-13

5.1 Inception, Scoping, Pre-Qualif ication Process

4.3

4.4

4.5

4.6

3.4

3.5

3.6

4.1

4.2

3.7

1.6

2.1

2.2

2.3

2.4

1.1

1.2

1.3

1.4

Sep-13 Oct-13 Nov-13 Dec-13

5.7 Implementation

5.4 Evaluation

5.5 Preparation of Contract Documents

5.6 Contract Aw ard

4.7 Implementation

Preparation of Contract Documents

Contract Aw ard

Floatation

Evaluation

5.2 Bidding Documents

5.3

Projected completion

by Jan 2014

Projected

completionby Apr 2014

Projected

completion by July 2014

Projected completion

by May 2014

Projected

completion by Dec 2014