A Technical Paper

Embed Size (px)

Citation preview

  • 8/10/2019 A Technical Paper

    1/51

    Strengthening of High Voltage Transmission

    Networks in Nigeria with the Introduction of

    Multi-Circuit Towers.

    A Technical Paper Presented

    To

    The Nigerian Institution of Electrical &

    Electronics Engineers

    (A Division Of NSE)

    By

    Engr. Salami, Adesina Jimoh (MNSE) Feb.

    2014.

  • 8/10/2019 A Technical Paper

    2/51

    Introduction

    The theme of this paper is Strengthening of

    High Voltage HV) Transmission Networks

    in Nigeria with the introduction of HV multi-

    circuit Towers

    The new technology of multi-circuit in the

    network was one of the solutions adopted

    to combat part of the numerous challengesin the Transmission sector.

  • 8/10/2019 A Technical Paper

    3/51

    Intro. Contnd

    The issue of acquisition of Right of Way(ROW) for the

    construction of new transmission lines has being a serious

    problem, which most of the time resulted to undue delay of

    project completion time or even a times marred completelythe accomplishment of the project. Though, this technology

    has been in existence in some other well developed countries

    long time ago, what we had in our network were HV single

    circuit & double circuits until recently when we were

    compelled to adopt the technology in solving the ROW

    problem encountered in the construction of a new 330KV

    double circuits lines that has to pass through a developed

    town of Onitsha, in Anambra State.

  • 8/10/2019 A Technical Paper

    4/51

    Itro.contnd

    The estimate for compensation for structures andproperty ran to about N3Billion for about 4.75Km

    length of the line and beside this huge sum there wthreat of litigations by not willing to let go owners oproperty along the proposed line. The operator of thnetwork, Transmission Company of Nigeria, assenteto the proposal brought forward to introduce a 5-cirHV towers into the system using an existing 132KV

    line route. The solution was so timely because theproject was completed at a reasonable time and alssolved the menace of frequent system collapsingwhich was threatening the system as at the time.

  • 8/10/2019 A Technical Paper

    5/51

    Business of electricity

    supply involves: *Generation

    *Transmission

    *Distribution

  • 8/10/2019 A Technical Paper

    6/51

    Business of electricity

    supply contdFor a better understanding of the Power Industry in Nigeria, I

    carried out a general over-view of the industry by giving its

    history from the inception to the present day status.

    Challenges that had militated against realization of the typeof an industry that is our collective dream, various solutions

    that were proffered by the Governments to correct some

    perceived anomalies in the operation of the industry, success

    and failures that were recorded over time were enumerated.

    And subsequently, the paper discussed the new development

    in the HV transmission network which witnessed the

    introduction of HV multi-circuit towers. Few design

    parameters and extent of compliance to international

    standard were given.

  • 8/10/2019 A Technical Paper

    7/51

    ELECTRICITY SUPPLY DEVELOPMENT

    IN NIGERIA:

    The history of electricity supply development

    in Nigeria can be traced to the end of the

    19thcentury when the first generating

    power plant was installed in the city ofLagos in 1898, fifteen years (15 years)

    after its introduction in England, United

    kingdom. The total capacity of the

    generators used then was 60kw.

  • 8/10/2019 A Technical Paper

    8/51

    ELECTRICITY SUPPLY DEVELOPMENT IN NIGERIA

    CONTND

    The Nigeria electricity supply company

    (NESCO) commenced operations in the city

    of Jos and its environs as an electric

    utility company in 1929 with theconstruction of a hydro electric power

    plant at kuru near Jos.

    In 1946, Nigerian Government Electricityundertaking was established under the

    jurisdiction of the public works department

    (PWD) the take-over the responsibility of

    electricity supply in Lagos.

  • 8/10/2019 A Technical Paper

    9/51

    ELECTRICITY SUPPLY DEVELOPMENT IN

    NIGERIA CONTND

    Electricity supply management in Nigeria remained under

    individual, municipal authority etc till 1950 when

    Electricity Corporation of Nigeria (ECN) was established tomanage and co-ordinate electricity supply in Nigeria.

    Niger Dam Authority (NDA) was established in 1962 with a

    mandate to develop the hydropower potentials of the

    country. ECN and NDA were merged in 1972 to formNational Electric Power Authority (NEPA) by decree. The

    decree empowers NEPA to enjoy the monopoly of all

    commercial electricity supply to the exclusion of all other

    organizations.

