47
Resettlement Due Diligence Report January 2019 Loan 3285-UZB: Northwest Region Power Transmission Line Project: Section 4– “Khorezm” Substation Section 7 – “Sarimay” Switchyard Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This resettlement due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

Resettlement Due Diligence Report January 2019

Loan 3285-UZB: Northwest Region Power Transmission Line Project: Section 4– “Khorezm” Substation Section 7 – “Sarimay” Switchyard Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This resettlement due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation

of or reference to a particular territory or geographic area in this document, the Asian

Development Bank does not intend to make any judgments as to the legal or other status of any

territory or area.

Page 2: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

Resettlement Due Diligence Report

January 2019

Loan 3285-UZB: Northwest Region Power Transmission Line Project: Section 4– “Khorezm” Substation Section 7 – “Sarimay” Switchyard Prepared by JSC Uzbekenergo for the Asian Development Bank

Page 3: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

2

ABBREVIATIONS

ADB – Asian Development BankAP – Affected PersonAH – Affected HouseholdCoM – Cabinet of Ministers of UzbekistanDMS – Detailed Measurement SurveyIA – Implementing AgencyEA – Executing AgencyEPC – Engineering, procurement, and constructionEMP – Environmental Management PlanDLARC – District Land Acquisition and Resettlement CommitteeDMS – Detailed Measurement SurveyFGD – Focus Group DiscussionGRM – Grievance Redress MechanismHa – HectareHH – HouseholdIA – Implementing AgencyIEE – Initial Environmental ExaminationLAA – Land Allocation ActLAR – Land Acquisition and ResettlementLARP – Land Acquisition and Resettlement PlanNWRTLP – Northwest Region Power Transmission Line ProjectNWMPN – North West Main Power NetworkO&M – Operation and MaintenancePMU – Project Management UnitPIC – Project Implementation ConsultantDDR – Resettlement Due Diligence ReportRoW – Right-Of-WaySCLRGCSC – State Committee on Land Resources, Geodesy, Cartography and

State CadasterSAESP – Sredazenergosetproject JSCSPS – Safeguard Policy Statement 2009ToR – Terms of ReferenceUE – UzbekenergoUZS – Uzbek Soum

CURRENCY EQUIVALENTS(As of January 15, 2019)

Currency Unit – Sum (UZS)$1.00 = UZS 8356.18

NOTEIn this report,

i. “$” refers to United State Dollars (USD)ii. UZS refers to Uzbekistan Sum

Page 4: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

3

Table of Contents

GLOSSARY .................................................................................................................................. 5

1. INTRODUCTION AND PROJECT BACKGROUND ............................................................... 7

1.1 Introduction ..................................................................................................................... 7

1.2 Project Background ........................................................................................................ 8

2. OBJECTIVES OF DUE DILIGENCE REPORT AND METHODOLOGY ................................. 9

2.1 Objective ........................................................................................................................ 9

2.2 Methodology ................................................................................................................. 10

2.3 Impact on Indigenous People ....................................................................................... 11

3. DUE DILIGENCE ON LAND ACQUISITION AND RESETTLEMENT .................................. 11

3.1 Possible Land Acquisition and Resettlement Impacts ................................................... 11

3.2 Khorezm Substation ..................................................................................................... 11

3.3 Sarimay Switchyard ...................................................................................................... 13

3.4 Impact of Construction to Access Roads ...................................................................... 15

3.5 Socio-economic Impacts ............................................................................................... 15

4. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION ........................ 16

4.1 General ........................................................................................................................ 16

4.2 Disclosure..................................................................................................................... 16

5. GRIEVANCE REDRESS MECHANISM ............................................................................... 17

5.1 General ........................................................................................................................ 17

5.2 Contact Details ............................................................................................................. 18

5.3 GRM Records and Documentation ............................................................................... 19

6. POLICY AND LEGAL FRAMEWORK .................................................................................. 19

6.1 General ........................................................................................................................ 19

6.2 Laws, Regulation, and Provision relating to LAR in Uzbekistan .................................... 20

6.2.1 Constitution ........................................................................................................... 21

6.2.2 Land Code (30 April 1998)..................................................................................... 21

6.2.3 Resolution of Cabinet of Ministers № 97 (29 May 2006) ........................................ 22

6.2.4 Civil Code (29 August 1996) .................................................................................. 22

6.2.5 Resolution of Cabinet of Ministers № 146 (25 May 2011) ...................................... 23

6.2.6 Resolution of Cabinet Ministers №317 (21 September 2016) ................................ 24

6.2.7 Resolution of Cabinet Ministers №3857 (16 July 2018) ......................................... 24

6.2.8 Decree of the President of the Republic of Uzbekistan №5495 (1 August 2018) ... 25

Page 5: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

4

6.2.9 Resolution of Cabinet of Ministers № 1047 (26 December 2018) .......................... 25

6.2.10 Presidential Decree 5421 (20 April 2018) .............................................................. 25

6.2.11 Resolution of Cabinet of Ministers № 44 (15 February 2013) ................................ 26

6.2.12 Tax Code ............................................................................................................... 26

6.2.13 Labor Code and Employment Law ......................................................................... 27

6.3 ADB Safeguard Policy Statement, 2009 ....................................................................... 28

7. INSTITUTIONAL ARRANGEMENT ..................................................................................... 30

7.1 General ........................................................................................................................ 30

7.2 UE and Project Management Unit ................................................................................ 30

7.3 Social Safeguards Specialists (SSS) ............................................................................ 31

7.4 Design Institute - “JSC Sredazenergosetproekt” (SAESP) ............................................ 31

7.5 UzDavYerLoyiha Design Institute ................................................................................. 31

7.6 District Branch of State Committee on Land Resources, Geodesy, Cartography and

State Cadaster (SCLRGCSC) ................................................................................................. 31

7.7 District (Khokimyat) (Governorates) .............................................................................. 32

7.8 Community-Based Organizations (CBOs)..................................................................... 32

8. IMPLEMENTATION SCHEDULE ........................................................................................ 32

9. CONCLUSION AND RECOMMENDATIONS ...................................................................... 33

9.1 Annex 1: No-objection Letter by ADB ........................................................................... 36

9.2 Annex 2: Architectural Planning Assignment for Khorezm Substation ........................... 37

9.3 Annex 3: Extract from Architectural Planning Assignment for Khorezm Substation ....... 38

9.4 Annex 4: Extract from Cadaster Document of Khorazmelektrqishloqqurilish ................. 39

9.5 Annex 5: Architectural Planning Assignment for Sarimay Switchyard ........................... 40

9.6 Annex 6: Extract from Architectural Planning Assignment showing the Allocated Land 41

9.7 Annex 7: Land Selection Order by District Khokim for Sarimay Switchyard .................. 42

9.8 Annex 8: Land Selection act prepared by Uzgiprozem for Sarimay Switchyard ............ 43

9.9 Annex 9: List of Consulted Stakeholders ...................................................................... 44

9.10 Annex 10: List of Consulted Stakeholders .................................................................... 45

9.11 Annex 11: List of Consulted Stakeholders .................................................................... 46

Page 6: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

5

GLOSSARY

Affected Persons Affected persons (APs)are the members of the affectedhouseholds, those who experience full or partial, permanent ortemporary physical displacement (relocation, loss of residentialland, or loss of shelter) and economic displacement (loss of land,assets, access to assets, income sources, or means oflivelihoods) resulting from (i) involuntary acquisition of land, or (ii)involuntary restrictions on land use or on access to legallydesignated parks and protected areas. Although this definition ofaffected people is at variance with the usage in the SPS-2009,this is how it is understood and officially used in Uzbekistan, andit is not different from ‘displaced person’ defined in the SPS-2009.

Affected Household A household consists of one or more people who live in thesame dwelling and share meals or living accommodation andmay consist of a single family. In the project, the household isthe unit for compensation and all the members of ahouseholdare considered as affected persons.

Architectural PlanningAssignments

A document containing a set of town-planning and architecturalrequirements. To construct an object following documentationshall be submitted such as approved city-planningdocumentation, relevant decisions of state authorities, includingrequirements and conditions for the protection of historical andcultural monuments, the environment, legal rights and interestsof third parties, persons for a specific land plot. Based onthesedocuments, architectural planning assignment for construction isbeing developed (re-constructions) of the object.

Cadastral Document A set of materials, cadastral surveys, technical inventories andcertification, quality and valuation of the object necessary for theformation, accounting and subsequent state registration of rightsto real property.

Compensation Payment for an asset to be acquired or affected by a project atreplacement cost.

Cut-off-date The date after which people will not be considered eligible forcompensation, i.e., they are not included in the list of AHs asdefined by the census. If the country expropriation law does notspecify a cut-off date, usually, the cut-off date is the date of thedetailed measurement survey which is based on the finalengineering design. The validity of the cut off date in ADBprojects typically is three years.

Economic Displacement Loss of land, assets, access to assets, income sources, ormeans of livelihoods, as a resultof (i) involuntary acquisition ofland, or (ii) involuntary restrictions on land use or access tolegally designated parks and protected areas.

Page 7: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

6

Entitlement The range of measures comprising the cost of compensation,relocation cost, income rehabilitation assistance, transferassistance, income substitution, and relocation which are due to/business restoration, which isdue to AH, depending on the typeand degree nature of their losses, to restore their social andeconomic base. All entitlements are given to all affectedhouseholds as per the entitlement matrix.

Hokimiyat Local government authority that interfaces between localcommunities and the government at the regional and nationallevel. It has ultimate administrative and legal power over localpopulations residing within its jurisdiction.

Land Acquisition The process whereby a person is compelled by a public agency toalienate all or part of the land s/he owns or possesses, to theownership and possession of that agency, for the State purposes,in return for fair compensation.

Land Allocation In this report, this term used when land is being allocated out ofthe unproductive/unsettled State Reserve Land or from the areasthat are being used by the State Organization for themodernization/construction of a new substation and transmissionline towers as well as stringing the power cables.

