Upload
marko-barisic
View
255
Download
1
Embed Size (px)
Citation preview
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 1/49
Generator Stator
Testing
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 2/49
AGTS ervices , Inc.
Generating timely r epair soluti ons
Session Objective
• Identify Stator Tests
– Electrical
• Standard and Specialized
– Mechanical
• Standard and Specialized
• Identify Standards That Define Tests
– IEEE
– ANSI
• Periodic Test Recommendations
• Testing Logic
• Examples Of: – bad test results
– recommendation/corrective actions
– good test results
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 3/49
AGTS ervices , Inc.
Generating timely r epair soluti ons
Purpose of Stator Testing
• Identify & correct detrimentalsituations before serious/expensive
damage occurs
• Provide confidence that the windingwill not fail in-service prior to the nextoutage
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 4/49
AGTS ervices , Inc.
Generating timely r epair soluti ons
IEEE Standards
ANSI / IEEE STANDARD TITLE
95
IEEE Recommended Practice for Insulation
Testing of Large AC Rotating Machinery with
High Direct Voltage
43
IEEE Recommended Practice for Testing
Insulation Resistance of Rotating Machinery
C50.10
American National Standard General
Requirements for Synchronous Machines
56
IEEE Guide for Insulation Maintenance of
Large Alternating Current Rotating Machinery(10,000 KVA and Larger)
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 5/49
AGTS ervices , Inc.
Generating timely r epair soluti ons
Industry Standard Recommendations
Grounding time should be 4x charge time - min. 1 hour IEEE 43 - sect. 4.6.2IEEE 95 - sect. 4.7.1
Windings should be shorted during high voltage tests to protect
against surges in the event of a failure IEEE 43 - sect. 7.2.4.1
Rm = minimum 1 minute megger at 40 deg. C should be : Rm = E
+1 where Rm = megs,E = rated AC line-to-line voltage in kilo volts (KV)
For 13.8 KV machine, Rm = 13.8 + 1 = 14.8 megs should expect
10 - 100 times minimum on healthy, clean windings IEEE 43 - sect. 8.2 & 9.3 & 9.3.4
Minimum PI for class B & class F stators prior to high voltage
testing = 2.0
IEEE 43 - sect. 9.2
IEEE 95 - sect. 6.3
Machines rated above 10 MVA should have both PI & megger
values per above before performing high voltage testing IEEE 43 - Section 9.5
New stator winding hi pot = 2E & 1 KV ANSI C50.10 section 9.3.1.1
New field winding hi Pot = 10 E AC ANSI C50.10 section 9.3.1.2.1
Hi Pot voltage is held for 1 minute
ANSI C50.10 section 9.3.3
IEEE 95 - section 5.3
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 6/49
AGTS ervices , Inc.
Generating timely r epair soluti ons
• Measure with Kelvin Bridge/DLRO
• Determine if phase resistances:
– Are balanced – Reflect design / factory
readings
– Are consistent over time
Winding Resistance
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 7/49
AGTS ervices , Inc.Generating timely r epair soluti ons
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 8/49
AGTS ervices , Inc.Generating timely r epair soluti ons
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 9/49
AGTS ervices , Inc.Generating timely r epair soluti ons
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 10/49
AGTS ervices , Inc.Generating timely r epair soluti ons
C
(LEFT)
B
(CENTER)
A
(RIGHT)
Resistance Taken @ 29OC 0.002287 0.002283 0.002284
Resistance Corrected to 25OC 0.002252 0.002248 0.002249
Factory Resistance @ 25OC 0.003120 0.003115 0.003116
Phases shou ld be balanced w ithin 1%
Winding Resistance
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 11/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Winding Resistance
• Problem if: – Not balanced
• Deteriorated bolted connection
• Deteriorated braze or solder joint• Cracked/broken strands
– Significantly different from factory /historical tests
• Poor test• Global deterioration
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 12/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Winding Resistance
• Recommendations:
– Search & Dissect
• Strip & inspect bolted connection(s)
• Sample strip & inspect braze/solder joints• Sample strip to expose strands
– Current & Thermo-Vision
• Not an industry standard test
• From experience
– 1000 amps/in2 of conductor cross section
– Investigate > 5o C differential
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 13/49
AGTS ervices , Inc.Generating timely r epair soluti ons
• Generally referred to as Megger test
• Per IEEE 43 & IEEE 95
• For stator windings, typically performed at either2500 VDC or 5000 VDC (megger)
• Indicates general cleanliness / dryness / condition of
insulation system
• Indicates insulation system is capable of highervoltage testing
Insulation Resistance & Polarization Index
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 14/49
AGTS ervices , Inc.Generating timely r epair soluti ons
PI - Before Drying
INSULATION RESISTANCE
0
500
1000
1500
2000
2500
0.5 1 2 3 4 5 6 7 8 9 10
MINUTES
M E G O H M S
C-Left
B-Center
A-Right
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 15/49
AGTS ervices , Inc.Generating timely r epair soluti ons
PI - After Drying
INSULATION RESISTANCE
0
1000
2000
3000
4000
5000
6000
7000
0.5 1 2 3 4 5 6 7 8 9 10
MINUTES
M E G O H M S
C-Left
B-Center
A-Right
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 16/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Insulation Resistance & Polarization Index
• Suitability for service megger, per IEEE43 – @ 1 minute, > E +1 in Megohms
– Expect 10 – 100 times that for clean, dry,healthy windings
• 10 min. megger reading / 1 min. reading
• Minimum PI for high voltage testing, per
IEEE 43 & 95 – 2.0 for class B and class F insulationsystems
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 17/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Insulation Resistance & Polarization Index
If megger or PI is low:
– Clean
• Solvents / rags
• Dry Ice (CO2) or corn cob blast
– Dry
• Heaters & dehumidifiers
• Current through the winding• Bake/oven
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 18/49
AGTS ervices , Inc.Generating timely r epair soluti ons
DC Leakage Test(Controlled Over Voltage)
• Somewhat over-voltage test
• Observe insulation characteristics upon
increasing voltage
• Can possibly see failure prior to
occurrence & abort test
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 19/49
AGTS ervices , Inc.Generating timely r epair soluti ons
DC Leakage Test(Controlled Over Voltage)
• Apply initial DC voltage
• Increase voltage in steps
• Hold at each step for a determined period• Monitor leakage current at each step
– In a perfect world, E = I*R yields astraight line when plotted
– If current takes off exponentially, canpossibly stop test prior to insulationfailure
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 20/49
AGTS ervices , Inc.Generating timely r epair soluti ons
DC LEAKAGE
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
10 12 14 16 18 20 22 24 26 28
KV
M I C
R O A M P S
A - Left
B -Center
C -Right
DC Leakage - Bad
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 21/49
AGTS ervices , Inc.Generating timely r epair soluti ons
DC LEAKAGE
0.00
5.00
10.00
15.00
20.00
25.00
10 12 14 16 18 20 22 24 26 28 30 32
KV
M I C
R O A M P S
C - Left
B -Center
A -Right
DC Leakage - Good
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 22/49
AGTS ervices , Inc.Generating timely r epair soluti ons
DC Leakage Test(Controlled Over Voltage)
• Graded method (IEEE 95 Appendix A) – Initial voltage approximately DC equivalent
of 0.3 E or 10 KVDC
– Each step increase = 20% of initial voltage – Time intervals per calculated “N” number
and IEEE 95 Table A1
– Max. Voltage typically E x 2 (2E) DC with no
conversion multiplier
Typically, 10 KVDC for < 18KV / 15 KVDC for > 18KV
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 23/49
AGTS ervices , Inc.Generating timely r epair soluti ons
High Voltage (Hi Pot) Testing
• Proof test
• DC or AC?
– DC via IEEE 4, 95 & 56, ANSI C50.10
– AC via IEEE 43 & 433 (.1 Hz.)
