Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
2016. UK Power Networks. All rights reserved 1
2016. UK Power Networks. All rights reserved
Today’s agenda
Time Topic Session host
09.00-09.30 Registration & refreshments
09.30-09.50 Welcome & introductions Neil Madgwick & Mark Adolphus
09.50-10.05 The last 5 years Steve Carlow, Jim Vasey & Steve Foster
10.05-10.20 A customer perspective Customer
10.20-10.35 Our engagement – owner/operator forum, Quicker and More Efficient Connections
(QMEC) - milestones
Neil Madgwick
10.35-11.00 UK Power Networks’ response to Flexibility Consultation Sotiris Georgiopoulos
11.00-11.30 Tea & coffee
11.30-13.00 Breakout sessions - Service Development Plan looking back (16/17), Service
Development Plan looking forward (17/18), the next 5 years
Neil Madgwick, Steve Bradley & Ian Cameron
13.00-13.30 Feedback and Q&A Neil Madgwick
13.30-14.15 Lunch
14.15-15.15 Connecting storage, future initiatives and transition to Distribution System
Operator (DSO)
Jose Barros, Lynne McDonald & Matt White
15.15-15.30 Q&A and close Mark Adolphus
2
2016. UK Power Networks. All rights reserved 3
2016. UK Power Networks. All rights reserved
Holborn Bars
Safety and housekeeping
4
2016. UK Power Networks. All rights reserved
Holborn Bars
Bus stop J, Fetter Lane
Please assemble next to the Fire Marshall who will be holding a
yellow sign.
5
In case of emergency…
2016. UK Power Networks. All rights reserved
Who’s here today
ConnectionsMark Adolphus Director of Connections
Neil Madgwick Head of Service Delivery
Steve Bradley Head of Major Connections
Steve Carlow Major Connections Manager SPN
Steve Foster Major Connections Manager LPN
Jim Vasey Major Connections Manager EPN
James Devriendt Connections Manager South East
Kellie Dillon DG Business Analyst
Connie Dickie Communications, Engagement & Events Lead
Judith Edgerton Customer Relationship Manager
Shenika Ford Customer Service Advisor
Asset Management
Sotiris Georgiopoulos Head of Smart Grid Development
Matt White Lead Power Systems Engineer
Lynne McDonald Programme Manager DSO Readiness
Tim Moore Infrastructure Planning Engineer
Jose Barros Infrastructure Planning Engineer
Zivanayi Musanhi Generation and System Coordinator
Kofi Marfo Distribution Planning Manager
Safety, Strategy & Support ServicesIan Cameron Head of Innovation
James Watson Communications and Engagement Lead
Network OperationsRichard Wilson Outage Planning Manager
6
A multi-directorate team…..
2016. UK Power Networks. All rights reserved
Which stakeholder group do you represent?
7
Enter
Number(s) and
Press Send1. Consultant
2. Developer
3. Investor
4. Utility
5. Contractor
6. Installer
7. Local Authority
8. NGO
9. Owner/Operator
10. Other20
2016. UK Power Networks. All rights reserved 8
2016. UK Power Networks. All rights reserved
Your feedback throughout the dayListening to our customers
Start doing/More of
Stop doing/Less of
Name:
Name:
9
2016. UK Power Networks. All rights reserved 10
2016. UK Power Networks. All rights reserved
DG over the last 5 years
11
2016. UK Power Networks. All rights reserved
DG over the last 5 years
12
Total
Enquiries
Total
Quotes
Total
Acceptances
Total
Connected
31,269
183.5GW
9,154
56GW
1,831
10.5GW
1,610
3.6GW
2016. UK Power Networks. All rights reserved
DG Surgeries over the last 5 years
13
No of Surgeries No of Site AssessedNo of sites moved to
formal offer
2014 212 521 322
2015 213 551 381
2016 143 157 97
Total 746 1786 1109
2013 178 557 309
Massive saving
on time for both
sides. Very, very
useful.
All of our questions
were answered and
UKPN staff were
friendly and proactive.
Thank you and I will
inform my colleagues
of the excellent
service you kindly
provided.
2016. UK Power Networks. All rights reserved
Capacity returned in last 5 years
14
No of DG
applications
cancelled
Total capacity
returned MVA
2012 3 2
2013 15 138
2014 38 461
2015 67 747
2016 52 688
Total 175 2036
No of Connections Total Capacity (MW)
Accepted yet to
connect >12months
87 1,438
2016. UK Power Networks. All rights reserved
Innovation in the last 5 years
15
Newhaven Fault Current Limiter
•Responding to customer demand
•Cheaper and quicker for new generation to connect
• Only DNO in the UK using this technology
Point of Connection Mast Trial
• Quarter cost of traditional solutions
• Faster deployment timescale
• Improves viability of projects
• Shorter power outage- wider network access period
• Minimal costly working at height
• Ongoing trial
Load Blinding
New solution available to the planning teams' to release constraints in transformers where the DOC rating is below the total reverse power flow rating
Able to discriminate between generation reverse power flow and fault conditions by the change in impedance
Hierarchical solution which can be deployed pending network configuration
Innovation
11 solutions in BAU
£77m net savings to customers
7 out of 7 projects awarded funding
£62m funding awarded
2016. UK Power Networks. All rights reserved 16
About Lightsource
• Europe’s leading solar energy company
• Full service capability - project development, planning , ICP design, legals, O&M
• First solar farm completed in 2011
• 1.4 GW of PV generation installed across 180+ sites (approx. 400MW / 44
sites in UKPN)
• £2.0 billion deployed in 5 years
• New connections with all UK DNO’s – 11kV, 33kV & 132kV
Our experience of dealing with UKPN
Things you do well
• Engagement with DG community
• Multiple capacity applications
• Offer novation (but £)
• Legals process (“better than most”)
• Time to connect
• G81 Design Specification Library
• Innovation in response to high penetration of DG (FPP/ANM)
• DG Owner / Operator Forum – first steps!
