Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
AES/PE/13-09 Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim 17.07.2013 Vegerd Veskimägi
Title : Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim Author : Vegerd Veskimägi Date : July 17th, 2013 Professor : Jan Dirk Jansen Supervisor (Statoil) : Martin Halvorsen TA Report number : AES/PE/13-09 Postal Address : Section for Petroleum Engineering Department of Geoscience & Engineering Delft University of Technology P.O. Box 5028 The Netherlands Telephone : (31) 15 2781328 (secretary) Telefax : (31) 15 2781189 Copyright ©2013 Section for Petroleum Engineering All rights reserved. No parts of this publication may be reproduced, Stored in a retrieval system, or transmitted, In any form or by any means, electronic, Mechanical, photocopying, recording, or otherwise, Without the prior written permission of the Section for Petroleum Engineering
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
Abstract The use of wells equipped with inflow control valves has steadily increased over the past decade. Most
of these wells are used to control the inflow from separate reservoirs or separate reservoir zones. This
solution is particularly attractive for high-rate horizontal wells in thin oil rim reservoirs. Through the
smart well technology, early gas or water breakthrough into the well can be delayed or even reduced.
The use of Inflow Control Devices (ICDs) and zonal flow control valves (FCVs) offers an opportunity to
evenly distribute the drawdown along the well, and therefore take corrective action if an early water or
gas breakthrough occurs. In September 2011, Statoil completed Troll’s first subsea three-zone horizontal
smart well. Just recently, anther well on Troll with a similar completion design was put into production.
One of the most important objectives in the study of well Q-12BH, which forms the basis for this report,
is understanding gas coning behavior. Without it, one would not be able to set appropriate operating
strategies, and therefore optimizing production would simply not reach the wanted results. The
approach taken begins by conducting an extensive literature review into coning control in thin oil rims
and horizontal well technology. Early production data of well Q-12BH is studied, because knowing
production history is a key into creating simulation models. These simulation models will analyze if the
well was put into production with the most optimal zonal valve opening positions and what could
possibly be even better setting for such a well.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
Table of Contents Introduction ......................................................................................................................................1
What is an oil rim? .................................................................................................................................... 1
What is coning? ......................................................................................................................................... 1
Troll field ...........................................................................................................................................3
Field layout ................................................................................................................................................ 3
Reservoir characteristics ........................................................................................................................... 4
Production and drilling units ..................................................................................................................... 6
Operation strategy .................................................................................................................................... 7
Well 31/2-Q-12 BH .............................................................................................................................8
Introduction .............................................................................................................................................. 8
Drilling information ................................................................................................................................... 8
Completion design .................................................................................................................................. 10
Synthetic permeability ............................................................................................................................ 13
Weighted arithmetic average ............................................................................................................. 14
Relative Permeability Data...................................................................................................................... 15
PVT properties ........................................................................................................................................ 16
Procedure into simulations and theoretical methods ........................................................................ 16
Well testing ............................................................................................................................................. 16
Reservoir pressure .............................................................................................................................. 16
Gas inflow............................................................................................................................................ 17
First well test ....................................................................................................................................... 18
Discussion of flow rates in different well tests ....................................................................................... 19
Simulation Modeling ........................................................................................................................ 21
Objectives ............................................................................................................................................... 21
Parameters .............................................................................................................................................. 21
Reservoir geometry ............................................................................................................................. 24
NETool modeling ..................................................................................................................................... 26
Transmissibility and mobility .............................................................................................................. 26
NETool Results ........................................................................................................................................ 27
Theoretical pressure drop across the 3.2 bar ICD-screen ................................................................... 31
Analytical Joshi’s and Muskat’s PI Models ........................................................................................ 33
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
Calculations with steady-state Joshi horizontal well PI model ............................................................... 33
Steady state Joshi horizontal well analytical simulation results ............................................................. 35
Muskat’s analytical PI calculation method ............................................................................................. 35
Assumptions of the method ............................................................................................................... 35
Theory ................................................................................................................................................. 36
Results of Muskat Method ...................................................................................................................... 37
Additional simulation ....................................................................................................................... 38
Discussion of final results ................................................................................................................. 39
Limitations .............................................................................................................................................. 43
Conclusion ....................................................................................................................................... 43
Acknowledgements.......................................................................................................................... 46
References ....................................................................................................................................... 47
Appendices ………………………………………………………………………………………………………………………………………49
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
ACRONYMS
API American Petroleum Institute
DH Downhole
DHG Downhole Gauge
FCV Flow Control Valve
FZI Flow Zone Indicator
GCGL Gas Cap Gas Lift
GOC Gas Oil Contact
GOR Gas Oil Ratio
GRN Normalized Gamma Ray
ICD Inflow Control Device
MD Measured Depth
MSL Mean Sea Level
NCS Norwegian Continental Shelf
OWC Oil Water Contact
PI Productivity Index
PVT Pressure Volume Temperature
RCP Rate Controlled Production
RKB Rotary Kelly Bushing
SCAL Special Core Analysis TWOP Troll West Oil Province
TD Total Depth
TVD True Vertical Depth
TWGP Troll West Gas Province
TWGPN Troll West Gas Province North
WC Water cut
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
NOMENCLATURE
a Half the major axis of a drainage ellipse
B Formation Volume Factor
b Half the minor axis of a drainage ellipse
g Gravity
h Thickness
J Productivity Index
k Permeability
L Length
Q Flow rate
P Pressure
R Gas oil ratio
r Radius
S Saturation
T Transmissibility
w Width
Z Zone
β Influence of anisotropy
μ Viscosity
ρ Density
λ Mobility
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
SUBSCRIPTS
ann annulus
B blanks
b bubble point
cal calibrated
eff effective
eH horizontal drainage
g gas
H horizontal well
h horizontal
in inflow
LIQ liquid
mix mixed
o oil
r,phase relative value of a phase
RES Reservoir
s specific
seg segment
SF sandface
SICD specific ICD valve
sol solution
ST standard condition
tub tubing
v vertical
w water
wb wellbore
z zone
α phase
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
FIGURES
Figure 1: Gas coning in a horizontal well ...................................................................................................... 1
Figure 2: Dimensionless pressure drawdowns in a vertical and horizontal well compared to relative
distance to the well. On the left, there are pictures of water coning and cresting. ..................................... 2
Figure 3: Troll oil and gas field near Norwegian coast in the North Sea is marked in red. It is zoomed in on
the right top corner of the figure .................................................................................................................. 3
Figure 4: The division of Troll field ................................................................................................................ 4
Figure 5: Gas and water flows between TWOP and TWGP, and through the communication channels
between Troll West and Troll East. ............................................................................................................... 4
Figure 6: Subcrop map through the geomodel (2009) in the area of well Q-12BH at 1560m TVD from the
MSL. Gamma logs lie on top of the well paths.............................................................................................. 5
Figure 7: The infrastructure of Troll West including the subsea templates on TWOP and TWGP and the
two operating platforms Troll B and Troll C .................................................................................................. 6
Figure 8: Geological cross-section of a well Q-12BH with the main three producing zones in 3CC clean
sands, 4Ac fine mica-rich sands and 4/5 heterolithic sands. ........................................................................ 9
Figure 9: Example of a multilateral Q-12 BH well completion where this sidetrack has a zonal separation
.................................................................................................................................................................... 10
Figure 10: Premium ICD screen used on the Troll Field ............................................................................... 11
Figure 11: Illustration of cable feed-through swellable packers used in smart wells ................................. 12
Figure 12: Downhole equipment and clarification of pressures ................................................................. 13
Figure 13: LET relative permeability curves for oil and water with respect to water saturation ................ 15
Figure 14: LET relative permeability curves for gas and oil with respect to gas saturation ....................... 15
Figure 15: Reservoir pressure decrease as a function of time. ................................................................... 17
Figure 16: First well test DHG pressure data together with reservoir and wellhead pressures, and FCV
openings. ..................................................................................................................................................... 19
Figure 17: Reservoir flow rates of all the well tests for different phases. ................................................... 20
Figure 18: Phase flow contribution comparison with all the well tests. ..................................................... 20
Figure 19: NETool reservoir geometry from the top and front view including yellow streamlines ............ 24
Figure 20: Simulated flow rates with varying reservoir geometry .............................................................. 25
Figure 21: NETool reservoir pressure and completion diagram. ................................................................. 29
Figure 22: NETool sandface (blue), annulus (purple) and tubing (red) pressures with respect to the length
of the well. Zonal separation is shown with dashed oval shaped circles. ................................................... 29
Figure 23: Reservoir geometry model for the three-zone horizontal well ................................................. 34
Figure 24: A box-shaped reservoir seen as a sink that drains water and oil (front view - the well runs into
the page) ..................................................................................................................................................... 36
Figure 25: Productivity Index results with different methods ..................................................................... 39
Figure 26: Total flow rate results with different methods .......................................................................... 40
Figure 27: Zonal liquid inflow contribution with different methods ........................................................... 40
Figure 28: Productivity Index for all the possible FCV openings before free gas production (See Table 3 for
FCV positions) .............................................................................................................................................. 41
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
Figure 29: DH zonal flow contribution with all the possible FCV openings before free gas production (See
Table 3 for FCV positions) ........................................................................................................................... 42
Figure 30: Liquid influx with all the possible FCV openings before free gas production (See Table 3 for FCV
positions) ..................................................................................................................................................... 42
Figure 31: Water cut with all the possible FCV openings before free gas production (See Table 3 for FCV
positions) ..................................................................................................................................................... 43
Figure 32: Simulated NETool model with equal zonal influx ....................................................................... 45
TABLES
Table 1: Reservoir and fluid properties of TWGPN during the production start-up of well 31/2-Q-12BH .... 6
Table 2: Completion design parameter lengths and positions.................................................................... 10
Table 3: FCV positions for Zone 2 and Zone 3 ............................................................................................. 12
Table 4: FCV positions for Zone 1 ................................................................................................................ 12
Table 5: Gas cap gas lift valve positions and flow area .............................................................................. 13
Table 6: Penetrated lithology layers of Q-12BH and weighted arithmetic average permeabilities. .......... 14
Table 7: 31/2-Q-12 BH first well test data (16.09.2011) ............................................................................. 18
Table 8: Parameters used for productivity indices calculation ................................................................... 22
Table 9: Reservoir width and thickness sensitivities. .................................................................................. 24
Table 10: Simulation model results of the first well test ............................................................................. 27
Table 11: NETool and well test results data comparison ............................................................................ 28
Table 12: NETool simulation model results with fully opened downhole FCVs. .......................................... 30
Table 13: DHG pressures of the actual well running with 100% opened FCV positions for two consecutive
days ............................................................................................................................................................. 31
Table 14: Pressure tag recordings in January 2012 compared with NETool simulation model results ...... 31
Table 15: Troll field ICD-valve and screen calibrated coefficients ............................................................... 31
Table 16: DH flow rate phase fractions with two different FCV openings .................................................. 32
Table 17: Average theoretical pressure drop across a single ICD-screen in all three zones ....................... 32
Table 18: Variation between NETool and theoretical pressure drop across a single ICD-screen................ 33
Table 19: Steady state Joshi horizontal well analytical simulation results ................................................. 35
Table 20: Muskat’s analytical model results .............................................................................................. 37
Table 21: Simulation #3 – Steady state Joshi’s NETool analytical method ................................................. 38
Table 22: Results of different methods ....................................................................................................... 39
Table 23: Productivity Index, zonal contribution (DH), total liquid rate (ST) and water cut of all the
possible valve positions of Q-12BH before free gas production ................................................................. 41
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
1
Introduction
What is an oil rim? An oil rim is a thin oil column in a reservoir located between a large gas cap and an aquifer. Its
production mechanism is complicated due to a very thin oil zone. One of the most challenging tasks in
such a reservoir is to keep the gas oil contact (GOC) and oil water contact (OWC) stable during the
production because drawdown causes their movement. Drawdown is also the main cause for gas and
water coning. [1]
What is coning? Coning is a tendency of gas and water to push oil towards the well in a cone shaped contour. As soon as
the cone breaks through the oil column, gas or water production increases substantially. The reason for
gas or water breakthrough is due to lower viscosity of these phases and therefore they are more mobile.
Coning phenomenon is known to reduce oil production and influence the overall recovery efficiency of
the well. It cannot be avoided, but there are some strategies that allow minimizing gas or water inflow
by delaying the breakthrough of the cone. For a better visual understanding see Figure 1, how the shape
of a gas cone forms in horizontal wells. Cone shape is also influenced by permeability. On this drawing,
the heel zone has a higher permeability, which results in a wider cone. Higher permeability zones cause
higher flow rates into the well and faster drainage compared to lower permeability sands in the toe
area. Usually high-permeability reservoirs have lower drawdowns, and therefore fewer problems related
to coning. On the opposite, lower permeability reservoirs form a narrower cone. The pressure drop
along the well is typically higher, because of the high flow rates, which leads to a strongly uneven
drawdown, and therefore inflow and coning along the well. This uneven behavior of drawdown and
inflows has a negative effect on oil production.
Figure 1: Gas coning in a horizontal well [1]
There are more parameters that affect coning. Coning tendencies are inversely proportional to density
differences and directly proportional to viscosities. For example, water coning is more likely to occur at
the same drawdown than gas coning, because the difference between water and oil density is much
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
2
smaller than the difference between gas and oil density. However, gas coning is more likely to occur
when viscosities are compared because gas is less viscous and due to the faster flow rate of gas, it is able
to finger through the oil column easier than water. In the end, both gas and water cones are likely to
occur and thereby the best theoretical solution recommends placing the wells in the center of the oil
column. Nonetheless, the current strategy on Troll places the wells almost at the OWC. As a result, Troll
wells experience much higher water cut, but more importantly they restrict gas cusping problems.
Coning is highly affected by drawdown, and drawdown is proportional to fluid production rates. This
situation makes maximizing oil production a challenge. Therefore, inflow and drawdown both need to
be reduced for production optimization. A good way to delay or reduce coning problems is using
horizontal wells as they are able to minimize pressure drop and sustain higher production rates. The
production rates can remain high because of their long wellbores. Figure 2 shows horizontal and vertical
well pressure drawdowns with respect to relative distance to the well. The pressure drop for horizontal
wells is lower and the increase much more steady. In addition, water coning and cresting are pictured on
the left side of Figure 2.
Figure 2: Dimensionless pressure drawdowns in a vertical and horizontal well compared to relative distance to the well. On the left, there are pictures of water coning and cresting. [4]
In this particular study about Troll field oil well, coning is a daily problem. Besides it being a problem, it
also helps to drive oil towards the well using gravity driven forces. This is especially helpful during the
start-up process of a well, but later the strategy of dealing with gas coning requires choking back wells
to keep the cone from reaching the wellbore. In other words, preventing coning behavior means
minimizing the gas-oil ratio (GOR) to maximize oil production. [1], [2], [3], [4]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
3
Troll field The first seismic on the Troll field in the North Sea was done in 1972. From then onwards, it took 23
years of intense research and innovative planning before the field started oil production in 1995. The
location of the field is about 80 km North West of the Norwegian city of Bergen. It lies on the edge of a
Viking Graben, which has been forming for the past 125 million years dividing Norwegian coast from the
British Isles. The field evolved by the underwater rifting processes, where the layers of C-sand and M-
sand accumulated along the eastern edge of the Sognefjord Formation. The discovery showed a massive
gas cap on top of the thin oil rim, which was initially thought not to have any commercial value.
However, time and technology proved this thin oil column to become one of the most important oil
fields in Europe. Today, Statoil ASA is the main operator on Troll field, and more than 500 well
tracks/branches have been drilled on Troll since the beginning of production. The field location on the
map is seen on Figure 3. [2], [5]
Figure 3: Troll oil and gas field near Norwegian coast in the North Sea is marked in red. It is zoomed in on the right top corner of the figure. [6]
Field layout North Sea area is divided into blocks, where Troll field is covering partly four of those blocks: 31/2, 31/3,
31/5, and 31/6. The estimated area of Troll field is about 750 km2. This area is divided into two main
production areas: Troll East and Troll West. Troll East operates with gas only, while Troll West still
remains the main oil producing area. In addition, Troll West is divided into two provinces based on the
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
4
type of reservoir fluids: Troll West Gas Province (TWGP) and Troll West Oil Province (TWOP). Most of the
upcoming study concentrates on the field characteristics of TWGPN where the well Q-12BH was drilled.
