Allen, Augurson, Gamboa, Harris, Snyder 1
EastSide Team
CMGT 410
Gerald Rojewski
6 February 2002
Automated Data Transmission System
Introduction
This document details the Automated Data Transmission System proposal that has been
developed by the Eastside Network Development Team, consisting of Graham Allen, T. Augurson,
Joe Gamboa, James Harris, and Scot Snyder. This system that has been developed will provide an
efficient, secure, automated, and cost saving solution to the present data transmission system.
Background
Eastside Network Development Team is a consulting agency that provides analysis, design,
development, and maintenance services involving hardware and/or software for virtually any
information system. Currently, Eastside maintains contracts and service agreements with several
military and government agencies, including existing service contracts with the 12Air Force. Due
to the nature and sensitivity of data these military and government contracts comprise, all
employees of Eastside require thorough background checks and are required to qualify for a
security clearance appropriate to the project that is assigned to them.
The 12 Air Force A2 gathers intelligence data from unmanned aircraft that fly over various
locations around the world. Data gathered from these aircraft are used for logistical purposes for
several sectors throughout the government. This data is transmitted in the form of email messages.
Users of this system must sort relevant messages and manually type this data into a report. This
8/3/2019 ADTS Paper Week 5
2/28
Allen, Augurson, Gamboa, Harris, Snyder 2
report is then printed and secure-faxed to a mobile command center. The current process is very
inefficient, time-consuming, and often produces inaccurate information since data must be
manually entered into the preformatted report.
Because this process needs to be performed constantly, a team of individuals is required to
process this data. At this time, there are five people that work on this assignment. Several major
problems with the current process have motivated the Air Force to develop a solution. The main
issue includes the time required to process and deliver these reports, as well as validity of these
documents due to mistyped information. Processing these reports is very time-consuming and
labor-intensive. To produce a finished report, email messages must be manually filtered for
relevant data. Then, data is copied and manually typed into another report. This manual process
often produces inaccurate records resulting in unusable information. Automating this process will
eliminate steps that cause this imprecision. Another issue concerns the way these reports are
delivered. At this time, only a secure facsimile is sent after the data is processed, but alternative
delivery methods have been suggested to enhance distribution of these documents. The last major
issue occurs is when one of these individuals is out sick, or takes vacation. Due to the inadequate
number of individuals assigned to this responsibility, nonattendance strains the rest of the team.
These reports must be processed constantly, so when one member is absent, the others must fill in
and work beyond their normal schedule.
The purpose of the project is to decrease time and man-hours necessary to perform these
duties, while increasing security. There are several obstacles that make this request problematic.
These reports contain classified material, which cannot be sent over regular networks (i.e. phone
lines, email, facsimile, etc) without some sort of protection or encryption. The original data
source is from various military aircraft operating throughout the world that are constantly
8/3/2019 ADTS Paper Week 5
3/28
Allen, Augurson, Gamboa, Harris, Snyder 3
transmitting data. It is not possible to change the method of receipt, as it is necessary to utilize the
existing secure email intranet network. The command center receiving the secure facsimile is
mobile, and is never in the same location for a long period of time. The method of secure facsimile
transmissions must remain intact.
Project Objectives
The objective of this assignment is to develop a cost-saving, efficient, and secure solution
to the current data processing situation. This will incorporate an increase in security, elimination
of erroneous data entries, decrease man-hours required to process these reports, and provide
alternative reporting methods. Once this project is implemented, reporting will be automated and
will require very little user intervention. This will eliminate the need for a team to process this
information twenty-four hours a day. The current team of five users will be downsized to two
users, and the remaining individuals may be reassigned to other critical projects within the 12 th Air
Force. This elimination of personnel will cut costs, and save more than the amount of the cost of
this project in the first year of usage. Upgraded facsimile machines will transmit these documents
more rapidly, and will provide a higher level of security. Alternative reporting methods will
provide the latest and most current data to recipients in the form of automatic printing, and
accurate intranet web page easily accessible to appropriate users within the secured Local Area
Network. The 12Air Force A2 Division has hired Eastside Network Development Team to create
a solution to this problem, and has established a $40,000 target budget for successful completion of
this project.
