51
Acton Campus Building #57 Hazardous Materials Report This document is uncontrolled once printed. You must consult the individual Building Register prior to work commencing.

Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Acton Campus

Building #57

Hazardous Materials Report

This document is uncontrolled once printed.

You must consult the individual Building

Register prior to work commencing.

Page 2: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Contents Page

1. Revision Table

2. ANU Hazardous Materials Register

3. ANU Hazardous Materials Maintenance Log

4. WSP Hazardous Materials Report Dated 14 February 2019

Page 3: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

1. Revision Table – Building 57

Rev.

Nature of changes

Approval

Date

WSP 15/02/2019

1 Building 57 – Hazardous Materials Survey SWE 03/02/2014

2 Building 57 – Hazardous Materials Survey WSP 14/02/2019

3 Building 57 HazMat Survey – PS112993Other- Addition of ANU Hazardous Materials Register- Addition of ANU Hazardous Materials MaintenanceLog.- Addition of ANU Documentation

Page 4: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

2. ANU Hazardous Materials Register

Page 5: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Site Location: Building 57, Acton Campus

Assessor: Anton Delac, Imam Malik, Joseph McNeill Inspection Date: 04 February 2019

Next Reinspection Date: February 2024

Sample No.

Res

ults

Phot

o ID

Description Location

Asb

esto

s Ty

pe

Con

ditio

n

Acc

essi

bilit

y

Airb

orne

Pot

entia

l

Expo

sure

Pot

entia

l

Ris

k Sc

ore

Act

ion

Prio

rity

Qua

ntity

(lm

, m2,

m3)

Actions/Comments

Asbestos Containing Materials

External Materials

WSP-015491 A, CHRefer toWSPReport

Fibre Cement Sheet Above South East porch adjacent stairs, window infill panel 1 2 3 1 2 12 L ~3m²

Maintain in good condition.Remove in accordance with WHS ACT document"How to Safely Remove Asbestos, Code ofPractice 2014" prior to any majorrefurbishment/demolition.

Internal Materials

WSP-015496 A, CHRefer toWSPReport

Fibre Cement Sheet Electric cupboard adjacent tea room behind stairs 1 2 1 2 2 8 L ~4m²

Maintain in good condition.Remove in accordance with WHS ACT document"How to Safely Remove Asbestos, Code ofPractice 2014" prior to any majorrefurbishment/demolition.

Lead Paint

WSP-015484 0.13%Refer toWSPReport

Blue paint systemwith white paintunderneath

External - Paint to Window - - - - - - L Throughout

Peel off in some areas. Recommendations toeither 1) Encapsulate and/or monitor the statuson the paint, 2) Remove in accordance withstate and national guidelines.

WSP-015485 0.38%Refer toWSPReport

Blue paint systemwith red paintunderneath

External - Front porch metal structures - - - - - - L Throughout

Peel off in some areas. Recommendations toeither 1) Encapsulate and/or monitor the statuson the paint, 2) Remove in accordance withstate and national guidelines.

Ozone Depleting Substances (ODS)

VisualObservation /Factory Label

Refrigerant R22Refer toWSPReport

Refrigerant R22 Roof - Air Conditioning Units (Lennox) - - - - - - L 4 UnitsMaintain ingood condition.Remove prior to refurbishment/demolition.

Page 6: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

VisualObservation /Factory Label

Refrigerant R22Refer toWSPReport

Refrigerant R22 Ground - South East corner AC Unit (Lennox) - - - - - - L 1 UnitMaintain ingood condition.Remove prior to refurbishment/demolition.

Synthetic Material Fibres (SMF)

Presumed SMFRefer toWSPReport

Insulation External - South East corner hot water unit - - - - - - L 1 UnitMaintain in good condition. Remove inaccordance with state and national guidelinesprior to any major refurbishment/demolition.

VisualAssessment

SMFRefer toWSPReport

Insulation External - South East cotner AC duct insulation - - - - - - L ThroughoutMaintain in good condition. Remove inaccordance with state and national guidelinesprior to any major refurbishment/demolition.

WSP-015494 SMFRefer toWSPReport

Wall Insulation Internal wall insulation - - - - - - L ThroughoutMaintain in good condition. Remove inaccordance with state and national guidelinesprior to any major refurbishment/demolition.

VisualAssessment

SMFRefer toWSPReport

Insulation Batts Level 2 - Ceiling cavity - - - - - - L ThroughoutMaintain in good condition. Remove inaccordance with state and national guidelinesprior to any major refurbishment/demolition.

No asbestos detected

WSP-015487 NADRefer toWSPReport

Mastic South East corner AC duct joint mastic - - - - - - - - No further action required.

WSP-015483 NADRefer toWSPReport

Mastic External window putty - - - - - - - - No further action required.

WSP-015490 NADRefer toWSPReport

Mastic Northern external window putty - - - - - - - - No further action required.

WSP-015493 NADRefer toWSPReport

Vermiculite Ceiling spray vermiculite to internal shower / toilet - - - - - - - - No further action required.

WSP-015495 OF, NADRefer toWSPReport

Fibre Cement Sheets Wall lining to shower and toilet - - - - - - - - No further action required.

WSP-015499 OF, NADRefer toWSPReport

Ceiling Tiles Suspended hallway ceiling tiles - - - - - - - - No further action required.

Lead free Paints

WSP-015486 0.03% w/wRefer toWSPReport

White Paint system External - Front porch concrete ceiling - - - - - - - - No further action required.

WSP-015489 0.04% w/wRefer toWSPReport

Beige Paint System External - North East porch wall / ceiling - - - - - - - - No further action required.

WSP-015492 <0.005 %w/wRefer toWSPReport

Blue / green Paintsystem

External - West stairs - - - - - - - - No further action required.

WSP-015497 0.094% w/wRefer toWSPReport

Yellow Paint system East stairs hand rail - - - - - - - - No further action required.

Page 7: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

WSP-015488 0.008% w/wRefer toWSPReport

White Paint system External - South east corner AC duct paint - - - - - - - - No further action required.

WSP-015498 0.02% w/wRefer toWSPReport

Pink Paint system East stairs - - - - - - - - No further action required.

Polychlorinated Biphenyls (PCB'S)VisualAssessment

-Refer toWSPReport

Light Fitting Throughout - Fluroescent lights - - - - - - - - No further action required.

Page 8: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

3. ANU Hazardous Materials Maintenance Log

Page 9: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Hazardous Materials Maintenance Log

Site: Building 57

ANU Hazardous Materials Maintenance LogThe following log should be maintained by the responsible person. It should contain information relating to the on-going maintenance or control measures associatedwith ACM including removal, remedial works, repairs, inspection, monitoring and clearance details etc.Site: Building 57Date Scope/Location Carried out by Result/Comments Entered by04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik &

Joseph McNeillUndertake a survey of the site to identify and access hazardous materials.

Jaeger Swanepoel – WSP14/02/2019

15/02/2019 Hazardous Materials Survey Report completed – Building 57Additions – ANU Cover page, Register, Maintenance Log

Jaeger Swanepoel Additions Jaeger Swanepoel – WSP 15/02/2019

Page 10: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

4. WSP Hazardous Material Report

Page 11: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

THE AUSTRALIAN NATIONAL UNIVERSITY

BUILDING J057 - NUCLEAR PHYSICSGARRAN ROAD, ACTON ACT 2601

HAZARDOUS MATERIALS SURVEY

FEBRUARY 2019 CONFIDENTIAL

Page 12: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

This document may contain confidential and legally privileged information, neither of which are intended to be waived, and must be used only for its intended purpose. Any unauthorised copying, dissemination or use in any form or by any means other than by the addressee, is strictly prohibited. If you have received this document in error or by any means other than as authorised addressee, please notify us immediately and we will arrange for its return to us.