Areas for improvement• Website – where’s the DG area gone? (24.16 - Update: DG is back!)
• Access to network mapping / GIS system – all voltage levels, cables & OHL (19.16)
• POC information stage of 33kV applications
• Detailed information in connection offer - works, costs, constraints (4.16)
• Interactive offer acceptance - payment
• Cost to connect – switchgear, use of contractors
• LV supplies to 33kV ‘customer point of supply’ substations – consistency!
• Engagement post offer acceptance• Fault levels
• Background harmonics
• Design / construction kick-off meetings
• Project management
• Speed of travel from innovation to BaU
‘Best in class’ network mapping
Above:
WPD Online Mapping Application (EMU Online)
Right:
SPEN Utility Map Viewer
2016. UK Power Networks. All rights reserved 24
2016. UK Power Networks. All rights reserved 25
UK Power Networks Communications events
You/DGs/DER
s
Projects/Major
Connections
Capital
Programme
Asset
Management
Network
Operations
Design
Build
Own
Operate
Developer
Builder
Asset Owner
Operator
DG Customer
Forum
Owner/Operator
Forum
The key parties – aligned interfaces
DG
Scrutiny
Panel
Project
timeline
2016. UK Power Networks. All rights reserved 26
DG Scrutiny Panel
• Neil Madgwick
• Steve Halsey
• Kellie Dillon
• Challenge our thinking
• Provide insight into other
DNO activities
Aidan Morris
Customer representatives
Keir Spiller
Graham Pannell Mark Draper
Paul Graham
Steve Gist
2016. UK Power Networks. All rights reserved
Owner/Operator Forum
27
20 Customers attended
“Positive knowing UKPN wish to
engage with people connected to
their network.”
“Thank you so much for your effort
in DGs connected on this - We
need to work together to make
UKPN an outstanding DSO!”
DG owner/operator forum presentation 12 December 2016
2016. UK Power Networks. All rights reserved
Interdependencies
Outage plan
Capital Programme
Asset Management
Projects/ Major
Connections
Interconnected DNOs
Faults & defects
National Grid
Maintenance
Large Power Users
You/Distributed Energy
Resources (DER)
Maintenance Plan
Capital Plan 120 MTHS
Enquiries
P6 Plan
ED1 Plan96 MTHS
Local
National
Asset Portfolio Plan
Network
Operations/Control
Customers
DAILY/WEEKLY/MONTHLY/YEARLY
WORK PIPELINE VISIBILITY
28
2016. UK Power Networks. All rights reserved
RISK CONFIDENCE
96
mo
nth
s
ED
1 P
lan
12
Mo
nth
s
8 W
eek
ah
ea
d
The challenge – striking a balance
3 M
on
ths
Projects/ Major
Connections
Asset Management
Capital Programme
18
Mo
nth
s
Network
Operations/Control
Week a
he
ad
29
2016. UK Power Networks. All rights reserved
Feedback from Owner/Operator forum
30
# Issue
1 We would like a family tree/structure showing who does what on the website
2 A single point of contact in UK Power Networks would be good
3 Would like ability to have multiple contacts on Site Responsibility Schedule (SRS) - (by role priority)
4 An online solution for SRS (beyond SRS document) would be useful
5 The SRS should be available/required for all voltages (< EHV)
6
It would be useful to know what information is required by UK Power Networks when generation site
is sold
7 Can generic data on type and duration of outages/maintenance for standard plant be provided?
8 Are you happy to consider mitigation plans - network reconfiguration requests
9 We would like to know the progress of works - outage performance is it early or late
10
We need to have access to information post outage such as - reason and precise times for outage
(fault/plan) on/off times for insurance purposes
11
An IT platform for investor/owner/asset operator would be helpful – as well as the ability to select
who will be informed
13 Ideally 100% confirmation 2 weeks out is required
14 It would be good to have access to UK Power Networks Outage Plan via email
15 A simple platform design is required – stakeholder engagement/communication before sign off
16 Can UK Power Networks simply turn down - saving site operating
# Issue
8 Are you happy to consider mitigation plans - network reconfiguration requests
10
We need to have access to information post outage such as - reason and precise times for outage
(fault/plan) on/off times for insurance purposes
15 A simple platform design is required – stakeholder engagement/communication before sign off
2016. UK Power Networks. All rights reserved
Overall, I have experienced a good level of
engagement from UK Power Networks over the
last 12 months
31
Enter Number(s)
and Press Send
0
1
2
3
4
5
6
7
8
1 2 3 4 5 6 7 8 9 10
2016. UK Power Networks. All rights reserved
Ofgem – Quicker & More Efficient
Connections (QMEC)
Existing customers not utilising existing capacity
Contracted but not connected
Future contracts
32
2016. UK Power Networks. All rights reserved
Approach
More rigidly to
More flexibly
Seven milestones
No. Milestone
M1 Initiate planning permission
M2 Secure planning permission
M3 Land Rights
M4 TSO interface
M5 Contestable works design submission
M6 Commence and progress works
M7 Project construction/completion
QVED= Quote Validity End date (30/90 days)
E= Energisation
Longstop date
QVED +2 months
M1 + 12 months
QVED +2 months
TBD
E – x months
E – y months
E – 1 month
33
3 April implementation
2016. UK Power Networks. All rights reserved
Monitoring and ……..if things change!!!