  • 8/10/2019 A Technical Paper

    10/51

    ELECTRICITY SUPPLY DEVELOPMENT

    IN NIGERIA CONTND

    Within this power conferred, Federal

    Government of Nigeria through Federal

    ministry of power (FMP) was responsible for

    policy formulation and regulation; and throughNEPA, was responsible for operation and

    investment in the management of electricity

    supply in Nigeria. NEPA wholly owned sole

    responsibility for power generation,transmission and distribution in Nigeria. There

    were many reasons that necessitated the

    establishment of NEPA, among them were:

  • 8/10/2019 A Technical Paper

    11/51

    ELECTRICITY SUPPLY DEVELOPMENT IN

    NIGERIA CONTND

    *To vest the responsibility for the financialobligation on one organization

    *Guarantee more effective utilization of

    human, finance and other resourcesallocated to the electricity supply industry

    throughout the country.

  • 8/10/2019 A Technical Paper

    12/51

    ELECTRICITY SUPPLY DEVELOPMENT IN

    NIGERIA CONTND

    NEPA strived to meet ever-increasing electricity demand

    of the nation but unfortunately their performance was

    adjudged to be poor and the organization was ladened

    with corrupt practices, ineptitude, insensitivity and all

    other attributes of a failed system. Poor performance ofNEPA was undoubtedly a source of concern to the

    Government. NEPA was confronted with issues of poor

    operational and financial performances. Attempt to

    address these issues of NEPA problems made the

    Government of the day then to amend the prevailing

    laws setting up NEPA (Electricity and NEPA acts) in

    1998. The act was amended to remove NEPA monopoly

    and encouraged private sector participation. With the

    amendment in the act, NEPA ceased to have an

    exclusive monopoly over electricity generation,

    transmission and distribution & sales of electricity

  • 8/10/2019 A Technical Paper

    13/51

    ELECTRICITY SUPPLY DEVELOPMENT IN

    NIGERIA CONTND

    But, in no distant time, the government discovered

    that the desired results were not being gotten. It then

    undone on the government of the day that a more

    holistic approach is required thus, total overhauling

    and reformation of the policy, legal and regulations

    setting up NEPA was carried out.

    Consequently, in the year 2001 amendments was made

    in the act which then provides legal basis for theunbundling of NEPA, the formation of successor

    companies and the privatization of the latter. This

    gave birth to Power Holding Company of Nigeria

    (PHCN) and its subsequent unbundling into 18

    successors companies.

  • 8/10/2019 A Technical Paper

    14/51

    ELECTRICITY SUPPLY DEVELOPMENT IN

    NIGERIA CONTND

    The Federal Government owned Electricity

    company then comprises of the following:

    Generation: 3 No. Hydro plants

    7 No. Thermal Generating plants.

  • 8/10/2019 A Technical Paper

    15/51

    ELECTRICITY SUPPLY DEVELOPMENT IN

    NIGERIA CONTND

    Worth of note is that, the total installed capacity of

    the plants was 6,852MW and total available

    capacity was 3542MW for a population of about 160

    million (as at 31-07-2010)

    Transmission: A radial transmission grid (330KV &

    132KV) owned and managed by Transmission

    company of Nigeria (TCN)

    Distribution and sales: 11no. distribution

    companies (33KV&11KV) which undertakes thewires, sales, billing & collection, customer care

    services within each companys catchment area.

  • 8/10/2019 A Technical Paper

    16/51

    ELECTRICITY SUPPLY DEVELOPMENT IN NIGERIA

    CONTND

    Strategically, the objectives of the reforms

    are:

    To transfer management and financing of

    the unbundled companies to organized

    private sector.

    Establish an independent and effective

    regulatory commission to oversee the

    industry.

    Focusing the Federal Government

    attention on policy formulation and long

    term developmental programme of the

    industry.

  • 8/10/2019 A Technical Paper

    17/51

    ELECTRICITY SUPPLY DEVELOPMENT IN

    NIGERIA CONTND

    Results expected from this holistic

    transformation are;

    Increased access to electricity

    services

    Improved efficiency, affordability,

    reliability and quality services.

    Greater investment into the sector

    to stimulate economic growth.

  • 8/10/2019 A Technical Paper

    18/51

    ELECTRICITY SUPPLY DEVELOPMENT IN

    NIGERIA CONTND

    In 2007, Bureau of public enterprises

    commenced the privatization policy and by

    30thSeptember 2013, PHCN ceased to

    exist following a successful privatizationprocess by the federal Government.

    The following listed tables are attached to

    this report for a better appreciation of the

    status of the utility company before itceased to exist.

  • 8/10/2019 A Technical Paper

    19/51

    ELECTRICITY SUPPLY DEVELOPMENT IN

    NIGERIA CONTND

    Table 1 : Installed/Available

    Generating capacity of the Nation

    Table 2 : Power supply module

    around the world.