Land Use Rights According to Land Code (article 17) real persons (can have theland plot under the lifelong inheritable possession right and landparcel use transferred as descent. This right is given to individualresidential housing construction and collective gardening andvineyard (orchards), peasant farms. Juridical persons(enterprises, stores, and business) can possess land parcelsaccording to the right to permanent possession, permanent use,temporary use, lease, and property. In two above cases, when aperson wants to sell the Property (land and building), he will sellthe building & structure and subsequently, theland parcel sold asan attachment (right is sold).

Makhalla A local level community-based organization recognized officiallyby the State that serves as the interface between state andcommunity is responsible for facilitating a range of social supportfacilities and ensuring the internal social and culturalcohesiveness of its members and local communities to electMakhalla leaders.

Rangelands The lands on which the native vegetation (climax or naturalpotential plant community) including grasses,grass-like plants, forbs, or shrubs are grownin the mountains,some deserts, many wetlands, tundra, and certainForb and shrub communities. Comparing with pasture landwhere grasses planted explicitly for grazing livestock, inrangelands grasses are grown naturally without humaninvolvement.

Physical Displacement Relocation, loss of residential land, or loss of shelter as a resultof (i) involuntary acquisition of property, or (ii) involuntaryrestrictions on land use or access to legally designated parksand protected areas

Page 8: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

7

1. INTRODUCTION AND PROJECT BACKGROUND

1.1 Introduction

1. This Resettlement Due Diligence Report (DDR) prepared as part of the process of

compliance with the ADB guidelines in regard of the two sections of the Loan 3285-UZB:

Northwest Region Transmission Line Project (NWRTLP). Two sections are described

below (para 4).

2. The State Joint-Stock Company Uzbekenergo (UE) is the executing agency of the project.

The draft Land Acquisition and Resettlement Plan (LARP) was prepared by UE based on

the preliminary design in March 2015. According to draft LARP the NWRTLP was

classified as Category B for involuntary resettlement.

3. In 2018 Uzbekenergo asked ADB to split the project into seven parts to start construction

works in sections where there is no involuntary resettlement nor affected persons. Later in

this year, No-Objection to Land Acquisition and Resettlement Plan Revision Letter was

given by Energy division of Central and West Asia Department (Annex 1). As a result, the

project split into seven sections such as:

1) The power line section between Takhiatash TPS and 1st river-crossing of the

transmission line with the Amudarya river (Republic of Karakalpakstan)

2) The power line section between and 1st (Republic of Karakalpakstan)2nd (Khorezm

region) river-crossing of the transmission line with Amudarya river

3) The power line section between 2nd (Khorezm region) river-crossing of the

transmission line with Amudarya river and “Khorezm” Substation

4) “Khorezm” Substation

5) The power line section between “Khorezm” Substation and 3rd river-crossing of the

transmission line with the Amudarya river (Khorezm region)

6) The power line section between the 3rd river-crossing of the transmission line with

Amudarya river and Sarimay Switchyard

7) Sarimay Switchyard

4. This DDR is prepared for only two sections such as 4 and 7 as described above and for

the remaining sections an upgraded LARPs will be prepared as separate documents.

5. The detailed final design for above sections was prepared by the Joint-Stock Company

Sredazenergosetproekt (SAESP) specialized in transmission line during 2016 - 2018

years.

6. Based on documents review, final design, site visits, and consultation with local

stakeholders, the “Khorezm” Substation (section 4) and “Sarimay” Switchyard (section 7)

are classified as subprojects with no involuntary resettlement impact, and DDR has been

prepared.

7. The objective of this DDR is to confirm that the “Khorezm” Substation (section 4) and

“Sarimay” Switchyard (section 7) of NWRTLP do not trigger ADB’s Safeguard Policy

Statement (2009)’s Safeguard Requirements 2 regarding involuntary resettlement or

Safeguard Requirement 3 regarding Indigenous Peoples.

Page 9: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

8

1.2 Project Background

8. The Project will strengthen energy security through improved power system reliability and

efficiency by constructing a new transmission line without passing through any country.

9. NWRTLPis located in the south-western provinces of Karakalpakstan and Khorezm of the

Republic of Uzbekistan, near the border of Turkmenistan.

10. The new line will transmit power from Takhiatash Thermal Power Plant (TPP) and

increase the reliability of power supply for the Khorezm province and Karakalpakstan in

the northwestern part of Uzbekistan benefiting at least 3 million population.

11. The first part of the TL route passes across the territories of Hojeyli, Nukus, Karauzyak,

Amudarya and Beruniy districts of the Republic of Karakalpakstan, and Urgench and

Yangibazar districts of the Khorezm region of the Republic of Uzbekistan. The second

part of the projected TL route is laid across territories of Urgench, Hanka, Yangiarik,

Bagat and Hazarasp districts of the Khorezm region and the Turtkul district of the

Republic of Karakalpakstan.

Figure 1: Map of Takhiatash TPP – Sarimay TL route

12. Construction activities of the above mentioned will be done and financially covered by

Uzbekenergo. Procurement of the equipment and goods will be performed under ADB

loan. The total cost of the project is 258,5mln. USD. Feasibility study approved by Decree

of the President of Uzbekistan No. 2541 on 06 June 2016.

Page 10: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

9

13. The Project consists of the following main components:

i. Construction of 363.8 km of 220 kV single-circuit overhead transmission line:

between Takhiatash TPP and 220 kV Khorezm substation (197.7 km) and between

Khorezm and V1 node (166.1 km)

ii. Expansion/Rehabilitation/Construction of 2 Substations. Including (a) rehabilitation

and expansion of 220/110 kV Khorezm SS; and (b) construction of an open

switchyard 220 kV of a new 500/220 kV SS Sarymay near V-1 node (Sarimay

settlement) and

iii. Support for Institutional Development, Capacity Building, and Project

Management: including (a) consultancy service for project supervision and

management, (b) upgrading transmission system planning and dispatch

automation, (c) implementation of asset management system, (d) external auditing

for project accounting, and (e) strengthening UE operational and maintenance

capacity for transmission assets.

14. In this report, component ii) Expansion/Rehabilitation/Construction of 2 Substations.

Including (a) rehabilitation and expansion of 220/110 kV Khorezm SS; and (b)

construction of an open switchyard 220 kV of a new 500/220 kV SS Sarymay near V-1

node (Sarimay settlement) was reviewed only. Based on the No-Objection to Land

Acquisition and Resettlement Plan Revision Letter was given by ADB to Uzbekenergo this

component is divided into “Khorezm” Substation (section 4) and “Sarimay” Switchyard

(section 7)

2. OBJECTIVES OF DUE DILIGENCE REPORT AND METHODOLOGY

2.1 Objective

15. The objective of this DDR is to confirm that “Khorezm” Substation (section 4) and

“Sarimay” Switchyard (section 7) sections of NWRTLP do not trigger ADB’s Safeguard

Policy Statement (2009)’s Safeguard Requirements 2 regarding involuntary resettlement

or Safeguard Requirement 3 regarding Indigenous Peoples.

16. The specific impacts of the DDR were:

i) determine whether the modernization of existing “Khorezm” Substation and

construction of new “Sarimay” Switchyard is free of any involuntary resettlement

impacts, e.g., land acquisition, displacement, and

ii) ascertain if there would be any adverse impacts on income and livelihood on any

of the indigenous people.

17. Consultation meetings were carried out with relevant stakeholders, including cadastral

office, land use engineer, design engineers, transmission line operators of the project. As

a result of discussions and consultations Grievance Redress Mechanism (GRM) is

developed for the people living near to substations that may have a complaint or

questions during the construction works. Social Safeguards Specialist undertook the field

visits between January 16-19, 2019. The consultation focused on avoidance of impacts on

household, business community buildings and lands as well as a temporary disruption of

livelihood, if any, from the proposed construction works.

18. Disclosure of DDR will be done in Urganch city for people living near to Khorezm

substation and in Nukus settlement for people living near to Sarimay switchyard. In these

Page 11: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

10

meetings, Project objectives, ADB’s policy on Involuntary Resettlement, and Grievance

Redress Mechanism will be described in the local language (Uzbek). A list (names,

address and contact numbers) of the persons at PMU to be approached will be distributed

in case of a grievance. The comments and feedbacks from the disclosure meetings will be

incorporated for final DDR.

19. The DDR did not identify compensation and resettlement assistance requirements for

affected persons (APs) as there no APs. The DDR is based on the latest design, cadastral

document, architectural planning assignments (APA) land allocation acts prepared for two

sections (4 and 7) of the NWRTLP.

20. The UE understands that ADB will not finance the project if NWRTLP do not comply with

its safeguard policy statement, nor will it fund if the project doesn't abide byUzbekistan’s

social and environmental laws and regulations, including those laws implementing

Uzbekistan’s obligations under international law.

2.2 Methodology

21. Present due diligence assessment was conducted based on a desk review of available

materials, site visits and consultation with specialists, stakeholders.

22. The following materials have been reviewed:

· Draft Land Acquisition and Resettlement Plan (LARP) that was prepared by TA

Resettlement Expert within August 2014 – February 2015.

· InitialEnvironmental Examination (IEE) that was prepared by TA Environmental

Expert in July 2015

· Architectural Planning Assignments (APA) developed for “Khorezm” Substation

(Annex 2-3)

· Cadastral document of “Khorezm” Substation and Khrorazmelektrqishloqqurilish

(Annex 4)

· Architectural Planning Assignments (APA) prepared for “Sarimay” Switchyard

(Annex 5-6)

· Decision of Khazorasp district khokim as well as Khorezm regional khokim for

“Sarimay” Switchyard on land allocation (Annex 7)

· Land Allocation Act for Sarimay Switchyard (Annex 8)

23. This Resettlement Due Diligence Report (DDR) was prepared by Social Safeguards

Specialist in January 2019. Due diligence review was based on the final design developed

by the Design Institute – Sredazenergoset project within the 2016-2018 period.

Architectural Planning Assignment that allows starting modernization and expansion in

Khorezm Substation that was issued on 22 March 2016 was reissued until 31 December

2019. Architectural Planning Assignment for new construction of Sarimay Switchyard that

was issued on 20 January 2016 was reissued until 31 December 2019.