• Milestone approaching
• Milestone missed/breached
• Milestone reviewed/amended – issue variation
• Milestone not achieved – withdrawal/termination
Milestone communications
34
Enforceable milestones
2016. UK Power Networks. All rights reserved 35
Material change – next steps
• Some re-drafting of original
scenarios
• Drawings added for clarity
• Review at DG-DNO Steering
Group
• Re-consult
2016. UK Power Networks. All rights reserved 36
2016. UK Power Networks. All rights reserved
Present UK Power Networks’ approach to defining and
delivering Distribution System Operation (DSO) roles
including:
• Definition of the DSO and roles
• DSO capability model
• Roadmap to deliver the capabilities
• Role of innovation
• Priorities for the regulator and policy makers
Purpose
37
2016. UK Power Networks. All rights reserved
Changing external environment
0
0.5
1
1.5
Year
20
14
20
15
20
16
20
17
20
18
20
19
20
20
20
21
20
22
20
23
20
24
20
25
20
26
20
27
20
28
20
29
20
30
Mill
ion
Year
UK Power Networks Electric Vehicle Baseline Forecast
675
12,107
-
5,000
10,000
15,000
0
200
400
600
800
Sep
-15
Oct
-15
No
v-1
5
Dec
-15
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
Dec
-16
Jan
-17
Cap
acit
y M
W
Vo
lum
e
Formal Storage Applications - cumulative W/E 6 January 2017
Formal Volume Formal Capacity
The pace and scale of change is increasing
Transmission System Operators (TSOs) will increasingly rely on distribution resources to manage the system
38
2016. UK Power Networks. All rights reserved
Implications for networks
Source: Ofgem / BEIS “A smart, flexible energy system”
Replacement of centralised large synchronous generation with a large number of intermittent
non-synchronous distribution generators
Low voltage monitoring & visibility, inc. smart
meters
Network control & automation
Commercial arrangements & charging signals
Increased SO/TO co-ordination
New social/local/commercial energy
models
New flexible technologies, providers and
solutions emerging
Rapid/unpredictable pace of change
Changing demand/more variable net demand profile
Drivers for system change
Changing use of distribution network by connectee has impacts on
distribution network
Changing use of distribution network by connectee wider system impacts
Use of distributed resources & novel techniques for local network
management impacts on wider systems
Increasing need for distribution-connected resources to support system
operation
ImpactsAll parties have appropriate visibility of existing and
future network
Facilitate timely and cost-efficient connections & appropriate signals on where to connect to
maximise system efficiency
Efficient, whole system planning including:a)Use of build/non build solutionsb) Use of optionality across transmission &
distribution
Efficient use of system resources (including flexible resources and innovative solutions) for local network
and system-wide operations*
Level playing field for new and existing flexible technologies, providers and solutions & access to
wide range of revenue streams
Resilient and secure system with efficient emergency and system recovery procedures
Responsiveness to readiness for rapid/unpredictable change
Market participants have trust and confidence in roles and governance of network companies
Emerging system requirements
A transformation of technology and capability39
2016. UK Power Networks. All rights reserved
The world in
2030
~4 GW of
storage
~13 GW of solar
~1.2 - 2m
electric vehicles
Risk and value in the new operating
environment
Whole system incentives are needed
£8bn pa benefits
Complexity ICT resilience and security
Network constraints
UnpredictabilityReliance on DER
integration
Benefits Source: National Infrastructure Commission “Smart Power” report 40
2016. UK Power Networks. All rights reserved
Distribution System Operator Roles
SO
DSO
1. SO requests demand turn up or
down from DSO
2
2. DSO contracts with generator to deliver
response to SO without constraining
its network
= Distributed Energy Resources / Aggregators
Overall effect is to deliver SO service efficiently while
maintaining reliability
Enabling marketsFair and cost-effective grid access
Efficient and economic network development
Keeping the lights on
Support the wider system
41
2016. UK Power Networks. All rights reserved
• Frequency balancing• System resilience• Inter DSO Coordination
• Constraint management• Customer service• Connections• Supply security• Reactive power• SO services inc. local
balancing
SODSO
Promote Competitive Service ProvisionNeutral Market Facilitation
T&D Coordination
DSO vs SO roles
42
2016. UK Power Networks. All rights reserved
Low Carbon LondonDER and demand side
customer engagement
Distributed Energy
Resource Planning
Predictive
diagnostics
Network visibilityContracting with
DER
Flexible Plug & PlayReal time dispatch of
DER
Contracting with DER
SCADA and Comms
Distributed Energy
Resource Planning
DER Growth
forecasting
Online capacity and
queue management
KASMIntegrated T&D planning
GBSO co-ordination
Network Visibility
Contingency
Planning
ICT Design and
Integration
Visualisation and
Simulation
Smarter Network StorageMarket Change and
Development
Offering SO services
Market Assessment
Commercial
optimisation
Commercial
Strategy
New business
models
Current level of
integration into BAU
Real time dispatch of
DER
Contracting with DER
Offering SO services
Integrated T&D planning
Network visibility
ICT Design and
Integration
SCADA and Comms
DER Growth
Forecasting
Online capacity and
queue management
Visualisation and
Simulation
Contingency Planning
Advanced
Intermediate
Foundation
Innovation has informed DSO Capabilities and delivered tangible benefits
Over 300MW of
enabled DG
£100m net savings to customers
New operational standards
New customer offerings
Visualisation and
Simulation
43
2016. UK Power Networks. All rights reserved
DSO Development – Roadmap to 2030ED1 ED2
Whole System Incentives
ANM rollout
