ASX: BOW Bow Energy Limited ACN 111 019 857 Street Level 7, 10 Eagle street, Brisbane QLD 4000 Post GPO Box 5244, Brisbane QLD 4001 Phone +61 7 3238 6300 Fax +61 7 3238 6399 Web www.bowenergy.com.au Email [email protected] 30 September 2010 Quarterly Report Highlights Promotion to S&P/ASX200 Index Bow was promoted to the S&P/ASX200 Index, effective after the close of business on 27 September 2010. The S&P/ASX200 Index is recognised as the primary investable benchmark in Australia, covering around 82% of Australian equity market capitalisation. Bow Targets Continued Reserves Growth Bow’s current gas reserves/resources and end 2011 gas reserves targets are summarised below. Project (all 100% unless stated otherwise) Current Certified Reserves/Resources End 2011 Reserve Targets 2C Resources (PJ net to Bow) 3P Reserves (PJ net to Bow) 2P Reserves (PJ net to Bow) 3P Reserves (PJ net to Bow) 2P Reserves (PJ net to Bow) Blackwater CSG Field* 435 1,382 59 1,600 450 Comet CSG Field* 439 871 1,000 200 Vermont CSG Field (within ATP1031P) 1,402 1,400 200 Norwich Project (within ATP1031P) 625 100 Dysart Project (within ATP1031P) 625 100 Gunyah Project (ATP 1053) 600 100 Bandanna Project (ATP 805) 200 Don Juan Project (55%) 107 55 150 100 Total Reserves (net PJ to Bow) 2,276 2,360 114 6,200 1,250 * 286PJ of 3P and 7PJ of 2P gas reserves included above is over land awaiting conclusion of native title processes which are in progress. Drilling Success at Norwich Park Indicates Large Gas Field The first six core holes have been drilled and completed (VM1, VM2, VM3, NW1, NW2 and NW3) within the Vermont CSG Prospect and Norwich CSG Prospect of ATP1031P. The core holes intersected an average of 60 metres of gassy coals. Bow obtained an initial certification of 2C (contingent) resource of 1,402 PJ in the Vermont CSG Prospect. Preliminary results from the drilling at the Norwich CSG Project indicate it could be of similar size and prospectivity to Vermont. Pilot Production Programs Underway at Blackwater Bow has started trialling several well completion techniques in the Blackwater CSG Field. The first ‘four spot’ vertical frac well pilot has been successful at fracturing the targeted zones and increasing permeability. A further ‘four spot’ vertical frac well pilot is scheduled to commence in Nov 2010. Both ‘four spot’ pilots are expected to be completed with pumping equipment by Dec 2010. Additionally two parallel lateral (horizontal) pilot wells drilling into an eight metre Rangal coal seam target are underway and also planned for completion in Dec 2010. Both completion methods have been successful in yielding commercial gas flows in other Bowen Basin CSG producing fields. Gas Development Strategy Bow has advanced discussions with a number of counterparties for significant volumes of longterm offtake gas arrangements. Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt gasfired Blackwater Power Project located approximately 15 kilometres northeast of the town of Blackwater. The first seven of ten GE Jenbacher engines have been delivered to site. The Blackwater Power Project will require around 2PJ of cleanburning coal seam gas (CSG) per annum which will be supplied from Bow’s underlying Blackwater CSG Field. Cash of $54.8 million at end of quarter

30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

ASX: BOW Bow Energy Limited ∙ ACN 111 019 857 ∙ Street Level 7, 10 Eagle street, Brisbane QLD 4000 ∙ Post GPO Box 5244, Brisbane QLD 4001 

Phone +61 7 3238 6300  ∙  Fax +61 7 3238 6399  ∙  Web www.bowenergy.com.au  ∙  Email [email protected]  

30 September 2010 Quarterly Report – HighlightsPromotion to S&P/ASX200 Index Bow was promoted to the S&P/ASX200 Index, effective after the close of business on 27 September 2010.  The S&P/ASX200  Index  is  recognised  as  the  primary  investable  benchmark  in  Australia,  covering  around  82%  of Australian equity market capitalisation.  

Bow Targets Continued Reserves Growth  Bow’s current gas reserves/resources and end 2011 gas reserves targets are summarised below.      

Project  (all 100% unless stated otherwise) 

Current Certified Reserves/Resources 

End 2011Reserve Targets 

2CResources (PJ net to Bow) 

3P Reserves (PJ net to Bow) 

2P Reserves  (PJ net to Bow) 

3P Reserves (PJ net to Bow) 

2P Reserves (PJ net to Bow) 

Blackwater CSG Field*   435  1,382  59  1,600  450

Comet CSG Field*   439  871  ‐  1,000  200

Vermont CSG Field (within ATP1031P)  1,402  ‐  ‐  1,400  200

Norwich Project (within ATP1031P)  ‐  ‐  ‐  625  100

Dysart Project (within ATP1031P)  ‐  ‐  ‐  625  100

Gunyah Project (ATP 1053)  ‐  ‐  ‐  600  100

Bandanna Project (ATP 805)  ‐  ‐  ‐  200  ‐

Don Juan Project (55%)   ‐  107  55  150  100

Total Reserves (net PJ to Bow)   2,276  2,360  114  6,200  1,250

*  286PJ of 3P and 7PJ of 2P gas reserves included above is over land awaiting conclusion of native title processes which are in progress. 

