40
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA DIVISION DE OBRAS GERENCIA DE INFRAESTRUCTURA DIVISION DE OBRAS INFORME TECNICO MESUAL OBRA MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO Residente de Obra : ING. MOISES MAMANI APAZA Supervisor de Obra : ING. DINA CAROLINE TAPIA FARFAN 2015 Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza Gerente de Infraestructura Residente de obra

3.pdf

Embed Size (px)

Citation preview

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    INFORME TECNICO MESUAL

    OBRAMEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y

    PEATONAL DE LA CALLE INCA YUPANQUI DE LAASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO

    DEL CUSCO, PROVINCIA DEL CUSCO

    Residente de Obra : ING. MOISES MAMANI APAZA

    Supervisor de Obra : ING. DINA CAROLINE TAPIAFARFAN

    2015

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR YPEATONAL DE LA CALLE INCA YUPANQUI DE LA

    ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DELCUSCO, PROVINCIA DEL CUSCO

    FICHA TECNICA

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    FICHA TECNICACODIGO SNIP 252096

    NOMBRE DEL PROYECTO MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCAYUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DEL CUSCO,

    PROVINCIA DEL CUSCO

    DATOS GENERALES UNIDAD EJECUTORA MUNICIPALIDAD PROVINCIAL DEL CUSCO

    FUNCION 15 TRANSPORTES

    PROGRAMA 36 TRANSPORTE URBANO

    SUB PROGRAMA 74 VIAS URBANAS

    PROYECTO Y/O ACTIVIDAD 004

    META 44

    FUENTE DE FINANCIAMIENTO CANON Y SOBRE CANON

    MODALIDAD DE EJECUCION ADMINISTRACION DIRECTA

    NRO DE RESOLUCION DEAPROVACION DEL EXPEDIENTETECNICO

    RGM-701-GM-MPC-2013

    FECHA DE INICIO 2015-03-09

    TIEMPO DE EJECUCION 300

    FECHA DE CONCLUCION 2016-01-03

    COSTO TOTAL DEL PROYECTO APROBADO

    COSTO DIRECTO : 2,408,070.50

    GASTOS DE SUPERVICION : 52,528.18

    GASTOS DE LIQUIDACION : 11,431.68

    EXPEDIENTE TECNICO : 13,719.63

    COSTO TOTAL : 2,485,750.25

    UBICACION DEPARTAMENTO : CUSCO

    PROVINCIA CUSCO

    DISTRITO CUSCO

    LUGAR APV. AYUDA MUTUA

    AVANCE FISICO PROGRAMADO

    AVANCE FISICO ACUMULADO 20,000.00 .83 %

    AVANCE FISICO MENSUAL 20,000.00 .83 %

    AVANCE FISICO EJECUTADO

    AVANCE FISICO ACUMULADO 104154.48 3.76 %

    AVANCE FISICO MENSUAL 2253.82 .08 %

    AVANCE FINANCIERO

    AVANCE FINANCIEROACUMULADO

    0.0 0.0 %

    AVANCE FINANCIERO MENSUAL 0.0 0.0 %

    INFORMACIO DEL PERSONA QUE ADMINISTRA LA OBRA

    CARGO NOMBRE COLEGIATURA N

    JEFE DE LA DIVISION DESUPERVICION

    ING. OSCAR VILLAGARAY

    SUPERVISOR DE OBRA ING. DINA CAROLINE TAPIA FARFAN 60282

    RESIDENTES DE OBRA ING. MOISES MAMANI APAZA 112705

    ASISTENTE TECNICO ALEXIS ZEA VIZCARRA

    ASISTENTE ADMINISTRATIVO JUAN CARLOS BORNAS

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR YPEATONAL DE LA CALLE INCA YUPANQUI DE LA

    ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DELCUSCO, PROVINCIA DEL CUSCO

    GENERALIDADES

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    A.1 INFORMACION DELPERSONAL Nombre del Residente ING. MOISES MAMANI APAZA

    Nombre del Inspector de Obra ING. DINA CAROLINE TAPIA FARFAN

    A.2 FECHA REPORTADA JUNIO

    A.3 DATOS DEL PROYECTO Unidad Ejecutora MUNICIPALIDAD PROVINCIAL DEL CUSCO

    Nombre de la Obra MEJORAMIENTO DE LA TRANSITABILIDADVEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACIONPROVIVIENDA AYUDA MUTUA, DISTRITODEL CUSCO, PROVINCIA DEL CUSCO

    Monto del Proyecto 2,769,342.25

    Meta 44

    Modalidad de Ejecucion ADMINISTRACION DIRECTA

    Plazo de ejecucion 300 Dias calendarios

    A.4 FINANCIERO Presupuesto Base 2,769,342.25

    Presuspuesto Ejecutado Mes 0.0 0.0 %

    Presupuesto Acumulado 0.0 0.0 %

    Presupuesto Saldo 2,769,342.25 100.00 %

    A.5 VALORIZACIONES Valorizacion Mensual 2,253.82 .08 %

    Valorizacion Acumnulada 104,154.48 3.76 %

    Valorizacion Saldos 2,303,916.00 96.24 %

    A:6 CRONOGRAMA DE OBRA Inicio 2015-03-09

    Programado 300 Dias calendarios

    Dias Ejecutados 113 dias

    A.7 UBICACION Lugar APV. AYUDA MUTUA

    Distrito CUSCO

    Provincia CUSCO

    Departamento CUSCO

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • B ASPECTOS TECNICOS

    B RECURSOS UTILIZADOS

    B.1.1 RECURSOS HUMANOS

    B.1.2 PLANILLA DE TAREOS

    MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    CATEGORIA MUNICIPALIDADDRESIDENTE DE OBRA 0INSPECTOR DE OBRA 0ASISTENTE TECNICO 0ASISTENTE ADMINISTRATIVO 0ASISTENTE DE LIQUIDACION 0ALMACENERO DE OBRA 0TECNICO DE SUELOS 0TOPOGRAFO 0MAESTRO DE OBRA 0OPERARIO 0OFICIAL 0PEON 0GUARDIANES 0 TOTAL 0

    DESCRIPCION ANTERIOR ACTUAL ACUMULADOMUNICIPALIDAD 0.0 0.0 0.0

    TOTAL 0.0 0.0 0.0

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • B.2 RECURSOS DE MAQUINARIA Y EQUIPO

    B.2.1 VALORIZACION DE MAQUINARIA Y EQUIPO

    B.3 AVANCE FISICO

    B.3.1 VALORIZACION DE OBRA

    MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    MAQUINARIA MUNICIPALIDAD

    PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO

    MAQUINARIA PROGRAMADO VALORIZADO % VALORIZADO % VALORIZADO % VALORIZADO %

    MAQUINARIA 0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %

    TOTAL 0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %

    PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO

    VALORIZACION PRESUPUESTO VALORIZADO

    S/.

