3632 A4 (SALIYAH TO PTI ) SCHEDULE PLANNING FEEDER1 Section1 / JB1 - FEEDER1 Section2 / JB2 - FEEDER1 Section3 / JB3 - FEEDER1 Section4 / JB4 - FEEDER1 Section5 / JB5 - FEEDER1 Section6 / JB6 - Sl No Activity Quantity Units Duration Quantity Units Duration Quantity Units Duration Quantity Units Duration Quantity Units Duration Quantity Units 1 TRAIL PITS Section1 / JB1 - FEEDER1 Section2 / JB2 - FEEDER1 Section3 / JB3 - FEEDER1 Section4 / JB4 - FEEDER1 Section5 / JB5 - FEEDER1 Section6 / JB6 - 1.a no. 22-Jun-15 22-Jun-15 1 no. 22-Jun-15 22-Jun-15 1 no. 22-Jun-15 22-Jun-15 1 no. 22-Jun-15 22-Jun-15 1 no. 22-Jun-15 22-Jun-15 1 no. 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 1.b MARKING 22-Jun-15 22-Jun-15 1 22-Jun-15 22-Jun-15 1 22-Jun-15 22-Jun-15 1 22-Jun-15 22-Jun-15 1 22-Jun-15 22-Jun-15 1 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 22-Jun-15 1.c MARKING INSPECTION 23-Jun-15 23-Jun-15 1 23-Jun-15 23-Jun-15 1 23-Jun-15 23-Jun-15 1 23-Jun-15 23-Jun-15 1 23-Jun-15 23-Jun-15 1 23-Jun-15 23-Jun-15 23-Jun-15 23-Jun-15 23-Jun-15 23-Jun-15 23-Jun-15 23-Jun-15 23-Jun-15 23-Jun-15 23-Jun-15 23-Jun-15 1.d TRAIL PIT EXCAVATION 24-Jun-15 25-Jun-15 2 24-Jun-15 25-Jun-15 2 24-Jun-15 25-Jun-15 2 24-Jun-15 25-Jun-15 2 24-Jun-15 25-Jun-15 2 24-Jun-15 24-Jun-15 25-Jun-15 24-Jun-15 25-Jun-15 24-Jun-15 25-Jun-15 24-Jun-15 25-Jun-15 24-Jun-15 25-Jun-15 24-Jun-15 1.e INSPECTION OF EXCAVATION 26-Jun-15 26-Jun-15 1 26-Jun-15 26-Jun-15 1 26-Jun-15 26-Jun-15 1 26-Jun-15 26-Jun-15 1 26-Jun-15 26-Jun-15 1 26-Jun-15 27-Jun-15 27-Jun-15 27-Jun-15 27-Jun-15 27-Jun-15 27-Jun-15 27-Jun-15 27-Jun-15 27-Jun-15 27-Jun-15 27-Jun-15 1.f DATA COLLECTION 27-Jun-15 27-Jun-15 1 27-Jun-15 27-Jun-15 1 27-Jun-15 27-Jun-15 1 27-Jun-15 27-Jun-15 1 27-Jun-15 27-Jun-15 1 27-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 1.g BACK FILLING OF TRAIL PITS 27-Jun-15 27-Jun-15 1 27-Jun-15 27-Jun-15 1 27-Jun-15 27-Jun-15 1 27-Jun-15 27-Jun-15 1 27-Jun-15 27-Jun-15 1 27-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 28-Jun-15 1.h REPORTS PREPARATION 28-Jun-15 28-Jun-15 1 28-Jun-15 28-Jun-15 1 28-Jun-15 28-Jun-15 1 28-Jun-15 28-Jun-15 1 28-Jun-15 28-Jun-15 1 28-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 1.i REPORTS SUBMISSION 29-Jun-15 29-Jun-15 1 29-Jun-15 29-Jun-15 1 29-Jun-15 29-Jun-15 1 29-Jun-15 29-Jun-15 1 29-Jun-15 29-Jun-15 1 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 29-Jun-15 2 ls 30-Jun-15 10-Jul-15 10 ls 30-Jun-15 10-Jul-15 10 ls 30-Jun-15 10-Jul-15 10 ls 30-Jun-15 10-Jul-15 10 ls 30-Jun-15 10-Jul-15 10 ls 30-Jun-15 3 JB 1ST STAGE JB1 - FEEDER1 JB2 - FEEDER1 JB3 - FEEDER1 JB4 - FEEDER1 JB5 - FEEDER1 3.a MARKING 1 no. 10-Aug-15 10-Aug-15 1 1 no. 01-Aug-15 01-Aug-15 1 1 no. 14-Jul-15 14-Jul-15 1 1 no. 12-Jul-15 12-Jul-15 1 1 no. 12-Jul-15 12-Jul-15 1 13-Jul-15 13-Jul-15 12-Jul-15 12-Jul-15 12-Jul-15 12-Jul-15 3.b SETTING OUT VBU'S 10-Aug-15 10-Aug-15 1 01-Aug-15 01-Aug-15 1 14-Jul-15 14-Jul-15 1 12-Jul-15 12-Jul-15 1 12-Jul-15 12-Jul-15 1 13-Jul-15 13-Jul-15 12-Jul-15 12-Jul-15 12-Jul-15 12-Jul-15 3.c INSPECTION 11-Aug-15 11-Aug-15 1 02-Aug-15 02-Aug-15 1 15-Jul-15 15-Jul-15 1 13-Jul-15 13-Jul-15 1 13-Jul-15 13-Jul-15 1 14-Jul-15 14-Jul-15 13-Jul-15 13-Jul-15 13-Jul-15 13-Jul-15 3.d EXCAVATION 18 11-Aug-15 13-Aug-15 3 18 02-Aug-15 04-Aug-15 3 18 15-Jul-15 17-Jul-15 3 18 13-Jul-15 15-Jul-15 3 18 13-Jul-15 15-Jul-15 3 15-Jul-15 16-Jul-15 14-Jul-15 26-Jul-15 14-Jul-15 15-Jul-15 3.e BLINDING 1 no. 14-Aug-15 14-Aug-15 1 1 no. 05-Aug-15 05-Aug-15 1 1 no. 18-Jul-15 18-Jul-15 1 1 no. 16-Jul-15 16-Jul-15 1 1 no. 16-Jul-15 16-Jul-15 1 19-Jul-15 19-Jul-15 16-Jul-15 16-Jul-15 3.f INPECTION FOR BLINDING 15-Aug-15 15-Aug-15 1 06-Aug-15 06-Aug-15 1 19-Jul-15 19-Jul-15 1 17-Jul-15 17-Jul-15 1 17-Jul-15 17-Jul-15 1 19-Jul-15 19-Jul-15 19-Jul-15 19-Jul-15 3.g BLINDING CONCRETE 15-Aug-15 15-Aug-15 1 06-Aug-15 06-Aug-15 1 19-Jul-15 19-Jul-15 1 17-Jul-15 17-Jul-15 1 17-Jul-15 17-Jul-15 1 19-Jul-15 19-Jul-15 19-Jul-15 19-Jul-15 3.h WATER PROOFING 16-Aug-15 16-Aug-15 1 07-Aug-15 07-Aug-15 1 20-Jul-15 20-Jul-15 1 18-Jul-15 18-Jul-15 1 18-Jul-15 18-Jul-15 1 19-Jul-15 19-Jul-15 19-Jul-15 19-Jul-15 3.i INSPECTION 16-Aug-15 16-Aug-15 1 07-Aug-15 07-Aug-15 1 20-Jul-15 20-Jul-15 1 18-Jul-15 18-Jul-15 1 18-Jul-15 18-Jul-15 1 20-Jul-15 20-Jul-15 19-Jul-15 19-Jul-15 3.k SCREEDING 16-Aug-15 16-Aug-15 1 07-Aug-15 07-Aug-15 1 20-Jul-15 20-Jul-15 1 18-Jul-15 18-Jul-15 1 18-Jul-15 18-Jul-15 1 20-Jul-15 20-Jul-15 20-Jul-15 20-Jul-15 3.l 17-Aug-15 18-Aug-15 2 08-Aug-15 09-Aug-15 2 21-Jul-15 22-Jul-15 2 19-Jul-15 20-Jul-15 2 19-Jul-15 20-Jul-15 2 20-Jul-15 21-Jul-15 20-Jul-15 21-Jul-15 3.m BASE SHUTTERING 17-Aug-15 18-Aug-15 2 08-Aug-15 09-Aug-15 2 21-Jul-15 22-Jul-15 2 19-Jul-15 20-Jul-15 2 19-Jul-15 20-Jul-15 2 20-Jul-15 21-Jul-15 20-Jul-15 21-Jul-15 3.n INSPECTION 19-Aug-15 19-Aug-15 1 10-Aug-15 10-Aug-15 1 23-Jul-15 23-Jul-15 1 21-Jul-15 21-Jul-15 1 21-Jul-15 21-Jul-15 1 21-Jul-15 21-Jul-15 22-Jul-15 22-Jul-15 3.o CONCRETE BASE 19-Aug-15 19-Aug-15 1 10-Aug-15 10-Aug-15 1 23-Jul-15 23-Jul-15 1 21-Jul-15 21-Jul-15 1 21-Jul-15 21-Jul-15 1 22-Jul-15 22-Jul-15 22-Jul-15 22-Jul-15 3.p SIDE WALL 20-Aug-15 20-Aug-15 1 11-Aug-15 11-Aug-15 1 24-Jul-15 24-Jul-15 1 22-Jul-15 22-Jul-15 1 22-Jul-15 22-Jul-15 1 22-Jul-15 22-Jul-15 22-Jul-15 22-Jul-15 3.q INSPECTION 21-Aug-15 21-Aug-15 1 12-Aug-15 12-Aug-15 1 25-Jul-15 25-Jul-15 1 23-Jul-15 23-Jul-15 1 23-Jul-15 23-Jul-15 1 23-Jul-15 23-Jul-15 23-Jul-15 23-Jul-15 3.r CONCRETING 21-Aug-15 21-Aug-15 1 12-Aug-15 12-Aug-15 1 25-Jul-15 25-Jul-15 1 23-Jul-15 23-Jul-15 1 23-Jul-15 23-Jul-15 1 23-Jul-15 23-Jul-15 23-Jul-15 23-Jul-15 3.S BORE HOLE EARTHING 22-Aug-15 24-Aug-15 3 13-Aug-15 15-Aug-15 3 26-Jul-15 28-Jul-15 3 24-Jul-15 26-Jul-15 3 24-Jul-15 26-Jul-15 3 4 RC OPEN CUT Section3 - FEEDER1 O/C-01 4.a RO PERMIT 14.42 NR NR 4.b VBU DIVERSION 08-Aug-15 08-Aug-15 1 4.c MARKING 09-Aug-15 09-Aug-15 1 4.d INSPECTION 10-Aug-15 10-Aug-15 1 4.e POLICE INSPECTION NR NR 4.f ASPHALT CUTTING 11-Aug-15 12-Aug-15 2 4.g EXCAVATION 13-Aug-15 14-Aug-15 2 4.h 15-Aug-15 16-Aug-15 2 4.i INSPECTION 17-Aug-15 17-Aug-15 1 Planned Start Date Planned Finish Date Planned Start Date Planned Finish Date Planned Start Date Planned Finish Date Planned Start Date Planned Finish Date Planned Start Date Planned Finish Date Planned Start Date SHIFTING & SETTING OUT VBU'S PROFILE DRAWING PREPARATION & Approval M 3 M 3 M 3 M 3 M 3 REINFORCEMENT SETTING FOR BASE SLAB & SIDE WALL M 3 DUCT SETTING ( PIPE SETTING)