Drilling Success at Norwich Park Indicates Large Gas Field  The first six core holes have been drilled and completed (VM‐1, VM‐2, VM‐3, NW‐1, NW‐2 and NW‐3) within the Vermont CSG Prospect and Norwich CSG Prospect of ATP1031P.   The core holes  intersected an average of 60 metres  of  gassy  coals.    Bow  obtained  an  initial  certification  of  2C  (contingent)  resource  of  1,402  PJ  in  the Vermont CSG Prospect.   Preliminary results from the drilling at the Norwich CSG Project  indicate  it could be of similar size and prospectivity to Vermont.   

Pilot Production Programs Underway at Blackwater Bow has  started  trialling  several well  completion  techniques  in  the Blackwater CSG Field. The  first  ‘four  spot’ vertical frac well pilot has been successful at fracturing the targeted zones and increasing permeability. A further ‘four spot’ vertical frac well pilot is scheduled to commence in Nov 2010. Both ‘four spot’ pilots are expected to be  completed with pumping  equipment by Dec 2010. Additionally  two parallel  lateral  (horizontal) pilot wells drilling into an eight metre Rangal coal seam target are underway and also planned for completion in Dec 2010.  Both  completion methods  have  been  successful  in  yielding  commercial  gas  flows  in  other  Bowen  Basin  CSG producing fields.  

Gas Development Strategy Bow has advanced discussions with a number of counterparties for significant volumes of long‐term off‐take gas arrangements.   

Blackwater Power Project Commences Construction Bow  has  commenced  the  construction  on  its  100%  owned  30 megawatt  gas‐fired  Blackwater  Power  Project located approximately 15 kilometres north‐east of the town of Blackwater.  The first seven of ten GE Jenbacher engines have been delivered to site.  The Blackwater Power Project will require around 2PJ of clean‐burning coal seam gas (CSG) per annum which will be supplied from Bow’s underlying Blackwater CSG Field. 

Cash of $54.8 million at end of quarter 

Page 2: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 2 

Bow Energy Limited Quarterly Report ending 30 September 2010     

Events Subsequent to 30 September 2010  Blackwater CSG Field – Pilot programs targeting commercial gas flows  Initial Fracture Work Successful   Initial  fracture  stimulations  (fracs)  have  been  completed  on  the  northern  ‘four  spot’  CSG fracture pilot, located about four kilometres west of the Blackwater Power Project.  The fracs were successful at fracturing the targeted zones and pumping sand to prop open the induced fractures  in the coals.   All of the fracced wells are expected to be completed for production testing during November.  While  the  initial  frac  work  was  successful  in  increasing  permeability,  gas  flows  are  not expected until these frac wells are completed with pumping equipment and dewatering of the target seams is in progress.    Lateral drilling has  commenced  after  vertical wells  encounter  free  gas  and  indications  of permeability in the thick target coal. The vertical production and  flush wells  for Bow’s  first  lateral CSG pilot program have been drilled  and  cased.    The  target  seam  varied  in  thickness  from  four  to  eight metres  and  the vertical wells encountered  live gas shows and good  indications of permeability during post‐drilling  flushing of  the holes.   A  surface  to  inseam  (SIS)  lateral  rig  is being used  to drill  the lateral well pilot program.  Lateral drilling and completions have been successful  in obtaining commercial gas flow rates in adjacent tenements and numerous other CSG and underground mine areas of the Bowen Basin.    Early results at Norwich Park confirm at least one large gas field   Bow has  identified  three high potential CSG prospects within  this block; Vermont, Norwich and Dysart. To date  six  core holes have been  completed within  the Vermont  and Norwich Prospects.    Bow Energy has obtained an  initial 2C  (contingent)  resource  certification of 1,402 PJ  in  the Vermont  CSG  Field  from  the  results  of  the  first  three  core‐holes  (VM‐1, VM‐2  and VM‐3).  Adjacent and to the southeast of the Vermont CSG Field is the Norwich Prospect.  Recent data from the three core holes in the Norwich prospect (NW‐1, NW‐2 and NW‐3) indicate it could be of similar size and prospectivity to Vermont.  Drilling has also recently commenced on the Dysart Prospect with the first of three core holes (DY‐3) spudded in October 2010.  Permeability  testing  is  currently being  carried out on  the Vermont  and Norwich  CSG wells targeting 2C to 3P and 2P reserve upgrades.   Federal Government Approves Third Party Gladstone LNG Projects  On  22 October  2010  the  Federal Government  approved  two major  CSG‐supplied  liquefied natural gas projects to be located at Gladstone.  The approvals are conditional on maintaining the highest environmental standards in construction and operation, including comprehensive water management requirements.   

Page 3: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 3 

Bow Energy Limited Quarterly Report ending 30 September 2010     

TABLE OF CONTENTS  

30 SEPTEMBER 2010 QUARTERLY REPORT – HIGHLIGHTS  1 

EVENTS SUBSEQUENT TO 30 SEPTEMBER 2010  2 

1.  STRATEGIC MILESTONES FOR BOW ENERGY  4 

2.  EXPLORATION, APPRAISAL AND PRODUCTION  5 COAL SEAM GAS (CSG) ACTIVITIES  5 

CURRENT CERTIFIED RESERVES AND RESERVES TARGETS  5 GAS IN PLACE OF OVER 13.8 TRILLION CUBIC FEET  5 INITIAL WATER MANAGEMENT ASSESSMENT IN NORTHERN BOWEN BASIN  7 ATP 1025P COMET BLOCK (Bow 100%)  7 ATP 1053P GUNYAH CSG PROJECT (BOW 100%)  10 ATP 805P BANDANA CSG PROJECT (BOW 100%)  11 SURAT BASIN DON JUAN CSG FIELD (Bow 55%)  11 