A closer layout of Troll West provinces is seen on Figure 4a. [2], [7], [8]
Figure 4: The division of Troll field. [2]
Figure 5: Gas and water flows between TWOP and TWGP, and through the communication channels between Troll West and Troll East. [2]
Reservoir characteristics The two most important reservoir formations on Troll are Fensfjord and Sognefjord. Fensfjord formation
formed during the Middle Jurassic period and it is much smaller in contributing size than Sognefjord
formation. Sognefjord formation, where most of the Troll wells have been drilled, developed during the
Late Jurassic period. This formation lies on top of the Viking Group and was formed near shore
environment in a shallow marine setting through transgression and regression of the sea. The entire
Troll field consists of three main fault blocks, where the pressure communication between Troll East and
West has been proven. It is defined though three of the communication channels on the eastern part of
Troll West shown on Figure 5. In addition, the field is heavily faulted because the bottom of the Viking
Graben continues to sink due to underwater rifting processes. These processes have enabled
hydrocarbons to migrate upwards into reservoir rock, where they are currently produced. [2], [5]
Sognefjord formation thickness varies substantially, but on average it is about 160 m thick. The actual
reservoir, where most of the oil wells are drilled in Troll West, is located about 1560 m from the mean
sea level (MSL). MSL is on average 300 m from the sea bed to the surface. On top of the formation,
there is a large gas cap present that can extend up to 200m on TWGP. Beneath it, lies an underlying
aquifer. Right in the middle of those two phases is the thin oil rim. In the beginning of production on
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
5
Troll West, the oil column thickness on TWOP was determined to be 22m to 26m, and for TWGP
between 8m to 13m. [1], [6], [8], [9]
The Sognefjord formation is slightly tilted and consists of high permeability alternating sand bodies,
which have excellent reservoir characteristics. Besides few calcite bodies on the way, the lithology is
divided into three different sands: clean and coarse sands (c-sands) with a typical permeability of 1-30 D,
micaceous sands (m-sands) with permeability less than 600 mD, and heterolithic sands which have
alternating characteristics. The porosities for c-sands and m-sands are found 30 – 35% and 20 – 28%,
respectively. About 60% of the lithology within the oil window on TWGP is formed of coarse-grained
clean sands, and the rest is mostly mica rich fine-grained sands or heterogeneous sands. The geomodel
at the depth of 1560 m in the area of interest is seen in Figure 3. Orange and red colours on the map
represent 3-series sands, while green and grey represent 4-series and heterolithic sands respectively.
The gamma log is shown on top of the well path. The yellow and green colours on the gamma logs stand
for c-sands (gravity lower than 68 API) and m-sands (gravity higher than 68 API) respectively. [2], [3], [6]
Figure 6: Subcrop map through the geomodel (2009) in the area of well Q-12BH at 1560m TVD from the MSL. Gamma logs lie on top of the well paths. [3]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
6
Reservoir and fluid properties for the northern part of TWGP are found in Table 1. Many of these values
were determined from the PVT properties. For well 31/2-Q-12 BH, it gives an overview of oil, gas, water
and rock properties of TWGPN found in Table A.1 in Appendix A.
Reservoir parameters used for Q-12 well start up Symbol Units Value
Bubble point pressure pb Bar 159.06
Reservoir temperature TRES oC 68
Solution gas oil ratio at the start-up RSOL Sm3/Sm3 47.8
Gas density at SC ρG kg/m3 0.75
Oil density at SC ρO kg/m3 890
Water density at SC ρW kg/m3 1045
Gas formation volume factor BG m3/Sm3 0.00765
Oil formation volume factor BO m3/Sm3 1.136
Water formation volume factor BW m3/Sm3 1.017
Gas viscosity μG mPa*s 0.017
Oil viscosity μO mPa*s 1.9
Water viscosity μW mPa*s 0.45
Water compressibility βW 1/bar 4.3*10^-5 Table 1: Reservoir and fluid properties of TWGPN during the production start-up of well 31/2-Q-12BH. [10]
Production and drilling units The Troll field has three offshore operating production units: Troll A, Troll B and Troll C. Troll A operates
on Troll East. It is a large gas processing platform with vertical wells. Troll B is a concrete floater that
drains both TWOP and TWGP, and Troll C is a steel semi-floater that has most of its operating wells on
TWGP with an exception of one template, which is installed on the northern part of Troll East.
Figure 7: The infrastructure of Troll West including the subsea templates on TWOP and TWGP and the two operating platforms Troll B and Troll C. [6]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
7
The Troll C platform is also a processing facility for a well 31/2-Q-12BH. It started production in
November 1999, and has a current processing capacity of 40000 Sm3/day of oil, 40000 Sm3/day of water
and 10.3 million Sm3/day of gas. Currently, Troll C has 15 interconnected templates with 59 producing
wells, but it also receives production from four further north located templates draining Fram oil field.
These subsea templates are routed to the platform through two production lines. During well testing
period, one of those lines is used for testing only. There are two test separators installed on Troll C, but
one is used for the Fram wells. In the end, when the production gets separated, oil is sent to onshore
refinery in Mongstad and gas is moved to Kollsnes through Troll A platform. Troll B production is routed
the same way, except some gas is injected back into the reservoir. Figure 7 shows an overall picture how
all the templates on the sea bottom are connected to the platforms through production lines, and how
these platforms separate oil and gas and send it out through different pipelines.
The Troll field is also one of the most actively drilled regions in the North Sea. Currently, there are four
drilling rigs actively at work. All the infill horizontal drilling is done from the subsea templates. On
average, subsea templates have four slots for drilling, except a few have six. The use of time-lapse
seismic and geosteering during the drilling process prevent hitting other wells and increase the
probability of drilling into better producing sands, where gas gusping is less of a problem. All the wells
on Troll West are horizontal and mostly multilaterals with 2 to 4 horizontal branches. [2], [8]
Operation strategy A good strategy develops with practice and learning. Therefore, knowing the history of a field is
important. The pilot holes that were drilled into different reservoir compartments during the field
development phase showed high hydrocarbon levels. The main concern was how to produce this thin oil
rim that was found. At that point in time the entire oil zone was seen as non-profitable. It took many
years until successful outcomes were received through horizontal well technology. Afterwards, Troll oil
field became world known. In September 1995, Troll B platform operated by Hydro, started production
on the TWOP. Less than a year later oil production started also from TWGP, which had a considerably
thinner oil zone. The strategy on Troll West has originated by producing the most productive zones with
the thickest oil column first and after that the more challenging prospects. That is why production on
TWOP started before TWGP.
The most important strategy on Troll West is to minimize oil column movement during slowly
decreasing reservoir pressure. Based on reservoir shut-in information, reservoir pressure is known to
decrease about 1.5 to 2 bars per year. As gas expansion and gusping are the driving flow mechanisms in
this reservoir, it is important to observe the changes in the reservoir pressure. Pressure drops can cause
GOC to move downwards as free gas expands. Therefore, on Troll Oil field the wells are not drilled in the
center of the oil column, but rather very near the OWC.
Another challenge on such a mature field is gas gusping. Today, gas gusping on Troll West can happen
immediately after a well is put on stream. The objective for production engineers is to maximize oil
production by keeping the gas oil ratio (GOR) as low as possible for as long as possible. However, there
are some limitations - Troll B and C have gas handling capacity on the platforms. Therefore, only as
much oil can be produced as gas limiting capacity allows. In other words, production optimization goal is
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
8
to lower the total gas production of all the wells on stream, which then lowers the GOR and increases oil
production. This procedure requires good understanding of wells and their behavior in different sands.
The long term oil production on Troll West is expected to extend into the next decade. This strategy
requires extracting more oil from m-sands through infill drilling technology. Even though, oil extraction
is becoming more challenging as the pressure in the reservoir keeps decreasing and the fluid contact
depths changing, the efforts have proven success on Troll. [1], [2]
Well 31/2-Q-12 BH
Introduction The main production problems for horizontal wells are caused from uneven inflow and drawdown along
the horizontal well. For wells without inflow control, the drawdown is often larger at the heel than at
the toe, therefore the production along the wellbore is not uniform, but rather increasing from the toe
towards the heel. Likewise, the tendency for gas and water coning is much higher in the heel if such a
pressure profile is presented. It would also raise questions whether it is worth drilling very long
wellbores if the toe zone is hardly contributing to production. [11]
Well 31/2-Q-12BH has a more advanced completion design to improve production recovery. It is
completed with ICD screens and a long stinger that has three remotely controllable FCVs. These
adjustable FCVs are used to even out the drawdown and balance liquid rates from different zones.
Furthermore, such completion design decreases gas and water coning problems as adjustable FCVs help
to reduce and delay gas coning. [12]
Drilling information 31/2-Q-12BH well path is located near the central communication channel on the TWGP in the
Sognefjord reservoir formation about 1560m TVD MSL. This horizontal well path was drilled from the Q
subsea template and sidetracked from the original mother well 31/2-Q-12AH at 1602.2m MD/1480m
TVD MSL. Most of the horizontal section of this sidetrack was drilled parallel to an old well in the
southeast direction found in Figure 6. At the depth of 1559m TVD MSL, the well was leveled out in the
3CC sand. Then, 4Ac and 4 Am sands were reached, and finally the total depth (TD) was set in the 4/5
heterolithic sands at 6068m MD. The cross section of the geomodel along the drilled well path is shown
in Figure 8.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
9
Figure 8: Geological cross-section of a well Q-12BH with the main three producing zones in 3CC clean sands, 4Ac fine mica-rich sands and 4/5 heterolithic sands. [3]
Based on the drilling experience, the areal structural interpretation quality was confirmed to be good.
The minor faults seen along the well path have very little influence, but there are three bigger
surrounding faults in the area. Namely, Q-12BH is bounded by two close to parallel faults on both sides
of the reservoir running from northwest to southeast. In the end of the channel there is a sealing
boundary fault with Troll East gas reservoir.
The horizontal part of the well was drilled about 0.5m above the OWC most of the way to avoid free gas
coning problems from the gas cap. It was drilled entirely with 9 ⅟₂” drill bit from 1602.2m MD to the
total depth of 6068m MD. Oil column thickness was only observed in the landing area of the well, where
it was found to be 7.1 m. Since Q-12BH is located near the central communication region, where Troll
East and Troll West meet, the pressure communication between those two areas had to be tested. Troll
East and Troll West pressure communication was proven, but mostly through the Northern
communication channel. The central communication channel might have connecting aquifers further
below, but now it is considered a sealing boundary. As Troll East gas is depleted on a fast rate, the
pressure on that part of the field also declines faster. Therefore, reservoir pressure near the central
communication channel should be continuously observed to reassure the sealing condition; otherwise it
can affect the oil production as the fluid contact lines can move. [2], [3]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
10
Completion design
Figure 9: Example of a multilateral Q-12 BH well completion where this sidetrack has a zonal separation [8]
31/2-Q-12BH well completion design is similar to Figure 9 sidetrack design. It is separated into three
production zones based on its lithology. Zone 1 is the longest and deepest production zone in the
heterolithic sands reaching up to the toe of the well. Zone 2 is the shortest production zone running in
the 4-series sands in the middle section of the well. Zone 3 is the highest producing zone starting from
the heel and running mostly in the 3CC sands. Zonation lithology is shown in Table 6. [3]
A more detailed well completion diagram can be found in Table A.2 in Appendix A, however, some more
important Q-12BH well completion design parameters together with the depths and lengths are given in
Table 2:
Parameter (MD from the RKB) RKB to MSL = 35.5 m Zone 3 (Heel) Zone 2 (Middle) Zone 1 (Toe)
Zonal length [m] 1277 1150 1558
Blanks length [m] 286 96 12
Swellpacker position (Top MD) [m] 2059 3340 4495
Dual gauge tub-ann position (Top MD) [m] 2084 3372 4524
FCV position (Top MD) [m] 2087 3374 4527
Table 2: Completion design parameter lengths and positions [13]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
11
A short description of some completion equipment that was observed more thoroughly during the study
process is given below:
ICD-screens are known to protect the well from sand production, but they are also used to restrict the
flow rate from the well. The flow rate with ICDs is lowered by the additional pressure drop they cause.
This additional pressure drop helps to increase well’s volumetric oil recovery. In other words, ICD-
screens contribute towards a more uniform production profile and are able to lower GOR by delaying
gas breakthrough. For erosion prevention, ICDs maintain a low flow velocity through the screens. For
well Q-12BH, ICD-screens are installed throughout the horizontal well section up to 6058m MD. The
diameter of those ICDs is 7in, except for the last 1000m it changes to 6 ⅝ in. Flow resistance elements
for Q-12BH are 3.2 bars per ICD with the water flow rate of 26 Sm3/d. If the well path drops below OWC,
then blanks are installed instead of ICD screens. Figure 10 shows a picture of an ICD-screen. [14], [15]
Figure 10: Premium ICD screen used on the Troll Field [14]
The tubing/stinger runs from the well head down to 4543m MD RKB. It is fixed inside the ICD-screens by
swellable packers. There are many installations set on the stinger – most importantly, the pressure and
temperature gauges for each downhole production zone and FCVs. Outer tubing diameters through the
horizontal well path vary between 3.5in to 4.5in. [13]
Swellpackers are used to divide and isolate production zones. On Q-12BH, they are installed between
inner tubing and inside the 7” screens. Swellpackers are also installed between screens and formation
for sectioning within the zones. Figure 9 shows their placement in the zonal well and Figure 11 shows an
illustration of a swellable packer. [13]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
12
Figure 11: Illustration of cable feed-through swellable packers used in smart wells [8]
Flow control valves (FCVs) are important installations on the stinger. On Figure 12, they are installed
behind the dual gauges, and illustrated in red for zone 3, in blue for zone 2 and in green for zone 1. In
more detail, Zone 1 is operated by a hydraulic sliding sleeve (HCM+), which has only two different valve
positions, 100% open and closed. Zones 2 and 3 FCVs have different settings. They are operated by
HCM-A adjustable chokes through the same hydraulic line. In total, there are 14 positions available, but
every second position sets both of the valves 100% open. The possible valve positions include 2%, 5%,
27% and 100% openings. The diameter of the FCVs is 2.75”. The different positions of the FCVs are
found in Tables 3 and 4. [12]
FCV Zone 2 (HCM-A non-shrouded) (Middle)
FCV Zone 3 (HCM-A) (Heel)
Position % Open Flow area (in2) dVolume (mL)
Position % Open Flow area (in
2) dVolume (mL)
1 Closed 0 449
1 Closed 0 449
2 100 5.94 449
2 100 5.94 449
3 2 0.119 140
3 27 1.604 77
4 100 5.94 140
4 100 5.94 77
5 5 0.297 126
5 27 1.604 77
6 100 5.94 126
6 100 5.94 77
7 Closed 0 449
7 27 1.604 77
8 100 5.94 449
8 100 5.94 77
9 27.1 1.61 77
9 2 0.119 140
10 100 5.94 77
10 100 5.94 140
11 27.1 1.61 77
11 5 0.297 126
12 100 5.94 77
12 100 5.94 126
13 27.1 1.61 77
13 Closed 0 449
14 100 5.94 77
14 100 5.94 449 Table 3: FCV positions for Zone 2 and Zone 3 [12]
FCV Zone 1 (HCM+)
Position % Open
1 100
2 0 Table 4: FCV positions for Zone 1 [12]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
13
Pressure and temperature dual gauges are installed in the beginning of each zone in front of the FCVs
to measure annulus and tubing conditions after inflow for each zone separately. Troll wells do not have
flow meters installed, but based on the pressure gauges, flow rates can be calculated. Pressure tags
provide continuous information about the well, and all the simulation models and flow rate calculations
use them as an input. They are illustrated in yellow color on Figure 12. [13]
Figure 12: Downhole equipment and clarification of pressures
Gas cap gas lift valve is used during initial start-up, production start-up following shut down, revision
stop, etc. It is also used if the well has high water cut and low GOR/gas rate, and therefore it is not able
to flow by itself. [12]
Baker HCM-A GCGL
Position Flow area (in2) % Open
1 0 Closed
2 0.5 100
3 0.2 40
4 0.1 20
5 0.05 10
6 0.02 4 Table 5: Gas cap gas lift valve positions and flow area [12]
Synthetic permeability Both horizontal and vertical permeability logs for well Q-12BH were calculated based on rock qualities in
September 2011. The parameter, which was measured under rock quality evaluation, was the flow zone
indicator (FZI). This is a function of normalized gamma ray (GRN). The method used is based on Carmen-
Kozeny relationship and the Amaefule FZI, where permeabilities are determined from porosity logs and
normalized gamma ray. In addition, the same method is also a function of density and gamma ray log.