  • 8/10/2019 A Technical Paper

    20/51

    DEVELOPMENT IN THE

    TRANSMISSION SECTOR:

    Electric power transmission is the bulk

    transfer of electric energy from the

    generating plants by high voltage links

    (wires) to transmission stations andSubstations and ensuring that, electricity

    generated anywhere within the network can

    be used to satisfy demand at any part of the

    network. Whereas, electricity distribution ismainly concerned with the conveyance of

    power to consumers by means of lower

    voltage.

  • 8/10/2019 A Technical Paper

    21/51

    DEVELOPMENT IN THE

    TRANSMISSION SECTOR CONTND

    Network formed by the very high voltage lines inthe network constitutes the interconnectivity

    which is called super grid or simply, national grid.

    Advantages of having system interconnectivity are

    as follows;

  • 8/10/2019 A Technical Paper

    22/51

    DEVELOPMENT IN THE

    TRANSMISSION SECTOR CONTND

    To achieve a more economical cost for a unit

    of power generated.

    To stabilize the network, thus making it more

    reliable by providing spinning reserve at low

    cost.

    Guarantee a common frequency for the supply

    within the net work.

    Ensure continuity of electricity supply to all

    over the system linked places irrespective of

    behavior at a particular time of the localized

    generating plant.

  • 8/10/2019 A Technical Paper

    23/51

    DEVELOPMENT IN THE

    TRANSMISSION SECTOR CONTND

  • 8/10/2019 A Technical Paper

    24/51

    DEVELOPMENT IN THE

    TRANSMISSION SECTOR CONTND

    It could be seen from the module that,

    the grid {operate at 400KV (Britain),

    500KV(USA), 330KV (Nigeria) feeds asub Transmission stations (operate at

    132KV ( Britain), 115KV (USA),

    132KV(Nigeria)}. At this voltage level ,

    sub-transmission , some less efficientgenerating plants feed into the network

    and also, major consumers of electricity

    supply are fed directly.

  • 8/10/2019 A Technical Paper

    25/51

    DEVELOPMENT IN THE

    TRANSMISSION SECTOR CONTND

    Electricity supply is transmitted at high voltages(120KV and above) to reduce energy loss in longdistance transmission. Thus , the voltage magnitu

    chosen for transmission are greatly influenced bygeography of the network. Very long transmissionlines require that the power should be transmittedhigh voltage. This is the situation found in the Nortand south America, Russia, China, India Etc. Powe

    is transmitted at voltage level of 765KV in North aSouth America and efforts are on to increase thegrid voltage to 1000KV1500KV whereas ingeographically small country like Europe the lengtof network is smaller and the upper voltage level i

    420KV.

  • 8/10/2019 A Technical Paper

    26/51

    DEVELOPMENT IN THE

    TRANSMISSION SECTOR CONTND

    Power systems are universally high

    voltage alternating current (HVac)

    and the use of high voltage directcurrent (HVdc) technology which is

    of better efficiency is mainly

    employed for specialized purposes

    such as extralong distancetransmission lines or in submarine

    power cable because of high cost of

    the conversion equipment.

  • 8/10/2019 A Technical Paper

    27/51

    OVERHEAD TRANSMISSION LINES:

    Overhead lines are mostly used for the power

    transmission on the ground of economy because,

    major part of insulation is provided by air which

    cost relatively zero naira. In a constrainedenvironments such as urban areas, underground

    cables are used for high voltage transmission, the

    cost is about 10 times that of high voltage

    overhead lines though, the ratio decreases withlower voltages. The difference in the cost arose

    from the cost of providing insulation. Overhead

    lines conductor(s) are suspended from insulators

    which are themselves supported by towers.

  • 8/10/2019 A Technical Paper

    28/51

    DESIGN OF OVERHEAD TRANSMISSION

    LINES

    Primary considerations in the design

    of transmission lines are;

    Determination of line length Grid voltage

    Line conductor size

    Tower structure Allowable sag on the line

    Tower span length

  • 8/10/2019 A Technical Paper

    29/51

    DESIGN OF OVERHEAD

    TRANSMISSION LINES contnd

    Grid voltage: The voltage level of the

    grid is determined based on the

    length of the network. The reasonbeing that, power loss is recorded

    along the line. Therefore to maintain

    allowable power loss which is based

    on the percentage of the declaredvoltage ( 6%) the grid voltage

    magnitude is proportional to the line

    length.

  • 8/10/2019 A Technical Paper

    30/51

    DESIGN OF OVERHEAD

    TRANSMISSION LINES contnd

    Conductor size:

    Powerloss = I2R .. (1)

    R = L/a . (2)

    - coeffient of expansion- Line length

    - Conductor cross sectional area.

    In equation 2

    R L/a

    Bundled conductors ,thats a more than 1 conductor per phaseline are used to reduce line reactances, corona loss & radio

    interference and conductor voltage gradient.