24. The detail due diligence assessment included a desk review of document containing a set

of town-planning and architectural requirements, special conditions for designing and

building an object arising from the provisions of approved city-planning documentation,

relevant decisions of state authorities, including requirements and conditions for the

protection of historical and cultural monuments, the environment, legal rights and interests

of third parties.

Page 12: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

11

25. Cadastral information containing technical, economic and legal characteristics of the land

plot, information about the owners of the land plots also studied from cadastral documents

for Khorezm substation and Khorazmelektrqishloqqurilish.

2.3 Impact on Indigenous People

26. The population of Khorezm is ethnically Uzbeks, and there are no indigenous minority

groups or sub-groups in the Khorasp and other districts who would be affected by the

project. Initial Poverty and Social Analysis prepared for this project also categorized as

“C” for Indigenous Peoples. Given this, it is evident that there is no impact on the

indigenous people from the proposed subsections of the project.

3. DUE DILIGENCE ON LAND ACQUISITION AND RESETTLEMENT

3.1 Possible Land Acquisition and Resettlement Impacts

27. The DDR document review indicates that the project will have neither permanent nor

temporary impact on households, farmers and business entities.

28. According to Draft LARP that was prepared in 2015, the project is classified as category B

for the Involuntary resettlement under ADB’s Safeguard Policy Statement (2009), however

the Plan indicated that the lands would be allocated out of the State Reserve Land for

construction of Sarimay Switchyard and the land for Khorezm SS will be expanded out of

the available lands without triggering any involuntary resettlement and land acquisition

from affected households. After the division of the NWRTLP into sections, it is identified

that not all the parts of the project include involuntary resettlement, notably the

substations/switchyards

29. Based on existing ADB Social Safeguard Policy (2009) and due diligence review

theSection-4: “Khorezm” Substation and Section-7: “Sarimay” Switchyard fall under ADB’s

project Category ‘C.’ The category ‘C’ is defined as: “A proposed project has no

involuntary resettlement impacts. No further action is required.”

3.2 Khorezm Substation

30. The Khorezm substation became operational in 1969. The substation has been in

operation for 45 years. Types of taken out of production equipment of all range of voltages

suggest its technical unsuitability and necessity of its replacement with modern ones.

Growing 30 number of connections made the original wiring scheme of 220 kV open

switchyard unsuitable and requires its reconfiguration.

31. Khorezm Substation is located in Urganch city of Khorezm region. As of cadastral

documents, the substation is located at the address Hanka street 96, Urganch city. The

geographic coordinates are given in WGS-84 as Latitude: 41°31'39.18"N, Longitude:

60°39'59.57"E.

32. North West Main Power Network uses the land for substation with permanent possession

rights. The total size of the substation is 64196.5 sqm. Additionally, 0.7 ha land will be

allocated for the expansion of current boundaries of the substation. Modernization of

substation includes to renew transformers and carry out modernization works. All

construction works will be carried out within the territory of Khorezm SS. Additionally 0.7

Page 13: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

12

ha of land was allocated as of preliminary design and architectural planning assignment

out of the area of Khorazmelektrqishloqqurilish. The allotted land is used for orchard by

Khorazmelektrqishloqqurilish. This organization is one of the regional branches of

Uzbekenergo specialized in the construction of power lines and towers in the rural areas

of Uzbekistan.

Figure 2: Cadastral boundary of Khorezm SS and expanded land

33. Expansion works include moving a fence and access road (within the territory of SS),

construction of five new bays and replacement of two old transformers. The current SS

also has 120 units of batteries which will be changed during modernization. There will be

no negative social impacts, but environmental effects are observed such as noise, dust

and air pollutant emissions from the construction equipment. Minor spills and leakages

may occur from vehicles and machinery and transformers when they are replaced. The

mitigation measures are described in detail in the InitialEnvironmental Examination (IEE)

report prepared for this project.

34. A resettlement screening for subsections was done in January 2019 by Social Safeguards

consultant. A draft Due Diligence Report can conclude that Section-4: “Khorezm”

Substation does not affect any households, farmers nor business entities. Based on

cadastral documents of Khorezm Substation and Khorezmqishloqqurilish, it has been

identified that land in the size of 0.7 ha for the expansion of Khorezm Substation is

allocated from Khorezmelektrqishloqqirilish. These two organizations are under the State

ownership and operated by Uzbekenergo. The cadastral documents show evidence

regarding the ownership status of the Khorezm SS to land. Cadastral document is

attached to this report. Also, Architectural Planning Assignment given by local

Architectural Department approves that there is no involuntary resettlement and land is

being allocated out of the territories of the organizations which belongs to the

Uzbekenergo.

Page 14: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

13

35. Socio-economic assessment that was done for the draft LARP in 2015 revealed that

majority (69%) of surveyed households expressed their strong interest in new TL

construction project. The average age of surveyed HHs heads is 50 years old and most of

the heads are married male persons. Thirty nine percent of surveyed persons are involved

in agricultural related activities, 31% are studying or young members of the family.

Housekeeping and/or seasonal workers are 12.5%. Governmental services occupation

related persons are 10.5%. Retired APs is 3%. In terms of ethnic composition according

to socio economic survey data in Khorezm all surveyed households are Uzbeks.

36. The pictures below give some idea about Khorezm SS sites where modernization works

will be carried out under the project.

Figure 3: Existing land for construction of new

Transformers

Figure 4: Allocated land in the size of 0.7 ha

3.3 Sarimay Switchyard

37. The construction site of switchyard at Sarimay situated to the North-East of Nukus

settlement on the opposite side of A-380 road. In draft LARP this switchyard was named

as Ellikqala, later EA decided is to rename it as Sarimay. This site is a relatively plain

surface compound of fine-grained sand which will significantly reduce the volume of

grading and leveling works during SS construction. Potential environmental impacts are

similar to the Khorezm substation sites even though the scale of construction activities is

bigger at Sarimay.

Page 15: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

14

Figure 5: Location of selected land plot for Sarimay Switchyard

38. To construct a new 500/220 kV Sarymay switchyard the land in the size of 22 hectares

was allocated from Sarimay village, Nukus makhalla of Khazorasp district of Khorezm

Region. The geographic coordinates are in WGS-84 as Latitude: 4105’54.50’’N,

Longitude: 61058’20.00’’E

39. According to the land allocation act documents the land is under rangeland category and

under the State Reserve Land which belongs to Khazorasp district hokimiyat.

40. The distance to Nukus settlement is around 700 meters and this settlement will not be

impacted due to the construction of a new switchyard. There is also existing natural

access road that will be used during the construction works. The neighboring lands of

allocated land are also under the category of rangelands which is under the State

Reserve Land.

41. Socio-economic assessment that was done for the draft LARP in 2015 revealed that

majority (69%) of surveyed households expressed their strong interest in new TL

construction project. The average age of surveyed HHs heads is 50 years old and most of

the heads are married male persons. Thirty nine percent of surveyed persons are involved

in agricultural related activities, 31% are studying or young members of the family.

Housekeeping and/or seasonal workers are 12.5%. Governmental services occupation

related persons are 10.5%. Retired APs is 3%. In terms of ethnic composition according

to socio economic survey data in Khorezm all surveyed households are Uzbeks.

42. A resettlement screening was done in January 2019 by Social Safeguards consultant. A

draft Due Diligence Report for Section-7: “Sarimay” Switchyard can be done since there

are no affected households, farmers nor business entities. Land in the size of 22 ha is

allocated from the State Reserve land. The land allocation act and architectural Planning

Page 16: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

15

Assignment given by local Architectural Department approves that there is no involuntary

resettlement and property is being allocated out of the State Reserve land.

43. DDR identified no impacts regarding involuntary land acquisition from households due to

the new construction of Sarimay Switchyard. According to the Land allocation act and

APA that were provided to Consultant and based on site visit, there are no households,

farmers, businesses are identifiedregarding involuntary resettlement and no land is being

acquired that may trigger ADB’s SPS 2009 Safeguard Requirements 2 regarding

Involuntary Resettlement.

44. The pictures below give some idea about Sarimay switchyard site where new construction

works will be carried out under the project.

Figure 6: View of the allocated land for Sarimay Switchyard

3.4 Impact of Construction to Access Roads

45. Road and rail access to the site for construction equipment, construction materials, and

power station equipment already will be used during the implementation of the project.

46. Reconstruction and expansion of Khorezm substation 220/110 kV and construction of

Sarimay Switchyard will not require an additional access road to the site. Access to land

will be through an already functioning path. The buffer zone for the switchyard and

substation will be within the available land parcels

3.5 Socio-economic Impacts

47. There will be no negative social impacts, but environmental impacts are observed such as

noise, dust and air pollutant emissions from the construction equipment. Minor spills and

leakages may occur from vehicles and machinery and transformers during the

replacement works. The mitigation measures are described in detail in the Initial

Environmental Examination.

48. Construction of substations will generate possibilities of local employment as some

laborers will be required during the project implementation. Uzbek companies will do all

construction activities. The exact number of domestic workers will be decided by the

Contractor who will be responsible for the project implementation. The forced and child

labor is strictly prohibited in ADB financed projects. Overall, the implementation of the

project has a positive impact on national and local socioeconomics.

Page 17: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

16

4. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION

4.1 General

49. Consultation meetings were carried out with relevant stakeholders, including cadastral

office, land use engineer, design engineers, transmission line operators of the project. List

of the stakeholders and discussed questions is attached in Annex 9. Social Safeguards

Specialist undertook the field visit on 16-19.01.2019.

50. The consultation focused on avoidance of impacts on households, farmers, business

community buildings and lands as well as temporary disruption of livelihood, if any, from

the proposed construction, works. Grievance Redress Mechanism will be explained in

local language (Uzbek) along with a list (names, address and contact numbers) of crucial

persons at PMU to be contacted in case of people living near to project area may have

grievance/complaint. The consultation will be carried out together with LARP update

public consultations. People living near Khorezm and Sarimay SS will be invited to these

meetings.