CONVENTIONAL OIL AND GAS ACTIVITIES  13 TECHNICAL REVIEW OF CONVENTIONAL ASSETS  13 COOPER BASIN  13 CENTRAL EROMANGA BASIN (Bow 40‐100%)  14 SURAT‐BOWEN BASIN  15 CLARENCE‐MORETON BASIN  15 CARNARVON BASIN ACTIVITIES  15 

3.  COMMERCIAL ACTIVITIES  16 GAS DEVELOPMENT STRATEGY  16 CONSTRUCTION COMMENCES ON BLACKWATER POWER PROJECT  17 

4.  EXECUTIVE APPOINTMENTS  18 

5.  BOW’S PLANNED ACTIVITIES FOR THE NEXT QUARTER  19 EXPLORATION, APPRAISAL AND PRODUCTION  19 COMMERCIAL ACTIVITIES  19 PL APPLICATIONS TO CONTINUE  19 

CORPORATE INFORMATION & DIRECTORY  20 

 

Page 4: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 4 

Bow Energy Limited Quarterly Report ending 30 September 2010     

1. STRATEGIC MILESTONES FOR BOW ENERGY  Bow  will  continue  to  develop  its  upstream  resource,  with  the  target  of  significant  gas production  from  2013.    In  parallel  with  production  growth,  Bow  will  continue  to  pursue multiple monetisation strategies including export LNG, electricity generation and domestic gas sales.  Discussions  with  counter  parties  for  long  term  gas  off‐take  for  significant  volumes  have continued.   Gas demand volumes  range  from 15  to 30PJ per annum  for  long  term 15 year contracts.  

Milestone  Indicative Timing o Reserves growth and commencement of gas 

production pilots o Commenced construction of the Blackwater Power 

Project

2010

o Continued reserves and gas production growth  o Blackwater Power Project commissioning o Seek development approvals: gas field and pipeline to 

Gladstone approvals  2011

o CSG field development and approvals o Conditional off take arrangements 

Late 2011 onwards

o Commence construction pipeline to Gladstone  Mid‐2012 to Mid‐2013

Sales:    Additional power generation, domestic supply    and/or LNG sales  Mid‐2013 Onwards

 

Page 5: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 5 

Bow Energy Limited Quarterly Report ending 30 September 2010     

 

2. EXPLORATION, APPRAISAL AND PRODUCTION  

COAL SEAM GAS (CSG) ACTIVITIES  

CURRENT CERTIFIED RESERVES AND RESERVES TARGETS  Bow has eight CSG projects in the Surat and Bowen Basins that have been, or are scheduled to be explored and appraised during 2010 and 2011.  Bow was granted 100% of the Comet (ATP 1025P) and Norwich Park (ATP 1031P) tenements in March 2009.  These blocks have a combined area of over 1,600km2 and are located in the heart of one of Australia’s highest rated CSG provinces 250 km west of the Port of Gladstone where several world class export LNG projects are planned by unrelated parties.    Following  delays  caused  by  unseasonal wet weather,  the  Company’s  pilot  CSG  production programs in Queensland’s Bowen Basin are targeting to deliver forecast gas reserve upgrades and commercial gas flows.   The Company  anticipates  continued  reserves  growth,  targeting  year‐end 2011  certified gas reserves of 1,250PJ (petajoules) of 2P gas and 6,200PJ of 3P (net to Bow).   GAS IN PLACE OF OVER 13.8 TRILLION CUBIC FEET A  study  conducted  by MBA  Petroleum  Consultants  Pty  Ltd  (MBA)  of  Bow’s  100%  owned Bowen Basin tenements; Norwich Park  (ATP 1031P), Gunyah  (ATP 1053P – subject  to grant) and Bandanna (ATP 805P) estimates a total of 8.7 Tcf of GIP potential.  Bow’s reserve certifier, MHA Petroleum Consultants, LLC (MHA) had previously provided GIP potential in Comet (ATP 1025P) and Don Juan CSG Field (ATP 771) of over 5.1 Tcf (net to Bow).   Bow’s current gas reserves and end 2011 gas reserves targets are summarised below.      

Project  (all 100% unless stated otherwise) 

Current  Certified Reserves/Resources 

End 2011  Reserve Targets 

2CResources (PJ net to Bow) 

3P Reserves (PJ net to Bow) 

2P Reserves  (PJ net to Bow) 

3P Reserves (PJ net to Bow) 

2P Reserves (PJ net to Bow) 

Blackwater CSG Field*   435  1,382  59  1,600  450 

Comet CSG Field*   439  871  ‐  1,000  200 

Vermont CSG Field (within ATP1031P)  1,402  ‐  ‐  1,400  200 

Norwich Project (within ATP1031P)  ‐  ‐  ‐  625  100 

Dysart Project (within ATP1031P)  ‐  ‐  ‐  625  100 

Gunyah Project (ATP 1053)  ‐  ‐  ‐  600  100 

Bandanna Project (ATP 805)  ‐  ‐  ‐  200  ‐ 

Don Juan Project (55%)   ‐  107  55  150  100 

Total Reserves (net PJ to Bow)   2,276  2,360  114  6,200  1,250 

*       286PJ  of  3P  and  7PJ  of  2P  gas  reserves  included  above  is  over  land  awaiting  conclusion  of  native  title processes which are in progress. 