TSO – DSO Interface
• Planning and operational coordination framework development
• TDI 2.0 commercial framework
2017 2018 2019 2020 2021 2022 2023 2024
Flexibility procurement
Targeted DSO Op Model Implementation
• Forecasting
• System monitoring
• Revised standards
EV Planning
IT & Cyber Readiness
EV Readiness
Complete ANM rollout EPN and SPN
Market arrangements for constraint management
Commercial platform innovation
Scaling up TDI functionality in EPN and SPN
T2/ED2 Strategy Development
Revised framework for T&D Planning
DSO IT - Targeted Implementation
Targeted LV Visibility and Automation
Formalised DSO Framework
EPN & SPN operating as regional DSO
DSO Commercial Operations becoming core business capability
Distributed Energy Resource planning
Creation of distribution level markets
LV visibility and automation
LV DER Dispatch
Extensive use data analytics
2030
Cu
sto
me
r an
d C
om
me
rcia
l De
velo
pm
ent
Tech
nic
al D
eve
lop
me
nt
EV Smart Charging
44
2016. UK Power Networks. All rights reserved
•Define new operating model and identify no regret investments•First dedicated DSO development team
Identify, prioritise & deliver the DSO capabilities
•Largest ANM operational network (over 300MW / £100m benefits)•Flexible connections fully rolled out across all EPN and SPN by 2020
•Procure flexibility as an alternative to network capacity (Tender in 2017)
Embed successful innovations and continue innovating
•New Technical Standards (EV, Grid Scale and Domestic Storage, System Monitoring)
•New Processes (Fast track G59 for domestic storage)
•EV Charging (Timed connection for London’s first fully electric bus depot)
Prepare for EV and Storage
•Regional Development Programme SPN & TDI 2.0 project
Working closely with the TSO on the TSO / DSO interface
•ENA Transmission and Distribution Interface (TSO – DSO project)
Working closely with the industry
DSO DevelopmentImmediate completed and ongoing actions
45
2016. UK Power Networks. All rights reserved
Support from the regulator and policy makers
Develop aligned incentives to promote whole system solutions
Understanding the costs of developing and deploying new
DSO capabilities
Framework for DNOs to build storage
DSO Commercial Frameworks & Market
Platforms
Smart EV Charging StandardsVisibility and Control
Cross VectorGas and Heat synergies
InnovationRegulatory Framework Efficient Costs
46
2016. UK Power Networks. All rights reserved
Break-out sessions
Group 1
Neil Madgwick
Service Development Plan -looking forward
Holborn Room
Group 2
Steve Bradley
Service Development Plan -looking back
Nickleby Room
Group 3
Ian Cameron
The next 5 years
Oliver Twist Room
47
2016. UK Power Networks. All rights reserved
Tea & coffee
48
Please reconvene in break-out room at 11.30
2016. UK Power Networks. All rights reserved 49
2016. UK Power Networks. All rights reserved
Service Development Plan – looking back
Steve Bradley
Service Development Plan
- looking back
50
2016. UK Power Networks. All rights reserved
Our Service Development plan 2016-17Ref Action Measure Target Date Status
6.16Implement trial of timed/profile connection agreements with generation customers
>1MWImplement trial by target date and publish findings within six months Jun-16 Complete
7.16Define a process to allow a queue position to be gained form budget estimate
requests
Co-design process with customers and published consultation by target
dateAug-16 Complete
15.16 Publish load capacity, export and import guidance information Publish heat map by target date Sep-16 Complete
17.16Offer connection 'Surgeries' to customers through different channels including web
share and video conferencing
Surgeries available to customers through different channels by target
dateMar-17 Complete
27.16 Publish quarterly updates to Contracted Connections Register (CCR) Updates made in line with target dateQuarterly from
Jun-16Complete
28.16Statement of Works (SoW) - introduce arrangements to advise customers on project
progress/status through SoW processStatements of Works process implemented by target date Sep-16 Complete
29.16 Implement process to identify DUoS charges up-front identifying potential red zones Charges provided with all quotes by target date Aug-16 Complete
30.16Publish details of cancelled and withdrawn offers. (Include capacity absorbed with
LV/G83 connections).Quarterly updates made in line with target date
Quarterly from
Jun-16Complete
31.16Provide queue position and technology type of projects ahead of you in the queue in
our quotesQuotes to contain technology type by target date Sep-16 Complete
32.16Publish outcome from QMEC works relating to queue management explaining our
milestones and how they will be enforced. (inc. information re project termination)Publish policy by agreed date Sep-16 Complete
33.16 Develop storage policy/guidance document with customers and publish Publish policy by agreed date May-16 Complete
36.16 Reduce the average transaction time for the completion of land rights A 10% reduction between April 2016 & March 2017 Mar-17 On track
37.16 Reduce the average time to send quotations A 10% reduction between April 2016 & March 2017 Mar-17 On track
43.16Provide details of history of outages/planned outages on request (or when known will
have an impact)Provide plans to customers on request by agreed target date Sep-16 Complete
44.16 Post connection assessment of Active Network Management (ANM) schemes Assessment complete and any recommendations documented and
published by target dateJul-16 Complete
45.16Agree kick-off meeting with customers within 4 weeks of project acceptance and
subsequently agree construction programme within a further 4 weeks
Construction programme issued within 8 weeks of acceptance for all
jobsSep-16 Complete
55.16 A storage guide for domestic/small commercial Guide published Jan 17 Complete
51
2016. UK Power Networks. All rights reserved
Your feedback
52
• Have we done what we said we would?