One risk that may hinder the completion of this project is the installation of the upgraded
facsimile machine in the mobile command center. The hardware technician assigned to this
8/3/2019 ADTS Paper Week 5
4/28
Allen, Augurson, Gamboa, Harris, Snyder 4
project must rendezvous with this vehicle at a scheduled time and location in order to perform this
installation and test its usage. Once this step is complete, all other modifications will be performed
at this location. Another risk that may affect this project is the dependency of newly ordered
hardware to be delivered in a timely manner. If this new hardware is not received at the proper
time, segments of this project will be unable to complete assigned tasks in the allocated time. This
delay will ultimately affect the entire project.
Mission and Goals of Project
Existing LAN based computers will be utilized to receive incoming data transmissions in
email format from the aircraft. As has been noted, these emails are too voluminous to be sorted
manually. Software will be developed and implemented that will automatically receive the
incoming data and filter what is necessary for this location. Intervention from the user will be
dramatically reduced.
Once the email messages have been sorted, the goal is to automatically update a database,
then organize, analyze, and generate reports defined by the project manager and the 12th Air Force
liaison representative. A data conversion system will be designed and implemented that will
convert and import the sorted email data into a format that is compatible the database. This data
will be initially converted into a text file, and then organized and reformatted as necessary by the
database. A new computer will be setup on the secure network to perform all data conversions and
importation, provide user interface for report generation, and function as the database server.
Additional user utilities will be added to the database to allow for customized searches and
regeneration of data reports as necessary. The database development is the core feature of the
automated report generation. It is proposed that once again, user interface will be minimal or non-
8/3/2019 ADTS Paper Week 5
5/28
Allen, Augurson, Gamboa, Harris, Snyder 5
existent, as opposed to the current system that requires constant attention, and is very manually
labor intensive.
The final stage of this design will solve the main issue of secure data transmission. A
three-tiered plan is being proposed that can be altered depending upon budget constraints. The
first item is an upgraded secure facsimile system, which will replace current hardware. This
solution includes a new secure telephone and facsimile unit for both sender and receiver.
Upgrading this hardware allows faster data transmissions and provides more security than the
existing hardware.
A second output option will be to update a web page at regular intervals located on the
existing secure intranet for internal use only. This will provide easily accessible reports to
intelligence officials in a timely manner. A new web server will be installed on this network to
facilitate automatic web page updates.
The third transmission option will send the material to an external, but secure, printer. One
of the automated reports will be printed to this printer not attached to the database server. A new
printer will be purchased that will contain a network card to allow it to function without a
dedicated server. This report will be printed automatically at regular intervals to be determined by
the project manager.
Project (Plan) Approach
The project will be structured and developed, in a manner that is consistent with achieving
all of the aforementioned goals, allowing the proposal to be implemented within the required
8/3/2019 ADTS Paper Week 5
6/28
Allen, Augurson, Gamboa, Harris, Snyder 6
budget and time constraints. Focus will be given to all areas that directly impact the timely
development of the project.
The sponsoring body is the 12th Air Force A2 division. They will oversee all aspects of the
ongoing project and monitor its development, from problem definition through to implementation
and maintenance. This division of the Air Force has employed the services of East Side Network
Developing to solve this problem. A project manager employed with East Side Network
Developing will report directly to the military management and a military liaison will be assigned
to insure communication is maintained at all times. Eastside is not responsible for any wages
accrued by the military liaison, but will provide all other labor required to complete this project.
Details of the project management and technical staff structure are detailed in the next section.
Eastside Network Developing is responsible for providing leadership and technical
personnel for this project. Continuous monitoring of development activities will be necessary so
that all tasks and sub-tasks are completed on time, and any potential delays to the proposed
schedule can be avoided. Should problems occur, it is the project managers responsibility to work
with the team leads to keep any negative impact to a minimum.
The technical staff of engineers and technicians specializing in their respective fields will
complete software development, hardware installation, and integration. A team lead will be
assigned to each key area to insure that progress is made according to the planned schedule.
Continuous feedback from all departments is mandatory, and emphasis will be placed on
constant communication between the team leads and the project manager. The manager will
oversee all aspects of the program and monitor budget levels accordingly. By creating a dynamic
team environment committed solely to the development and integration of the new process, this
program will be implemented on time and within budget.
8/3/2019 ADTS Paper Week 5
7/28
Allen, Augurson, Gamboa, Harris, Snyder 7
Project (Plan) Organization
This section identifies the team members that will be involved in every aspect of
completing this project. Included on the following page is the graphical depiction of the full
project organization chart.
The sponsoring body is the 12 Air Force A2, and they will oversee every phase of the
project development. The project manager will report directly to the Air Force command, on all
issues relating to schedule, budget, and process issues. The project manager will also answer any
questions or issues raised by the military during this program. To enable a smooth transition of the
process upon its completion to military management, a military liaison will be assigned to assist
the project manager and the development teams. This is indicated on the organization chart as the
Tech Sergeant.