51. The main objectives of the public consultations are as follows:

· to make people aware of the project and let the beneficiaries know about the

positive outcome of the project regarding reliable new employment opportunities,

power supply

· to disseminate information to the people about the project regarding its activities

and scope of work

· to involve people as stakeholders in project planning and further during

implementation

· to seek local peoples' views on minimizing probable adverse impacts on land

acquisition, involuntary resettlement and indirect impact to livelihood

· to make people aware of the plan of action

· to make people aware of the process of Grievance Redress Mechanism

· to assess the local people's willingness to get involved with the project, and

enumerate the measures to be taken during the implementation of the project

· to make people aware of the general policy principles of national laws and ADB

Safeguard Policy Statement, 2009 and full eligibility and entitlements.

4.2 Disclosure

52. Disclosure of DDR will be done in Urganch city for people living near to Khorezm

substation and in Nukus settlement for people living nesr to Sarimay switchyard. In this

meetings, a Project objectives, ADB’s policy on Involuntary resettlement, and Grievance

Redress Mechanism will be described in the local language (Uzbek).A list (names,

address and contact numbers) of the persons at PMU to be approached will be distributed

in case of a grievance. The comments and feedbacks from the disclosure meetings will be

incorporated for final DDR.

53. The project information will be disseminated through disclosure of the Resettlement Due

Diligence Report (DDR) on ADB’s (in the English Language) and in the UE websites (in

English, and Uzbek language) upon approval.

Page 18: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

17

5. GRIEVANCE REDRESS MECHANISM

5.1 General

54. Consultation meetings were carried out with relevant stakeholders, including cadastral

office, land use engineer, design engineers, transmission line operators of the project. As

a result of discussions and consultations, a simple Grievance Redress Mechanism (GRM)

is developed for the people living near to substations that may have complaint or

questions during the construction works.

55. The PMU of the UE will establish a simple and accessible grievance redress mechanism

which shall ensure some instruments and levels for grievance resolution and appeals

process. PMU’s Safeguards Specialist through PMU representative on site will be

responsible for the project implementation and GRM.

56. The primary goals of GRM are ensuring the receipt and timely redress of grievances and

concerns submitted by the aggrieved project affected persons and resolve complaints at

the project level and prevent escalation to the national courts or ADB Accountability

Mechanism.

57. People will have the right to file complaints and queries on any aspect of land acquisition,

compensation and resettlement. The PMU will ensure that grievances and complaints on

any point of the project implementation during the construction works are addressed in a

timely and satisfactory manner.

58. The National law on the appeals of individuals and legal entities1 obliges state authorities

to deal with requests and provides a clear framework to handle the case. This law has

recently replaced previous Law on the requests of citizens and gives the right for

individuals and legal entities to file requests. The requests can be in the form of

applications, proposals and complaints and submitted in three ways: oral, written and

digital format.

59. The Grievance Redress Mechanism (GRM) can also be established through mobile-

based and web-based applications that are common nowadays in Uzbekistan. GRM can

be established through a particular group in Telegram or on Facebook. The State’s Public

Reception (Halq Qabulhonasi) also is playing a vital role to address grievances and

concerns of the population. People may raise their questions also viaweb-based Single

Portal (The Single interactive state services portal). The Single portal is designed to

facilitate and empower people to access online public services by using modern

information technology and connected with the portal called E-Government. Additionally,

web-based President’s portal is also commonly used to address any complaints or

concerns of the population.

60. The Grievance Redress Mechanism (GRM) developed for this subprojects will be

available to people living or working in the nearby areas. The Project GRM will be

disseminated via the DDR disclosure meetings in the leaflets that will be distributed to

people through local khokimiyat, the makhalla, village assembly of citizens or farmers

councils. In case there will be any person impacted by or concerned about the project

activities he/she has the right to participate in the GRM. They should have the easy

access to it and be encouraged to use it. The proposed GRM does not replace the known

1Republic of Uzbekistan Law on the appeals of individuals and legal entities (№ЗРУ-378, 03.12.2014).

Page 19: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

18

mechanisms of complaint and conflict resolution envisaged by the legal system of the

Uzbekistan but attempts to minimize the use of it to the extent possible.

61. The PMU of the EA will establish a simple and accessible GRM. The GRM provides some

avenues and levels for grievance resolution and appeals process. The primary objective

behind project specific grievance mechanism is to ensure a timely and user-friendly

solution to the complaints received from the people living near to subproiects. However,

the Project GRM does not prevent any person to approach the governmental legal system

to resolve their claims at any stage of the grievance redress process. The people can

address their complaints to the courts at any time and not only after using the GRM.

62. Level 1 (Makhalla / Village Assembly). Under this project grievance redress mechanism,

complaints can be submitted to the district level khokimmiyat, makhalla, village assembly

of citizens, farmer councils, Contractor or directly to NWMPN. The makhalla/village

assembly and Site Engineer of NWMPN will try to resolve or clarify the issue within 15

days. Unresolved issues will be referred to the PMU in Tashkent.

63. Level 2 (Project Management Unit). The UE through its PMU on a regular basis (weekly)

and as per immediate request will check with the NWMPN whether any complaint is

received by Site engineer. The PMU, on receipt of a complaint from NWMPN or any other

local bodies, will immediately take the following actions:

(i) will inform the complainant within five days

(ii) inform ADB office both resident mission and HQ

(iii) if required, establish complaint handling a team (Level 3) with members Head of

PMU, representatives from the EA, District Khokimiyat, Land Resources and

Cadastral Department, and Makhalla or Village Assembly of Citizens or/and

Farmer’s Councils, or/and Women Association.

64. Level 3 The complaint handling team will be headed by one of the EA management staff

designated for handling grievances of the project.

(i) The team will consult the complainant and gather complainant’s concerns.

(ii) The team will also take advise from independent valuation company (in case of

grievances related to valuation).

(iii) All complaints will be resolved in 15 days, and in case additional details are

required, a maximum of 30 days will be used to address and close the complaint.

(iv) If the complaint is not addressed by Project Grievance Mechanism Team, the PMU

will inform ADB and District khokimiyat regarding the issue and district or provincial

khokimiyat will also have 15 calendar days to resolve the complain

65. Level 4 (Court). If the complaint is still unresolved, the complainant can submit his/her

complaint to the appropriate court of law. The schematic explanation of GRM is given

Annex 10.

5.2 Contact Details

66. The PMU will be responsible for recording the complaint; the step was taken to address

the grievance, a minute of the meetings, and preparation of a report for each complaint.

The complaint handling process will be reported to ADB through the quarterly project

Page 20: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

19

implementation report. Citizens may address their complaint and concerns to the following

address:

6, Istiqlol street, Tashkent, 100000, Uzbekistan

Tel/fax.: +998 71 2362700

E-mail: [email protected]

Mr. Azizbek Batirov - Safeguards Specialist

67. The aggrieved persons can also use the ADB Accountability Mechanism (AM) through the

direct citizens’ application to the Head Quarter in Manila, particularly to Complaints

Receiving Officer, Accountability Mechanism Asian Development Bank Headquarters6

ADB Avenue, Mandaluyong City 1550, Philippines Email: [email protected], Fax +63-2-

636-2086.

68. AM is the last resort and ADB has its availability as a recourse in case other mechanisms

for dealing with harmful project effects are not successful. SPS requires GRM and the use

of project level GRM should be encouraged first.

5.3 GRM Records and Documentation

69. The UE and its Project Management Unit will keep a record of complaints received for its

use as well as for review by ADB during regular missions. The grievance mechanism

applies equally to all affected households and for population living near to subrjects.

When reference is made to the makhalla, it is to the makhalla that the affected persons

are located. The PMU will be responsible for recording the complaint; the step was taken

to address a grievance, minutes of the meetings and preparation of a report for each

grievance. The complaint handling process will be reported to ADB through project

progress reports. All grievances received from the population will be registered in a log

book (Annex 11 attached in this DDR) which should be available at levels 1 and 2: at the

site office of the Contractor, each mahalla committee of subproject area districts and PMU

Tashkent office. Besides, there are also logbooks in the Hokimiyats where the grievances

of the population are usually registered. Even so, the information on received by

Contractor grievances and applications from the aggregated persons, and undertook

measures should be submitted to the representatives of PMU on the project site for the

accounting all grievances. Thereafter the information on all received grievances will be

collected at the PMU.

6. POLICY AND LEGAL FRAMEWORK

6.1 General

70. The legal and policy framework of the project is based on national laws and legislation

related to land acquisition and compensation policy in Uzbekistan and ADB Safeguard

Policy Statement 2009 (SPS). Project related LAR principles have been adopted by this

Report based on the analysis of applicable laws and policies and ADB’s Policy

requirement; In the subsections included in this report, there is no Involuntary

resettlement nor land acquisition from affected households. However, the policies below

are to be applied in case any LAR related impacts are identified during the

implementation.

Page 21: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

20

6.2 Laws, Regulation, and Provision relating to LAR in Uzbekistan

71. In Uzbekistan, a land expropriation takes place for the public needs under the Land Code

(LC). The expropriation in this context refers to the taking away of private land for a public

purpose by the government with or without the owner’s consent subject to laws of eminent

domain, which stipulates prompt and adequate compensation. In Uzbekistan, there is no

separate legal document about Land acquisition and Resettlement but supported by

different Resolutions, Acts and Codes. In the table below the summary of a legal

framework which is related to resettlement is given.

Table 5.1: Legal instruments applicable to Land acquisition and resettlement and

categorization of vulnerable groups

Legal Framework Functional Relationship to Resettlement

Land acquisition and resettlement

The Land Code (LC) dated on 30 April 1998 Describes a condition for permanent landexpropriation and temporary land acquisition

The resolution of Cabinet of Ministers (CoM)“On Approval of the procedure of damages tocitizens and legal persons in connection withthe withdrawal of land plots for state andpublic needs” dated on 29 May 2006 #97

Regulates resettlement compensations foraffected buildings, structures, and plantingsin the settlements.

Civil Code (CC) dated on 29 August 1996 Regulates general rules of property seizure,determination of property cost and rights forcompensation, terms of rights termination

The resolution of CoM “On measures toimprove the procedure for granting land plotsfor urban development activities and othernon-agricultural purposes” dated on 25 May2011 #146

Regulates resettlement compensations forthe profit loss, the value of agricultural lossbelonging to landowners, users, tenants incase of land acquisition.Also,it regulates theprovision of land to land compensation incase of agricultural and forest relates losses.