• Do we need to do anymore on any of the initiatives –
should any be carried over to 2017/18?
• What difference have they made?
• Did any other DNO do anything you feel we should be
considering?
2016. UK Power Networks. All rights reserved
Initiative 7.16
53
7.16Define a process to allow a queue position to be
gained from budget estimate requests
Co-design process with customers and
published consultation by target dateAug-16 Complete
• Limited responses
• No real consensus
• Why chargeable?
• Alternative being worked-up
2016. UK Power Networks. All rights reserved 54
Existing process
Unlimited Budget Estimate
applications
Unlimited formal Connection
Offer applications
APPLICATION DATE
Respond within 20 working days
maximum
Respond within 65 working days maximum
• No LOA• No Q position• No upfront
payment
• LOA required• Q position from
application date
DAY 0
• Lots of wasted effort for UKPN
• Customers submit multiple applications
• Difficult to manage
• Increased O/H
20 WDs 65 WD’s45 WDs10 WDs
2016. UK Power Networks. All rights reserved 55
Consultation proposed process
Maximum 3 Budget Estimate
applications
formal Connection
Offer Chosen
APPLICATION DATE 10 DAYS
TO
CONFIRM• £500/ BE
application• Response within
35WD’s very challenging
• Increased probability of errors/LC12 failures
• Less wasted effort for UKPN
• Payment received
INFORMATION:
LOA required at day 0
ENA application form required at day 0
Interactivity Q position and minimum info date
from application date DAY 0
DAY 0
Respond within remainder 65 working days maximum
(MINIMUM NO OF DAYS = 35WDs)
Respond within 20 working days
maximum
20 WDs 65 WD’s45 WDs10 WDs 30 WDs
2016. UK Power Networks. All rights reserved
Service Development Plan – looking forward
Neil Madgwick
Service Development Plan - looking forward
56
2016. UK Power Networks. All rights reserved
…...anything else?
57
Our Service Development plan 2017-18
StorageBehind
the meter
EVs DSO transition
Initiative Measure
1 Improve DG mapping tool Review heat-map functionality and consider how existing version can be
improved and how other technologies functionality might be added/included
2 Actively encourage storage in the right places Develop methodologies/processes to encourage connection of storage to our
network using appropriate signals
3 Review application form to assess suitability for augmentation of an existing
connection
Assess suitability of current application form against current market
4 Offer extracts of the DG mapping tool as shape files Offer output of DG mapping tool in different formats in line with customer
request
5 Develop and publish a capacity loaning process Publish capacity loaning policy to allow more connections to the network
6 Continue owner/operator workshops Hold bi-annual O/O workshops
7 Develop and publish Budget Estimate to Formal application process Policy published
8 Review connection offer is it fit for purpose? Review offer, for DG customers (mainly) as feedback suggests it is not always
appropriate
+ others that are relevant to other market segments
2016. UK Power Networks. All rights reserved
1. Improve DG mapping tool
58
Scottish Power
Energy Networks
Northern Power Grid
Electricity North West
2016. UK Power Networks. All rights reserved
2. Encourage storage
59
2016. UK Power Networks. All rights reserved
3. Review application form
60
2016. UK Power Networks. All rights reserved
4. DG mapping tool shape files
61
2016. UK Power Networks. All rights reserved
5. Capacity loaning process
62
• Identifying slow moving
projects (smp)
• DNO “borrows” capacity
from (smp)
• DNO “lends” capacity to
new party
• Ability to terminate loan
if necessary
• Facilitate more
connections
2016. UK Power Networks. All rights reserved
6. Owner/operator workshops
63
2016. UK Power Networks. All rights reserved 64
Existing process
Unlimited Budget Estimate
applications
Unlimited formal Connection
Offer applications
APPLICATION DATE
Respond within 20 working days
maximum
Respond within 65 working days maximum
• No LOA• No Q position• No upfront
payment
• LOA required• Q position from
application date
DAY 0
• Lots of wasted effort for UK Power Networks
• Customers submit multiple applications
• Difficult to manage
• Increased O/H
20 WDs 65 WD’s45 WDs10 WDs
7. Budget Estimate to Formal application
2016. UK Power Networks. All rights reserved 65
Consultation proposed process
Maximum 3 Budget Estimate
applications
formal Connection
Offer Chosen
APPLICATION DATE 10 DAYS
TO
CONFIRM• £500/ BE
application• Response within
35WD’s very challenging
• Increased probability of errors/LC12 failures
• Less wasted effort for UK Power Networks
• Payment received
INFORMATION:
LOA required at day 0
ENA application form required at day 0