PS112993-HAZ-REP-ANU Building 57 Confidential February 2019

Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPLevel 1, 121 Marcus Clarke Street Canberra ACT 2601PO Box 1551 Canberra ACT 2600

Tel: +61 2 6201 9600Fax: +61 2 6201 9666wsp.com

REV DATE DETAILS

1 14/02/2019 Original

NAME DATE SIGNATURE

Prepared by: Jaeger Swanepoel 13/02/2019

Reviewed by: Imam Malik 14/02/2019

Approved by: Anton Delac 14/02/2019

Page 13: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

1 INTRODUCTION................................................................A-11.1 LEGISLATIVE REQUIREMENTS ...........................................A-1

1.2 OBJECTIVES ..........................................................................A-2

1.3 SCOPE OF WORK ..................................................................A-21.3.1 TASK 1 – PRE- SITE INSPECTION PREPARATION.........................A-21.3.2 TASK 2 – SITE INSPECTION AND SAMPLE COLLECTION .............A-21.3.3 TASK 3 – ANALYSIS OF SUSPECT MATERIALS .............................A-21.3.4 TASK 4 – REPORTING & HAZARDOUS MATERIALS

REGISTER ..........................................................................................A-2

2 METHODOLOGY...............................................................A-32.1 GENERAL ...............................................................................A-3

2.2 IDENTIFICATION OF MATERIAL...........................................A-32.2.1 ASBESTOS CONTAINING MATERIAL...............................................A-32.2.2 LEAD-BASED PAINT SYSTEMS ........................................................A-32.2.3 SYNTHETIC MINERAL FIBRES (SMF) MATERIALS.........................A-32.2.4 POLYCHLORINATED BIPHENYLS (PCBS) .......................................A-32.2.5 OZONE DEPLETING SUBSTANCES (ODS) ......................................A-4

3 RESTRICTIONS / INACCESSIBLE AREA ....................A-5

4 SURVEY FINDINGS ..........................................................A-6

5 RECOMMEDATION FOR REMOVAL............................A-85.1 GENERAL SITE ESTABLISHMENT.......................................A-8

5.2 ENCLOSURE SET-UP ............................................................A-8

5.3 NON-FRIABLE ACM FROM THE BUILDING.........................A-9

5.4 FRIABLE ACM FROM THE INTERIOR OF THE BUILDING................................................................................A-9

5.4.1 REMOVAL OF GASKET OR ROPE SEALS .......................................A-95.4.2 REMOVAL OF ASBESTOS-BACKED VINYL ...................................A-10

5.5 SYNTHETIC MINERAL FIBRES (SMF) ................................A-10

5.6 LEAD .....................................................................................A-10

5.7 POLYCHLORINATED BIPHENYLS (PCBS) ........................A-11

5.8 OZONE DEPLETING SUBSTANCES (ODS)........................A-11

6 CLOSE...............................................................................A-12

TABLE OF CONTENTS

Page 14: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

APPENDICES

APPENDIX A – PHOTOGRAPHS

APPENDIX B – HAZARDOUS MATERIALS REGISTER

APPENDIX C – CERTIFICATES OF ANALYSIS

APPENDIX D – FLOOR PLAN

APPENDIX E – RISK ASSESSMENT

APPENDIX F – STATEMENT OF LIMITATIONS

Page 15: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-1

1 INTRODUCTIONWSP Australia was engaged by Brett Morrison the Asset Planning Officer for the Engineering & Technical Services, Facilities and Services team of The Australian National University to undertake a hazardous materials survey of the Building J057 – “Nuclear Physics” located at Garran Road, Australian National University (ANU), Acton ACT 2601.

The purpose of the survey was to identify the presence of hazardous materials and provide a management plan for the building.

The survey was undertaken by licensed asbestos assessors, Anton Delac (License no. AA00007), Imam Malik (License no. LAA001048) and Joseph McNeill (License no. AA464842), on behalf of WSP Australia on Monday 4th February 2019.

For the purpose of this report, the term hazardous materials (HAZMAT) refers to the following:

— Asbestos containing materials (ACM);

— Lead based paints;

— Synthetic mineral fibre (SMF) materials,

— Light fittings and accessible electrics that may contain polychlorinated biphenyls (PCB) capacitors and;

— Ozone depleting substances (ODS)

This report provides a summary of the methodology, references, purpose and scope of works.

No one section or part of a section of this Report should be taken as giving an overall idea of this Report. Each section must be read in conjunction with the whole of this Report, including the hazardous materials registers and sample results.

1.1 LEGISLATIVE REQUIREMENTSThe survey works and production of this report have been undertaken in accordance with the requirements of the following documents:

— Work Health and Safety Regulation 2017

— Work Health and Safety (How to Manage and Control Asbestos in the Workplace: Code of Practice) 2014 (ACT)

— Work Health and Safety (How to Safely Remove Asbestos: Code of Practice) 2014 (ACT).

— National Code of Practice for the Control and Safe Use of Inorganic Lead at Work 1994.

— National Code of Practice for the Safe Use of Synthetic Mineral Fibres 1990.

— ANZECC (1997) Identification of PCB-containing Capacitors: An information booklet for Electricians and Electrical Contractors.

— AS 1216, Standards Association of Australia, Classification and Class Labels for Dangerous Goods

— AS 1319, Standards Association of Australia, Rules for the Design and Use of Safety Signs for the Occupational Environment

— AS 1715, Standards Association of Australia, Selection, Use and Maintenance of Respiratory Protective Devices

— AS 1716, Standards Association of Australia, Respiratory Protective Devices

— AS4361.2 2017 Guide to Lead Paint Management Part 2: Residential, Public & Commercial buildings

— AS 2601 Demolition of Structures

Page 16: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-2

— AIOH positional paper: Synthetic Mineral Fibres and Occupational Health Issues 2011

— NOHSC (1989b). Guidance Note on the Membrane Filter Method for the Estimation of Airborne Synthetic Mineral Fibres. [NOHSC:3006 (1989)] June 1989

— National Standard for Synthetic Mineral Fibres [NOSHC:1004 (1990)]

— National Code of Practice for the Safe Use of Synthetic Mineral Fibres [NOSHC:2006 (1990)]

— AS 3640 Workplace atmospheres - Methods for sampling and gravimetric determination of inhalable dust 2009

1.2 OBJECTIVESThe objectives of the hazardous material survey were to:

— identify hazardous materials;

— provide a qualitative risk assessment of the hazardous materials identified;

— provide recommendations on the control measure strategies in the event of any refurbishment or demolition works; and

— prepare a hazardous materials register and hazardous materials management plan to ensure compliance with state legislation, Commonwealth codes of practice and Australian Standards as outlined in Section 1.1 above.

1.3 SCOPE OF WORKThe investigation will be undertaken to identify and document all visible and accessible hazardous materials (if identified) as far as reasonably practicable.

The scope of works covers the following:

1.3.1 TASK 1 – PRE- SITE INSPECTION PREPARATION

— Provide a Safe Work Method Statement (SWMS) for the activities on site, ensuring hazards identified within are safely inspected for asbestos and documented within a detailed hazardous material(s) register.

1.3.2 TASK 2 – SITE INSPECTION AND SAMPLE COLLECTION

— Site investigations, includes identification of hazardous materials, location, type, condition, extent and qualitative risk assessment;

— Sampling of representative materials suspected of containing asbestos; and

— Sampling of representative paint systems for the purpose of confirming lead content.

1.3.3 TASK 3 – ANALYSIS OF SUSPECT MATERIALS

Suspected ACM and lead containing paint collected during the survey were sent to NATA accredited laboratories for analysis.

1.3.4 TASK 4 – REPORTING & HAZARDOUS MATERIALS REGISTER

All data generated from the survey was used to update the hazardous materials register/spread sheet, which identifies and defines the condition of the materials, lists any factual findings and provides consideration to their removal priority.

Page 17: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-3

2 METHODOLOGY

2.1 GENERALThe identification of hazardous materials involves a combination of visual inspection of the accessible areas of the building/structure and the collection of representative samples of the suspect materials for the purpose of analytical confirmation. Where identical suspect materials are detected at different locations, visual confirmation only may have been made rather than additional sample collection.

2.2 IDENTIFICATION OF MATERIAL

2.2.1 ASBESTOS CONTAINING MATERIAL

Representative samples of materials suspected of containing asbestos were collected and analysed at our in-house NATA accredited laboratory. The identification of asbestos fibres is based on using polarised light microscopy supplemented with dispersion staining techniques. This is detailed in Australian Standard 4964-2004 ‘Method for the qualitative identification of asbestos in bulk samples’. Asbestos samples were only collected for analysis where the safety of personnel would not be compromised. Sampling was conducted in accordance with the WSP’s in house survey guide and the United Kingdom Health & Safety Executive publication, ‘Methods for the Determination of Hazardous Substances 100, surveying, sampling and assessment of asbestos-containing materials’.