The program manager will have prior experience in project development and
implementation and will focus on effective communication between the development teams and
the sponsoring body. An administrative assistant will be assigned to the project manager
throughout this project to assist with clerical and general support functions.
There are a total of three management/leadership positions in the proposed organization.
The second level will consist of a development team lead. The development team is essentially
split into three distinct sections; software, hardware, and test and integration. Each section will
have a team lead responsible for the progress and resource distribution assigned to that particular
area. Each section lead reports directly to the development team lead, which is responsible for
coordinating all development activities, and insuring timely completion of all activities. The
8/3/2019 ADTS Paper Week 5
8/28
Allen, Augurson, Gamboa, Harris, Snyder 8
development team lead, in accordance to direction from the program manager, will also allocate
resources and move personnel if necessary.
The final level of the organization chart shows the technical personnel involved in the
program. The software team will consist of a skilled database programmer, with experience in
software process development, and an application support engineer, responsible for the installation
and running of all necessary software applications.
The primary function of the hardware lead is to insure that all necessary computer and
electronic hardware is installed correctly, and functioning according to specifications. A
technician will be assigned to install and test the hardware.
The third segment of the development team is test and integration. A qualified
electronic/system test engineer and technician will support test and integration. The organizational
structure is designed to maximize efficient use of the skills of the technical staff while providing
the necessary skills to design and implement this project. Effective communication is very
important in order for this to be successful, and the leadership and team structure has been
organized accordingly.
Automated Data Transmission System
Project Organization Chart
8/3/2019 ADTS Paper Week 5
9/28
Allen, Augurson, Gamboa, Harris, Snyder 9
Task/Responsibility Matrix
The following diagram lists Statement Of Work (SOW) duties assigned to each of the
members of this project. This chart represents the matrix of tasks and responsibilities, and the
USAF
Project Management
Technical Staff
Admin Support
A d m i n A s
D a t a b a s A p p . S u p W e b P r
S o f t w a r e
T e c h n i c
H a r d w a r e
T e s t E n g T e s t T e c
T e s t / I n t e g S y s t e m A
D e v e l o p m e n
P r o j e c t M a M i l i t a r y L i
T e c h S e r g
1 2 t h A i r F o
P r o j e c t S p
8/3/2019 ADTS Paper Week 5
10/28
Allen, Augurson, Gamboa, Harris, Snyder 10
individuals that are necessary to perform these duties. The number scheme is the same one used
for Work Breakdown Structure, which is used to identify similar processes.
8/3/2019 ADTS Paper Week 5
11/28
Allen, Augurson, Gamboa, Harris, Snyder 11
Work Breakdown Structure
The Work Breakdown Structure (WBS) of this project is demonstrated in two methods. An
outline shows all work details in a simple text display. This is used to summarize the required
8/3/2019 ADTS Paper Week 5
12/28
Allen, Augurson, Gamboa, Harris, Snyder 12
tasks in a step-by-step fashion. Following the outline, a graphical representation is given in the
form of a hierarchy chart. The numbering scheme used in the WBS graphical chart is the same
one used in the WBS outline, the Gantt chart, and Task/Responsibility Matrix. The following
outline describes the details for the Work Breakdown Structure (WBS) of this project in outline
format. It describes all task involved in creating an automated data transmission system.
