2015

EDUCATIONAL PLANT SURVEY

Approved by Brevard County School Board: June 9, 2015

Approved by Florida Department of Education: June 11, 2015

Page 2: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - ii - June 2015

BREVARD COUNTY

DISTRICT SCHOOL BOARD

DISTRICT I Misty Belford

DISTRICT II John Craig

DISTRICT III Amy Kneessy

DISTRICT IV Karen Henderson

DISTRICT V Andy Ziegler

SUPERINTENDENT OF SCHOOLS Brian T. Binggeli, Ed.D.

2700 Judge Fran Jamieson Way

Viera, FL 32940

Phone: (321) 633-1000

Page 3: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - iii - June 2015

EDUCATIONAL PLANT SURVEY TEAM

The survey was completed by

The School Board of Brevard County Facilities Planning Department

with

coordination and technical assistance provided by

Fran Pickett & Associates Inc.

458 St. Johns Drive

Satellite Beach, FL 32937

Page 4: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - iv - June 2015

2015

EDUCATIONAL PLANT SURVEY

TABLE OF CONTENTS

GUIDE TO THE EDUCATIONAL PLANT SURVEY

Overview

Historical Perspective

Fiscal Perspective

Facility Lists – EPS Section 2

Recommendations – EPS Section 3

COFTE – EPS Section 4

Student Membership – EPS Section 5

Financial Summary – EPS Section 6

Long Range Planning Summary – EPS Section 7

Board Priorities for Capital Outlay

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

SECTION 1 – SURVEY Preface

Introduction to the Educational Plant Survey

• Definition of an Educational Plant Survey

• Purpose of an Educational Plant Survey

• Legal Basis for Educational Plant Surveys

• Method for Making Educational Plant Surveys

• State-level Requirements

• School Size

• Wooden Buildings

• Unsatisfactory Space

• Inadequate Space

• Relocatable Building

Page 5: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - v - June 2015

• Student Station

• Student Capacity

• Utilization Factor

• Initial and Ultimate Student Capacity

• Use of State and Local Funds for Recommended Facilities

• District School Board Policies and Prerogatives

• Guide to Capital Outlay Classification (COC)

• School Plant Planning

• School Size

• Educational Facilities Planning

• School Plant Design

• Florida Inventory of School Houses (FISH)

• School Sites

SECTION 2 – FACILITY LISTS Facilities List

• Minimum Space Requirements

• Building New Schools or Additions To Existing Schools Relative To

Approved Facility Lists

Elementary (KG - 06)

Elementary (PK - 06)

Elementary (KG - 03)

Elementary (03 - 06)

Alternative Education (KG - 12)

Middle (07 - 08)

Combination (07 - 12)

Senior High (09 -12)

County Administration (District Services)

Maintenance (District Services)

Transportation (District Services)

Warehouse (District Services)

Multiple Use Support (District Services)

Pre-K ESE (PK)

Adult Education (AE)

Exceptional Student (PK – 12)

Page 6: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - vi - June 2015

SECTION 3 – RECOMMENDATIONS By Facility in Alphabetical Order

Districtwide Recommendations

SECTION 4 – COFTE Analysis of Student Populations

• Technique for Predicting COFTE Student Membership Trends

SECTION 5 – STUDENT MEMBERSHIP

SECTION 6 – FINANCIAL SUMMARY

SECTION 7 – LONG RANGE PLANNING SUMMARY Ten Year Capacity

Ten Year Infrastructure

Ten Year Maintenance

Ten Year Utilization

Twenty Year Capacity

Twenty Year Infrastructure

Twenty Year Maintenance

Twenty Year Utilization

Page 7: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - 1 - June 2015 2015

GUIDE TO THE 2015

EDUCATIONAL PLANT SURVEY

_______________________________________________________________________________________________

The Educational Plant Survey (EPS) must be submitted o n l i n e in an

electronic reporting format provided by the Florida Department of Education’s

(FDOE) Office of Educational Facilities. The report, generated from the electronic

format, begins with Section 1. The purpose of this Guide is to supplement the

report from the FDOE with information that is specific to Brevard County and to

clarify information contained in the report.