    % VALORIZADO

    S/.

    % VALORIZADO

    S/.

    % VALORIZADO

    S/.

    %

    COSTO DIRECTO 2,408,070.50 101,900.65 4.23 % 2,253.82 .09 % 104,154.48 4.33 % 2,303,916.00 95.67 %

    COSTO TOTAL 2,769,342.25 117,188.32 4.23 % 2,591.95 .09 % 119,780.28 4.33 % 2,649,561.75 95.67 %

    MAYORESMETRADOS

    0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %

    TOTAL MAYORESMETRADOS

    0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %

    PARTIDAS NUEVAS 156,410.00 80,507.35 51.47 % 7,335.63 4.69 % 87,842.98 56.16 % 68,567.02 43.84 %

    TOTAL PARTIDASNUEVAS

    156,410.00 80,507.35 51.47 % 7,335.63 4.69 % 87,842.98 56.16 % 68,567.02 43.84 %

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • B.3.3 MEMORIA DESCRIPTIVA VALORIZADA

    MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    ITEM DESCRIPTION METRADO COSTO01 OBRAS PROVISIONALES01.01 CARTEL DE OBRA 0.0 0.001.02 ALMACEN Y RESIDENCIA DE OBRA 0.0 0.002 OBRAS PRELIMINARES02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS 0.0 0.002.02 TRAZO, NIVELES Y REPLANTEO 0.0 0.002.03 SEALIZACION Y SEGURIDAD DE OBRA 0.0 0.002.04 LIMPIEZA MANUAL DE TERRENO 0.0 0.002.05 TRANSPORTE DE MATERIALES PARA LA OBRA 0.0 0.003 MOVIMIENTO DE TIERRAS03.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL

    PROCESO DE CONSTRUCCION0.0 0.0

    03.02 NIVELACION DE BUZONES EN GENERAL 0.0 0.003.03 RECONEXIONES DOMICILIARIAS DE AGUA 0.0 0.003.04 RECONEXIONES DOMICILIARIAS DE DESAGUE 0.0 0.003.05 CORTE DE TERRENO A NIVEL DE SUB RASANTE 0.0 0.003.06 EXCAVACION MANUAL 0.0 0.003.07 PERFILADO Y COMPACTADO DE SUB RASANTE EN

    ZONAS DE CORTE0.0 0.0

    03.08 RIEGO 0.0 0.003.09 RELLENO COMPACTADO CON MATERIAL PROPIO 0.0 0.003.10 RELLENO Y COMPACTADO CON MATERIAL PROPIO

    (MANUAL)9.24 430.12

    03.11 TRANSPORTE DE MATERIAL EXCEDENTE MANUAL(C/BUGUIE D=100M)

    10.00 182.50

    03.12 ELIMINACION MATERIAL EXCEDENTE 0.0 0.004 ESTRUCTURA DEL PAVIMENTO04.01 BASE GRANULAR (e=0.20CM)04.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL

    PROCESO DE CONSTRUCCION0.0 0.0

    04.01.02 EXTRACCION Y PREPARACION DE MATERIAL DE BASE 0.0 0.004.01.03 CARGUIO Y TRANSPORTE DE MATERIAL DE BASE

    (Dmax=10KM)0.0 0.0

    04.01.04 EXTENDIDO Y COMPACTADO DE BASE 0.0 0.004.01.05 RIEGO 0.0 0.004.02 LOSA DE RODADURA

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    ITEM DESCRIPTION METRADO COSTO04.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL

    PROCESO DE CONSTRUCCION0.0 0.0

    04.02.02 ENCOFRADO Y DESENCOFRADO EN LOSA DEPAVIMENTO

    0.0 0.0

    04.02.03 ACERO DE TEMPERATURA DE 1/4" 0.0 0.004.02.04 ACERO CORRUGADO G-60 DE 1/2" EN JUNTA

    LONGITUDINAL0.0 0.0

    04.02.05 ACERO DE 3/4" EN JUNTA DE CONTRACCION 0.0 0.004.02.06 ACERO LISO DE 1" EN JUNTA DE DILATACION 0.0 0.004.02.07 CONCRETO F'C=210KG/CM2 0.0 0.004.02.08 CURADO DE LOSA DE CONCRETO 0.0 0.004.02.09 SELLADO DE JUNTAS DE CONTR. Y LONG 0.0 0.004.02.10 SELLADO DE JUNTAS DE DILATACION e=3/4", h=0.15M 0.0 0.004.03 ADOQUINADO04.03.01 SUMINISTRO DE ADOQUINADO DE PIEDRA 0.0 0.004.03.02 COLOCADO DE ADOQUINES DE PIEDRA 0.0 0.004.03.03 SELLADO DE JUNTAS ENTRE ADOQUINES (C, F'C=210

    KG/CM2)0.0 0.0

    05 SARDINELES Y VEREDAS05.01 SARDINELES DE CONCRETO05.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL

    PROCESO DE CONSTRUCCION0.0 0.0

    05.01.02 ENCOFRADO Y DESENCOFRADO DE SARDINELES 0.0 0.005.01.03 CONCRETO F'C=175KG/CM2 0.0 0.005.01.04 CURADO DE CONCRETO 0.0 0.005.01.05 SELLADO DE JUNTAS EN SARDINELES 0.0 0.005.02 VEREDAS05.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL

    PROCESO DE CONSTRUCCION0.0 0.0

    05.02.02 NIVELACION Y COMPACTADO MANUAL 0.0 0.005.02.03 ENCOFRADO Y DESENCOFRADO PARA VEREDAS

    HASTA H=0.20M0.0 0.0

    05.02.04 EMPEDRADO DE 6" 0.0 0.005.02.05 CONCRETO F'C=175KG/CM2 0.0 0.005.02.06 CURADO DE CONCRETO 0.0 0.005.02.07 SUMINISTRO DE LOSETAS DE PIEDRA 0.0 0.005.02.08 COLOCADO DE LOSETAS DE PIEDRA 0.0 0.0

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    ITEM DESCRIPTION METRADO COSTO05.02.09 EMBOQUILLADO ENTRE LOSETAS DE PIEDRA 0.0 0.005.02.10 CURADO DE CONCRETO 0.0 0.006 MUROS DE CONTENCION06.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL

    PROCESO DE CONSTRUCCION0.0 0.0

    06.02 SOLADOS DE 2", MEZCLA 1:12 0.0 0.006.03 ENCOFRADO Y DESENCOFRADO DE MUROS DE

    SOSTENIMIENTO33.50 1,461.60

    06.04 CONCRETO CICLOPEO F'C=140 KG/CM2 + 30% PG 0.0 0.006.05 FILTRO DE GRAVA 0.0 0.006.06 TUBERIA PVC SAL 3" 11.70 179.6006.07 EMBOQUILLADO DE MURO (AREA VISIBLE) C:A 1:5,

    e=0.02M0.0 0.0

    06.08 CURADO DE CONCRETO 0.0 0.006.09 JUNTAS ASFALTICAS 1"X0.06M, 1:4 0.0 0.007 SISTEMA DE EVACUACION DE AGUAS PLUVIALES07.01 SUMIDEROS07.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL

    PROCESO DE CONSTRUCCION0.0 0.0

    07.01.02 NIVELACION Y COMPACTADO MANUAL 0.0 0.007.01.03 EMPEDRADO DE 4" 0.0 0.007.01.04 ENCOFRADO Y DESENCOFRADO NORMAL 0.0 0.007.01.05 ACERO DE REFUERZO G-60 0.0 0.007.01.06 CONCRETO F'C=210KG/CM2 0.0 0.007.01.07 REJILLA SUMIDERO PLAT 2 1/2"x 1/2" C/RIEL 0.0 0.007.01.08 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:5

    e=1.5 CM0.0 0.0

    07.01.09 CURADO DE CONCRETO 0.0 0.007.01.10 JUNTAS ASFALTICAS 1"X0.06M, 1:4 0.0 0.007.01.11 CAMA DE APOYO 0.0 0.007.01.12 TENDIDO DE TUBERIA DE 8" 0.0 0.007.02 CANAL CON TAPAS DE CONCRETO07.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL

    PROCESO DE CONSTRUCCION0.0 0.0

    07.02.02 NIVELACION Y COMPACTADO MANUAL 0.0 0.007.02.03 EMPEDRADO DE 4" 0.0 0.0

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    ITEM DESCRIPTION METRADO COSTO07.02.04 ENCOFRADO Y DESENCOFRADO NORMAL 0.0 0.007.02.05 ACERO DE REFUERZO G-60 0.0 0.007.02.06 CONCRETO F'C = 210 KG/CM2 0.0 0.007.02.07 TAPA DE CONCRETO ARMADO PREFABRICADO 0.0 0.007.02.08 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:5

    e=1.5 CM0.0 0.0

    07.02.09 CURADO DE CONCRETO 0.0 0.008 OBRAS COMPLEMENTARIAS08.01 SEALIZACION08.01.01 SEALES PREVENTIVAS 0.0 0.008.02 DEMARCACION08.02.01 PINTADO DE SARDINELES AL BORDE DE LA VIA 0.0 0.008.02.02 PINTADO DE SEALES EN PISO 0.0 0.008.03 BANCAS08.03.01 BANCAS DE MADERA CON ESTRUCTURA METALICA 0.0 0.008.04 PAPELERA08.04.01 SUMINISTRO E INSTALACION DE CONTENEDOR TIPO

    PAPELERA0.0 0.0

    08.05 ESTRUCTURAS VARIAS08.05.01 BARANDAS METALICAS (SEGN DISEO) 0.0 0.009 CONTROL DE CALIDAD DE LA OBRA09.01 DISEO DE MEZCLAS09.01.01 DISEO DE MEZCLA DE CONCRETO 0.0 0.009.02 PRUEBA DE CONTROL09.02.01 PRUEBA DE DENSIDAD DE CAMPO 0.0 0.009.02.02 ROTURA DE BRIQUETAS 0.0 0.010 INTERVENCION ARQUEOLOGICA10.01 MONITOREO ARQUEOLOGICO 0.0 0.011 MITIGACION DE IMPACTOS11.01 TRATAMIENTO DE AREAS VERDES11.01.01 ACONDICIONAMIENTO DE AREAS VERDES 0.0 0.012 LIMPIEZA DE OBRA

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    ITEM DESCRIPTION METRADO COSTO12.01 LIMPIEZA DE OBRA 0.0 0.0- TOTAL - 2,253.82

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR YPEATONAL DE LA CALLE INCA YUPANQUI DE LA

    ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DELCUSCO, PROVINCIA DEL CUSCO

    RESUMEN DE VALORIZACION GENERAL

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • RESUMEN DE VALORIZACION GENERAL

    MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    ITEM DESCRIPCION PRESUPUESTOPARCIAL

    AVANCEVALORIZADO

    ANTERIOR

    AVANCEVALORIZADOTOTAL JUNIO

    AVANCEACUMULADOTOTAL 2015

    AVANCEPORCENTUAL

    01 MEJORAMIENTO DE LA TRANSITABILIDADVEHICULAR Y PEATONAL DE LA CALLE INCAYUPANQUI DE LA ASOCIACION PROVIVIENDAAYUDA MUTUA, DISTRITO DEL CUSCO,PROVINCIA DEL CUSCO

    2,408,070.50 101,900.65 2,253.82 104,154.47 4.33 %

    COSTO DIRECTO 2,408,070.50 101,900.65 2,253.82 104,154.47 4.33 %

    GASTOS GENERALES 283,591.94 12,000.56 265.43 12,265.99 4.33 %

    GASTOS DE SUPERVICION 52,528.18 2,222.80 49.16 2,271.96 4.33 %

    GASTOS DE EXPEDIENTE TECNICO 13,719.63 580.56 12.84 593.40 4.33 %

    LIQUIDACION DE OBRA 11,431.68 483.75 10.70 494.45 4.33 %

    COSTO TOTAL 2,769,342.25 117,188.32 2,591.95 119,780.27 4.33 %

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO

    DEL CUSCO, PROVINCIA DEL CUSCO

    RESUMEN DE VALORIZACION DE OBRA

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • RESUMEN DE VALORIZACION DE OBRA

    OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA

    AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO

    CORRESPONDIENTE AL MES DE : JUNIO

    MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO

    ITEM VALORIZACION PRESUPUESTO VALORIZADO S/. % VALORIZADO S/. % VALORIZADO S/. % VALORIZADO S/. %

    1 COSTO DIRECTO 2,408,070.50 101,900.65 4.23 % 2,253.82 .09 % 104,154.48 4.33 % 2,303,916.00 95.67 %

    COSTO TOTAL 2,769,342.25 117,188.32 4.23 % 2,591.95 .09 % 119,780.28 4.33 % 2,649,561.75 95.67 %

    2 MAYORES METRADOS 0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %

    TOTAL MAYORES METRADOS 0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %

    3 PARTIDAS NUEVAS 156,410.00 80,507.35 51.47 % 7,335.63 4.69 % 87,842.98 56.16 % 68,567.02 43.84 %

    TOTAL PARTIDAS NUEVAS 156,410.00 80,507.35 51.47 % 7,335.63 4.69 % 87,842.98 56.16 % 68,567.02 43.84 %

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO

    DEL CUSCO, PROVINCIA DEL CUSCO

    VALORIZACION DE OBRA

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • VALORIZACION DE AVANCE DE OBRA PROGRAMADA

    OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA

    AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO

    CORRESPONDIENTE AL MES DE : JUNIO

    MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO

    UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %

    01 OBRAS PROVISIONALES

    01.01 CARTEL DE OBRA UND 2.00 652.12 1,304.24 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 2.00 1,304.24 100.00 %

