3rd Year and Final Report on Project Management and Use of Resources p 1 of 34
3rd Year and Final Report on Project Management and Use of Resources
Deliverable D6.4
Grant Agreement number: FP7-243845
Project acronym: ROOTHz
Project title: Semiconductor Nanodevices for Room Temperature THz Emission and
Detection
Funding Scheme: Collaborative Project (STREP)
Project website address: www.roothz.eu
Date: 25 July 2013
TABLE OF CONTENTS 1. Project Management 2
2. Deliverables and milestones tables 6
3. Explanation of the use of the resources 9
4. Financial statements - Forms C and Summary financial report 34
3rd Year and Final Report on Project Management and Use of Resources p 2 of 34
1. PROJECT MANAGEMENT
Interaction
The coordination of this project has been a simple task not only due to the small number of partners but
also because of the strong interactions between them and the high level of commitment and effort of each of
them. For that sake the monthly teleconferences (28 in total, minutes can be found in the reserved area of
the project webpage) have revealed as a very useful tool, where the important aspects of the individual work
of the partners were put in common in order to obtain the maximum global benefit and to help the
coordination of the different tasks. Frequent plenary meetings where also held, totalling 11 face-to-face
meetings (including the 3 review meetings), about three per year throughout the 42 months of the project,
which were very effective in order to improve the interchange of information and the coordination of the
research efforts. The detailed information about the plenary meetings is given in the following table.
*RA=Roger Appleby, CM=Chris Mann, NA=Naomi Alexander, CC=Carlos Callejero
Face-to-face Plenary Meetings
Date Month Place Type of meeting
IAB Members* Comments
1st Review Period
Jan. 2010
M1 Salamanca
(Spain) Kickoff meeting
RA, CM, NA, CC
Sept. 2010
M9 Gothenburg (Sweden)
Progress meeting
RA, CM, CC
Jan. 2011
M13 Brussels (Belgium)
1st year Review
Preceded by an internal meeting
2nd Review Period
June 2011
M18 Lille
(France) Progress meeting
Sept. 2011
M21 Manchester
(UK) Progress meeting
RA, CM, NA
In coincidence with the European Microwave week
Feb. 2012
M26 Brussels (Belgium)
2nd year Review
Preceded by an internal meeting
3rd Review Period
July 2012
M31 Salamanca
(Spain) Progress meeting
RA, CM
Oct. 2012
M34 Amsterdam (Nederland)
Progress meeting
RA In coincidence with the European Microwave week
March. 2013
M39 Gothenburg (Sweden)
Progress meeting
RA, CM, NA
June 2013
M42 Lille
(France) Progress meeting
RA, NA In coincidence with the PhD defence of Paul Sangaré, in whose committee J. Mateos (USAL) and J. Grahn (CHAL) were participating
Sept. 2013
Brussels (Belgium)
Final Review
Preceded by an internal meeting
3rd Year and Final Report on Project Management and Use of Resources p 3 of 34
Correction actions
The correction actions have been taken by unanimity and no conflict has aroused in the consortium.
The main issues that have been dealt with are:
The difficulties found during the first two years of ROOTHz for the fabrication of InAs SSDs, mainly due
to the oxidation of the AlSb buffer and the sidewalls of the trenches. This task, initially developed at
UNIMAN, was then assumed by CHAL (once the fabrication of InGaAs slot diodes was under control),
were the technological problems have been finally solved and working devices were produced on
December 2012 (M36).
The absence of evidence of THz emission from both SSDs and slot-diodes has not been solved. Some
correction actions were tried:
o InGaAs-based planar diodes were fabricated as a possible alternative, but was discarded do
to their low efficiency and oscillation frequencies.
o The excessive heating observed in GaN SSDs avoided reaching DC bias above the
threshold voltage for the onset of Gunn oscillations. This was corrected in a third run of
fabrication at IEMN (not scheduled in the proposal) and by developing a pulsed RF
characterization setup which allows applying biases above 50 V while performing the THz
characterization.
o More sensitive characterization techniques than those available at the partners’ laboratories
were used through collaboration with other laboratories (Univ. of Montpellier, Univ. of Leeds
and Univ. of Rochester).
o A new fabrication run would have been necessary in order to integrate adequate resonators,
but the funding of ROOTHz was not enough to cover its costs. As a cheap solution, the
connection of an external feedback loop is being tried.
o The resources (both personnel effort and fabrication costs) initially dedicated to the tasks of
WP4 that have not been realized due to the lack of evidence of THz emission from the
fabricated devices have been dedicated to additional fabrication runs of discrete devices and
their time consuming THz characterization. As a consequence, most of the ROOTHz budget
has been invested on the technological processes, while the personnel effort, larger than the
initial prevision (also due to the project extension), has been assumed in part by the
partners’ institutions.
Industrial Advisory Board
The continuous presence of the IAB members in the progress meetings (Chris Mann, Roger Appleby
and one representative of Alfa Imaging were attending to most of the progress meetings, 6 out of 8, as
shown in the table above, Prof. M. Pepper, Teraview, was too busy for attending) evidenced their interest in
the work developed within ROOTHz and their generous involvement in our research. The help of the IAB has
been very valuable for orienting our efforts based in their broad experience. Their opinion about the results
obtained within the ROOTHz and the recommendations given are the following:
Tuesday 16th July 2013
Industrial Advisory Board: R Appleby, C Mann, N Alexander
The ROOTHz project has worked very well with excellent interaction between the partners. There
has been an open and frank exchange of information and resources. The project set itself the ambitious target of developing a new class of III-V detector device and signal emitter that should equal or better existing commercially available technology.
With respect to the detector device, very challenging materials were targeted for processing and this required the development of new process technologies. This in itself represented a high level of
3rd Year and Final Report on Project Management and Use of Resources p 4 of 34
risk. Nevertheless the resulting detectors had interesting characteristics that may have industrial applications. The sensitivity of the detectors is close to that available from conventional zero bias devices fabricated from GaAs and so from this perspective the goal was met. However, the power handling capability is likely to be orders of magnitude higher due to the increased bandgap and excellent thermal heat sinking. This development may have interesting implications as a new class of very high power vacuum Continuous Wave (CW) sources with output powers in excess of 1 kW have been recently developed initially targeted at material processing applications. The subsequent systems are likely to require detectors with much higher power handling capability and dynamic range. The detectors developed in the ROOTHz project may be ideally suited for this task and so it is recommended that there is early engagement with the source developers and likely end users.
With respect to the emitters the ROOTHz project has failed to develop any devices that have demonstrated any signal emission. However, this aspect of the project was extremely ambitious with a high degree of risk. Nevertheless the team pursued each avenue as problems in their device design, fabrication and testing were encountered with the result that the likely reasons for a lack of emission are now well understood from a theoretical perspective. One aspect which became clear to the industrial panel was that the consortium did not have previous experience of working with classical RF sources such as Gunn diodes and amplifier oscillators but towards the end of the project the theoretical analysis started to show that some kind of external feedback circuit would most likely be required for the devices that had been fabricated to oscillate. The industrial panel have gained sufficient confidence in the consortiums ability to simulate the device and it is recommended that further effort is put into this area. A suitable circuit simulation tool should be used to develop and external resonator circuit before the approaches viability as a source is written off.
It is recommended that the Intellectual Property surrounding the detectors is moved forward but that relating to operation as a emitter put on hold until such time that it has been verified.
The members of the industrial panel would like to thank the ROOTHz consortium whole heartedly for their enthusiastic approach to the project even when they experienced significant problems. It has been very rewarding for the members to play a part of this successful project.
Website
The ROOTHz website (www.roothz.eu) have been continuously updated in order to disseminate the
achievements of the project and highlight the latest publications and invited conference presentations
provided by the partners.
Contacts with other EU projects
The coordinator has been involved in the organization of a THz dedicated workshop (Terahertz
Technologies: from Devices to Diverse Systems and Applications) in the last 3 editions of the European
Microwave Week (EuMW’2011 in Manchester, EuMW’2012 in Amsterdam and the forthcoming EuMW’2013
in Nurnberg), where the results of the ROOTHz projects were also presented. Within these workshops the
participation of speakers working in other EU projects has been promoted, in order to improve the
interchange of information and possible interactions and collaborations. Indeed, Dr. Audrey Berrier was
presenting the latest achievements of the ULTRA project (Ultra-fast Electronics for Terahertz Rapid Analysis
in Compact Lab-on-Chip Applications) in the 2011 and 2012 editions, and in the upcoming 2013 one Dr.
Samuel Ver Hoeye will provide their contribution in the area of THz detection with graphene devices applied
to the painting scanning (the subject of the recently started INSIDDE project, INtegration of cost-effective
Solutions for Imaging, Detection, and Digitisation of hidden Elements in paintings).
