MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
INFORME TECNICO MESUAL
OBRAMEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y
PEATONAL DE LA CALLE INCA YUPANQUI DE LAASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO
Residente de Obra : ING. MOISES MAMANI APAZA
Supervisor de Obra : ING. DINA CAROLINE TAPIAFARFAN
2015
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR YPEATONAL DE LA CALLE INCA YUPANQUI DE LA
ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DELCUSCO, PROVINCIA DEL CUSCO
FICHA TECNICA
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
FICHA TECNICACODIGO SNIP 252096
NOMBRE DEL PROYECTO MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCAYUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DEL CUSCO,
PROVINCIA DEL CUSCO
DATOS GENERALES UNIDAD EJECUTORA MUNICIPALIDAD PROVINCIAL DEL CUSCO
FUNCION 15 TRANSPORTES
PROGRAMA 36 TRANSPORTE URBANO
SUB PROGRAMA 74 VIAS URBANAS
PROYECTO Y/O ACTIVIDAD 004
META 44
FUENTE DE FINANCIAMIENTO CANON Y SOBRE CANON
MODALIDAD DE EJECUCION ADMINISTRACION DIRECTA
NRO DE RESOLUCION DEAPROVACION DEL EXPEDIENTETECNICO
RGM-701-GM-MPC-2013
FECHA DE INICIO 2015-03-09
TIEMPO DE EJECUCION 300
FECHA DE CONCLUCION 2016-01-03
COSTO TOTAL DEL PROYECTO APROBADO
COSTO DIRECTO : 2,408,070.50
GASTOS DE SUPERVICION : 52,528.18
GASTOS DE LIQUIDACION : 11,431.68
EXPEDIENTE TECNICO : 13,719.63
COSTO TOTAL : 2,485,750.25
UBICACION DEPARTAMENTO : CUSCO
PROVINCIA CUSCO
DISTRITO CUSCO
LUGAR APV. AYUDA MUTUA
AVANCE FISICO PROGRAMADO
AVANCE FISICO ACUMULADO 20,000.00 .83 %
AVANCE FISICO MENSUAL 20,000.00 .83 %
AVANCE FISICO EJECUTADO
AVANCE FISICO ACUMULADO 104154.48 3.76 %
AVANCE FISICO MENSUAL 2253.82 .08 %
AVANCE FINANCIERO
AVANCE FINANCIEROACUMULADO
0.0 0.0 %
AVANCE FINANCIERO MENSUAL 0.0 0.0 %
INFORMACIO DEL PERSONA QUE ADMINISTRA LA OBRA
CARGO NOMBRE COLEGIATURA N
JEFE DE LA DIVISION DESUPERVICION
ING. OSCAR VILLAGARAY
SUPERVISOR DE OBRA ING. DINA CAROLINE TAPIA FARFAN 60282
RESIDENTES DE OBRA ING. MOISES MAMANI APAZA 112705
ASISTENTE TECNICO ALEXIS ZEA VIZCARRA
ASISTENTE ADMINISTRATIVO JUAN CARLOS BORNAS
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR YPEATONAL DE LA CALLE INCA YUPANQUI DE LA
ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DELCUSCO, PROVINCIA DEL CUSCO
GENERALIDADES
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
A.1 INFORMACION DELPERSONAL Nombre del Residente ING. MOISES MAMANI APAZA
Nombre del Inspector de Obra ING. DINA CAROLINE TAPIA FARFAN
A.2 FECHA REPORTADA JUNIO
A.3 DATOS DEL PROYECTO Unidad Ejecutora MUNICIPALIDAD PROVINCIAL DEL CUSCO
Nombre de la Obra MEJORAMIENTO DE LA TRANSITABILIDADVEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACIONPROVIVIENDA AYUDA MUTUA, DISTRITODEL CUSCO, PROVINCIA DEL CUSCO
Monto del Proyecto 2,769,342.25
Meta 44
Modalidad de Ejecucion ADMINISTRACION DIRECTA
Plazo de ejecucion 300 Dias calendarios
A.4 FINANCIERO Presupuesto Base 2,769,342.25
Presuspuesto Ejecutado Mes 0.0 0.0 %
Presupuesto Acumulado 0.0 0.0 %
Presupuesto Saldo 2,769,342.25 100.00 %
A.5 VALORIZACIONES Valorizacion Mensual 2,253.82 .08 %
Valorizacion Acumnulada 104,154.48 3.76 %
Valorizacion Saldos 2,303,916.00 96.24 %
A:6 CRONOGRAMA DE OBRA Inicio 2015-03-09
Programado 300 Dias calendarios
Dias Ejecutados 113 dias
A.7 UBICACION Lugar APV. AYUDA MUTUA
Distrito CUSCO
Provincia CUSCO
Departamento CUSCO
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
B ASPECTOS TECNICOS
B RECURSOS UTILIZADOS
B.1.1 RECURSOS HUMANOS
B.1.2 PLANILLA DE TAREOS
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
CATEGORIA MUNICIPALIDADDRESIDENTE DE OBRA 0INSPECTOR DE OBRA 0ASISTENTE TECNICO 0ASISTENTE ADMINISTRATIVO 0ASISTENTE DE LIQUIDACION 0ALMACENERO DE OBRA 0TECNICO DE SUELOS 0TOPOGRAFO 0MAESTRO DE OBRA 0OPERARIO 0OFICIAL 0PEON 0GUARDIANES 0 TOTAL 0
DESCRIPCION ANTERIOR ACTUAL ACUMULADOMUNICIPALIDAD 0.0 0.0 0.0
TOTAL 0.0 0.0 0.0
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
B.2 RECURSOS DE MAQUINARIA Y EQUIPO
B.2.1 VALORIZACION DE MAQUINARIA Y EQUIPO
B.3 AVANCE FISICO
B.3.1 VALORIZACION DE OBRA
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
MAQUINARIA MUNICIPALIDAD
PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO
MAQUINARIA PROGRAMADO VALORIZADO % VALORIZADO % VALORIZADO % VALORIZADO %
MAQUINARIA 0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %
TOTAL 0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %
PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO
VALORIZACION PRESUPUESTO VALORIZADO
S/.
% VALORIZADO
S/.
% VALORIZADO
S/.
% VALORIZADO
S/.