Interactivity Q position and minimum info date
from application date DAY 0
DAY 0
Respond within remainder 65 working days maximum
(MINIMUM NO OF DAYS = 35WDs)
Respond within 20 working days
maximum
20 WDs 65 WD’s45 WDs10 WDs 30 WDs
2016. UK Power Networks. All rights reserved 66
Post-Consultation proposed process
Maximum 3 Budget Estimate
applications
formal Connection
Offer Chosen
APPLICATION DATE
FOR Q POSITION IN
INTERACTIVITY
Respond within 20 working days
maximum
• No upfront payment
• Slightly longer to receive Quote
• Same effort as Consultation Process
• No payment required
• More time to quote than Consultation Process
Respond within 65 working days maximum
MINIMUM INFORMATION DATE
SET REGULATORY CLOCKS
1 Site/1 technology type
20 WDs
65 WD’s45 WDs
10 WDs 30 WDs
10 DAYS
TO
CONFIRM
2ND DAY 0 DAY 0
INFORMATION:
LOA required at 2ND day 0
ENA application form required at 2ND day 0
Interactivity Q position from DAY 0
Minimum info date from 2nd DAY 0
2016. UK Power Networks. All rights reserved
8. Review Connection Offer/Quote
67
2016. UK Power Networks. All rights reserved
The next 5 years - Innovation
Ian Cameron
The next 5 years
68
2016. UK Power Networks. All rights reserved
Innovation in the next 5 years
69
The Challenge:
Limited Capacity
Maximise Existing Capacity
•Real Time Transformer Ratings
•Demand Side Response
•Flexible Urban Networks-LV
•Flexible Urban Networks-HV
•Kent Active System Management
•Losses Management
The Challenge:
LV Network Visibility
Integrated LV Control Project
•Develop and go-live with a live LV control diagram for all three networks
•Targeted rollout of secondary substation monitoring (RTUs) providing visibility, control, and signalling
•Smart Urban LV Network
The Challenge:
Reliable Dynamic Network
•Power flow Monitoring
•More Active Network Management- Load
•Transmission Distribution Interface 2.0
The Challenge:
Rush for Storage
•PowerFuL-CB- Power Electronic fault limiting CB
•Domestic Energy Storage & Control
•Smarter Network Storage operational experience
The Challenge: Ambitious Low Carbon Transition targets
•UPS London Fleet electrification
•TfL Electric Buses
•London Taxi fleet electrification
•Time of use Connections
•Energywise
What else?
http://innovation.ukpowernetworks.co.uk/innovation/en/
2016. UK Power Networks. All rights reserved 70
2016. UK Power Networks. All rights reserved 72
2016. UK Power Networks. All rights reserved 73
2016. UK Power Networks. All rights reserved
Applying for a new Distributed Generation
scheme
74
- Customer is offered unrestricted
access to the requested capacity;Key aspects
Level of control
required
Cost of
connection
- Connection is offered with minimal
export control requirements.
Normal G59 application
(“business-as-usual”)
- In several network locations there is
limited unrestricted capacity available;
- In those locations offers often include
significant network reinforcement.G
.
.
.
M
max= 20 MW
20 MW
2016. UK Power Networks. All rights reserved
Applying for a new Distributed Generation
scheme
75
G59 application with
export limitation
- Customer is able to install capacity above
the maximum export limit (assuming other
design aspects, such as fault levels, are
observed);
Key aspects
Level of control
required
Cost of
connection
- An Export Limiting Scheme compliant with
EREC G100 needs to be installed by the
customer to keep export below the
maximum limit.- A scheme based on EREC G100 should
have marginal impact on total project
cost.
G
.
.
.
M
max= 20 MW
25 MW
G100
2016. UK Power Networks. All rights reserved
Applying for a new Distributed Generation
scheme
76
Profile-based connection
- Customer specifies power requirements
per time of day/season.
- No real-time constraint monitoring.
Key aspects
Level of control
required
Cost of
connection
- Two layers of control:o Limitation scheme with “time of day /
season” logic to be installed by the
customer;
o UK Power Networks generation substation
RTU to monitor compliance with contracted
profile.
- Upstream network reinforcement
requirements are minimised;
G
.
.
.
M
max= 20 MW
20 MW
P20MW
t24h
P
t24hEXPORT
EXPORT
UK Power Networks RTU
G100
2016. UK Power Networks. All rights reserved
Applying for a new Distributed Generation
scheme
77
Flexible DG connection
- Customer export is managed in real time for
pre-specified constraints.
- Annual estimation of energy curtailment is
provided to the customer;
Key aspects
Level of control
required
Cost of connection
- Live monitoring and control infrastructure is
required on both customer’s and UK Power
Networks ends.
- Upstream network reinforcement
requirements are minimised;
- Increased costs for monitoring and control
infrastructure.G
.
.
.
M
20 MW
...