Deliverables & Milestones reports
The achievement of milestones MS.4 (RT operation of Run 1 emitters at >200 GHz demonstrated) and
MS.5 (RT operation of Run 1 detectors at >1 THz demonstrated) was delayed to M30 after the 6 month
project extension that was agreed in the 2nd year review meeting. The initial reports corresponding to those
milestones, produced on July 2011 (M18), have been updated at the end of the project summarizing the
efforts dedicated to the achievements of both objectives. The updated reports of MS.4 and MS.5, together
3rd Year and Final Report on Project Management and Use of Resources p 5 of 34
with this Scientific Report provide the details of the work performed on both emission and detection sides
and the final status reached at the end of the project, including the justification of the failure to reach the
planned objectives
Unfortunately, in spite of all that work we have not been able to observe any THz emission from any of
the devices fabricated within ROOTHz. On the detection side, the results have been quite encouraging, even
if a clear demonstration of detection above 1 THz has not been obtained due to the low power of the THz
sources available at the partners’ laboratories (and those of the Univ. of Montpellier and Rochester that have
collaborated in the characterization of the devices fabricated within ROOTHz). As a result, the milestones
corresponding to the optimization of emitters and detectors (MS.6) and the fabrication of a emitter/detector
subsystem (MS.9, corresponding to the definition of the subsystem design and MS.7 to its characterization)
have neither been achieved. The work realized aiming to develop the antenna design in discrete emitters
and detectors is described in the report of MS.8. Moreover, as all the technologies were investigated until the
end of the project (in agreement with the result of the 2nd year review of ROOTHz), the Milestone
corresponding to the choice of the best technology for emitters and detectors to be used in the THz
subsystem fabricated in WP4 (MS.1), was not addressed.
Regarding the preparation of the reports corresponding to the deliverables we have produced reports
for D1.4 and D3.3 (reports on modelling and characterization, respectively), D2.3 and D2.4 (fabrication of
NBG and WBG SSDs), where the work has nearly followed the initial schedule, even if the final objective of
generating THz emission was not achieved. As a consequence, the deliverables corresponding to the WP4
subsystem integration cannot be provided (D4.1 fabrication of emitter/detector subsystem, D4.2 spectrum of
a benchmark substance obtained and D4.3 benchmarking of THz subsystem). This Scientific reports clearly
explains the causes for not reaching them and the part of the objectives that have been reached (for
example, the benchmarking of the THz detectors in D4.3).
3rd Year and Final Report on Project Management and Use of Resources p 6 of 34
2. DELIVERABLES AND MILESTONES TABLES
Despite the fact that THz emission has not been observed from the devices fabricated within ROOTHz,
most of the project tasks have followed the initial workplan (with the exception of WP4 where the integration
of emitters and detectors was scheduled). As a consequence, all the deliverables corresponding to the 3
initial scientific workpackages WP1 (modelling), WP2 (fabrication) and WP3 (characterization) have been
achieved, as well as those related to the dissemination and management (WP5 and WP6). In the last part of
the project, CHAL has been able to improve the technological process in order to fabricate InAs SSDs with a
good reproducibility and yield. Therefore, most of the technological challenges brought up in the ROOTHz
project have been solved. Indeed, we can consider as an important success the fact that GaN and InAs
SSDs have been fabricated for the first time within this project, and also the slot-diode technology has been
optimized.
On the other hand, in spite of the 6 month extension and the important efforts dedicated to the
characterization of the fabricated devices, this has not provided any evidence of THz emission. As a
consequence, even if some of the tasks corresponding to WP4 have been realized (like the antenna design
and the benchmarking of the THz detectors), the deliverables corresponding to WP4 have not been
completely accomplished (D4.1 fabrication of emitter/detector subsystem, D4.2 spectrum of a benchmark
substance obtained and D4.3 benchmarking of THz subsystem).
Regarding THz detection above 1 THz (corresponding to MS.5), it was demonstrated in GaAs SSDs
(fabricated not within the ROOTHz project), and its confirmation for InGaAs and InAs SSDs was also one of
the priority objectives of the consortium in the last 18 months of ROOTHz. The successful experimental
demonstration of detection at 600 GHz has been achieved with InAs SSDs. However, even if MC simulations
show that their cutoff frequency is above 1 THz, the low responsivity of the diodes, together with the low
power of the THz sources available at f> 1THz, has not allowed us to show such an experimental evidence.
Del. No Deliverable name WP
NoLead
beneficiaryNature
Delivery month
Delivered Comments
1st Review Period
D1.1 Report on the modelling of THz nanodevices (included in Year 1 scientific report)
1 USAL R M12 YES
D2.1 Fabrication of Run 1 of NBG SSDs and Slot-diodes
2 UNIMAN P M12 YES
D3.1 Report on physical and electrical characterization of preliminary devices (included in Year 1 scientific report)
3 IEMN R M12 YES
D5.1 Year 1 Scientific Report 5 USAL R M12 YES
D6.1 Project Website 6 USAL O M6 YES
D6.2 Year 1 Periodic Report 6 USAL R M12 YES
2nd Review Period
D1.2 Design rules for the optimization of Run 2 devices
1 USAL R M18 YES
D1.3 Report on the modelling of THz nanodevices (included in Year 2 scientific report)
1 USAL R M24 YES
D2.2 Fabrication of Run 1 of WBG SSDs 2 IEMN P M18 YES 6 Months in
3rd Year and Final Report on Project Management and Use of Resources p 7 of 34
advance
D3.2 Report on characterization of Run 1 nanodevices (included in Year 2 scientific report)
3 IEMN R M24 YES
D5.2 Year 2 Scientific Report 5 USAL R M24 YES
D6.3 Year 2 Periodic Report 6 USAL R M24 YES
3rd Review Period
D1.4 Report on the modelling of THz nanodevices (included in Year 3 scientific report)
1 USAL R M42 YES
D2.3 Fabrication of Run 2 of NBG SSDs and Slot-diodes
2 CHAL P M36 YES
D2.4 Fabrication of Run 2 of WBG SSDs 2 IEMN P M36 YES 3rd Run completed at M30
D3.3 Report on characterization of Run 2 nanodevices and emitter/detector system (included in final report).
3 IEMN R M42 YES Only discrete devices
characterized
D4.1 Emitter/detector system with integrated antenna fabricated
4 UNIMAN P M39 NO No THz emission achieved
D4.2 Transmission/reflection spectrum of a benchmark substance obtained in the 0.5-2 THz band
4 UNIMAN R M42 NO No THz emission achieved
D4.3 Benchmarking of working RT THz subsystem
4 UNIMAN R M42 NO Only for THz detectors
D5.3 Year 3 Scientific Report 5 USAL R M42 YES
D5.4 Final plan for the use and dissemination of Foreground (included in final report)
5 USAL R M42 YES
D6.4 Year 3 Periodic Report and Final Report
6 USAL R M42 YES
D6.5 Report on awareness and wider societal implications
6 USAL R M42 YES
Nature: R=Report, P=Prototype, O=Others
List and schedule of milestones
Mile-stone
numberMilestone name
Work package involved
Delivery date from
Annex I
Lead benefi-ciary
Status Report delivered
MS.1 Choice of the best technology for emitters and detectors to
be used in the THz subsystem fabricated in WP4
WP1, WP2, WP3
M30 USAL All the technologies have been investigated until the end of the project aiming to
obtain THz emission
NO
MS.2 WBG technology process defined
WP2 M9 IEMN OK YES
MS.3 Design of masks for fabrication of optimized THz
WP1, WP2,
M18 USAL OK YES
3rd Year and Final Report on Project Management and Use of Resources p 8 of 34
emitters and detectors with the different technologies in
Run 2
WP3
MS.4 RT operation of emitters at >200 GHz demonstrated
WP2, WP3
M30 CHAL No THz emission observed YES
Updated at M42
MS.5 RT operation of detectors at >1 THz demonstrated
WP2, WP3
M30 UNIMAN Detection >1 THz observed in GaAs SSDs with a free electron laser. Experiment
not performed with ROOTHz devices.
Detection @600 GHz with low responsivity, but
expected to remain >1 THz.
YES
Updated at M42
MS.6 THz RT operation of Run 2 emitters and detectors
demonstrated in the 0.5-2 THz band (emitter with 1 mW power and passive detector with sensitivity
above 500 mV/mW)
WP2, WP3
M36 UNIMAN No THz emission observed (highest priority).
