3.25.2008 RSC
An Overview ofFill-In-the-Blanks (FIB) Reliability
Standards
Farzaneh TafreshiManager, Reliability Standards
Texas Regional [email protected]
RSC3.25.2008
2
Regional Reliability Standards
● Any Regional Entity may develop, through its own processes, separate Standards that go beyond, add detail to, or implement NERC Reliability Standards
● A Regional Standard shall be more stringent than a continent-wide reliability standard, including a regional difference that addresses matters that the continent-wide reliability standard does not, or shall be a regional difference necessitated by a physical difference in the bulk power system
RSC3.25.2008
3
Regional Reliability Standards (Cont.)
● Proposed Reliability Standards shall be subject to approval by NERC, as the Electric Reliability Organization (ERO) , and by FERC before becoming mandatory and enforceable under Section 215 of the FPA.
● No Standard shall be effective within the Texas RE area unless filed by NERC with FERC and approved by FERC.
RSC3.25.2008
4
Regional Reliability Standards (Cont.)
● The NERC Regional Reliability Standards Working Group (RRSWG) was established in May of 2006
● Manage the development of specific regional reliability standards and the development of regional information for certain NERC reliability standards, based on the NERC three-year standards work plan
RSC3.25.2008
5
Regional Reliability Standards (Cont.)
● The RRSWG group coordinates regional activities that are intrinsically related to the development of Regional Reliability Standards between the eight Regional Entities, NERC staff, and industry volunteers working on NERC reliability standards
● The RRSWG has identified 4 NERC standards to have FIB characteristics and has recommended to have four Regional Reliability Standards to be developed by each region in support of those NERC standards
RSC3.25.2008
6
Intended Number of Regional Standards
● NERC’s 3 year plan (2008 through 2010) has listed specific projects to address various issues by grouping similar standards.
● Reliability Standards Work Plan: 2008-2010
● Volume III: Regional Reliability Standards Projects
RSC3.25.2008
7
Fill in the Blank Standards
● Project 2007-01 Underfrequency Load Shedding
● Project 2007-05 Balancing Authority Controls
● Project 2007-11 Disturbance Monitoring
● Project 2008-04 Protection Systems
RSC3.25.2008
8
Project 2007-01 Underfrequency Load Shedding
PRC-006 — Development and Documentation of Regional ReliabilitOrganizations Underfrequency Load Shedding ProgramsPRC-007 — Assuring Consistency with Regional UFLS Programs
PRC-009 — UFLS Performance Following an Underfrequency Event
http://www.nerc.com/~filez/standards/Underfrequency_Load_Shedding.html
StatusFirst draft to be posted for comments around April 2008
RSC3.25.2008
9
UFLS Project Schedule
RSC3.25.2008
10
Project 2007-05 Balancing Authority Controls
BAL-002, and BAL-004 to BAL-006
BAL-002 — Disturbance Control Performance
http://www.nerc.com/~filez/standards/Balancing_Authority_Controls_Project_2007-05.html
Status
The Standards Committee is seeking industry experts to serve on the Balancing Authority Control Standard drafting Team beginning January 2, 2008.
RSC3.25.2008
11
BA Project Schedule
RSC3.25.2008
12
Project 2007-11 Disturbance Monitoring
PRC-002 — Define and Document Disturbance Monitoring and Equipment Requirements
PRC-018 — Disturbance Monitoring Equipment Installation and Data
http://www.nerc.com/~filez/standards/Disturbance_Monitoring_Project_2007-11.html
StatusMay change to a continent wide standard
RSC3.25.2008
13
DM Project Schedule
RSC3.25.2008
14
Project 2009-06 Protection Systems
PRC-003,PRC-004, PRC-012, PRC-014, and PRC-016
PRC-012 — Special Protection System Review
Status No update is available at this time
RSC3.25.2008
15
Next Step/ Updates
● An update on the status of all NERC FIB standards projects will be provided to the RRSWG at the March 26 meeting in Charlotte
● The regions will also discuss their regional standards activities
● An update will be provided to RSC at the April meeting