3632-A4 Saliyah to Pti

Embed Size (px)

DESCRIPTION

66KV Cable laying

Citation preview

3632 A4-FEEDER13632 A4 (SALIYAH TO PTI ) SCHEDULE PLANNING FEEDER121-Jul-201515-Oct-2014Section1 / JB1 - FEEDER1Section2 / JB2 - FEEDER1Section3 / JB3 - FEEDER1Section4 / JB4 - FEEDER1Section5 / JB5 - FEEDER1Section6 / JB6 - FEEDER1RemarksSl NoActivityQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDuration1TRAIL PITSSection1 / JB1 - FEEDER1Section2 / JB2 - FEEDER1Section3 / JB3 - FEEDER1Section4 / JB4 - FEEDER1Section5 / JB5 - FEEDER1Section6 / JB6 - FEEDER11.aSHIFTING & SETTING OUT VBU'Sno.22-Jun-1522-Jun-151no.22-Jun-1522-Jun-151no.22-Jun-1522-Jun-151no.22-Jun-1522-Jun-151no.22-Jun-1522-Jun-151no.22-Jun-1522-Jun-15122-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-151.bMARKING22-Jun-1522-Jun-15122-Jun-1522-Jun-15122-Jun-1522-Jun-15122-Jun-1522-Jun-15122-Jun-1522-Jun-15122-Jun-1522-Jun-15122-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-151.cMARKING INSPECTION23-Jun-1523-Jun-15123-Jun-1523-Jun-15123-Jun-1523-Jun-15123-Jun-1523-Jun-15123-Jun-1523-Jun-15123-Jun-1523-Jun-15123-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-151.dTRAIL PIT EXCAVATION24-Jun-1525-Jun-15224-Jun-1525-Jun-15224-Jun-1525-Jun-15224-Jun-1525-Jun-15224-Jun-1525-Jun-15224-Jun-1525-Jun-15224-Jun-1525-Jun-1524-Jun-1525-Jun-1524-Jun-1525-Jun-1524-Jun-1525-Jun-1524-Jun-1525-Jun-1524-Jun-1525-Jun-151.eINSPECTION OF EXCAVATION26-Jun-1526-Jun-15126-Jun-1526-Jun-15126-Jun-1526-Jun-15126-Jun-1526-Jun-15126-Jun-1526-Jun-15126-Jun-1526-Jun-15127-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-151.fDATA COLLECTION27-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15128-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-151.gBACK FILLING OF TRAIL PITS27-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15128-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-151.hREPORTS PREPARATION28-Jun-1528-Jun-15128-Jun-1528-Jun-15128-Jun-1528-Jun-15128-Jun-1528-Jun-15128-Jun-1528-Jun-15128-Jun-1528-Jun-15129-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-151.iREPORTS SUBMISSION29-Jun-1529-Jun-15129-Jun-1529-Jun-15129-Jun-1529-Jun-15129-Jun-1529-Jun-15129-Jun-1529-Jun-15129-Jun-1529-Jun-15129-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-152PROFILE DRAWING PREPARATION & Approvalls30-Jun-1510-Jul-1510ls30-Jun-1510-Jul-1510ls30-Jun-1510-Jul-1510ls30-Jun-1510-Jul-1510ls30-Jun-1510-Jul-1510ls30-Jun-1510-Jul-15103JB 1ST STAGEJB1 - FEEDER1JB2 - FEEDER1JB3 - FEEDER1JB4 - FEEDER1JB5 - FEEDER13.aMARKING1no.10-Aug-1510-Aug-1511no.01-Aug-1501-Aug-1511no.14-Jul-1514-Jul-1511no.12-Jul-1512-Jul-1511no.12-Jul-1512-Jul-15113-Jul-1513-Jul-1512-Jul-1512-Jul-1512-Jul-1512-Jul-153.bSETTING OUT VBU'S10-Aug-1510-Aug-15101-Aug-1501-Aug-15114-Jul-1514-Jul-15112-Jul-1512-Jul-15112-Jul-1512-Jul-15113-Jul-1513-Jul-1512-Jul-1512-Jul-1512-Jul-1512-Jul-153.cINSPECTION11-Aug-1511-Aug-15102-Aug-1502-Aug-15115-Jul-1515-Jul-15113-Jul-1513-Jul-15113-Jul-1513-Jul-15114-Jul-1514-Jul-1513-Jul-1513-Jul-1513-Jul-1513-Jul-153.dEXCAVATION18M311-Aug-1513-Aug-15318M302-Aug-1504-Aug-15318M315-Jul-1517-Jul-15318M313-Jul-1515-Jul-15318M313-Jul-1515-Jul-153JB (4.5*3.5*1.45) = 18 CUM15-Jul-1516-Jul-1514-Jul-1526-Jul-1514-Jul-1515-Jul-153.eBLINDING1no.14-Aug-1514-Aug-1511no.05-Aug-1505-Aug-1511no.18-Jul-1518-Jul-1511no.16-Jul-1516-Jul-1511no.16-Jul-1516-Jul-15119-Jul-1519-Jul-1516-Jul-1516-Jul-153.fINPECTION FOR BLINDING15-Aug-1515-Aug-15106-Aug-1506-Aug-15119-Jul-1519-Jul-15117-Jul-1517-Jul-15117-Jul-1517-Jul-15119-Jul-1519-Jul-1519-Jul-1519-Jul-153.gBLINDING CONCRETE15-Aug-1515-Aug-15106-Aug-1506-Aug-15119-Jul-1519-Jul-15117-Jul-1517-Jul-15117-Jul-1517-Jul-15119-Jul-1519-Jul-1519-Jul-1519-Jul-153.hWATER PROOFING16-Aug-1516-Aug-15107-Aug-1507-Aug-15120-Jul-1520-Jul-15118-Jul-1518-Jul-15118-Jul-1518-Jul-15119-Jul-1519-Jul-1519-Jul-1519-Jul-153.iINSPECTION16-Aug-1516-Aug-15107-Aug-1507-Aug-15120-Jul-1520-Jul-15118-Jul-1518-Jul-15118-Jul-1518-Jul-15120-Jul-1520-Jul-1519-Jul-1519-Jul-153.kSCREEDING16-Aug-1516-Aug-15107-Aug-1507-Aug-15120-Jul-1520-Jul-15118-Jul-1518-Jul-15118-Jul-1518-Jul-15120-Jul-1520-Jul-1520-Jul-1520-Jul-153.lREINFORCEMENT SETTING FOR BASE SLAB & SIDE WALL17-Aug-1518-Aug-15208-Aug-1509-Aug-15221-Jul-1522-Jul-15219-Jul-1520-Jul-15219-Jul-1520-Jul-15220-Jul-1521-Jul-1520-Jul-1521-Jul-153.mBASE SHUTTERING17-Aug-1518-Aug-15208-Aug-1509-Aug-15221-Jul-1522-Jul-15219-Jul-1520-Jul-15219-Jul-1520-Jul-15220-Jul-1521-Jul-1520-Jul-1521-Jul-153.nINSPECTION19-Aug-1519-Aug-15110-Aug-1510-Aug-15123-Jul-1523-Jul-15121-Jul-1521-Jul-15121-Jul-1521-Jul-15121-Jul-1521-Jul-1522-Jul-1522-Jul-153.oCONCRETE BASE19-Aug-1519-Aug-15110-Aug-1510-Aug-15123-Jul-1523-Jul-15121-Jul-1521-Jul-15121-Jul-1521-Jul-15122-Jul-1522-Jul-1522-Jul-1522-Jul-153.pSIDE WALL20-Aug-1520-Aug-15111-Aug-1511-Aug-15124-Jul-1524-Jul-15122-Jul-1522-Jul-15122-Jul-1522-Jul-15122-Jul-1522-Jul-1522-Jul-1522-Jul-153.qINSPECTION21-Aug-1521-Aug-15112-Aug-1512-Aug-15125-Jul-1525-Jul-15123-Jul-1523-Jul-15123-Jul-1523-Jul-15123-Jul-1523-Jul-1523-Jul-1523-Jul-153.rCONCRETING21-Aug-1521-Aug-15112-Aug-1512-Aug-15125-Jul-1525-Jul-15123-Jul-1523-Jul-15123-Jul-1523-Jul-15123-Jul-1523-Jul-1523-Jul-1523-Jul-153.SBORE