2.2.2 LEAD-BASED PAINT SYSTEMS

Representative samples of paint were collected and analysed at Envirolab Services NATA Accredited Laboratory. Lead content is reported in percentage weight by weight and compared with AS4361.2-2017, Guide to Lead Paint Management, Part 2: Residential and Commercial Buildings lead containing paint system level of 0.1 per cent (w/w) of the dried film.

2.2.3 SYNTHETIC MINERAL FIBRES (SMF) MATERIALS

The survey for SMF was undertaken in accordance with the guidelines documented in the Code of Practice for the Safe Use of Synthetic Mineral Fibres [NOHSC: 2006 (1990)]. This includes documenting any materials visually assessed on site as being consistent with SMF.

Our experienced surveyor visually identified and recorded the presence of synthetic mineral fibre products onsite.

The roof space and all levels containing ceiling voids must be visually inspected to verify the presence of SMF. Additionally, special detail must also be paid to pipework and ducting insulations types.

2.2.4 POLYCHLORINATED BIPHENYLS (PCBS)

Where access was available and power was isolated representative examples of each major type of fluorescent light fittings were examined to determine which lights were fitted with PCB containing ballast capacitors. The details of the brand, model of each capacitor and capacity were recorded and checked against with the ANZECC database of known PCB capacitors and PCB free capacitors.

The Australian and New Zealand Environment Conservation Council ‘Polychlorinated Biphenyls Management Plan, November 1996’ outlines the National Strategy for the management of PCBs.

Page 18: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-4

The document defines PCB materials and wastes as follows:

Table 2.1 PCB concentration classification

PCB concentration Waste classification

<2 mg/kg - PCB free.

2 mg/kg - <50 mg/kg - Non-Scheduled PCB material or waste.

>50 mg/kg - Scheduled PCB material or waste.

>100,000 mg/kg (10%) - Concentrated PCB material.

2.2.5 OZONE DEPLETING SUBSTANCES (ODS)

The main cause of ozone depletion and the ozone hole is man-made chemicals, especially man-made halocarbon refrigerants, solvents, propellants, and foam-blowing agents which are commonly referred to as ozone-depleting substances (ODS).

The identification of potentially ODS, such as industrial refrigerators and air conditioning units, were visually identified during the current survey.

Where ODS have been previously identified at the site, they have been included in the updated HAZMAT register.

Page 19: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-5

3 RESTRICTIONS / INACCESSIBLE AREA

Every effort was made to access all areas of the buildings; however, some areas were restricted due to building damage, excessive heights and electrical hazards. This included, but is not limited to the following areas:

— The roof-line to all buildings and structures over 3.0m in height;

— Inground and underground services (pits / pipes / etc);

— Inset pipe-works to the brick/concrete walls

— Under ceramic tiles to walls and floors

— All live electricity and mechanical plant/equipment

— All electrical boards and circuit breakers.

In general, a presumption should be made that hazardous materials are present within areas not able to be accessed during the survey. Caution should be given during demolition works and works ceased if suspected hazardous materials are encountered and an assessment undertaken by a suitably qualified hazardous materials expert.

Page 20: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-6

4 SURVEY FINDINGS

This section of the report summarises the findings of the asbestos materials types identified and their general locations. All findings are presented in Appendix A: Asbestos Materials Register. The register is supplemented with photos within Appendix B: Photographs

Table 4.1 Asbestos Containing Materials

LOCATION DESCRIPTION COMMENTS

External - Window infill panel above South East porch adjacent stairs

Asbestos containing fibre cement sheet

Maintain in good condition. Remove in accordance with WHS ACT document "How to Safely Remove Asbestos, Code of Practice 2014" prior to any major refurbishment/demolition.

Internal - Electrical cupboard adjacent tea room and stairs, wall lining

Asbestos containing fibre cement sheet

Maintain in good condition. Remove in accordance with WHS ACT document "How to Safely Remove Asbestos, Code of Practice 2014" prior to any major refurbishment/demolition.

Table 4.2 Synthetic Materials (SMF’s)

LOCATION DESCRIPTION COMMENTSExternal - South East corner hot water unit

Presumed SMF Insulation Maintain in good condition. Remove in accordance with state and national guidelines prior to any major refurbishment/ demolition.

External – AC duct insulation SMF Insulation Maintain in good condition. Remove in accordance with state and national guidelines prior to any major refurbishment/ demolition.

Internal – Wall cavity to internal walls SMF Insulation Maintain in good condition. Remove in accordance with state and national guidelines prior to any major refurbishment/ demolition.

Internal – Level 2, Ceiling cavity SMF Insulation batts Maintain in good condition. Remove in accordance with state and national guidelines prior to any major refurbishment/ demolition.

Table 4.3 Lead Based Paint

LOCATION DESCRIPTION COMMENTS

External, Paint to Windows Blue Paint system Peel off in some areas. Recommendations to either

1) Encapsulate and/or monitor the status on the paint, 2) Remove in accordance with state and national guidelines.

Front porch metal structures Blue Paint system Peel off in some areas. Recommendations to either

1) Encapsulate and/or monitor the status on the paint, 2) Remove in accordance with state and national guidelines.

Page 21: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-7

Table 4.4 Ozone Depleting Substances (ODS’s)

LOCATION DESCRIPTION COMMENTSExternal – South east corner - Lenox Air Conditioning Unit

Refrigerant R22 Maintain in good condition. Remove in accordance with state and national guidelines prior to any major refurbishment/ demolition.

Building Roof - Lenox Air Conditioning Units

Refrigerant R22 Maintain in good condition. Remove in accordance with state and national guidelines prior to any major refurbishment/ demolition.

Table 4.5 Polychlorinated Biphenyls (PCB’s)

LOCATION DESCRIPTION COMMENTS

Building throughout No PCB capacitors No further action required.

Page 22: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-8

5 RECOMMEDATION FOR REMOVAL

5.1 GENERAL SITE ESTABLISHMENT The asbestos containing materials should be removed prior to the commencement of demolition works.

The asbestos removal works are to be conducted in accordance with the SafeWork Australia document How to Safely Remove Asbestos – Code of Practice.

All asbestos removal, transport and disposal must be performed in accordance with ACT legislative requirements.

Where asbestos cannot be removed prior to mechanical demolition (e.g. where structures are unsound, inhibiting access to asbestos removal personnel), dust suppression must be employed during demolition. All building waste suspected of containing asbestos must be removed as asbestos waste and placed in appropriately lined bins/trucks for disposal to an approved waste facility.

It is recommended that the removal works to be undertaken by a licenced asbestos removal contractor. The removal to be undertaken in accordance with the code of practice noted above and by a licenced asbestos removal contractor.

Environmental management and WHS procedures should be put in place for the asbestos removal during demolition works to protect the workers, surrounding residents and environment.

It is recommended that a licenced asbestos assessor is engaged to carry out asbestos fibre air monitoring during the removal of the asbestos materials if asbestos removal works are to take place during other demolition works. The monitoring is to be conducted in accordance with the National Occupational Health and Safety Commission Guidance Note on the Membrane Filter Method for the Estimating Airborne Asbestos Fibre, 2nd Edition [NOHSC 3003(2005)], April 2005, by a NATA accredited laboratory such as WSP Australia.

At all times “H Class” asbestos vacuums and negative air units fitted with HEPA filters are to be used during asbestos removal and remediation. These are to be regularly tested and maintained to operate at 99.995% efficiency, in accordance with the manufacturer’s instructions.

Filters for “H Class” vacuums should conform to the requirements for AS 4260-1997 High efficiency particulate are (HEPA) filters – Classification, construction and performance or its equivalent.

Disposal of asbestos containing material must be undertaken in accordance the SafeWork Australia document How to Safely Remove Asbestos – Code of Practice 2014 and the ACT EPA Guidelines at a land fill site licenced to accept asbestos waste.

5.2 ENCLOSURE SET-UP Potential entry points to the asbestos work area should be signposted and barrier taped in accordance with AS1319-

1994 Safety Signs for the Occupational Environment.

A minimum 3 stage decontamination unit with clean change-shower-dirty shower-dirty change areas must also be installed and used under negative air pressure. Water from the decontamination unit should be captured, filtered, and the filters are to be disposed of as asbestos waste.

Construction of the main negative air enclosures may require the inclusion of the outer brick walls in order to maintain negative air conditions in the interior of the building. To obtain negative air conditions in the roof space, the contractor will be required to place plastic sheeting (minimum of 200µm thickness) over the roof tiles or roof sheets, eaves and back to the brick outer walls. All windows and penetrations to the dwelling such as vents will be sealed with 200µm plastic sheeting.

