Upload
initiative1972
View
220
Download
0
Embed Size (px)
Citation preview
8/12/2019 3 Greg Howell-Lean Construction
1/23
8/12/2019 3 Greg Howell-Lean Construction
2/23
2
A brief history of project management
Enter the Critical Path
Practice and the Industry Evolves
Surprising Data
A New Planning System
Practice and the Industry Evolves
8/12/2019 3 Greg Howell-Lean Construction
3/23
4 Lean Construction Institute, 2005 www.leanconstruction.org
How do we manage projects now ?
Determine client requirements including quality, time andbudget limits. Design to meet them.
Break project into activities, estimating duration and resourcerequirements for each activity and placing them in a logicalorder with CPM
Assign or contract each activity, give start notice and monitorsafety, quality, time and cost standards. Act on negativevariance from standards
Coordinate with master schedule and weekly meetings
reduce cost by productivity improvement.
reduce duration by speeding each piece or changing logic.
improve quality and safety with inspection and enforcement.
8/12/2019 3 Greg Howell-Lean Construction
4/23
8/12/2019 3 Greg Howell-Lean Construction
5/23
7
O A R
Change the observer
8/12/2019 3 Greg Howell-Lean Construction
6/23
8
Contractor 1 33 %
Contractor 2 52 %
Contractor 3 61 %
Contractor 4 70 %
Contractor 5 64 %Contractor 6 57 %
Contractor 7 45 %
Average 54 %
Research Findings from early 1990s
The percentage of tasks completed of thoseassigned in a week, that is ready for the
next crew to begin work.
8/12/2019 3 Greg Howell-Lean Construction
7/23 2009 Lean Construction Institute 9
Percent Plan Complete (PPC) Chart
Rasacaven: Electrical Power Distribution
8/12/2019 3 Greg Howell-Lean Construction
8/23 2009 Lean Construction Institute 11
The Last Planner System of Production Control
5 - Connected Conversations
Set milestones & strategy
Identify long lead items
Specify handoffsIdentify operational conflicts
Make ready & LaunchReplanning when needed
Promise
Measure PPC & act onreasons for failure to keeppromises
SHOULD
CAN
WILL
DID
Weekly Work Planning
Make Work ReadyPlanning
Learning
Master Scheduling
Milestones
Phase Pull
Planning
8/12/2019 3 Greg Howell-Lean Construction
9/23
8/12/2019 3 Greg Howell-Lean Construction
10/2315
Impeccable Coordination
8/12/2019 3 Greg Howell-Lean Construction
11/23 2009 Lean Construction Institute 16
Courtesy of DPR, Inc
8/12/2019 3 Greg Howell-Lean Construction
12/23 2009 Lean Construction Institute 17
Courtesy of DPR, Inc
8/12/2019 3 Greg Howell-Lean Construction
13/23 2009 Lean Construction Institute 18
Courtesy of DPR, Inc
8/12/2019 3 Greg Howell-Lean Construction
14/23 2009 Lean Construction Institute 19
The Last Planner System of Production Control
5 - Connected Conversations
Set milestones & strategy
Identify long lead items
Specify handoffsIdentify operational conflicts
Make ready & LaunchReplanning when needed
Promise
Measure PPC & act onreasons for failure to keeppromises
SHOULD
CAN
WILL
DID
Weekly Work Planning
Make Work ReadyPlanning
Learning
Master Scheduling
Milestones
Phase Pull
Planning
8/12/2019 3 Greg Howell-Lean Construction
15/23
8/12/2019 3 Greg Howell-Lean Construction
16/2321
8/12/2019 3 Greg Howell-Lean Construction
17/2322
8/12/2019 3 Greg Howell-Lean Construction
18/23
23
8/12/2019 3 Greg Howell-Lean Construction
19/23
24
CPM -Activities Transactional Command &Control
Lean - Flow Relational Collaborative
OperatingSystem
CommercialTerms
Organization
Project management common sense: New Coherence
Optimizing the project not the piece
8/12/2019 3 Greg Howell-Lean Construction
20/23
Results of Lean/Baker 2.0
Lost Time Case Rate (LTCR): Down 100%
Recordable Incident Rate (RIR) Down 75%
BEST Safety performance in the company
LOWEST overtime percentage in the company Spot Labor Productivity: -10% to +75%
Variance is most likely a function of the estimate
Schedules: Ahead or Within a few Days Average gain is 2-3 days per month
Rework / Punch list cost: Down 15-25%
8/12/2019 3 Greg Howell-Lean Construction
21/23
69,000 sq. ft. MOB
$19m budget -- $20m original estimate
IFOA team assembled at concept
3D model for coordination/clashdetection
Total station layout
8/12/2019 3 Greg Howell-Lean Construction
22/23
$1m+ in scope added w/o increasingbudget (TVD wish list)
Construction savings -- $600k underGMP
Zero field conflicts at installation
Layout using Total Station
MH reduction - 75%; duration - 50%
8/12/2019 3 Greg Howell-Lean Construction
23/23
To Learn More
http://www.leanconstruction.org/
http://www.leanconstruction.org/http://www.leanconstruction.org/