HOLE EARTHING22-Aug-1524-Aug-15313-Aug-1515-Aug-15326-Jul-1528-Jul-15324-Jul-1526-Jul-15324-Jul-1526-Jul-1534RC OPEN CUTSection3 - FEEDER1 O/C-014.aRO PERMIT14.42M3NRNRRC O/C #01 (S3F1) type H Road crossing LxWxD is 10.3x1.4x1 = 14.42C.u.m.4.bVBU DIVERSION08-Aug-1508-Aug-1514.cMARKING09-Aug-1509-Aug-1514.dINSPECTION10-Aug-1510-Aug-1514.ePOLICE INSPECTIONNRNR4.fASPHALT CUTTING11-Aug-1512-Aug-1524.gEXCAVATION13-Aug-1514-Aug-1524.hDUCT SETTING ( PIPE SETTING)15-Aug-1516-Aug-1524.iINSPECTION17-Aug-1517-Aug-1514.JCONCRETING17-Aug-1517-Aug-1515RC HDDRC HDD#03 Section4 - FEEDER1RC HDD#04 Section5 - FEEDER1RC HDD#05 Section5 - FEEDER1RC HDD#07 Section6 - FEEDER15.aRO PERMIT81.94M22-Jun-1523-Jun-15217.36M11-Jul-1512-Jul-15212.3M11-Jul-1512-Jul-15210.3M11-Jul-1512-Jul-152Entry pit LxWxD is 3x3x3.5 =32Cu.m. Exit pit LxWxD is 2.5x2.5x3.5 =22Cu.m. Hence total Entry & Exit pit excavation for each HDD is 54Cu.m.22-Jun-1523-Jun-1511-Jul-1512-Jul-1511-Jul-1512-Jul-1511-Jul-1512-Jul-155.bTRAIL PITS EXCAVATION24-Jun-1525-Jun-15213-Jul-1513-Jul-15213-Jul-1513-Jul-15213-Jul-1513-Jul-15224-Jun-1525-Jun-1513-Jul-1513-Jul-1513-Jul-1513-Jul-1513-Jul-1513-Jul-155.cPROFILE DRAWING PREPARATION26-Jun-1528-Jun-15314-Jul-1516-Jul-15314-Jul-1516-Jul-15314-Jul-1516-Jul-15327-Jun-1530-Jun-1514-Jul-1516-Jul-1514-Jul-1516-Jul-1514-Jul-1516-Jul-155.dINSPECTION04-Jul-1504-Jul-15119-Jul-1519-Jul-15101-Aug-1501-Aug-15107-Aug-1507-Aug-15104-Jul-1504-Jul-1519-Jul-1519-Jul-155.eENTRY & EXIT PIT EXCAVATION54M305-Jul-1508-Jul-15454M320-Jul-1523-Jul-15454M302-Aug-1504-Aug-15354M308-Aug-1511-Aug-15405-Jul-1511-Jul-1520-Jul-155.fINSPECTION81.9M09-Jul-1509-Jul-15117.36M24-Jul-1524-Jul-15112.3M05-Aug-1505-Aug-15110.3M12-Aug-1512-Aug-15112-Jul-1512-Jul-155.gPILOT DRILLING10-Jul-1512-Jul-15325-Jul-1526-Jul-15206-Aug-1507-Aug-15213-Aug-1514-Aug-15213-Jul-1515-Jul-155.hREEMING13-Jul-1518-Jul-15627-Jul-1529-Jul-15308-Aug-1510-Aug-15315-Aug-1517-Aug-15316-Jul-155.iPIPE PULLING20-Jul-1521-Jul-15230-Jul-1531-Jul-15211-Aug-1512-Aug-15218-Aug-1519-Aug-1525.jGROUTING22-Jul-1522-Jul-15101-Aug-1501-Aug-15113-Aug-1513-Aug-15120-Aug-1520-Aug-1515.kINPECTION & MEASUREMENT23-Jul-1523-Jul-15102-Aug-1502-Aug-15114-Aug-1514-Aug-15121-Aug-1521-Aug-1515.lBENTONITE FILLING24-Jul-1524-Jul-15103-Aug-1503-Aug-15115-Aug-1515-Aug-15122-Aug-1522-Aug-1516TRENCHINGSection1 - FEEDER1Section2 - FEEDER1Section3 - FEEDER1Section4 - FEEDER1Section5 - FEEDER1Section6 - FEEDER16.aMARKING901.6M314-Aug-1514-Aug-151901.6M301-Aug-1501-Aug-151887.18M306-Aug-1506-Aug-151866.684M320-Jul-1520-Jul-151935.676M312-Jul-1512-Jul-151962.78M324-Jul-1524-Jul-1511) SECTION LENGHT*1 MTR WIDTH*1.4 DEPTH = CUM10-Jul-1510-Jul-1516-07-1516-07-156.bINSPECTION15-Aug-1515-Aug-15102-Aug-1502-Aug-15107-Aug-1507-Aug-15121-Jul-1521-Jul-15113-Jul-1513-Jul-15125-Jul-1525-Jul-15111-Jul-1511-Jul-1516-07-1516-07-152) EXCAVATION WITH 2 EXCAVATORS WITH AVG 40 CUM /DAY FOR EACH SECTIONS6.cVBU'S SETTING15-Aug-1515-Aug-15102-Aug-1502-Aug-15107-Aug-1507-Aug-15121-Jul-1521-Jul-15113-Jul-1513-Jul-15125-Jul-1525-Jul-15111-Jul-1511-Jul-1519-07-1519-07-156.eEXCAVATION16-Aug-1526-Aug-151103-Aug-1512-Aug-151008-Aug-1517-Aug-151022-Jul-1531-Jul-151014-Jul-1524-Jul-151126-Jul-1505-Aug-151112-Jul-1593%20-07-1553%6.fTRENCH INSPECTION27-Aug-1527-Aug-15113-Aug-1513-Aug-15118-Aug-1518-Aug-15101-Aug-1501-Aug-15125-Jul-1525-Jul-15106-Aug-1506-Aug-1516.gSURPLUS REMOVAL28-Aug-1530-Aug-15314-Aug-1516-Aug-15319-Aug-1521-Aug-15302-Aug-1504-Aug-15326-Jul-1528-Jul-15307-Aug-1509-Aug-1537FTBSection1 - FEEDER1Section2 - FEEDER1Section3 - FEEDER1Section4 - FEEDER1Section5 - FEEDER1Section6 - FEEDER17.aFTB BEDDING644M28-Aug-1529-Aug-152644M13-Aug-1514-Aug-152644M19-Aug-1520-Aug-152701M01-Aug-1502-Aug-152698M04-Aug-1505-Aug-152698M24-Aug-1525-Aug-1527.bINSPECTION30-Aug-1530-Aug-15115-Aug-1515-Aug-15121-Aug-1521-Aug-15103-Aug-1503-Aug-15106-Aug-1506-Aug-15126-Aug-1526-Aug-1518CABLE PULLINGSection1 - FEEDER1Section2 - FEEDER1Section3 - FEEDER1Section4 - FEEDER1Section5 - FEEDER1Section6 - FEEDER18.aDRUM SHIFTING644M01-Sep-1501-Sep-151644M17-Aug-1517-Aug-151644M22-Aug-1522-Aug-151701M05-Aug-1505-Aug-151698M15-Aug-1515-Aug-151698M27-Aug-1527-Aug-1518.bFO & DTS PIPE SHIFTING01-Sep-1501-Sep-15117-Aug-1517-Aug-15122-Aug-1522-Aug-15105-Aug-1505-Aug-15115-Aug-1515-Aug-15127-Aug-1527-Aug-1518.cDUCT INSTALLATION02-Sep-1502-Sep-15118-Aug-1518-Aug-15123-Aug-1523-Aug-15106-Aug-1506-Aug-15116-Aug-1516-Aug-15128-Aug-1528-Aug-1518.dCABLE PULLING02-Sep-1502-Sep-15118-Aug-1518-Aug-15123-Aug-1523-Aug-15106-Aug-1506-Aug-15116-Aug-1516-Aug-15128-Aug-1528-Aug-1518.eINTERNAL SHEATH TEST03-Sep-1503-Sep-15119-Aug-1519-Aug-15124-Aug-1524-Aug-15108-Aug-1508-Aug-15117-Aug-1517-Aug-15129-Aug-1529-Aug-1518.fAS BUILT MEASUREMENT03-Sep-1503-Sep-15119-Aug-1519-Aug-15124-Aug-1524-Aug-15108-Aug-1508-Aug-15117-Aug-1517-Aug-15129-Aug-1529-Aug-1518.gEMPTY DRUM SHIFTING03-Sep-1503-Sep-15119-Aug-1519-Aug-15124-Aug-1524-Aug-15108-Aug-1508-Aug-15117-Aug-1517-Aug-15129-Aug-1529-Aug-1519CBSSection1 - FEEDER1Section2 - FEEDER1Section3 - FEEDER1Section4 - FEEDER1Section5 - FEEDER1Section6 - FEEDER19.aCBS BEDDING644M04-Sep-1505-Sep-152644M20-Aug-1521-Aug-152644M25-Aug-1526-Aug-152701M09-Aug-1510-Aug-152698M18-Aug-1519-Aug-152698M30-Aug-1531-Aug-1529.bINPECTION06-Sep-1506-Sep-15122-Aug-1522-Aug-15127-Aug-1527-Aug-15111-Aug-1511-Aug-15120-Aug-1520-Aug-15101-Sep-1501-Sep-15110TILES INTALLATIONSSection1 - FEEDER1Section2 - FEEDER1Section3 - FEEDER1Section4 - FEEDER1Section5 - FEEDER1Section6 - FEEDER110.aPROTECTION TILES