%
COSTO DIRECTO 2,408,070.50 101,900.65 4.23 % 2,253.82 .09 % 104,154.48 4.33 % 2,303,916.00 95.67 %
COSTO TOTAL 2,769,342.25 117,188.32 4.23 % 2,591.95 .09 % 119,780.28 4.33 % 2,649,561.75 95.67 %
MAYORESMETRADOS
0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %
TOTAL MAYORESMETRADOS
0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %
PARTIDAS NUEVAS 156,410.00 80,507.35 51.47 % 7,335.63 4.69 % 87,842.98 56.16 % 68,567.02 43.84 %
TOTAL PARTIDASNUEVAS
156,410.00 80,507.35 51.47 % 7,335.63 4.69 % 87,842.98 56.16 % 68,567.02 43.84 %
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
B.3.3 MEMORIA DESCRIPTIVA VALORIZADA
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
ITEM DESCRIPTION METRADO COSTO01 OBRAS PROVISIONALES01.01 CARTEL DE OBRA 0.0 0.001.02 ALMACEN Y RESIDENCIA DE OBRA 0.0 0.002 OBRAS PRELIMINARES02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS 0.0 0.002.02 TRAZO, NIVELES Y REPLANTEO 0.0 0.002.03 SEALIZACION Y SEGURIDAD DE OBRA 0.0 0.002.04 LIMPIEZA MANUAL DE TERRENO 0.0 0.002.05 TRANSPORTE DE MATERIALES PARA LA OBRA 0.0 0.003 MOVIMIENTO DE TIERRAS03.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION0.0 0.0
03.02 NIVELACION DE BUZONES EN GENERAL 0.0 0.003.03 RECONEXIONES DOMICILIARIAS DE AGUA 0.0 0.003.04 RECONEXIONES DOMICILIARIAS DE DESAGUE 0.0 0.003.05 CORTE DE TERRENO A NIVEL DE SUB RASANTE 0.0 0.003.06 EXCAVACION MANUAL 0.0 0.003.07 PERFILADO Y COMPACTADO DE SUB RASANTE EN
ZONAS DE CORTE0.0 0.0
03.08 RIEGO 0.0 0.003.09 RELLENO COMPACTADO CON MATERIAL PROPIO 0.0 0.003.10 RELLENO Y COMPACTADO CON MATERIAL PROPIO
(MANUAL)9.24 430.12
03.11 TRANSPORTE DE MATERIAL EXCEDENTE MANUAL(C/BUGUIE D=100M)
10.00 182.50
03.12 ELIMINACION MATERIAL EXCEDENTE 0.0 0.004 ESTRUCTURA DEL PAVIMENTO04.01 BASE GRANULAR (e=0.20CM)04.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION0.0 0.0
04.01.02 EXTRACCION Y PREPARACION DE MATERIAL DE BASE 0.0 0.004.01.03 CARGUIO Y TRANSPORTE DE MATERIAL DE BASE
(Dmax=10KM)0.0 0.0
04.01.04 EXTENDIDO Y COMPACTADO DE BASE 0.0 0.004.01.05 RIEGO 0.0 0.004.02 LOSA DE RODADURA
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
ITEM DESCRIPTION METRADO COSTO04.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION0.0 0.0
04.02.02 ENCOFRADO Y DESENCOFRADO EN LOSA DEPAVIMENTO
0.0 0.0
04.02.03 ACERO DE TEMPERATURA DE 1/4" 0.0 0.004.02.04 ACERO CORRUGADO G-60 DE 1/2" EN JUNTA
LONGITUDINAL0.0 0.0
04.02.05 ACERO DE 3/4" EN JUNTA DE CONTRACCION 0.0 0.004.02.06 ACERO LISO DE 1" EN JUNTA DE DILATACION 0.0 0.004.02.07 CONCRETO F'C=210KG/CM2 0.0 0.004.02.08 CURADO DE LOSA DE CONCRETO 0.0 0.004.02.09 SELLADO DE JUNTAS DE CONTR. Y LONG 0.0 0.004.02.10 SELLADO DE JUNTAS DE DILATACION e=3/4", h=0.15M 0.0 0.004.03 ADOQUINADO04.03.01 SUMINISTRO DE ADOQUINADO DE PIEDRA 0.0 0.004.03.02 COLOCADO DE ADOQUINES DE PIEDRA 0.0 0.004.03.03 SELLADO DE JUNTAS ENTRE ADOQUINES (C, F'C=210
KG/CM2)0.0 0.0
05 SARDINELES Y VEREDAS05.01 SARDINELES DE CONCRETO05.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION0.0 0.0
05.01.02 ENCOFRADO Y DESENCOFRADO DE SARDINELES 0.0 0.005.01.03 CONCRETO F'C=175KG/CM2 0.0 0.005.01.04 CURADO DE CONCRETO 0.0 0.005.01.05 SELLADO DE JUNTAS EN SARDINELES 0.0 0.005.02 VEREDAS05.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION0.0 0.0
05.02.02 NIVELACION Y COMPACTADO MANUAL 0.0 0.005.02.03 ENCOFRADO Y DESENCOFRADO PARA VEREDAS
HASTA H=0.20M0.0 0.0
05.02.04 EMPEDRADO DE 6" 0.0 0.005.02.05 CONCRETO F'C=175KG/CM2 0.0 0.005.02.06 CURADO DE CONCRETO 0.0 0.005.02.07 SUMINISTRO DE LOSETAS DE PIEDRA 0.0 0.005.02.08 COLOCADO DE LOSETAS DE PIEDRA 0.0 0.0
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
ITEM DESCRIPTION METRADO COSTO05.02.09 EMBOQUILLADO ENTRE LOSETAS DE PIEDRA 0.0 0.005.02.10 CURADO DE CONCRETO 0.0 0.006 MUROS DE CONTENCION06.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION0.0 0.0
06.02 SOLADOS DE 2", MEZCLA 1:12 0.0 0.006.03 ENCOFRADO Y DESENCOFRADO DE MUROS DE
SOSTENIMIENTO33.50 1,461.60
06.04 CONCRETO CICLOPEO F'C=140 KG/CM2 + 30% PG 0.0 0.006.05 FILTRO DE GRAVA 0.0 0.006.06 TUBERIA PVC SAL 3" 11.70 179.6006.07 EMBOQUILLADO DE MURO (AREA VISIBLE) C:A 1:5,
e=0.02M0.0 0.0
06.08 CURADO DE CONCRETO 0.0 0.006.09 JUNTAS ASFALTICAS 1"X0.06M, 1:4 0.0 0.007 SISTEMA DE EVACUACION DE AGUAS PLUVIALES07.01 SUMIDEROS07.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION0.0 0.0
07.01.02 NIVELACION Y COMPACTADO MANUAL 0.0 0.007.01.03 EMPEDRADO DE 4" 0.0 0.007.01.04 ENCOFRADO Y DESENCOFRADO NORMAL 0.0 0.007.01.05 ACERO DE REFUERZO G-60 0.0 0.007.01.06 CONCRETO F'C=210KG/CM2 0.0 0.007.01.07 REJILLA SUMIDERO PLAT 2 1/2"x 1/2" C/RIEL 0.0 0.007.01.08 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:5
e=1.5 CM0.0 0.0
07.01.09 CURADO DE CONCRETO 0.0 0.007.01.10 JUNTAS ASFALTICAS 1"X0.06M, 1:4 0.0 0.007.01.11 CAMA DE APOYO 0.0 0.007.01.12 TENDIDO DE TUBERIA DE 8" 0.0 0.007.02 CANAL CON TAPAS DE CONCRETO07.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL
PROCESO DE CONSTRUCCION0.0 0.0
07.02.02 NIVELACION Y COMPACTADO MANUAL 0.0 0.007.02.03 EMPEDRADO DE 4" 0.0 0.0
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
ITEM DESCRIPTION METRADO COSTO07.02.04 ENCOFRADO Y DESENCOFRADO NORMAL 0.0 0.007.02.05 ACERO DE REFUERZO G-60 0.0 0.007.02.06 CONCRETO F'C = 210 KG/CM2 0.0 0.007.02.07 TAPA DE CONCRETO ARMADO PREFABRICADO 0.0 0.007.02.08 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:5
e=1.5 CM0.0 0.0