Page 23: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-9

In order to complete the above it may be necessary to remove items such as awnings, solar panels, fences, trellises or other fittings attached to the house, that may impact upon enclosure or scaffold set-up.

Once the enclosure set-up is complete an asbestos assessor is conduct an enclosure integrity test to all the seals of the enclosure and to measure the flow of the negative pressure units to ensure that it can maintain negative pressure. Work can only commence once the asbestos assessor has deemed the enclosure to be “satisfactory” to do so. A manometer is to be attached to the enclosure to ensure that negative air pressure within is above 12 kPa.

5.3 NON-FRIABLE ACM FROM THE BUILDING Remove non-friable ACM material with minimal breakage.

Maintain work in progress air monitoring (Control and Perimeter Locations).

Refer to Worksafe ACT How to Safely Remove Asbestos Code of Practice 2014.

Please Note that If present, all nails, screws and fasteners associated with ACM must be removed and disposed of as asbestos contaminated waste. All timber or metal battens must be decontaminated with the use of a HEPA vacuum cleaner.

Place fragments of AC Sheeting material in 200µm polythene bags which are no longer than 1200mm and no wider than 900mm.

Place sheets of AC Sheeting directly into a bin in close proximity to works, lined with 200 µm plastic, and kept damp to minimise the generation of airborne asbestos. Ensure that the bin is labelled and if to remain on site for any period of time, kept secure at all times.

In relation to the asbestos containing joint mastic and electrical backing board, polythene sheeting drop sheets should be placed under the material. The material removed with minimal breakage and placed within 200 µm thick polythene bags or wrapped with 200 µm thick polythene sheeting. Any fixtures or fittings associated with the material such as screws, nails or brackets should be removed asbestos waste or if possible decontaminated. The area should be clear of any visible dust following the removal.

Following the satisfactory clearance inspection and if deemed necessary by the licenced asbestos assessor, tinted PVA solution should be sprayed on timber or metal battens and polythene drop sheets prior to its removal for the work area and disposal.

Following the completion of the above, an ‘emu or sparrow pick’ of the ground surface in proximity to removal works (and along any waste/work route) is to be undertaken to remove any fragments of AC sheeting. All fragments are to be placed in 200 µm thick polythene bags which are no longer than 1200 mm and no wider than 900 mm wide. Bags are to be sealed and double bagged to reduce the risk of the bags splitting.

Once the pick is complete, a clearance is to be conducted by the licenced asbestos assessor.

5.4 FRIABLE ACM FROM THE INTERIOR OF THE BUILDING

5.4.1 REMOVAL OF GASKET OR ROPE SEALS

The asbestos in gaskets and rope from plant and equipment will be friable. An enclosure with negative air extraction units must be used for this type of asbestos removal work. When removing gaskets and rope seals: ensure the plant or equipment is shut down and isolated

dismantle the equipment carefully. Protect any other components with plastic sheeting;

ensure the plant and equipment has been made safe (pipework emptied, electrical supply isolated and equipment shutdown, etc.);

unbolt or unscrew the flange or dismantle the equipment;

Page 24: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-10

once accessible, dampen the asbestos with a fine water mist or similar. Continue dampening the asbestos as more of it is exposed/accessible;

ease the gasket or rope seal away with the scraper and place into the waste container positioned directly beside/beneath it. Keep the area damp and scrape away any residue; and

consider using an industrial vacuum cleaner fitted with a HEPA filter while scraping.

5.4.2 REMOVAL OF ASBESTOS-BACKED VINYL

As asbestos millboard is typically 100 per cent asbestos and very friable. An enclosure with negative air extraction units must be used for this type of asbestos removal work.

The asbestos millboard should be wetted down as the vinyl is peeled from the floor, preferably with the millboard attached.

The vinyl can be cut into strips prior to its removal to facilitate bagging, or it can be rolled into one roll and wrapped securely with plastic, making sure it is totally sealed.

If the vinyl sheeting cannot be removed without leaving some of the asbestos millboard on the floor surface, the remaining asbestos millboard should be wetted down and, when thoroughly soaked, scraped off the floor surface.

Sufficient water should be used to dampen the asbestos millboard, but not so much that run-off or pools of contaminated water will occur.

Alternative removal methods should only be used if they do not result in excessive fibre release from the asbestos millboard and do not result in any additional hazard.

5.5 SYNTHETIC MINERAL FIBRES (SMF)Synthetic Mineral Fibres may be classified as hazardous depending on their age and manufacturing origin. It is therefore recommended that some precautionary measures be implemented to ensure adequate protection of workers from potential exposure.

Where SMF materials are to be handled or disturbed, the precautionary measures as outlined in the National Occupational Health and Safety Commission's National Code of Practice for the Safe use of Synthetic Mineral Fibre Products [NOHSC:2006(1990)] should be observed. The general requirements are as follows:

Personal protective clothing (long sleeve, loose fitting), gloves and half face (Class P1 or P2) respirators should be used, as well as eye protection and head covering in some circumstances.

The work area should be isolated and signposted.

Waste material should be bagged or sealed in solid containers prior to transport and disposal.

5.6 LEAD It is recommended that the easily detachable items containing lead paint do not require to go through the lead paint

removal procedures (i.e. wet sanding, chemical stripping or hand scrapping). However, when these items are removed it is recommended that 200 micron thick drop sheets are to be placed on all ground surfaces in proximity to the works and wrapped in 200 micron thick plastic sheeting to prevent contamination to the ground surfaces surrounding the building.

Items that cannot be easily removed which contain lead paint will be demolished under controlled conditions to reduce limit further ground contamination to the site and the waste will be included with demolition waste. Controls will consist of but not limited too;

Page 25: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-11

Spraying the lead in paint surface with a binding agent to limit potential paint flakes or dust depositing on the ground surface;

Bunding around the demolition area to contain water run-off;

Water dust suppression during the demolition and loading phase; and

A minimum 10 metre exclusion zone around the demolition and loading out of the demolition waste.

As a precautionary and control measure, static lead in air monitoring should be undertaken during the remediation works in accordance with Australian Standard AS 3640-2004 Workplace atmospheres - Method for sampling and gravimetric determination of inhalable dust by an experienced environmental scientist.

Clearance certification should be undertaken at the completion of the removal work. The clearance inspection should to be carried out by an occupational hygienist or licensed asbestos assessor specialised in the management of hazardous materials.

Environmental management and OH&S procedures should be put in place for the remediation works to protect the workers and the environment.

5.7 POLYCHLORINATED BIPHENYLS (PCBS)If the presence of PCB’s can be confirmed with the light fittings the following should be followed for the safe removal;

A detailed and site-specific work scope and technical specification will be developed prior to the removal of ‘hazardous materials’ from the residence;

In accordance with the NSW WHS Regulations 2012 and NSW WHS Act 2012, removal of hazardous materials must be completed by a contractor licensed to remove hazardous materials (i.e. asbestos, lead, PCBs) and must be completed under a site-specific permit. This permit can only be applied for by a licensed and qualified hazardous materials removal contractor; and

Removal of PCB containing materials is recommended to be removed by a qualified contractor with experience in hazardous waste and PCB removal. The removal contractor must follow legislative requirements for the PCB containing materials removal.

5.8 OZONE DEPLETING SUBSTANCES (ODS) Remove in accordance with the AIRAH Refrigerant Handling Code of Practice 2007.

Unit should be de-gassed by a licensed HVAC technician before disposal. As per the ozone protection and synthetic greenhouse gas management regulations 1996 (amended 2016).

Page 26: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-12

6 CLOSEThank you for the opportunity to be involved with the on-going management of hazardous materials at ANU.

If you have any queries regarding this report, please feel free to contact any of the undersigned on +61 2 6201 9600.

Yours sincerely,

Anton Delac

Senior Occupational Hygiene & Hazardous Materials Consultant

OHHS Team Leader - ACT

Licensed Asbestos Assessor - No. AA00007 ACT

On behalf of WSP Australia Pty Limited

Joseph McNeill

Occupational Hygiene Consultant

Licensed Asbestos Assessor - No. AA464842 NT

On behalf of WSP Australia Pty Limited

Imam Malik

Occupational Hygiene Consultant

Licensed Asbestos Assessor - No. LAA001048 NSW

On behalf of WSP Australia Pty Limited

Page 27: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

APPENDIX APHOTOGRAPHS

Page 28: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-14

Photograph 1. External – Window infill panel above South East porch adjacent stairs – WSP-015491 - Chrysotile and Amosite Detected.