– DC has proven adequate for decades
– Some feel AC is “better”, but can notquantify
• DC value is 1.7 x AC value per IEEE 95
• Recommended test value per IEEE 56125% to 150% of rated line to line voltage
• 60 second duration
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 24/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Power Factor/Tip Up
(Doble Test)
• IEEE 286
• Indicates voids/delamination of insulation
• Sensitive on short conductors
• Loses sensitivity as conductors are connected in
series
• Track/trend data over-time for analysis
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 25/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Power Factor/Tip Up
(Doble Test)
• Measure Power Factor at low AC voltage
(25% phase to ground, below PD levels)
• Measure power factor at higher voltage(100% phase to ground)
• Calculate difference in % = % Tip Up
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 26/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Power Factor/Tip Up (Doble Test)
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 27/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Resistance Temperature Detection
Devices (RTD’s)
• Isolate from
instrumentation
• Measure resistance of
legs – Compare to each other
– Compare to expected
• Megger (500 volts)
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 28/49
AGTS ervices , Inc.Generating timely r epair soluti ons
RTD’s
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 29/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Inner Gas Cooled Windings
Westinghouse and GE
• Tube-to-TubeResistance
• Tube-to-StrandResistance
• Tube-to-Copper 5,000Ohm Resistor Test
• Gas Flow• Core Torque – Thru
Bolts and Building Bolts
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 30/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Electro Magnetic Core Imperfection
Detector (EL CID)
– Performed in lieu of Ring
Test @ 85% rated flux – Applies 4% rated flux
density
– Measure current between
laminations – High current indicates
shorted laminations
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 31/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Electro Magnetic Core Imperfection Detector
(EL CID)
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 32/49
AGTS ervices , Inc.
Generating timely r epair soluti ons
Core Ring (Loop) Test
– Performed @ 80% - 95%
rated flux
– Thermovision Camera
used to detect
temperature differential
– W – during rewind 5 C,
otherwise 10 C
– GE - ~18 C
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 33/49
AGTS ervices , Inc.
Generating timely r epair soluti ons
Core Ring Test Set Up
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 34/49
AGTS ervices , Inc.
Generating timely r epair soluti ons
Core Ring Test Set Up
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 35/49
AGTS ervices , Inc.
Generating timely r epair soluti ons
Thermo-Vision Analysis
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 36/49
AGTS ervices , Inc.
Generating timely r epair soluti ons
“Hot” Spots Detected via Thermo-Vision
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 37/49
AGTS ervices , Inc.
Generating timely r epair soluti ons
Core Ring Test – Prior
to Core Restack
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 38/49
AGTS ervices , Inc.
Generating timely r epair soluti ons
Core Ring Test – After
Core Restack
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 39/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Bottom of Slot Before Unstacking Core Iron
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 40/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Bottom of Slot After Unstacking Core Iron
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 41/49
AGTS ervices , Inc.Generating timely r epair soluti ons
End Winding Resonance Frequency
Test (Bump Test)
• Excite end winding with calibrated,accelerometer equipped hammer
• Monitor response via accelerometer
• Investigate amplitude & frequency ofresponse
• Modify as required: – Add stiffness
– Add mass – Reduce stiffness
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 42/49
AGTS ervices , Inc.Generating timely r epair soluti ons
End Winding Resonance Test
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 43/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Bump Test - Tangential Excitation
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 44/49
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 45/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Initial Bump Test Results
Tangential Radial
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 46/49
AGTS ervices , Inc.Generating timely r epair soluti ons
After Nose Ring Modification
B T t R lt
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 47/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Bump Test Results(After End Winding Stiffening)
Tangential Radial
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 48/49
AGTS ervices , Inc.Generating timely r epair soluti ons
Other Tests - Specialized
• Surge
– Performed during rewind of multi turnbars/coils
– Tests turn insulation
– Comparison test
– Not sensitive on long conductors
• Partial Discharge
– Monitors quantity & magnitude of highfrequency/partial discharges
– On-line/off-line – Indicator of winding condition
• AC Hi Pot – 60 Hz and .10 Hz
8/10/2019 5-Generator Stator Testing.pdf
http://slidepdf.com/reader/full/5-generator-stator-testingpdf 49/49
AGTS ervices , Inc.
Stator DC Testing Summary
• Phase (Winding) Resistance
• 2.5 KV or 5 KV Insulation Resistance (Megger) &
Polarization Index (PI)
• DC Leakage Test
• High-potential Test(Hipot)
• RTD Resistance & Megger
• EL CID Test