Low responsivity of the detectors due to power
mismatch
NO
MS.7 Broadband THz emitter/detector subsystem
with integrated antenna characterized in the 0.5-2.0
THz band
WP3, WP4
M42 UNIMAN Not achieved due to the lack of THz emission
NO
MS.8 Antenna design defined WP1, WP2, WP3, WP4
M33 UNIMAN OK YES
MS.9 Subsystem design defined WP1, WP2, WP3, WP4
M33 USAL Not achieved due to the lack of THz emission
NO
3rd Year and Final Report on Project Management and Use of Resources p 9 of 34
3. EXPLANATION OF THE USE OF THE RESOURCES
Table 3.1.1 Major Direct costs for Beneficiary 1 (USAL) for Year 1
RTD/Innovation (A)
WP Item description Amount Explanations
WP1 Personnel costs (RTD) 8,274.49 € Salary of Postdoc – Ignacio Iñiguez (3.7 person.month = 491 hours)
WP1 Personnel costs (RTD) 18,006.00 € Salary of J. Mateos (4.6 person.month = 600 hours)
WP1 Personnel costs (RTD) 14,820.00 €Salary of T. González (3.0 person.month = 400 hours)
WP1 Personnel costs (RTD) 16,375.00 € Salary of S. Pérez (3.8 person.month = 500 hours)
WP1 Personnel costs (RTD) 11,710.00 €Salary of B. G. Vasallo (3.8 person.month = 500 hours)
WP1 Personnel costs (RTD) 8,862.00€ Salary of D. Pardo (1.5 person.month = 200 hours)
Total Personnel costs (RTD) 78,047.49 €
WP1 Workstation + portable computer
2,384.46 € 1 year use (total price 7,153.38 €)
Total Other direct costs (RTD) 2,384.46 €
Management (C)
WP Item description Amount Explanations
WP6 Personnel costs (MGT) 6,002.00 € Salary of J. Mateos (1.5 person.month = 200 hours)
Total Personnel costs (MGT) 6,002.00 €
WP6 Web maintenance 18.00 € roothz.eu 1 year domain name registration
WP6 IAB Missions 885.20 € Travel of C. Mann to Salamanca – 3.5 days (Participation in the ROOTHz kick-off meeting)
WP6 IAB Missions 145.59 € Travel of N. Alexander to Salamanca – 2 days (Participation in the ROOTHz kick-off meeting)
WP6 IAB Missions 117.24 € Travel of C. Callejero to Salamanca – 2 days (Participation in the ROOTHz kick-off meeting)
WP6 IAB Missions 485.29 € Travel of R. Appleby to Salamanca – 2.5 days (Participation in the ROOTHz kick-off meeting)
WP6 Meeting organization 234.63 € Kick-off meeting coffee-breaks + lunch
WP6 Meeting organization 640.00 € Kick-off meeting dinner
WP6 Travels to ROOTHz meetings
887.32 € Travel of J. Mateos to Gothenburg – 2.5 days (Participation in the Sept. 2010 ROOTHz progress meeting)
WP6 Travels to ROOTHz meetings
952.09 € Travel of T. González to Gothenburg – 2.5 days (Participation in the Sept. 2010 ROOTHz progress
3rd Year and Final Report on Project Management and Use of Resources p 10 of 34
meeting)
WP6 Travels to ROOTHz meetings
807.21 € Travel of A. Iñiguez to Gothenburg – 2.5 days (Participation in the Sept. 2010 ROOTHz progress meeting)
WP6 IAB Missions 939.37 € Travel of C. Mann to Gothenburg – 1.5 days (Participation in the Sept. 2010 ROOTHz progress meeting)
WP6 IAB Missions 835.21 € Travel of C. Callejero to Gothenburg – 2.5 days (Participation in the Sept. 2010 ROOTHz progress meeting)
WP6 IAB Missions 612.23 € Travel of R. Appleby to Gothenburg – 2.5 days (Participation in the Sept. 2010 ROOTHz progress meeting)
Total Other direct costs (MGT) 7,559.38 €
Other (D)
WP Item description Amount Explanations
WP5 Personnel costs (OTHER) 1,800.60 € Salary of J. Mateos (0.5 person.month = 60 hours)
WP5 Personnel costs (OTHER) 1,111.50 € Salary of T. González (0.2 person.month = 30 hours)
WP5 Personnel costs (OTHER) 655.00 € Salary of S. Pérez (0.15 person.month = 20 hours)
WP5 Personnel costs (OTHER) 468.40 € Salary of B. G. Vasallo (0.15 person.month = 20 hours)
Total Personnel costs (OTHER) 4,035.50 €
WP5 Travels to conferences 658.94 €
Travel of J. Mateos to Gijon, Spain – 2.5 days (Participation in the launching of the Nanofutures Initiative. Poster presentation entitled “ROOTHz: Semiconductor Nanodevices for Room Temperature THz Emission and Detection”)
WP5 Travels to conferences 507.08 €
Travels of T. Gonzalez to Gijon, Spain – 2.5 days (Participation in the launching of the Nanofutures Initiative. Poster presentation entitled “ROOTHz: Semiconductor Nanodevices for Room Temperature THz Emission and Detection”)
Total other direct costs (OTHER) 1,166.02 €
TOTAL DIRECT COSTS 99,194.85 € USAL Year 1
3rd Year and Final Report on Project Management and Use of Resources p 11 of 34
Table 3.1.2 Major Direct costs for Beneficiary 1 (USAL) for Year 2
RTD/Innovation (A)
WP Item description Amount Explanations
WP1 Personnel costs (RTD) 22,879.75 € Salary of Postdoc – Ignacio Iñiguez (8.7 person.month = 1150 hours)
WP1 Personnel costs (RTD) 13,990.00 € Salary of J. Mateos (3.8 person.month = 500 hours)
WP1 Personnel costs (RTD) 7,026.00 €Salary of T. González (1.6 person.month = 200 hours)
WP1 Personnel costs (RTD) 11,228.00 € Salary of S. Pérez (3.0 person.month = 400 hours)
WP1 Personnel costs (RTD) 4,672.00 €Salary of B. G. Vasallo (1.5 person.month = 200 hours)
WP1 Personnel costs (RTD) 4,192.00 € Salary of D. Pardo (0.8 person.month = 100 hours)
WP4 Personnel costs (RTD) 3,513.00 €Salary of T. González (0.7 person.month = 100 hours)
WP4 Personnel costs (RTD) 4,672.00 €Salary of B. G. Vasallo (1.5 person.month = 200 hours)
Total Personnel costs (RTD) 72,172.75 €
WP1 Workstation + portable computer
2,384.46 € 1 year use (total price 7,153.38 €)
Total Other direct costs (RTD) 2,384.46 €
Management (C)
WP Item description Amount Explanations
WP6 Personnel costs (MGT) 4,197.00 € Salary of J. Mateos (1.2 person.month = 150 hours)
WP6 Personnel costs (MGT) 702.60 € Salary of T. González (0.2 person.month = 20 hours)
WP6 Personnel costs (MGT) 561.40 € Salary of S. Pérez (0.2 person.month = 20 hours)
Total Personnel costs (MGT) 5,461.00 €
WP6 Web maintenance 18.00 € roothz.eu 1 year domain name renovation
WP6 Travels to ROOTHz meetings
859.61 € Travel of J. Mateos to Brussels – 3 days (Participation in the 1st Year review meeting)
WP6 Travels to ROOTHz meetings
884.67 € Travel of T. González to Brussels – 3 days (Participation in the 1st Year review meeting)
WP6 Travels to ROOTHz meetings
683.20 € Travel of S. Pérez to Brussels – 3 days (Participation in the 1st Year review meeting)
WP6 Travels to ROOTHz meetings
583.29 € Travel of I. Iñiguez to Brussels – 3 days (Participation in the 1st Year review meeting)
WP6 Travels to ROOTHz meetings
581.98 € Travel of A. Iñiguez to Brussels – 3 days (Participation in the 1st Year review meeting)
3rd Year and Final Report on Project Management and Use of Resources p 12 of 34
WP6 Meeting organization 642.82 €Meeting room + lunch at IBIS Hotel in Brussels (preparation review meeting)
WP6 Meeting organization 51.96 € Photocopies for reviewers
WP6 Travels to ROOTHz meetings
764.55 €Travel of J. Mateos to Lille – 2.5 days (Participation in the Jul. 2011 ROOTHz progress meeting)
WP6 Travels to ROOTHz meetings
485.07 € Travel of I. Iñiguez to Lille – 2.5 days (Participation in the Jul. 2011 ROOTHz progress meeting)
WP6 Travels to ROOTHz meetings
454.13 €Travel of J. Mateos to Manchester – 2 days (Participation in the Oct. 2011 ROOTHz progress meeting)
WP6 IAB Missions 396.00 €Travel of C. Mann to Manchester – 2 days (Participation in the Oct. 2011 ROOTHz progress meeting)
WP6 IAB Missions 530.50 €Travel of N. Alexander to Manchester – 2 days (Participation in the Oct. 2011 ROOTHz progress meeting)
WP6 IAB Missions 393.01 €Travel of R. Appleby Manchester – 2 days (Participation in the Oct. 2011 ROOTHz progress meeting)
Total Other direct costs (MGT) 7,328.79 €
Other (D)
WP Item description Amount Explanations
WP5 Personnel costs (OTHER) 1,678.80 € Salary of J. Mateos (0.5 person.month = 60 hours)
WP5 Personnel costs (OTHER) 1,756.50 € Salary of T. González (0.4 person.month = 50 hours)
WP5 Personnel costs (OTHER) 842.10 € Salary of S. Pérez (0.2 person.month = 30 hours)
WP5 Personnel costs (OTHER) 467.20 €Salary of B. G. Vasallo (0.15 person.month = 20 hours)
WP5 Personnel costs (OTHER) 994.77 € Salary of I. Iñiguez (0.4 person.month = 50 hours)
Total Personnel costs (OTHER) 5,739.37 €
WP5 Travels to conferences 3,117.84 €Travel of J. Mateos to Singapore – 9.5 days (Invited talk for the Interest Group THz in the IEEE 802 plenary session)