Photograph 2. Internal – Electrical cupboard adjacent tea room and stairs, wall lining – WSP-015496 - Chrysotile and Amosite Detected.

Photograph 3. External – South East corner hot water unit insulation – Presumed SMF

Photograph 4. Internal – South East corner AC duct insulation – SMF insulation

Photograph 5. Internal – Internal wall cavity insulation – WSP-015494 – SMF insulation

Photograph 6. Internal – Ceiling cavity – SMF insulation

Page 29: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page A-15

Photograph 7. External – Ground, South East AC unit (Lennox) – Ozone Depleting Substance refrigerant

Photograph 8. External – Roof AC units (Lennox) - Ozone Depleting Substance refrigerant

Photograph 9. External – Blue paint to windows – WSP-0155484 - 0.13% w/w lead detected

Photograph 10. External – Blue paint to front porch metal structure beam – WSP-015485 – 0.38% w/w lead detected

Page 30: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

APPENDIX BHAZARDOUS MATERIALS REGISTER

Page 31: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Building J057 "Nuclear Physics" - Australian Nation University ACT IHT

ACM - Asbestos Containing Material, CH - Chrysotile, A - Amosite, C - Crocidolite, PCB's - Polychlorinated Biphenyls, ODS - Ozone Depleting Substances, NAD - No Asbestos Detected, Pr - Presumed, OF - Organic Fibres Page 1 of 2

Building NameProperty Address Building J057, Garren Road - Acton ACT 2601 Dates of inspection 04-Feb-19 Inaccessible areas • The roof-line to all buildings and structures over 3.0m in height

• Inground and underground services (pits / pipes / etc)• Portions of Ceiling voids• Portion of wall cavities• Inset pipe-works to the walls throughout• All live electricity and mechanical plant/equipment• All electrical boards and circuit breakers

Property DescriptionThe property consist of two storey building whichincorporated many Offices, Workshops, Laboratories,Storage Facilities and Services

Inspected byAnton DelacImam MalikJoseph McNeill

Event Location Application Material Description Sample Number Analytical Result Photo Extent Estimate Friability

Material

Condition

Risk Status

Control

Priority

Control Recommendations/ Comments

Consultant / Hygienist

name

Control action taken Date actioned Contractor details

Building J057 External - Asbestos Containing Materials

1 Above South East porch adjacent stairs,window infill panel Infill panel Fibre Cement Sheet WSP-015491 A, CH 1 3m2

Non Friable F Low

Low

Maintain in good condition. Remove in accordancewith WHS ACT document "How to Safely RemoveAsbestos, Code of Practice 2014" prior to any majorrefurbishment/demolition.

Building J057 Internal - Asbestos Containing Materials

2 Electric cupboard adjacent tea room behindstairs Fibre cement sheet Fibre Cement Sheet WSP-015496 A, CH 2 4m2 Non Friable G Low Low

Maintain in good condition. Remove in accordancewith WHS ACT document "How to Safely RemoveAsbestos, Code of Practice 2014" prior to any majorrefurbishment/demolition.

Building J057 External - No Asbestos Containing Materials

3 South East corner AC duct joint mastic joint mastic Mastic WSP-015487 NAD Throughout Non Friable F - - No futher action required

4 External Window Putty Window putty Mastic WSP-015483 NAD Throughout Non Friable F - - No futher action required

5 Northern external window putty Window putty Mastic WSP-015490 NAD 3m2 Non Friable F - - No futher action required

Building J057 Internal - No Asbestos Containing Materials

6 Ceiling spray vermiculite to internal shower/toilet Vermiculite Ceiling spray Vermiculite WSP-015493 NAD Throughout Friable F - - Throughout the building. No futher action required

7 Wall lining to shower and toilet Fibre cement wall sheeting Fibre cement sheet WSP-015495 OF, NAD 15m2 Friable G - - No futher action required

8 Suspended hallway ceiling tiles Ceiling tiles Tiling WSP-015499 OF, NAD Throughout Friable G - - No futher action required

Building J057 External - Synthetic Mineral Fibre (SMF)

9 South East Corner Hot Water Unit Insulation SMF Insulation Presumed SMF 3 1 unit Friable G Low LowMaintain in good condition. Remove in accordancewith state and national guidelines prior to any majorrefurbishment/demolition.

10 South East Corner AC duct insulation Insulation SMF Insulation Visual Assessment SMF 4 Throughout Friable F Low LowMaintain in good condition. Remove in accordancewith state and national guidelines prior to any majorrefurbishment/demolition.

Building J057 Internal - Synthetic Mineral Fibre (SMF)

11 Internal Wall Insulation Wall Insulation Insulation WSP-015494 SMF 5 Throughtout Friable G Low LowMaintain in good condition. Remove in accordancewith state and national guidelines prior to any majorrefurbishment/demolition.

12 Level 2, Ceiling Cavity Insulation Batts Insulation Visual Assessment SMF 6 Throughtout Friable F Low LowMaintain in good condition. Remove in accordancewith state and national guidelines prior to any majorrefurbishment/demolition.

Page 32: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Building J057 "Nuclear Physics" - Australian Nation University ACT IHT

ACM - Asbestos Containing Material, CH - Chrysotile, A - Amosite, C - Crocidolite, PCB's - Polychlorinated Biphenyls, ODS - Ozone Depleting Substances, NAD - No Asbestos Detected, Pr - Presumed, OF - Organic Fibres Page 2 of 2

Building J057 External - ODS Containing Materials

13 Roof - Air Conditioning Units (Lennox) Refrigerant Refrigerant R22 Factory label ODS 7 4 Units Good NA Low Low Maintain ingood condition.Remove prior to refurbishment/demolition.

14 Ground - South East corner AC Unit(Lennox) Refrigerant Refrigerant R22 Factory label ODS 8 1 Unit Good NA Low Low Maintain ingood condition.

Remove prior to refurbishment/demolition.

Building J057 - PCB's Containing Materials

15 Building throughout Light fitting Light fitting Visual Assessment No PCB found - - - - - - No futher action required

Building J057 External - Lead Paint

16 External - Paint to Window Blue paint system and white paintunderneath Paint WSP-015484 0.13% w/w 9 Throughout NA Fair Med Med

Peel off in some areas. Recommendations to either1) Encapsulate and/or monitor the status on the paint,2) Remove in accordance with state and nationalguidelines.

17 External - Front porch metal structures Blue paint system and red paintunderneath Paint WSP-015485 0.38% w/w 10 Throughout NA Fair Med Med

Peel off in some areas. Recommendations to either 1)Encapsulate and/or monitor the status on the paint,2) Remove in accordance with state and nationalguidelines.

Building J057 External - No Lead Paint

18 External - Front porch concrete ceiling White Paint system Paint WSP-015486 0.03% w/w Throughout - - - - No further action required.

19 External - North East porch wall / ceiling Beige Paint System Paint WSP-015489 0.04% w/w Throughout - - - - No further action required.

20 External - West stairs Blue / green Paint system Paint WSP-015492 <0.005 %w/w Throughout (6m2) - - - - No further action required.

21 East stairs hand rail Yellow Paint system Paint WSP-015497 0.094% w/w Throughout - - - - No further action required.

22 External - South east corner AC duct paint White Paint system Paint WSP-015488 0.008% w/w Throughout - - - - No further action required.

23 East stairs Pink Paint system Paint WSP-015498 0.02% w/w Throughout (8m2) - - - - No further action required.

Event Location Application Material Description Sample Number Analytical Result Photo Extent Estimate Friability

Material

Condition

Risk Status

Control

Priority

Control Recommendations/ Comments

Consultant / Hygienist

name

Control action taken Date actioned Contractor details

Page 33: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

APPENDIX CCERTIFICATES OF ANALYSIS

Page 34: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Lab No Sample ID Location Sample Description Sample Dimensions Identification Type

001 WSP-015483 External window putty Putty 11.8 gm NAD

002 WSP-015487 South east corner AC duct joint mastic

Mastic 2.1 gm NAD

003 WSP-015491 Above south east porch adjacent stairs, window infill panel

Fibre Cement Sheet 1.8 gm A, CH

004 WSP-015493 Ceiling spray vermiculite to internal shower/toilet

Vermiculite 11.6 gm NAD

005 WSP-015494 Internal wall insulation to shower/toilet

Insulation 1.8 gm SMF, NAD

006 WSP-015495 Wall lining to shower and toilet Fibre Cement Sheet 1.9 gm OF, NAD

007 WSP-015496 Electric cupboard adjacent tea room and stairs

Fibre Cement Sheet 1.7 gm A, CH

008 WSP-015490 Northern external window putty Putty 11.9 gm NAD

009 WSP-015499 Suspended hallway ceiling tiles Tile 1.8 gm OF, NAD

TEST METHOD: Qualitative identification of Asbestos fibre in bulk and soil samples at WSP Corporate Laboratories, by polarised light microscopy, including dispersion staining techniques using AS4964 (2004) and supplementary in house laboratory procedure (LP3 - Identification of Asbestos Fibres). This document is issued in accordance with NATA's requirements under NATA accreditation No. 17199, accredited for compliance with ISO/IEC: 17025 - Testing. The results of the tests, calibrations and/or measurements included in this document are traceable to Australian/national standard.