    01.02 ALMACEN Y RESIDENCIA DE OBRA MES 10.00 150.00 1,500.00 3.00 450.00 30.00 % 0.0 0.0 0.0 % 3.0 450.00 30.00 % 7.00 1,050.00 70.00 %

    02 OBRAS PRELIMINARES

    02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 2,433.44 2,433.44 0.60 1,460.06 60.00 % 0.0 0.0 0.0 % 0.6 1,460.06 60.00 % 0.40 973.38 40.00 %

    02.02 TRAZO, NIVELES Y REPLANTEO M2 7,935.74 .75 5,951.81 7,935.74 5,951.81 100.00 % 0.0 0.0 0.0 % 7935.74 5,951.81 100.00 % 0.0 0.0 0.0 %

    02.03 SEALIZACION Y SEGURIDAD DE OBRA UND 1.00 720.80 720.80 1.00 720.80 100.00 % 0.0 0.0 0.0 % 1.0 720.80 100.00 % 0.0 0.0 0.0 %

    02.04 LIMPIEZA MANUAL DE TERRENO M2 7,935.34 .33 2,618.66 3,752.06 1,238.18 47.28 % 0.0 0.0 0.0 % 3752.06 1,238.18 47.28 % 4,183.28 1,380.48 52.72 %

    02.05 TRANSPORTE DE MATERIALES PARA LA OBRA GLB 1.00 5,000.00 5,000.00 1.00 5,000.00 100.00 % 0.0 0.0 0.0 % 1.0 5,000.00 100.00 % 0.0 0.0 0.0 %

    03 MOVIMIENTO DE TIERRAS

    03.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION

    M2 7,935.74 .54 4,285.30 1,915.98 1,034.63 24.14 % 0.0 0.0 0.0 % 1915.98 1,034.63 24.14 % 6,019.76 3,250.67 75.86 %

    03.02 NIVELACION DE BUZONES EN GENERAL UND 11.00 309.65 3,406.15 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 11.00 3,406.15 100.00 %

    03.03 RECONEXIONES DOMICILIARIAS DE AGUA UND 44.00 283.35 12,467.40 13.00 3,683.55 29.55 % 0.0 0.0 0.0 % 13.0 3,683.55 29.55 % 31.00 8,783.85 70.45 %

    03.04 RECONEXIONES DOMICILIARIAS DE DESAGUE UND 44.00 283.35 12,467.40 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 44.00 12,467.40 100.00 %

    03.05 CORTE DE TERRENO A NIVEL DE SUB RASANTE M3 3,683.40 6.72 24,752.45 336.90 2,263.97 9.15 % 0.0 0.0 0.0 % 336.9 2,263.97 9.15 % 3,346.50 22,488.48 90.85 %

    03.06 EXCAVACION MANUAL M3 873.87 27.05 23,638.18 768.97 20,800.64 88.00 % 0.0 0.0 0.0 % 768.97 20,800.64 88.00 % 104.90 2,837.55 12.00 %

    03.07 PERFILADO Y COMPACTADO DE SUB RASANTE ENZONAS DE CORTE

    M2 5,497.33 4.77 26,222.26 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 26,222.26 100.00 %

    03.08 RIEGO M2 5,497.33 .47 2,583.75 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 2,583.75 100.00 %

    03.09 RELLENO COMPACTADO CON MATERIAL PROPIO M3 489.02 5.05 2,469.55 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 489.02 2,469.55 100.00 %

    03.10 RELLENO Y COMPACTADO CON MATERIAL PROPIO(MANUAL)

    M3 230.58 46.55 10,733.50 204.17 9,504.11 88.55 % 9.24 430.12 4.01 % 213.41 9,934.24 92.55 % 17.17 799.26 7.45 %

    03.11 TRANSPORTE DE MATERIAL EXCEDENTE MANUAL(C/BUGUIE D=100M)

    M3 1,092.34 18.25 19,935.20 363.50 6,633.88 33.28 % 10.00 182.50 .92 % 373.5 6,816.38 34.19 % 718.84 13,118.83 65.81 %

    03.12 ELIMINACION MATERIAL EXCEDENTE M3 5,696.59 15.25 86,873.00 374.00 5,703.50 6.57 % 0.0 0.0 0.0 % 374.0 5,703.50 6.57 % 5,322.59 81,169.49 93.43 %

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO

    UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %

    04 ESTRUCTURA DEL PAVIMENTO

    04.01 BASE GRANULAR (e=0.20CM)

    04.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION

    M2 5,497.33 .54 2,968.56 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 2,968.56 100.00 %

    04.01.02 EXTRACCION Y PREPARACION DE MATERIAL DE BASE M3 1,099.47 8.16 8,971.68 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,099.47 8,971.67 100.00 %

    04.01.03 CARGUIO Y TRANSPORTE DE MATERIAL DE BASE(Dmax=10KM)

    M3 1,374.33 29.04 39,910.54 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,374.33 39,910.54 100.00 %

    04.01.04 EXTENDIDO Y COMPACTADO DE BASE M2 5,497.33 2.47 13,578.41 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 13,578.41 100.00 %

    04.01.05 RIEGO M2 5,497.33 .47 2,583.75 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 2,583.75 100.00 %

    04.02 LOSA DE RODADURA

    04.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION

    M2 5,497.33 .54 2,968.56 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 2,968.56 100.00 %

    04.02.02 ENCOFRADO Y DESENCOFRADO EN LOSA DEPAVIMENTO

    M2 784.10 38.91 30,509.33 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 784.10 30,509.33 100.00 %

    04.02.03 ACERO DE TEMPERATURA DE 1/4" KG 6,257.18 5.56 34,789.92 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 6,257.18 34,789.92 100.00 %

    04.02.04 ACERO CORRUGADO G-60 DE 1/2" EN JUNTALONGITUDINAL

    KG 990.02 5.99 5,930.22 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 990.02 5,930.22 100.00 %

    04.02.05 ACERO DE 3/4" EN JUNTA DE CONTRACCION KG 4,806.14 5.99 28,788.78 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 4,806.14 28,788.78 100.00 %

    04.02.06 ACERO LISO DE 1" EN JUNTA DE DILATACION KG 133.39 6.44 859.03 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 133.39 859.03 100.00 %