For Sognefjord and Fensfjord formations the equations were slightly edited. Since both horizontal and
vertical permeability logs were already calculated, the derivations of such are outside the scope of this
study. [3], [16]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
14
Both calculated permeability logs run from 1611m MD down to 6047m MD. Theoretical and simulation
models use them for productivity index calculations. The method for averaging permeabilities depends
on rock formations – how they have deposited and what type of secondary processes they have
experienced. For Q-12BH, weighted arithmetic average method is the most appropriate one to use,
because the surrounding deposits extend laterally with the well path and calculated permeability logs
are equally spaced over one meter intervals. [17]
Weighted arithmetic average
Both horizontal and vertical permeability logs were divided into zones. The separation of zones was
done by drawing a line where the log values made a sudden jump or fall. After that, the entire log was
divided into three zones based on the installed swellpackers - zone 3 (Z3), zone 2 (Z2) and zone 1 (Z1).
Since the thicknesses of the layers in a single zone varied, arithmetic permeabilities had to be weighted
first. The formula for arithmetic average permeability is
where w is the weight (length of the layer over the total length of the zone), and k is the average
permeability of a certain layer out of the many that can be present in one zone. Subscript Z stands for
the zone, and h and v stand for horizontal and vertical permeabilities. Table 6 shows the lithology based
on synthetic permeability logs, and also calculated arithmetic average permeabilities for each zone.
Zonal length Top MD (m) Bottom MD (m) Length (m) Stratigraphy Kh (mD) Kv (mD)
ZONE 3 2059 2064 5 Packer 6153 4258
1277m
2064 3031 967 3CC(2) 7282 5058
3031 3175 144 3CM(2) 199 103
3175 3340 165 3CC(3) 4771 3222
ZONE 2 3340 3345 5 Packer 1517 958
1150m
3345 3395 50 3CC(3) 4531 3022
3395 3438 43 ? (M) 67 32
3438 3551 113 3CC(3) 2681 1720
3551 3891 340 4AM(2) 447 257
3891 4172 281 4AC(2) 1913 1188
4172 4258 86 ? (M) 42 20
4258 4481 223 4AC(2) 2320 1485
4481 4495 14 4_5HETR 82 41
ZONE 1 4495 4500 5 Packer 1503 1017
1558m 4500 6058 1558 4_5HETR 1503 1017 Table 6: Penetrated lithology layers of Q-12BH and weighted arithmetic average permeabilities. [3], [13]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
15
Relative Permeability Data Relative permeability curves were changed during the study process from Corey to LET relative
permeability correlations. This data was provided by Statoil ASA Troll department, because Corey values
seemed to be wrong. For LET curve calculations, reservoir properties had to be upscaled, and adjusted
to match single and two-phase historic production. Upscaling relative permeabilities is difficult because
they depend on saturations, and some scientists still debate about this method. Even though, the
calculations of LET relative permeabilities are outside the scope of this study, they were a good match
for a well Q-12BH. Thus, standard type of unnormalized LET family of correlations is used. All the
unnormalized basic imbibition data is provided for gas and oil, and oil and water relative permeabilities
in Table A.3 in Appendix A. Figure 13 and 14 show a graphical display of this data. [18]
Figure 13: LET relative permeability curves for oil and water with respect to water saturation
Figure 14: LET relative permeability curves for gas and oil with respect to gas saturation
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0.0 0.2 0.4 0.6 0.8 1.0
Re
lati
ve p
erm
eab
iliti
y, K
r,α
Water saturation, Sw
Krw
Kro
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0.0 0.2 0.4 0.6 0.8 1.0
Re
lati
ve p
erm
eab
ility
, K,rα
Gas saturation, Sg
Krg
Kro
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
16
PVT properties The data used for Troll field modeling is gathered from the PVT report and Special Core Analysis (SCAL)
data. This report includes a list of pilot wells that were drilled and measured for gas, oil and rock
reservoir properties. The closest pilot well for Q-12BH was 31/2-3. It was drilled in the northern part of
TWGP. Based on the changing reservoir pressures, one can interpolate viscosity (μ), formation volume
factor (FVF) and solution gas (RSOL) for Q-12BH. Table A.1 in Appendix A provides PVT data for TWGPN.
[10]
Procedure into simulations and theoretical methods
Well testing Production data is collected via well testing and it is used as a reference for constructing simulations.
Wells at Troll are normally tested at least once during a six month period. New wells and wells in
development are tested more frequently. Testing is used for production verification. Since there are no
flow meters installed on the individual Troll C and B wells, testing them helps to tune the well allocation
and optimize oil production. Currently, there are 14 well test results available for Q-12BH, but only the
first one of them is relevant in this study. The reason for using only that particular test data is explained
more thoroughly in the upcoming text. For comparative purposes between simulation models and well
test results, few of the parameters need to be calculated and explained in more detail. The following
subparagraphs will focus on these parameters.
Reservoir pressure
Reservoir pressure during the first well test is extrapolated from the well shut-in data gathered from
Aspen Process Explorer software. Table B.1 with all these values is found in Appendix B. For better linear
relationship, only the first four shut-in times are used. The time period for these four data recordings is
roughly half year and seen graphically in Figure 15. This graph represents shut-in pressures with respect
to the number of days since Q-12BH was put on stream. Since the trend lines are matching well,
reservoir pressure during day 6 can be extrapolated by the equations shown in the legend.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
17
Figure 15: Reservoir pressure decrease as a function of time.
Gas inflow
Gas coning is unpredictable, it may start immediately after a new well is put on stream or it may take
months/years for the gas cone to reach the well. As the field matures and the oil column becomes
thinner, gas breakthrough will generally occur at an earlier stage in a wells life. This scenario makes well
simulations a challenge. Once the cone reaches the well, it will be more difficult to model and
understand well’s behavior.
In general, there are three different types of gases being produced from the well. They all vary slightly in
their chemical compositions, but it is still difficult to know exactly the fraction of each gas. A large gas
cap on top of the oil column is called free gas. Free gas enters into the well during gas coning. High free
gas production diminishes oil flow rate, and therefore production engineers try to avoid producing free
gas for as long as possible. In some cases like starting up a high water cut well, free gas inflow is
required, but then it is done through the gas cap gas lift valve, and not from the zones.
The second type of gas being produced is solution gas. Solution gas cannot be separated from oil at
reservoir conditions. It remains in the oil as long as the pressure and temperature conditions are
unchanged. During production process, the pressure in the wellbore keeps decreasing as oil travels
towards the surface and such a decrease helps solution gas to bubble out from the oil. Solution gas rates
are calculated and found from the PVT data in Table A.1 in Appendix A. For calculations, solution GOR
needs to be interpolated from the PVT data based on the actual reservoir pressures and then, solution
gas rate can be determined by multiplying solution GOR with oil flow rate in standard conditions.
Thirdly, there is riser gas injection, which is injected to the production line near the sea bed to push the
oil column upwards. This injection technique is also used during starting up high water cut wells. Thus,
based on injection rate and calculated solution gas rate, a rough estimate of free gas can be determined
as well tests provide total gas inflow rate.
y = -0.0043x + 136.33 R² = 0.9916
y = -0.007x + 136.59 R² = 0.9979
y = -0.009x + 136.49 R² = 0.9995
134.8
135.0
135.2
135.4
135.6
135.8
136.0
136.2
136.4
0 25 50 75 100 125 150 175 200
Re
serv
oir
Pre
ssu
re [
Bar
]
Number of days since well start up
Zone 3
Zone 2
Zone 1
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
18
In the end, for well productivity calculations, gas inflow needs to be simplified. A few important
assumptions need to be made. The first simplification excludes free gas production from the well as
there is no gas saturation log present. Without gas saturation, it is extremely difficult to predict gas
behavior across different zones. Hence, this assumption can only be relevant when the gas cone has not
yet reached the wellbore, and the flow into the well is a two-phase flow of oil and water. Based on well
testing data, this situation does not exist. The first well test, done only six days after Q-12BH was put on
stream, shows some free gas production. Since this is calculated by subtracting solution gas and riser gas
from the total gas rate, it is considered to be a value in that range. However, since free gas rate is low, it
is still worth trying to match the first well test with a two-phase simulation model excluding gas as long
as liquid rates and downhole pressures can be matched.
First well test
The first well test was run six days after the well was put on stream in September 11th, 2011. It was a
twelve hour long test with the following zonal FCV openings: 5% opened for Zone 3, 27% opened for
Zone 2 and 100% opened for Zone 1. As a reminder, these valves are located on the stinger and have
adjustable settings for production optimization. All the measured pressures, flow rates and ratios for the
first well test are found in Table 7. This well test data shows that there is already some gas influx present
in the well, but it also includes solution gas since it all flows together into the same separator. In the
separator all the rates can be determined. There is also an illustration shown on Figure 16 with all the
DHGs, reservoir and wellhead pressures, and flow control valve opening positions. This data is later
compared with the simulation models to conclude whether these FCV positions were the most optimal
ones to start up the production on Q-12BH. [19]
31/2 Q-12 BH WELL TEST #1
Start Stop Duration
16.09.2011 01:14 16.09.2011 13:14 12:00:00
ZONAL FLOW CONTROL VALVE (FCV) OPENINGS (HEEL → TOE)
Zone 3 Zone 2 Zone 1
5 % 27 % 100 %
ANNULUS PRESSURE (DHG) [Bar]
Zone 3 Zone 2 Zone 1
134.6 134.2 135.2
TUBING PRESSURE (FBHP) [Bar]
Zone 3 Zone 2 Zone 1
125.4 133.1 135.04
FLOW RATES, WATER CUT AND GAS OIL RATIO
QO, ST [Sm3/d] QW, ST [Sm
3/d] QG, ST [Sm
3/d]
1443 933 83784
QLIQ, ST [Sm3/d] GOR Water cut
2376 58.1 39.3
Table 7: 31/2-Q-12 BH first well test data (16.09.2011) [19]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
19
Figure 16: First well test DHG pressure data together with reservoir and wellhead pressures, and FCV openings.
Discussion of flow rates in different well tests All the 14 well tests experienced gas influx. The least amount of gas was measured during the first well
test found in Table B.2 in Appendix B. First of all, solution gas rate was subtracted from the total gas
influx found by well tests, and then it was multiplied by gas FVF. Free gas rate during the first well test
was found to be 113 Rm3/d, which formed only 4% of the total influx. For modeling purposes, this 4% of
free gas inflow is neglected for simplicity in order to use the two-phase liquid model. In Figures 17 and
18, well test comparisons with respect to reservoir flow rates and contribution of the phases at DH
conditions are shown respectively.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
20
Figure 17: Reservoir flow rates of all the well tests for different phases.
Figure 18: Phase flow contribution comparison with all the well tests.
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
WT1 WT2 WT3 WT4 WT5 WT6 WT7 WT8 WT9 WT10WT11WT12WT13WT14
Re
serv
oir
flo
w r
ate
, Qα [
Rm
3 /d
]
Well tests
Water
Free gas
Oil
35 37 39 37 32 36
30 24
7
29 20 17 16
22
4
16 15 20 22
28 44 58 83
53 69 73 75 65
61
47 46 42 46 36
26 18
10 18
12 10 9 13
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Co
ntr
ibu
tio
n o
f p
has
e f
low
Number of days since well start up
Oil
Free gas
Water
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
21
Simulation Modeling There are three analytical simulation models built to resemble the first well test behavior.
1. NETool model with built-in steady-state Joshi inflow equations [21]
2. Theoretical steady-state Joshi PI model for horizontal wells [22]
3. Muskat’s analytical PI model for horizontal wells [20]
First, NETool model is used to determine the productivity index of each zone. Then, the two other
methods are used to determine the difference between numerical NETool model and two other
analytical models.
Objectives NETool model result should resemble the first well test result. Thus, parameters such as completion
string design, correct FCV openings, saturation, permeability and hydrostatic reservoir pressure logs,
PVT data and relative permeabilities need to be set into NETool just like they were during the time of
the first well test. After set-up, tubing and annulus pressures are tried to be matched with the first well
test pressures for each zone. These pressures are not average zonal pressures. They are recorded at the
DHG sensors and therefore NETool pressures should be matched at the same location. The exact
measured depths of all the DHGs are found in Table 2. Then, flow rates and water cut should be
matched with the same data. Gas rate will be different, because NETool only calculates solution gas rate.
Once there is a close match with the first well test, NETool pressures will be tested by fully opening all
the FCVs, and comparing annulus and tubing pressures with the pressure tags. If these pressure tag
values are similar or almost matching, then NETool simulation model is considered reliable and
independent of FCV positions. In the end, NETool model is tested with the two analytical models to
determine the difference with productivity indices.
Parameters NETool is software used for numerical simulation modeling. Horizontal well productivity index in NETool
is calculated by a steady-state Joshi homogeneous flow equation. Homogeneous flow equation, which is
common in the oil industry, uses average properties of the phases present in each of the segments. A
segment in NETool is set to 12 meters with a few exceptions in the beginning of every zone as some of
the shorter equipment is modeled right there. This Joshi model assumes constant reservoir pressure
over time with constant reservoir pressure boundaries. It also assumes that the well is centered in the
middle of the reservoir, and drains an ellipsoid shape in the horizontal plane and a thickness of the layer
in the vertical plane. Table 8 gives some of the average parameters used for flow rate calculations and
productivity indices in NETool and in analytical models. These parameters are discussed more
thoroughly in the following text. [21]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
22
Parameter Symbol Units Zone 3 Zone 2 Zone 1 Comments
Reservoir dimensions
Length of a zone LZ m 1277 1150 1558 Fixed
Total length of the zones LTOTAL m 3985 Fixed
Blanks in each zone LB m 286 96 12 Fixed
Width of the reservoir wR m 120 120 120 Assumption
Thickness of the reservoir h m 20 20 20 Assumption
Wellbore radius rwb m 0,12 0,12 0,12 Fixed
Pressures
Reservoir pressure pRES Bar 136.22 136.48 136.38 NETool FCVs 100% open
Sandface pressure pSF Bar 135.88 135.81 135.65 NETool FCVs 100% open
Drawdown (pRES - pSF) Δp Bar 0.34 0.67 0.72 Calculated
Reservoir properties
Horizontal permeability (Synt.) kH mD 6134 1510 1503 Calculated
Vertical permeability (Synt.) kV mD 4245 954 1017 Calculated
Oil viscosity (PVT) µO cp 1.903 1.901 1.902 Interpolated
Water viscosity (PVT) µW cp 0.45 0.45 0.45 Fixed
Oil formation volume factor (PVT) BO Rm3/Sm
3 1.136 1.136 1.136 Interpolated
Water formation volume factor (PVT) BW Rm3/Sm
3 1.017 1.017 1.017 Fixed
Relative permeability data
Average effective saturation per zone Sw - 0.462 0.456 0.594 Averaged from a log
Relative permeability of oil kro - 0.122 0.130 0.024 Calculated from Sw log
Relative permeability of water krw - 0.050 0.047 0.157 Calculated from Sw log
Oil mobility λo 1/cp 0.06 0.07 0.01 Calculated
Water mobility λw 1/cp 0.11 0.10 0.35 Calculated
Total mobility (no gas) λ 1/cp 0.17 0.17 0.36 Calculated
Table 8: Parameters used for productivity indices calculation [10], [12]
Fixed values are simply unchangeable and usually known after the completion is set. They are the most
reliable parameters. For Q-12 BH, fixed values are:
Zonal length and the total length
Blanks of the zone
Wellbore radius
Water viscosity
Water formation volume factor
Calculated values could vary, if they are not calculated from the fixed values. In Q-12BH, calculated
values are:
Drawdown
It is calculated by subtracting the average sandface pressure from the hydrostatic reservoir
pressure. Both pressures vary with respect to the segments in NETool.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
23
(Horizontal and vertical) synthetic permeability
Since synthetic permeabilities are calculated from the log values that only reach a certain radius
from the wellbore, overall permeability of the zone could vary.