 

    

Page 6: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 6 

Bow Energy Limited Quarterly Report ending 30 September 2010     

 Bow’s CSG Tenements in Queensland 

 

Page 7: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 7 

Bow Energy Limited Quarterly Report ending 30 September 2010     

  

INITIAL WATER MANAGEMENT ASSESSMENT IN NORTHERN BOWEN BASIN  Bow commissioned an initial hydrogeology assessment of the water resources in Norwich Park and Comet blocks.  The key conclusions highlighted the following:   The Great Artesian Basin (GAB) and Recharge Area for the GAB does not  intersect Bow’s 

Norwich Park block and only has a minor overlap of 6.7 km2 within the south‐east corner of the 470 km2 Blackwater CSG Field.  Bow has no current or future plans to drill in this 6.7 km2 overlap area; 

Groundwater resources in Bow’s Bowen Basin areas are primarily limited to water courses in the region; and  

Groundwater  is not heavily utilised in the region and, where available, is commonly used for stock watering, domestic use and local coal mining operations. 

 Bow’s Chief Executive Officer, John De Stefani said: “Importantly, associated water production from the development of these Bowen Basin projects will be substantially less than that of the Surat Basin CSG fields.  Furthermore, Bow’s northern Bowen Basin projects do not overlay the Great Artesian Basin,  its  recharge  area or other  significant water  aquifers.   This  is  a major strategic advantage for Bow as there is an expectation of relatively lower water management costs and lower environmental water resource risk.”  ATP 1025P COMET BLOCK (Bow 100%)  Bow has obtained 3P gas reserves of 2,253PJ and 2P gas reserves of 59PJ in the Comet Block.  Adjacent  tenements  are  operated  by  BG  Group  and  Arrow  (50:50  owned  by  Shell  and PetroChina).  Bow is in the process of trialing several completion techniques in the Blackwater CSG Field to deliver commercial gas flow rates.     Initial Fracture Work Successful As  a  part  of  the  ongoing  production  enhancement  operations,  Bow  is  testing  fracture stimulations  of  target  coal  seams  to  increase  gas  production.    This  process  is  commonly referred to in the industry as fracing.    The  fracture  stimulations  are  designed  to  enhance  the  existing  permeability  and  thereby improve  fluid  and  gas  flow  rates.    Fracture  stimulation  completions  have  resulted  in commercial gas flow rates elsewhere in the Bowen Basin.  Bow closely monitors its operations and  follows  strict procedures  in  relation  to environmental and operational management,  in accordance with Queensland’s environmental regulations.   Initial  fracture  stimulations  (fracs)  have  been  completed  on  the  northern  ‘four  spot’  CSG fracture pilot, located about four kilometres west of the Blackwater Power Project.  The fracs were successful at fracturing the targeted zones and pumping sand to prop open the induced fractures  in the coals.   All of the fracced wells are expected to be completed for production testing during November.   

Page 8: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 8 

Bow Energy Limited Quarterly Report ending 30 September 2010     

 Bow’s frac fluids do not contain BTEX Concerning  the  use  of  chemicals  for  hydraulic  fracturing  fluids,  Bow  has  confirmed  to  the Queensland  Government  that  it  does  not  use  fracture  stimulation  fluids  containing  BTEX (benzene,  ethylbenzene,  toluene,  xylene),  naphthalene  or  phenanthrene;  or  use  chemicals that could  likely  form benzene, ethylbenzene,  toluene or xylene, as  they break down  in  the environment.    Lateral Drilling commenced after vertical wells encounter free gas and inferred permeability in the thick target coal. The vertical production and  flush wells  for Bow’s  first  lateral CSG pilot program have been drilled  and  cased.    The  target  seam  varied  in  thickness  from  four  to  eight metres  and  the vertical wells encountered  live gas shows and good  indications of permeability during post‐drilling  flushing of  the holes.   A  surface  to  inseam  (SIS)  lateral  rig  is being used  to drill  the lateral well pilot program.  Lateral drilling and completions have been successful  in obtaining commercial gas flow rates in adjacent tenements and numerous other CSG and underground mine areas of the Bowen Basin.    Commenting on the early results of the frac and  lateral drilling program, Mr De Stefani said: “Bow’s first frac wells have been a technical success and we are very pleased with the results.  Now that the wells are fraced, the next step is to complete the wells with pumping equipment and commence dewatering the seams, with the aim of achieving commercial gas flows.”      

Comet ‐ 100% Bow

871PJ 3P 439PJ 2C

(Certified in Rangal andBurngroveCoal Seams

Blackwater ‐ 100% Bow

59PJ 2P 1382PJ 3P435PJ 2C

(Certified in Rangal andBurngrove Coal Seams

Over 2,253PJ reserves at Bow 100% owned Comet Block 

Blackwater CSG FieldComet CSG Field

Drilled Core Holes

Test WellsLateral Wells4 Spot FRAC PilotExisting Wells

Kilometers

0 5 10

Powerstation

 

Page 9: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 9 

Bow Energy Limited Quarterly Report ending 30 September 2010     

 ATP 1031P NORWICH PARK PROJECTS (BOW 100%)   Early results confirm a large gas field Bow has identified three high potential CSG prospects within this block; Vermont, Dysart and Norwich and has now completed 6 core holes of a 9 well initial CSG exploration program.  Bow has obtained an initial certification of a 2C gas resource of 1,402 petajoules (PJ) from the Vermont CSG Field.   The  initial 2C resources are within the Fort Cooper and Moranbah Coal Measures.   Bow  is carrying out a permeability  testing program during this quarter  targeting conversion of the 2C resources into substantial 3P and initial 2P reserves in the Vermont CSG Field.  Gas contents in the Norwich Park Block are high to very high and range from 10‐26 m3/tonne (Dry Ash Free) and are over 96% methane gas.    Adjacent and to the southwest of the Vermont CSG Field is the Norwich CSG prospect.  Recent data from the core holes drilled in the Norwich prospect indicate it could be of similar size and prospectivity to Vermont.  A second core hole exploration drilling  rig  is scheduled  to commence  in November 2010  to complete the Norwich Park initial exploration program by year end, weather permitting.    Pilot production programs are scheduled early next year following similar programs scheduled in the Blackwater CSG Field.   