    04.02.07 CONCRETO F'C=210KG/CM2 M3 934.55 415.01 387,847.59 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 934.55 387,847.59 100.00 %

    04.02.08 CURADO DE LOSA DE CONCRETO M2 5,497.33 .85 4,672.73 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 4,672.73 100.00 %

    04.02.09 SELLADO DE JUNTAS DE CONTR. Y LONG M 4,805.95 3.38 16,244.11 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 4,805.95 16,244.11 100.00 %

    04.02.10 SELLADO DE JUNTAS DE DILATACION e=3/4", h=0.15M M 77.00 7.69 592.13 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 77.00 592.13 100.00 %

    04.03 ADOQUINADO

    04.03.01 SUMINISTRO DE ADOQUINADO DE PIEDRA M2 5,497.33 147.00 808,107.50 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 808,107.50 100.00 %

    04.03.02 COLOCADO DE ADOQUINES DE PIEDRA M2 5,497.33 18.48 101,590.66 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 101,590.66 100.00 %

    04.03.03 SELLADO DE JUNTAS ENTRE ADOQUINES (C, F'C=210KG/CM2)

    M2 5,497.33 21.20 116,543.40 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 116,543.40 100.00 %

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO

    UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %

    05 SARDINELES Y VEREDAS

    05.01 SARDINELES DE CONCRETO

    05.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION

    M2 149.27 .54 80.61 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 149.27 80.61 99.99 %

    05.01.02 ENCOFRADO Y DESENCOFRADO DE SARDINELES M2 149.27 38.91 5,808.10 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 149.27 5,808.10 100.00 %

    05.01.03 CONCRETO F'C=175KG/CM2 M3 89.56 406.02 36,363.15 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 89.56 36,363.15 100.00 %

    05.01.04 CURADO DE CONCRETO M 995.15 .39 388.11 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 995.15 388.11 100.00 %

    05.01.05 SELLADO DE JUNTAS EN SARDINELES M 149.40 9.27 1,384.94 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 149.40 1,384.94 100.00 %

    05.02 VEREDAS

    05.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION

    M2 931.88 .54 503.22 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 931.88 503.22 100.00 %

    05.02.02 NIVELACION Y COMPACTADO MANUAL M2 931.88 1.47 1,369.86 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 931.88 1,369.86 100.00 %

    05.02.03 ENCOFRADO Y DESENCOFRADO PARA VEREDAS HASTAH=0.20M

    M 1,014.15 20.18 20,465.55 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,014.15 20,465.55 100.00 %

    05.02.04 EMPEDRADO DE 6" M2 931.88 22.31 20,790.24 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 931.88 20,790.24 100.00 %

    05.02.05 CONCRETO F'C=175KG/CM2 M3 69.89 406.02 28,376.74 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 69.89 28,376.74 100.00 %

    05.02.06 CURADO DE CONCRETO M2 931.88 .85 792.10 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 931.88 792.10 100.00 %

    05.02.07 SUMINISTRO DE LOSETAS DE PIEDRA M2 86.00 94.50 8,127.00 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 86.00 8,127.00 100.00 %

    05.02.08 COLOCADO DE LOSETAS DE PIEDRA M2 86.00 18.51 1,591.86 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 86.00 1,591.86 100.00 %

    05.02.09 EMBOQUILLADO ENTRE LOSETAS DE PIEDRA M2 86.00 27.38 2,354.68 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 86.00 2,354.68 100.00 %

    05.02.10 CURADO DE CONCRETO M2 86.00 .85 73.10 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 86.00 73.10 100.00 %

    06 MUROS DE CONTENCION

    06.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION

    M2 225.67 .54 121.86 225.67 121.86 100.00 % 0.0 0.0 0.0 % 225.67 121.86 100.00 % 0.0 0.0 0.0 %

    06.02 SOLADOS DE 2", MEZCLA 1:12 M2 225.67 14.51 3,274.47 225.67 3,274.47 100.00 % 0.0 0.0 0.0 % 225.67 3,274.47 100.00 % 0.0 0.0 0.0 %

    06.03 ENCOFRADO Y DESENCOFRADO DE MUROS DESOSTENIMIENTO

    M2 371.26 43.63 16,198.07 226.27 9,872.16 60.95 % 33.50 1,461.60 9.02 % 259.77002 11,333.77 69.97 % 111.49 4,864.31 30.03 %

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO

    UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %

    06.04 CONCRETO CICLOPEO F'C=140 KG/CM2 + 30% PG M3 224.45 241.84 54,280.99 37.11 8,974.68 16.53 % 0.0 0.0 0.0 % 37.11 8,974.68 16.53 % 187.34 45,306.30 83.47 %

    06.05 FILTRO DE GRAVA M3 3.96 93.53 370.38 2.78 260.01 70.20 % 0.0 0.0 0.0 % 2.78 260.01 70.20 % 1.18 110.37 29.80 %

    06.06 TUBERIA PVC SAL 3" M 93.75 15.35 1,439.06 78.40 1,203.44 83.63 % 11.70 179.60 12.48 % 90.1 1,383.04 96.11 % 3.65 56.03 3.89 %

    06.07 EMBOQUILLADO DE MURO (AREA VISIBLE) C:A 1:5,e=0.02M

    M2 313.11 27.34 8,560.43 155.29 4,245.63 49.60 % 0.0 0.0 0.0 % 155.29 4,245.63 49.60 % 157.82 4,314.80 50.40 %

    06.08 CURADO DE CONCRETO M2 371.26 .85 315.57 323.28 274.79 87.08 % 0.0 0.0 0.0 % 323.28 274.79 87.08 % 47.98 40.78 12.92 %

    06.09 JUNTAS ASFALTICAS 1"X0.06M, 1:4 M 77.80 5.09 396.00 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 77.80 396.00 100.00 %

    07 SISTEMA DE EVACUACION DE AGUAS PLUVIALES

    07.01 SUMIDEROS

    07.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION

    M2 15.40 .54 8.32 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 15.40 8.32 99.95 %

    07.01.02 NIVELACION Y COMPACTADO MANUAL M2 15.40 1.47 22.64 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 15.40 22.64 99.99 %

    07.01.03 EMPEDRADO DE 4" M2 15.40 15.88 244.55 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 15.40 244.55 100.00 %

    07.01.04 ENCOFRADO Y DESENCOFRADO NORMAL M2 22.40 26.35 590.24 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 22.40 590.24 100.00 %

    07.01.05 ACERO DE REFUERZO G-60 KG 292.72 6.09 1,782.66 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 292.72 1,782.66 100.00 %

    07.01.06 CONCRETO F'C=210KG/CM2 M3 5.13 415.01 2,129.00 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5.13 2,129.00 100.00 %

    07.01.07 REJILLA SUMIDERO PLAT 2 1/2"x 1/2" C/RIEL M2 10.60 1,218.34 12,914.40 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 10.60 12,914.40 100.00 %