The resolution of CoM “On amending andadding to some decrees of the Republic ofUzbekistan, aimed the further improvementof registration of cadastral document on areal property” dated on 21 September 2016 #317

It defines the procedure of registration oftitled and non-titled land users and realproperty owners. It also establishes theprocess and payment method forcompensation in case of land acquisition.

Presidential resolution “On measures toimprove the effectiveness of training andrealizing projects with participation ofinternational financial institutions and foreigngovernment financial organizations” dated on16 July 2018 #3857

Confirms that the resettlement costs are paidbased on assessment documents preparedby IFI by their methodology.

Presidential Decree “On measures on majorimprovement of investment climate in theRepublic of Uzbekistan" dated on 1 August2018 #5495

Defines that land expropriation can beimplemented only after meaningfulconsultation with PAPs.

Presidential Decree “On measures toimprove the system of protection of rightsand legal interests of subjects ofentrepreneurship” dated 27 July 2018 # 5490

It defines the source of Resettlement budgetin the investment projects.

Implementation of Land acquisition and resettlement

Presidential Decree “On measures on majorimprovement of investment climate in theRepublic of Uzbekistan" dated on 1 August

Defines that land expropriation can beimplemented only after meaningfulconsultation with PAPs. The resolution

Page 22: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

21

Legal Framework Functional Relationship to Resettlement

Land acquisition and resettlement

2018 #5495 prohibits a land confiscation without theconsent of the Republican Centralized Fund.

The resolution of CoM “On the procedure forthe formation and use of funds of centralizedfunds for the compensation to affectedindividuals and legal entities for theexpropriation of land for the state or publicneeds” dated 26 December 2018 # 1047

It defines the source of compensationpayments based on the type of projects.Establishes Republican Centralized Fund(RCF) as the main body which is responsiblefor the compensation payments to AHs. TheSupervisory Board of RCF decides on theallocation of funds for compensation.

Presidential Decree on Additional measuresfor social support of citizens andimplementation of a latest public campaignon recognition of ownership rights to illegallybuilt residential structures dated on 20 April2018 # PF 5421

Residents of Uzbekistan are allowed tolegalize ownership rights to theirunregistered and non-titled residentialstructures until 1st May 2019. The Decreedefines the conditions for legalization.

Categorization of vulnerable groups

The resolution of CoM “On approval of theorder of the appointment and payment ofsocial allowances and material (financial)assistance to low-income families” dated on15 February 2013 #44.

Regulates the mechanism to thedetermination of vulnerable groups and theirentitlements

Tax Code of Uzbekistan Regulates compensation for a vulnerablegroup of people regarding applying fordiscounts or exemption from property taxes,land tax, income tax, and other taxes

Labor code and Law on employment Regulates labor relations of individualsemployed with labor contract by enterprises,institutions, organizations of all typeownership forms, including contracted byindividuals.

6.2.1 Constitution

72. The Constitution of the Republic of Uzbekistan (December 8, 1992) provides that:

· Everyone shall have the right to own property (Article 36). The economy of

Uzbekistan, evolving towards market relations, is based on various forms of

ownership. The state shall guarantee freedom of economic activity,

entrepreneurship and labor with due regard for the priority of consumers’ rights,

equality and legal protection of all forms of ownership (Article 53).

· An owner, at his discretion, shall possess, use and dispose of his property. The

use of any property must not be harmful to the ecological environment nor shall it

infringe on the rights and legally protected interests of citizens, juridical entities and

the state (Article 54).

· The land, its minerals, waters, fauna and flora, other natural resources shall

constitute the national wealth and shall be rationally used and protected by the

state (Article 55).

6.2.2 Land Code (30 April 1998)

73. The Land Code (LC) is the primary regulatory framework for land-related matters in

Uzbekistan. The LC regulates allocation, transfer, and sale of land plots, defines

Page 23: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

22

ownership and rights on the land. It describes responsibilities of different state authorities

(Cabinet of Ministers, province, district, city Hokimiyat) in land management; rights and

obligations of the land possessor, user, tenant, and owner; land category types, land

acquisition, and compensation, resolution of land disputes and land protection. The LC

also defines the terms of rights termination on land plot, seizure and land acquisition of

land plot for state and public needs, and conditions of confiscation of land plot in violation

of land legislation.

74. According to the new version of the Code, currently, the granted lands for construction of

infrastructure, business and residential houses shall be carried out within the three years.

After that land can be taken back by local municipalities.

6.2.3 Resolution of Cabinet of Ministers № 97 (29 May 2006)

75. This resolution regulates compensation for losses to individuals and legal entities due to

the seizure of land plots for state and public needs. This regulation is mainly dealing with

land plots, houses, building and structures of individuals and legal entities.

76. The resolution determines the procedure for seizure of land or part thereof, as well as the

method for calculating the amount of compensation to individuals and legal entities for the

demolished residential, industrial and other buildings, structures and plantings in due to

the seizure of land for state and public needs. The details of the Resolution is given in the

draft LARP prepared for this project.

6.2.4 Civil Code (29 August 1996)

77. The Civil Code (CC) defines the legal status of participants of public relations, the

grounds, and procedure of implementation of property rights and other proprietary rights,

rights ofintellectual property, regulates the contractual and other obligations, as well as

other property and related personal non-property relations. The CC defines general rules

of property seizure, determination of property cost and rights for compensation, terms of

rights termination.

78. The CC provides that: a person whose right has been violated may demand full

compensation for damages unless the law or the contract provides compensation for

losses in a smaller size (Article 14, Clause 1). The Civil Code (Article 14, Clause 2) also

specifies that losses are understood as:

· expenses that the person whose right is violated, made or must make to restore

the violated right

· the loss of or damage to property

· the revenues that this person would have received under normal conditions of civil

turnover if his right had not been violated (lost profits).

79. According to article 14, Clause 3 “If the person has violated the law, revenues received as

a result of this, the person whose rights were violated, has the right to demand

compensation along with other losses, lost profits in the amount not less than such

profits.”

80. According to article 7 “If an international treaty or agreement stipulates other rules than

those stipulated by civil legislation, rules of the international treaty or agreement.” This

rule is a standard rule for all of Uzbekistan’s laws.

Page 24: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

23

81. According to Article 8, Clause 3, the rights to the property which is subject to state

registration shall arise upon the record of the relevant rights to it, unless otherwise

provided by law. Article 84, Clause 1 provides that the right of ownership and other real

property rights, creation, transfer, restriction, and termination of these rights are subject to

state registration. This means that without registration the right to real estate property

does not enter into the force. This statement is significant for the further understanding of

LAR processes related to land acquisition and building’s demolition.

6.2.5 Resolution of Cabinet of Ministers № 146 (25 May 2011)

82. This Resolution is aimed to improve the procedure of granting land plots, protect the rights

of legal entities and individuals on land, improve the architecture of settlements and the

efficient use of their land for construction by the Land Code and the Town Planning Code.

This resolution has approved two Regulations: (i) Regulation on the procedure for

granting land for urban development and other non-agricultural purposes, (ii) Regulation

on the method of compensation for land possessors, users, tenants, and owners, as well

as losses of agriculture and forestry. The Regulation on the procedure for granting land

for urban development and other non-agricultural purposes contains the following

provisions:

· order of land plot location, preparation and approval of site selection and land

allocation documents without approved planning documentation

· order of placement, selection and land allocation with approved planning

documentation

· order for rejection in the land allocation and selection for construction

· provision (sale) of land plots for individual housing construction

· elements of urban planning documents and development regulation lines.

83. The Regulation on the procedure of compensation for possessors, users, tenants, and

landowners, as well as losses of agriculture and forestry, includes the following:

· compensation for losses of owners, users, tenants, and landowners

· compensation for losses of agriculture and forestry

· cost of irrigation and developing the equal new land plot in return for seized

irrigated agricultural land

· cost of fundamental improvement of grassland and pasture

· scheme for determination of losses of land possessors, users, tenants, and

owners, as well as damages of agriculture and forestry

· coefficients on the location of seized land plots.

84. The losses of land possessors, users, tenants, and owners, as well as losses in

agriculture and forestry, should be compensated before granting of documents certifying

rights on land plot. The regulation also orders that demolition of the house or building shall

be done only after agreeing on compensation and providing replacement premises. The

regulation orders that compensation has to be paid before starting any construction work.

The land possessors, users, tenants and owners, whose land plots are seized and to

whom land plots are granted, in case of disagreement with a defined amount of losses,

can appeal to the court. In case of acquisition and temporary occupation of land plot or

part thereof, the following would be subject to compensation:

Page 25: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

24

· cost of the land plot owned by individuals and legal entities

· Value of residential houses, constructions, and installations, including incomplete

buildings, and also located outside of the allocated plot, if its further utilization is

impossible due to seizing of the land plot

· cost of fruits and berries, protection and other perennial plants

· cost of incomplete agricultural production

· lost profit.

85. Above described Laws and Regulations mention that non-titled and squatters on land and

building/structures are ineligible for any compensation.

86. Collectively, these regulations provide a sound basis for acquiring land for public

purposes and for compensating land users according to the registered user of the affected

land in Uzbekistan.

87. This resolution shall be implemented together with the Resolution of Cabinet of Ministers

#317 dated on 21 September 2016.

6.2.6 Resolution of Cabinet Ministers №317 (21 September 2016)

88. The resolution “On amending and adding to some decrees of the Republic of Uzbekistan,

aimed the further improvement of registration of cadastral document on real property”

defines responsible design institution which calculates the agricultural and forest-related

losses belonging to legal land users, tenants. This institute is “Uzdavyerloyiha” and its

branches in the regions. It defines that in case of the following type of construction works,

then compensation for agricultural and forest-related losses will not be compensated:

· construction of individual housing and maintenance of a residential house

· construction of pre-school, general secondary, secondary special, professional

educational and medical institutions

· construction of water management facilities, land reclamation facilities and

hydraulic structures

· formation of protected natural areas.