07.02.09 CURADO DE CONCRETO 0.0 0.008 OBRAS COMPLEMENTARIAS08.01 SEALIZACION08.01.01 SEALES PREVENTIVAS 0.0 0.008.02 DEMARCACION08.02.01 PINTADO DE SARDINELES AL BORDE DE LA VIA 0.0 0.008.02.02 PINTADO DE SEALES EN PISO 0.0 0.008.03 BANCAS08.03.01 BANCAS DE MADERA CON ESTRUCTURA METALICA 0.0 0.008.04 PAPELERA08.04.01 SUMINISTRO E INSTALACION DE CONTENEDOR TIPO
PAPELERA0.0 0.0
08.05 ESTRUCTURAS VARIAS08.05.01 BARANDAS METALICAS (SEGN DISEO) 0.0 0.009 CONTROL DE CALIDAD DE LA OBRA09.01 DISEO DE MEZCLAS09.01.01 DISEO DE MEZCLA DE CONCRETO 0.0 0.009.02 PRUEBA DE CONTROL09.02.01 PRUEBA DE DENSIDAD DE CAMPO 0.0 0.009.02.02 ROTURA DE BRIQUETAS 0.0 0.010 INTERVENCION ARQUEOLOGICA10.01 MONITOREO ARQUEOLOGICO 0.0 0.011 MITIGACION DE IMPACTOS11.01 TRATAMIENTO DE AREAS VERDES11.01.01 ACONDICIONAMIENTO DE AREAS VERDES 0.0 0.012 LIMPIEZA DE OBRA
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
ITEM DESCRIPTION METRADO COSTO12.01 LIMPIEZA DE OBRA 0.0 0.0- TOTAL - 2,253.82
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR YPEATONAL DE LA CALLE INCA YUPANQUI DE LA
ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO DELCUSCO, PROVINCIA DEL CUSCO
RESUMEN DE VALORIZACION GENERAL
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
RESUMEN DE VALORIZACION GENERAL
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
ITEM DESCRIPCION PRESUPUESTOPARCIAL
AVANCEVALORIZADO
ANTERIOR
AVANCEVALORIZADOTOTAL JUNIO
AVANCEACUMULADOTOTAL 2015
AVANCEPORCENTUAL
01 MEJORAMIENTO DE LA TRANSITABILIDADVEHICULAR Y PEATONAL DE LA CALLE INCAYUPANQUI DE LA ASOCIACION PROVIVIENDAAYUDA MUTUA, DISTRITO DEL CUSCO,PROVINCIA DEL CUSCO
2,408,070.50 101,900.65 2,253.82 104,154.47 4.33 %
COSTO DIRECTO 2,408,070.50 101,900.65 2,253.82 104,154.47 4.33 %
GASTOS GENERALES 283,591.94 12,000.56 265.43 12,265.99 4.33 %
GASTOS DE SUPERVICION 52,528.18 2,222.80 49.16 2,271.96 4.33 %
GASTOS DE EXPEDIENTE TECNICO 13,719.63 580.56 12.84 593.40 4.33 %
LIQUIDACION DE OBRA 11,431.68 483.75 10.70 494.45 4.33 %
COSTO TOTAL 2,769,342.25 117,188.32 2,591.95 119,780.27 4.33 %
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO
RESUMEN DE VALORIZACION DE OBRA
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
RESUMEN DE VALORIZACION DE OBRA
OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO
ITEM VALORIZACION PRESUPUESTO VALORIZADO S/. % VALORIZADO S/. % VALORIZADO S/. % VALORIZADO S/. %
1 COSTO DIRECTO 2,408,070.50 101,900.65 4.23 % 2,253.82 .09 % 104,154.48 4.33 % 2,303,916.00 95.67 %
COSTO TOTAL 2,769,342.25 117,188.32 4.23 % 2,591.95 .09 % 119,780.28 4.33 % 2,649,561.75 95.67 %
2 MAYORES METRADOS 0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %
TOTAL MAYORES METRADOS 0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %
3 PARTIDAS NUEVAS 156,410.00 80,507.35 51.47 % 7,335.63 4.69 % 87,842.98 56.16 % 68,567.02 43.84 %
TOTAL PARTIDAS NUEVAS 156,410.00 80,507.35 51.47 % 7,335.63 4.69 % 87,842.98 56.16 % 68,567.02 43.84 %
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO
VALORIZACION DE OBRA
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
VALORIZACION DE AVANCE DE OBRA PROGRAMADA
OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO
UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %
01 OBRAS PROVISIONALES
01.01 CARTEL DE OBRA UND 2.00 652.12 1,304.24 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 2.00 1,304.24 100.00 %
01.02 ALMACEN Y RESIDENCIA DE OBRA MES 10.00 150.00 1,500.00 3.00 450.00 30.00 % 0.0 0.0 0.0 % 3.0 450.00 30.00 % 7.00 1,050.00 70.00 %
02 OBRAS PRELIMINARES
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 2,433.44 2,433.44 0.60 1,460.06 60.00 % 0.0 0.0 0.0 % 0.6 1,460.06 60.00 % 0.40 973.38 40.00 %
02.02 TRAZO, NIVELES Y REPLANTEO M2 7,935.74 .75 5,951.81 7,935.74 5,951.81 100.00 % 0.0 0.0 0.0 % 7935.74 5,951.81 100.00 % 0.0 0.0 0.0 %
02.03 SEALIZACION Y SEGURIDAD DE OBRA UND 1.00 720.80 720.80 1.00 720.80 100.00 % 0.0 0.0 0.0 % 1.0 720.80 100.00 % 0.0 0.0 0.0 %
02.04 LIMPIEZA MANUAL DE TERRENO M2 7,935.34 .33 2,618.66 3,752.06 1,238.18 47.28 % 0.0 0.0 0.0 % 3752.06 1,238.18 47.28 % 4,183.28 1,380.48 52.72 %
02.05 TRANSPORTE DE MATERIALES PARA LA OBRA GLB 1.00 5,000.00 5,000.00 1.00 5,000.00 100.00 % 0.0 0.0 0.0 % 1.0 5,000.00 100.00 % 0.0 0.0 0.0 %
03 MOVIMIENTO DE TIERRAS
03.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION
M2 7,935.74 .54 4,285.30 1,915.98 1,034.63 24.14 % 0.0 0.0 0.0 % 1915.98 1,034.63 24.14 % 6,019.76 3,250.67 75.86 %
03.02 NIVELACION DE BUZONES EN GENERAL UND 11.00 309.65 3,406.15 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 11.00 3,406.15 100.00 %
03.03 RECONEXIONES DOMICILIARIAS DE AGUA UND 44.00 283.35 12,467.40 13.00 3,683.55 29.55 % 0.0 0.0 0.0 % 13.0 3,683.55 29.55 % 31.00 8,783.85 70.45 %
03.04 RECONEXIONES DOMICILIARIAS DE DESAGUE UND 44.00 283.35 12,467.40 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 44.00 12,467.40 100.00 %
03.05 CORTE DE TERRENO A NIVEL DE SUB RASANTE M3 3,683.40 6.72 24,752.45 336.90 2,263.97 9.15 % 0.0 0.0 0.0 % 336.9 2,263.97 9.15 % 3,346.50 22,488.48 90.85 %
03.06 EXCAVACION MANUAL M3 873.87 27.05 23,638.18 768.97 20,800.64 88.00 % 0.0 0.0 0.0 % 768.97 20,800.64 88.00 % 104.90 2,837.55 12.00 %
03.07 PERFILADO Y COMPACTADO DE SUB RASANTE ENZONAS DE CORTE
M2 5,497.33 4.77 26,222.26 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 26,222.26 100.00 %
03.08 RIEGO M2 5,497.33 .47 2,583.75 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 2,583.75 100.00 %
03.09 RELLENO COMPACTADO CON MATERIAL PROPIO M3 489.02 5.05 2,469.55 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 489.02 2,469.55 100.00 %
