4TPD Tentative Costs - Cashew Processing Unit

Embed Size (px)

Citation preview

  • 7/30/2019 4TPD Tentative Costs - Cashew Processing Unit

    1/2

    PROJECT PROFILE FOR CASHEW PROCESSING UNIT(CAPACITY 4 TPD)

    1.0 SCOPE OF THE PROJECT IN THE AREA OF OPERATION

    Sufficient information needs to be collected about the availability of raw

    material in the area, no of existing cashew processing with their processingcapacity and arrangement of marketing of cashew.

    The annual capacity assuming working for 300 days work out to 1200 tons ofraw cashew and shall produce 153 MT of whole cashew nuts, 102 MT brokencashew nuts, 51 MT of small bits and other products at 85% capacityutilization.

    2.0 FOR IMPLEMENTATION OF THE PROJECT:

    The society has to raise the requisite share capital;

    Land Purchase/Leased by the society;

    Obtained assurance from State Electricity Board for providing required

    electricity connection;

    NOC from Pollution control board;

    Prepared plan and estimates for civil work of main plant and other

    ancillary buildings;

    Obtained quotations from suppliers of plant & machinery and other

    equipments;

    Identify market for finished products.

    3.0 PROJECT COMPONENTS AND THEIR TENTATIVE COST(Rs. in lakhs)

    3.1 Land and Land Development

    Cost of Land (6200 sq. metres) 7.00

    Cost of Leveling/Development 1.00

    Cost of Boundary Wall & Fencing 2.00

    TOTAL - 10.00

    3.2 Civil Works Plant Shed (600 Sq.M) 48.00

    Raw Material Godown (300 Sq,M) 13.50

    Finished Goods Godown(250 Sq,M) 11.50

    Boiler, Store & Toilets 10.00

    Security Office 1.00

    Administrative Office 1.50

    Drying Room (250 Sq,M) 5.00

    TOTAL - 90.50

    3.3 Plant & Machinery (Processing Capacity 4 tons of raw cashew per day) 85.00

    Excise Duty & other Taxes 14.00

    TOTAL - 99.00

  • 7/30/2019 4TPD Tentative Costs - Cashew Processing Unit

    2/2

    3.4 Miscellaneous Fixed Assets

    OFFICE FURNITURES & FIXTURES 2.50

    COMPUTER & OFFICE EQUIPMENT 1.50 ELECTRICAL EQUIPMENTS 6.50

    FIRE FIGHTING EQUIPMENTS 1.00

    M.S.E.B. DEPOSIT, TRANSFORMER ETC. 4.00

    VEHICAL (TRUCK) 18.00

    Miscellaneous Others 5.00

    TOTAL - 38.503.5 Pre-operative Expenses - 15.50

    3.6 Margin Money for Working Capital requirement for one month.

    TOTAL - 114.50TOTAL PROJECT COST - 368.00

    4.0 PROJECT IMPLMENTATION SCHEDULE

    It is expected that the project is completed within one year after sanction offinancial assistance.

    5.0 REQUIREMENT OF STAFF

    The mill will require approximately 200 workers and 20 staff.

    6.0 PATTERN OF FUNDING:

    As per NCDCs pattern of funding for Cooperatively Developed States 90% ofloan is sanctioned to the State Govt. for passing on to the beneficiarysocieties as 50% loan and 40% share capital contribution. However, the debtequity ratio may vary depending on viability of the proposed project. In caseof Under-developed & Least-developed States subsidy is available 20% &25% respectively of the project cost.

    Loan application forms are available with the offices of Registrars ofCooperative Societies/Regional Directorates of the NCDC besides HeadOffice at New Delhi. Application forms can also be downloaded fromNCDC Web-site (http://ncdc.in).

    RAW MATERIAL 90.50

    ELECTRICITY CHARGES 1.50

    SALARY& WAGES 2.50

    STORES & SPARES 1.50

    PACKING 0.50

    STOCK OF FINISHED GOODS 16.00

    STOCK OF GOODS IN PROCESS 2.00

    http://ncdc.in/http://ncdc.in/