    07.01.08 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:5 e=1.5CM

    M2 32.80 20.73 679.94 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 32.80 679.94 100.00 %

    07.01.09 CURADO DE CONCRETO M 32.80 .39 12.79 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 32.80 12.79 100.02 %

    07.01.10 JUNTAS ASFALTICAS 1"X0.06M, 1:4 M 44.00 5.09 223.96 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 44.00 223.96 100.00 %

    07.01.11 CAMA DE APOYO M3 12.03 139.84 1,682.28 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 12.03 1,682.28 100.00 %

    07.01.12 TENDIDO DE TUBERIA DE 8" M 240.50 100.91 24,268.86 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 240.50 24,268.86 100.00 %

    07.02 CANAL CON TAPAS DE CONCRETO

    07.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION

    M2 599.49 .54 323.72 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 599.49 323.72 100.00 %

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO

    UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %

    07.02.02 NIVELACION Y COMPACTADO MANUAL M2 599.49 1.47 881.25 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 599.49 881.25 100.00 %

    07.02.03 EMPEDRADO DE 4" M2 599.49 15.88 9,519.90 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 599.49 9,519.90 100.00 %

    07.02.04 ENCOFRADO Y DESENCOFRADO NORMAL M2 1,005.57 26.35 26,496.77 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,005.57 26,496.77 100.00 %

    07.02.05 ACERO DE REFUERZO G-60 KG 2,543.90 6.09 15,492.35 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 2,543.90 15,492.35 100.00 %

    07.02.06 CONCRETO F'C = 210 KG/CM2 M3 179.94 415.01 74,676.90 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 179.94 74,676.90 100.00 %

    07.02.07 TAPA DE CONCRETO ARMADO PREFABRICADO UND 996.00 24.50 24,402.00 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 996.00 24,402.00 100.00 %

    07.02.08 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:5 e=1.5CM

    M2 1,398.81 20.73 28,997.33 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,398.81 28,997.33 100.00 %

    07.02.09 CURADO DE CONCRETO M2 1,398.81 .85 1,188.99 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,398.81 1,188.99 100.00 %

    08 OBRAS COMPLEMENTARIAS

    08.01 SEALIZACION

    08.01.01 SEALES PREVENTIVAS UND 14.00 526.09 7,365.26 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 14.00 7,365.26 100.00 %

    08.02 DEMARCACION

    08.02.01 PINTADO DE SARDINELES AL BORDE DE LA VIA M 1,990.30 6.37 12,678.21 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,990.30 12,678.21 100.00 %

    08.02.02 PINTADO DE SEALES EN PISO M2 49.50 6.51 322.25 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 49.50 322.25 100.00 %

    08.03 BANCAS

    08.03.01 BANCAS DE MADERA CON ESTRUCTURA METALICA UND 5.00 1,477.90 7,389.50 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5.00 7,389.50 100.00 %

    08.04 PAPELERA

    08.04.01 SUMINISTRO E INSTALACION DE CONTENEDOR TIPOPAPELERA

    UND 4.00 639.11 2,556.44 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 4.00 2,556.44 100.00 %

    08.05 ESTRUCTURAS VARIAS

    08.05.01 BARANDAS METALICAS (SEGN DISEO) M 190.00 196.62 37,357.80 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 190.00 37,357.80 100.00 %

    09 CONTROL DE CALIDAD DE LA OBRA

    09.01 DISEO DE MEZCLAS

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO

    UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %

    09.01.01 DISEO DE MEZCLA DE CONCRETO UND 2.00 350.00 700.00 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 2.00 700.00 100.00 %

    09.02 PRUEBA DE CONTROL

    09.02.01 PRUEBA DE DENSIDAD DE CAMPO UND 20.00 35.00 700.00 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 20.00 700.00 100.00 %

    09.02.02 ROTURA DE BRIQUETAS UND 25.00 25.00 625.00 10.00 250.00 40.00 % 0.0 0.0 0.0 % 10.0 250.00 40.00 % 15.00 375.00 60.00 %

    10 INTERVENCION ARQUEOLOGICA

    10.01 MONITOREO ARQUEOLOGICO MES 10.00 2,992.83 29,928.30 3.00 8,978.49 30.00 % 0.0 0.0 0.0 % 3.0 8,978.49 30.00 % 7.00 20,949.81 70.00 %

    11 MITIGACION DE IMPACTOS

    11.01 TRATAMIENTO DE AREAS VERDES

    11.01.01 ACONDICIONAMIENTO DE AREAS VERDES M2 365.00 14.56 5,314.40 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 365.00 5,314.40 100.00 %

    12 LIMPIEZA DE OBRA

    12.01 LIMPIEZA DE OBRA M2 7,935.74 .80 6,348.59 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 7,935.74 6,348.59 100.00 %

    COSTO DIRECTO 2,408,070.50

    101,900.65 4.23 % 2,253.82 .09 % 104,154.48 4.33 % 2,303,916.00

    95.67 %

    GASTOS GENERALES 283,591.94 12,000.56 265.43 12,265.99 271,325.97

    GASTOS DE SUIPERVICION 52,528.18 2,222.80 49.16 2,271.96 50,256.22

    GASTOS DE LIQUIDACION 11,431.68 483.75 10.70 494.45 10,937.23

    GASTOS DE EXPEDIENTE TECNICO 13,719.63 580.56 12.84 593.40 13,126.23

    GASTOS TOTAL PRESUPUESTO 2,769,342.25

    117,188.32 4.23 % 2,591.95 .09 % 119,780.28 4.33 % 2,649,561.75

    95.67 %

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO

    UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO

    DEL CUSCO, PROVINCIA DEL CUSCO

    METRADO DIARIO DE AVANCE DE OBRA PROGRAMADA

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • METRADO DIARIO DE AVANCE DE OBRA PROGRAMADA

    OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA

    AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO

    CORRESPONDIENTE AL MES DE : JUNIO

    MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES

    ACUMULADO

    SALDO

    01 OBRAS PROVISIONALES

    01.01 CARTEL DE OBRA UND 2.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 2.00

    01.02 ALMACEN Y RESIDENCIA DEOBRA

    MES 10.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 3.00 7.00

    02 OBRAS PRELIMINARES

    02.01 MOVILIZACION YDESMOVILIZACION DE EQUIPOS

    GLB 1.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.60 0.40

    02.02 TRAZO, NIVELES Y REPLANTEO M2 7935.74 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 7,935.74 0.0

    02.03 SEALIZACION Y SEGURIDAD DEOBRA

    UND 1.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 1.00 0.0

    02.04 LIMPIEZA MANUAL DE TERRENO M2 7935.34 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 3,752.06 4,183.28

    02.05 TRANSPORTE DE MATERIALESPARA LA OBRA

    GLB 1.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 1.00 0.0

    03 MOVIMIENTO DE TIERRAS

    03.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION

    M2 7935.74 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 1,915.98 6,019.76

