19
3-14-2002 Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

ARCS Review

Engineering Design

Ralph Niemann

Don Ghilardi

Robb Williams

Page 2: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Recent Design Issues

• Detector Mounting• Vacuum Vessel Concepts• System Integration

Page 3: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Detector Module Mounting

• 8 Detectors per Module

• Neutron Shielding

• Read out card (ROC) mounting

• Current concept ~35 pounds

Page 4: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Module Mounting

• Assume Man Access from behind for now

• Potential Access:

– From above/below

– Remote Access

Page 5: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Module Mounting

Page 6: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Module Mounting

Page 7: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Module Mounting

Page 8: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Vacuum Vessel

• Tank Particulars

– 70 Cubic Meters

– 3.9 meter radius

– Irregular shape to accommodate building

– 35,000 pounds

Page 9: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Tank Drawing

Page 10: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Tank Plan View

Page 11: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Sample Gate Concept

• Ability to change sample without bringing entire vessel to atmosphere

• Other concepts still need to be investigated.

Page 12: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Sample Chamber

Page 13: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Sample Chamber

Page 14: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Sample Access

• Hoist for sample equipment

• Access to sample area from Central Lab Office

• Miscellaneous tank controls accessible from sample area

Page 15: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Pump Access

Page 16: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Instrument Shielding

• Poured in Place High Density Concrete

• Stackable High Density Concrete

• Steel Shielding 18” around the beam

Page 17: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Fermi Chopper Mounting

• Remote Adjustment in and out of beam

• Integrate design with shielding to allow access from the top of shielding

Page 18: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Page 19: 3-14-2002Instrument Engineering ARCS Review Engineering Design Ralph Niemann Don Ghilardi Robb Williams

3-14-2002 Instrument Engineering

Upcoming Efforts

• Detector Mounting– Test Chamber

• Detector in Vacuum

• Module Handling

• Vacuum Chamber– Tank Access

– Installation Issues

– “Crispy Mix” Mounting and Vacuum Effects

• Sample Chamber– Gate Concept

– Sample Manipulation

– Other Components

• Collimator

• “Thimble”

• System Integration– Conventional Facilities

– Safety Regulations