03.10 RELLENO Y COMPACTADO CON MATERIAL PROPIO(MANUAL)
M3 230.58 46.55 10,733.50 204.17 9,504.11 88.55 % 9.24 430.12 4.01 % 213.41 9,934.24 92.55 % 17.17 799.26 7.45 %
03.11 TRANSPORTE DE MATERIAL EXCEDENTE MANUAL(C/BUGUIE D=100M)
M3 1,092.34 18.25 19,935.20 363.50 6,633.88 33.28 % 10.00 182.50 .92 % 373.5 6,816.38 34.19 % 718.84 13,118.83 65.81 %
03.12 ELIMINACION MATERIAL EXCEDENTE M3 5,696.59 15.25 86,873.00 374.00 5,703.50 6.57 % 0.0 0.0 0.0 % 374.0 5,703.50 6.57 % 5,322.59 81,169.49 93.43 %
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO
UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %
04 ESTRUCTURA DEL PAVIMENTO
04.01 BASE GRANULAR (e=0.20CM)
04.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION
M2 5,497.33 .54 2,968.56 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 2,968.56 100.00 %
04.01.02 EXTRACCION Y PREPARACION DE MATERIAL DE BASE M3 1,099.47 8.16 8,971.68 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,099.47 8,971.67 100.00 %
04.01.03 CARGUIO Y TRANSPORTE DE MATERIAL DE BASE(Dmax=10KM)
M3 1,374.33 29.04 39,910.54 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,374.33 39,910.54 100.00 %
04.01.04 EXTENDIDO Y COMPACTADO DE BASE M2 5,497.33 2.47 13,578.41 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 13,578.41 100.00 %
04.01.05 RIEGO M2 5,497.33 .47 2,583.75 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 2,583.75 100.00 %
04.02 LOSA DE RODADURA
04.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION
M2 5,497.33 .54 2,968.56 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 2,968.56 100.00 %
04.02.02 ENCOFRADO Y DESENCOFRADO EN LOSA DEPAVIMENTO
M2 784.10 38.91 30,509.33 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 784.10 30,509.33 100.00 %
04.02.03 ACERO DE TEMPERATURA DE 1/4" KG 6,257.18 5.56 34,789.92 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 6,257.18 34,789.92 100.00 %
04.02.04 ACERO CORRUGADO G-60 DE 1/2" EN JUNTALONGITUDINAL
KG 990.02 5.99 5,930.22 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 990.02 5,930.22 100.00 %
04.02.05 ACERO DE 3/4" EN JUNTA DE CONTRACCION KG 4,806.14 5.99 28,788.78 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 4,806.14 28,788.78 100.00 %
04.02.06 ACERO LISO DE 1" EN JUNTA DE DILATACION KG 133.39 6.44 859.03 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 133.39 859.03 100.00 %
04.02.07 CONCRETO F'C=210KG/CM2 M3 934.55 415.01 387,847.59 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 934.55 387,847.59 100.00 %
04.02.08 CURADO DE LOSA DE CONCRETO M2 5,497.33 .85 4,672.73 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 4,672.73 100.00 %
04.02.09 SELLADO DE JUNTAS DE CONTR. Y LONG M 4,805.95 3.38 16,244.11 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 4,805.95 16,244.11 100.00 %
04.02.10 SELLADO DE JUNTAS DE DILATACION e=3/4", h=0.15M M 77.00 7.69 592.13 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 77.00 592.13 100.00 %
04.03 ADOQUINADO
04.03.01 SUMINISTRO DE ADOQUINADO DE PIEDRA M2 5,497.33 147.00 808,107.50 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 808,107.50 100.00 %
04.03.02 COLOCADO DE ADOQUINES DE PIEDRA M2 5,497.33 18.48 101,590.66 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 101,590.66 100.00 %
04.03.03 SELLADO DE JUNTAS ENTRE ADOQUINES (C, F'C=210KG/CM2)
M2 5,497.33 21.20 116,543.40 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5,497.33 116,543.40 100.00 %
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO
UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %
05 SARDINELES Y VEREDAS
05.01 SARDINELES DE CONCRETO
05.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION
M2 149.27 .54 80.61 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 149.27 80.61 99.99 %
05.01.02 ENCOFRADO Y DESENCOFRADO DE SARDINELES M2 149.27 38.91 5,808.10 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 149.27 5,808.10 100.00 %
05.01.03 CONCRETO F'C=175KG/CM2 M3 89.56 406.02 36,363.15 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 89.56 36,363.15 100.00 %
05.01.04 CURADO DE CONCRETO M 995.15 .39 388.11 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 995.15 388.11 100.00 %
05.01.05 SELLADO DE JUNTAS EN SARDINELES M 149.40 9.27 1,384.94 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 149.40 1,384.94 100.00 %
05.02 VEREDAS
05.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION
M2 931.88 .54 503.22 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 931.88 503.22 100.00 %
05.02.02 NIVELACION Y COMPACTADO MANUAL M2 931.88 1.47 1,369.86 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 931.88 1,369.86 100.00 %
05.02.03 ENCOFRADO Y DESENCOFRADO PARA VEREDAS HASTAH=0.20M
M 1,014.15 20.18 20,465.55 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,014.15 20,465.55 100.00 %
05.02.04 EMPEDRADO DE 6" M2 931.88 22.31 20,790.24 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 931.88 20,790.24 100.00 %
05.02.05 CONCRETO F'C=175KG/CM2 M3 69.89 406.02 28,376.74 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 69.89 28,376.74 100.00 %
05.02.06 CURADO DE CONCRETO M2 931.88 .85 792.10 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 931.88 792.10 100.00 %
05.02.07 SUMINISTRO DE LOSETAS DE PIEDRA M2 86.00 94.50 8,127.00 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 86.00 8,127.00 100.00 %
05.02.08 COLOCADO DE LOSETAS DE PIEDRA M2 86.00 18.51 1,591.86 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 86.00 1,591.86 100.00 %