89. By this resolution, the Government defined the procedure of legalization cadastral

document of titled and not titled (illegal) land users. The main requirements for the

legalization of non-titled land users are to provide i) explanation of circumstances of

unlawful use of land, ii) certificate from local self-governed bodies on possession of last

15 years, iii) payment of land tax for the previousfive years. This resolution updates

compensation mechanism of agricultural and forest-related losses. Therefore, in the

calculation of compensation, this resolution shall be used together with Resolution of

Cabinet of Ministers #146 dated on 25 May 2011.

6.2.7 Resolution of Cabinet Ministers №3857 (16 July 2018)

90. The resolution “On measures to improve the effectiveness of training and realizing

projects with participation of international financial institutions and foreign government

financial organizations” partly provides that payment of compensation for the land

acquisition, demolition of houses, structures, plantings within the framework of projects

with the participation of International Financial Institutions (IFIs). If it is agreed and stated

in agreements, then project implementation procedure will be followed by authorized

bodies following the requirements of IFIs or Foreign Governmental Finance Organizations

(FGFOs). This resolution gives to Executing Agencies to implement ADB’s LAR or other

principles in case of discrepancies between national legislation and ADB policies.

Page 26: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

25

6.2.8 Decree of the President of the Republic of Uzbekistan №5495 (1 August 2018)

91. Decree “On measures on cardinal improvement of investment climate in the Republic of

Uzbekistan" regulates that the seizure of land for state and public needs is allowed only

after an open discussion with interested parties whose land plots are confiscated. It also

sets that demolition of residential, industrial premises, other structures, and structures

belonging to individuals and legal entities and seizure of land is allowed after the full

compensation of the market value of immovable property and losses caused to owners in

connection with such seizure.

6.2.9 Resolution of Cabinet of Ministers № 1047 (26 December 2018)

92. This full name of the resolutionis called as “On the procedure for the formation and use of

funds of centralized funds for the compensation to affected individuals and legal entities

for the expropriation of land for the state and public needs.” This resolution appoints

Republican Centralized Fund (RCF) under the Cabinet of Ministers for calculation and

distribution of compensation during the involuntary resettlements to affected households

and affected entities. Involuntary resettlement can be done only for public and the state

needs. RCF will be responsible for the Governmental level and internationally funded

projects. This resolution sets the procedure of compensation payments to affected

physical and legal entities. The Supervisory Board under RCF has the right to decide and

the decisions are compulsory to execute. The Board will also monitor the allocation of

funds to AHs during the resettlement implementation period. Local managing bodies

(khokimiyats) should start the process by inquiring to RCF on the distribution of necessary

funds for LAR. The Board will review this application and the appropriate decisions will be

accepted. Regional khokimiyats issue the Decree on the allocation of compensation

based on the RCF’s decision. The Decree serves as a legal instrument to provide

compensation to affected physical and legal entities.

6.2.10 Presidential Decree 5421 (20 April 2018)

93. Decree announced a one-time nationwide campaign for recognition of the ownership

rights to the residential premises that were builtillegally or built without proper

documentation. The campaign will last until May 1, 2019.

94. To be eligible for the campaign and legalize ownership right to anillegally built or without a

building permit structure following conditions shall be fulfilled:

· The building should be built before the adoption of this Decree.

· A land plot or part of the land plot is not located on land which cannot be realized

for housing purposes. These lands include the safety zones, protected areas,

military zones.

· Shall meet requirements of urban-planning norms and rules, as well as its

possession will not violate the rights and legally protected interests of other

persons or pose a threat to the lives and health of citizens.

· Specific cases in which the non-titled buildings cannot be recognized by the

Cabinet of Ministers of the Republic of Uzbekistan.

95. Recognition of the non-titled rights to buildings is carried out by the decision of the khokim

of the district (city) on the recommendation of the Commission after paying a one-time fee

in the amount of five times minimum wages.

Page 27: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

26

96. After legalization, the owner is granteda lifelong inheritable possession right to the land

plot (part of the plot) on which the building was erected. The size of the legalized land

shall not exceed the limits established by law. The legalization will be carried out without

imposing a fine to the owner that was foreseen by Article 121 of the Tax Code of the

Republic of Uzbekistan (see 5.2.12 Tax code).

6.2.11 Resolution of Cabinet of Ministers № 44 (15 February 2013)

97. This resolution determines the procedure for the appointment and payment of Makhalla

allowances for a) low-income families with children under the age of 14 years, b)

allowances for low-income parents for child care until the age of two years and c)

allowance for low-income families. According to this resolution the following types of

families are entitled to benefits:

· families where the average monthly income does not exceed 1.5 minimal wages

per person during the last three months. Along with incomes household members

gain officially, additional factors are also to be considered by makhalla committee

members, including the availability of land, employment status of family members,

and presence of persons in need of care

· the preferential rights for makhalla allowances have families who have lost both

parents and children involved in family education

· families where one or both parents are disabled children

· widow(er), raising two or more children under the age of 14, living separately from

other relatives

· family with disabled children

· mothers or fathers who are bringing up the children in a single-parent family. In this

case the fact of child rearing mother (father) in an incomplete family established by

makhalla

· families in which one or both parents are unemployed who have been registered at

state employment bodies (regional and city departments of the Ministry of

Employment and Labor Relations) as job-seekers

· single retired persons.

98. The amount of allowances is determined by the Ministry of Finance of the Republic of

Uzbekistan according to calculations submitted by the People’s Bank. According to the

interpretation of this Resolution by the Ministry of Finance2, the amount of financial

assistance can be from 1.5 times uptothree times of minimum wage. The maximum

duration of giving allowance is uptosix months. Therefore, in this project setting an

allowance in the amount of 3 times of minimum wage for vulnerable groups fits the

National legislation of Uzbekistan. In translating this document into local language, the

term, an allowance shall be interpreted as moddiy yordam (in the Uzbek language) to

avoid misunderstandings during the implementation stage.

6.2.12 Tax Code

99. The Tax Code (TC) is a regulatory framework for taxation related matters of individuals

and legal entities. This law regulates compensation for a vulnerable group of people

regardingapplying for discounts or exemption from property taxes, income tax and other

taxes stipulated in this TC.

2https://www.mf.uz/uz/news/2615.html

Page 28: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

27

100. By the article 121, the use of entire land plot or expanding the territory without

documents or illegally is subject for sanctions in the amount equivalent to:

· four times of land taxes for legal entities

· three times of land taxes for physical bodies

101. According to the Presidential Decree 5421, this fine is not applied during the

campaign period till 1stMay 2019.

6.2.13 Labor Code and Employment Law

102. These two documents are centrallegislation regulating labor relations of individuals

employed with labor contract by enterprises, institutions, organizations of all type

ownership forms, including contracted by individuals. These legislations are considering

interests of employees and employers provide the efficient function of the labor market,

just and secure labor conditions, protection of labor rights and employees health, promote

the growth of labor productivity, an increase of work quality, raising on this matter welfare

and social livelihood level of the population.

103. Both ADB policy and the Uzbek law provide for the indemnification of APs who

lose a job because of land/assets acquisition under a public interest project. The two,

however, differ substantially on how the matter is conceptualized and resolved in practice.

ADB policy compounds the case as an income rehabilitation issue and thus requires that

the actual job income lost by the APs is fully reimbursed to them. This approach covers

temporary and permanent job losses and is generally implemented through an allowance

providing the APs their declared monthly salary (what should be substantiated by the

supporting documents) for the number of months of business stoppage up to a maximum

of 12 months which is the benchmark for permanent job loss. For informal permanent jobs

without declared salaries, the approach is the same but based on the national minimum

wage. To guarantee proper policy application the payment of the job loss allowances is to

be directly disbursed to the APs by the project proponent.

104. The national legislation, instead, limits the matter to the payment as mandated by

the Labor Code of fixed employment termination indemnities due by an employer to his

employees and to the obligation of the project proponent to reimburse the employer of the

cost of those indemnities mandate by the Civil Code. Such an approach excludes from job

loss compensation informal employees without a declared salary, applies only to

permanently affected jobs and does not automatically guarantee that the APs receive their

job termination dues3.

3Based on the Labor Code of 1996, last amended on 2015 (Art icle 67) loss of employment is to be compensated with 2 months average salary plus

a severance pay of a maximum of 1 month average salary depending on the length of the employment lost. Also according to the Civil Code

(Art icle 14) all losses (including real damage, lost profits) are to be compensated.

Page 29: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

28

6.3 ADB Safeguard Policy Statement, 2009

105. ADB adopted its Safeguard Policy Statement (SPS) in 2009 including safeguard

requirements for environment, involuntary resettlement, and indigenous people. The

objectives of the Involuntary Resettlement Safeguard policy are to avoid involuntary

resettlement wherever possible; to minimize involuntary resettlement by exploring project

and design alternatives; to enhance, or at least restore, the livelihoods of all displaced

persons in real terms relative to pre-project levels; and to improve the standards of living

of the displaced poor and other vulnerable groups.

106. The involuntary resettlement safeguards cover physical displacement (relocation,

loss of residential land, or loss of shelter) and economic displacement (loss of land,

assets, access to assets, income sources, or means of livelihoods) as a result of (i)

involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to

legally designated parks and protected areas. It covers them whether such losses and

involuntary restrictions are full or partial, permanent or temporary. The three essential

elements of ADB’s SPS are: (i) compensation at replacement cost for lost assets,

livelihood, and income prior to displacement; (ii) assistance for relocation, including

provision of relocation sites with appropriate facilities and services; and (iii) assistance for

rehabilitation to achieve at least the same level of well-being with the project as without it.

The SPS gives special attention to poor and vulnerable households to ensure their

improved well-being as a result of project interventions.

107. The rate of compensation for acquired housing, land and other assets will be

calculated at full replacement costs. The calculation of full replacement cost will be based

on the following elements: (i) fair market value; (ii) transaction costs; (iii) interest accrued,

(iv) transitional and restoration costs; and (v) other applicable payments if any. Where

market conditions are absent or in a formative stage, the borrower/client will consult with

the displaced persons and host populations to obtain adequate information about recent

land transactions, land value by types, land titles, land use, cropping patterns and crop

production, availability of land in the project area and district, and other related

information. The borrower/client will also collect baseline data on housing, house types,

and construction materials. Qualified and experienced experts will undertake the valuation

of acquired assets. In applying this method of valuation, depreciation of structures and

assets should not be taken into account. The following are the basic policy principles of

ADB’s SPS, 2009:

(i) Screen the project early on to identify past, present, and future involuntary

resettlement impacts and risks.