DATE\S SAMPLED:

DATE RECEIVED:

DATE ANALYSED:

ORDER NUMBER:

SAMPLED BY:

5/02/2019

8/02/2019

N/A

4/02/2019

Imam MalikCONTACT:

EMAIL:

TELEPHONE: +61 2 6125 9727

[email protected]

Brett Morrison

F & S Anthony Low Building (#124), Garran Road, Acton ACT 2601

CLIENT ADDRESS:

Australian National UniversityCLIENT:

Page 1 of 1

Notes:If no asbestos is detected in vinyl tiles, mastics, sealants, epoxy resins and ore samples then confirmation by another independent analytical technique is advised due to the nature of the samples.The results contained within this report relate only to the sample(s) submitted for testing. The laboratory accepts no responsibility for location, sampling date, sample ID, sampler, and client details provided by the sampler. WSP accepts no responsibility for the initial collection, packaging or transportation of samples submitted by external persons. NATA does not accredit the sampling process, therefore sampling is not covered by the scope of accreditation. This document may not be reproduced except in full.

AUTHORISATION DATE

Approved Identifier

Name: Bec McLean

Approved Signatory

Laura Wilson-DennisName:

Friday, 8 February 2019

NADCHACUMFSMFOF

-------

No Asbestos DetectedChrysotile Asbestos DetectedAmosite Asbestos DetectedCrocidolite Asbestos DetectedUnknown Mineral Fibres DetectedSynthetic Mineral Fibres DetectedOrganic Fibres Detected

LEGEND:

Hand picked refers to small discrete amounts of asbestos distributed unevenly in a large body of non asbestos material.

Certificate of Analysis

Level 1 121 Marcus Clarke StreetPO Box 1551 Canberra ACT 2600Telephone +61 2 6201 9600Facsimile +61 2 6201 9666Email [email protected]

WSP AustraliaPty Limited

ABN 80 078 004 798

NCSI Certified Quality System ISO 9001

CERTIFICATE NO: ACT-PS112993-110523LOCATION: ANU Building 57

Page 35: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Envirolab Services Pty Ltd

ABN 37 112 535 645

12 Ashley St Chatswood NSW 2067

ph 02 9910 6200 fax 02 9910 6201

[email protected]

www.envirolab.com.au

CERTIFICATE OF ANALYSIS 210878

GPO Box 5394, Sydney, NSW, 2001Address

Anton DelacAttention

WSP Australia Pty LimitedClient

Client Details

06/02/2019Date completed instructions received

06/02/2019Date samples received

8 PaintNumber of Samples

Your Reference PS112993 / ANU BLDG 57

Sample Details

Results are reported on a dry weight basis for solids and on an as received basis for other matrices.

Samples were analysed as received from the client. Results relate specifically to the samples as received.

Please refer to the following pages for results, methodology summary and quality control data.

Analysis Details

Tests not covered by NATA are denoted with *Accredited for compliance with ISO/IEC 17025 - Testing.

NATA Accreditation Number 2901. This document shall not be reproduced except in full.

07/02/2019Date of Issue

07/02/2019Date results requested by

Report Details

Jacinta Hurst, Laboratory Manager

Authorised By

Giovanni Agosti, Group Technical Manager

Results Approved By

Revision No: R00

210878Envirolab Reference: Page | 1 of 6

Page 36: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Client Reference: PS112993 / ANU Childcare BLDG 57

0.040.0080.03%w/wLead in paint

07/02/201907/02/201907/02/2019-Date analysed

07/02/201907/02/201907/02/2019-Date prepared

PaintPaintPaintType of sample

04/02/201904/02/201904/02/2019Date Sampled

WSP-015489WSP-015488WSP-015486UNITSYour Reference

210878-8210878-7210878-6Our Reference

Lead in Paint

0.380.130.020.094<0.005%w/wLead in paint

07/02/201907/02/201907/02/201907/02/201907/02/2019-Date analysed

07/02/201907/02/201907/02/201907/02/201907/02/2019-Date prepared

PaintPaintPaintPaintPaintType of sample

04/02/201904/02/201904/02/201904/02/201904/02/2019Date Sampled

WSP-015485WSP-015484WSP-015498WSP-015497WSP-015492UNITSYour Reference

210878-5210878-4210878-3210878-2210878-1Our Reference

Lead in Paint

Envirolab Reference: 210878

R00Revision No:

Page | 2 of 6

Page 37: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Client Reference: PS112993 / ANU Childcare BLDG 57

Digestion of Paint chips/scrapings/liquids for Metals determination by ICP-AES/MS and or CV/AAS.Metals-004

Methodology SummaryMethod ID

Envirolab Reference: 210878

R00Revision No:

Page | 3 of 6

Page 38: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Client Reference: PS112993 / ANU Childcare BLDG 57

[NT]107290.030.048<0.005Metals-0040.005%w/wLead in paint

[NT]07/02/201907/02/201907/02/2019807/02/2019-Date analysed

[NT]07/02/201907/02/201907/02/2019807/02/2019-Date prepared

[NT]LCS-1RPDDup.Base#BlankMethodPQLUnitsTest Description

Spike Recovery %DuplicateQUALITY CONTROL: Lead in Paint

Envirolab Reference: 210878

R00Revision No:

Page | 4 of 6

Page 39: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Client Reference: PS112993 / ANU Childcare BLDG 57

Not ReportedNR

National Environmental Protection MeasureNEPM

Not specifiedNS

Laboratory Control SampleLCS

Relative Percent DifferenceRPD

Greater than>

Less than<

Practical Quantitation LimitPQL

Insufficient sample for this testINS

Test not requiredNA

Not testedNT

Result Definitions

Australian Drinking Water Guidelines recommend that Thermotolerant Coliform, Faecal Enterococci, & E.Coli levels are less than1cfu/100mL. The recommended maximums are taken from "Australian Drinking Water Guidelines", published by NHMRC & ARMC2011.

Surrogates are known additions to each sample, blank, matrix spike and LCS in a batch, of compounds whichare similar to the analyte of interest, however are not expected to be found in real samples.

Surrogate Spike

This comprises either a standard reference material or a control matrix (such as a blank sand or water) fortifiedwith analytes representative of the analyte class. It is simply a check sample.

LCS (LaboratoryControl Sample)

A portion of the sample is spiked with a known concentration of target analyte. The purpose of the matrix spikeis to monitor the performance of the analytical method used and to determine whether matrix interferencesexist.

Matrix Spike

This is the complete duplicate analysis of a sample from the process batch. If possible, the sample selectedshould be one where the analyte concentration is easily measurable.

Duplicate

This is the component of the analytical signal which is not derived from the sample but from reagents,glassware etc, can be determined by processing solvents and reagents in exactly the same manner as forsamples.

Blank

Quality Control Definitions

Envirolab Reference: 210878

R00Revision No:

Page | 5 of 6

Page 40: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Client Reference: PS112993 / ANU Childcare BLDG 57

Measurement Uncertainty estimates are available for most tests upon request.

Where sampling dates are not provided, Envirolab are not in a position to comment on the validity of the analysis whererecommended technical holding times may have been breached.

When samples are received where certain analytes are outside of recommended technical holding times (THTs), the analysis hasproceeded. Where analytes are on the verge of breaching THTs, every effort will be made to analyse within the THT or as soon aspracticable.

In circumstances where no duplicate and/or sample spike has been reported at 1 in 10 and/or 1 in 20 samples respectively, thesample volume submitted was insufficient in order to satisfy laboratory QA/QC protocols.