Relative permeabilities
These are dependent on saturations, and saturation log is calculated without including gas.
(Oil and water) mobility
Both of them are based on relative permeability curves, which in addition depend on
saturations.
Interpolated values depend on the accuracy of reservoir pressures. They are interpolated from the PVT
data and for Q-12BH, they are the following:
Oil viscosity
Oil formation volume factor
Averaged values could have a large variation depending on their discrepancies. In Q-12BH, averaged
values are:
Effective saturation
This is a log calculated from Archie equations.
Assumed values are the parameters most difficult to determine. Some reservoir geometry values for Q-
12BH are assumed:
Reservoir thickness
Reservoir width
These last two parameters are described in more detail since they were determined having the least
amount of references.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
24
Reservoir geometry
Figure 19: NETool reservoir geometry from the top and front view including yellow streamlines [21]
In NETool, reservoir widths and thicknesses were tested to determine how these two parameters affect
pressures and flow rates. The intension was to match NETool with the first well test data. Many
simulations were run in NETool only by changing the thickness and width of the reservoir zones. As a
result, Table 9 was created. The yellow columns indicate the first good pressure match going from lower
to higher thickness values. Figure 20 shows it graphically.
Thickness (m)
RESERVOIR GEOMETRY w/h ratio Width (m)
0 120 200 300 400 500 6.18
10 2185 2151 2117 2087 2059
20 2203 2185 2166 2151 2132 6
30 2210 2197 2183 2171 2159 6.67
40 2212 2203 2192 2182 2173
50 2214 2206 2197 2189 2181 6
60 2215 2206 2201 2194 2187 6.67
70 2215 2210 2203 2197 2191
80 2215 2210 2204 2199 2194
90 2215 2211 2206 2201 2196 5.56
100 2215 2211 2207 2202 2198
110 2215 2212 2207 2203 2199
120 2215 2212 2208 2204 2200
130 2215 2212 2210 2205 2201
140 2215 2212 2209 2205 2202
150 2214 2212 2209 2206 2203
160 2215 2212 2209 2206 2203 Table 9: Reservoir width and thickness sensitivities.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
25
Figure 20: Simulated flow rates with varying reservoir geometry
Figure 20 shows the behavior of changing flow rates as a function of reservoir geometry. Around 2200
Sm3/d, NETool DHG pressures are closely matched with the first well test pressures. Hence, the flow
rates at these pressures were used to calculate the ratio of width to thickness for Q-12BH reservoir. It
was found to be 6, and used as a reference to determine reservoir geometry. However, the width and
thickness were still unknown as they could vary having the same ratio. This question was solved by
reading “Advanced well optimization in thin oil rim reservoirs” report that had the following statement
about the lateral extent of Q-12AH (mother well), which well path runs parallel to Q-12BH trajectory:
There were no natural structural limitations sufficiently close. … The lateral extent of the box model is
adjusted to cover a typical drainage radius of 60 m for the horizontal Troll wells and to incorporate the
nearby faults. [1]
Based on this calculated ratio and the text material above, reservoir geometry was determined.
Reservoir width, which is equal to two times the length of a drainage radius, is equal to 120m, and the
thickness is 20m. Even though, reservoir geometry was now finalized and set the same for every zone in
the reservoir, it is still an assumption. In reality, different zonal permeabilities would cause drainage
radiuses to be different.
2040
2060
2080
2100
2120
2140
2160
2180
2200
2220
2240
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160
Flo
w r
ate
, Q, (
Sm3
/d)
Reservoir thickness, h (m)
width 120m
width 200m
width 300m
width 400m
width 500m
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
26
NETool modeling The following paragraphs describe the theory and equations how NETool calculations are set up. The
reservoir model used for this horizontal well is AMAP2013-PRED-3FLUX-MA with a starting date of
01.04.2012. It is an Eclipse model made by the Statoil ASA reservoir engineers and entered into NETool.
First of all, horizontal well path going from the heel to the toe needs to be entered into NETool.
Geographic coordinates together with measured and true vertical depths make up this well path.
Entering the path is the foundation for modeling completions, where many other reservoir parameters
are required. Since the actual well was completed with 12m string pipes, the segments in NETool were
also set to 12m intervals. That made hole and completion design modeling easier. NETool completion
design is found in Table C.1 in Appendix C. [13]
For every segment, the inflow of every component (phase) is calculated separately by the following
formula
[1]
where the letter indicates different phases – oil, solution gas and water. is the mobility of the
phase. is the transmissibility and is the pressure drop from reservoir to sandface. [21]
For zonal productivity indices, one should understand how mobility and transmissibility influence the
final result, because these terms vary over every segment when specific productivity index, , is
calculated
[2]
Transmissibility and mobility
Transmissibility forms part of PI modeling. It is calculated by NETool based on upscaled permeabilities
and other geometric parameters. Every segment has the following formula
(
)
(
) [3]
where √
There are many parameters in this equation that do affect the inflow and productivity index. The most
influential ones are horizontal permeability that varies between segments; then influence of anisotropy
factor ; and lastly both assumed geometry values: reservoir width and thickness, which are considered
the same for all the three zones.
Another important term in flow rate calculations is phase mobility:
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
27
[4]
For flow rate calculations, transmissibility is multiplied with the difference between reservoir pressure
and sandface pressure, and the mobility of each phase separately seen in Equation (1). That results in
three different flow rates of gas, oil and water at reservoir condition. Next, these separate phase flow
rates are added together to calculate the total flow rate per segment. Then, the total flow rate per
segment is divided by the pressure drop between reservoir pressure and sandface pressure resulting in
specific productivity index found in Equation (2). [21]
NETool Results Table 10 shows the best simulation model results when matching the first well test data.
Pressures in NETool (FCV openings Z3 = 5%, Z2 = 27%, Z1 = 100%)
Parameter Symbol Units Zone 3 Zone 2 Zone 1
Reservoir pressure pRES Bar 136.22 136.48 136.38
Sandface pressure pSF Bar 136.09 135.76 135.52
Average annulus pressure pANN Bar 135.76 135.26 135.25
Annulus pressure (at DHG) pANN_DHG Bar 134.86 133.70 135.24
Average tubing pressure pTUB Bar 128.72 133.93 135.22
Flowing tubing hole pressure (at DHG) pTUB_DHG Bar 125.40 132.92 135.03
Drawdown (pRES - pSF) Δp Bar 0.14 0.72 0.86
Pressure drop across ICDs (pSF - pANN) ΔpICD Bar 0.32 0.50 0.26
Pressure drop across stinger (pANN - pTUB) ΔpSTI Bar 7.04 1.33 0.03
Flow rates in NETool (FCV openings Z3 = 5%, Z2 = 27%, Z3 = 100%)
Oil rate QO Sm3/d 1326
Water rate QW Sm3/d 877
Gas rate QG Sm3/d 63362
Total liquid rate (ST condition) QLIQ Sm3/d 2203
Gas to oil ratio (solution gas) GOR % 47.8
Water cut WC % 39.8
Total liquid rate per zone (ST condition) QIN,LIQ_ST Sm3/d 615 739 848
Oil rate per zone QOIL,ST Sm3/d 388 556 382
Water rate per zone QWAT,ST Sm3/d 227 184 466
Gas rate per zone QGAS,ST Sm3/d 18526 26553 18283
Total influx per zone (DH condition) QIN,DH Rm3/d 673 821 909
Oil rate per zone QOIL,DH Rm3/d 440 630 434
Water rate per zone QWAT,DH Rm3/d 232 187 474
Gas rate per zone QGAS,DH Rm3/d 1 4 1
Inflow contribution per zone %Q % 28 34 38
Productivity Index J Sm3/d/bar 4523 1030 985
Table 10: Simulation model results of the first well test
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
28
A comparison of NETool simulation model results and the first well test data is found in Table 11. The
following parameters are compared: DHG pressure measurements, liquid inflow rates and water cut.
Table 11: NETool and well test results data comparison
This was the best match between the first well test and NETool simulation model in terms of these
parameters. Reservoir pressure calculated through extrapolation of well shut-ins gives slightly higher
values than reservoir pressure calculated by hydrostatic pressure log used in NETool. The difference is
less than 0.1 bars for all the three zones. Hydrostatic pressure calculation is explained more thoroughly
under theoretical steady-state Joshi’s model. NETool reservoir pressure can be found in Figure 21.
Overall, the tubing pressures and annulus pressures at the DHG sensors have a small difference. The
most difficult zone to match the pressures was zone 2, because neither tubing nor annulus pressures
Comparisons Zone 3 Zone 2 Zone 1
Reservoir pressure [Bar]
Well test (shut-in) 136.31 136.55 136.44
NETool (hyd stat P) 136.22 136.48 136.38
Difference (Bar) 0.09 0.07 0.06
Annulus pressure at DHG [Bar]
Well test 134.6 134.2 135.2
NETool 134.9 133.7 135.2
Difference (Bar) 0.3 0.5 0
Tubing pressure at DHG [Bar]
Well test 125.4 133.1 135.0
NETool 125.4 132.9 135.0
Difference (Bar) 0 0.2 0
Oil flow rate in ST [Sm3/d]
Well test 1443
NETool 1326
Difference 8.11 %
Water flow rate in ST [Sm3/d]
Well test 933
NETool 877
Difference 6.03 %
Total flow rate in ST [Sm3/d]
Well test 2376
NETool 2203
Difference 7.29 %
Water cut in ST [%]
Well test 39.3
NETool 39.8
Difference 1.36 %
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
29
gave an exact result. NETool annulus and tubing pressure graph is given in Figure 22. Notice how the
pressures have a sudden change due to zonal separations.
Figure 21: NETool reservoir pressure and completion diagram.
Figure 22: NETool sandface (blue), annulus (purple) and tubing (red) pressures with respect to the length of the well. Zonal separation is shown with dashed oval shaped circles.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
30
In terms of flow rates, NETool oil flow rate in standard condition is off by 8.11 % and water flow rate is
off by 6.03 % in comparison to the first well test. Hence, the total liquid rate is 7.29 % lower from the
total well test liquid rate. On the other hand, water cut varied only by 1.36 %.
In the next step, all the downhole FCVs in the same NETool model were fully opened. This was done to
compare productivity indices when FCV positions are different and for later comparisons with the other
two theoretical models. NETool simulation results with three 100% open FCVs are found in Table 12.
Pressures in NETool (All FCVs are 100% opened)
Parameter Symbol Units Zone 3 Zone 2 Zone 1
Reservoir pressure pRES Bar 136.22 136.48 136.38
Sandface pressure pSF Bar 135.88 135.81 135.65
Average annulus pressure pANN Bar 133.66 135.36 135.46
Annulus pressure (at DHG) pANN_DHG Bar 128.15 133.97 135.46
Average tubing pressure pTUB Bar 129.97 134.42 135.41
Flowing tubing hole pressure (at DHG) pTUB_DHG Bar 126.39 133.61 135.29
Drawdown (pRES - pSF) Δp Bar 0.34 0.67 0.72
Pressure drop across ICDs (pSF - pANN) ΔpICD Bar 2.22 0.45 0.19
Pressure drop across stinger (pANN - pTUB) ΔpSTI Bar 3.69 0.94 0.05
Flow rates in NETool (All FCVs are 100% opened)
Oil rate QO Sm3/d 1879
Water rate QW Sm3/d 1168
Gas rate QG Sm3/d 89804
Total liquid rate (ST condition) QLIQUID Sm3/d 3047
Gas to oil ratio (solution gas) GOR % 47.8
Water cut WC % 38.3
Total liquid rate per zone (ST condition) QIN,LIQ_ST Sm3/d 1604 696 747
Oil rate per zone QOIL,ST Sm3/d 1014 524 341
Water rate per zone QWAT,ST Sm3/d 590 172 406
Gas rate per zone QGAS,ST Sm3/d 48455 25050 16299
Total influx per zone (DH condition) QIN,DH Rm3/d 1771 773 801
Oil rate per zone QOIL,DH Rm3/d 1145 594 387
Water rate per zone QWAT,DH Rm3/d 601 175 413
Gas rate per zone QGAS,DH Rm3/d 24 3 1
Inflow contribution per zone %Q % 53 23 24
Productivity Index J Sm3/d/bar 4760 1039 1030
Table 12: NETool simulation model results with fully opened downhole FCVs.
Notice that the difference between productivity indices in Table 10 and Table 12 is small, but FCV
openings do affect the inflow contribution per zone. Throughout Q-12BH production period, this well
was operated only two days with three 100% opened FCVs. The pressure tag values of these two days
are shown in Table 13 and compared with NETool pressure calculations in Table 14. If these values are
similar, then NETool simulation model is considered reliable.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
31
Date PANN_Z3 PANN_Z2 PANN_Z1 PTUB_ Z3 PTUB_Z2 PTUB_Z1
23-Jan-12 128.08 133.64 134.35 126.90 133.40 134.46
24-Jan-12 128.05 133.62 134.35 126.85 133.39 134.45
Average 128.06 133.63 134.35 126.87 133.39 134.46
Table 13: DHG pressures of the actual well running with 100% opened FCV positions for two consecutive days
CASE PANN_Z3 PANN_Z2 PANN_Z1 PTUB_ Z3 PTUB_Z2 PTUB_Z1
Actual 128.06 133.63 134.35 126.87 133.39 134.46
NETool 128.15 133.97 135.46 126.39 133.61 135.29
Difference (Bar) 0.09 0.34 1.11 0.49 0.22 0.84
Table 14: Pressure tag recordings in January 2012 compared with NETool simulation model results
There is a small difference between NETool and the actual situation, because in January 2012 when the
actual pressure tags where measured, the well Q-12BH was experiencing a much larger gas influx.
Therefore, actual DHG annulus and tubing pressures should be lower than NETool calculated pressures.
Just like pre-assumed, the difference seems to be in correlation with the NETool results where only
solution gas is present.
The next objective is to determine the pressure drop across the ICD-screens for the accuracy of sandface
pressures. NETool calculates sandface pressures, but theoretically they could also be calculated by
adding a pressure drop across the ICD-screens to an average zonal annulus pressure in NETool.