INSTALLATION644M07-Sep-1508-Sep-152644M23-Aug-1524-Aug-152644M28-Aug-1529-Aug-152701M12-Aug-1513-Aug-152698M21-Aug-1522-Aug-152698M02-Sep-1503-Sep-15210.bTILES INSPECTION09-Sep-1509-Sep-15125-Aug-1525-Aug-15130-Aug-1530-Aug-15114-Aug-1514-Aug-15123-Aug-1523-Aug-15104-Sep-1504-Sep-15110.cFINAL SHEATH TEST09-Sep-1509-Sep-15125-Aug-1525-Aug-15130-Aug-1530-Aug-15114-Aug-1514-Aug-15123-Aug-1523-Aug-15104-Sep-1504-Sep-15111TRENCH BACKFILLINGSection1 - FEEDER1Section2 - FEEDER1Section3 - FEEDER1Section4 - FEEDER1Section5 - FEEDER1Section6 - FEEDER111.a1ST LAYER BACK FILLING644M10-Sep-1511-Sep-152644M26-Aug-1527-Aug-152644M31-Aug-1501-Sep-152701M15-Aug-1516-Aug-152698M24-Aug-1525-Aug-152698M05-Sep-1506-Sep-15211.bCOMPACTION TEST12-Sep-1512-Sep-15128-Aug-1528-Aug-15102-Sep-1502-Sep-15117-Aug-1517-Aug-15126-Aug-1526-Aug-15107-Sep-1507-Sep-15111.c2ND LAYER BACK FILLING12-Sep-1513-Sep-15228-Aug-1529-Aug-15202-Sep-1503-Sep-15217-Aug-1518-Aug-15226-Aug-1527-Aug-15207-Sep-1508-Sep-15211.dCOMPACTION TEST14-Sep-1514-Sep-15130-Aug-1530-Aug-15104-Sep-1504-Sep-15119-Aug-1519-Aug-15128-Aug-1528-Aug-15109-Sep-1509-Sep-15111.eWARNING TAPE INSTALLATION14-Sep-1514-Sep-15130-Aug-1530-Aug-15104-Sep-1504-Sep-15119-Aug-1519-Aug-15128-Aug-1528-Aug-15109-Sep-1509-Sep-15111.fWARNING TAPE INSPECTION15-Sep-1515-Sep-15131-Aug-1531-Aug-15105-Sep-1505-Sep-15120-Aug-1520-Aug-15129-Aug-1529-Aug-15110-Sep-1510-Sep-15111.g3RD LAYER BACK FILLING15-Sep-1516-Sep-15231-Aug-1501-Sep-15205-Sep-1506-Sep-15220-Aug-1521-Aug-15229-Aug-1530-Aug-15210-Sep-1511-Sep-15211.hCOMPACTION TEST17-Sep-1517-Sep-15102-Sep-1502-Sep-15107-Sep-1507-Sep-15122-Aug-1522-Aug-15131-Aug-1531-Aug-15112-Sep-1512-Sep-15111.i4TH LAYER BACK FILLING17-Sep-1518-Sep-15202-Sep-1503-Sep-15207-Sep-1508-Sep-15222-Aug-1523-Aug-15231-Aug-1501-Sep-15212-Sep-1513-Sep-15211.jCOMPACTION TEST19-Sep-1519-Sep-15104-Sep-1504-Sep-15109-Sep-1509-Sep-15124-Aug-1524-Aug-15102-Sep-1502-Sep-15114-Sep-1514-Sep-15111.k5TH LAYER BACK FILLING19-Sep-1520-Sep-15204-Sep-1505-Sep-15209-Sep-1510-Sep-15224-Aug-1525-Aug-15202-Sep-1503-Sep-15214-Sep-1515-Sep-15211.lCOMPACTION TEST21-Sep-1521-Sep-15106-Sep-1506-Sep-15111-Sep-1511-Sep-15126-Aug-1526-Aug-15104-Sep-1504-Sep-15116-Sep-1516-Sep-15112JB 2ND STAGESection1 / JB1 - FEEDER1Section2 / JB2 - FEEDER1Section3 / JB3 - FEEDER1Section4 / JB4 - FEEDER1Section5 / JB5 - FEEDER112.aPARTETION WALL1No.07-Oct-1508-Oct-1521No.17-Sep-1518-Sep-1521No.07-Sep-1508-Sep-1521No.27-Aug-1528-Aug-1521No.27-Sep-1528-Sep-15212.bWATER PROOFING09-Oct-1509-Oct-15119-Sep-1519-Sep-15109-Sep-1509-Sep-15129-Aug-1529-Aug-15129-Sep-1529-Sep-15112.cPAINTING10-Oct-1510-Oct-15120-Sep-1520-Sep-15110-Sep-1510-Sep-15130-Aug-1530-Aug-15130-Sep-1530-Sep-15112.dINSPECTION11-Oct-1511-Oct-15121-Sep-1521-Sep-15111-Sep-1511-Sep-15131-Aug-1531-Aug-15101-Oct-1501-Oct-15112.eFTB & DUNE SAND BACK FILLING12-Oct-1512-Oct-15122-Sep-1522-Sep-15112-Sep-1512-Sep-15101-Sep-1501-Sep-15102-Oct-1502-Oct-15112.fLINK BOX & PD BOX INSTALLATION13-Oct-1513-Oct-15123-Sep-1523-Sep-15113-Sep-1513-Sep-15102-Sep-1502-Sep-15103-Oct-1503-Oct-15112.gINSPECTION14-Oct-1514-Oct-15124-Sep-1524-Sep-15114-Sep-1514-Sep-15103-Sep-1503-Sep-15104-Oct-1504-Oct-15113FO BLOWING & SPLICINGSection1 - FEEDER1Section2 - FEEDER1Section3 - FEEDER1Section4 - FEEDER1Section5 - FEEDER1Section6 - FEEDER113.aFO BLOWING644M17-Oct-1518-Oct-152644M17-Oct-1518-Oct-152644M17-Oct-1518-Oct-152701M17-Oct-1518-Oct-15269817-Oct-1518-Oct-152698M17-Oct-1518-Oct-15213.bSPLICING19-Oct-1519-Oct-15119-Oct-1519-Oct-15119-Oct-1519-Oct-15119-Oct-1519-Oct-15119-Oct-1519-Oct-15119-Oct-1519-Oct-15114ROUTE MARKER INSTALLATIONS13NO24-Oct-1526-Oct-153NO24-Oct-1526-Oct-153NO24-Oct-1526-Oct-153NO24-Oct-1526-Oct-15324-Oct-1526-Oct-153NO24-Oct-1526-Oct-15315AS BUILT DRAWINGLs27-Oct-1528-Oct-152Ls27-Oct-1528-Oct-152Ls27-Oct-1528-Oct-152Ls27-Oct-1528-Oct-15227-Oct-1528-Oct-152Ls27-Oct-1528-Oct-15216HANDING OVERNo.29-Oct-1529-Oct-151No.29-Oct-1529-Oct-151No.29-Oct-1529-Oct-151No.29-Oct-1529-Oct-15129-Oct-1529-Oct-151No.29-Oct-1529-Oct-151LEGENDS :COMPLETEDPROGRESSBALANCEON HOLD

Nagraj:300.648 Mtrs upto 24.07.2015ashwinr:370 Mtrs Completed Upto 24.07.2015

3632 A4-FEEDER23632 A4 (SALIYAH TO PTI ) SCHEDULE PLANNING FEEDER221-Jul-201515-Oct-2014Section1 / JB1 - FEEDER2Section2 / JB2 - FEEDER2Section3 / JB3 - FEEDER2Section4 / JB4 - FEEDER2Section5 / JB5 - FEEDER2Section6 / JB6 - FEEDER2RemarksSl NoActivityQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDuration1TRAIL PITSSection1 / JB1 - FEEDER2Section2 / JB2 - FEEDER2Section3 / JB3 - FEEDER2Section4 / JB4 - FEEDER2Section5 / JB5 - FEEDER2Section6 / JB6 - FEEDER21.aSHIFTING & SETTING OUT VBU'Sno.22-Jun-1522-Jun-151no.22-Jun-1522-Jun-151no.22-Jun-1522-Jun-151no.22-Jun-1522-Jun-151no.22-Jun-1522-Jun-151no.22-Jun-1522-Jun-15122-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-151.bMARKING22-Jun-1522-Jun-15122-Jun-1522-Jun-15122-Jun-1522-Jun-15122-Jun-1522-Jun-15122-Jun-1522-Jun-15122-Jun-1522-Jun-15122-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-1522-Jun-151.cMARKING INSPECTION23-Jun-1523-Jun-15123-Jun-1523-Jun-15123-Jun-1523-Jun-15123-Jun-1523-Jun-15123-Jun-1523-Jun-15123-Jun-1523-Jun-15123-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-1523-Jun-151.dTRAIL PIT EXCAVATION24-Jun-1525-Jun-15224-Jun-1525-Jun-15224-Jun-1525-Jun-15224-Jun-1525-Jun-15224-Jun-1525-Jun-15224-Jun-1525-Jun-15224-Jun-1525-Jun-1524-Jun-1525-Jun-1524-Jun-1525-Jun-1524-Jun-1525-Jun-1524-Jun-1525-Jun-1524-Jun-1525-Jun-151.eINSPECTION OF EXCAVATION26-Jun-1526-Jun-15126-Jun-1526-Jun-15126-Jun-1526-Jun-15126-Jun-1526-Jun-15126-Jun-1526-Jun-15126-Jun-1526-Jun-15127-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-1527-Jun-151.fDATA COLLECTION27-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15128-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-151.gBACK