    03.02 NIVELACION DE BUZONES ENGENERAL

    UND 11.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 11.00

    03.03 RECONEXIONES DOMICILIARIASDE AGUA

    UND 44.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 13.00 31.00

    03.04 RECONEXIONES DOMICILIARIASDE DESAGUE

    UND 44.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 44.00

    03.05 CORTE DE TERRENO A NIVEL DESUB RASANTE

    M3 3683.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 336.90 3,346.50

    03.06 EXCAVACION MANUAL M3 873.87 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 768.97 104.90

    03.07 PERFILADO Y COMPACTADO DESUB RASANTE EN ZONAS DECORTE

    M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33

    03.08 RIEGO M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33

    03.09 RELLENO COMPACTADO CONMATERIAL PROPIO

    M3 489.02 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 489.02

    03.10 RELLENO Y COMPACTADO CONMATERIAL PROPIO (MANUAL)

    M3 230.58 9.24 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 9.24 213.41 17.17

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES

    ACUMULADO

    SALDO

    03.11 TRANSPORTE DE MATERIALEXCEDENTE MANUAL (C/BUGUIED=100M)

    M3 1092.34 10.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 10.00 373.50 718.84

    03.12 ELIMINACION MATERIALEXCEDENTE

    M3 5696.59 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 374.00 5,322.59

    04 ESTRUCTURA DEL PAVIMENTO

    04.01 BASE GRANULAR (e=0.20CM)

    04.01.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION

    M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33

    04.01.02 EXTRACCION Y PREPARACIONDE MATERIAL DE BASE

    M3 1099.47 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,099.47

    04.01.03 CARGUIO Y TRANSPORTE DEMATERIAL DE BASE (Dmax=10KM)

    M3 1374.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,374.33

    04.01.04 EXTENDIDO Y COMPACTADO DEBASE

    M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33

    04.01.05 RIEGO M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33

    04.02 LOSA DE RODADURA

    04.02.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION

    M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33

    04.02.02 ENCOFRADO Y DESENCOFRADOEN LOSA DE PAVIMENTO

    M2 784.1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 784.10

    04.02.03 ACERO DE TEMPERATURA DE1/4"

    KG 6257.18 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 6,257.18

    04.02.04 ACERO CORRUGADO G-60 DE1/2" EN JUNTA LONGITUDINAL

    KG 990.02 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 990.02

    04.02.05 ACERO DE 3/4" EN JUNTA DECONTRACCION

    KG 4806.14 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 4,806.14

    04.02.06 ACERO LISO DE 1" EN JUNTA DEDILATACION

    KG 133.39 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 133.39

    04.02.07 CONCRETO F'C=210KG/CM2 M3 934.55 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 934.55

    04.02.08 CURADO DE LOSA DECONCRETO

    M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33

    04.02.09 SELLADO DE JUNTAS DE CONTR.Y LONG

    M 4805.95 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 4,805.95

    04.02.10 SELLADO DE JUNTAS DEDILATACION e=3/4", h=0.15M

    M 77.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 77.00

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES

    ACUMULADO

    SALDO

    04.03 ADOQUINADO

    04.03.01 SUMINISTRO DE ADOQUINADODE PIEDRA

    M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33

    04.03.02 COLOCADO DE ADOQUINES DEPIEDRA

    M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33

    04.03.03 SELLADO DE JUNTAS ENTREADOQUINES (C, F'C=210KG/CM2)

    M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33

    05 SARDINELES Y VEREDAS

    05.01 SARDINELES DE CONCRETO

    05.01.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION

    M2 149.27 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 149.27

    05.01.02 ENCOFRADO Y DESENCOFRADODE SARDINELES

    M2 149.27 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 149.27

    05.01.03 CONCRETO F'C=175KG/CM2 M3 89.56 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 89.56

    05.01.04 CURADO DE CONCRETO M 995.15 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 995.15

    05.01.05 SELLADO DE JUNTAS ENSARDINELES

    M 149.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 149.40

    05.02 VEREDAS

    05.02.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION

    M2 931.88 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 931.88

    05.02.02 NIVELACION Y COMPACTADOMANUAL

    M2 931.88 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 931.88

    05.02.03 ENCOFRADO Y DESENCOFRADOPARA VEREDAS HASTA H=0.20M

    M 1014.15 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,014.15

    05.02.04 EMPEDRADO DE 6" M2 931.88 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 931.88

    05.02.05 CONCRETO F'C=175KG/CM2 M3 69.89 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 69.89

    05.02.06 CURADO DE CONCRETO M2 931.88 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 931.88

    05.02.07 SUMINISTRO DE LOSETAS DEPIEDRA

    M2 86.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 86.00

    05.02.08 COLOCADO DE LOSETAS DEPIEDRA

    M2 86.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 86.00

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES

    ACUMULADO

    SALDO

    05.02.09 EMBOQUILLADO ENTRELOSETAS DE PIEDRA

    M2 86.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 86.00

    05.02.10 CURADO DE CONCRETO M2 86.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 86.00

    06 MUROS DE CONTENCION

    06.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION

    M2 225.67 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 225.67 0.0

    06.02 SOLADOS DE 2", MEZCLA 1:12 M2 225.67 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 225.67 0.0

    06.03 ENCOFRADO Y DESENCOFRADODE MUROS DE SOSTENIMIENTO

    M2 371.26 33.50 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 33.50 259.77 111.49