Theoretical pressure drop across the 3.2 bar ICD-screen
Pressure drop across the 3.2 bar single ICD-screen is calculated by Equation [5]:
(
) ⁄
(
)
[5]
where and are multiphase densities and viscosities calculated by downhole flow rate
volumetric fractions found in NETool and shown in Table 16. is the total liquid rate of a zone at
reservoir condition, and the following three parameters in Table 15 are Troll field specific calibrated
coefficients:
Parameter Value Units
aSICD 3.46E-03 Bar/(Rm³/day)²
ρ_cal 1000.3 kg/m³
µ_cal 1.45 cP Table 15: Troll field ICD-valve and screen calibrated coefficients
Table 16 gives DH flow rates with two different FCV openings:
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
32
Segments Opening
Total Influx DH
Oil Fraction
Gas Fraction
Water Fraction
Oil flow rate
Gas flow rate
Water flow rate
[Rm³/day] αo αg αw [Rm³/day] [Rm³/day] [Rm³/day]
ZONE 3 100 % 1771 64.68 % 1.38 % 33.93 % 1145 24 601
ZONE 2 100 % 773 76.89 % 0.44 % 22.68 % 594 3 175
ZONE 1 100 % 801 48.33 % 0.09 % 51.58 % 387 1 413
ZONE 3 5 % 673 65.37 % 0.21 % 34.41 % 440 1 232
ZONE 2 27 % 821 76.72 % 0.49 % 22.79 % 630 4 187
ZONE 1 100 % 909 47.75 % 0.12 % 52.14 % 434 1 474 Table 16: DH flow rate phase fractions with two different FCV openings
Table 17 shows calculated mixed densities and viscosities. It also gives an average theoretical pressure
drop across a single ICD-screen in all the three zones. From the screen tally of Q-12BH, Zone 3 includes
80 x 7” ICD-screens, Zone 2 includes 86 x 7” ICD-screens, and Zone 1 includes 44 x 7” ICD-screens and 82
x 6 ⅝” ICD screens, which makes a total of 126 ICD-screens in Zone 1. The total number of ICD- screens
in the entire well is 292. [23]
Fluid properties at reservoir pressure 136.3 Bar and 68 oC
Parameter Zone 3 Zone 2 Zone 1 Units
Oil density 890.0 kg/m³
Water density 1045.0 kg/m³
Gas density 0.75 kg/m³
ρ_mix (3*100% opened FCVs) 930.3 921.3 969.1 kg/m³
ρ_mix (5%,27%,100% opened FCVs) 941.4 921.0 969.8 kg/m3
Oil viscosity 1.903 1.901 1.902 cP
Water viscosity 0.45 cP
Gas viscosity 0.017 0.017 0.017 cP
µ_mix (3*100% opened FCVs) 1.38 1.56 1.15 cP
µ_mix (5%,27%,100% opened FCVs) 1.40 1.56 1.14 cP
Average pressure drop across a single ICD-screen with two different FCV openings
Length of the zone 1277 1150 1558 m
Number of ICD-screens per zone 80 86 126
Pressure drop across ICDs (3*100% opened FCVs) 1.59 0.27 0.13 Bar
Pressure drop across ICDs (5%,27%,100% opened FCVs) 0.23 0.30 0.17 Bar Table 17: Average theoretical pressure drop across a single ICD-screen in all three zones
Thus, Table 18 compares NETool simulated average pressure drop across the single ICD-screen and the
theoretical pressure drop values calculated in Table 17.
Pressure drop across the ICD-screens
CASE Units Zone 3 Zone 2 Zone 1
FCV openings % 100 100 100
NETool Bar 2.22 0.45 0.19
Theoretical Bar 1.59 0.27 0.13
Difference % 28 40 30
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
33
FCV openings % 5 27 100
NETool Bar 0.32 0.50 0.26
Theoretical Bar 0.23 0.30 0.17
Difference % 29 41 36 Table 18: Variation between NETool and theoretical pressure drop across a single ICD-screen
There is a difference between NETool and theoretical pressure drop across the ICDs, but it has a similar
trend with respect to zones. This difference in bars is not large, and therefore one can consider that the
actual sandface pressure is about the same as in NETool. Hence, NETool model is considered reliable.
Analytical Joshi’s and Muskat’s PI Models
The next two methods are Joshi’s analytical steady-state inflow method for horizontal wells assuming an
elliptical reservoir, and Muskat’s analytical streamline model method assuming a box-reservoir. Both
methods are described in following text.
Calculations with steady-state Joshi horizontal well PI model Theoretical steady state Joshi model is set up to calculate reservoir inflows and productivity indices for
the three separate zones of the well Q-12BH. Therefore, Joshi’s theoretical model drains three ellipsoids
in the horizontal plane through all the zones.
Reservoir pressure is averaged NETool pressure, which is calculated for each segment and derived from
hydrostatic pressure Equation (6)
[6]
where is the calculated reservoir pressure of each separate segment, is the interpolated
reservoir pressure based on well shut-ins at the heel pressure gauge, is the density of oil, is the
gravity, is the fixed true vertical depth of the heel pressure gauge, and is the varying
true vertical depth of each segment.
Drawdown is calculated by taking the difference between an average reservoir pressure and an average
sandface pressure found in NETool. For flow calculations in standard condition, Joshi’s model for
horizontal wells uses the following Equation (7):
[ √ ⁄
]
(
)
for [7]
⁄ [
√
⁄]
, √
, √ and √ ⁄
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
34
where subscript indicates the phase; is the calculated horizontal well flow rate in bbl/d converted
to Sm3/d; and are the horizontal and vertical permeabilities respectively in D converted to m2; is
the thickness of the reservoir in m; is the drawdown from the reservoir boundary up to wellbore in
bars; is the phase viscosity in cp converted to bars*d; is the phase formation volume factor in
Rm3/Sm3; is half the major axis of a drainage ellipse in m; is half of the minor axis of drainage ellipse
in m; is the length of the zone in m; is the dimensionless influence coefficient for anisotropy; and
is the wellbore radius in m. All the parameters described here are found in Table 8. Reservoir geometry
model is shown in Figure 23. [22]
Figure 23: Reservoir geometry model for the three-zone horizontal well
Equation (7) calculates the flow rates of two different phases, oil and water, separately. The difference
with a single phase Joshi formula lies in mobility term. Mobility is a multiplier of the equation formed by
relative permeability term in the numerator, and viscosity term in the denominator. For permeability,
the zonal weighted averages based on synthetic permeability logs were calculated and used in the same
equation. In addition, the influence coefficient for anisotropy was calculated by permeability averages.
In terms of reservoir geometry, Equation (7) considers a constant pressure boundary around the
horizontal drainage radius, and that is how the steady state condition is met. On top and bottom of the
reservoir, there is no-flow boundary and the well is assumed to lie in the center of the reservoir. Thus,
this equation is highly dependent on reservoir geometry parameters like thickness, h, drainage radius,
reH, zonal length, L, and half the major axis of drainage ellipse, a. Since Rend from Figure 19 is very small,
the overlap of the ellipses is negligible.
However, this method is set up just like NETool, except it does not have segments in the zones, but
instead it uses a single average values for each zone. The difference between analytical Joshi’s inflow
model and NETool Joshi’s inflow model is shown in Appendix D. [21], [22]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
35
Steady state Joshi horizontal well analytical simulation results
Joshi's Theoretical Method (SPE 15375 eq.10a for two phase situation)
Influence of anisotropy β - 1.20 1.26 1.22
Horizontal drainage radius reH ft 643 611 710
Half the minor axis of a drainage ellipse b ft 197 197 197
Half the major axis of a drainage ellipse a ft 2103 1897 2563
Distance from the end of the zone until ellipse boundary Rend ft 9.2 10.2 7.6
First term in the denominator ln[(a+...)] - 0.094 0.104 0.077
Second term in the denominator βh/LZ*ln(...) - 0.087 0.102 0.072
Denominator - - 0.18 0.21 0.15
Numerator - rB/d 2466 1192 2688
Oil flow rate qO rB/d 5002 2301 637
Water flow rate qW rB/d 8659 3492 17411
Total liquid rate qH rB/d 13660 5793 18048
Zonal contribution QZ % 36 15 48
Rates in Standard condition
Oil flow rate qO STB/d 4403 2025 561
Water flow rate qW STB/d 8514 3434 17120
Total liquid rate qH STB/d 12917 5459 17681
Total flow rate QLIQ STB/d 36056
Productivity Index of a zone J STB/d/psi 2643 562 1681
Conversion to SI units
Oil flow rate qO Sm3/d 700 322 89
Water flow rate qW Sm3/d 1354 546 2722
Flow rate into horizontal well qH Sm3/d 2054 868 2811
Total flow rate QLIQ Sm3/d 5732
Water cut WC % 80.62
Productivity Index of a zone J Sm3/d/Bar 6094 1295 3877
Table 19: Steady state Joshi horizontal well analytical simulation results
Muskat’s analytical PI calculation method
Assumptions of the method
This anisotropic reservoir has a box-shaped geometry with two constant horizontal pressure boundaries
and two vertical no-flow boundaries. The well is centralized between all the boundaries and could be
visualized as a sink. The flow into the well is two -phase steady-state flow through a reservoir. There is
no gas influx, and the two liquid phases flowing together are calculated separately. The streamlines of
the well are have a specific shape shown in Figure 24.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
36
Figure 24: A box-shaped reservoir seen as a sink that drains water and oil (front view - the well runs into the page)
Theory
As known, well Q-12BH has three producing zones in the wellbore. The objective of the study is to
understand the production of each zone separately, and therefore every zone is treated on its own. This
method calculates specific PIs, JS,(x) of the zone. Specific PI has units Sm2/d/bar, and it needs to be
multiplied by specific zonal length for the actual PI values.
[8]
The specific zonal inflow, , has units Sm3/d/m. For the normal inflow of the zone, specific inflow needs
to be multiplied by the length of the zone just like specific PI. The sum of all reservoir zone inflows
equals the total production of the well.
[9]
The governing equation for PI is based on a classic flow potential of a well per unit length expression.
This this case unit length is zonal length. The principle analytical function describing two-dimensional
flow of incompressible fluid has two parts: real part and imaginary part. The real part describes potential
distribution, whereas its imaginary part describes the stream function. For PI determination, only the
real part is required. Thus, pressure Equation (10) is explained and derived in the Appendix E. [20], [24]
(
) [10]
Here and are the scaled coordinates that count for anisotropy just like specified reservoir
coordinates and that stand for reservoir width and thickness respectively. The additional term c is
the integration constant, µ is viscosity, and k is permeability.
√
√
√
√
[11]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
37
These initially derived scaled coordinates and from Equation (10) are now replaced with reservoir
dimensions as width and as reservoir thickness. Both parameters are multiplied with the
permeability ratios to count for anisotropy.
Next, pressure Equation (10) is substituted into specific productivity index Equation (8). To simplify the
result of this substitution, two reference points are chosen. The first one at the reservoir boundary is
. The second one at the wellbore is . Then, mobility term,
⁄ , and FVF are added to this specific PI equation to calculate two phase liquid rates and PI.
[ (
)]
[12]
Subscript indicates liquid phase; is specific flow rate changed to standard condtition; is
drawdown; is effective permeability; is relative permeability of a phase; is the viscosity of a
phase; and is the wellbore diameter. This specific PI Equation (12) is only valid if . [20]
Results of Muskat Method
Muskat's Theoretical Method (ŵZ >> ĥZ)
Effective permeability k m2 5.10E-12 1.20E-12 1.24E-12
Scaled zone width ŵR m 109.4 107.0 108.8
Scaled zone thickness ĥR m 21.9 22.4 22.1
Wellbore diameter dW m 0.24 0.24 0.24
Specific zone oil inflow qs,O Rm2/d 0.5 0.3 0.1
Specific zone water inflow qs,W Rm2/d 0.9 0.4 1.5
Specific zone liquid inflow qs,H Rm2/d 1.5 0.7 1.6
Oil flow rate (DH) qO Rm3/d 680 316 87
Water flow rate (DH) qW Rm3/d 1178 480 2375
Total reservoir liquid rate (DH) per zone qH Rm3/d 1858 796 2462
Zonal contribution QZ % 36 16 48
Rates in Standard condition
Specific zone oil inflow qs,O Sm2/d 0.47 0.24 0.05
Specific zone water inflow qs,W Sm2/d 0.91 0.41 1.50
Specific zone liquid inflow qs,H Sm2/d 1.38 0.65 1.55
Oil flow rate qO Sm3/d 599 278 76
Water flow rate qW Sm3/d 1158 472 2335
Total liquid rate per zone qH Sm3/d 1757 751 2412
Total flow rate QLIQ Sm3/d 4919
Water cut WC % 80.61
Specific productivity index Js Sm2/d/Bar 4.1 1.0 2.1
Productivity index per zone J Sm3/d/Bar 5213 1120 3327
Table 20: Muskat’s analytical model results
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
38
Additional simulation There is one other simulation model which was run with the same reservoir properties. It is a steady
state Joshi NETool method made in Excel with average zonal values, transmissibilities and mobilities.
This will show the difference between NETool numerical calculations and theoretical Joshi’s method.
This simulation #3 is expected to have similar flow rates and productivity indices as Joshi’s theoretical
method. Therefore, if there is a difference between NETool and the theoretical steady state Joshi’s
model results, it can be concluded that one should not average some parameters over the entire
reservoir zone.
Simulation #3 uses NETool Joshi’s equations and drains three ellipses from each reservoir zone.
Simulation #3. Joshi's NETool Analytical Method (three zones draining three ellipses)
Influence of anisotropy β - 1.20 1.26 1.22
Half reservoir thickness d m 10 10 10
Half zone length c m 638 575 779
Half the minor axis of a drainage ellipse b m 60 60 60
Half the major axis of a drainage ellipse a m 641 578 781
Distance from end of zone until ellipse boundary Rend m 2.8 3.1 2.3
First term in the denominator cosh-1
(a/c) - 0.094 0.104 0.077
Second term in the denominator βh/LZ*ln(...) - 0.087 0.102 0.072
Denominator - - 0.18 0.21 0.15
Numerator - Rm3/d 392 190 427
Flow rate into horizontal well qH Rm3/d 2172 921 2869
Transmissibility factor A ATRANS cp*Rm3/d/Bar/m 277.0 65.2 67.1
Transmissibility factor B BTRANS - 9.6 9.4 9.5
Total transmissibility T cp*Rm3/d/Bar/m 28.9 6.9 7.0
Oil flow rate qO Rm3/d 795 366 101
Water flow rate qW Rm3/d 1377 555 2768
Flow rate into horizontal well qH Rm3/d 2172 921 2869
Zonal contribution QZ % 36 15 48
Rates in Standard condition
Oil flow rate qO Sm3/d 700 322 89
Water flow rate qW Sm3/d 1354 546 2722
Flow rate into horizontal well qH Sm3/d 2054 868 2811
Total flow rate QLIQUID Sm3/d 5732
Water cut WC % 80.62
Productivity Index of a zone J Sm3/d/Bar 6094 1295 3877
Table 21: Simulation #3 – Steady state Joshi’s NETool analytical method
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
39
Discussion of final results Table 22 lists all the productivity indices, flow rates, water cuts and zonal liquid contributions for all the
different methods used in this study. The largest difference between NETool and the other three
simulation methods is the fact that NETool averages different parameters by the segment size of 12m
and other simulations average the same parameters by the size of the zone. Hence, NETool results are
considered the closest to the actual results.
Productivity Index (Sm3/d/Bar)
Zones NETool Joshi Muskat Sim # 3
Zone 3 4760 6094 5213 6094
Zone 2 1039 1295 1120 1295
Zone 1 1030 3877 3327 3877
Flow rate in ST (Sm3/d)
Zone 3 1604 2054 1757 2054
Zone 2 696 868 751 868
Zone 1 747 2811 2412 2811
Total 3047 5732 4919 5732
Zonal contribution (%)
Zone 3 53 36 36 36
Zone 2 23 15 16 15
Zone 1 24 48 48 48
Total 100 100 100 100
Water cut (%)
Well 38.3 80.6 80.6 80.6
Table 22: Results of different methods
The following Figures 25, 26 and 27 show the difference between NETool data and all the rest of the
analytical methods.
Figure 25: Productivity Index results with different methods
0
1000
2000
3000
4000
5000
6000
7000
NETool Joshi Muskat Sim # 3
Pro
du
ctiv
ity
Ind
ex,
J, (
Sm3 /
d/B
ar)
Zone 3
Zone 2
Zone 1
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
40
Figure 26: Total flow rate results with different methods
Figure 27: Zonal liquid inflow contribution with different methods
Theoretical results in comparison to NETool results for Zone 1 and Zone 3 have larger differences than
Zone 2. Zone 2 has a more similar trend and productivity index, but it also had the worst matching
annulus and tubing pressures for the first well test. Zone 1 is the only zone with heterolithic sands and
high permeability fluctuations. This zone’s permeabilities are not weighted compared to the other two
zones. Zone 3 has the highest average permeability. Liquid flow rate behavior seen on Figure 26 seems
to be in correspondence with the zonal length. The longest zone in the well is Zone 1 and it also shows
the highest production based on theoretical methods. One should also keep in mind that reservoir
geometry in each zone is based on assumptions and not very strongly reliable, since all the zones are set
to have the same thickness and width. Averaging saturation logs, synthetic permeability logs and
0
500
1000
1500
2000
2500
3000
NETool Joshi Muskat Sim # 3
Liq
uid
flo
w r
ate
in S
T (S
m3 /
d)
Zone 3
Zone 2
Zone 1
0
10
20
30
40
50
60
70
80
90
100
NETool Joshi Muskat Sim # 3
Zon
al L
iqu
id In
flo
w C
on
trib
uti
on
. %
Zone 1
Zone 2
Zone 3
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
41
hydrostatic reservoir pressure over the zones could also cause an error to the calculations, if there are
high fluctuations over a long zone interval. For example, averaging saturations over the entire zone
should not be done, because saturations are used to calculate relative permeabilities, and relative
permeabilities are used to calculate mobilities. If zonal saturations fluctuate highly, then average
mobilities can be erroneous.