OVERVIEW

The EPS is a document containing all of the facility improvements (new

construction and remodeling/renovation of existing space) that have been approved

by the FDOE. The EPS is the also the basis of the School District’s annual

Five Year District Facilities Work Program. The purpose of the EPS is to

document the facility needs of the School District on a school-by-school basis, and

to identify which capital projects may be initiated. It is important to note that a

facility improvement must be contained in the approved EPS in order to finance

the improvement with “state” funds (COP, RAN, PECO, or 1.5-mill ad valorem

tax). Improvements funded with locally generated revenue (impact fees, sales tax,

local bonds) do not have to be in the approved EPS.

By statute, a new EPS supersedes all previous Educational Plant Surveys.

Recommendations in the previous EPS that have not been implemented are not

eligible for the expenditure of state capital outlay funds unless recommended in the

new Survey. The EPS must be prepared and submitted for approval every five

years at a minimum, but intermediate updates, called “spot surveys” may be

submitted at any time in order to obtain FDOE approvals for changes to the plan.

Brevard County must complete a new EPS by the end of the 2014-15 school year.

In November of 2014, the Brevard County voters approved a half cent sales surtax to

be used for facility renewal, education technology, and school security. Items that

will be funded with the sales surtax revenue are included in this EPS in order to

document the work. Additionally, including it in the EPS will give the District

flexibility to utilize state funds if there are projects that must be done before sales

surtax revenue is available.

The construction, renovation and maintenance of educational facilities are the

largest capital investment of a public school system. To achieve the greatest benefit,

school administrators must ensure that:

Page 8: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - 2 - June 2015 2015

The investment reflects the strategic direction of the School Board

Master plans, designs and capital improvement funding initiatives meet

the functional requirements to provide the desired services

All work performed meets regulatory standards

The validity of an EPS is dependent upon:

An accurate inventory of existing facilities in the Florida Inventory of

School Houses (FISH)

Accurate school-by-school membership projections

Facility lists which reflect the curriculum priorities of the District, the

intentions of the Board and compliance to the State Requirements for

Educational Facilities (SREF)

This document reflects the input from:

Planners in the Facilities Planning Department who validated the

FISH data and met with school-based management teams to

determine the capital requirements at each school

Inspectors from the Plant Operations and Maintenance Department who

performed individual school condition assessments to identify deferred

maintenance tasks that would extend the useful life of these assets

School-based management teams

Consultants who provided a statewide perspective as well as technical

assistance and coordination

Based on the “state” capital funding projected to be available during the next five

fiscal years, the focus of the School District will be the projects in this document that

address the needs associated with:

Health and Safety – Removing or correcting structural and

environmental conditions that threaten or imperil occupants to include

mandated improvements required by regulatory agencies

Maintenance and Repair – Completing deferred maintenance projects

that will extend the useful life of existing facilities

Sales Surtax funds will be used to address the needs associated with:

Priority 3: Renewal – Rebuilding, replacing, or adding to existing

environments by bringing them up to current standards.

Page 9: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - 3 - June 2015 2015

HISTORICAL PERSPECTIVE

The international space race of the 1950’s and 1960’s brought a population

explosion to Brevard County that continues to influence the facility needs of the

School District today. In 1955, there were 8,500 students enrolled in Brevard

County's Public Schools. Over the next 15 years, the number of students increased

nearly eight-fold, peaking at 62,500 in 1969. Of the 82 schools in the School District

today, 16 were built in the 1950’s and 38 in the 1960’s.

Brevard Public Schools maintains the public school enrollment statistics for the

number of students in public schools and reports those figures to FDOE. The

historic student enrollment statistics are outlined in Figure 1. In 1972,

enrollment began a ten-year decline at the end of the Apollo program.

Membership dropped by 18,000 students and resulted in the closure of seven

schools. In 1982, a new growth trend began and membership peaked again in

2004-05 with over 76,000 students; however membership declined for several

years until 2013. Membership rose again for the 2014-15 school year, with small

increases projected each year until 2022.