WP5 Travels to conferences 716.14 €Travel of J. Mateos to Manchester, UK – 5.5 days (Participation in the European Microwave Week. THz workshop organization and ROOTHz presentation)
Total other direct costs (OTHER) 3,833.98 €
TOTAL DIRECT COSTS 96,920.35 € USAL Year 2
3rd Year and Final Report on Project Management and Use of Resources p 13 of 34
Table 3.1.3 Major Direct costs for Beneficiary 1 (USAL) for Year 3
RTD/Innovation (A)
WP Item description Amount Explanations
WP1 Personnel costs (RTD) 45,106.19 € Salary of Postdoc – Jean Francois Millithaler (18 person.month = 2400 hours)
WP1 Personnel costs (RTD) 6,960.15 € Salary of J. Mateos (2.0 person.month = 260 hours)
WP1 Personnel costs (RTD) 4,441.66 €Salary of T. González (1.0 person.month = 130 hours)
WP1 Personnel costs (RTD) 3,512.26 € Salary of S. Pérez (1.0 person.month = 130 hours)
WP1 Personnel costs (RTD) 5,025.18 € Salary of I. Iñiguez (2.0 person.month = 260 hours)
WP4 Personnel costs (RTD) 3,173.90 €Salary of B. G. Vasallo (1.0 person.month = 130 hours)
WP4 Personnel costs (RTD) 2,594.77 € Salary of I. Iñiguez (1.0 person.month = 130 hours)
Total Personnel costs (RTD) 70,814.11 €
WP1 Workstation + portable computer
2,384.46 € 1 year use (total price 7,153.38 €)
Total Other direct costs (RTD) 2,384.46 €
Management (C)
WP Item description Amount Explanations
WP6 Personnel costs (MGT) 4,015.47 € Salary of J. Mateos (1.2 person.month = 150 hours)
WP6 Personnel costs (MGT) 683.33 € Salary of T. González (0.2 person.month = 20 hours)
WP6 Personnel costs (MGT) 540.35 € Salary of S. Pérez (0.2 person.month = 20 hours)
WP6 Personnel costs (RTD) 798.39 € Salary of I. Iñiguez (0.4 person.month = 40 hours)
Total Personnel costs (MGT) 6,037.54 €
WP6 Web maintenance 36.00 € roothz.eu 2 year domain name renovation
WP6 Travels to ROOTHz meetings
570.23 € Travel of J. Mateos to Brussels – 3 days (Participation in the 2nd Year review meeting)
WP6 Travels to ROOTHz meetings
716.72 € Travel of T. González to Brussels – 3 days (Participation in the 2nd Year review meeting)
WP6 Travels to ROOTHz meetings
470.23 € Travel of S. Pérez to Brussels – 3 days (Participation in the 2nd Year review meeting)
WP6 Travels to ROOTHz meetings
470.23 €Travel of I. Iñiguez to Brussels – 3 days (Participation in the 2nd Year review meeting)
WP6 Meeting organization 616.32 €Meeting room + lunch at IBIS Hotel in Brussels (preparation review meeting)
WP6 Meeting organization 63.00 € Photocopies for reviewers
3rd Year and Final Report on Project Management and Use of Resources p 14 of 34
WP6 Travels to external laboratories
1,082.54 €Travel of J. Mateos to Montpellier – 4 days (measurement campaign June 2012)
WP6 Travels to external laboratories
814.25 €Travel of I. Iñiguez to Montpellier – 4 days (measurement campaign June 2012)
WP6 Travels to external laboratories
809.50 €Travel of J.F. Millithaler to Montpellier – 4 days (measurement campaign June 2012)
WP6 Travels to ROOTHz meetings
973.21 €Travel of J. Mateos to Gothenburg – 2.5 days (Participation in the March 2013 ROOTHz progress meeting)
WP6 Travels to ROOTHz meetings
704.84 € Travel of I. Iñiguez to Gothenburg – 2.5 days (Participation in the March 2013 ROOTHz progress meeting)
WP6 IAB Missions 724.05 €Travel of C. Mann to Gothenburg – 2.5 days (Participation in the March 2013 ROOTHz progress meeting)
WP6 IAB Missions 962.61 €Travel of N. Alexander to Gothenburg – 2.5 days (Participation in the March 2013 ROOTHz progress meeting)
WP6 IAB Missions 672.87 €Travel of R. Appleby Gothenburg – 2.5 days (Participation in the March 2013 ROOTHz progress meeting)
WP6 Travels to external laboratories
753.35 €Travel of J.F. Millithaler to Montpellier – 6 days (measurement campaign May 2013)
WP6 Travels to ROOTHz meetings
1,203.33 €Travel of J. Mateos to Lille – 3.5 days (Participation in the June 2013 ROOTHz progress meeting)
WP6 Travels to ROOTHz meetings
654.09 € Travel of I. Iñiguez to Lille – 2.5 days (Participation in the June 2013 ROOTHz progress meeting)
WP6 Travels to ROOTHz meetings
826.09 € Travel of S. Pérez to Lille – 2.5 days (Participation in the June 2013 ROOTHz progress meeting)
WP6 IAB Missions 218.27 €Travel of C. Mann to Lille – 2.5 days (Participation in the June 2013 ROOTHz progress meeting)
WP6 IAB Missions 560.39 €Travel of N. Alexander to Lille – 1.5 days (Participation in the June 2013 ROOTHz progress meeting)
Total Other direct costs (MGT) 13,902.12 €
Other (D)
WP Item description Amount Explanations
WP5 Personnel costs (OTHER) 1,606.19 € Salary of J. Mateos (0.5 person.month = 60 hours)
WP5 Personnel costs (OTHER) 1,708.33 € Salary of T. González (0.4 person.month = 50 hours)
WP5 Personnel costs (OTHER) 732.44 € Salary of B. G. Vasallo (0.2 person.month = 30 hours)
WP5 Personnel costs (OTHER) 997.99 € Salary of I. Iñiguez (0.4 person.month = 50 hours)
Total Personnel costs (OTHER) 5,044.95 €
3rd Year and Final Report on Project Management and Use of Resources p 15 of 34
WP5 Travels to conferences 1,289.42 €
Travel of J. Mateos to Amsterdam, Netherland – 6 days (Participation in the European Microwave Week. THz workshop organization and ROOTHz presentation, October 2012)
WP5 Travels to conferences 601,56 €Travel of J.F. Millithaler to Valladolid, Spain – 3 days (Participation in the CDE’2013 conference, February 2013)
WP5 Travels to conferences 3,393.29 €Travel of J. Mateos to Kyoto, Japan – 8 days (Participation in the OTST’2013 conference. Invited talk on the results of ROOTHz, April 2013)
Total other direct costs (OTHER) 5,284.27 €
TOTAL DIRECT COSTS 103,467.45 € USAL Last 18 months
TOTAL DIRECT COSTS 299.582.65 € USAL TOTAL PROJECT
In the initial ROOTHz proposal, an amount of 17.820 € was incorrectly budgeted at USAL for audit
costs; the total budget of USAL is below 375 k€ and such an audit is not necessary. These funds, together
with 2.000 € that were supposed to be dedicated to informatics and office consumables (which were not
necessary) have been moved to cover in part the travel costs, that were increased due to extension of the
project and the frequent plenary meetings, and also to extend 6 months the PostDoc contract of J. F.
Millithaler in order to reach the end of ROOTHz. Both the personnel effort dedicated to the project and the
spending has exceeded the initial previsions, but they have been covered with internal resources. This
demonstrates the commitment of USAL with the ROOTHz project, together with the fact that USAL had
requested only for 70% of the expected RTD costs (lower than the maximum allowed EU contribution of
75%) in order to reduce the total budget.
3rd Year and Final Report on Project Management and Use of Resources p 16 of 34
Table 3.2.1 Major Direct costs for Beneficiary 2 (UNIMAN) for Year 1
RTD/Innovation (A)
WP Item description Amount Explanations
WP2 Personnel costs (RTD) 20,014.98 € Salary of PhD student Yasaman Alimi (11.5 person.month = 1581.5 hours)
WP2 Personnel costs (RTD) 20,067.49 € Salary of PhD student Linqing Zhang (10 person.month = 1377 hours)
WP2 Personnel costs (RTD) 6,698.18 € Salary of A. M. Song (1 person.month = 138 hours)
WP2 Personnel costs (RTD) 4853.76 € Salary of A. Rezazadeh (0.7 person.month = 100 hours)
WP2 Personnel costs (RTD) 2,160.74 € Salary of M. Halsall (0.4 person.month = 54 hours)
WP3 Personnel costs (RTD) 2,683.01 € Salary of PhD student Yasaman Alimi (1.5 person.month = 212 hours)
WP3 Personnel costs (RTD) 2,630.49 € Salary of PhD student Linqing Zhang (1.3 person.month = 180.5 hours)
WP3 Personnel costs (RTD) 2,135.65 € Salary of A. M. Song (0.3 person.month = 44 hours)
WP3 Personnel costs (RTD) 2,523.95 € Salary of A. Rezazadeh (0.4 person.month = 52 hours)
WP3 Personnel costs (RTD) 1,672.41 € Salary of M. Halsall (0.3 person.month = 41.5 hours)
Total Personnel costs (RTD) 65,440.65 €
WP3 Equipment 34,799.42 € THz laser system
WP3 Travel 553.37 € THz experiment at FELBE (April 2010, L. Zhang)
WP2 & WP3
Consumables 4,571.21 € Consumables for laser parts and cleanroom chemicals and metals, etc.