FILLING OF TRAIL PITS27-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15127-Jun-1527-Jun-15128-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-1528-Jun-151.hREPORTS PREPARATION28-Jun-1528-Jun-15128-Jun-1528-Jun-15128-Jun-1528-Jun-15128-Jun-1528-Jun-15128-Jun-1528-Jun-15128-Jun-1528-Jun-15129-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-151.iREPORTS SUBMISSION29-Jun-1529-Jun-15129-Jun-1529-Jun-15129-Jun-1529-Jun-15129-Jun-1529-Jun-15129-Jun-1529-Jun-15129-Jun-1529-Jun-15129-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-1529-Jun-152PROFILE DRAWING PREPARATION & Approvalls30-Jun-1510-Jul-1510ls30-Jun-1510-Jul-1510ls30-Jun-1510-Jul-1510ls30-Jun-1510-Jul-1510ls30-Jun-1510-Jul-1510ls30-Jun-1510-Jul-15103JB 1ST STAGEJB1 - FEEDER2JB2 - FEEDER2JB3 - FEEDER2JB4 - FEEDER2JB5 - FEEDER23.aMARKING1no.10-Aug-1510-Aug-1511no.02-Aug-1502-Aug-1511no.13-Jul-1513-Jul-1511no.12-Jul-1512-Jul-1511no.12-Jul-1512-Jul-15113-Jul-1513-Jul-1512-Jul-1512-Jul-1512-Jul-1512-Jul-153.bSETTING OUT VBU'S10-Aug-1510-Aug-15102-Aug-1502-Aug-15113-Jul-1513-Jul-15112-Jul-1512-Jul-15112-Jul-1512-Jul-15113-Jul-1513-Jul-1512-Jul-1512-Jul-1512-Jul-1512-Jul-153.cINSPECTION11-Aug-1511-Aug-15103-Aug-1503-Aug-15114-Jul-1514-Jul-15113-Jul-1513-Jul-15113-Jul-1513-Jul-15114-Jul-1514-Jul-1513-Jul-1513-Jul-1513-Jul-1513-Jul-153.dEXCAVATION18M311-Aug-1513-Aug-15318M303-Aug-1505-Aug-15318M314-Jul-1516-Jul-15318M313-Jul-1515-Jul-15318M313-Jul-1515-Jul-153JB (4.5*2.5*1.6) = 18 CUM15-Jul-1514-Jul-1515-Jul-1514-Jul-1515-Jul-153.eBLINDING1no.14-Aug-1514-Aug-1511no.06-Aug-1506-Aug-1511no.17-Jul-1517-Jul-1511no.16-Jul-1516-Jul-1511no.16-Jul-1516-Jul-1513.fINPECTION FOR BLINDING15-Aug-1515-Aug-15107-Aug-1507-Aug-15118-Jul-1518-Jul-15117-Jul-1517-Jul-15117-Jul-1517-Jul-1513.gBLINDING CONCRETE15-Aug-1515-Aug-15107-Aug-1507-Aug-15118-Jul-1518-Jul-15117-Jul-1517-Jul-15117-Jul-1517-Jul-1513.hWATER PROOFING16-Aug-1516-Aug-15108-Aug-1508-Aug-15119-Jul-1519-Jul-15118-Jul-1518-Jul-15118-Jul-1518-Jul-1513.iINSPECTION16-Aug-1516-Aug-15108-Aug-1508-Aug-15119-Jul-1519-Jul-15118-Jul-1518-Jul-15118-Jul-1518-Jul-1513.kSCREEDING16-Aug-1516-Aug-15108-Aug-1508-Aug-15119-Jul-1519-Jul-15118-Jul-1518-Jul-15118-Jul-1518-Jul-1513.lREINFORCEMENT SETTING FOR BASE SLAB & SIDE WALL17-Aug-1518-Aug-15209-Aug-1510-Aug-15220-Jul-1521-Jul-15219-Jul-1520-Jul-15219-Jul-1520-Jul-1523.mBASE SHUTTERING17-Aug-1518-Aug-15209-Aug-1510-Aug-15220-Jul-1521-Jul-15219-Jul-1520-Jul-15219-Jul-1520-Jul-1523.nINSPECTION19-Aug-1519-Aug-15111-Aug-1511-Aug-15122-Jul-1522-Jul-15121-Jul-1521-Jul-15121-Jul-1521-Jul-1513.oCONCRETE BASE19-Aug-1519-Aug-15111-Aug-1511-Aug-15122-Jul-1522-Jul-15121-Jul-1521-Jul-15121-Jul-1521-Jul-1513.pSIDE WALL20-Aug-1520-Aug-15112-Aug-1512-Aug-15123-Jul-1523-Jul-15122-Jul-1522-Jul-15122-Jul-1522-Jul-1513.qINSPECTION21-Aug-1521-Aug-15113-Aug-1513-Aug-15124-Jul-1524-Jul-15123-Jul-1523-Jul-15123-Jul-1523-Jul-1513.rCONCRETING21-Aug-1521-Aug-15113-Aug-1513-Aug-15124-Jul-1524-Jul-15123-Jul-1523-Jul-15123-Jul-1523-Jul-1513.SBORE HOLE EARTHING22-Aug-1524-Aug-15314-Aug-1516-Aug-15325-Jul-1527-Jul-15324-Jul-1526-Jul-15324-Jul-1526-Jul-1534RC OPEN CUTSection3 - FEEDER2 O/C-024.aRO PERMIT14.42M3NRNRRC O/C #01 (S3F1) type H Road crossing LxWxD is 10.3x1.4x1 = 14.42C.u.m.4.bVBU DIVERSION08-Aug-1508-Aug-1514.cMARKING09-Aug-1509-Aug-1514.dINSPECTION10-Aug-1510-Aug-1514.ePOLICE INSPECTIONNRNR4.fASPHALT CUTTING11-Aug-1512-Aug-1524.gEXCAVATION13-Aug-1514-Aug-1524.hDUCT SETTING ( PIPE SETTING)15-Aug-1516-Aug-1524.iINSPECTION17-Aug-1517-Aug-1514.JCONCRETING17-Aug-1517-Aug-1515RC HDDRC HDD#06 Section6 - FEEDER2RC HDD#08 Section6 - FEEDER25.aRO PERMIT83.37M22-Jun-1523-Jun-15210.3M11-Jul-1512-Jul-152Entry pit LxWxD is 3x3x3.5 =32Cu.m. Exit pit LxWxD is 2.5x2.5x3.5 =22Cu.m. Hence total Entry & Exit pit excavation for each HDD is 54Cu.m.22-Jun-1523-Jun-1511-Jul-1512-Jul-155.bTRAIL PITS EXCAVATION24-Jun-1525-Jun-15213-Jul-1513-Jul-15224-Jun-1525-Jun-1513-Jul-1513-Jul-155.cPROFILE DRAWING PREPARATION26-Jun-1528-Jun-15314-Jul-1516-Jul-15327-Jun-1530-Jun-1514-Jul-1516-Jul-155.dINSPECTION11-Jul-1511-Jul-15110-Aug-1510-Aug-15111-Jul-1511-Jul-155.eENTRY & EXIT PIT EXCAVATION54M312-Jul-1515-Jul-15454M311-Aug-1514-Aug-15412-Jul-1515-Jul-155.fINSPECTION83.37M19-Jul-1519-Jul-15114.4M15-Aug-1515-Aug-15116-07-1516-07-155.gPILOT DRILLING20-Jul-1522-Jul-15316-Aug-1517-Aug-15220-07-1520-07-155.hREEMING23-Jul-1528-Jul-15618-Aug-1520-Aug-15321-07-155.iPIPE PULLING29-Jul-1530-Jul-15221-Aug-1522-Aug-1525.jGROUTING31-Jul-1531-Jul-15123-Aug-1523-Aug-1515.kINPECTION & MEASUREMENT01-Aug-1501-Aug-15124-Aug-1524-Aug-1515.lBENTONITE FILLING02-Aug-1502-Aug-15125-Aug-1525-Aug-1516TRENCHINGSection1 - FEEDER2Section2 - FEEDER2Section3 - FEEDER2Section4 - FEEDER2Section5 - FEEDER2Section6 - FEEDER26.aMARKING919.8M314-Aug-1514-Aug-151919.8M301-Aug-1501-Aug-151905.38M304-Aug-1504-Aug-151915.6M309-Jul-1509-Jul-151915.6M309-Jul-1509-Jul-151798.882M324-Jul-1524-Jul-1511) SECTION LENGHT*1 MTR WIDTH*1.4 DEPTH = CUM10-Jul-1510-Jul-1509-Jul-1509-Jul-1514-Jul-1514-Jul-156.bINSPECTION15-Aug-1515-Aug-15102-Aug-1502-Aug-15105-Aug-1505-Aug-15110-Jul-1510-Jul-15110-Jul-1510-Jul-15125-Jul-1525-Jul-15111-Jul-1511-Jul-1510-Jul-1510-Jul-1515-Jul-1515-Jul-152) EXCAVATION WITH 2 EXCAVATORS WITH AVG 40 CUM /DAY FOR EACH SECTIONS6.cVBU'S SETTING15-Aug-1515-Aug-15102-Aug-1502-Aug-15105-Aug-1505-Aug-15110-Jul-1510-Jul-15110-Jul-1510-Jul-15125-Jul-1525-Jul-15112-Jul-1512-Jul-1510-Jul-1510-Jul-1515-Jul-1516-Jul-156.eEXCAVATION16-Aug-1526-Aug-151103-Aug-1512-Aug-151006-Aug-1516-Aug-151111-Jul-1521-Jul-151111-Jul-1521-Jul-151126-Jul-1504-Aug-151013-Jul-1530%11-Jul-1521-07-1521-Jul-1510%6.fTRENCH