05.02.09 EMBOQUILLADO ENTRE LOSETAS DE PIEDRA M2 86.00 27.38 2,354.68 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 86.00 2,354.68 100.00 %
05.02.10 CURADO DE CONCRETO M2 86.00 .85 73.10 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 86.00 73.10 100.00 %
06 MUROS DE CONTENCION
06.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION
M2 225.67 .54 121.86 225.67 121.86 100.00 % 0.0 0.0 0.0 % 225.67 121.86 100.00 % 0.0 0.0 0.0 %
06.02 SOLADOS DE 2", MEZCLA 1:12 M2 225.67 14.51 3,274.47 225.67 3,274.47 100.00 % 0.0 0.0 0.0 % 225.67 3,274.47 100.00 % 0.0 0.0 0.0 %
06.03 ENCOFRADO Y DESENCOFRADO DE MUROS DESOSTENIMIENTO
M2 371.26 43.63 16,198.07 226.27 9,872.16 60.95 % 33.50 1,461.60 9.02 % 259.77002 11,333.77 69.97 % 111.49 4,864.31 30.03 %
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO
UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %
06.04 CONCRETO CICLOPEO F'C=140 KG/CM2 + 30% PG M3 224.45 241.84 54,280.99 37.11 8,974.68 16.53 % 0.0 0.0 0.0 % 37.11 8,974.68 16.53 % 187.34 45,306.30 83.47 %
06.05 FILTRO DE GRAVA M3 3.96 93.53 370.38 2.78 260.01 70.20 % 0.0 0.0 0.0 % 2.78 260.01 70.20 % 1.18 110.37 29.80 %
06.06 TUBERIA PVC SAL 3" M 93.75 15.35 1,439.06 78.40 1,203.44 83.63 % 11.70 179.60 12.48 % 90.1 1,383.04 96.11 % 3.65 56.03 3.89 %
06.07 EMBOQUILLADO DE MURO (AREA VISIBLE) C:A 1:5,e=0.02M
M2 313.11 27.34 8,560.43 155.29 4,245.63 49.60 % 0.0 0.0 0.0 % 155.29 4,245.63 49.60 % 157.82 4,314.80 50.40 %
06.08 CURADO DE CONCRETO M2 371.26 .85 315.57 323.28 274.79 87.08 % 0.0 0.0 0.0 % 323.28 274.79 87.08 % 47.98 40.78 12.92 %
06.09 JUNTAS ASFALTICAS 1"X0.06M, 1:4 M 77.80 5.09 396.00 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 77.80 396.00 100.00 %
07 SISTEMA DE EVACUACION DE AGUAS PLUVIALES
07.01 SUMIDEROS
07.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION
M2 15.40 .54 8.32 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 15.40 8.32 99.95 %
07.01.02 NIVELACION Y COMPACTADO MANUAL M2 15.40 1.47 22.64 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 15.40 22.64 99.99 %
07.01.03 EMPEDRADO DE 4" M2 15.40 15.88 244.55 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 15.40 244.55 100.00 %
07.01.04 ENCOFRADO Y DESENCOFRADO NORMAL M2 22.40 26.35 590.24 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 22.40 590.24 100.00 %
07.01.05 ACERO DE REFUERZO G-60 KG 292.72 6.09 1,782.66 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 292.72 1,782.66 100.00 %
07.01.06 CONCRETO F'C=210KG/CM2 M3 5.13 415.01 2,129.00 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5.13 2,129.00 100.00 %
07.01.07 REJILLA SUMIDERO PLAT 2 1/2"x 1/2" C/RIEL M2 10.60 1,218.34 12,914.40 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 10.60 12,914.40 100.00 %
07.01.08 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:5 e=1.5CM
M2 32.80 20.73 679.94 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 32.80 679.94 100.00 %
07.01.09 CURADO DE CONCRETO M 32.80 .39 12.79 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 32.80 12.79 100.02 %
07.01.10 JUNTAS ASFALTICAS 1"X0.06M, 1:4 M 44.00 5.09 223.96 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 44.00 223.96 100.00 %
07.01.11 CAMA DE APOYO M3 12.03 139.84 1,682.28 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 12.03 1,682.28 100.00 %
07.01.12 TENDIDO DE TUBERIA DE 8" M 240.50 100.91 24,268.86 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 240.50 24,268.86 100.00 %
07.02 CANAL CON TAPAS DE CONCRETO
07.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESODE CONSTRUCCION
M2 599.49 .54 323.72 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 599.49 323.72 100.00 %
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO
UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %
07.02.02 NIVELACION Y COMPACTADO MANUAL M2 599.49 1.47 881.25 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 599.49 881.25 100.00 %
07.02.03 EMPEDRADO DE 4" M2 599.49 15.88 9,519.90 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 599.49 9,519.90 100.00 %
07.02.04 ENCOFRADO Y DESENCOFRADO NORMAL M2 1,005.57 26.35 26,496.77 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,005.57 26,496.77 100.00 %
07.02.05 ACERO DE REFUERZO G-60 KG 2,543.90 6.09 15,492.35 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 2,543.90 15,492.35 100.00 %
07.02.06 CONCRETO F'C = 210 KG/CM2 M3 179.94 415.01 74,676.90 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 179.94 74,676.90 100.00 %
07.02.07 TAPA DE CONCRETO ARMADO PREFABRICADO UND 996.00 24.50 24,402.00 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 996.00 24,402.00 100.00 %
07.02.08 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:5 e=1.5CM
M2 1,398.81 20.73 28,997.33 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,398.81 28,997.33 100.00 %
07.02.09 CURADO DE CONCRETO M2 1,398.81 .85 1,188.99 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,398.81 1,188.99 100.00 %
08 OBRAS COMPLEMENTARIAS
08.01 SEALIZACION
08.01.01 SEALES PREVENTIVAS UND 14.00 526.09 7,365.26 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 14.00 7,365.26 100.00 %
08.02 DEMARCACION
08.02.01 PINTADO DE SARDINELES AL BORDE DE LA VIA M 1,990.30 6.37 12,678.21 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 1,990.30 12,678.21 100.00 %
08.02.02 PINTADO DE SEALES EN PISO M2 49.50 6.51 322.25 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 49.50 322.25 100.00 %
08.03 BANCAS
08.03.01 BANCAS DE MADERA CON ESTRUCTURA METALICA UND 5.00 1,477.90 7,389.50 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 5.00 7,389.50 100.00 %