Total Other direct costs (RTD) 39,924.00 €
Management (C)
WP Item description Amount Explanations
WP6 Personnel costs (MGT) 321.16 € Salary of M. Halsall (0.1 person.month = 8 hours)
Total Personnel costs (MGT) 321.26 €
WP6 Travels to ROOTHz meetings
390.96 € A. Song travel to ROOTHz kick-off meeting, Salamanca,14-16 Jan 2010
WP6 Travels to ROOTHz meetings
346.93 € A. Rezazadeh travel to ROOTHz kick-off meeting, Salamanca,14-16 Jan 2010
WP6 Travels to ROOTHz meetings
539.00 € M. Halsall travel to ROOTHz kick-off meeting, Salamanca,14-16 Jan 2010
3rd Year and Final Report on Project Management and Use of Resources p 17 of 34
WP6 IAB member visit to UNIMAN
448.68 € Travel of C. Mann to Manchester on 28 June 2010
WP6 IAB member visit to UNIMAN
215.60 € Travel of Roger Appleby to Manchester on 12 July 2010
WP6 Travels to ROOTHz meetings
445.50 € Travel of A. Song to Gothenburg for ROOTHz progress meeting, 9-11 Sept 2010
WP6 Travels to ROOTHz meetings
686.62 € Travel of L. Zhang to Gothenburg for ROOTHz progress meeting, 9-12 Sept 2010
WP6 Travels to ROOTHz meetings
598.51 € Travel of Y. Alimi to Gothenburg for ROOTHz progress meeting, 9-12 Sept 2010
Total Other direct costs (MGT) 3,671.80 €
Other (D)
WP Item description Amount Explanations
WP5 Personnel costs (OTHER)
39.85 € Salary of M. Halsall (0.01 person.month = 1 hours)
Total Personnel costs (OTHER) 39.85 €
WP5 Other meetings 129.65 € Local meetings costs with collaborators (including those with IAB members) that are exclusively related to ROOTHz
Total Other direct costs (OTHER)
129.65 €
TOTAL DIRECT COSTS 109,527.20 € UNIMAN Year 1
3rd Year and Final Report on Project Management and Use of Resources p 18 of 34
Table 3.2.2 Major Direct costs for Beneficiary 2 (UNIMAN) for Year 2
RTD/Innovation (A)
WP Item description Amount Explanations
WP2 Personnel costs (RTD) 12,318.40 €Salary of PhD student Yasaman Alimi (6.3 person.month = 863 hours)
WP2 Personnel costs (RTD) 16,584.08 €Salary of PhD student Linqing Zhang (8.5 person.month = 1091 hours)
WP2 Personnel costs (RTD) 7,270.47 € Salary of Dr Yi Luo (1.6 person.month = 210 hours)
WP3 Personnel costs (RTD) 2,799.94 € Salary of A. M. Song (0.3 person months = 44 hours)
WP3 Personnel costs (RTD) 2,799.94 € Salary of A. Rezazadeh (0.3 person months = 44 hours)
WP3 Personnel costs (RTD) 11,090.85 €Salary of PhD student Yasaman Alimi (5.7 person.month = 777 hours)
WP3 Personnel costs (RTD) 5,837.11 €Salary of PhD student Linqing Zhang (3 person.month = 384 hours)
WP4 Personnel costs (RTD) 1,590.88 € Salary of A. M. Song (0.2 person months = 25 hours)
WP4 Personnel costs (RTD) 1,654.51 € Salary of A. Rezazadeh (0.2 person months = 26 hours)
Total Personnel costs (RTD) 61,946.18 €
WP3 Equipment Maintenance 6,214.53 € Maintenance costs of electron microscope
WP3 Software License costs 1,436.88 € HFSS License costs
WP3 Consumables 300.83 € Purchase of digital hotplate
WP3 Consumables 348.31 € Equipment Maintenance Costs
WP3 Consumables 609.54 € Purchase of Quartz photomask
WP2 & WP3
Consumables 3,293.72 €Consumables for laser parts and cleanroom chemicals and metals, etc
WP3 Travel 110.48 € Experiment in Leeds, Nov 24 (A. Song)
Total Other direct costs (RTD) 12,314.29 €
Management (C)
WP Item description Amount Explanations
WP6 Personnel costs (MGT) 159.10 € Salary of M. Halsall (0.02 person.month = 3 hours)
WP6 Personnel costs (MGT) 127.27 € Salary of A. Rezazadeh (0.02 person months = 2 hours)
Total Personnel costs (MGT) 286.37 €
WP6 Travels to ROOTHz meetings, Brussels
979.00 € ROOTHz 1st yr review meeting, Brussels, Belgium, Jan 25-27 (A. Song, A. Rezazadeh, M. Halsall)
WP6 Travels to ROOTHz meetings, Lille
499.29 € ROOTHz Project meeting, Lille, France, June 30-July 1 (A. Song)
3rd Year and Final Report on Project Management and Use of Resources p 19 of 34
WP6 Travels to ROOTHz meetings, Lille
1,125.12 € ROOTHz Project meeting, Lille, France, June 30-July 1 (A. Rezazadeh)
WP6 Travels to ROOTHz meetings, Lille
366.47 € ROOTHz Project meeting, Lille, France, June 30-July 1 (M. Halsall)
WP6 Travels to ROOTHz meetings, Lille
426.84 € ROOTHz Project meeting, Lille, France, June 30-July 1 (C. Balocco)
WP6 Travel to ROOTHz meetings, Gothenburg
327.45 € Project meeting in Gothenburg, 9th – 10th Sep (A. Song)
WP6 Local Arrangement for ROOTHz meeting, Manchester
968.70 € ROOTHz project meeting Manchester 13 Oct (meals for all partners)
WP6 Other Local Meeting 155.65 € Local meetings costs with collaborators that are exclusively related to ROOTHz
Total Other direct costs (MGT) 4,521.07 €
Other (D)
WP Item description Amount Explanations
WP5 Personnel costs (OTHER) 127.27 € Salary of A.Song (0.02 person.month = 2 hours)
WP5 Personnel costs (OTHER) 265.16 € Salary of M. Halsall (0.04 person.month = 5 hours)
Total Personnel costs (OTHER) 392.43 €
WP5 Travel to conferences 1,126.09 €International Conference on Solid-State and Integrated Circuit Technology, Shanghai, Oct 31- Nov 9 2010 (bill processed in Jan 2011, A. Song)
WP5 Travel to conferences 866.51 € Semiconductor Technology International Conference March 13-18, 2011, Shanghai (A. Song)
WP5 Travel to conferences 3,068.92 €EDISON17 conference August 8 to 12, 2011 at the University of California, Santa Barbara (A. Song)
WP5 Travel to conferences 448.55 € 6th European Microwave Integrated Circuits (EuMIC) Conference October 10-12 Manchester (A. Song)
WP5 Travel to conferences 164.88 € UK semiconductor conference Sheffield July 6-7, 2011 (L. Zhang)
WP5 Travel to conferences 165.00 € UK semiconductor conference Sheffield July 6-7, 2011 (Y. Alimi)
WP5 Travel to conferences 96.56 € UK semiconductor conference Sheffield July 6-7, 2011 (A. Song)
WP5 Travel to conferences 2,164.88 €IRMMW-THz 2011 Houston Texas October 2-7, 2011 (L. Zhang)
Total Other direct costs (OTHER)
8,101.39 €
TOTAL DIRECT COSTS 86,303.05 € UNIMAN Year 2
3rd Year and Final Report on Project Management and Use of Resources p 20 of 34
Table 3.2.3 Major Direct costs for Beneficiary 2 (UNIMAN) for Year 3
RTD/Innovation (A)
WP Item description Amount Explanations
3 Personnel costs (RTD) 370 € Salary of A. M. Song (6 hours)
4 Personnel costs (RTD) 309 € Salary of A. M. Song (5 hours)
3 Personnel costs (RTD) 375 € Salary of A. Rezazadeh (6 hours)
4 Personnel costs (RTD) 313 € Salary of A. Rezazadeh (5 hours)
2 Personnel costs (RTD) 10,267 € Salary of PhD student Yasaman Alimi (1173 hours)
3 Personnel costs (RTD) 16,010 € Salary of PhD student Yasaman Alimi (1829 hours)
2 Personnel costs (RTD) 9,920 € Salary of PhD student Linqing Zhang (1202 hours)
3 Personnel costs (RTD) 16,357 € Salary of PhD student Linqing Zhang (1982 hours)
Total personnel costs (RTD) 53,921 €
2,3 Travel costs 171 €Experiment in Leeds, UK (Aimin Song and Linqing Zhang) 10/07/12
2 Travel costs 140 €Visit to Glasgow University, Scotland 01/10/12 to 05/10/12
(Aimin Song)
3 Subsistence costs 55 €Meeting with Students 23/3/12 (Aimin Song, Zhang Linqing, Yasaman Alimi)
3 Subsistence costs 28 €Meeting with Students 18/7/12 (Aimin Song, Zhang Linqing, Yasaman Alimi)
2,3 Subsistence costs 206 €Catering for servicing company engineers and academic visitors for RooTHz
2,3 Small equipment costs 6,348 € Agilent high power SMU, cable and Calibration
2,3 Other direct costs 1,050 € Miscellaneous delivery charges
3 Equipment depreciation correction