INSPECTION27-Aug-1527-Aug-15113-Aug-1513-Aug-15117-Aug-1517-Aug-15122-Jul-1522-Jul-15122-Jul-1522-Jul-15105-Aug-1505-Aug-1516.gSURPLUS REMOVAL28-Aug-1530-Aug-15314-Aug-1516-Aug-15318-Aug-1520-Aug-15323-Jul-1525-Jul-15323-Jul-1525-Jul-15306-Aug-1508-Aug-1537FTBSection1 - FEEDER2Section2 - FEEDER2Section3 - FEEDER2Section4 - FEEDER2Section5 - FEEDER2Section6 - FEEDER27.aFTB BEDDING657M31-Aug-1501-Sep-152657M15-Aug-1516-Aug-152657M21-Aug-1522-Aug-152654M06-Aug-1507-Aug-152654M28-Jul-1529-Jul-152654M26-Aug-1527-Aug-1527.bINSPECTION02-Sep-1502-Sep-15117-Aug-1517-Aug-15123-Aug-1523-Aug-15108-Aug-1508-Aug-15130-Jul-1530-Jul-15128-Aug-1528-Aug-1518CABLE PULLINGSection1 - FEEDER2Section2 - FEEDER2Section3 - FEEDER2Section4 - FEEDER2Section5 - FEEDER2Section6 - FEEDER28.aDRUM SHIFTING657M03-Sep-1503-Sep-151657M19-Aug-1519-Aug-151657M24-Aug-1524-Aug-151654M12-Aug-1512-Aug-151654M02-Aug-1502-Aug-151654M29-Aug-1529-Aug-1518.bFO & DTS PIPE SHIFTING03-Sep-1503-Sep-15119-Aug-1519-Aug-15124-Aug-1524-Aug-15112-Aug-1512-Aug-15102-Aug-1502-Aug-15129-Aug-1529-Aug-1518.cDUCT INSTALLATION04-Sep-1504-Sep-15120-Aug-1520-Aug-15125-Aug-1525-Aug-15113-Aug-1513-Aug-15103-Aug-1503-Aug-15130-Aug-1530-Aug-1518.dCABLE PULLING04-Sep-1504-Sep-15120-Aug-1520-Aug-15125-Aug-1525-Aug-15113-Aug-1513-Aug-15103-Aug-1503-Aug-15130-Aug-1530-Aug-1518.eINTERNAL SHEATH TEST05-Sep-1505-Sep-15121-Aug-1521-Aug-15126-Aug-1526-Aug-15114-Aug-1514-Aug-15104-Aug-1504-Aug-15131-Aug-1531-Aug-1518.fAS BUILT MEASUREMENT05-Sep-1505-Sep-15121-Aug-1521-Aug-15126-Aug-1526-Aug-15114-Aug-1514-Aug-15104-Aug-1504-Aug-15131-Aug-1531-Aug-1518.gEMPTY DRUM SHIFTING05-Sep-1505-Sep-15121-Aug-1521-Aug-15126-Aug-1526-Aug-15114-Aug-1514-Aug-15104-Aug-1504-Aug-15131-Aug-1531-Aug-1519CBSSection1 - FEEDER2Section2 - FEEDER2Section3 - FEEDER2Section4 - FEEDER2Section5 - FEEDER2Section6 - FEEDER29.aCBS BEDDING657M06-Sep-1507-Sep-152657M22-Aug-1523-Aug-152657M27-Aug-1528-Aug-152654M15-Aug-1516-Aug-152654M05-Aug-1506-Aug-152654M01-Sep-1502-Sep-1529.bINPECTION08-Sep-1508-Sep-15124-Aug-1524-Aug-15129-Aug-1529-Aug-15117-Aug-1517-Aug-15107-Aug-1507-Aug-15103-Sep-1503-Sep-15110TILES INTALLATIONSSection1 - FEEDER2Section2 - FEEDER2Section3 - FEEDER2Section4 - FEEDER2Section5 - FEEDER2Section6 - FEEDER210.aPROTECTION TILES INSTALLATION657M09-Sep-1510-Sep-152657M25-Aug-1526-Aug-152657M30-Aug-1531-Aug-152654M18-Aug-1519-Aug-152654M08-Aug-1509-Aug-152654M04-Sep-1505-Sep-15210.bTILES INSPECTION11-Sep-1511-Sep-15127-Aug-1527-Aug-15101-Sep-1501-Sep-15120-Aug-1520-Aug-15110-Aug-1510-Aug-15106-Sep-1506-Sep-15110.cFINAL SHEATH TEST11-Sep-1511-Sep-15127-Aug-1527-Aug-15101-Sep-1501-Sep-15120-Aug-1520-Aug-15110-Aug-1510-Aug-15106-Sep-1506-Sep-15111TRENCH BACKFILLINGSection1 - FEEDER2Section2 - FEEDER2Section3 - FEEDER2Section4 - FEEDER2Section5 - FEEDER2Section6 - FEEDER211.a1ST LAYER BACK FILLING657M12-Sep-1513-Sep-152657M28-Aug-1529-Aug-152657M02-Sep-1503-Sep-152654M21-Aug-1522-Aug-152654M11-Aug-1512-Aug-152654M07-Sep-1508-Sep-15211.bCOMPACTION TEST14-Sep-1514-Sep-15130-Aug-1530-Aug-15104-Sep-1504-Sep-15123-Aug-1523-Aug-15113-Aug-1513-Aug-15109-Sep-1509-Sep-15111.c2ND LAYER BACK FILLING14-Sep-1515-Sep-15230-Aug-1531-Aug-15204-Sep-1505-Sep-15223-Aug-1524-Aug-15213-Aug-1514-Aug-15209-Sep-1510-Sep-15211.dCOMPACTION TEST16-Sep-1516-Sep-15101-Sep-1501-Sep-15106-Sep-1506-Sep-15125-Aug-1525-Aug-15115-Aug-1515-Aug-15111-Sep-1511-Sep-15111.eWARNING TAPE INSTALLATION16-Sep-1516-Sep-15101-Sep-1501-Sep-15106-Sep-1506-Sep-15125-Aug-1525-Aug-15115-Aug-1515-Aug-15111-Sep-1511-Sep-15111.fWARNING TAPE INSPECTION17-Sep-1517-Sep-15102-Sep-1502-Sep-15107-Sep-1507-Sep-15126-Aug-1526-Aug-15116-Aug-1516-Aug-15112-Sep-1512-Sep-15111.g3RD LAYER BACK FILLING17-Sep-1518-Sep-15202-Sep-1503-Sep-15207-Sep-1508-Sep-15226-Aug-1527-Aug-15216-Aug-1517-Aug-15212-Sep-1513-Sep-15211.hCOMPACTION TEST19-Sep-1519-Sep-15104-Sep-1504-Sep-15109-Sep-1509-Sep-15128-Aug-1528-Aug-15118-Aug-1518-Aug-15114-Sep-1514-Sep-15111.i4TH LAYER BACK FILLING19-Sep-1520-Sep-15204-Sep-1505-Sep-15209-Sep-1510-Sep-15228-Aug-1529-Aug-15218-Aug-1519-Aug-15214-Sep-1515-Sep-15211.jCOMPACTION TEST21-Sep-1521-Sep-15106-Sep-1506-Sep-15111-Sep-1511-Sep-15130-Aug-1530-Aug-15120-Aug-1520-Aug-15116-Sep-1516-Sep-15111.k5TH LAYER BACK FILLING21-Sep-1522-Sep-15206-Sep-1507-Sep-15211-Sep-1512-Sep-15230-Aug-1531-Aug-15220-Aug-1521-Aug-15216-Sep-1517-Sep-15211.lCOMPACTION TEST23-Sep-1523-Sep-15108-Sep-1508-Sep-15113-Sep-1513-Sep-15101-Sep-1501-Sep-15122-Aug-1522-Aug-15118-Sep-1518-Sep-15112JB 2ND STAGESection1 - FEEDER2Section2 - FEEDER2Section3 - FEEDER2Section4 - FEEDER2Section5 - FEEDER212.aPARTETION WALL1No.07-Oct-1508-Oct-1521No.17-Sep-1518-Sep-1521No.06-Sep-1507-Sep-1521No.24-Aug-1525-Aug-1521No.27-Sep-1528-Sep-15212.bWATER PROOFING09-Oct-1509-Oct-15119-Sep-1519-Sep-15108-Sep-1508-Sep-15126-Aug-1526-Aug-15129-Sep-1529-Sep-15112.cPAINTING10-Oct-1510-Oct-15120-Sep-1520-Sep-15109-Sep-1509-Sep-15127-Aug-1527-Aug-15130-Sep-1530-Sep-15112.dINSPECTION11-Oct-1511-Oct-15121-Sep-1521-Sep-15110-Sep-1510-Sep-15128-Aug-1528-Aug-15101-Oct-1501-Oct-15112.eFTB & DUNE SAND BACK FILLING12-Oct-1512-Oct-15122-Sep-1522-Sep-15111-Sep-1511-Sep-15129-Aug-1529-Aug-15102-Oct-1502-Oct-15112.fLINK BOX & PD BOX INSTALLATION13-Oct-1513-Oct-15123-Sep-1523-Sep-15112-Sep-1512-Sep-15130-Aug-1530-Aug-15103-Oct-1503-Oct-15112.gINSPECTION14-Oct-1514-Oct-15124-Sep-1524-Sep-15113-Sep-1513-Sep-15131-Aug-1531-Aug-15104-Oct-1504-Oct-15113FO BLOWING & SPLICINGSection1 - FEEDER2Section2 - FEEDER2Section3 - FEEDER2Section4 - FEEDER2Section5 - FEEDER2Section6 - FEEDER213.aFO BLOWING657M20-Oct-1522-Oct-152657M20-Oct-1522-Oct-152657M20-Oct-1522-Oct-152654M20-Oct-1522-Oct-15265420-Oct-1522-Oct-15654M20-Oct-1522-Oct-15213.bSPLICING23-Oct-1523-Oct-15123-Oct-1523-Oct-15123-Oct-1523-Oct-15123-Oct-1523-Oct-15123-Oct-1523-Oct-1523-Oct-1523-Oct-15114ROUTE MARKER INSTALLATIONSNO24-Oct-1526-Oct-152NO24-Oct-1526-Oct-152NO24-Oct-1526-Oct-152NO24-Oct-1526-Oct-15224-Oct-1526-Oct-15NO24-Oct-1526-Oct-15215AS BUILT DRAWINGLs27-Oct-1528-Oct-152Ls27-Oct-1528-Oct-152Ls27-Oct-1528-Oct-152Ls27-Oct-1528-Oct-15227-Oct-1528-Oct-15Ls27-Oct-1528-Oct-15216HANDING OVERNo.29-Oct-1529-Oct-151No.29-Oct-1529-Oct-151No.29-Oct-1529-Oct-151No.29-Oct-1529-Oct-15129-Oct-1529-Oct-15No.29-Oct-1529-Oct-151LEGENDS :COMPLETEDPROGRESSBALANCEON HOLD

