32
5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition of ALP Seminar Series organized by Akindelano Legal Practitioners (ALP)

5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

Embed Size (px)

Citation preview

Page 1: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

5th Marcch,2014

The Nigerian Power Sector- Post Privatization Challenges and Prospects

By Dr. A. T. Atiku

Deputy Managing Director at the

3rd Edition of ALP Seminar Series organized by Akindelano Legal Practitioners (ALP)

Page 2: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

Outline

2

1. IntroductionObjectives of Reforms and Privatization of Power SectorPrivatization UpdateTCN Management Contract

2. Overview of TCNCore TCN FunctionsTransmission System DataPower GridSystem/Market Operation PracticeTransmission Planning Practice

3. Challenges in the Power Sector4. Way Forward

FundingGrid Best PracticePower System Stability Issue

5. Conclusion

Page 3: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

Objectives of Reforms and Privatization of Power Sector

Ensure Rapid growth in stable power supply on a reliable and sustainable basis

Lower cost of production and enable Nigeria’s manufacturing sector to compete favourably internationally

Reduce FGN’s expenditure profileFuel the growth and development of other

economic and social activities and become the engine driving job creation

3Source: BPE Presentation on Post Privatization Challenges

Page 4: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

4

Privatization Update

After a Two years and Five months of rigorous

and complex transaction process, successful

preferred bidders paid for the Generation and

Distribution companies on August 21 2013

The 14 Companies were handed over to the

new owners on November 1, 2013

Kaduna Disco and Afam Genco already have

preferred bidders Source: BPE Presentation on Post Privatization Challenges

Page 5: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

5

Privatization Update cont’

RFP’s were harvested on 8th November 2013

for the 10 NIPP plants privatization

A total 40668 Workers of PHCN have been

paid their severances, gratuity and pension in

full

This signals a new dawn for the

transformation of the power sector in

Nigeria Source: BPE Presentation on Post Privatization Challenges

Page 6: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

TCN is at the forefront of achieving the overall well planned privatization programme by the federal Government . Hence as part of the privatization process TCN management was decided to be contracted out.

Manitoba Hydro International (MHI) of Canada and Grid Co. of India submitted their bids for the Management Contract

6

Privatization Update cont’

Page 7: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

The appointment after international competitive bidding process of MHI as Management Contractor of TCN was particularly to;

Management Contracting

• Inject expertise in capital programme planning and delivery

• Bring in experience on market development and the evolution of the MO, SO and TSP functions

• Leading to ring fencing and unbundling of TCN into the three Business Entities.

• Enable knowledge transfer to, and development of, Nigerians to manage the Transmission Business

Page 8: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

• To transition TCN into a financially sustainable, stable, self-sufficient and market driven company that transmits generated energy throughout Nigeria and that is available 24 hours a day, 365 days a yearA key prerequisite in attaining this goal is to

develop the capacity of local personnel such that, by the end of the contract period, Nigerians can take over efficiently and effectively the Management and Operation of the Company

Goals and Objectives of TCN Management

Page 9: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

• to ensure a reliable, cost effective network for the supply of electrical energy and help facilitate the increased availability of electricity throughout Nigeria

• to develop the Company’s capability to build for its long-term future and sustainability.

• to separate the activities of the three principal functions of the Company (MO, SO and TSP) to enable them operate as distinct viable business units and prepare them for concession in future

Goals and Objectives cont’

Page 10: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

• TCN is among the 18 successor companies ‘unbundled’ from PHCN; set up as a corporate entity in 2006

• Performs three principal functions namely: Market Operations (MO), System Operations (SO) and Transmission services Provider(TSP)

• TCN is a strategic National asset, retained in state ownership

• TCN is responsible for its efficient operation, maintenance, expansion and reinforcement of the National Grid that ensures system stability and reliability.