Norwich CSG Prospect ‐ 100% Bow

Primary target ‐ Rangal CM

Secondary target – Fort Cooper & Moranbah CM

Dysart CSG Prospect – 100% Bow

Primary target ‐ Rangal CM Secondary target – Fort Cooper

& Moranbah CM  

Norwich ProjectDysart ProjectVermont ProjectRangal CM OutcropRegional FaultProposed Core HolesDrilled Core Holes

1,402PJ 2C resources certified at Vermontin Norwich Park Block

Exploration results to date

WellTotal net coal(metres)

DAF Gas Content (m3/t)

VM1 52 14‐22

VM2 77 12‐22

VM3 62 10‐22

NW1 66 18‐26

NW2 53 Data pending

NW3 38 Data pending

0 5 10

Kilometers

Vermont  CSG Field ‐ 100% Bow

Primary target – Fort Cooper & Moranbah CM

1,402PJ 2C

  

Page 10: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 10 

Bow Energy Limited Quarterly Report ending 30 September 2010     

ATP 1053P GUNYAH CSG PROJECT (BOW 100%)  Bow owns 100% of the Gunyah block centrally located between the Moura‐Dawson Creek and Scotia Peat CSG production projects.  A recent review of Bow’s CSG assets performed by MBA Petroleum Consultants Pty Ltd estimated gas in place (GIP) potential of 1.8 trillion cubic feet (Tcf) for the Gunyah Block.   Bow  has  finalised  all  relevant  documentation,  including  a  Conjunctive Ancillary Agreement (between  Bow  and  the Wulli Wulli  People)  and  the  State  Deed  (all  parties  including  the Queensland  Government).    The  Conjunctive  Ancillary  agreement  captures  the  significant requirements  for  CSG  exploration  and  production  such  as  cultural  heritage  management plans.    Bow  is  currently  awaiting  formal  granting  of  the  tenement  from  the  Queensland Government.   

Target (150m to 700m)

Gunyah CSG Project (Bow 100%)Initial 3P program of 3 core holes

LOCATION

3P core holes

Bandana CM Out-Crop

GUNYAH PROJECT GIP Potential 1.8 Tcf

  

  

Page 11: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 11 

Bow Energy Limited Quarterly Report ending 30 September 2010     

ATP 805P BANDANA CSG PROJECT (BOW 100%)  The Bandana CSG project, is located 70 km north‐west of Santos’s Fairview CSG Field, targets Bandana Coal Measures  interpreted  to occur at depths between 200‐1000 metres.   Bow  is planning to drill 2 exploration core holes in the Bandanna prospect in 2011.  

CSG DrillingBandana Prospect

Bandana CM Outcrop

Permit - ATP805P

Proposed Core Hole

LEGENDLEGENDLEGENDLEGENDLEGENDLEGENDLEGENDLEGENDLEGEND

ATP805 Bandana Project (Bow’s 100%) Targeting the Bandana coal measures

Bow’s Bandana CSG ProjectBandana Coal Measures Target

Analogous to Fairview and Spring Gully

5 km

SURAT BASIN DON JUAN CSG FIELD (Bow 55%)  The Don  Juan CSG Project  is a  joint venture between Bow, as Operator with a 55%  interest (Walloon Coal Measures only,  including  the  Juandah and Taroom  coal  seams), and Victoria Petroleum having a 45% interest. The Don Juan CSG project includes ATP 771P and ATP 593P and is located in the western Surat Basin about 40 kilometres north of Roma, adjacent to and west of BG Group’s Lacerta CSG field. All certified reserves to date are within ATP 771P.  Summary of the gas reserves certified for Don Juan CSG project is as follows:    

ATP771P  Walloon Coal Measures 

Gross 2P Certified 

Reserves (PJ) 

Gross 3P Certified 

Reserves (PJ) Juandah coal seams 34.2 69.4 Taroom coal seams 66.7 128.0 Total Gross Reserves  100.9  197.4 

Page 12: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 12 

Bow Energy Limited Quarterly Report ending 30 September 2010     

Interpreted Walloon CSG Fairway

Approx. area of 101PJ 2P & 197PJ 3P Certified Reserves

ATP771PATP593P

Existing core holes

CN1CN2

Existing production holes

Don Juan CSG Project (Bow 55%)Gross certified reserves of 101 PJ (2P) and 197 PJ (3P)

BG LACERTA CSG FIELD44PJ  1P Reserves469PJ  2P Reserves1097PJ  3P Reserves

Proposed 3P Core Holes

Location

50kilometers

1019

>150 PJ POTENTIAL

GLADSTONE

  ATP593P Exploration Program to Target Additional 3P and 2P Reserves  Bow has  interpreted the Don Juan CSG fairway to extend  further west  into ATP 593P where the Walloon Coal Measures are expected to be at reasonable depths.  Bow is now planning a 2 well  exploration  drilling  and  testing  program  within  ATP  593P  to  commence  in  the  next quarter, with the aim of certifying additional 3P and 2P reserves.    Bow  is progressing development paths  for  the Don  Juan CSG Field with gas connection  into the nearby Queensland Gas Pipeline which is approximately 15km east of the field.  