For zonal inflow optimization with NETool, all the possible FCV positions were tested.
FCV position
Valve openings (%)
PI (Sm3/d/bar)
Zonal contribution DH (%)
QLIQ
(Sm3/d)
WC (%)
Z3 Z2 Z1 Z3 Z2 Z1 Z3 Z2 Z1 All zones All
zones
Pos 2 (Z1 open) 100 100 100 4760 1039 1030 53 23 24 3047 38,3
Pos 2 (Z1 closed) 100 100 0 4774 967 - 60 40 0 2744 32,5
Pos 3 (Z1 open) 27 2 100 4756 1171 913 55 7 38 2758 43,1
Pos 3 (Z1 closed) 27 2 0 4766 1136 - 85 15 0 1915 34,8
Pos 5 (Z1 open) 27 5 100 4750 1120 943 53 13 33 2824 41,4
Pos 5 (Z1 closed) 27 5 0 4761 1069 - 74 26 0 2153 33,6
Pos 7 (Z1 open) 27 0 100 4754 - 882 58 0 42 2677 45,3
Pos 7 (Z1 closed) 27 0 0 4770 - - 100 0 0 1655 36,8
Pos 9 (Z1 open) 2 27 100 4183 1027 977 16 40 44 1928 40,4
Pos 9 (Z1 closed) 2 27 0 4218 954 - 21 79 0 1472 28,4
Pos 11 (Z1 open) 5 27 100 4523 1030 985 28 34 38 2203 39,8
Pos 11 (Z1 closed) 5 27 0 4511 957 - 35 65 0 1772 29,9
Pos 13 (Z1 open) 0 27 100 - 1022 971 0 47 53 1659 41,1
Pos 13 (Z1 closed) 0 27 0 - 951 - 0 100 0 1182 26,1
Average zonal PI 4627 1047 955
Table 23: Productivity Index, zonal contribution (DH), total liquid rate (ST) and water cut of all the possible valve positions of Q-12BH before free gas production
Figure 28: Productivity Index for all the possible FCV openings before free gas production (See Table 3 for FCV positions)
0
1000
2000
3000
4000
5000
6000
Pro
du
ctiv
ity
Ind
ex,
J, (
Sm3 /
d/B
ar)
Zone 3
Zone 2
Zone 1
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
42
Figure 29: DH zonal flow contribution with all the possible FCV openings before free gas production (See Table 3 for FCV positions)
Figure 30: Liquid influx with all the possible FCV openings before free gas production (See Table 3 for FCV positions)
0
20
40
60
80
100
120D
H z
on
al f
low
co
ntr
ibu
tio
n, (
%)
Zone 3
Zone 2
Zone 1
0
500
1000
1500
2000
2500
3000
3500
Pos 2(Z1
open)
Pos 2(Z1
closed)
Pos 3(Z1
open)
Pos 3(Z1
closed)
Pos 5(Z1
open)
Pos 5(Z1
closed)
Pos 7(Z1
open)
Pos 7(Z1
closed)
Pos 9(Z1
open)
Pos 9(Z1
closed)
Pos 11(Z1
open)
Pos 11(Z1
closed)
Pos 13(Z1
open)
Pos 13(Z1
closed)
Liq
uid
Infl
ux
(Sm
3/d
)
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
43
Figure 31: Water cut with all the possible FCV openings before free gas production (See Table 3 for FCV positions)
Limitations Numerical NETool model is considered the most accurate simulation tool out of the four simulation
models created in this study, because it can take into account well completions. For theoretical models,
well completions are not used. All the logs in NETool are averaged over 12m long segments, but for
theoretical methods, there are no segments and all the parameters are averaged over the length of the
zone. All the three zones are over a kilometer long, and therefore averaging parameters is not the best
solution. Especially, when the data fluctuates and it is later used as an input for other parameters.
Unfortunately, Troll wells have no gas saturation logging data present. This could have been entered
into NETool to model free gas production, because free gas production had already started when the
first well test data was taken. Therefore, modeling correct phase flow rates even for the first well test
was difficult, and with increasing free gas influx rate, the later well test were not even used in NETool. In
the end, NETool model calculated the two liquid phases and solution gas rate. In addition, there are
definitely more limiting factors that cause small errors, which are hard to estimate. Some of them can
be calculated logs, such as synthetic permeability, effective saturation or LET relative permeabilities, etc.
Conclusion It difficult to predict the current production behavior of well Q-12BH based on these simulations,
because it is missing gas saturation data. However, there is enough data to discuss that this well was put
on stream with the most optimal FCV opening positions. Q-12BH can be operated in 14 different FCV
0
10
20
30
40
50
60
70
80
90
100
Pos 2(Z1
open)
Pos 2(Z1
closed)
Pos 3(Z1
open)
Pos 3(Z1
closed)
Pos 5(Z1
open)
Pos 5(Z1
closed)
Pos 7(Z1
open)
Pos 7(Z1
closed)
Pos 9(Z1
open)
Pos 9(Z1
closed)
Pos 11(Z1
open)
Pos 11(Z1
closed)
Pos 13(Z1
open)
Pos 13(Z1
closed)
Wat
er
Cu
t (%
)
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
44
positions and all the simulation results of all the positions are given in Table 23. After simulating all the
data with different FCV settings in the same NETool simulation model, it is clear that this well had the
most optimal FCV settings during the initial production and during the first well test. The reason why this
conclusion is reached is seen on Table 23 and Figure 29, where FCV opening position 11 (5% opened in
Zone 3, 27% opened in Zone 2, and 100% opened in Zone 1) shows the most balanced zonal liquid inflow
contribution – 28 % inflow from Zone 3, 34% inflow from Zone 2, and 38% inflow from Zone 1. All the
other FCV positions are not able to equalize the flow that well, when there is no free gas present.
However, the other positions might be more useful when gas influx becomes higher. Average PI values
for all the three zones were found to be the following:
Zone 3 PI: 4627
Zone 2 PI: 1047
Zone 1 PI: 955
The most optimal FCV settings in NETool were calculated by trial and error method found in Table 32.
These results indicated 6,5% opening in Zone 3, 27% opening in Zone 2 and 23% opening in Zone 1.
Hence, these FCV openings for a new well are irrelevant, because if a well with the same completion
design is put on stream at some other reservoir location, then these FCV openings need to be in
accordance with the new reservoir parameters.
Pressures in NETool (FCV openings 6,5%, 27%, 23%)
Parameter Symbol Units Zone 3 Zone 2 Zone 1
Reservoir pressure pRES Bar 136,22 136,48 136,38
Sandface pressure pSF Bar 136,05 135,74 135,61
Average annulus pressure pANN Bar 135,54 135,21 135,40
Annulus pressure (at DHG) pANN_DHG Bar 134,16 133,59 135,39
Average tubing pressure pTUB Bar 128,78 133,69 135,32
Flowing tubing hole pressure (at DHG) pTUB_DHG Bar 125,52 132,79 134,66
Drawdown (pRES - pSF) Δp Bar 0,17 0,74 0,77
Pressure drop across ICDs (pSF - pANN) ΔpICD Bar 0,51 0,53 0,21
Pressure drop across stinger (pANN - pTUB) ΔpSTI Bar 6,77 1,52 0,08
Flow rates in NETool (FCV openings 6,5%, 27%, 23%)
Oil rate QO Sm3/d 1413
Water rate QW Sm3/d 898
Gas rate QG Sm3/d 67512
Total liquid rate (ST condition) QLIQUID Sm3/d 2311
Gas to oil ratio (solution gas) GOR % 47,8
Water cut WC % 38,9
Total liquid rate per zone (ST condition) QIN,LIQ_ST Sm3/d 769 758 785
Oil rate per zone QOIL,ST Sm3/d 485 569 359
Water rate per zone QWAT,ST Sm3/d 284 189 426
Gas rate per zone QGAS,ST Sm3/d 23163 27185 17161
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
45
Total influx per zone (DH condition) QIN,DH Rm3/d 842 841 842
Oil rate per zone QOIL,DH Rm3/d 550 645 408
Water rate per zone QWAT,DH Rm3/d 289 192 434
Gas rate per zone QGAS,DH Rm3/d 3 4 1
Inflow contribution per zone %Q % 33 33 33
Productivity Index J Sm3/d/bar 4574 1026 1019
Figure 32: Simulated NETool model with equal zonal influx
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
46
Acknowledgements
This master thesis was conducted for MSc. Applied Earth Sciences with concentration to Petroleum
Engineering for Delft University of Technology. My appreciation goes out to many Statoil ASA Troll
department engineers, especially to my company supervisor Martin Halvorsen, Gunn Helen Tonning,
Farzad Farshbaf Zinati and Mathias Vikøren Mo. In addition, I appreciated the help of NETool
Development Learder Vitaly Khoriakov. Most importantly, I want to thank my university supervisor Dr.
Jan-Dirk Jansen for all the advice and directions I was given throughout this study.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
47
References
[1] Aashelm, R., Gyllensten, A., Zadeh, A.M., Arland, K., Videla, J.: "Advanced well optimisation in thin
oil rim reservoirs," Statoil ASA Internal document, (2012).
[2] Madsen,T. and Abtahi, M.: "Handling the Oil Zone on Troll," paper OTC 17109 presented at the
2005 Offshore Technology Conference, Houston, 2 - 5 May.
[3] Solheimsnes,K., Gjengedal, J.A., Hamnes, G. M., Ahmadhadi, F., Tonning, G.H.: "Final Well Report
Norway 31/2-Q-12 BH Troll Field," Statoil ASA Internal document, (2012).
[4] Joshi, S.D.: Horizontal Well Technology, PennWell Publishing Company, Tulsa, Oklahoma (1991) 251
- 253.
[5] Waldeland, T.M. (Director): Troll Oil - Raising the Bar, visCo AS Production (Film), Norway (2005).
[6] Halvorsen, M., Elseth, G., Nævdal, O.M.: "Increased oil production at Troll by autonomous inflow
control with RCP valves," paper SPE 159634 presented at the 2012 SPE Annual Technical
Conference and Exhibition, San Antonio, 8-10 October.
[7] Richard, J.D., Saeverhagen, E., Thorsen, A.K., Gard, S.: "Troll West Oilfield Development - How a
Giant Gas Field Became the Largest Oil Field in the NCS through Innovative Field and Technology
Development," paper SPE 112616 presented at the 2008 IADC/SPE Drilling conference, Orlando, 4 -
6 March.
[8] Dahle, B.O., Smith, P.E., Gjelstad, G., Solhaug, K.: "First Intelligent Well Completion in the Troll Field
Enables Feed-Through Zonal Isolation: A Case History," paper SPE 160060 presented at the 2012
SPE Annual Technical Conference and Exhibition, San Antonio, 8 - 10 October.
[9] Kydland, T., Wennemo, S., Olsen, G.: "Reservoir Management Aspects of Producing Oil from Thin Oil
Rims in the Troll Field," paper OTC 7173 presented at the 1993 25th Annual Offshore Technology
Conference, Houston, 3 - 6 May.
[10] Norsk Hydro, "Fluid and Rock Properties," Statoil ASA Internal document, (November 1991).
[11] Jansen, J.-D., Wagenvoort, A.M., Droppert, V.S., Daling, R., Glandt, C.A.: "Smart Well Solutions for
Thin Oil Rims: Inflow Switching and the Smart Stinger Completion," paper SPE 77942 presented at
the 2002 SPE Asia Pacific Oil and Gas Conference and Exhibition, Melbourne, 8 - 10 October.
[12] Birkeland, Ø., Halvorsen, M., Midtkandal, P.A.: "Oppstartsprogram for Q-12 BH," Statoil ASA
Internal document, (May 2011).
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
48
[13] Mjølhus, S., "31/2-Q-12 BH Final Completion String Diagram," Statoil ASA Internal document, (18
October 2011).
[14] Henriksen,K.H., Gule, E.I., Augustine, J: "Case Study: The Application of Inflow Control Devices in the
Troll Oil Field," paper SPE 100308 presented at the 2006 SPE Europec/EAGE Annual Conference and
Exhibition, Vienna, 12 - 15 June.
[15] Mathiesen, V., Aakre, H., Werswick, B. and Elseth, G.: "The Autonomous RCP Valve - New
Technology for Inflow Control In Horizontal Wells," paper SPE 145737 presented at the 2011 SPE
Offshore Europe Oil and Gas Conference and Exhibition, Aberdeen, 6 - 8 September.
[16] Rodgers, S., Smaaskjaer, G., Midtkandal, P.A.: "Troll Field, Sognefjord Formation: FZI Synthetic
Permeability Model," Statoil ASA Internal document,(2000).
[17] Brendsdal, A. and Halvorsen, C.: "Quantification of Permeability Variations across Thin Laminae in
Cross Bedded Sandstone," (1992). [Online]. http://www.scaweb.org/assets/papers/1992_papers/1-
SCA1992-02EURO.pdf.
[18] Lomeland, F., Hasanov, B., Ebeltoft, E., Berge, M.: "A Versatile Representation of Upscaled Relative
Permeability for Field Applications," paper SPE 154487 presented at the 2012 EAGE Annual
Conference and Exhibition, Copenhagen, 4 - 7 June.
[19] Troll PROTEK Teamsite, 31/2-Q-12 BH well tests, Statoil ASA Internal document," [Online].
[20] Jansen, J.-D.: "A Semianalytical Model for Calculating Pressure Drop Along Horizontal Wells With
Stinger Completions," SPE J. 8 (2): 138-146. Paper SPE 74212, (2003).
[21] Halliburton, "NETool 5000.1.x User Guide," Landmark Graphics Corporation, Houston, TX, 2012.
[22] Joshi, S.D.: "Augmentation of Well Productivity with Slant and Horizontal Wells," paper SPE 15375
presented at the 1988 SPE Annual Technical Conference and Exhibition, New Orleans, June.
[23] Bindl, B., Hodnefjell, B., Hansen, S.: "Screen Tally of Well Q-12BH Mainbore as Run," Statoil ASA
Internal document, (2011).