(ii) Determine the scope of resettlement planning through a survey and census of

displaced persons, including gender analysis, specifically related to resettlement

impacts and risks.

(iii) Carry out meaningful consultations with affected persons, host communities, and

concerned non-government organizations. Inform all displaced persons of their

entitlements and resettlement options. Ensure their participation in planning,

implementation, and monitoring and evaluation of resettlement programs. Pay

particular attention to the needs of vulnerable groups, especially those below the

poverty line, the landless, the elderly, women and children, and Indigenous

Peoples, and those without legal title to land, and ensure their participation in

consultations. Establish a grievance redress mechanism to receive and facilitate

resolution of the affected persons’ concerns. Support the social and cultural

Page 30: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

29

institutions of displaced persons and their host population. Where involuntary

resettlement impacts and risks are highly complex and sensitive, compensation

and resettlement decisions should be preceded by a social preparation phase.

(iv) Improve, or at least restore, the livelihoods of all displaced persons through (a)

land-based resettlement strategies when affected livelihoods are land-based

where possible or cash compensation at replacement value for land when the loss

of land does not undermine livelihoods, (b) prompt replacement of assets with

access to assets of equal or higher value, (c) immediate compensation at full

replacement cost for assets that cannot be restored, and (iv) additional revenues

and services through benefit sharing schemes where possible.

(v) Provide physically and economically displaced persons with needed assistance,

including the following: (a) if there is relocation, secured tenure to relocation land,

better housing at resettlement sites with comparable access to employment and

production opportunities, integration of resettled persons economically and socially

into their host communities, and extension of project benefits to host communities;

(b) transitional support and development assistance, such as land development,

credit facilities, training, or employment opportunities; and (c) civic infrastructure

and community services, as required.

(vi) Improve the standards of living of the displaced poor and other vulnerable groups,

including women, to at least national minimum standards. In rural areas provide

them with legal and affordable access to land and resources, and in urban areas

provide them with appropriate income sources and legal and affordable access to

adequate housing.

(vii) Develop procedures in a transparent, consistent, and equitable manner if land

acquisition is through a negotiated settlement to ensure that those people who

enter into negotiated settlements will maintain the same or better income and

livelihood status.

(viii) Ensure that displaced persons without titles to land or any recognizable legal rights

to land are eligible for resettlement assistance and compensation for loss of non-

land assets.

(ix) Prepare a resettlement plan elaborating on displaced persons’ entitlements, the

income and livelihood restoration strategy, institutional arrangements, monitoring

and reporting framework, budget, and time-bound implementation schedule.

(x) Disclose a draft resettlement plan, including documentation of the consultation

process promptly, before project appraisal, in an accessible place and a form and

language(s) understandable to affected persons and other stakeholders. Disclose

the final resettlement plan and its updates to affected persons and other

stakeholders.

(xi) Conceive and execute involuntary resettlement as part of a development project or

program. Include the full costs of resettlement in the presentation of project’s costs

and benefits. For a project with significant involuntary resettlement impacts,

consider implementing the involuntary resettlement component of the project as a

stand-alone operation.

(xii) Pay compensation and provide other resettlement entitlements before physical or

economic displacement. Implement the resettlement plan under close supervision

throughout project implementation.

(xiii) Monitor and assess resettlement outcomes, their impacts on the standards of living

of displaced persons, and whether the objectives of the resettlement plan have

been achieved by taking into account the baseline conditions and the results of

resettlement monitoring. Disclose monitoring reports.

Page 31: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

30

7. INSTITUTIONAL ARRANGEMENT

7.1 General

108. This section describes institutional arrangements for preparing, implementing, and

monitoring involuntary land acquisition and resettlement activities of the project including

a description of organizational procedures for delivering entitlements, implementation

process, including how resettlement preparation, approval, and implementation will be

linked to contract awards and the start of the project’s civil works.

7.2 UE and Project Management Unit

109. The Uzbekenergo will have overall responsibility for all aspects of the program.

The Project Management Unit (PMU) within Uzbekenergo will be responsible for the day

to day management of the Project including cross-agency coordination, and via the

Resettlement Expert (RE) for LARP implementation and monitoring the compensation and

disbursement.

110. The RE under PMU will be directly involved in all LAR related planning,

implementation, inter-agency coordination, monitoring and reporting. The RE will receive

support from the relevant project consultants and benefit from inputs from the Design

Institute (DI), district/city executive authority and land resources and cadaster department

as appropriate.

111. Northwest main power network (NWMPN) is one of five power networks of

Uzelektroset responsible for power transmission and maintenance of transmission lines

and substations in North – West region of Uzbekistan. The Uzelektroset is a central

organization of Uzbekenergo responsible for sustainable and regular service of power

consumers as well as maintenance of the grid in constant high technical operation. This

organization has integrated five regional branches so-called Main Power Networks (MPN).

Through MPNs power is transmitted from a power plant to regional power grids.

112. NWMPN will be the entry point for receiving a complaint or known as a Focal

Grievance Point (FGP). Moreover, NWMPN will ensure local monitoring of LARP

implementation assisting PMU in all LARP related implementation activities.

113. UE as the EA has established a PMU with required staff, including a safeguards

specialist within the PMU. UE will also be responsible for the selection of Construction

Supervision Consultant (CSC). UE and its PMU will be responsible for finalizing final

LARP after detailed design with support from resettlement consultants hired by Fichtner.

UE will be capable for approval of adequate budgetary support for DDR implementation

and will facilitate coordination with the concerned government line agencies on LAR

activities as well as with independent valuation firms. UE and its PMU will be responsible

for finalizing/updating the draft LARP, getting the government’s endorsement, approval of

the DDR from ADB and will ensure compliance regarding complete payment of

compensation to APs before the start of civil construction.

Page 32: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

31

7.3 Social Safeguards Specialists (SSS)

114. UE has hired Fichtner GmbH & Co. KG as Project Implementation Consultant

(PIC) for the overall development of DDR and final LARPs. An International Social

Safeguard Specialist (SSS) of PIC will work closely with PMU’s Safeguards Specialist and

the engineering team. SSS will assist in all necessary information to develop this DDR

and prepare updated LARPs for other sections based on detailed designs. The work for

the SSS will broadly be segregated in two parts such as developing final DDR and

updating LARP based on detailed design, implementation of the LARP including

preparation of monitoring reports. The SSS will assist Safeguards Specialist of PMU in the

overall supervision of the project and ensure that LAR activities are implemented in a

smooth and timely manner by the provisions of the LARP. During the implementation of

DDR, the consultants will ensure that no persons/households are impacted due to

construction works, including ongoing rehabilitation measures.

7.4 Design Institute - “JSC Sredazenergosetproekt” (SAESP)

115. SAESP is one the most significant design and survey company in Uzbekistan as

well as in Central Asia for designinghigh voltage transmission line projects. It has past

experiences with previous transmission line designs of UE. In this project, SAESP will be

responsible for finalizing the detailed design. The role of the TEP in this TPP2 project

includes design and control during the construction activity.

116. SAESP will collaborate and work closely with the PMU/Safeguard Team and has

the following tasks:

(i) look for measures and alternatives to avoid and minimize land acquisition and

resettlement impacts during detail design;

(ii) assemble all documents required for compensation if any impactis determined

during detail design

(iii) carry out topographic surveys of the expropriated land and replacement lands, if

any

(iv) elaborate layouts indicating the location of worksites, permanent infrastructures

and perimeter of required surfaces differentiating the land use patterns in the

areas being occupied to serve as a base for the selection of compensation land

(v) Conduct landmarking of the land allocated for the construction.

7.5 UzDavYerLoyiha Design Institute

117. This Design Institute is mainly responsible for land use designs in Uzbekistan. By

the Resolution of Cabinet of Ministers #317, Uzdavyerloyiha is the authorized institution

that develops documentation for land acquisition and land allocation and calculates

agricultural losses due to permanent and temporary land acquisition. It is also responsible

for identifying and verifying property boundaries and ownership for allocated land during

the preparation of the Land Acquisition and Allocation Act (otvod zemli).

7.6 District Branch of State Committee on Land Resources, Geodesy, Cartography and

State Cadaster (SCLRGCSC)

118. SCLRGCSC is a permanent committee with its Provincial and District level

branches. However, it plays an enhanced role throughout implementation. It is

responsible for:

· identifying land losses incurred by land users plus agricultural output losses

Page 33: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

32

· determining the degree and area of land restitution, including removal and

temporary storage of productive soil layer

· determining the need for protective sanitary and water protection zones around

constructions

· preparing proposals on the allocation of land plots of equal value under land for

land

· investigating alternatives to acquiring currently used land through developing

unused land

· approving the Implementation Act and the attached plan

· amending government edicts on land use and land ownership as well as other

cadaster documents.

7.7 District (Khokimyat) (Governorates)

119. District (Khokimyat) will be intimately involved in the LARP review and

implementation which forms the Commission on Land Acquisition and District Evaluation

Commissions. These will form district land acquisition and resettlement committee

(DLARC) which will undertake the following:

· outline locations of constructions and structures affected by the project

· select a land for the construction sites

· approves the decree for the right to use the land plot

· forwards the complaints of citizens and affected households to PMU.

7.8 Community-Based Organizations (CBOs)

120. Board of Farmers in Uzbekistan (BFU) and Makhalla leaders will be involved in

land acquisition activities to ensure the rights and interests of affected households.

Implementation of LARP will require close coordination with the local Makhalla

representatives and Board of Farmers. This coordination will help Uzbekenergo in the

following:

(i) dissemination of LARP related information

(ii) checking timely disbursement of compensation to AHs

(iii) obtaining early warnings on the grievances of AHs

(iv) verifying as to whether the vulnerable AHs were identified according to requirement

laid down in this LARP and

(v) collecting information regarding any unexpected impacts, if any, being incurred by

the AHs

(vi) forwards the complaints of citizens and affected households to PMU.