Page 13: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 13 

Bow Energy Limited Quarterly Report ending 30 September 2010     

CONVENTIONAL OIL AND GAS ACTIVITIES  TECHNICAL REVIEW OF CONVENTIONAL ASSETS  Bow has engaged an external independent consultant to perform a technical review of Bow’s conventional  petroleum  assets  in  Australia.  The majority  of  these  conventional  assets  are located in Queensland, in both the Cooper‐Eromanga and Surat basins.  The first phase of this review will provide a refreshed assessment of Bow’s conventional petroleum assets including risked potential and recommended work programs.  The review is expected to be complete by end of 2010.   

 COOPER BASIN   ATP 752P (Bow 15% after farmin work completed)   Bow is fully carried on a staged farmin oil exploration program in the Barta and Wompi Blocks of ATP 752P,  located  in  the  southwest corner of Queensland.   The  farmin consists of up  to seven wells (two completed) and 300km2 of 3D seismic by Santos and Bengal (formally Avery Resources).  The blocks are adjacent to and on trend with areas that Santos has concentrated its Cooper Basin oil program.  The first two farmin wells drilled resulted in an oil discovery at Cuisinier‐1 in the Barta Block.   Barta Block – Cuisinier‐1 continuing to produce at 400 BOPD  Cuisinier‐1 is located approximately 6.2km west of the Santos operated Cook oil field.    Production commenced during May 2010 with the Cuisinier‐1 well producing at an initial rate of approximately 440 barrels of oil per day.  The well continues to produce approximately 400 bopd.  Given the higher than expected oil flow rates of the first well on the field, the ATP 752P Joint  Venture  has  agreed  to  an  additional  appraisal  well  on  the  field  following  detailed mapping  using  the  3D  seismic  data  acquired  over  the  field  last  year.    The  Cuisinier  2010 appraisal well, a 450 metre step out, will be drilled as a substitute for a Wompi Block Phase 2 farmin commitment.  The well is expected to spud in November 2010.  Several other oil prospects have been  identified  in the vicinity of the Cuisinier oil discovery.  One such prospect; Barta North, is a new structure located 4.2km WSW of the Cuisinier 1 oil well has been high graded for immediate drilling.   Barta North‐1 is due to spud in October 2010.    Bow is carried for the drilling of both wells.  

Page 14: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 14 

Bow Energy Limited Quarterly Report ending 30 September 2010     

Wompi Block ‐ 3D seismic completed prior to next phase of drilling – Bow fully carried (Bow 15% after farmin work completed).  Cuisinier Appraisal well to be drilled prior to year end.  Santos and Bengal are farming into this Block with a staged earning program of up to 4 wells plus 200km2 of 3D seismic acquisition. Bow is fully carried through this program.  The  JV  agreed  to  allow  the drilling  of  a well  in  the Barta Block  as  an  earning well  for  the Wompi Block.    CENTRAL EROMANGA BASIN   ATP 736P, ATP 737P, ATP 738P, ATP 944P and ATP 948P (Bow 20‐100%)  A  large  portfolio  of  leads  and  prospects  has  been  identified  in  Bow’s  Central  Eromanga permits.    The  highest  ranked  prospects  are  considered  to  be  the  Barcoo  Junction  North  and  the Moothandella prospects (both in ATP 794P).  These areas are being reviewed by an independent consultant.  The review is expected to be complete by year end 2010. 

Bow’s Central Eromanga Projects

Bow Tenement

Bow Tenement Under Application

Prospects and Leads

Gas Pipeline

Town/City

1000 km

50 km

(20%)

(20%)

(20%)

(100%)

(100%)

(100%)

(100%)

(40%)

(40%)

(65%)

(65%)

(16%)

(16%)

(50%)

(10%)

(20.37%)

 

Page 15: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 15 

Bow Energy Limited Quarterly Report ending 30 September 2010     

SURAT‐BOWEN BASIN    A total of 70 leads and prospects have been identified in Bow’s SW Surat areas.  These areas are been reassessed by an independent consultant.  

 CLARENCE‐MORETON BASIN   During  the quarter, no additional work was  conducted on Clarence Moreton Basin  licences PEL 445 and ATP 644P  (conventional only).   Expenditure  commitments  in  these areas have been met though CSG activities carried out by Arrow on the shallower CSG targets.    

CARNARVON BASIN ACTIVITIES  

WA‐261‐P (Bow 10%) The offshore permit contains the Chamois oil field, located on the western side of the block. This discovery is deemed sub‐commercial at this stage.  A 3D seismic program is planned over the permit to detail the Chamois oil field and high grade other prospects for potential drilling.  EP 325 (Bow 11.1%)  The  completed  initial  feasibility  of  supplying  gas  from  the  Rivoli  Gas  Field  to  fuel  power generation  for  the  Defence  Communication  Station  located  nearby  was  submitted  to  the Defence  Department  (DOD)  for  review.    The  operator  is  continuing  to  investigate  other markets.  