[24] Bear, J.: Dynamics of Fluids in Porous Media, Elsevier, New York City (1972). Reprinted by Dover
Publishers, Mineola, New York (1988) 312 - 322.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
49
APPENDIX A
TABLE A.1: PVT data for the TWGPN
Pressure Oil viscosity
(μo) Oil FVF (Bo) Solution GOR
(RS) Gas viscosity
(μg) Gas FVF (Bg)
[Bar] [cP] [Rm3/Sm
3] [Sm
3/Sm
3] [cP] [Rm
3/Sm
3]
20 1.044
40 3.311 1.060 13.6 0.0128 0.02660
60 2.848 1.076 20.4 0.0136 0.01860
80 2.504 1.091 27.4 0.0143 0.01370
100 2.242 1.107 34.5 0.0151 0.01060
120 2.037 1.123 41.8 0.0160 0.00875
140 1.873 1.139 49.2 0.0170 0.00741
159.06* 1.747 1.154 56.4 0.0179 0.00645
* Bubble point pressure
TABLE A.2: 31/2-Q-12BH Screen tally (confidential)
Table A.3: LET family of correlations for relative permeability
LET Family of Correlations for relative permeability
Unnormalized Base case
Imbibition
Imbibition
SWOF
SGOF
Sw Krw Kro
Sg Krg Kro
0.1500 0 1.0
0.3000 0 1.0
0.1685 0.00002 0.96229
0.3120 0.00003 0.99154
0.1870 0.00014 0.91025
0.3240 0.00017 0.97458
0.2055 0.00039 0.85029
0.3360 0.00047 0.95066
0.2240 0.00084 0.78512
0.3480 0.00099 0.92017
0.2425 0.00151 0.71694
0.3600 0.00177 0.88344
0.2610 0.00247 0.64774
0.3720 0.00287 0.84090
0.2795 0.00377 0.57924
0.3840 0.00435 0.79318
0.2980 0.00547 0.51292
0.3960 0.00625 0.74108
0.3165 0.00762 0.44998
0.4080 0.00863 0.68561
0.3350 0.01030 0.39128
0.4200 0.01157 0.62791
0.3535 0.01359 0.33738
0.4320 0.01513 0.56920
0.3720 0.01756 0.28860
0.4440 0.01938 0.51070
0.3905 0.02230 0.24498
0.4560 0.02441 0.45354
0.4090 0.02792 0.20643
0.4680 0.03030 0.39873
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
50
0.4275 0.03451 0.17270
0.4800 0.03715 0.34708
0.4460 0.04218 0.14345
0.4920 0.04506 0.29918
0.4645 0.05105 0.11830
0.5040 0.05413 0.25544
0.4830 0.06123 0.09684
0.5160 0.06449 0.21604
0.5015 0.07286 0.07867
0.5280 0.07625 0.18100
0.5200 0.08604 0.06340
0.5400 0.08954 0.15022
0.5385 0.10090 0.05065
0.5520 0.10452 0.12347
0.5570 0.11755 0.04008
0.5640 0.12131 0.10048
0.5755 0.13607 0.03139
0.5760 0.14009 0.08091
0.5940 0.15653 0.02430
0.5880 0.16100 0.06442
0.6125 0.17898 0.01857
0.6000 0.18421 0.05066
0.6310 0.20341 0.01398
0.6120 0.20989 0.03930
0.6495 0.22978 0.01035
0.6240 0.23820 0.03002
0.6680 0.25797 0.00751
0.6360 0.26933 0.02253
0.6865 0.28783 0.00532
0.6480 0.30341 0.01657
0.7050 0.31909 0.00366
0.6600 0.34062 0.01189
0.7235 0.35145 0.00244
0.6720 0.38108 0.00828
0.7420 0.38449 0.00156
0.6840 0.42492 0.00556
0.7605 0.41774 0.00094
0.6960 0.47223 0.00356
0.7790 0.45066 0.00053
0.7080 0.52307 0.00215
0.7975 0.48263 0.00027
0.7200 0.57747 0.00119
0.8160 0.51301 0.00012
0.7320 0.63540 0.00059
0.8345 0.54106 0.00004
0.7440 0.69679 0.00024
0.8530 0.56595 0.00001
0.7560 0.76149 0.00007
0.8715 0.58657 0
0.7680 0.82932 0.00001
0.8900 0.6 0
0.7800 0.9 0
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
51
APPENDIX B
TABLE B.1: Well shut-in data used for reservoir pressure calculations (1st
well test pressures are interpolated)
Well shut-in date (until it reached
constant pressure)
Number of days Reservoir pressure [Bar]
since well start up Zone 3 Zone 2 Zone 1
11.09.2011 START UP 136.33 136.59 136.49
16.09.2011* 6 136.31 136.55 136.44
21.10.2011 40 136.18 136.33 136.14
05.11.2011 55 136.10 136.19 136.00
17.12.2011 97 135.88 135.88 135.60
07.03.2012 178 135.59 135.34 134.90
11.03.2012 182 135.61 135.39 134.90
29.04.2012 231 135.31 135.15 134.73
30.04.2012 232 135.31 135.15 134.73
23.05.2012 255 135.15 135.15 134.75
11.06.2012 274 135.17 134.94 134.46
20.06.2012 283 135.08 134.91 134.47
02.09.2012 357 134.79 134.76 134.33
29.09.2012 384 134.76 134.85 134.45
13.10.2012 398 134.61 134.67 134.27
13.11.2012 429 134.49 134.51 134.09
18.11.2012 434 134.50 134.58 134.17
06.12.2012 452 134.50 134.56 134.15
28.01.2013 505 134.18 134.24 133.84
04.02.2013 512 134.23 134.14 133.73
27.02.2013 535 134.07 134.14 133.73
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
52
TABLE B.2: Reservoir influx (DH rates) and phase contribution per well test with different FCV positions
Test No.
FCV Z3
FCV Z2
FCV Z1
PRES Z3 PRES Z2 PRES Z1 Bo avg
Bg avg
Bw avg
Qoil res
Qgas total
Qgas solut.
Qgas free
Qwat res
Qtot res
QoilDH
QgasDH
QwatDH
Start % % % Bar Bar Bar Rm3/S
m3 Rm3/Sm3
Rm3/Sm3
Rm3/d Rm3/d Rm3/d Rm3/d Rm3/d Rm3/d % % %
1 5 27 100 136.31 136.55 136.44 1.136 0.00765 1.017 1639 641 528 113 949 2701 61 4 35
2 5 27 100 136.25 136.46 136.33 1.136 0.00765 1.017 1363 901 439 462 1072 2896 47 16 37
3 5 27 100 136.23 136.43 136.28 1.136 0.00766 1.017 1365 871 440 431 1171 2968 46 15 39
4* 5 27 0 136.23 136.42 136.27 1.136 0.00766 1.017 1227 989 395 594 1091 2912 42 20 37
5* 0 27 100 136.17 136.33 136.15 1.136 0.00766 1.017 1445 1168 466 702 1021 3168 46 22 32
6 5 27 100 136.06 136.14 135.92 1.136 0.00768 1.017 1465 1620 473 1147 1453 4065 36 28 36
7 5 27 100 135.95 135.96 135.69 1.136 0.00769 1.017 1187 2390 383 2007 1373 4567 26 44 30
8 5 27 100 135.80 135.73 135.38 1.136 0.00770 1.017 917 3299 297 3002 1243 5163 18 58 24
9* 0 27 0 135.77 135.68 135.32 1.135 0.00771 1.017 306 2631 99 2532 214 3052 10 83 7
10* 27 2 0 135.76 135.67 135.31 1.135 0.00771 1.017 392 1296 127 1169 647 2208 18 53 29
11 5 27 100 135.48 135.30 134.87 1.135 0.00773 1.017 719 4479 233 4246 1204 6169 12 69 20
12 5 27 100 135.35 135.19 134.77 1.135 0.00774 1.017 597 4669 193 4476 1059 6132 10 73 17
13 5 27 100 135.20 135.07 134.65 1.135 0.00775 1.017 564 4801 182 4619 999 6182 9 75 16
14 5 27 100 134.42 134.45 134.07 1.134 0.00779 1.017 432 2390 140 2250 760 3442 13 65 22
*FCV positions are changed
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
53
APPENDIX C Table C.1: NETool completion diagram
Seg Segment Segment Casing/Liner Sand Inflow Stinger Tubing
# Top MD Length Control Control
1 2052.000 7.000 - - Blank Pipe Blank Pipe Open
2 2059.000 3.000 - Packer Blank Pipe Blank Pipe Open
3 2062.000 2.000 - Packer Blank Pipe Packer Open
4 2064.000 2.000 - - Blank Pipe Packer Open
5 2066.000 10.000 - - Blank Pipe Blank Pipe Open
6 2076.000 7.600 - - Baker Spiral ICD, Troll Blank Pipe Open
7 2083.600 1.300 - - Baker Spiral ICD, Troll Blank Pipe Open
8 2084.900 0.200 - - Baker Spiral ICD, Troll Blank Pipe Open
9 2085.100 1.400 - - Baker Spiral ICD, Troll Blank Pipe Open
10 2086.500 0.200 - - Baker Spiral ICD, Troll Blank Pipe Open
11 2086.700 4.300 - - Baker Spiral ICD, Troll ICV Open
12 2091.000 9.000 - - Baker Spiral ICD, Troll Blank Pipe Open
13 2100.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
14 2112.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
15 2118.000 6.000 - Packer Blank Pipe Blank Pipe Open
16 2124.000 12.000 - - Blank Pipe Blank Pipe Open
17 2136.000 12.000 - - Blank Pipe Blank Pipe Open
18 2148.000 12.000 - - Blank Pipe Blank Pipe Open
19 2160.000 12.000 - - Blank Pipe Blank Pipe Open
20 2172.000 12.000 - - Blank Pipe Blank Pipe Open
21 2184.000 12.000 - - Blank Pipe Blank Pipe Open
22 2196.000 12.000 - - Blank Pipe Blank Pipe Open
23 2208.000 12.000 - Packer Blank Pipe Blank Pipe Open
24 2220.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
25 2232.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
26 2244.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
27 2256.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
28 2268.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
29 2280.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
30 2292.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
31 2304.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
32 2316.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
33 2328.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
34 2340.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
35 2346.000 6.000 - Packer Blank Pipe Blank Pipe Open
36 2352.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
37 2364.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
38 2376.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
39 2388.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
40 2400.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
41 2412.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
42 2424.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
54
43 2436.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
44 2448.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
45 2460.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
46 2472.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
47 2484.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
48 2490.000 6.000 - Packer Blank Pipe Blank Pipe Open
49 2496.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
50 2508.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
51 2520.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
52 2532.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
53 2544.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
54 2556.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
55 2568.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
56 2580.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
57 2592.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
58 2604.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
59 2616.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
60 2622.000 6.000 - Packer Blank Pipe Blank Pipe Open
61 2628.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
62 2640.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
63 2652.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
64 2664.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
65 2676.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
66 2688.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
67 2700.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
68 2712.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
69 2724.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
70 2736.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
71 2748.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
72 2754.000 6.000 - Packer Blank Pipe Blank Pipe Open
73 2760.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
74 2772.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
75 2784.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
76 2796.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
77 2808.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
78 2820.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
79 2832.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
80 2844.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
81 2856.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
82 2868.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
83 2880.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
84 2892.000 6.000 - Packer Blank Pipe Blank Pipe Open
85 2898.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
86 2904.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
87 2916.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
88 2928.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
89 2940.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
90 2952.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
55
91 2964.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
92 2976.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
93 2988.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
94 3000.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
95 3012.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
96 3018.000 6.000 - Packer Blank Pipe Blank Pipe Open
97 3024.000 12.000 - - Blank Pipe Blank Pipe Open
98 3036.000 12.000 - - Blank Pipe Blank Pipe Open
99 3048.000 12.000 - - Blank Pipe Blank Pipe Open
100 3060.000 12.000 - - Blank Pipe Blank Pipe Open
101 3072.000 12.000 - - Blank Pipe Blank Pipe Open
102 3084.000 12.000 - - Blank Pipe Blank Pipe Open
103 3096.000 12.000 - - Blank Pipe Blank Pipe Open
104 3108.000 12.000 - - Blank Pipe Blank Pipe Open
105 3120.000 12.000 - - Blank Pipe Blank Pipe Open
106 3132.000 12.000 - - Blank Pipe Blank Pipe Open
107 3144.000 12.000 - - Blank Pipe Blank Pipe Open
108 3156.000 12.000 - - Blank Pipe Blank Pipe Open
109 3168.000 12.000 - - Blank Pipe Blank Pipe Open
110 3180.000 12.000 - - Blank Pipe Blank Pipe Open
111 3192.000 12.000 - - Blank Pipe Blank Pipe Open
112 3204.000 12.000 - Packer Blank Pipe Blank Pipe Open
113 3216.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
114 3228.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
115 3240.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
116 3252.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
117 3264.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
118 3276.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
119 3288.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
120 3300.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
121 3312.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
122 3324.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
123 3336.000 4.000 - - Baker Spiral ICD, Troll Blank Pipe Open
124 3340.000 5.000 - Packer Blank Pipe Blank Pipe Open
125 3345.000 3.000 - - Blank Pipe Blank Pipe Open
126 3348.000 3.000 - - Blank Pipe Blank Pipe Open
127 3351.000 4.000 - - Blank Pipe Packer Open
128 3355.000 5.000 - - Blank Pipe Blank Pipe Open
129 3360.000 12.000 - - Blank Pipe Blank Pipe Open
130 3372.000 1.400 - - Blank Pipe Blank Pipe Open
131 3373.400 0.200 - - Blank Pipe Blank Pipe Open
132 3373.600 4.300 - - Blank Pipe ICV Open
133 3377.900 6.100 - - Blank Pipe Blank Pipe Open
134 3384.000 12.000 - - Blank Pipe Blank Pipe Open
135 3396.000 12.000 - - Blank Pipe Blank Pipe Open
136 3408.000 12.000 - - Blank Pipe Blank Pipe Open
137 3420.000 12.000 - - Blank Pipe Blank Pipe Open
138 3432.000 12.000 - Packer Blank Pipe Blank Pipe Open
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
56
139 3444.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
140 3456.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
141 3468.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
142 3480.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
143 3492.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
144 3504.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
145 3516.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
146 3528.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
147 3540.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
148 3552.000 6.000 - Packer Blank Pipe Blank Pipe Open
149 3558.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
150 3564.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
151 3576.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
152 3588.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
153 3600.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
154 3612.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
155 3624.000 6.000 - Packer Blank Pipe Blank Pipe Open
156 3630.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
157 3636.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
158 3648.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
159 3660.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
160 3672.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
161 3684.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
162 3696.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
163 3708.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
164 3720.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
165 3732.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
166 3744.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
167 3756.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
168 3768.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
169 3774.000 6.000 - Packer Blank Pipe Blank Pipe Open
170 3780.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
171 3792.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
172 3804.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
173 3816.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
174 3828.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
175 3840.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
176 3852.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
177 3864.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
178 3876.000 6.000 - Packer Blank Pipe Blank Pipe Open
179 3882.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
180 3888.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
181 3900.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
182 3912.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
183 3924.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
184 3936.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
185 3948.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
186 3960.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
57
187 3972.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
188 3984.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
189 3996.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
190 4008.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
191 4020.000 6.000 - Packer Blank Pipe Blank Pipe Open
192 4026.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
193 4032.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
194 4044.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
195 4056.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