-29,829 €Correction to P1 equipment claim – only the depreciated amount should have been claimed (per auditor)
3 Equipment depreciation costs
11,974 €Correction to P2 equipment claim – only the depreciated amount should have been claimed (per auditor)
3 Equipment depreciation costs 18,003 € Period 3 depreciation charges for THz laser system
2,3 Consumables 1,973 € Gases and chemicals used during period
2,3 Small equipment costs 4,704 € Sputtering Targets
2,3 Equipment maintenance costs 12,727 €
Necessary service and maintenance of electron microscope and semiconductor measurement kit
2,3 IT equipment 1,537 € Computer equipment
2,3 Consumables 9,502 €Miscellaneous electronic components purchased during Period 3
2,3 Consumables 4,992 € Miscellaneous Lab consumables purchased during period 3
2,3 Small equipment costs 3,996 € Replacement turbo pump for SEM
3rd Year and Final Report on Project Management and Use of Resources p 21 of 34
2,3 Small equipment costs 4,422 € Semiconductor wafers from IQE
Total other direct costs (RTD) 51,999 €
Management (C)
WP Item description Amount Explanations
6 Personnel costs (MGT) 1,913 € Salary of A.M.Song (31 hours)
6 Personnel costs (MGT) 1,125 € Salary of A.Rezazadeh (18 hours)
Total personnel costs (MGT) 3,038 €
6 Travel to ROOTHZ meetings 425 €EU project meeting in Salamanca, Spain 04/07/12 (Aimin
Song)
6 Travel to ROOTHZ meetings 335 € EU Progress Meeting in Amsterdam, Netherlands 30-31 Oct 2012 (Aimin Song)
6 Travel to ROOTHZ meetings 843 € EU Progress Meeting in Gothenburg, Sweden 11/3/13 - 13/3/13 (Aimin Song)
6 Travel to ROOTHZ meetings 2,295 € 2nd Year review meeting in Brussels, Belgium 05/02/12 to 07/02/12, (Aimin Song, Ali Rezazadeh, Yasaman Alimi)
6 Travel to ROOTHZ meetings 1,126 € EU Project Meeting in Lille, France, 03/06/13 to 04/06/13 (Aimin Song, Zhang Linqing, Yasaman Alimi)
6 Subcontracting 2,803 € UNIAC audit fee
Total Other direct costs (MGT) 7,827 €
Other (D)
WP Item description Amount Explanations
Total Personnel costs (OTHER) 0 €
5 Travel to conferences 971 €2nd Annual World Congress of Nano-S&T, Beijing 22/10/12 to 28/10/12 (Aimin Song)
5 Travel to conferences 1,430 €International conference on Materials for Renewable Energy & Environment (Beijing 20/05/12 - 22/05/12) – Aimin Song
Total Other direct costs (OTHER)
2,401 €
TOTAL DIRECT COSTS 119,186 € UNIMAN Last 18 months
TOTAL DIRECT COSTS 315,016 € UNIMAN TOTAL PROJECT
3rd Year and Final Report on Project Management and Use of Resources p 22 of 34
Table 3.3.1 Major Direct costs for Beneficiary 3 (CNRS) for Year 1
RTD/Innovation (A)
WP Item description Amount Explanations
WP2 Personnel costs (RTD) 18,004.96 € Salary of PhD student – Paul Sangaré (6.05 person.month = 841 hours)
WP2 Personnel costs (RTD) 4,080.12 € Salary of M. Francois (0.43 person.month=61 hours))
WP2 Personnel costs (RTD) 5,349.55 € Salary of P. Tilmant (0.99 person.month=127 hours)
WP2 Personnel costs (RTD) 3,426.87 € Salary of A. Leroy (0.77 person.month=62 hours)
WP2 Personnel costs (RTD) 1,372.19 € Salary of D Theron (0.13 person.month=21 hours)
WP3 Personnel costs (RTD) 11,485.30 € Salary of PhD student – Paul Sangaré (3.57 person.month=510 hours)
WP3 Personnel costs (RTD) 7,204.82 € Salary of D. Theron (0.72 person.month=100 hours)
WP3 Personnel costs (RTD) 4,080.16 € Salary of V. Sbrugnera (0.84 person.month=122 hours)
Total Personnel costs (RTD) 55,003.97 €
WP2 Consumables 787.50 € GaN on Silicon Wafers
WP3 Consumables 953.00 € Calibration substrate
WP2 Consumables 782.18 € Clean room consumables
WP3 Equipment 649.53 €Amplifier for sync. Detection, external Mixer 140 220 GHz, antenna hornet 110-170 GHz
Total Other direct costs (RTD) 3,172.21 €
Management (C)
WP Item description Amount Explanations
WP6 Travels to ROOTHz meetings
714.85 € Travel of C. Gaquiere to Salamanca – 2 days (Participation in the ROOTHz kick-off meeting)
WP6 Travels to ROOTHz meetings
751.09 € Travel of G. Ducournau to Salamanca – 2 days (Participation in the ROOTHz kick-off meeting)
WP6 Travels to ROOTHz meetings
598.99 € Travel of C. Gaquiere to Gothenburg – 2 days (Participation in the Sept. 2010 ROOTHz progress meeting)
WP6 Travels to ROOTHz meetings
751.69 € Travel of B. Grimbert to Gothenburg – 2 days (Participation in the Sept. 2010 ROOTHz progress meeting)
Total Other direct costs (MGT) 2,816.62 €
TOTAL DIRECT COSTS 60,992.80 € CNRS Year 1
3rd Year and Final Report on Project Management and Use of Resources p 23 of 34
Table 3.3.2 Major Direct costs for Beneficiary 3 (CNRS) for Year 2
RTD/Innovation (A)
WP Item description Amount Explanations
WP2 Personnel costs (RTD) 4,038.68 € Salary of M. Francois (0.44 person.month =61 hours)
WP2 Personnel costs (RTD) 5,573.02 € Salary of P. Tilmant (1.16 person.month =161 hours)
WP2 Personnel costs (RTD) 973.31 € Salary of D. Theron (0.09 person.month =13 hours)
WP2 Personnel costs (RTD) 3,877.20 € Salary of A. Leroy (0.59 person.month =82 hours)
WP3 Personnel costs (RTD) 32,462.60 € Salary of P. Sangaré (9.82 person.month =1365 hours)
WP3 Personnel costs (RTD) 27,892.90 € Salary of V. Brandli (6.88 person.month=956 hours)
WP3 Personnel costs (RTD) 3,917.55 € Salary of D. Theron (0.38 person.month=53 hours)
WP3 Personnel costs (RTD) 3,935.56 € Salary of V. Sbrugnera (1.14 person.month=158 hours)
Total Personnel costs (RTD) 82,670.82 €
WP2, WP3 & WP4
Consumables 60,949.16 € Clean room consumables
WP3 Equipment 6,449.82 €Tripler 590-610 GHz, corrugated feedhorn WR-5.1, 2 Amplifiers Farrandiv 75/110 GHz
Total Other direct costs (RTD) 67,398.98 €
Management (C)
WP Item description Amount Explanations
WP6 Travels to ROOTHz meetings
240.43 € Travel of C. Gaquiere to Brussels – 2 days (Participation in the 1st Year review meeting)
WP6 Travels to ROOTHz meetings
240.43 € Travel of G. Ducournau to Brussels – 2 days (Participation in the 1st Year review meeting)
WP6 Travels to ROOTHz meetings
242.82 € Travel of P. Sangaré to Brussels – 2 days (Participation in the 1st Year review meeting)
WP6 Meeting organization 1,153.51 € Meals for Jul. 2011 ROOTHz progress meeting
Total Other direct costs (MGT) 1,877.19 €
Other (D)
WP Item description Amount Explanations
WP5 Travels to conferences 336.45 € Travel of P. Sangaré to Brest, France – 4 days
WP5 Travels to conferences 572.90 € Travel of C. Gaquiere to Brest, France – 4 days
WP5 Travels to conferences 1,006.96 €Travel of C. Gaquiere to Manchester, UK – 5 days (Participation in the European Microwave Week)
Total other direct costs (OTHER) 1,916.31 €
TOTAL DIRECT COSTS 153,863.30 € CNRS Year 2
3rd Year and Final Report on Project Management and Use of Resources p 24 of 34
Table 3.3.3 Major Direct costs for Beneficiary 3 (CNRS) for Year 2
RTD/Innovation (A)
WP Item description Amount Explanations
WP2 Personnel costs (RTD) 4,071.00 € Salary of M. François (0.48 person.month =66 hours)
WP2 Personnel costs (RTD) 2,668.00 € Salary of P. Tilmant (0.44 person.month = 61 hours)
WP2 Personnel costs (RTD) 3,912.00 € Salary of A. Leroy (0.48 person.month =66 hours)
WP3 Personnel costs (RTD) 1,198.00 € Salary of V. Sbrugnera (0.24 person.month =33 hours)
WP3 Personnel costs (RTD) 31,921.00 € Salary of P. Sangaré (12.58 person.month =1 736 hours)
WP3 Personnel costs (RTD) 12,251.00 € Salary of V. Brandli (3.77 person.month = 520 hours)