Page 16: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 16 

Bow Energy Limited Quarterly Report ending 30 September 2010     

3. COMMERCIAL ACTIVITIES   

GAS DEVELOPMENT STRATEGY Bow continues to pursue its stated strategy of progressing opportunities in power generation, domestic  gas  supplies  and  export  LNG  and  has  advanced  discussions  with  a  number  of counterparties for long term off‐take gas arrangements.      Generic details of off‐take opportunities include: 

o Combination  of  existing  operating  projects  and  new  developments  (domestic  and export LNG); 

o Contract  renewals where  incumbent gas  supplier  intending  to divert gas  reserves  to export projects; 

o Expected FID ranging from as early as mid‐2011 to mid‐2012; o Gas Supply Agreements ranging from 15 to 30 PJ per annum; and o Delivery of first gas from mid‐2013 to mid‐2015 

 During the quarter Bow had been in discussions with the Board and management of LNG Ltd regarding a number of potential commercial arrangements.  Bow ended discussions with LNG Ltd on 21 September 2010.    In  addition  to  the 30MW Blackwater Power Project Bow  is  continuing  to pursue electricity generation including feasibility for a 200MW power plant located at Blackwater, Queensland.  A  key  element  of  Bow’s  long‐term  development  strategy  is  the  required  gas  pipeline infrastructure from Bow’s Bowen Basin gas reserve base to Gladstone for potential supply to both domestic and export gas markets.   Bow has obtained a pipeline survey  licence (PSL 51) under  the  Petroleum  and  Gas  (Production  and  Safety)  Act  2004  for  the  corridor  from Blackwater  through  to  Gladstone  and  a  third  party  consultant  has  outlined  the  preferred pipeline route of 257km.   

 PROPOSED BLACKWATER – GLADSTONE PIPELINE  

Page 17: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 17 

Bow Energy Limited Quarterly Report ending 30 September 2010     

CONSTRUCTION COMMENCES ON BLACKWATER POWER PROJECT  

Bow  announced  on  12th  August  2010  the  commencement  of  construction  on  Bow’s  100% owned 30 megawatt gas‐fired Blackwater Power Project, located approximately 15 kilometres north‐east of the town of Blackwater in central Queensland.  

 “Bow continues to progress the construction phase of the project as planned,” Mr De Stefani said.  “The first 7 of ten GE Jenbacher engines have arrived on site and are ready for electrical and mechanical connection to the HV control room.”   

The Blackwater Power Project will be supplied with clean‐burning coal seam gas  (CSG)  from Bow’s  adjacent  Blackwater  CSG  Field,  which  has  current  certified  CSG  reserves  of  1,382 petajoules  (PJ) of 3P and 59PJ of 2P  (net  to Bow). This  initial power project  is expected  to require around 2PJ per annum of gas.  

The  civil  works  are  now  100%  complete  with  electrical  and  mechanical  installations  to continue  over  the  coming months.  The  procurement  of  all major  items  of  equipment  is complete, including the switchroom, high voltage switchboard, low voltage main switchboard, gas  conditioning unit, gas  compressor  and 10  x 3 megawatt GE  Jenbacher  generating  sets, enclosures, radiators and transformers.  

Electrical Connection Bow Energy  is  in continuous discussions with Ergon Energy  for the connection of the power station to an Ergon substation located at Blackwater.   

A single circuit 66kV transmission line route has been selected to transmit electricity from the power station to the Blackwater substation.  Construction of the transmission line is expected to commence following finalisation of permits and approvals over the coming months.    

Installation of the first GE Jenbacher engine to the Blackwater Power Project  

  

 

Page 18: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 18 

Bow Energy Limited Quarterly Report ending 30 September 2010     

4. EXECUTIVE APPOINTMENTS    Richard Fenton – General Manager Project Services  Mr Richard Fenton  started with  the company  in September, and  is  responsible  for  the new project services team.   Richard has 14 years of experience  in upstream oil and gas projects, principally around the end‐to‐end delivery of CSG projects.   Richard’s experience has ranged from, Manager – Environment and Regulatory Compliance with RLMS to Manager – CSG with Sinclair Knight Merz and recently to Manager Water Business Planning for QGC and QCLNG.   As the GM Project Services Richard will hold responsibility for Bow’s:  

o Landholder Liaison activities; o Environment & Sustainability activities; o Health & Safety; and o Coal Mine Liaison for our overlapping tenure areas. 

 

        Competent Person Statements MHA ‐ The estimates of gas reserve and resources for the Comet Block (ATP 1025P) and Don Juan CSG Field (ATP 771P) has been prepared by MHA Petroleum Consultants, LLC (MHA) in accordance with the definitions and guidelines set forth in the 2007 Petroleum Resources Management System approved by the Society of Petroleum Engineers. The reserve statement has been compiled by Mr Timothy L Hower Chairman of MHA, together with personnel under his supervision. Mr Hower, who has over 28 years  industry experience, and MHA have consented to the  inclusion of the technical  information contained  in this announcement in the form and context in which it appears. MBA – The estimates of gas  in place potential for the Norwich Park (ATP 1031P), Gunyah Block (ATP 1053P) and Bandanna Project (ATP 805P) has been prepared by Mr Doug Barrenger of MBA Petroleum Consultants Pty Ltd  (MBA).   Mr Barrenger has more than 25 years of experience in the petroleum industry and 10 years of experience in the coal seam gas industry.   Bow – Other  technical  information contained herein  is based on  information compiled by  the Company’s Chief Operating Officer, Vic Palanyk, who has more than 15 years experience in coal seam gas.  Contingent Resources are  those quantities of petroleum estimated, as of a given date,  to be potentially  recoverable  from known accumulations, but the applied project(s) are not yet considered mature enough for commercial development due to one or more contingencies. Contingent Resources may include, for example, projects for which there are currently no viable markets,  or  where  commercial  recovery  is  dependent  on  technology  under  development,  or  where  evaluation  of  the accumulation is insufficient to clearly assess commerciality. Contingent Resources are further categorized in accordance with the level of certainty associated with the estimates and may be sub‐classified based on project maturity and/or characterized by  their  economic  status.[Reference:  Petroleum  Resources Management  System  as  sponsored  by:  Society  of  Petroleum Engineers (SPE), American Association of Petroleum Geologists (AAPG), World Petroleum Council (WPC), Society of Petroleum Evaluation Engineers (SPEE)]   Figure 1 References  Great Artesian Basin including Recharge Area (coloured yellow on Figure 1) ‐ digital data sourced from Queensland Government Information Services, DERM Department. Great Artesian Basin Area (coloured green on Figure 1) ‐ digitized from map sourced from the Australian Government Department of Sustainability, Environment, Water, Population and Communities website.  