Roshan:200+

3628 C13 A2-FEEDER2.3628 C-13 A2 ( DSS TO AL BARAHA ) SCHEDULE PLANNING Feeder2Date : 26-Nov-1415-Oct-2014Section1 / JB1 - Feeder2Section2 / JB2 - Feeder2Section3 / JB3 - Feeder2Section4 / JB4 - Feeder2Section5 / JB5 - Feeder2Section6 / JB6 - Feeder2Section7 / JB7 - Feeder2Section8 / JB8 - Feeder2Section9 - Feeder2RemarksSl NoActivityQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDurationQuantityUnitsPlanned Start DatePlanned Finish DateDuration1TRAIL PITSSection1 / JB1 - Feeder2Section2 / JB2 - Feeder2Section3 / JB3 - Feeder2Section4 / JB4 - Feeder2Section5 / JB5 - Feeder2Section6 / JB6 - Feeder2Section7 / JB7 - Feeder2Section8 / JB8 - Feeder2Section9 - Feeder21.aSHIFTING & SETTING OUT VBU'S26-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-1411.bMARKING26-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-14126-Nov-1426-Nov-1411.cMARKING INSPECTION27-Nov-1427-Nov-14127-Nov-1427-Nov-14127-Nov-1427-Nov-14127-Nov-1427-Nov-14127-Nov-1427-Nov-14127-Nov-1427-Nov-14127-Nov-1427-Nov-14127-Nov-1427-Nov-14127-Nov-1427-Nov-1411.dTRAIL PIT EXCAVATION28-Nov-1428-Nov-14128-Nov-1428-Nov-14128-Nov-1428-Nov-14128-Nov-1428-Nov-14128-Nov-1428-Nov-14128-Nov-1428-Nov-14128-Nov-1428-Nov-14128-Nov-1428-Nov-14128-Nov-1428-Nov-1411.eINSPECTION OF EXCAVATION29-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-1411.fDATA COLLECTION29-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-1411.gBACK FILLING OF TRAIL PITS29-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-1411.hREPORTS PREPARATION29-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-14129-Nov-1429-Nov-1411.iREPORTS SUBMISSION30-Nov-1430-Nov-14130-Nov-1430-Nov-14130-Nov-1430-Nov-14130-Nov-1430-Nov-14130-Nov-1430-Nov-14130-Nov-1430-Nov-14130-Nov-1430-Nov-14130-Nov-1430-Nov-14130-Nov-1430-Nov-1412PROFILE DRAWING PREPARATIONls29-Nov-1405-Dec-147ls29-Nov-1405-Dec-147ls29-Nov-1405-Dec-147ls29-Nov-1405-Dec-147ls29-Nov-1405-Dec-147ls29-Nov-1405-Dec-147ls29-Nov-1405-Dec-147ls29-Nov-1405-Dec-147ls29-Nov-1405-Dec-1473JB 1ST STAGEJB1 - Feeder2JB2 - Feeder2JB3 - Feeder2JB4 - Feeder2JB5 - Feeder2JB6 - Feeder2JB7 - Feeder2JB8 - Feeder23.aMARKING1no.06-Dec-1406-Dec-1411no.06-Dec-1406-Dec-1411no.06-Dec-1406-Dec-1411no.06-Dec-1406-Dec-1411no.06-Dec-1406-Dec-1411no.06-Dec-1406-Dec-1411no.06-Dec-1406-Dec-1411no.06-Dec-1406-Dec-141JB area LxWxD is 9.6x3.5x1.45 = 48Cu.m & Snaking area LxWxD is 10x3.5x1.45x2 sides = 102Cu.m. Hence Total JB+Sanking area Excavation is 150Cu.m.3.bSETTING OUT VBU'S06-Dec-1406-Dec-14106-Dec-1406-Dec-14106-Dec-1406-Dec-14106-Dec-1406-Dec-14106-Dec-1406-Dec-14106-Dec-1406-Dec-14106-Dec-1406-Dec-14106-Dec-1406-Dec-1413.cINSPECTION07-Dec-1407-Dec-14107-Dec-1407-Dec-14107-Dec-1407-Dec-14107-Dec-1407-Dec-14107-Dec-1407-Dec-14107-Dec-1407-Dec-14107-Dec-1407-Dec-14107-Dec-1407-Dec-1413.dEXCAVATION150M308-Dec-1411-Dec-144150M308-Dec-1411-Dec-144150M308-Dec-1411-Dec-144150M308-Dec-1411-Dec-144150M312-Dec-1415-Dec-144150M312-Dec-1415-Dec-144150M312-Dec-1415-Dec-144150M312-Dec-1415-Dec-1443.eBLINDING1no.12-Dec-1412-Dec-1411no.12-Dec-1412-Dec-1411no.12-Dec-1412-Dec-1411no.12-Dec-1412-Dec-1411no.16-Dec-1416-Dec-1411no.16-Dec-1416-Dec-1411no.16-Dec-1416-Dec-1411no.16-Dec-1416-Dec-1413.fINPECTION FOR BLINDING13-Dec-1413-Dec-14113-Dec-1413-Dec-14113-Dec-1413-Dec-14113-Dec-1413-Dec-14117-Dec-1417-Dec-14117-Dec-1417-Dec-14117-Dec-1417-Dec-14117-Dec-1417-Dec-1413.gBLINDING CONCRETE13-Dec-1413-Dec-14113-Dec-1413-Dec-14113-Dec-1413-Dec-14113-Dec-1413-Dec-14117-Dec-1417-Dec-14117-Dec-1417-Dec-14117-Dec-1417-Dec-14117-Dec-1417-Dec-1413.hWATER PROOFING14-Dec-1414-Dec-14114-Dec-1414-Dec-14114-Dec-1414-Dec-14114-Dec-1414-Dec-14118-Dec-1418-Dec-14118-Dec-1418-Dec-14118-Dec-1418-Dec-14118-Dec-1418-Dec-1413.iINSPECTION14-Dec-1414-Dec-14114-Dec-1414-Dec-14114-Dec-1414-Dec-14114-Dec-1414-Dec-14118-Dec-1418-Dec-14118-Dec-1418-Dec-14118-Dec-1418-Dec-14118-Dec-1418-Dec-1413.kSCREEDING14-Dec-1414-Dec-14114-Dec-1414-Dec-14114-Dec-1414-Dec-14114-Dec-1414-Dec-14118-Dec-1418-Dec-14118-Dec-1418-Dec-14118-Dec-1418-Dec-14118-Dec-1418-Dec-1413.lREINFORCEMENT SETTING FOR BASE SLAB & SIDE WALL15-Dec-1416-Dec-14215-Dec-1416-Dec-14215-Dec-1416-Dec-14215-Dec-1416-Dec-14219-Dec-1420-Dec-14219-Dec-1420-Dec-14219-Dec-1420-Dec-14219-Dec-1420-Dec-1423.mBASE SHUTTERING15-Dec-1416-Dec-14215-Dec-1416-Dec-14215-Dec-1416-Dec-14215-Dec-1416-Dec-14219-Dec-1420-Dec-14219-Dec-1420-Dec-14219-Dec-1420-Dec-14219-Dec-1420-Dec-1423.nINSPECTION17-Dec-1417-Dec-14117-Dec-1417-Dec-14117-Dec-1417-Dec-14117-Dec-1417-Dec-14121-Dec-1421-Dec-14121-Dec-1421-Dec-14121-Dec-1421-Dec-14121-Dec-1421-Dec-1413.oCONCRETE BASE17-Dec-1417-Dec-14117-Dec-1417-Dec-14117-Dec-1417-Dec-14117-Dec-1417-Dec-14121-Dec-1421-Dec-14121-Dec-1421-Dec-14121-Dec-1421-Dec-14121-Dec-1421-Dec-1413.pSIDE WALL18-Dec-1418-Dec-14118-Dec-1418-Dec-14118-Dec-1418-Dec-14118-Dec-1418-Dec-14122-Dec-1422-Dec-14122-Dec-1422-Dec-14122-Dec-1422-Dec-14122-Dec-1422-Dec-1413.qINSPECTION19-Dec-1419-Dec-14119-Dec-1419-Dec-14119-Dec-1419-Dec-14119-Dec-1419-Dec-14123-Dec-1423-Dec-14123-Dec-1423-Dec-14123-Dec-1423-Dec-14123-Dec-1423-Dec-1413.rCONCRETING19-Dec-1419-Dec-14119-Dec-1419-Dec-14119-Dec-1419-Dec-14119-Dec-1419-Dec-14123-Dec-1423-Dec-14123-Dec-1423-Dec-14123-Dec-1423-Dec-14123-Dec-1423-Dec-1413.SBORE