Matrix Spikes, LCS and Surrogate recoveries: Generally 70-130% for inorganics/metals; 60-140% for organics (+/-50% surrogates)and 10-140% for labile SVOCs (including labile surrogates), ultra trace organics and speciated phenols is acceptable.

Duplicates: >10xPQL - RPD acceptance criteria will vary depending on the analytes and the analytical techniques but is typically inthe range 20%-50% – see ELN-P05 QA/QC tables for details; <10xPQL - RPD are higher as the results approach PQL and theestimated measurement uncertainty will statistically increase.

For VOCs in water samples, three vials are required for duplicate or spike analysis.

Spikes for Physical and Aggregate Tests are not applicable.

Filters, swabs, wipes, tubes and badges will not have duplicate data as the whole sample is generally extracted during sampleextraction.

Duplicate sample and matrix spike recoveries may not be reported on smaller jobs, however, were analysed at a frequency to meetor exceed NEPM requirements. All samples are tested in batches of 20. The duplicate sample RPD and matrix spike recoveries forthe batch were within the laboratory acceptance criteria.

Laboratory Acceptance Criteria

Envirolab Reference: 210878

R00Revision No:

Page | 6 of 6

Page 41: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

APPENDIX DFLOOR PLAN

Page 42: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

1.14

UP

1.12

1.11

1.13

DISABLED

1.05

1.04

1.03

1.02

1.07

1.09

TE

LS

/B

UP

1.10

1.21

1.20

1.01

UP

1.16

1.17

FEMALE

1.19

10.6m² 16.1m²15.5m²

21.1m²

8m²

46m²

45.7m²

10.9m²

25.5m²

17.9m²

4.5m² 7.9m²

207.3m²

6.5m²

12m²

S/B

1.01

1.02

1.03

1.04

1.05

1.07

1.10

1.09

1.11

1.12

1.13

1.14

1.16

1.17

1.19

1.20

1.21

1.13B

1.13A

1.07A

1.07B

1.07C

1.07D

1.01A

1.01B

61.4m²

14.7m²

1.1m²

0.8m²

12.3m²

.4m²

.4m²

.4m²

0.9m²

MEETING

STAFF COMMON ROOM

KITCHEN

MEETING

MALE

TECHNICIANS WORKSHOP

WET AREA

STAIRS

LOCKERS

STORE

OFFICE

OFFICE

FOYER

OFFICE

OFFICE

GROSS BUILDING AREA = 620.3m²

GROSS FLOOR AREA = 567.4m²

ST

OR

AG

E

S.R

WORKSHOP

FACILITIES AND SERVICES

NUCLEAR PHYSICAL BUILDING

BUILDING N0. J057

FLOOR PLAN

LEVEL 1

MAR 88

CANGRAPHICS

X:\ANU CAD LIBRARY\ACTON\J057 NUCLEAR PHYSICS BUILDING\J057.01 ARCHITECTURAL FLOOR PLANS\A-J057-PLAN-L1

1:100

A1

A-J057-PLAN-L1 1

LEGEND (Sample Locations):

AUJS500530
Arrow
AUJS500530
Typewriter
WSP-015487 WSP-015488
AUJS500530
Arrow
AUJS500530
Typewriter
WSP-015490
AUJS500530
Typewriter
WSP-015489
AUJS500530
Arrow
AUJS500530
Arrow
AUJS500530
Typewriter
WSP-015493
AUJS500530
Typewriter
WSP-015494
AUJS500530
Typewriter
WSP-015495
AUJS500530
Arrow
AUJS500530
Arrow
AUJS500530
Arrow
AUJS500530
Typewriter
WSP-015496
AUJS500530
Arrow
AUJS500530
Typewriter
WSP-015496
AUJS500530
Arrow
AUJS500530
Typewriter
WSP-015483 WSP-015484
AUJS500530
Rectangle
AUJS500530
Rectangle
AUJS500530
Arrow
AUJS500530
Typewriter
WSP-015485 WSP-015486
AUJS500530
Text Box
WSP-0154XX: No Asbestos/SMF/Lead Detected WSP-0154XX: Asbestos Detected WSP-0154XX: SMF Detected WSP-0154XX: Lead Detected
MalikI
Text Box
Asbestos cupboard wall lining
MalikI
Line
MalikI
Line
Page 43: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

2.44

DN

2.29 2.30

2.31 2.33

2.34 2.36

2.28

2.272.26

2.25

2.24

2.55

2.54

2.53

DN

2.35

2.23

2.32

S/B F

HR

WC

2.382.37

WC

2.43

2.41

2.45

2.42

2.39

2.40

2.48

2.49

2.50

2.51

2.46

2.47

FHR

12.8m² 10.6m² 10.9m² 11.9m²

15.4m²13.6m²

11.1m²

15.2m²

14.8m²

5.5m²

11.5m²

25.7m²

39.2m²

16.6m²

14m²

12.6m²

36.4m²

11m²

16.5m²

10.7m²

10.2m²

11m²

18.2m²

27m²

52.2m²

7.4m²

4m²

4.1m²

2.3m² 2.4m²

2.53

2.54

2.55

2.24

2.25

2.26

2.27

2.28

2.23

2.29 2.30

2.312.33

2.32

2.34

2.36

2.35

2.372.38

2.37A

2.39

2.40

2.41

2.43

2.42

2.44

2.45

2.46

2.48

2.49

2.50

2.51

2.21

2.32A

2.23A

2.35A

53.2m²

.2m²

.2m²

11.7m²

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

STAIR

WC

OFFICE

OFFICE

OFFICE

OFFICE

LIBRARY

COMPACTUS

MEETING

OPEN OFFICE

OFFICE

OFFICE

STORE

OFFICEOFFICE

OPEN OFFICE

COPIER / PRINTERSSTAIR

CORRIDOR

ENSUITE

GROSS BUILDING AREA = 616.8m²

GROSS FLOOR AREA = 566m²

21-7-991 AMENDMENT BD

FACILITIES AND SERVICES

NUCLEAR PHYSICS BUILDING

BUILDING N0. J057

FLOOR PLAN

LEVEL 2

MAR 88

CANGRAPHICS

X:\ANU CAD LIBRARY\ACTON\J057 NUCLEAR PHYSICS BUILDING\J057.01 ARCHITECTURAL FLOOR PLANS\A-J057-PLAN-L2

1:100

A1

A-J057-PLAN-L2 1

LEGEND (Sample Locations):

AUJS500530
Arrow
AUJS500530
Typewriter
WSP-015491
AUJS500530
Arrow
AUJS500530
Arrow
AUJS500530
Typewriter
WSP-015497
AUJS500530
Typewriter
WSP-015498
AUJS500530
Typewriter
WSP-015499
AUJS500530
Arrow
AUJS500530
Text Box
WSP-0154XX: No Asbestos/SMF/Lead Detected WSP-0154XX: Asbestos Detected WSP-0154XX: SMF Detected WSP-0154XX: Lead Detected
MalikI
Text Box
Asbestos window infill panel
MalikI
Line
Page 44: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

APPENDIX ERISK ASSESSMENT

Page 45: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Appendix ERisk AssessmentAsbestos and Hazardous Materials

Risk rankings were calculated by assessing the condition of, and the accessibility to the Hazardous Materials instances, as observed during survey.

For full details of the locations, analysis results, condition, accessibility and risks associated with the identified Hazardous Materials, please refer to the attached Hazardous Materials Register.

Asbestos

Table 1 Friable descriptors

Item Score Description

Y Asbestos cement debris, or material which when dry may become crumbled, pulverised or reduced to powder by hand pressure.