At the same time, the FDOE uses the enrollment statistics and calculates actual and

projected Capital Outlay Full-Time Equivalent (COFTE) Student Membership data

as a measure for school financing. For the latest COFTE calculations released in

June of 2014, the actual COFTE for Brevard was 62569.59 for the 2013-14 School

Year, with 62,268.91 projected for the 2014-15 School Year. When we compare the

COFTE to the BPS enrollment statistics, there is a significant gap. More details

about this gap will be described in the section titled “COFTE – EPS Section 4.”

Figure 1

Page 10: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - 4 - June 2015 2015

In addition to membership growth, there are other factors that have increased the

need for additional space and the renovation of existing spaces:

School building lifetimes are, for the purposes of “life-cycle cost” analyses,

assumed to be 50 years. Life-cycle cost analysis is a method utilized for

assessing the total cost of facility ownership, which involves translating all

expenses associated with building ownership over a prescribed “life cycle”

period into current dollars. A factor used in the analysis is a service period,

typically 25 years, since many components of a building’s infrastructure

must be renovated or replaced at the end of the service period. Because of

the tremendous growth in the 1950’s and 1960’s, approximately half of the

District’s square footage of school buildings was over 25 years old by the

year 2000. This was in spite of the fact that a considerable number of new

classrooms had been built to accommodate the 1982 resurgence in growth.

The Class Size Reduction (CSR) amendment to the Florida Constitution in

2002 necessitated the construction of new classrooms to accommodate the

additional teachers necessary to achieve the reduced class sizes.

The expansion of programs offered by the District, including exceptional

student education (ESE) and early childhood programs, further increased

the number of square feet required to accommodate students.

Finally, recent growth management legislation requires School Districts

and Local Governments to coordinate efforts to ensure student stations will

be available for new students arriving with residential growth. Just as

water, sewer, roads, parks, etc. must be “concurrent” with the proposed

growth, school concurrency must also be evaluated to insure that new

students will have adequate facilities.

The growth patterns in the county have changed over the years, with some

cities growing and others shrinking. New schools or additions are needed to

accommodate these changes in population. Innovations such as “magnet”

schools and “schools of choice,” where families are given the opportunity to

select a school because of unique program offerings rather than a defined

attendance zone, are efforts that the School District implemented to make

maximum use of facilities. Programs of choice are offered in schools where

student populations are declining, thereby relieving over-capacity schools

and increasing the operating efficiency of both.

Page 11: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - 5 - June 2015 2015

FISCAL PERSPECTIVE

The 1994 Educational Plant Survey identified over $500 million in capital

improvements for the District. In 1995, voters defeated a proposed $350 million

bond referendum to fund a portion of the projects. During the next several years,

the District prioritized spending to solve water intrusion and indoor air quality

problems in order to ensure a safer, more healthful environment for students and

employees. While many of the projects identified in the 1994 survey were

addressed, most additions, school renovations and remodeling plans were deferred

in favor of the above priorities. With the 1996 refinancing and expansion of

previously issued Certificates of Participation (COPs), and the 1997 “Classrooms

First” funds (restricted by the Legislature for new construction), some progress was

made on alleviating overcrowding and eliminating relocatable classrooms by

constructing permanent facilities.

In 2002, the School Board authorized the issuance of an additional $50 million in

COPs to fund a program aimed at reducing the use of relocatable classrooms. With

the construction of two new elementary schools (Manatee and Quest) and new

classroom additions, permanent classrooms replaced relocatable classrooms on

twenty-two campuses. However, the passage of the Class Size Reduction

Amendment (CSR) in 2002, which became effective in 2004, made the continued

use of relocatables necessary. The CSR requirement to have smaller class sizes for

the existing student population necessitated the addition of many more classrooms.

In 2003, Brevard voters rejected a sales tax referendum to build new classrooms

and upgrade existing facilities. The state, however, made additional money

available through the “Classrooms for Kids” (CFK) program. Of the $12.8 million

of CFK funds from 2003, $8 million was used to partially fund Sunrise

Elementary School. Without the revenue to construct permanent classroom

facilities, another $4.8 million in CFK funds was utilized to purchase and install 60

relocatables in 2004. Another 71 portables were acquired and installed in 2004

through a lease/purchase program.