08.04 PAPELERA
08.04.01 SUMINISTRO E INSTALACION DE CONTENEDOR TIPOPAPELERA
UND 4.00 639.11 2,556.44 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 4.00 2,556.44 100.00 %
08.05 ESTRUCTURAS VARIAS
08.05.01 BARANDAS METALICAS (SEGN DISEO) M 190.00 196.62 37,357.80 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 190.00 37,357.80 100.00 %
09 CONTROL DE CALIDAD DE LA OBRA
09.01 DISEO DE MEZCLAS
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO
UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %
09.01.01 DISEO DE MEZCLA DE CONCRETO UND 2.00 350.00 700.00 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 2.00 700.00 100.00 %
09.02 PRUEBA DE CONTROL
09.02.01 PRUEBA DE DENSIDAD DE CAMPO UND 20.00 35.00 700.00 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 20.00 700.00 100.00 %
09.02.02 ROTURA DE BRIQUETAS UND 25.00 25.00 625.00 10.00 250.00 40.00 % 0.0 0.0 0.0 % 10.0 250.00 40.00 % 15.00 375.00 60.00 %
10 INTERVENCION ARQUEOLOGICA
10.01 MONITOREO ARQUEOLOGICO MES 10.00 2,992.83 29,928.30 3.00 8,978.49 30.00 % 0.0 0.0 0.0 % 3.0 8,978.49 30.00 % 7.00 20,949.81 70.00 %
11 MITIGACION DE IMPACTOS
11.01 TRATAMIENTO DE AREAS VERDES
11.01.01 ACONDICIONAMIENTO DE AREAS VERDES M2 365.00 14.56 5,314.40 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 365.00 5,314.40 100.00 %
12 LIMPIEZA DE OBRA
12.01 LIMPIEZA DE OBRA M2 7,935.74 .80 6,348.59 0.0 0.0 0.0 % 0.0 0.0 0.0 % 0.0 0.0 0.0 % 7,935.74 6,348.59 100.00 %
COSTO DIRECTO 2,408,070.50
101,900.65 4.23 % 2,253.82 .09 % 104,154.48 4.33 % 2,303,916.00
95.67 %
GASTOS GENERALES 283,591.94 12,000.56 265.43 12,265.99 271,325.97
GASTOS DE SUIPERVICION 52,528.18 2,222.80 49.16 2,271.96 50,256.22
GASTOS DE LIQUIDACION 11,431.68 483.75 10.70 494.45 10,937.23
GASTOS DE EXPEDIENTE TECNICO 13,719.63 580.56 12.84 593.40 13,126.23
GASTOS TOTAL PRESUPUESTO 2,769,342.25
117,188.32 4.23 % 2,591.95 .09 % 119,780.28 4.33 % 2,649,561.75
95.67 %
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO
UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO
METRADO DIARIO DE AVANCE DE OBRA PROGRAMADA
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
METRADO DIARIO DE AVANCE DE OBRA PROGRAMADA
OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES
ACUMULADO
SALDO
01 OBRAS PROVISIONALES
01.01 CARTEL DE OBRA UND 2.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 2.00
01.02 ALMACEN Y RESIDENCIA DEOBRA
MES 10.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 3.00 7.00
02 OBRAS PRELIMINARES
02.01 MOVILIZACION YDESMOVILIZACION DE EQUIPOS
GLB 1.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.60 0.40
02.02 TRAZO, NIVELES Y REPLANTEO M2 7935.74 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 7,935.74 0.0
02.03 SEALIZACION Y SEGURIDAD DEOBRA
UND 1.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 1.00 0.0
02.04 LIMPIEZA MANUAL DE TERRENO M2 7935.34 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 3,752.06 4,183.28
02.05 TRANSPORTE DE MATERIALESPARA LA OBRA
GLB 1.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 1.00 0.0
03 MOVIMIENTO DE TIERRAS
03.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION
M2 7935.74 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 1,915.98 6,019.76
03.02 NIVELACION DE BUZONES ENGENERAL
UND 11.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 11.00
03.03 RECONEXIONES DOMICILIARIASDE AGUA
UND 44.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 13.00 31.00
03.04 RECONEXIONES DOMICILIARIASDE DESAGUE
UND 44.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 44.00
03.05 CORTE DE TERRENO A NIVEL DESUB RASANTE
M3 3683.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 336.90 3,346.50
03.06 EXCAVACION MANUAL M3 873.87 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 768.97 104.90
03.07 PERFILADO Y COMPACTADO DESUB RASANTE EN ZONAS DECORTE
M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33
03.08 RIEGO M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33
03.09 RELLENO COMPACTADO CONMATERIAL PROPIO
M3 489.02 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 489.02
03.10 RELLENO Y COMPACTADO CONMATERIAL PROPIO (MANUAL)
M3 230.58 9.24 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 9.24 213.41 17.17
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES
ACUMULADO
SALDO
03.11 TRANSPORTE DE MATERIALEXCEDENTE MANUAL (C/BUGUIED=100M)
M3 1092.34 10.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 10.00 373.50 718.84
03.12 ELIMINACION MATERIALEXCEDENTE
M3 5696.59 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 374.00 5,322.59
04 ESTRUCTURA DEL PAVIMENTO
04.01 BASE GRANULAR (e=0.20CM)
04.01.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION
M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33
04.01.02 EXTRACCION Y PREPARACIONDE MATERIAL DE BASE
M3 1099.47 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,099.47
04.01.03 CARGUIO Y TRANSPORTE DEMATERIAL DE BASE (Dmax=10KM)
M3 1374.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,374.33
04.01.04 EXTENDIDO Y COMPACTADO DEBASE
M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33
04.01.05 RIEGO M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33
04.02 LOSA DE RODADURA
04.02.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION
M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33
04.02.02 ENCOFRADO Y DESENCOFRADOEN LOSA DE PAVIMENTO
M2 784.1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 784.10