Friable

N Bonded i.e. non-friable material

A Assumed (Identification Unconfirmed)

Table 2 Material Assessment Descriptors

Item Score Description

0 No asbestos detected

1 Bonded asbestos in good condition

2 Friable asbestos in good condition or cement in poor condition

Product type

3 Friable asbestos in poor condition

A Assumed (Identification Unconfirmed)

0 No visible damage

1 Minor scratches or mark, broken edges

2 Significant breakage, many small areas of damage to friable material

Extent of Damage

3 High damage, visible debris

A Assumed (Identification Unconfirmed)

0 Bonded asbestos including encapsulated asbestos cement

1 Enclosed laggings, sprays and boards or bare cement

2 Bare board or encapsulated lagging/spray or cement debris

Surface Treatment

3 Unsealed lagging/spray

A Assumed (Identification Unconfirmed)

Page 46: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page E-23

Table 3 Location Assessment Descriptors

Item Score Description

0 Usually inaccessible or unlikely to be disturbed (e.g. little used store room)

1 Minimal likelihood for disturbance (e.g. office type activity)

2 Likely disturbance (e.g. industrial or vehicular activity)

Likelihood of Disturbance

3 Frequent disturbance (e.g. fire door in constant use)

A Assumed (Identification Unconfirmed)

0 Infrequent

1 Monthly

2 Weekly

Human Exposure Potential

3 Daily

A Assumed (Identification Unconfirmed)

0 Minor disturbance (e.g. possibility of contact when gaining access)

1 Low Disturbance (e.g. changing light bulbs in asbestos insulating board ceiling).

2 Medium disturbance (e.g. lifting one or two ceiling tiles to access a valve)

Maintenance Activity

3 High level of disturbance (e.g. moving a number of asbestos ceiling tiles to replace a valve or for re-cabling)

A Assumed (Identification Unconfirmed)

The asbestos containing material risk score is a quantitative assessment determined by the sum of the scores based on the Materials and Location Assessments; i.e. Risk score = Material Score + Location Score (out of as possible 24).

Should no asbestos be detected then the register will indicate a risk score of 0.

Table 4 Asbestos Risk Score Descriptors

Item Score Description

0 No asbestos risk

1 – 6 Low Risk

7 – 12 Medium Risk

Risk

13 – 24 High Risk

Other Hazardous Materials

Other hazardous materials, with the exception of asbestos.

Page 47: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page E-24

Table 5 Friability Descriptors

Item Score Description

Y Unsealed SMF

N Sealed SMF

Friable

NA Applicable to PCB and Lead in paint

Table 6 Material Assessment Descriptors

Item Score Description

G Good condition

Av Average condition

Extent of Damage

P Poor condition

Y Sealed

P Part sealed

Surface Treatment

N Not sealed

Table 7 Location Assessment Descriptors

Item Score Description

H High traffic area

M Medium traffic area

Human Exposure Potential

L Low traffic area

The other hazardous materials risk score is a qualitative assessment determined by the combination of Material and Location Assessments. Depending on the material one or all of these criteria may be used in assessing the recommended Action.

Table 8 Other Hazardous Materials Risk Score Descriptors

Item Score Description

L Low exposure risk

M Medium exposure risk

Risk Score

H High exposure risk

Recommended Risk Controls

Following the assessment for both asbestos containing and other hazardous materials an action score is assigned. The action score will be assigned according to the surveyor’s assessment of the situation.

Page 48: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page E-25

Table 9 Recommended Risk Controls – Actions

Descriptor Item Action

Restrict access and remove by a licensed contractorsP1 Priority 1

As a guide, the material conforms to one, or more, of the following:

Friable or poorly bonded to substrate, located in accessible areas;

Severely water damaged, or unstable;

Further damage or deterioration likely;

Friable asbestos material located in air conditioning ducting;

Asbestos debris and stored asbestos in reasonably accessible areas;

Significant peeling and flaking lead paint in areas that pose immediate risk to children/resident.

Enclose, encapsulate or seal

Reinspect Periodically

P2 Priority 2

As a guide, the material conforms to one, or more, of the following:

Damaged material;

In reasonably accessible area;

Friable material or poorly bonded to substrate, with bonding achievable;

Possibility of disturbance through contact;

Possibility of deterioration caused by weathering;

Large areas of peeling and flaking lead paint in an area that poses high risk.

Remove during refurbishment or maintenance

Enclose, encapsulate or seal by general maintenance contractors

Reinspect Periodically

P3 Priority 3

As a guide, the material conforms to one, or more, of the following:

Asbestos debris or stored material in rarely accessed areas;

Further disturbance or damage unlikely other than during maintenance or service;

Readily visible for further assessment;

Asbestos friction materials, gaskets and brake linings;

Small/moderate areas of peeling and flaking lead paint in an area that poses low risk. Remedial works suitable by a general maintenance contractor.

No remedial action – Reinspect PeriodicallyP4 Priority 4

As a guide, the material conforms to one, or more, of the following:

Firmly bonded to substrate and readily visible for inspection;

Inaccessible and fully contained;

Stable and damage unlikely.

Page 49: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

APPENDIX FSTATEMENT OF LIMITATIONS

Page 50: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page 1

LIMITATIONS OF A HAZARDOUS MATERIALS INSPECTION

SCOPE OF SERVICESThis hazardous materials inspection report (‘the report’) has been prepared in accordance with the scope of services set out in the contract, or as otherwise agreed, between the Client and WSP Australia (‘scope of services’). In some circumstances the scope of services may have been limited by a range of factors such as time, budget, access and/or site disturbance constraints.

RELIANCE ON DATAIn preparing the report, WSP has relied upon data, surveys, analyses, designs, plans and other information provided by the Client and other individuals and organisations, most of which are referred to in the report (‘the data’). Except as otherwise stated in the report, WSP has not verified the accuracy or completeness of the data. To the extent that the statements, opinions, facts, information, conclusions and/or recommendations in the report (‘conclusions’) are based in whole or part on the data, those conclusions are contingent upon the accuracy and completeness of the data. WSP will not be liable in relation to incorrect conclusions should any data, information or condition be incorrect or have been concealed, withheld, misrepresented or otherwise not fully disclosed to WSP.

NO INSPECTION CAN BE GUARANTEED TO LOCATE ALL HAZARDOUS MATERIALSIn practice, it is generally impossible to locate all hazardous materials in the course of an inspection.

This is because of factors such as:

The availability of building/plant construction plans. There is no instrument which can detect hazardous materials.

Inaccessible and restricted areas during survey

The presence of hazardous materials must be determined visually, as there is no single, cost effective instrument currently available for the purpose. Usually an inspector will take samples of suspect materials and have them analysed in a laboratory. Thus, any restrictions on the amount of sampling will reduce confidence in the hazardous materials inspection findings. The consequence of this is that hazardous materials which cannot be seen will not be found.

Page 51: Acton Campus Building #57 Hazardous Materials Report · 2019. 3. 6. · 04/02/2019 Hazardous Materials Survey Anton Delac, Imam Malik & Joseph McNeill Undertake a survey of the site

Project No PS112993Building J057 - Nuclear PhysicsGarran Road, Acton ACT 2601Hazardous Materials SurveyThe Australian National University

WSPFebruary 2019

Page 2

HAZARDOUS MATERIALS ARE COMMONPLACEFrom the early 1900s until the early 1970s, asbestos was widely used in industry. The use of asbestos cement sheets in roof pipes and wall cladding was particularly widespread, as was the use of ‘limpet’ asbestos fibre insulation in steel framed high-rise buildings. Asbestos was also used for applications such as insulation of pipes and high temperature electricity cables, in plastics, in PVC floor tiles, for reinforcement in cements, putties and mastic and in gaskets and friction materials.

Whilst major uses of hazardous materials were sometimes recorded on engineering drawings, there are few records of the ad hoc use of hazardous materials and products. To give examples from the building industry, plumbers frequently used asbestos fibre in caulking compounds and builders often used Asbestos Cement sheeting as packing under floorboards.

In short, asbestos could be almost anywhere in a building or plant constructed before the 1980s.

RELIANCE ON A HAZARDOUS MATERIALS INSPECTIONThe client must not rely upon an inspection or report as indicating that a site or building is ‘hazardous materials free’. All that the report can be relied upon to show is that no hazardous materials were found (or that only such hazardous materials were found as was reported to have been found) in the course of the inspection. The findings of the report must be considered together with the specific scope and limitations of the type of inspection undertaken.

REPORT FOR BENEFIT OF CLIENTThe report has been prepared for the benefit of the Client and no other party. WSP assumes no responsibility and will not be liable to any other person or organisation for or in relation to any matter dealt with or conclusions expressed in the report, or for any loss or damage suffered by any other person or organisation arising from matters dealt with or conclusions expressed in the report (including without limitation matters arising from any negligent act or omission of WSP or for any loss or damage suffered by any other party relying upon the matters dealt with or conclusions expressed in the report). Other parties should not rely upon the report or the accuracy or completeness of any conclusions and should make their own enquiries and obtain independent advice in relation to such matters.

For the purposes of this limitations statement, ‘conclusions’ include statements, opinions, facts, information, conclusions and/or recommendations in the report.