Total Personnel costs (RTD) 56,021.00 €
WP3 Equipment 9,670.00 €
Amplifier (1784 €), external mixer 140 220 GHz (1306 €), antenna horn 110-170 Ghz (547 €), tripler 590-610 GHz (2843 €), corrugated feedhorn WR-5.1 (789 €), 2 amplifiers Farrandiv 75/110 Ghz (2401 €)
WP3 Consumables 6,593.00 € Consumables for THz imaging bench
Total Other direct costs (RTD) 16,263.00 €
Management (C)
WP Item description Amount Explanations
WP6 Travels to ROOTHz meetings
474.00 €2nd year review at Brussels - 06-07/02/2012 – 2 people (G. Ducournau ; P. Sangaré)
WP6 Travels to ROOTHz meetings
234.00 €2nd year review at Brussels - 06-07/02/2012 – 1 person - (C. Gaquiere)
WP6 Travels to ROOTHz meetings
638.00 €Progress meeting at Salamanca, Spain - 02-03/07/2012 – 1 person (G. Ducournau)
WP6 Travels to ROOTHz meetings
704.00 €Progress meeting at Salamanca, Spain - 02-03/07/2012 - 1 person (C. Gaquiere)
WP6 Travels to ROOTHz meetings
980.00 €Progress meeting at Gothenburg, Sweden - 11-13/03/2013 – 1 person (G. Ducournau)
Total Other direct costs (MGT) 3,030.00 €
Other (D)
WP Item description Amount Explanations
WP5 Travels to conferences 2,411.00 €IMS2012 Conference - Montreal – Canada – 16- 22/06/2012 – 1 person – (C. Gaquiere)
WP5 Travels to conferences 4,488.00 €IRMMW-THZ 2012 Conference – Wollongong - Australia - 21-29/09/2012 – 1 person – (P. Sangaré)
WP5 Travels to conferences 956.00 €European Microwave week 2012 – Amsterdam - Netherlands - 28-3/10/2012 – 1 person - (C. Gaquiere)
3rd Year and Final Report on Project Management and Use of Resources p 25 of 34
Total other direct costs (OTHER)
7,855.00 €
TOTAL DIRECT COSTS 83,169.00 € CNRS Last 18 months
TOTAL DIRECT COSTS 298,024.00 € CNRS TOTAL PROJECT
3rd Year and Final Report on Project Management and Use of Resources p 26 of 34
Table 3.3.4 Major Direct costs for Beneficiary 3 Third party (USTL) for Year 1
RTD/Innovation (A)
WP Item description Amount Explanations
WP2 Personnel costs (RTD) 5,921.85 € Salary of C. Gaquiere (0.65 person.month = 90 hours)
WP2 Personnel costs (RTD) 12,831.51 € Salary of B. Grimbert (1.71 person.month=243 hours)
WP2 Personnel costs (RTD) 6,661.88 € Salary of G. Ducournau (1.14 person.month = 158 hours)
WP3 Personnel costs (RTD) 3,048.01 € Salary of C. Gaquiere (0.33 person.month=47 hours)
WP3 Personnel costs (RTD) 3,633.50 € Salary of G. Ducournau (0.60 person.month=87 hours)
Total Personnel costs (RTD) 32,096.75 €
Other (D)
WP Item description Amount Explanations
WP6 Personnel costs (OTHER)
435.43 € Salary of C. Gaquiere (0.05 person.month = 7 hours)
Total Other direct costs (OTHER)
435.43 €
TOTAL DIRECT COSTS 32,532.18 € USTL Year 1
3rd Year and Final Report on Project Management and Use of Resources p 27 of 34
Table 3.3.5 Major Direct costs for Beneficiary 3 Third party (USTL) for Year 2
RTD/Innovation (A)
WP Item description Amount Explanations
WP2 Personnel costs (RTD) 10,485.60€ Salary of C. Gaquiere (0.95 person.month =132 hours)
WP2 Personnel costs (RTD) 6,962.70€ Salary of B. Grimbert (0.91 person.month =126 hours)
WP3 Personnel costs (RTD) 8,912.76€ Salary of C. Gaquiere (0.81 person.month =113 hours)
WP3 Personnel costs (RTD) 17,564.67€ Salary of G. Ducournau (2.40 person.month=334 hours)
WP3 Personnel costs (RTD) 1,983.95€ Salary of P. Delemotte (0.24 person.month =33 hours)
Total Personnel costs (RTD) 45,909.68 €
Management (C)
WP Item description Amount Explanations
WP6 Personnel costs (MGT) 1,048.56 € Salary of C. Gaquiere (0.01 person.month =14 hours)
Total Personnel costs (MGT) 1,048.56 €
Other (D)
WP Item description Amount Explanations
WP5 Personnel costs (MGT) 4,194.24€ Salary of C. Gaquiere (0.38 person.month =53 hours)
WP5 Personnel costs (RTD) 1,280.79€ Salary of G. Ducournau (0.17 person.month =24 hours)
Total Personnel costs (OTHER)
5,475.03 €
TOTAL DIRECT COSTS 52,433.27 € USTL Year 2
3rd Year and Final Report on Project Management and Use of Resources p 28 of 34
Table 3.3.6 Major Direct costs for Beneficiary 3 Third party (USTL) for Year 3
RTD/Innovation (A)
WP Item description Amount Explanations
WP2 Personnel costs (RTD) 14,406.00 € Salary of B. Grimbert (1.71 person.month = 236 hours)
WP3 Personnel costs (RTD) 24,295.00 € Salary of C. Gaquiere (2.01 person.month = 278 hours)
WP3 Personnel costs (RTD) 20,008.00 € Salary of G. Ducournau (2.57 personmonth =355hours)
WP4 Personnel costs (RTD) 27,758.00 € Salary of C. Gaquiere (2.29 person.month = 316 hours)
WP4 Personnel costs (RTD) 14,442.00 € Salary of G. Ducournau (1.86 personmonth =257hours)
Total Personnel costs (RTD) 100,909.00 €
Management (C)
WP Item description Amount Explanations
WP6 Personnel costs (MGT) 6,982.00 € Salary of C. Gaquiere (0.58 person.month =80 hours)
WP6 Personnel costs (MGT) 4,475.00 € Salary of C. Ducournau (0.58 person.month =80 hours)
Total Personnel costs (MGT) 11,457.00 €
Other (D)
WP Item description Amount Explanations
WP5 Personnel costs (OTH) 6,376.00 € Salary of C. Gaquiere (0.53 person.month =73 hours)
WP5 Personnel costs (OTH) 4,086.00 € Salary of G. Ducournau (0.53 personmonth =73 hours)
Total Personnel costs (OTHER)
10,462.00 €
TOTAL DIRECT COSTS 122,828.00 € USTL Last 18 months
TOTAL DIRECT COSTS 207,793.00 € USTL TOTAL PROJECT
The use of budget has exceeded the grant allocated by the EC. The CNRS and the USTL have covered
any additional expenses until the end of the project. Accordingly, no contribution is requested for the USTL in
the third period.
3rd Year and Final Report on Project Management and Use of Resources p 29 of 34
Table 3.4.1 Major Direct costs for Beneficiary 4 (CHAL) for Year 1
RTD/Innovation (A)
WP Item description Amount Explanations
WP2 Personnel costs (RTD) 14,378.00 € Salary of PhD student Andreas Westlund (2.9 person.month = 400 hours)
WP2 Personnel costs (RTD) 27,674.00 € Salary of Per-Åke Nilsson (3.7 person.month =517 hours)
WP2 Personnel costs (RTD) 11,560.00 € Salary of J. Grahn (1.1 person.month = 159 hours)
WP2 Personnel costs (RTD) 9,123.00 € Salary of Huan Zhao (1.7 person.month = 240 hours)
WP3 Personnel costs (RTD) 3,307.00 € Salary of PhD student Andreas Westlund (0.7 person.month = 92 hours)
WP3 Personnel costs (RTD) 3,739.00 € Salary of Giuseppe Moschetti (1.0 person.month = 134 hours)
Total Personnel costs (RTD) 69,781.00 €
WP2 Material 8,332.00 € InP epilayers from IQE
WP2 Transportation costs 195.00 € DHL deliveries
WP2 Clean room costs 25,400.00 € Chalmers clean room
WP3 Material analysis 1,146.00 € SIMS analysis, Probion Analysis
Total Other direct costs (RTD) 35,073.00 €
Management (C)
WP Item description Amount Explanations
WP6 Personnel costs (MGT) 2,908.00 € Salary of J. Grahn (0.3 person.month = 40 hours)
Total Personnel costs (MGT) 2,908.00 €
WP6 Travels to ROOTHz meetings
381.00 € Travel of J. Grahn to Salamanca – 3 days (Participation in the ROOTHz kick-off meeting)
WP6 Travels to ROOTHz meetings
800.00 € Travel of P. A. Nilsson to Salamanca – 3 days (Participation in the ROOTHz kick-off meeting)
WP6 Meeting organization 2,297.00 € Progress meeting Göteborg, coffee, lunch, dinner
Total Other direct costs (MGT) 3,478.00 €
Other (D)
WP Item description Amount Explanations
WP5 Personnel costs (OTHER) 2,908.00 € Salary of J. Grahn (0.3 person.month = 40 hours)
Total Personnel costs (OTHER) 2,908.00 €
WP5 Travels to conferences 2,246.00 € Per-Åke Nilsson, IPRM 2010, Japan. 6 days.