Page 19: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 19 

Bow Energy Limited Quarterly Report ending 30 September 2010     

5. BOW’S PLANNED ACTIVITIES FOR THE NEXT QUARTER  

  

Exploration, Appraisal and Production  Blackwater CSG Field:  Fracture  stimulation and  lateral drilling production enhancement pilots  will  continue  with  focus  on  achieving  commercial  gas  flow  rates.    2P  appraisal programs to continue. 

Comet CSG Field: Continuation of 2P appraisal programs.    Norwich Park Block: Accelerate 3P  reserves drilling program by  securing a  second  core drill rig as well as carrying out 2P reserves testing program.   

Other  CSG  Projects:  Planning  and  the  commencement  of  3P  drilling  program  across Gunyah, Bandanna and eastern Don Juan CSG Projects during the 4th Quarter of 2010 and early 2011. 

Conventional Oil:  Drilling  of  Barta  North‐1  oil  exploration  and  Cuisinier‐2  oil  appraisal wells in the Cooper Basin  

Commercial Activities  Blackwater Power Project to continue construction.   Progress  commercial  discussions  with  counter  parties  in  line  with  Bow’s  strategic development paths.  

Progress early phase development activities associated with the Blackwater to Gladstone gas pipeline infrastructure including environmental approvals. 

PL applications to continue    Negotiate overlapping tenure agreements with coal parties as required in the Comet Block (ATP1025P).   

Drilling Program 2010 2011

3rd Quarter(Jul‐Sep)

4th Quarter(Oct‐Dec)

1st Quarter (Jan‐Mar)

2 nd Quarter(Apr‐ Jun)

Production Program (end2010)• 2 x 4 Fracture Stimulation Wellproduction pilots, 1 x 2 Lateral Well production pilot in the BlackwaterCSG Field

Testing Program (end 2011) • Total of 21 wells across entire CSGportfolio

Core Hole Program (end2011)• Total of 21 core holes across entireCSG portfolio

Blackwater 30MWPower Station

END 2011 TOTAL RESERVES(net to Bow) 1,250 PJ 2P / 6,200 PJ3P

Drilling /Completions

Gas Contents and Saturations

Construction

Pumping /Testing Connection

Completions/Testing/Pumping

Commissioning/Ops

Page 20: 30 September 2010 Quarterly Report – Highlights Promotion ... · Blackwater Power Project Commences Construction Bow has commenced the construction on its 100% owned 30 megawatt

Page | 20 

Bow Energy Limited Quarterly Report ending 30 September 2010     

CORPORATE INFORMATION & DIRECTORY  

    

For further information, contact John De Stefani, CEO or Duncan Cornish, Company Secretary.  Telephone +61 7 3238 6300 or e‐mail [email protected]  Electronic copies and more information are available on Bow’s website www.bowenergy.com.au  

DIRECTORS 

Howard Stack (Non‐Executive Chairman) Ron Prefontaine (Executive Director) Nicholas Mather (Non‐Executive Director) Stephen Bizzell (Non‐Executive Director)  EXECUTIVES   

John De Stefani (Chief Executive Officer) Vic Palanyk (Chief Operating Officer) Peter Harbison (Chief Financial Officer) Duncan Cornish (Company Secretary)  SHAREHOLDER ENQUIRIES 

Link Market Services Ltd manages Bow Energy Ltd’s share registry. 

If you would like to monitor your shareholding online, you can do so by visiting Link Market Services Ltd’s website, 

 www.linkmarketservices.com.au and following the instructions. 

For issuer‐sponsored shareholders, if you change address, or if you have any other queries regarding the details of your shareholding, please contact the Company’s share registry directly: 

Link Market Services Ltd  ANZ Building, Level 19 324 Queen Street, Brisbane QLD 4000 Phone: 1300 554 474 

ISSUED CAPITAL

Bow Energy Ltd has the following securities on issue: 

Ordinary shares on issue  at 30 September 2010:  280,607,187 

Outstanding options at 30 September 2010: 

12.05 million (unquoted) 50c options expiring 7/11/11 

16.50 million (unquoted) employee options (various exercise prices and expiry dates) 

 AUSTRALIAN STOCK EXCHANGE (“ASX”) 

ASX Code: BOW (Ordinary shares) S&P ASX 200 Index    INTERNET ADDRESS 

All Company announcements, reports and presentations are posted on our website www.bowenergy.com.au  

If you would like to receive news releases by email, please send us an email to [email protected] or register your details on our website. 