Automated Data Transmission System WBS Outline
1.0 Analyze1.1 Current Process
1.1.1 Question operators
1.1.2 Question customers1.1.3 Determine problem
1.2 Propose Solution1.2.1 Desired outcome1.2.2 Outline solution1.2.3 Solution requirements
2.0 Design2.1 Hardware
2.1.1 Determine needs2.1.2 Block diagram of needs
2.2 Software2.2.1 Electronic Mail filter2.2.1.1 Define constraints
2.2.2 Conversion process2.2.3 Web Pages
2.2.3.1 Design web layout2.2.3.2 Document web configuration
2.2.4 Database2.2.4.1 Define data2.2.4.2 Define reports
3.0 Implement3.1 Purchase Hardware
3.1.1 Printer 3.1.2 STU-III3.1.3 Secure Fax machine3.1.4 Database server
8/3/2019 ADTS Paper Week 5
13/28
Allen, Augurson, Gamboa, Harris, Snyder 13
3.1.5 Web server3.2 Build Software
3.2.1 Electronic mail filter3.2.2 Electronic mail conversion script3.2.3 Web pages
3.2.4 Database3.3 Install and Test3.3.1 Hardware
3.3.1.1 Printer3.3.1.2 STU-III3.3.1.3 Secure Fax machine3.3.1.4 Database Server3.3.1.5 Web Server
3.3.2 Software3.3.2.1 Electronic mail filter3.3.2.2 Electronic mail conversion script
3.3.2.3 Web pages3.3.2.4 Database3.4 Walk through of process3.5 Deliver Product
4.0 Support4.1 Write standard operating procedures4.2 Write maintenance contract4.3 Train users
Automated Data Transmission System WBS Diagram
The following chart represents the work breakdown structure outline describing all task
involved in creating an automated data transmission system. Due to its size, the chart is split into
two separate diagrams. The first diagram shows details for the first two major items listed on the
hierarchy chart. The second diagram illustrates last two major items in this chart, and the dotted
boxes refer to items detailed on the other chart.
8/3/2019 ADTS Paper Week 5
14/28
Allen, Augurson, Gamboa, Harris, Snyder 14
Automated Data
Transmission System
2.0 Design1.0 Analyze
1.1 Current Process1.2 Proposed
Solution2.1 Hardware 2.2 Software
1.1.3 Determine
problems
1.1.1 Question
operators
1.1.2 Question
customers
1.2.3 Solution
requirements
1.2.2 Outline
solution
1.2.1 Desired
outcome
2.1.1 Determine
needs
2.1.2 Block
diagram of needs
2.2.1 Electronicmail filter
2.2.1.1 Define
constraints
2.2.2 Conversion
process2.2.3 Web Pages 2.2.4 Database
2.2.3.1 Design web
layout
2.2.4.1 Define
data
2.2.3.2 Document
web configuration
2.2.4.2 Define
reports
3.0 Implement
Continued on pg.2
4.0 Support
Continued on pg.2
1
4.0 Support3.0 Implement
Automated Data
Transmission System
3.1.1 Printer
3.1.2 STU-III
3.1.4 Database
server
4.2 Write maintenance
contract
4.1 Write SOP
4.3 Train users
2.0 Design
Continued on pg.1
1.0 Analyze
Continued on pg.1
2
3.3 Install and Test3.1 Purchase
hardware3.2 Build software
3.4 Walk through
of process
3.5 Deliver
product
3.1.3 Secure fax
machine
3.1.5 Web server
3.2.3 Web Pages
3.2.1 Electronic mail
filter
3.2.2 Electronic mail
conversion script
3.2.4 Database
3.3.2 Software3.3.1 Hardware
3.3.1.3 Secure fax
machine
3.3.1.5 Web
server
3.3.1.4 Database
server
3.3.1.2 STU-III
3.3.1.1 Printer
3.3.2.3 Web
pages
3.3.2.2 Electronic
mail conversion
script
3.3.2.4 Database
3.3.2.1 Electronic
mail filter
8/3/2019 ADTS Paper Week 5
15/28
Allen, Augurson, Gamboa, Harris, Snyder 15
Project Reporting
Each Tuesday at 9 a.m., throughout the duration of the project, the project team will meet
in the corporate conference room to analyze the project status. Between meetings, the project
manager will deliver project updates via e-mail to the applicable staff members. Some verbal
communication will be utilized for minor routine project tasks and to establish contingency plans
in the event of an emergency situation
Project Schedule
This section of the ADTS proposal addresses the project schedule. The following Gantt
chart depicts the planned schedule for all of the tasks in this project that were outlined in the work
breakdown structure. Total project length is planned for 48 days and will be divided into four
distinct phases. This will insure that every task within the program is accounted for, and will
enhance project management and control.
The four stages of the plan encompass an Analyze Situation (11 days), Design Solution (8
days), Implement Solution with testing (20 days), and the Support stage (9 days). Tasks have been
planned to occur concurrently as much as possible within the framework of the project team
structure.
Dependencies are shown on the Gantt chart as links, and the critical path is highlighted in
red. The design phase is planned in the most efficient manner possible, utilizing the three separate
development teams of hardware, software, and test. This allows completion of design activities in
only 8 days. Milestones are shown at the end of each project stage to enable project tracking.
Pending approval the project is scheduled to begin on Monday February 11th and finish on
Wednesday April 17th.