    06.04 CONCRETO CICLOPEO F'C=140KG/CM2 + 30% PG

    M3 224.45 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 37.11 187.34

    06.05 FILTRO DE GRAVA M3 3.96 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 2.78 1.18

    06.06 TUBERIA PVC SAL 3" M 93.75 11.70 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 11.70 90.10 3.65

    06.07 EMBOQUILLADO DE MURO (AREAVISIBLE) C:A 1:5, e=0.02M

    M2 313.11 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 155.29 157.82

    06.08 CURADO DE CONCRETO M2 371.26 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 323.28 47.98

    06.09 JUNTAS ASFALTICAS 1"X0.06M,1:4

    M 77.8 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 77.80

    07 SISTEMA DE EVACUACION DEAGUAS PLUVIALES

    07.01 SUMIDEROS

    07.01.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION

    M2 15.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 15.40

    07.01.02 NIVELACION Y COMPACTADOMANUAL

    M2 15.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 15.40

    07.01.03 EMPEDRADO DE 4" M2 15.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 15.40

    07.01.04 ENCOFRADO Y DESENCOFRADONORMAL

    M2 22.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 22.40

    07.01.05 ACERO DE REFUERZO G-60 KG 292.72 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 292.72

    07.01.06 CONCRETO F'C=210KG/CM2 M3 5.13 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5.13

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES

    ACUMULADO

    SALDO

    07.01.07 REJILLA SUMIDERO PLAT 2 1/2"x1/2" C/RIEL

    M2 10.6 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 10.60

    07.01.08 TARRAJEO CONIMPERMEABILIZANTE MEZCLA1:5 e=1.5 CM

    M2 32.8 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 32.80

    07.01.09 CURADO DE CONCRETO M 32.8 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 32.80

    07.01.10 JUNTAS ASFALTICAS 1"X0.06M,1:4

    M 44.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 44.00

    07.01.11 CAMA DE APOYO M3 12.03 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 12.03

    07.01.12 TENDIDO DE TUBERIA DE 8" M 240.5 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 240.50

    07.02 CANAL CON TAPAS DECONCRETO

    07.02.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION

    M2 599.49 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 599.49

    07.02.02 NIVELACION Y COMPACTADOMANUAL

    M2 599.49 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 599.49

    07.02.03 EMPEDRADO DE 4" M2 599.49 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 599.49

    07.02.04 ENCOFRADO Y DESENCOFRADONORMAL

    M2 1005.57 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,005.57

    07.02.05 ACERO DE REFUERZO G-60 KG 2543.9 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 2,543.90

    07.02.06 CONCRETO F'C = 210 KG/CM2 M3 179.94 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 179.94

    07.02.07 TAPA DE CONCRETO ARMADOPREFABRICADO

    UND 996.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 996.00

    07.02.08 TARRAJEO CONIMPERMEABILIZANTE MEZCLA1:5 e=1.5 CM

    M2 1398.81 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,398.81

    07.02.09 CURADO DE CONCRETO M2 1398.81 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,398.81

    08 OBRAS COMPLEMENTARIAS

    08.01 SEALIZACION

    08.01.01 SEALES PREVENTIVAS UND 14.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 14.00

    08.02 DEMARCACION

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES

    ACUMULADO

    SALDO

    08.02.01 PINTADO DE SARDINELES ALBORDE DE LA VIA

    M 1990.3 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,990.30

    08.02.02 PINTADO DE SEALES EN PISO M2 49.5 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 49.50

    08.03 BANCAS

    08.03.01 BANCAS DE MADERA CONESTRUCTURA METALICA

    UND 5.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5.00

    08.04 PAPELERA

    08.04.01 SUMINISTRO E INSTALACION DECONTENEDOR TIPO PAPELERA

    UND 4.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 4.00

    08.05 ESTRUCTURAS VARIAS

    08.05.01 BARANDAS METALICAS (SEGNDISEO)

    M 190.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 190.00

    09 CONTROL DE CALIDAD DE LAOBRA

    09.01 DISEO DE MEZCLAS

    09.01.01 DISEO DE MEZCLA DECONCRETO

    UND 2.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 2.00

    09.02 PRUEBA DE CONTROL

    09.02.01 PRUEBA DE DENSIDAD DECAMPO

    UND 20.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 20.00

    09.02.02 ROTURA DE BRIQUETAS UND 25.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 10.00 15.00

    10 INTERVENCION ARQUEOLOGICA

    10.01 MONITOREO ARQUEOLOGICO MES 10.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 3.00 7.00

    11 MITIGACION DE IMPACTOS

    11.01 TRATAMIENTO DE AREASVERDES

    11.01.01 ACONDICIONAMIENTO DE AREASVERDES

    M2 365.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 365.00

    12 LIMPIEZA DE OBRA

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES

    ACUMULADO

    SALDO

    12.01 LIMPIEZA DE OBRA M2 7935.74 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 7,935.74

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO

    DEL CUSCO, PROVINCIA DEL CUSCO

    VALORZACION DE MAYORES METRADOS

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • VALORIZACION DE MAYORES METRADOS

    OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA

    AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO

    CORRESPONDIENTE AL MES DE : JUNIO

    MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO

    UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %

    COSTO DIRECTO 0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %

    GASTOS GENERALES 0.0 0.0 0.0 0.0 0.0

    GASTOS DE SUIPERVICION 0.0 0.0 0.0 0.0 0.0

    GASTOS DE LIQUIDACION 0.0 0.0 0.0 0.0 0.0

    GASTOS DE EXPEDIENTE TECNICO 0.0 0.0 0.0 0.0 0.0

    GASTOS TOTAL PRESUPUESTO 0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO

    DEL CUSCO, PROVINCIA DEL CUSCO

    METRADO DIARIO DEMAYORES METRADOS

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • METRADO DIARIO DE MAYORES METRADOS

    OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA

    AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO

    CORRESPONDIENTE AL MES DE : JUNIO

    MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES

    ACUMULADO

    SALDO

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO

    DEL CUSCO, PROVINCIA DEL CUSCO

    VALORIZACION DE PARTIDAS NUEVAS

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • VALORIZACION DE PARTIDAS NUEVAS

    OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA

    AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO

    CORRESPONDIENTE AL MES DE : JUNIO

    MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO

    UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %

    06.10 CONCRETO CICLOPEO FC=140 +50%PG M3 500.0 312.82 156,410.00 257.36 80,507.35 51.47 % 23.45 7,335.63 4.69 % 280.81 87,842.98 56.16 % 219.19 68,567.02 43.84 %

    COSTO DIRECTO 156,410.00 80,507.35 51.47 % 7,335.63 4.69 % 87,842.98 56.16 % 68,567.02 43.84 %

    GASTOS GENERALES 0.0 0.0 0.0 0.0 0.0

    GASTOS DE SUIPERVICION 0.0 0.0 0.0 0.0 0.0

    GASTOS DE LIQUIDACION 0.0 0.0 0.0 0.0 0.0

    GASTOS DE EXPEDIENTE TECNICO 0.0 0.0 0.0 0.0 0.0

    GASTOS TOTAL PRESUPUESTO 156,410.00 80,507.35 51.47 % 7,335.63 4.69 % 87,842.98 56.16 % 68,567.02 43.84 %

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO

    DEL CUSCO, PROVINCIA DEL CUSCO

    METRADO DIARIO DE PARTIDAS NUEVAS

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra

  • METRADO DIARIO DE PARTIDAS NUEVAS

    OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA

    AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO

    CORRESPONDIENTE AL MES DE : JUNIO

    MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA

    DIVISION DE OBRAS

    CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES

    ACUMULADO

    SALDO

    06.10 CONCRETO CICLOPEO FC=140+50%PG

    M3 500.0 23.45 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 23.45 280.81 219.19

    Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza

    Gerente de Infraestructura Residente de obra