121. The CBOs will ensure that vulnerable households be adequately supported by

national livelihood support program.

8. IMPLEMENTATION SCHEDULE

122. Upon the approval of final DDR, notice to proceed for construction works will be

given by ADB to UE. The activities mainly includes initiation of the land development

process, site preparation for delivering the site to contractors for construction and finally

commencement of the civil work. There is no any compensation payments and

allowances so that construction works can be commenced right after the disclosure of

DDR in the website of UE and ADB.

Page 34: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

33

123. During implementation, the AHs will need to be informed about their rights and

options, at which point they will have their say and discuss matters that need clarification.

Cash compensation amount and size of land offered for compensation will be presented

to each eligible APs for consideration and endorsement before cash payment, or land

compensation can be affected. A committee of peers will be set up for grievance redress.

124. Implementation of DDR for the selected sections of the project and post-

implementation is summarized in below Table 7.1

Table 7.1: Implementation schedule

Step Action Responsibility Timing

A. UPDATING OF DDR

1. Finalization of DDR PMU February 2019

B. DDR IMPLEMENTATION

2. No objection notice from ADB ADB February 2019

3. Notice to proceed for civil works is issued ADB/UE February 2019

C. ITERATIVE TASKS

4. Internal monitoring. Quarterly reporting to ADB PMU continuous

5. Inter-agency coordination and communication PMU, UE continuous

125. If during the implementation stage any involuntary resettlement, land acquisition

from households or entities will be identified, then these AHs are eligible to get

entitlements specified in draft LARP developed for NWRTLP.

9. CONCLUSION AND RECOMMENDATIONS

126. As per the findings of due diligence study and final design documents neither

permanent nor temporary impact to households, farmers and private legal entities are

expected due to the modernization/expansion of Khorezm SS and new construction of

Sarimay Switchyard. There will be no impact regarding land acquisition and no

physical/economic displacement that may trigger involuntary resettlement in these two

sections of the project.

127. During the construction works at sections of the project, there may be some

temporary disturbance caused by project contractors. Such a disruption would possibly be

incurred by excavation works on the sediment excluding basin, mobilizing heavy

machinery and equipment to the construction site, limited access to the agricultural land

plots in the neighborhood of the construction site, etc. Temporary disturbances will be

mitigated/reduced/eliminated by:

i) informing all residents, local households and traders about the nature and duration

of work though makhalla chairman

ii) providing access roads for Sarimay Switchyard

iii) Providing walkways for pedestrians of near to Khorezm Substation

iv) increasing the workforce and using appropriate equipment to complete the work in

a minimum timeframe on these stretches.

Page 35: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

34

128. EA will address such issues through proper conditions in the Environmental

Management Plan that will be annexed to the main Contract between UE and Contractor

for the Civil Works.

129. One of the conditions for there lease of final payment to the civil works contractors

is the submission of proof that DDR followed and neither permanent nor temporary impact

has been observed during the construction period. If there were unanticipated impacts,

then, temporarily used lands have been fully restored to their pre-project conditions.

130. Since land allocated for Sarimay Switchyard out of the State Reserve Land, a land

restoration cost was paid by UE to the special account of Regional SCLRGCSC branch of

Khorezm Region. This payment is not considered as compensation for affected

households. This payment is paid from one state organization to account of the other

state organization. Therefore, it is not considered as involuntary resettlement.

131. The EA will be responsible for documenting monitoring reports on DDR completion

reports through its PMU to ADB for review on the semi-annual (annual) basis.

132. The contractor will submit construction plan/schedule particularly for Khorezm and

Sarimay SS to EA and this will be notified and disseminated to the local people in

advance. EA through its PMU representative and PIC’s supervision consultants on the

site will monitor and supervise this process. All necessary steps should be taken during

construction to avoid temporary impacts like loss of access leading to an impact on

livelihoods or any other kinds of restrictions.

133. Any grievances by local people will be addressed through the grievance redress

mechanism established under the project. EA will ensure resolution.

134. If during the project implementation any unanticipated impacts or additional

impacts are identified regarding involuntary land acquisition then EA shall prepare a LARP

by the Safeguard Policy Statement 2009 of ADB. Until such planning documents are

formulated, disclosed and approved by ADB, the Executing Agency will not proceed with

implementing the specific project components for which involuntary resettlement impacts

are identified. Affected land and attachments on the land will be restored to its pre-

subproject condition. Permanent damages to improvements/structures, if any, will be

compensated in cash at replacement cost following the provisions in the entitlement’s

matrix provided in this resettlement due diligence report and rules made in a LARP if

required.

135. Despite there is no negative social impact regarding involuntary resettlement and

land acquisition from affected households, there is an environmental impact during the (i)

pre-construction, (ii) construction, (iii) operation and maintenance, and iv)

decommissioning stages. Environmental Management Plan (EMP) was prepared for this

purpose that identifies feasible and cost-effective measures to be taken to reduce

potential significant, adverse impacts to acceptable levels. Here, proper mitigation

measures are proposed for each potential impact, including details on responsible parties

for the implementation of mitigation measures and supervision. This EMP shall be

followed by the Contractor during the construction phase and monitored by Safeguards

Specialist of PMU.

Page 36: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

35

136. The results of this Due Diligence study conclude that, as per ADB Safeguard

Policy Statement, the project’s sections (4) Khorezm Substation and (7) Sarimay

Switchyard is categorized as ‘C’ for both Involuntary Resettlement and Indigenous

Peoples. As the construction will be confined to the distinct project site and the state

reserve land, there will be no temporary disruption of livelihood of any household or group

of community in Urgench and Nukus settlements during the construction period. In case

any claims or complaints are submitted during the project implementation period, an

effective and efficient Grievance Redress Mechanism will enhance the provision of timely

and sensible hearings and facilitate solutions.

Page 37: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

36

9.1 Annex 1: No-objection Letter by ADB

Page 38: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

37

9.2 Annex 2: Architectural Planning Assignment for Khorezm Substation

Page 39: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

38

9.3 Annex 3: Extract from Architectural Planning Assignment for Khorezm Substation

Page 40: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

39

9.4 Annex 4: Extract from Cadaster Document of Khorazmelektrqishloqqurilish

(Allocated land is marked in red lines)

Page 41: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

40

9.5 Annex 5: Architectural Planning Assignment for Sarimay Switchyard

Page 42: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

41

9.6 Annex 6: Extract from Architectural Planning Assignment showing the Allocated Land

(Allocated land for Sarimay switchyard marked as a rectangle)

Page 43: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

42

9.7 Annex 7: Land Selection Order by District Khokim for Sarimay Switchyard

Page 44: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

43

9.8 Annex 8: Land Selection act prepared by Uzgiprozem for Sarimay Switchyard

Page 45: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

44

9.9 Annex 9: List of Consulted Stakeholders

StakeholderOrganization

Name and Position Discussed Questions

State Unitary Enterprise,Uzelektroset

Karimov BahriddinDeputy Director

Possibility to start construction worksfor sections where there is noinvoluntary resettlement.

North West Main PowerNetwork

Saparboyev RufatDirector

Construction works during theimplementation. Unanticipatedimpacts during the implementationstage

Sredazenergosetproekt Alla DrobovaChief Design Engineer

Final Design and right of ways, safetyzones of substations discussed.Settlements are out of the safety zoneare has been confirmed

Sredazenergosetproekt Asanov RemziHead of Survey division

The survey work was carried outduring the 2016-2018 years. Impactson other grids and networks within theselected land for Sarimay switchyard

Khazorasp districtKhokimiyat

Ravshan JabborovKhokim

Discussion on selected lands forSarimay switchyard. Avoidance andmitigation of possible impacts byContractors duringtheconstructionworks

Urganch city SCLRGCSC N.JabborovHead of the division

The cadastral document ofKhorazmelektrqishloqqurilish andKhorezm substation wereconfirmedfor the boundaries and territories.Ownership status and owners areidentified.

Uzdavyerloyiha DesignInstitute

Artur TadjievEngineer

Land allocation procedure, theownership status of the SarimaySwitchyard lands are discussed.Engineer confirmed that the land isunder the State Reserve land and noaffected households exist.

Page 46: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

45

9.10 Annex 10: List of Consulted Stakeholders

Not addressed within

2 weeks

LEVEL-2

·M akhalla

committee

·Site Engineer of

NWM PN

·Site office of

Contractor

· District khokimiyat

Grievance

Addressed

People living near

to subprojects

Project M anagement

Unit in Tashkent

Grievance

Addressed

Complaint handling team within

PM U

Not addressed within

15 Days

Economic Court

People can approach the court of law at time during

the Grievance redress process independent of GRM

and the grievance mechanism should not impede

access to the country’s judicial or administrative

remedies

Page 47: 47296-001: Northwest Region Power Transmission Line Project · Prepared by State Joint Stock Company Uzbekenergo for the Republic of Uzbekistan and the Asian Development Bank. This

46

9.11 Annex 11: List of Consulted Stakeholders

Cover page:

GRIEVANCE REDRESS MECHANISM

THE LOG BOOK OF COMPLAINTS, SUGGESTIONS, AND GRATITUDE

N Date The contentof

Grievances/Complaint

/Suggestions/Gratitude

Applicant/Aggrieved

Person(Full

Name)

Contactdetails

Signature/Note

Accepted by

Continuation:1) Answer orally /

date2) Replied inwriting/date

3) Forwarded toanother authority(to be indicated) /

date4) Other action (tobe indicated) / date

The shortcontent ofthe status

ofresponse

andreimburse

ment(1-

satisfactory,

2-partiallysatisfactory,

3-unsatisfacto

ry.)

1

2

3

For the implementation of :

Loan 3285-UZB: Northwest Region Transmission Line Project (NWRTLP)

Subproject Name (Sections 1 to 7)

Name Makhalla committee/ Contractor working office/Hokimiyat and PMUTashkentoffice/:

District, Province:

Notice: The grievance book should sequentially be numbered and pages have been bound

securely