8/3/2019 ADTS Paper Week 5
16/28
8/3/2019 ADTS Paper Week 5
17/28
8/3/2019 ADTS Paper Week 5
18/28
8/3/2019 ADTS Paper Week 5
19/28
Allen, Augurson, Gamboa, Harris, Snyder 19
This documentation is intended to provide an accurate management tool that can be used
and reviewed during the important weekly project communication meetings. The team now has a
baseline for the project that the Project Manager can use to determine progress, successes, failures,
and any potential barriers to the development and deployment of this system.
8/3/2019 ADTS Paper Week 5
20/28
Allen, Augurson, Gamboa, Harris, Snyder 20
8/3/2019 ADTS Paper Week 5
21/28
Allen, Augurson, Gamboa, Harris, Snyder 21
8/3/2019 ADTS Paper Week 5
22/28
Allen, Augurson, Gamboa, Harris, Snyder 22
8/3/2019 ADTS Paper Week 5
23/28
Allen, Augurson, Gamboa, Harris, Snyder 23
8/3/2019 ADTS Paper Week 5
24/28
Allen, Augurson, Gamboa, Harris, Snyder 24
8/3/2019 ADTS Paper Week 5
25/28
8/3/2019 ADTS Paper Week 5
26/28
Allen, Augurson, Gamboa, Harris, Snyder 26
Performance Measurement
When measuring performance, there are many variables to consider. All of the major
variables can be identified as milestones on the Gantt charts presented as the project schedule. The
project manager will closely follow the progress of the project utilizing these Gantt charts as a tool
in charting the performance of the project. Every milestone on the Gantt chart indicates a
significant portion of the overall completed project. In the event of delays or setbacks, the project
manager will have to call a meeting with his managers to create a new plan to get the project back
on schedule. This portion of the project is especially crucial if the critical path is affected. The
project manager should present a weekly progress report that indicates the percentage of the
project that has been completed. When the percentile is out of an acceptable range, the project
manager should be able to devise a plan to bring the project back within acceptable tolerances.
Performance Evaluation and Reporting
The project manager will conduct a check on a weekly basis, figuring the actual cost of
work performed, the budgeted cost of work performed, and the budget at completion. The project
manager will be in charge of converting this data into useful information. For example, the Cost
Performance Index and Scheduled Performance Index are used to compare budget and work
completed. To estimate the cost performance index, the project manager will divide the budgeted
cost of work performed by the actual cost of work performed. The scheduled performance index
can be estimated by dividing the budgeted cost of work performed by the budgeted cost of work
scheduled. The project manager will also be in charge of tracking numbers by building an Earned
Value Table. When a portion of the project is completed, an earned value for that portion of the
project is credited. If the project is on schedule, the costs of work performed will be equal to the
8/3/2019 ADTS Paper Week 5
27/28
Allen, Augurson, Gamboa, Harris, Snyder 27
budgeted cost of work scheduled. If there are any scheduled or cost variances, the project manager
can forecast the cost to completion and the cost at completion. With this information, the project
manager can communicate to upper management and to the consumer. Through these weekly
briefings, all the variable factors can be assessed, and if corrective action is necessary, it can be
made without affecting the project cost at completion.
Project Termination
The project will have met all of its objectives when all of the tasks are complete. The
project manager must conduct a post-audit to justify that all vendors have been paid; this may
include closing all accounts connected with the project. The project manager will then prepare a
report stating that the project was a success because it was completed on time and under budget.
This report will also include a termination checklist. The checklist should include account
balances, closure of accounts, and notification of project termination to all stakeholders in the
project. A list of employees that need to be reassigned may also be necessary. This will be helpful
for a timely and effective transfer. Once all of this is complete, the project can be officially
terminated.
Summary of Lessons Learned
In the development of the project management plan, the concept of failures within the plan
evolved. These failures need to be recognized and dealt with in an appropriate manner. The major
contributors to project failure are as follows:
A) The project management model is inadequate. It does not fit the objectives and
environment, and does not receive support from top management.
8/3/2019 ADTS Paper Week 5
28/28
Allen, Augurson, Gamboa, Harris, Snyder 28
B) If the project manager fails to properly utilize basic management skills, the success of the
project would be in jeopardy.
C) Failure to fully define project goals and the use of vague wording will lead to poor
estimations of time and resources. In turn, the project will go through various changes
during its life cycle.
D) Failures in planning and controlling the project will occur if all members of the team are
not engaged in the communication loop.
Eliminating the above failures will not guarantee success of the project, but will greatly enhance
the opportunity for a successful project.