  • 8/10/2019 A Technical Paper

    31/51

    DESIGN OF OVERHEAD TRANSMISSION LINES contnd

    3. Line Insulation:

    The insulators provide adequate leakage path from

    conductor to earth .

    Pin type insulator are used for line voltage up to 33KVwhile suspension/ tensioning strings are used for line

    voltage above 33KV. This consist of string of inter

    linking separate discs made of glass, or porcelain or

    silicon.

    Number of discs in the string depend upon the linevoltage (11No for 132KV, 18No. for 330KV)

  • 8/10/2019 A Technical Paper

    32/51

    DESIGN OF OVERHEAD TRANSMISSION

    LINES contnd

    Towers:

    There are two main types of HV Towers.

    Those for straight runs called suspension

    towers in which stress due to weight of the

    line conductors and string insulators has to be

    withstood.

    Those for changes in route called deviation

    towers (angle towers). This withstands theresultant forces set up when the line changes

    direction in addition to weight of the line

    conductor and string insulators.

  • 8/10/2019 A Technical Paper

    33/51

    Contnd

    TYPES OF TOWERS. 330kv 132kv

    DC SC DC SC

    Suspension towers (0 - 20) AAH AH DD2 SS2

    Strain/Tension/section Tower

    (0 - 100) BBH BH DD10 SS10

    Strain/Tension/section Tower

    (10 - 300) CCH CH DD30 SS30

    Strain/Tension/section Tower

    (30- 600) DDH DH DD60 SS60

    Dead End Tower (60 - 900) EEH EH DD90

    SS90

  • 8/10/2019 A Technical Paper

    34/51

    Contnd

    Other general considerations in

    design of tower are

    Extra forces resulting from abreak in the lines on one side of

    the tower ( Uplift force)

    Nature of the conductor surface( e.g. effect of ice, dust)

    Wind loading

  • 8/10/2019 A Technical Paper

    35/51

    Contnd

    Allowable Sag on the Line.

    This is subject to Standard Specification

    for electrical clearance and

    characteristics of the conductor. The value

    of sag determines the tower height, towers

    span.

    Tower span length is the distance between2 steel towers ( lattice) which on high-

    voltage lines (330KV) are in the range of

    370m-470m and the tower height is about

    45m for 2X330KV lines.

  • 8/10/2019 A Technical Paper

    36/51

    Design Criteria

    Initial and final sag is

    calculated for each ruling span

    without exceeding the tensionlimit specified below:

  • 8/10/2019 A Technical Paper

    37/51

    Contnd

    Loading Condition Tension limit

    ACSR unloaded

    Initial, 10 30%

    Final, 10 overland 25%

    Final, 10 18%

    Open bodies of water

    ACSR loaded

    Final, 10 60%

  • 8/10/2019 A Technical Paper

    38/51

    Contnd

    Tension limits are given as a percentage of the

    conductor ultimate tensile strength calculated in

    accordance with IEC 61089.

    Vertical Clearances specified are based onmaximum line conductor sag at 75

    330KV 132KV

  • 8/10/2019 A Technical Paper

    39/51

    Contnd

    Vertical Distances

    Normal ground 8.0 6.7

    Road crossing 9.0 8.3

    Buildings, poles, structures, walls,

    And cradle guards. 5.2 5.0

    Limited access motorways and

    dual carriage ways. 10.0 10.0

    Navigable waterways (at high water level) 15.0 15.0

    Pipelines (oil, gas, water). 10.0 10.0

    Communication and power line wires 4.6 3.6 Cradle guard to top of railway track 9. 8.3

  • 8/10/2019 A Technical Paper

    40/51

    Contnd

    Horizontal Distances

    Nearest steel of transmission tower to

    Edge of navigable waterways,pipesline,

    Bridges, highways, pavement, railway

    (nearest rail), buildings on right-of-way

    And at crossing, to structure of line being

    Crossed 50.0 50.0

  • 8/10/2019 A Technical Paper

    41/51

    Contnd

  • 8/10/2019 A Technical Paper

    42/51

    Contnd

  • 8/10/2019 A Technical Paper

    43/51

    Contnd

  • 8/10/2019 A Technical Paper

    44/51

    Contnd

  • 8/10/2019 A Technical Paper

    45/51

    Contnd

  • 8/10/2019 A Technical Paper

    46/51

    Contnd

  • 8/10/2019 A Technical Paper

    47/51

    Contnd

  • 8/10/2019 A Technical Paper

    48/51

    Contnd

  • 8/10/2019 A Technical Paper

    49/51

  • 8/10/2019 A Technical Paper

    50/51

    Contnd

  • 8/10/2019 A Technical Paper

    51/51

    Contnd