An overview of Transmission Company of Nigeria

Page 11: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

Core TCN FunctionsSO

Efficient scheduling and dispatch

Demand forecasting, system and operational planning

Grid Code compliance Fault management

and restoration Security and Reliability

TSP Design,

specification, commissioning, construction of assets

Inspection, preventive and planned maintenance

Connections

Field workforce

Project management

MO

Settlements (energy and cash balancing)

Payments (collections from Discos, payments to Gencos and other market participants

Bulk metering

Page 12: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

The task of Transmission Company of Nigeria entails the development and maintenance of a reliable transmission grid in order to:

Provide Equal Access for power

evacuation to all participants at all times

Ensure full evacuation capability and

reliability at minimum technical loss

Ensure equitable load allocation to

consumers

12

Function

Page 13: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

PEAK DEMAND FORECAST 10,200MWMAXIMUM GENERATION CAPABILITY 5781MWPEAK GENERATION TO DATE 4321MWMAXIMUM INSTALLED CAPACITY 9,915.4MWMAXIMUM ENERGY GENERATED 96,768.53MWH

139

MAXIMUM VOLTAGE 330KVSTATUTORY LIMITS 313.5KV – 346.5KVNOMINAL FREQUENCY 50HZSTATUTORY LIMITS 49.75HZ – 50.25HZ

Transmission System Data

Page 14: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

1 Capacity 330/132kV (MVA) 8,1382 Capacity 132/33kV (MVA) 10,1623 Number of 330kV Substations 284 Number of 132kV Substations 1195 Total Number of 330kV circuits 60

6 Total Number of 132kV circuits 153

7 Length of 330kV lines (kM) 5,650

8 Length of 132kV lines (kM) 6,687

9 Work Centres 34

10 National Control Centre 1

11 Supplementary National Control Centre 1

12 Regional Control Centres 8

Transmission Data

Page 15: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

GOMBE

YOBE

BORNO

BAUCHI

TARABA

PLATEAU

ZAMFARA JIGAWA

KANO

KATSINA

KADUNA

SOKOTO

KEBBI

NASSARAWA

ONDO

NIGER

OSUN

EKITI

KWARA

OYO

DELTA

EDO

KOGI

AN

AM

BR

A

EN

UG

U

BENUE

ABIA

AKWAIBOM

IMO

RIVERSBAYELSA

OGUN

Maiduguri W/C

Yola W/C

Makurdi W/CAjaokuta W/C

Jos W/C

Shiroro W/CKainji W/C

Jebba W/C

Abuja W/C

Dutse W/C

Kano W/CGusau W/C

B/Kebbi W/C

Kaduna W/CGombe W/C

New Haven W/C

Onitsha W/COwerri W/C

Calabar W/C

Ahoada W/C

Sapele W/C

Delta W/C

Papalanto W/C

Afam W/C

Ikot Ekpene W/C

Benin W/C

Benin North

Omotosho W/C

Osogbo W/C

Ilorin(Ganmo) W/C

Ayede W/C

Akangba W/C Ikeja West W/C Egbim W/C Aja W/C

15

GEOGRAPHICAL STRUCTURE OF THE TRANSMISSION COMPANY OF NIGERIA, TCN

TCN is comprised of eight Transmission Regions each headed by a General Manager (Transmission) who are responsible for running and maintenance of transmission and transformation facilities in their areas of operation as shown in the following map of Nigeria:

Page 16: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

TO SAKETE

ONITSHA

KAINJI

JEBBA/GS

JEBBA/TS

SHIRORO

Ikeja

Akure

Uyo

BirninKebbi

Minna

Kaduna

Abuja

Jos

Bauchi

Gombe

Damaturu

MaiduguriKano

IIorin

AdoEkiti

EnuguAkwa

Ibadan

Sokoto

Gusau

Katsina

Hadejia

Jalingo

Yola

Abakaliki

Calabar

JIGAWA

KANO

KATSINA

SOKOTO

ZAMFARA

KEBBI

KWARA

KADUNA

NIGER

NASSARAWA

TARABA

YOBE

PLATEAU

EBONYI

CROSSRIVER

OSUN

BAYELSA

EDO

DELTA

ONDO

OYO

IMO

ADAMAWA

BORNO

GOMBE

BAUCHI

EKITI

LAGOS

ATLANTIC OCEAN

NIGER

REPUBLICOF BENIN

REPUBLICOF CAMEROON

REPUBLICOF

CHAD

SAPELEP/ST.