The IPRM visit gave us the opportunity to learn the
3rd Year and Final Report on Project Management and Use of Resources p 30 of 34
latest results in processing technology for devices to be developed in the ROOTHz-project, especially slot-diode-like devices.
Part of the conference time was used for meetings with other ROOTHz project participants for project discussions.
Total Other direct costs (OTHER) 2,246.00 €
TOTAL DIRECT COSTS 116,394.00 € CHAL Year 1
3rd Year and Final Report on Project Management and Use of Resources p 31 of 34
Table 3.4.2 Major Direct costs for Beneficiary 4 (CHAL) for Year 2
RTD/Innovation (A)
WP Item description Amount Explanations
WP2 Personnel costs (RTD) 32,533.00 €Salary of PhD student Andreas Westlund (7.9 person.month = 1100 hours)
WP2 Personnel costs (RTD) 11,759.00 €Salary of Per-Åke Nilsson (1.4 person.month =200 hours)
WP2 Personnel costs (RTD) 4,475.00 € Salary of J. Grahn (1.0 person.month = 140 hours)
WP2 Personnel costs (RTD) 6,477.00 € Salary of Huan Zhao (1.2 person.month = 163 hours)
WP2 Personnel costs (RTD) 9,474.00 €Salary of PhD student Giuseppe Moschetti (2.1 person month=300 hours)
WP3 Personnel costs (RTD) 7,394.00 €Salary of PhD student Andreas Westlund (1.8 person.month = 250 hours)
WP3 Personnel costs (RTD) 6,505.00 €Salary of PhD student Giuseppe Moschetti (1.5 person.month = 206 hours)
WP4 Personnel costs (RTD) 5,472.00 €Salary of PhD student Andreas Westlund (1.3 person.month = 185 hours)
Total Personnel costs (RTD) 84,089.00 €
WP2 Material 3,036.00 €Material from Intelligent Epitaxy and Farnell Components
WP2 Transportation costs 424.00 € Transportation cost, DHL etc
WP2 Clean room costs 22,175.00 € Chalmers clean room
WP3 Material 1,941.00 € Material from Advanced Circuits
Total Other direct costs (RTD) 27,576.00 €
Management (C)
WP Item description Amount Explanations
WP6 Personnel costs (MGT) 1,279.00 € Salary of J. Grahn (0.3 person.month = 40 hours)
WP6 Personnel costs (MGT) 941.00 €Salary of Per-Åke Nilsson (0.1 person.month =16 hours)
Total Personnel costs (MGT) 2,220.00 €
WP6 Travels to ROOTHz meetings
975.00 € Travel of J. Grahn to Brussels – 2 days (Participation in the ROOTHz project meeting)
WP6 Travels to ROOTHz meetings
963.00 € Travel of P-Å Nilsson to Brussels – 2 days (Participation in the ROOTHz project meeting)
WP6 Travels to ROOTHz meetings
889.00 € Travel of H Zhao to Brussels – 2 days (Participation in the ROOTHz project meeting)
WP6 Travels to ROOTHz meetings
934.00 € Travel of A Westlund to Brussels – 2 days (Participation in the ROOTHz project meeting)
3rd Year and Final Report on Project Management and Use of Resources p 32 of 34
WP6 Travels to ROOTHz meetings
268.00 € Travel of J. Grahn to Lille – 2 days (Participation in the ROOTHz project meeting)
WP6 Travels to ROOTHz meetings
750.00 € Travel of A Westlund to Lille – 2 days (Participation in the ROOTHz project meeting)
WP6 Travels to ROOTHz meetings
758.00 € Travel of G Moschetti to Lille – 2 days (Participation in the ROOTHz project meeting)
WP6 Travels to ROOTHz meetings
518.00 € Travel of J. Grahn to Manchester – 2 days (Participation in the ROOTHz project meeting)
WP6 Travels to ROOTHz meetings
445.00 € Travel of G Moschetti to Manchester – 2 days (Participation in the ROOTHz project meeting)
WP6 Travels to ROOTHz meetings
546.00 € Travel of P-Å Nilsson to Manchester – 2 days (Participation in the ROOTHz project meeting)
WP6 Travels to ROOTHz meetings
416.00 € Travel of A Westlund to Manchester – 2 days (Participation in the ROOTHz project meeting)
Total Other direct costs (MGT) 7,462.00 €
Other (D)
WP Item description Amount Explanations
WP5 Personnel costs (OTHER) 1,279.00 € Salary of J. Grahn (0.3 person.month = 40 hours)
WP5 Personnel costs (OTHER) 588.00 €Salary of Per-Åke Nilsson (0.1 person.month =10 hours)
WP5 Personnel costs (OTHER) 1,183.00 €Salary of PhD student Andreas Westlund (0.3 person.month = 40hours)
Total Personnel costs (OTHER) 3,050.00 €
WP5 Travels to conferences 1,156.00 € Huan Zhao, MBE 2011 Conference, France, 5 days
WP5 Travels to conferences 1,659.00 € Andreas Westlund, WOCSDICE 2011, Italy, 6 days
WP5 Printing cost 109.00 € Poster for conference
Total Other direct costs (OTHER)
2,924.00 €
TOTAL DIRECT COSTS 127,321.00 € CHAL Year 2
3rd Year and Final Report on Project Management and Use of Resources p 33 of 34
Table 3.4.3 Major Direct costs for Beneficiary 4 (CHAL) for Year 3
RTD/Innovation (A)
WP Item description Amount Explanations
WP2 Personnel cost 607.00 € Salary Jan Grahn (0.2 person month = 21 hours)
WP2 Personnel cost 30,554,00 €Salary Per-Åke Nilsson (3.6 person month = 504 hours)
WP2 Personnel cost 12.418,00 €Salary Andreas Westlund (4.2 person month = 592 hours)
WP2 Personnel cost 5.071,00 €Salary Giuseppe Moschetti (1.0 person month = 135 hours)
WP3 Personnel cost 26.219,00 €Salary Andreas Westlund (8.9 person month = 1250 hours)
WP3 Personnel cost 607,00 € Salary Jan Grahn (0.2 person month = 21 hours)
WP4 Personnel cost 636,00 € Salary Jan Grahn (0.2 person month = 22 hours)
WP4 Personnel cost 10.488,00 €Salary Andreas Westlund (3.6 person month = 500 hours)
Total Personnel costs (RTD) 86.600,00 €
WP2 Material 4.744,00 € Epitaxial layers, etc.
WP2 Clean room cost 22.766,00 € Clean room cost Chalmers
WP3 Transport cost 204,00 € Transport cost, DHL etc.
WP3 Travel cost 1.505,00 € Andreas Westlund, measurements in Lille, 9 days
WP3 Travel cost 1.310,00 € Andreas Westlund, measurements in Lille, 5 days
Total Other direct costs (RTD) 30.529,00 €
Management (C)
WP Item description Amount Explanations
WP6 Personnel cost 2.313,00 € Salary Jan Grahn (0.6 person month = 80 hours)
WP6 Personnel cost 839,00 €Salary Andreas Westlund (0.3 person month = 40 hours)
Total Personnel costs (MGT) 3.152,00 €
WP6 Meeting cost 2.325,00 € Meeting cost, project meeting in Göteborg
WP6 Travel cost 284,00 € Jan Grahn, project meeting, Brussels, 2 days
WP6 Travel cost 256,00 € Andreas Westlund, project meeting, Brussels, 2 days
WP6 Travel cost 1.092,00 € Jan Grahn, project meeting, Salamanca, 3 days
WP6 Travel cost 727,00 €Andreas Westlund, project meeting, Salamanca, 3 days
WP6 Travel cost 409,00 € Jan Grahn, project meeting, Amsterdam, 1 day
3rd Year and Final Report on Project Management and Use of Resources p 34 of 34
WP6 Travel cost 1.177,00 €Andreas Westlund, project meeting, Amsterdam, 1 day
WP6 Travel cost 496,00 € Jan Grahn, project meeting, Lille, 1 day
WP6 Travel cost 474,00 € Andreas Westlund, project meeting, Lille, 1 day
Total Other direct costs (MGT) 7.240,00 €
Other (D)
WP Item description Amount Explanations
WP5 Personnel cost 2.892,00 € Salary Jan Grahn (0.7 person month = 100 hours)
WP5 Personnel cost 3.146,00 €Salary Andreas Westlund (1.1 person month = 150 hours)
Total Personnel costs (OTHER) 6.038,00 €
WP5 Printing cost 1.244,00 € Posters for conferences, reports etc.
WP5 Travels to conferences 870,00 €Andreas Westlund, GHz symposium, Stockholm, 3 days
WP5 Travels to conferences 2.830,00 €Andreas Westlund, IPRM 2012, San Francisco, 7 days
Total Other direct costs (OTHER) 4.944,00 €
TOTAL DIRECT COSTS 138.505,00 € CHAL Last 18 months
TOTAL DIRECT COSTS 382.220,00 € CHAL TOTAL PROJECT
4. FINANCIAL STATEMENTS - FORMS C AND SUMMARY FINANCIAL REPORT
The financial statement from each beneficiary will be provided online through the NEF webpage via the
EC Research Participant Portal.