M
Active Network Management
max= 20 MW
2016. UK Power Networks. All rights reserved 78
2016. UK Power Networks. All rights reserved
Where we are now
79
Flexible DG is supporting the low carbon transition - enabling cheaper and faster connection of renewable energy
FPP March – 15 generators connected
FDG Norwich Main – 8 generators connected
FDG Maldon – 1 generator connected
FPP
March
FDG
Norwich Main
Flexible DG has supported:
39.9MW 68.35MW 0.5MWFDG
Maldon
FDG
Walpole East
• 111MW connected
FDG Walpole East – 4 generators contracting
2016. UK Power Networks. All rights reserved
What we have announced
80
Extending our Flexible DG service across East Anglia
5 zones are open for Flexible DG applications
from 31 January 2017
o FPP March
o FDG Norwich Main
o FDG Walpole East
o FDG Maldon
o FDG Great Yarmouth
2016. UK Power Networks. All rights reserved
What we have coming up
81
Continuing to expand our Flexible DG service
EPN - 1 further zone will open for Flexible DG
applications Q1 2017
o FDG Burwell
SPN - South East open for Flexible DG
applications from June 2017
o FDG South East
2016. UK Power Networks. All rights reserved
What we have committed
82
FDG rollout plan to 2020/21 across East Anglia
FDG areas opened Jan’2017
FDG zones in 2017
FDG zones in 2018/19
FDG zones in 2020/21
No current plans for FDG
Flexible DG roll-out plan for East Anglia
- Subject to review by UK Power Networks and dependant on the uptake of DG in the area and completion of network investments
Flexible DG rolled out across East Anglia and South Coast by 2021 - Subject to review by UK Power Networks and dependant on the uptake of
DG in the area and completion of network investments
2016. UK Power Networks. All rights reserved
Are you happy with the scale of our
ambition to roll-out Flexible DG?
83
Vote Now
10
0 2 4 6 8 10 12 14
Yes - Flexible DG connections fully rolled-out across EPN and SPN by 2021
No - We wish you to increase the scale of your ambition
2016. UK Power Networks. All rights reserved
PowerFuL-CB
84
Type Who Where What Why
1 Primary Sub(in bus tie or incomer)
Releases fault level headroom that can be used by any customer
Strategic investment to enable one large generator, or several smaller generators to connect
2 Customer’s premises(in series with GCB)
Reduces or eliminates a single customer’s fault level contribution
Get smaller generators (<5MVA) connected quickly, even if no fault level headroom – no need to wait for DNO to reinforce or install a FCL
Power-Electronic Fault-Limiting Circuit Breakers (FLCBs) will make it quicker and cheaper to connect
DG in urban areas where fault level headroom is the main constraint.
A FLCB is 20 times faster than a conventional circuit breaker – fast enough to block the first peak of a fault
current. We are running a £6.2m, 4½ year NIC project to develop and trial two types:
Why are we investing in FLCBs?
• High fault levels will make it increasingly difficult to connect DG in urban areas
• Traditional reinforcement is too expensive and too slow; fault current limiters take up too much space
• FLCBs are affordable & small enough to retrofit into indoor substations / customers’ premises
• FLCBs could save £400m and release 460MW of DG capacity across GBOfgem: PowerFul-CB
2016. UK Power Networks. All rights reserved
Which do you think is the best place
to install a FCL or FLCB
85
At the DNO substation, so it
creates a certain amount of
fault level headroom for all
customers
1.
At the customer's premises,
so it enables that customer to
connect as much generation
as they want without causing
fault level rises
2.
Vote Now
At the DNO substation, soit creates a certainamount of fault levelheadroom for allcustomers
At the customer'spremises, so it enablesthat customer to connectas much generation asthey want withoutcausing fault level rises
2016. UK Power Networks. All rights reserved
We need a customer to help us trial Method 2
86
What we’re looking for
• Accepted or existing non-firm generator connection (i.e. on an inhibit scheme)
• Synchronous generator up to 4.5MW continuous export (ideally CHP)
• Enough space for the FLCB (approx. 4.0x1.3m footprint)
• Can tolerate your generator being tripped several times during the 2-year trial period
What’s in it for you
• Get a free upgrade to a firmer connection at the end of the 2-year trial(if successful)
• First-hand experience with a new technology that could unlock additional sites for your generation portfolio
• Monetary compensation
Timeline
• Feb 2017: project kickoff
• Jan 2018: trial agreements signed –commence design and manufacture
• Jan 2019: commence FLCB installation and commissioning
• Jun 2019: trial start
• Jun 2021: trial end
• Trial can potentially start earlier if we can confirm a suitable customer!
Please email [email protected] if you would like to participate
2016. UK Power Networks. All rights reserved
How are you able to help?
87
Vote Now
10
I’d like to trial a FLCB on my premises as part of my generation project
I’d like to engage during the trial to help UKPN understand customer’s requirements for fault level solutions
I’d like to know more once it’s ready for BAU
I’m not interested in this technology
2016. UK Power Networks. All rights reserved 88
2016. UK Power Networks. All rights reserved 89
Bolney GSP
Ninfield GSP
Sellindge GSP
Canterbury
GSP
South East Network
2016. UK Power Networks. All rights reserved
BETTESHANGER
CANTERBURY SOUTH
HERNE BAY
RICHBOROUGHTHANET
FOLKESTONE
SELLINDGE
CANTERBURY NORTH
NATIONAL GRID GSP
NATIONAL GRID GSP
RUCKINGE
ASHFORD
HASTINGS
RYE
TO NINFIELD & BOLNEY
LITTLE CHEYNE
THANET OFFSHORE WINDFARM
CANTERBURY NORTH
SELLINDGE
CLEVE HILL
DUNGENESSNINFIELDBOLNEY
KEMSLEY
LOVEDEAN
1.1GW
IFA (existing)2GW
London Array0.63GW
Voltage Collapse
Voltage Collapse
System Constraints
90
2016. UK Power Networks. All rights reserved 91
Connecting You to the South East Network
Regional
Development
Programme
Transmission
& Distribution
Interface 2.0
Flexible
Connections
Kent Active
System
Management
2016. UK Power Networks. All rights reserved
Regional Development Programme (RDP) –
UKPN/National Grid
Kick-off
meeting
Scoping of
InitiativesImplementation
1 2
First workshop
Aug 2016
Scoping
Aug – Dec 2016
Implementation of whole
system initiatives from
Jan 2017
Work Plan
3
Work plan
Jan 2017
• Initiatives include:
– Development of a Technical and Commercial Framework (ANM)
– Enhanced modelling and data sharing
– Facilitating Storage/Commercial Services in ANM areas
– Addressing Loss of Mains challenges
4
92
Maximising and optimising network capacity
2016. UK Power Networks. All rights reserved
Flexible DG Zone
Expression of Interest
Joint National Grid and
UK Power Networks RDP
Work
Start offering Flexible
DG connections
1 2 3
Expression of
Interest
Oct – Dec 2016
FDG applications from
June 2017
Working to provide new connections to our customers
93
Commercial and
Technical frameworks
Jan – May 2017
2016. UK Power Networks. All rights reserved
Flexible DG Zone and RDP – What It Means?