DELTAPOWER ST.

OGUN

Osogbo

NIGERIA

Potiskum

Niamey

132 kV

Mambila

Bali

AFAM POWER ST.

AsabaBenin

EGBINP/ST.

Lokoja

ABUJA

AJAOKUTA

Lafia

Makurdi

MAKURDI

BENUEKOGI

ENUGU

Aliade

ABIA

AKWAIBOM

Owerri

AN AMBRA

PortHarcourt

RIVERS

Umuahia

2

2

2

22 2

2

4

3

TRANSMISSION LINE LEGEND

BULK SUPPLY POINT

HYDROELECTRIC POWER STATION

THERMAL POWER STATIONS

330 KV

H

330KV LINES (EXISTING) – MULTIPLE CIRCUITS

330KV LINES - EXISTING

2

2

2

330KV LINES (FGN) – MULTIPLE CIRCUITS

330KV LINES (PROPOSED PROJECT) – MULTIPLE CIRCUITS

330KV LINES (NIPP) – MULTIPLE CIRCUITS

330KV LINES - FGN

330KV LINES - NIPP

330KV LINES - PROPOSED PROJECT

2

Nigerian Power Grid: Existing 330KV Lines Network

ALAGBADO

Abeokuta

Olorunsogo

Page 17: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

17

Calabar

561MW

Geregu414M

W

Olorunsogo 1

355MW

Omotosho

335MW

Ibom155MW

Egbema

270MW

SHELL650M

W

Ihovbor

360MWSapele

150MW

Shiroro

600MW

Jebba578.4MW

Kainji760M

W

Egbin/AES

1,622MW

Delta900M

W

Afam351M

W

Okpai480M

W

Sapele720M

W

Omoku150M

W

Omoku NIPP

200MW

N I G E R I A

Alaoji305MW

Insert fig shows the concentration of power stations remote from major load centre. This has posed a major challenge in power evacuation to the load centers

Power Station Spread in Nigeria

Olorunsogo II

500MW

Page 18: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

System Operation Practice

The responsibility of SO includes the following:

allocating available generating capacity to Bulk Supply Points

(BSPs)/distribution entities/ bulk customers (these may be large

industrial and commercial users in country, or other countries).

ensure the National Control Centre (NCC), together with the

Supplementary National Control Centre (SNCC) and the Eight

Regional Control Centres, perform their ‘despatch’ function on a day

to day basis and

ensure conformance with the terms of the Grid Code

Coordinate the preparation of the 20yr Nigerian Power Sector

Master Plan

The System Operator (SO)

Page 19: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

System Operation Practice

Generators Objectives Maximize Profit Meet Demand Contracts Get More Customers Transmission Objectives Meet Transaction Contracts Maximize Profit System Operator’s objectives• Ensure Network Security and Reliability

Page 20: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

Market Management Practice

The Market Operator (MO).

Formally referred to as the Operator of the Nigerian Electricity Market (ONEM).

Administration of bulk metering at the interface between generators/ TCN;

and TCN /the distributors/bulk users;

Ensure conformity with the Market Rules

Settlements; payments and equalisation

Contribute in the major review of the Multi Year Tariff Order (MYTO) and

planned changes to the Market Rules.

Page 21: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

Transmission Planning PracticeThe Transmission Service Provider (TSP)

To manage, operate and maintain the transmission network

To ensure accurate energy metering at the transaction points

ensuring the transmission network is extended and upgraded

Guarantee stability and security of the transmission facilities

to enable the efficient evacuation of power from generators to

the distributor and large industrial/commercial users.