HOLE EARTHING20-Dec-1422-Dec-14323-Dec-1426-Dec-14327-Dec-1430-Dec-14331-Dec-1403-Jan-15304-Jan-1507-Jan-15308-Jan-1511-Jan-15312-Jan-1515-Jan-15316-Jan-1519-Jan-1534RC OPEN CUTSection1 - Feeder2 O/C-02Section3 - Feeder2 ACC-02section8 - Feeder2 O/C-04section8 - Feeder2 O/C-06section8 - Feeder2 O/C-084.aRO PERMIT61M3NRNR234M3NRNR72M3NRNR202M3NRNR205M3NRNRRC O/C #02 (S9F1) type H Road crossing LxWxD is 17x2.4x1.5 = 61Cu.m. RC ACC #03 (S3F1) LxWxD is 65*2.4*1.5=234 RC O/C #04 (S8F1) 20*2.4*1.5=72 RC O/C #06 (S8F1) 56*2.4*1.5=202 RC O/C #08 (S8F1) 57*2.4*1.5=2054.bVBU DIVERSION11-Dec-1411-Dec-14126-Dec-1426-Dec-14112-Dec-1412-Dec-14112-Dec-1412-Dec-14112-Dec-1412-Dec-1414.cMARKING12-Dec-1412-Dec-14127-Dec-1427-Dec-14113-Dec-1413-Dec-14113-Dec-1413-Dec-14113-Dec-1413-Dec-1414.dINSPECTION12-Dec-1412-Dec-14127-Dec-1427-Dec-14113-Dec-1413-Dec-14113-Dec-1413-Dec-14113-Dec-1413-Dec-1414.ePOLICE INSPECTIONNRNRNRNRNRNRNRNRNRNR4.fASPHALT CUTTING13-Dec-1415-Dec-14328-Dec-1402-Jan-15616-Dec-1418-Dec-14319-Dec-1424-Dec-14625-Dec-1431-Dec-1474.gEXCAVATION13-Dec-1415-Dec-14328-Dec-1402-Jan-15616-Dec-1418-Dec-14319-Dec-1424-Dec-14625-Dec-1431-Dec-1474.hDUCT SETTING ( PIPE SETTING)16-Dec-1418-Dec-14303-Jan-1505-Jan-15319-Dec-1421-Dec-14325-Dec-1427-Dec-14301-Jan-1503-Jan-1534.iINSPECTION19-Dec-1419-Dec-14106-Jan-1506-Jan-15122-Dec-1422-Dec-14128-Dec-1428-Dec-14104-Jan-1504-Jan-1514.JCONCRETING19-Dec-1419-Dec-14106-Jan-1506-Jan-15122-Dec-1422-Dec-14128-Dec-1428-Dec-14104-Jan-1504-Jan-1515RC HDDRC HDD#02 Section9 - Feeder2RC HDD#04 Section9 - Feeder25.aRO PERMIT23M12-Dec-1413-Dec-14220M12-Dec-1413-Dec-142Entry pit LxWxD is 3x3x3.5 =32Cu.m. Exit pit LxWxD is 2.5x2.5x3.5 =22Cu.m. Hence total Entry & Exit pit excavation for each HDD is 54Cu.m.5.bTRAIL PITS EXCAVATION14-Dec-1415-Dec-14214-Dec-1415-Dec-1425.cPROFILE DRAWING PREPARATION16-Dec-1418-Dec-14316-Dec-1418-Dec-1435.dINSPECTION19-Dec-1419-Dec-14119-Dec-1419-Dec-1415.eENTRY & EXIT PIT EXCAVATION54M320-Dec-1423-Dec-14454M324-Dec-1427-Dec-1445.fINSPECTION23M24-Dec-1424-Dec-14120M28-Dec-1428-Dec-1415.gPILOT DRILLING25-Dec-1428-Dec-14405-Jan-1508-Jan-1545.hREEMING29-Dec-1403-Jan-15609-Jan-1514-Jan-1565.iPIPE PULLING04-Jan-1504-Jan-15115-Jan-1515-Jan-1515.jGROUTING05-Jan-1505-Jan-15116-Jan-1516-Jan-1515.kINPECTION & MEASUREMENT06-Jan-1506-Jan-15117-Jan-1517-Jan-1515.lBENTONITE FILLING6TRENCHINGSection1 - Feeder2Section2 - Feeder2Section3 - Feeder2Section4 - Feeder2Section5 - Feeder2Section6 - Feeder2Section7 - Feeder2Section8 - Feeder2Section9 - Feeder26.aMARKING1169.3M306-Dec-1406-Dec-1411151.88M306-Dec-1406-Dec-141969.18M313-Nov-1413-Nov-1411082.28M313-Nov-1413-Nov-1411113.6M313-Nov-1413-Nov-1411113.6M313-Nov-1413-Nov-1411113.6M313-Nov-1413-Nov-141880.44M313-Nov-1413-Nov-1411160.6M313-Nov-1413-Nov-141Trench WxD is 1.2x1.45. Snaking area at Substation for S1 & S9 LxWxD is 33x2.8x1.45 =134Cu.m.6.bINSPECTION07-Dec-1407-Dec-14107-Dec-1407-Dec-14114-Nov-1414-Nov-14114-Nov-1414-Nov-14114-Nov-1414-Nov-14114-Nov-1414-Nov-14114-Nov-1414-Nov-14114-Nov-1414-Nov-14114-Nov-1414-Nov-1416.cVBU'S SETTING07-Dec-1407-Dec-14107-Dec-1407-Dec-14114-Nov-1414-Nov-14114-Nov-1414-Nov-14114-Nov-1414-Nov-14114-Nov-1414-Nov-14114-Nov-1414-Nov-14114-Nov-1414-Nov-14114-Nov-1414-Nov-1416.eEXCAVATION03-Feb-1509-Feb-15708-Dec-1415-Dec-14816-Dec-1422-Dec-14723-Dec-1429-Dec-14730-Dec-1405-Jan-15706-Jan-1512-Jan-15713-Jan-1519-Jan-15720-Jan-1526-Jan-15727-Jan-1502-Feb-1576.fTRENCH INSPECTION10-Feb-1510-Feb-15116-Dec-1416-Dec-14123-Dec-1423-Dec-14130-Dec-1430-Dec-14106-Jan-1506-Jan-15113-Jan-1513-Jan-15120-Jan-1520-Jan-15127-Jan-1527-Jan-15103-Feb-1503-Feb-1516.gSURPLUS REMOVAL11-Feb-1513-Feb-15317-Dec-1419-Dec-14324-Dec-1426-Dec-14331-Dec-1402-Jan-15307-Jan-1509-Jan-15314-Jan-1516-Jan-15321-Jan-1523-Jan-15328-Jan-1530-Jan-15304-Feb-1506-Feb-1537FTBSection1 - Feeder2Section2 - Feeder2Section3 - Feeder2Section4 - Feeder2Section5 - Feeder2Section6 - Feeder2Section7 - Feeder2Section8 - Feeder2Section9 - Feeder27.aFTB BEDDING655M12-Feb-1513-Feb-152662M18-Dec-1419-Dec-142622M25-Dec-1426-Dec-142622M01-Jan-1502-Jan-152662M08-Jan-1509-Jan-152640M15-Jan-1516-Jan-152648M22-Jan-1523-Jan-152630M29-Jan-1530-Jan-152503M05-Feb-1506-Feb-1527.bINSPECTION14-Feb-1514-Feb-15120-Dec-1420-Dec-14127-Dec-1427-Dec-14103-Jan-1503-Jan-15110-Jan-1510-Jan-15117-Jan-1517-Jan-15124-Jan-1524-Jan-15131-Jan-1531-Jan-15107-Feb-1507-Feb-1518CABLE PULLINGSection1 - Feeder2Section2 - Feeder2Section3 - Feeder2Section4 - Feeder2Section5 - Feeder2Section6 - Feeder2Section7 - Feeder2Section8 - Feeder2Section9 - Feeder28.aDRUM SHIFTING655M662M622M622M662M640M648M630M630M8.bFO & DTS PIPE SHIFTING8.cDUCT INSTALLATION8.dCABLE PULLING8.eINTERNAL SHEATH TEST8.fAS BUILT MEASUREMENT8.gEMPTY DRUM SHIFTING9CBS9.aCBS BEDDING655M662M622M622M662M640M648M630M503M9.bINPECTION10TILES INTALLATIONS10.aPROTECTION TILES INSTALLATION655M662M622M622M662M640M648M630M503M10.bTILES INSPECTION10.cFINAL SHEATH TEST11TRENCH BACKFILLING11.a1ST LAYER BACK FILLING655M662M622M622M662M640M648M630M503M11.bCOMPACTION TEST11.c2ND LAYER BACK FILLING11.dCOMPACTION TEST11.eWARNING TAPE INSTALLATION11.fWARNING TAPE INSPECTION11.g3RD LAYER BACK FILLING11.hCOMPACTION TEST11.i4TH LAYER BACK FILLING11.jCOMPACTION TEST11.k5TH LAYER BACK FILLING11.lCOMPACTION TEST12JB 2ND STAGE12.aPARTETION WALL1No.1No.1No.1No.1No.1No.1No.1No.1No.12.bWATER PROOFING12.cPAINTING12.dINSPECTION12.eFTB & DUNE SAND BACK FILLING12.fLINK BOX & PD BOX INSTALLATION12.gINSPECTION13FO BLOWING & SPLICING13.aFO BLOWING655M662M622M622M662M640M648M630M503M13.bSPLICING14ROUTE MARKER INSTALLATIONS22NO22NO21NO21NO22NO21NO22NO21NO17NO15AS BUILT DRAWINGLsLsLsLsLsLsLsLsLs16HANDING OVER1No.1No.1No.1No.1No.1No.1No.1No.1No.LEGENDS : COMPLETEDPROGRESSBALANCEON HOLD