94
Continued access to network capacity
Better informed connection offers
Cross network queue management
Improved analysis means a better understanding of the collective
capability of the Transmission and Distribution networks
Establishing a means of compensating Distribution curtailment for
Transmission congestion
Greater commitment needed from developers
2016. UK Power Networks. All rights reserved
Innovation strategy continues to be pivotal
Technical Commercial Services
2011 2012 2013 2014 2015 2016 - 2017
Low Carbon
London (LCL)
Flexible Plug
and Play (FPP)
Smarter
Network Storage (SNS)
Kent Active
System Management (KASM)
Transmission/Distribution
Interface (TDI)
Understanding
smart grids
2016
TDIConnecting
more DG
ANMNew
technologies
Interface with
TSO
DNO TSO
95
2016. UK Power Networks. All rights reserved
Transmission & Distribution Interface 2.0 (TDI2.0)
8
Project funding
approvedProject
kick-offTrials
1 2
Project Start
Jan-Feb 2017
Trials on the
network
2019
Project design
Technical and
Commercial
3
Design Phase
2017
• Joint UK Power Networks/NG Project
• Distributed Energy Resources (DER) services to relieve transmission constraints
Reactive injection to manage low voltages
Reactive absorption to manage high voltages
Active power reduction
Build and
Test
Final Decision
Nov 2016
54
96
New market opportunities for distribution customers
Readiness
before trials
2018
2016. UK Power Networks. All rights reserved 97
TDI 2.0 – Customer Engagement
A Clear Message
• Flexible DG
Applications
• TDI2.0
Expression of
Interest
Working with
customers to build
technical
requirements
2016. UK Power Networks. All rights reserved
Our 2017 South East Plan
98
Joint readiness
• UKPN and NGET working together to create:
• Commercial Frameworks
• Technical requirements
Customer engagement:
• Creating a product that works for you
• TDI 2.0 technical requirements workshops
• We want your feedback!
Flexible DG South East Application Process and TDI 2.0 Expression of
Interest
Release Date June 2017
A single clear message for the South East
Jan to May June onwards
2016. UK Power Networks. All rights reserved 99
ENA TSO – DSO Project
ENA
TSO-
DSO
ProjectT-D Process Charging
Customer
ExperienceDSO
Transition
TDI Workshops
London: 15th February 2017For the London workshop please click here.
Glasgow: 22nd February 2017For the Glasgow workshop please click here.
2016. UK Power Networks. All rights reserved 100
2016. UK Power Networks. All rights reserved
Acronyms
101
ANM Active Network Management
BAU Business As Usual
BEIS Business, Energy and Industrial Strategy
CB Circuit Breaker
CHP Combined Heat & Power
DER Distributed Energy Resources
DG Distributed Generation
DG-DNO Distributed Generation- Distribution Network Operator
DGs Distributed Generators
DNO Distribution Network Operator
DSO Distribution System Operator
DUoS Distribution Use of System
ED1 Electricity Distribution
EHV Extra High Voltage >11kV
ENA Energy Network Association
EPN Eastern Power Networks
EREC Engineering Recommendation
EU European Union
EV Electric Vehicle
FPP Flexible Plug and Play
G100 Engineering Recommendation - Small Scale Export Limitation
G59 Engineering Recommendation - Generation over 50kW
G81 Our technical library
G83 Engineering Recommendation - Small scale generation under 3.68kW single phase/11.04kW three phase
GBSO Great Britain System Operator
GRP Glass Reinforced Plastic
GSP Grid Supply Point
I&C Industrial & Commercial
ICT Information Communication Technology
IT Information Technology
KASM Kent Active System Management
LC12 Licence Condition 12
LCL Low Carbon London
LOA Letter of Authority
LPN London Power Networks
LV Low Voltage
NG National Grid
O/H Over Heads
OHL Over Head Line
P2 Engineering Recommendation P2
P6 Primavera (version 6)
QMEC Quicker and More Efficient Connections
RTUs Remote Terminal Unit
SCADA Supervisory Control and Data Acquisition
SNS Smarter Network Storage
SO System Operator
SOW Statement of Works
SPN South Eastern Power Networks
SRS Site Responsibility Schedule
T&D Transmission & Distribution
T-D Transmission - Distribution
TDI Transmission Distribution Interface
TfL Transport for London
TO Transmission Operator
TX Transformer
UPS Uninterruptible Power Supply
WD Working Days
If you have any questions/feedback please contact [email protected]