196 4068.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
197 4080.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
198 4092.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
199 4104.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
200 4116.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
201 4128.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
202 4140.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
203 4152.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
204 4164.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
205 4176.000 6.000 - Packer Blank Pipe Blank Pipe Open
206 4182.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
207 4188.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
208 4200.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
209 4212.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
210 4224.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
211 4236.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
212 4248.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
213 4260.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
214 4272.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
215 4284.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
216 4296.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
217 4308.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
218 4320.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
219 4332.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
220 4338.000 6.000 - Packer Blank Pipe Blank Pipe Open
221 4344.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
222 4356.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
223 4368.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
224 4380.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
225 4392.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
226 4404.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
227 4416.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
228 4428.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
229 4440.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
230 4452.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
231 4464.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
232 4476.000 12.000 - - Baker Spiral ICD, Troll Blank Pipe Open
233 4488.000 7.000 - - Baker Spiral ICD, Troll Blank Pipe Open
234 4495.000 5.000 - Packer Blank Pipe Blank Pipe Open
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
58
235 4500.000 3.400 - - Blank Pipe Blank Pipe Open
236 4503.400 4.000 - - Blank Pipe Packer Open
237 4507.400 4.600 - - Blank Pipe Blank Pipe Open
238 4512.000 11.700 - - Baker Spiral ICD, Troll Blank Pipe Open
239 4523.700 1.300 - - Baker Spiral ICD, Troll Blank Pipe Open
240 4525.000 0.200 - - Baker Spiral ICD, Troll Blank Pipe Open
241 4525.200 1.300 - - Baker Spiral ICD, Troll Blank Pipe Open
242 4526.500 0.200 - - Baker Spiral ICD, Troll Blank Pipe Open
243 4526.700 2.620 - - Baker Spiral ICD, Troll ICV Open
244 4529.320 6.680 - - Baker Spiral ICD, Troll Blank Pipe Open
245 4536.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Open
246 4542.000 6.000 - - Baker Spiral ICD, Troll Blank Pipe Plug
247 4548.000 12.000 - - Baker Spiral ICD, Troll - Open
248 4560.000 12.000 - - Baker Spiral ICD, Troll - Open
249 4572.000 12.000 - - Baker Spiral ICD, Troll - Open
250 4584.000 12.000 - - Baker Spiral ICD, Troll - Open
251 4596.000 12.000 - - Baker Spiral ICD, Troll - Open
252 4608.000 12.000 - - Baker Spiral ICD, Troll - Open
253 4620.000 6.000 - - Baker Spiral ICD, Troll - Open
254 4626.000 6.000 - Packer Blank Pipe - Open
255 4632.000 12.000 - - Baker Spiral ICD, Troll - Open
256 4644.000 12.000 - - Baker Spiral ICD, Troll - Open
257 4656.000 12.000 - - Baker Spiral ICD, Troll - Open
258 4668.000 12.000 - - Baker Spiral ICD, Troll - Open
259 4680.000 12.000 - - Baker Spiral ICD, Troll - Open
260 4692.000 12.000 - - Baker Spiral ICD, Troll - Open
261 4704.000 12.000 - - Baker Spiral ICD, Troll - Open
262 4716.000 12.000 - - Baker Spiral ICD, Troll - Open
263 4728.000 12.000 - - Baker Spiral ICD, Troll - Open
264 4740.000 12.000 - - Baker Spiral ICD, Troll - Open
265 4752.000 12.000 - - Baker Spiral ICD, Troll - Open
266 4764.000 12.000 - - Baker Spiral ICD, Troll - Open
267 4776.000 12.000 - - Baker Spiral ICD, Troll - Open
268 4788.000 12.000 - - Baker Spiral ICD, Troll - Open
269 4800.000 12.000 - - Baker Spiral ICD, Troll - Open
270 4812.000 12.000 - - Baker Spiral ICD, Troll - Open
271 4824.000 12.000 - - Baker Spiral ICD, Troll - Open
272 4836.000 6.000 - - Baker Spiral ICD, Troll - Open
273 4842.000 6.000 - Packer Blank Pipe - Open
274 4848.000 12.000 - - Baker Spiral ICD, Troll - Open
275 4860.000 12.000 - - Baker Spiral ICD, Troll - Open
276 4872.000 12.000 - - Baker Spiral ICD, Troll - Open
277 4884.000 12.000 - - Baker Spiral ICD, Troll - Open
278 4896.000 12.000 - - Baker Spiral ICD, Troll - Open
279 4908.000 12.000 - - Baker Spiral ICD, Troll - Open
280 4920.000 12.000 - - Baker Spiral ICD, Troll - Open
281 4932.000 12.000 - - Baker Spiral ICD, Troll - Open
282 4944.000 12.000 - - Baker Spiral ICD, Troll - Open
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
59
283 4956.000 12.000 - - Baker Spiral ICD, Troll - Open
284 4968.000 12.000 - - Baker Spiral ICD, Troll - Open
285 4980.000 12.000 - - Baker Spiral ICD, Troll - Open
286 4992.000 12.000 - - Baker Spiral ICD, Troll - Open
287 5004.000 12.000 - - Baker Spiral ICD, Troll - Open
288 5016.000 12.000 - - Baker Spiral ICD, Troll - Open
289 5028.000 12.000 - - Baker Spiral ICD, Troll - Open
290 5040.000 6.000 - Packer Blank Pipe - Open
291 5046.000 6.000 - - Baker Spiral ICD, Troll - Open
292 5052.000 12.000 - - Baker Spiral ICD, Troll - Open
293 5064.000 6.000 - - Blank Pipe - Open
294 5070.000 18.000 - - Baker Spiral ICD, Troll - Open
295 5088.000 12.000 - - Baker Spiral ICD, Troll - Open
296 5100.000 12.000 - - Baker Spiral ICD, Troll - Open
297 5112.000 12.000 - - Baker Spiral ICD, Troll - Open
298 5124.000 12.000 - - Baker Spiral ICD, Troll - Open
299 5136.000 12.000 - - Baker Spiral ICD, Troll - Open
300 5148.000 12.000 - - Baker Spiral ICD, Troll - Open
301 5160.000 12.000 - - Baker Spiral ICD, Troll - Open
302 5172.000 12.000 - - Baker Spiral ICD, Troll - Open
303 5184.000 12.000 - - Baker Spiral ICD, Troll - Open
304 5196.000 12.000 - - Baker Spiral ICD, Troll - Open
305 5208.000 12.000 - - Baker Spiral ICD, Troll - Open
306 5220.000 6.000 - - Baker Spiral ICD, Troll - Open
307 5226.000 6.000 - Packer Blank Pipe - Open
308 5232.000 12.000 - - Baker Spiral ICD, Troll - Open
309 5244.000 12.000 - - Baker Spiral ICD, Troll - Open
310 5256.000 12.000 - - Baker Spiral ICD, Troll - Open
311 5268.000 12.000 - - Baker Spiral ICD, Troll - Open
312 5280.000 12.000 - - Baker Spiral ICD, Troll - Open
313 5292.000 12.000 - - Baker Spiral ICD, Troll - Open
314 5304.000 12.000 - - Baker Spiral ICD, Troll - Open
315 5316.000 12.000 - - Baker Spiral ICD, Troll - Open
316 5328.000 12.000 - - Baker Spiral ICD, Troll - Open
317 5340.000 12.000 - - Baker Spiral ICD, Troll - Open
318 5352.000 12.000 - - Baker Spiral ICD, Troll - Open
319 5364.000 12.000 - - Baker Spiral ICD, Troll - Open
320 5376.000 12.000 - - Baker Spiral ICD, Troll - Open
321 5388.000 12.000 - - Baker Spiral ICD, Troll - Open
322 5400.000 12.000 - - Baker Spiral ICD, Troll - Open
323 5412.000 6.000 - Packer Blank Pipe - Open
324 5418.000 6.000 - - Baker Spiral ICD, Troll - Open
325 5424.000 12.000 - - Baker Spiral ICD, Troll - Open
326 5436.000 12.000 - - Baker Spiral ICD, Troll - Open
327 5448.000 12.000 - - Baker Spiral ICD, Troll - Open
328 5460.000 12.000 - - Baker Spiral ICD, Troll - Open
329 5472.000 12.000 - - Baker Spiral ICD, Troll - Open
330 5484.000 12.000 - - Baker Spiral ICD, Troll - Open
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
60
331 5496.000 12.000 - - Baker Spiral ICD, Troll - Open
332 5508.000 12.000 - - Baker Spiral ICD, Troll - Open
333 5520.000 12.000 - - Baker Spiral ICD, Troll - Open
334 5532.000 12.000 - - Baker Spiral ICD, Troll - Open
335 5544.000 12.000 - - Baker Spiral ICD, Troll - Open
336 5556.000 6.000 - Packer Blank Pipe - Open
337 5562.000 6.000 - - Baker Spiral ICD, Troll - Open
338 5568.000 12.000 - - Baker Spiral ICD, Troll - Open
339 5580.000 12.000 - - Baker Spiral ICD, Troll - Open
340 5592.000 12.000 - - Baker Spiral ICD, Troll - Open
341 5604.000 12.000 - - Baker Spiral ICD, Troll - Open
342 5616.000 12.000 - - Baker Spiral ICD, Troll - Open
343 5628.000 12.000 - - Baker Spiral ICD, Troll - Open
344 5640.000 12.000 - - Baker Spiral ICD, Troll - Open
345 5652.000 12.000 - - Baker Spiral ICD, Troll - Open
346 5664.000 12.000 - - Baker Spiral ICD, Troll - Open
347 5676.000 12.000 - - Baker Spiral ICD, Troll - Open
348 5688.000 12.000 - - Baker Spiral ICD, Troll - Open
349 5700.000 12.000 - - Baker Spiral ICD, Troll - Open
350 5712.000 12.000 - - Baker Spiral ICD, Troll - Open
351 5724.000 12.000 - - Baker Spiral ICD, Troll - Open
352 5736.000 12.000 - - Baker Spiral ICD, Troll - Open
353 5748.000 6.000 - - Baker Spiral ICD, Troll - Open
354 5754.000 6.000 - Packer Blank Pipe - Open
355 5760.000 12.000 - - Baker Spiral ICD, Troll - Open
356 5772.000 12.000 - - Baker Spiral ICD, Troll - Open
357 5784.000 12.000 - - Baker Spiral ICD, Troll - Open
358 5796.000 12.000 - - Baker Spiral ICD, Troll - Open
359 5808.000 12.000 - - Baker Spiral ICD, Troll - Open
360 5820.000 12.000 - - Baker Spiral ICD, Troll - Open
361 5832.000 12.000 - - Baker Spiral ICD, Troll - Open
362 5844.000 12.000 - - Baker Spiral ICD, Troll - Open
363 5856.000 12.000 - - Baker Spiral ICD, Troll - Open
364 5868.000 6.000 - - Baker Spiral ICD, Troll - Open
365 5874.000 6.000 - Packer Blank Pipe - Open
366 5880.000 12.000 - - Baker Spiral ICD, Troll - Open
367 5892.000 12.000 - - Baker Spiral ICD, Troll - Open
368 5904.000 12.000 - - Baker Spiral ICD, Troll - Open
369 5916.000 12.000 - - Baker Spiral ICD, Troll - Open
370 5928.000 12.000 - - Baker Spiral ICD, Troll - Open
371 5940.000 12.000 - - Baker Spiral ICD, Troll - Open
372 5952.000 12.000 - - Baker Spiral ICD, Troll - Open
373 5964.000 12.000 - - Baker Spiral ICD, Troll - Open
374 5976.000 12.000 - - Baker Spiral ICD, Troll - Open
375 5988.000 6.000 - Packer Blank Pipe - Open
376 5994.000 6.000 - - Baker Spiral ICD, Troll - Open
377 6000.000 12.000 - - Baker Spiral ICD, Troll - Open
378 6012.000 12.000 - - Baker Spiral ICD, Troll - Open
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
61
379 6024.000 12.000 - - Baker Spiral ICD, Troll - Open
380 6036.000 12.000 - - Baker Spiral ICD, Troll - Open
381 6048.000 10.000 - - Baker Spiral ICD, Troll - Open
382 6058.000 2.000 - - Baker Spiral ICD, Troll - Plug
383 6060.000 10.000 - - Baker Spiral ICD, Troll - Plug
TOE 6070.000
APPENDIX D Derivation of NETool inflow model equations
NETool inflow model runs on Joshi’s horizontal well technology theory. The following chapter covers the
derivation of the formula. Before derivation, one should know that the well model in NETool is divided
into segments of 12 meters. This value is used because the joint length on the real well is around 12m.
Near the FCVs and DHGs, the completion equipment lengths are shorter and modeled more precisely.
Each segment, , has three phase components – oil, gas and water. The equation that calculates inflow is
the following
[D.1]
Here, is the mobility of a phase, is transmissibility and is the drawdown. Transmissibility, that
forms part of the PI modeling for each segment is calculated as:
[D.2]
where and are the two factors of transmissibility equation. Parameter stands for
skin, but skin is considered zero for the Troll field. It means there is no formation damage near the
wellbore, which can often be the case when the reservoir sands are less permeable.
In order to understand transmissibility, one should know how the factors and are
calculated. First of all, see Table D.1 for all the parameters.
β √ ⁄
d
c
b
a √ rwb
Table D.1: NETool inflow equation parameters
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
62
Transmissibility factors are described below:
[D.3]
(
) (
) [D.4]
Substitution of these factors into transmissibility equation shows similarities with Joshi’s equation (10a)
from paper SPE 15375. This equation (10a) is shown in Equation (D.5). The flow rate is calculated in
standard condition since the numerator is divided by FVF. [22]
[ √ ⁄
]
(
)
[D.5]
Hyperbolic arccosine term in in Equation (D.4) is the same term as the first natural logarithmic
term in the denominator of Equation (D.5). Both terms in the denominator are compared below:
[ √ ] [D.6]
(
) [(
) √(
) ] [D.7]
Next, Table 1 values (except ) are substituted into Equation (D.7)
(
) [(
) √(
) ] [D.8]
(
) [(
) √
] [D.9]
(
) [(
) √
] [D.10]
(
) [(
)
√
] [D.11]
(
) [
√
] [D.12]
It is important to know that parameters and are the major and minor axes of the drainage ellipse.
√ √(
)
(
)
[
√
⁄ ]
[D.13]
Half of the major axis of drainage ellipse, , can be calculated in two ways shown in Equation (D.13).
One of the formulas includes horizontal drainage radius term, and the other one, does not. The result is
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
63
the same for both of them, and therefore it does not matter which formula is used. For example, NETool
uses the method with Pythagoras theorem, and Joshi’s paper SPE 15375 presents the one with
horizontal drainage radius ( ) term for the theoretical method.
Next, transmissibility factors are substituted into transmissibility equation with no skin present.
(
) (
) [D.14]
Then, the top and bottom term are multiplied with ⁄ . This results the following
(
)
(
) [D.15]
In the next step, Table 1 parameters are substituted into the previous Equation (D.15):
(
)
(
) [D.16]
Now, some terms can be cancelled
(
)
(
) [D.17]
The denominator for transmissibility equation used in NETool, and the denominator for Joshi’s
horizontal well inflow model used for analytical calculations, is exactly the same for both equations.
Mobility in NETool is calculated based on effective water saturations and relative permeabilities shown
in Equation (D.18)
[D.18]
The formulas that NETool uses for reservoir inflow and productivity indices calculations are as followed:
(
)
(
) [D.19]
(
)
(
) [D.20] [D.20]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
64
APPENDIX E Explanation of the theoretical PI from J.Bear book “Dynamics of Fluids in Porous Media” [24]
Flow potential, which is a real part of the function of an infinite array of sinks, is derived as follows
[ ] ∑ [ ]
[E.1]
Here z is the complex number, and ⁄ . is the flow rate, and d is the total distance on x-axis.
To keep it simple, m is changed later.
The problem requires finding a complex function, where the interest remains for the real part. This
function also has a conjugate part, z*.
[E.2]
[E.3]
Based on the rule ⁄ and complex number identities, the following flow potential
equation can be written as
(
)
[(
) (
)]
[ (
) (
)] [E.4]
Next, trigonometric part of the function has to be transferred into complex exponential function
(
)
( ) [E.5]
(
)
( ) [E.6]
Then, substitution of these exponential identities from [E.5] and [E.6] should be entered into Equation
[E.4]. This results in [E.7].
[
( ) (
) ( ) ] [E.7]
[
(
) ] [E.8]
As a reminder
[E.9]
[E.10]
Then, reorganize the terms by substituting in x and y
[
(
) ] [E.11]
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
65
The previous equation can now be written as
[
(
) ] [E.12]
(
) [E.13]
The following trigonometric identities are shown how the real part of the flow potential equation was
found
[E.14]
[E.15]
As a result, flow potential formula is
(
) [E.16]
For the upcoming calculations, paper SPE 74212 is followed. Variable d is the thickness of the reservoir,
ĥR. Variable m is flow to the sink divided by 2π (L2t-1) while considering Darcy flow characteristics such as
viscosity, µ, and permeability, k. One should also remember that with the use of Darcy’s Law, the flow
has a negative sign in front of it as the fluid flows from high pressure zones to low pressure zones.
Therefore, the equation can be rewritten as
[E.17]
[
(
) ] [E.18]
Then, both sides are integrated
∫ ∫
[
(
) ] [E.19]
[
(
) ] [E.20]
where c is the integration coefficient.
Finally, a specific productivity index formula is created. In order to simplify this formula, two reference
points are used. One of the reference points is at the constant reservoir boundary
,
and the second one is at the wellbore (sandface)
. Notice that the term cancels
out.
Gas Coning Control with a Smart Horizontal Well in a Thin Oil Rim
66
[
(
) ]
[
(
) ] [E.21]
Therefore,
[ [
(
) ] [
(
) ]]
[E.22]
[
(
)
(
)]
[E.23]
The final theoretical PI formula from the SPE 74212 paper was derived and found in Equation (E.24)
[ (
)]
[E.24]
Next, Equation (E.24) was edited by phase mobility ⁄ and FVF term, ,shown in Equation
(E.25). This allows calculation of two-phase liquid flow in standard condition. The flow rates of the
phases are calculated separately, and then added afterwards. After addition, specific productivity index
seen in Equation (E.26) is calculated and multiplied by the length of the zone for zonal productivity
index, found in Equation (E.27)
[ (
)]
[E.25]
[ (
)]
[E.26]
[ (
)]
[E.27]