Key responsibilities include:

Page 22: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

22

Key Challenges in the Power SectorTransmission

• Evacuation Bottlenecks• Menace of Erosion of Tower bases• Violation of Transmission Right of Ways• Ageing Workforce• Lack of adequate technical manpower at various

work centres• Old and Obsolete Equipment• Overloaded transmission lines and Substations• Control of the Grid is still largely manual• Inadequate Infrastructure coverage • Inadequate Funding• Vandalism

Page 23: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

23

Key Challenges in the Power Sector

• Inadequate Infrastructure coverage • Limited Funds for Development projects• Inadequate supply of Gas for Thermal Stations• Low Water level in the Hydros• Ageing Workforce• Lack of adequate technical manpower at various

stations• Old and Obsolete Equipment• unhealthy distribution networks (33kV, 11kV and

0.415kV

Generation and Distribution

Page 24: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

24

Key Challenges cont’

• Inadequate funding of the power sector• Slow performance by contractors• Unpredictable energy sources (water and gas pose

serious operation planning problems.• Large disparity between energy supply and demand.• Inadequate telecommunication facilities and control

aids limit operational effectiveness .• Low voltage in the North due to concentration of

Power Stations in the South

Page 25: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

25

Evacuation Bottlenecks

Generation -Transmission interface constraintsTransmission Substation capacity constraintsTransmission lines and wheeling constraintsTransmission - Distribution interface constraints

Page 26: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

26

Load Shedding

Voltage/Frequency instability

Stranded power

System Collapse due to inadequate generation and spinning reserves and lack of redundancies in transmission

Effects of Evacuation Bottlenecks

Page 27: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

Way Forward

Encourage investment in Transmission by: Contractor-Financing Foreign Loans ( Euro Bond, AFDB, World Bank, ABD,

JICA and China Nexxim Bank etc). Recently, a conference was organized on Financing Power Projects in Nigeria were about 300 participants attended and about 12 MOUs signed between potential investors and TCN.

Another potential investment is from NDPHC from sales of its 10 Power Plants to upgrade the transmission infrastructure.

Page 28: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

Way Forward cont’

Create Adequate network redundancies to meet up with N-1 Contingency / security criterion

Reduce Transmission Loss to comply with NERC requirements on the 4.5GW existing Transmission network as soon as possible.

MHI has come up with a blueprint on system improvement over the next 5 years with corresponding financial requirements which aligns with 10GW, 16GW and 20GW transmission capabilities to be achieved.

Page 29: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

GRID BEST PRACTICE

DEMAND FORCAST AND INSTALLED CAPACITY

Transmission Expansion Plan

Expansion strategy should include the following

All 330kV Transmission corridors to have alternative

evacuation routes

All 132kV Transmission Lines to have alternative evacuation

routes

Substation Automation should be pursued.

State Capitals to have 330/132kV Transmission Substation

Local Govt. Headquarters to have at least 2x40MVA 132/33kV

Transmission Substation

Page 30: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

Power System Stability Issues

Frequent review of powers system studies

Dynamic system stability studies and

mitigation procedures to minimise system

collapse

Insulation coordination studies for avoiding

chattering of substation equipment

Protection coordination particularly at the

interface connection points

Page 31: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

Conclusion

TCN as a critical component of the Power Sector Value Chain

which should not be the weak-link for the Power Sector Reform

to achieve its aim.

Sustained and Adequate funding mechanism must be in place

for TCN to enable it cope with the increased generation and

improved distribution facilities to be realised from the privatized

Gencos and Discos

Federal Government of Nigeria needs to concentrate its

financial investment in Power in the Transmission Sector which

is still publicly owned to ensure the success of the Reforms and

Transformation agenda

Page 32: 5 th Marcch,2014 The Nigerian Power Sector- Post Privatization Challenges and Prospects By Dr. A. T. Atiku Deputy Managing Director at the 3 rd Edition

32

Thank You for listening