04.02.03 ACERO DE TEMPERATURA DE1/4"
KG 6257.18 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 6,257.18
04.02.04 ACERO CORRUGADO G-60 DE1/2" EN JUNTA LONGITUDINAL
KG 990.02 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 990.02
04.02.05 ACERO DE 3/4" EN JUNTA DECONTRACCION
KG 4806.14 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 4,806.14
04.02.06 ACERO LISO DE 1" EN JUNTA DEDILATACION
KG 133.39 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 133.39
04.02.07 CONCRETO F'C=210KG/CM2 M3 934.55 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 934.55
04.02.08 CURADO DE LOSA DECONCRETO
M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33
04.02.09 SELLADO DE JUNTAS DE CONTR.Y LONG
M 4805.95 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 4,805.95
04.02.10 SELLADO DE JUNTAS DEDILATACION e=3/4", h=0.15M
M 77.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 77.00
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES
ACUMULADO
SALDO
04.03 ADOQUINADO
04.03.01 SUMINISTRO DE ADOQUINADODE PIEDRA
M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33
04.03.02 COLOCADO DE ADOQUINES DEPIEDRA
M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33
04.03.03 SELLADO DE JUNTAS ENTREADOQUINES (C, F'C=210KG/CM2)
M2 5497.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5,497.33
05 SARDINELES Y VEREDAS
05.01 SARDINELES DE CONCRETO
05.01.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION
M2 149.27 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 149.27
05.01.02 ENCOFRADO Y DESENCOFRADODE SARDINELES
M2 149.27 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 149.27
05.01.03 CONCRETO F'C=175KG/CM2 M3 89.56 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 89.56
05.01.04 CURADO DE CONCRETO M 995.15 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 995.15
05.01.05 SELLADO DE JUNTAS ENSARDINELES
M 149.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 149.40
05.02 VEREDAS
05.02.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION
M2 931.88 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 931.88
05.02.02 NIVELACION Y COMPACTADOMANUAL
M2 931.88 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 931.88
05.02.03 ENCOFRADO Y DESENCOFRADOPARA VEREDAS HASTA H=0.20M
M 1014.15 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,014.15
05.02.04 EMPEDRADO DE 6" M2 931.88 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 931.88
05.02.05 CONCRETO F'C=175KG/CM2 M3 69.89 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 69.89
05.02.06 CURADO DE CONCRETO M2 931.88 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 931.88
05.02.07 SUMINISTRO DE LOSETAS DEPIEDRA
M2 86.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 86.00
05.02.08 COLOCADO DE LOSETAS DEPIEDRA
M2 86.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 86.00
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES
ACUMULADO
SALDO
05.02.09 EMBOQUILLADO ENTRELOSETAS DE PIEDRA
M2 86.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 86.00
05.02.10 CURADO DE CONCRETO M2 86.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 86.00
06 MUROS DE CONTENCION
06.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION
M2 225.67 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 225.67 0.0
06.02 SOLADOS DE 2", MEZCLA 1:12 M2 225.67 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 225.67 0.0
06.03 ENCOFRADO Y DESENCOFRADODE MUROS DE SOSTENIMIENTO
M2 371.26 33.50 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 33.50 259.77 111.49
06.04 CONCRETO CICLOPEO F'C=140KG/CM2 + 30% PG
M3 224.45 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 37.11 187.34
06.05 FILTRO DE GRAVA M3 3.96 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 2.78 1.18
06.06 TUBERIA PVC SAL 3" M 93.75 11.70 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 11.70 90.10 3.65
06.07 EMBOQUILLADO DE MURO (AREAVISIBLE) C:A 1:5, e=0.02M
M2 313.11 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 155.29 157.82
06.08 CURADO DE CONCRETO M2 371.26 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 323.28 47.98
06.09 JUNTAS ASFALTICAS 1"X0.06M,1:4
M 77.8 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 77.80
07 SISTEMA DE EVACUACION DEAGUAS PLUVIALES
07.01 SUMIDEROS
07.01.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION
M2 15.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 15.40
07.01.02 NIVELACION Y COMPACTADOMANUAL
M2 15.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 15.40
07.01.03 EMPEDRADO DE 4" M2 15.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 15.40
07.01.04 ENCOFRADO Y DESENCOFRADONORMAL
M2 22.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 22.40
07.01.05 ACERO DE REFUERZO G-60 KG 292.72 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 292.72
07.01.06 CONCRETO F'C=210KG/CM2 M3 5.13 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5.13
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES
ACUMULADO
SALDO
07.01.07 REJILLA SUMIDERO PLAT 2 1/2"x1/2" C/RIEL
M2 10.6 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 10.60
07.01.08 TARRAJEO CONIMPERMEABILIZANTE MEZCLA1:5 e=1.5 CM
M2 32.8 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 32.80
07.01.09 CURADO DE CONCRETO M 32.8 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 32.80
07.01.10 JUNTAS ASFALTICAS 1"X0.06M,1:4
M 44.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 44.00
07.01.11 CAMA DE APOYO M3 12.03 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 12.03
