5.01 Cold Water Pipe Sizing Testing and Commissioning 2

Embed Size (px)

Citation preview

  • 8/3/2019 5.01 Cold Water Pipe Sizing Testing and Commissioning 2

    1/3

    T: 1300 815 127

    www.pic.vic.gov.au

    PO Box 536

    Melbourne

    Victoria, Australia 3001

    Goods Shed North

    733 Bourke Street

    Docklands, Victoria 3008

    5: COLD WATER PLUMBING

    COLD WATER PIPE sIzING, TEsTING AND COMMIssIONING

    TECHNICAL sOLUTION 5.01

    Page 1

    AIM

    The aim of this technical solution is to clarify therequirements for sizing, testing and commissioning acold water plumbing installation.

    PLUMBING REGULATIONs 2008

    The Pin C f Asraia (PCA) is adopted byand forms part of the Pin Rains 2008. PartB1 of the PCA species the objectives and performancerequirements related to the installation of cold waterservices.AS/NZS 3500.1: Pin an raina Par 1:War srvics, is a deemed to satisfy document listed

    in Part B1 of the PCA and contains sections on Sizingof water services and Testing and Commissioning.

    CERTIfyING A COLD WATER PLUMBINGINsTALLATION

    There is an increasing variety of materials and productsfor the supply of cold (and heated) water. It is particularlyimportant when using unfamiliar products to ensure thatpipe sizing will be correct for adequate performance ofthe installation.

    There are two ways that an installation may be certiedas complying:

    1. PCA - The purpose of this provision is to enableexibility to achieve an installation outcome thatmay not strictly comply withAS/NZS 3500.1 but willproduce an equivalent performing result.

    2. AS/NZS 3500.1 - Generally, it is expected thatplumbing work will be certied toAS/NZS 3500.1. Inthis case, your work must comply withAS/NZS 3500.1 and would meet the PCA performance requirements.

    If you are certifying a water supply installation toAS/NZS3500.1 Water Services, it is important to understandhow to size the system, and then select the correct pipe

    sizes for different pipe materials.

    ExAMPLE

    This example (see Figure 1) follows the method of sizinga typical installation in accordance withAS/NZS 3500.1 .You will need to know the following:

    > The Inde length.The length in metres from the water meter to themost distant outlet. In this case to the back hosetap. In this case 35m.

    > The height in metre.

    The height in metres (above the water meter) ofthe highest outlet. In this case 3m.

    > The preure available at the outlet.

    > The available preure.

    > flow rate and loading unit.

    sTEPs

    1. sketch the intallation.

    The sketch should include the xtures and their loadingunits and pipe sections identied by lettering as per

    example in Figure 2.

    2. Determine Available Preure:

    Measure static pressure at meter = 720 kPa

    Allow 67% of 720 kPa to represent a minimum pressure= 482.4 kPa or 48.24m head

    3. Determine Preure Drop:

    The following formula is used to calculate the pressuredrop along the index length.

    P.D. = Hm Hs Hx

    Where Hm = minimum available head in

    metres = In his cas 48Hs = height of the heighest outlet

    = In his cas 3

    Hx = minimum head required at anyoutlet

    = In his cas 5

    Therefore:

    P.D. = Hm Hs Hx

    P.D. = 48 3 5

    = 40m head

    AS/NZS 3500.1 (Clause 3.3.2) requires a pressureof 50kPa (5m head) at the most disadvantagedoutlet. In this case the back hose tap requires aminimum of 50kPa pressure at a ow rate of 0.20L/s(ow rate from Table 3.1).

    If the water authority will specify a minimum pressureavailable, use that gure. Alternatively, you cancheck the available pressure at the meter and use67% of the reading to simulate minimum pressureconditions. In this case pressure at the meter is

    measured at 720kPa.

    AS/NZS 3500.1 Table 3.1 species ow rates andloading units of xtures and appliances.

  • 8/3/2019 5.01 Cold Water Pipe Sizing Testing and Commissioning 2

    2/3

  • 8/3/2019 5.01 Cold Water Pipe Sizing Testing and Commissioning 2

    3/3

    T: 1300 815 127

    www.pic.vic.gov.au

    PO Box 536

    Melbourne

    Victoria, Australia 3001

    Goods Shed North

    733 Bourke Street

    Docklands, Victoria 3008

    5: COLD WATER PLUMBING

    COLD WATER PIPE sIzING, TEsTING AND COMMIssIONING

    TECHNICAL sOLUTION 5.01

    Page 3

    FIguRe 4 - teStINg PRoCeduRe

    Water service/rst x/rough in completed

    Isolated/disconnect any xtures or appliances that may bedamaged by a high test pressure

    Connect test bucket at a convenient point to enable testing of piping(both hot and cold if required)

    Cap all open ends

    Fill system with water

    Isolate water main if connected to mains supply

    Pressure test system to 1500kPa with test bucketfor not less than 30 minutes

    Does pressure hold at 1500 kPa?

    Yes

    Locate and repair leak/s

    Retest at 1500 kPa for 30 minutes

    If possible ensure the water service is charged at mains pressure duringconcealment prior to commissioning. Note: smaller services may require regular

    ushing to elimate problems caused by dead water over a long period.

    Is service DN80 or larger or supplied from a storage tank?

    No

    Yes

    After t off ush each outlet(0.75m/s velocity) to remove dirty

    water and debris

    No

    Service/tank to be ushed anddisinfected as per Appendix G

    and/or H AS/NZS 3500 1.2

    COMMIssIONINGWhen the water service has been completed, check the operation of all taps,

    valves, cisterns, etc., to conrm their correct performance.