07.01.12 TENDIDO DE TUBERIA DE 8" M 240.5 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 240.50
07.02 CANAL CON TAPAS DECONCRETO
07.02.01 TRAZO, NIVELES Y REPLANTEODURANTE EL PROCESO DECONSTRUCCION
M2 599.49 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 599.49
07.02.02 NIVELACION Y COMPACTADOMANUAL
M2 599.49 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 599.49
07.02.03 EMPEDRADO DE 4" M2 599.49 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 599.49
07.02.04 ENCOFRADO Y DESENCOFRADONORMAL
M2 1005.57 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,005.57
07.02.05 ACERO DE REFUERZO G-60 KG 2543.9 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 2,543.90
07.02.06 CONCRETO F'C = 210 KG/CM2 M3 179.94 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 179.94
07.02.07 TAPA DE CONCRETO ARMADOPREFABRICADO
UND 996.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 996.00
07.02.08 TARRAJEO CONIMPERMEABILIZANTE MEZCLA1:5 e=1.5 CM
M2 1398.81 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,398.81
07.02.09 CURADO DE CONCRETO M2 1398.81 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,398.81
08 OBRAS COMPLEMENTARIAS
08.01 SEALIZACION
08.01.01 SEALES PREVENTIVAS UND 14.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 14.00
08.02 DEMARCACION
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES
ACUMULADO
SALDO
08.02.01 PINTADO DE SARDINELES ALBORDE DE LA VIA
M 1990.3 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 1,990.30
08.02.02 PINTADO DE SEALES EN PISO M2 49.5 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 49.50
08.03 BANCAS
08.03.01 BANCAS DE MADERA CONESTRUCTURA METALICA
UND 5.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 5.00
08.04 PAPELERA
08.04.01 SUMINISTRO E INSTALACION DECONTENEDOR TIPO PAPELERA
UND 4.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 4.00
08.05 ESTRUCTURAS VARIAS
08.05.01 BARANDAS METALICAS (SEGNDISEO)
M 190.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 190.00
09 CONTROL DE CALIDAD DE LAOBRA
09.01 DISEO DE MEZCLAS
09.01.01 DISEO DE MEZCLA DECONCRETO
UND 2.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 2.00
09.02 PRUEBA DE CONTROL
09.02.01 PRUEBA DE DENSIDAD DECAMPO
UND 20.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 20.00
09.02.02 ROTURA DE BRIQUETAS UND 25.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 10.00 15.00
10 INTERVENCION ARQUEOLOGICA
10.01 MONITOREO ARQUEOLOGICO MES 10.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 3.00 7.00
11 MITIGACION DE IMPACTOS
11.01 TRATAMIENTO DE AREASVERDES
11.01.01 ACONDICIONAMIENTO DE AREASVERDES
M2 365.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 365.00
12 LIMPIEZA DE OBRA
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES
ACUMULADO
SALDO
12.01 LIMPIEZA DE OBRA M2 7935.74 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.0 0.0 7,935.74
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO
VALORZACION DE MAYORES METRADOS
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
VALORIZACION DE MAYORES METRADOS
OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO
UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %
COSTO DIRECTO 0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %
GASTOS GENERALES 0.0 0.0 0.0 0.0 0.0
GASTOS DE SUIPERVICION 0.0 0.0 0.0 0.0 0.0
GASTOS DE LIQUIDACION 0.0 0.0 0.0 0.0 0.0
GASTOS DE EXPEDIENTE TECNICO 0.0 0.0 0.0 0.0 0.0
GASTOS TOTAL PRESUPUESTO 0.0 0.0 0.0 % 0.0 0.0 % 0.0 0.0 % 0.0 0.0 %
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO
METRADO DIARIO DEMAYORES METRADOS
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
METRADO DIARIO DE MAYORES METRADOS
OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES
ACUMULADO
SALDO
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO
VALORIZACION DE PARTIDAS NUEVAS
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
VALORIZACION DE PARTIDAS NUEVAS
OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO CODIGO PARTIDA UNID METRADO PRECIO
UNITARIO PARCIAL METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %
06.10 CONCRETO CICLOPEO FC=140 +50%PG M3 500.0 312.82 156,410.00 257.36 80,507.35 51.47 % 23.45 7,335.63 4.69 % 280.81 87,842.98 56.16 % 219.19 68,567.02 43.84 %
COSTO DIRECTO 156,410.00 80,507.35 51.47 % 7,335.63 4.69 % 87,842.98 56.16 % 68,567.02 43.84 %
GASTOS GENERALES 0.0 0.0 0.0 0.0 0.0
GASTOS DE SUIPERVICION 0.0 0.0 0.0 0.0 0.0
GASTOS DE LIQUIDACION 0.0 0.0 0.0 0.0 0.0
GASTOS DE EXPEDIENTE TECNICO 0.0 0.0 0.0 0.0 0.0
GASTOS TOTAL PRESUPUESTO 156,410.00 80,507.35 51.47 % 7,335.63 4.69 % 87,842.98 56.16 % 68,567.02 43.84 %
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLEINCA YUPANQUI DE LA ASOCIACION PROVIVIENDA AYUDA MUTUA, DISTRITO
DEL CUSCO, PROVINCIA DEL CUSCO
METRADO DIARIO DE PARTIDAS NUEVAS
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra
METRADO DIARIO DE PARTIDAS NUEVAS
OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LA CALLE INCA YUPANQUI DE LA ASOCIACION PROVIVIENDA
AYUDA MUTUA, DISTRITO DEL CUSCO, PROVINCIA DEL CUSCO
CORRESPONDIENTE AL MES DE : JUNIO
MUNICIPALIDAD PROVINCIAL DEL CUSCO GERENCIA DE INFRAESTRUCTURA
DIVISION DE OBRAS
CODIGO PARTIDA UNID METRADO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTALMES
ACUMULADO
SALDO
06.10 CONCRETO CICLOPEO FC=140+50%PG
M3 500.0 23.45 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 23.45 280.81 219.19
Ing. Tricia Santoyo Cruz Ing. Moises Mamani Apaza
Gerente de Infraestructura Residente de obra