In 2004, COPs were sold for $50 million; these funds were used to build Viera High

School and to replace some older elementary school classrooms in use at Rockledge

High. Revenue Anticipation Notes (RANs) for $29.3 million were also sold to fund

new classrooms and other improvements at Space Coast and Edgewood Jr/Sr High

Schools and Thomas Jefferson Middle School.

In 2004, the Brevard County Commission approved an impact fee ordinance to fund

new school construction. The fees are currently $4,445.40 per single family

detached residence; $2,794.25 per multifamily residence and $2,667.24 per

manufactured home. The fees are collected in four Benefit Districts and must be

spent in the Benefit District in which they are collected. While the ordinance took

effect in October 2004, a large number of building permits were approved before the

effective date, resulting in a delay of approximately six months before significant

Page 12: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - 6 - June 2015 2015

collections occurred. Approximately $69 million in impact fees have been received by

the School District through June 2014. Projected collections for Fiscal Year 2014-15

and the next several years are estimated at approx imat e ly $5 million per

year. Figure 2 shows historical collections by year.

Figure 2

In 2005, the School Board determined that, with additional revenues from

property taxes and impact fees, it had sufficient borrowing capacity to embark upon

a Seven Year Facilities Improvement Plan to renovate many of the older

schools and build sufficient permanent capacity to eliminate the need for portables.

The Plan, originally estimated to cost $714 million, included three new elementary

schools, three middle schools, one high school and eleven classroom addition

projects, as well as three performing arts centers and additional competitive sports

facilities. Existing schools would benefit from facilities renewal and core facility

equity improvements as well as Educational Technology and Applied Technology

upgrades. The Plan was financed with $377.8 million of COPs, $66 million of RANs,

$20 million of CFKs, $44 million of Impact Fees and $44 million of local (ad valorem)

tax. The Plan was terminated in 2009 due a lack of available funding resulting

from the financial crisis and a decline in student membership.

Beginning in 2008, the capital fund balance was used to pay debt and provide

minimal funding for capital needs. In 2012, Brevard voters rejected a sales tax

referendum to renew critical infrastructure, resulting in a “repair at failure”

situation for facilities.

Page 13: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - 7 - June 2015 2015

In November of 2014, Brevard County voters approved a half-cent sales surtax for

six years to fund facility renewal, educational technology, and district school

security. The revenues from the sales surtax are estimated to generate

approximately $156.9 million for facility renewal, $25.3 million for educational

technology, and $5.7 million for district school security.

FACILITY LISTS - EPS SECTION 2

The gross square footage for new construction is determined by the guidelines in the

State Requirements for Educational Facilities (SREF). The Facilities Lists in

Section 2 were updated to the latest version of SREF, and form the basis of the

school “prototypes” for the School District. The Facilities Planning Department

incorporated input from the Offices of Curriculum & Instruction, Career &

Technical Education, Transportation and Food Services to establish the lists. Note

that the Facility Lists for each school type are generated for the largest school of

that type in the District – smaller schools can be constructed.

Using the “Size of Space and Occupant Design Criteria” tables in Chapter Six of the

SREF to calculate net square footage, the following process was used:

1. The desired facility space was selected.

2. The recommended size was calculated by multiplying the square footage per

occupant or unit (norm) to get the size of the main space.

3. Related spaces were taken from the SREF table, and added to the size of the

main space to get the total net square footage for the program.

Once the program net square footages were determined, the gross building space

was estimated as follows:

1. The aggregate amount of program net square footage was increased six

percent (per SREF) for interior enclosed space needed for electrical,

mechanical, and HVAC equipment. The result is total net square footage for

the building.

2. The total building net square footage was supplemented for general

circulation, interior and exterior walls, open malls, and roof overhangs. The

additional space is the net-to-gross square footage difference for the building.

The recommended amounts in the SREF are as follows:

(a) Elementary school (grades K-6): 27% of building net square footage.

(b) Middle school (grades 6-9): 32% of building net square footage.

(c) High school (grades 9-12): 34% of building net square footage.

Thus, for an elementary school, the net square footage (NSF) is multiplied by 1.06,

then by 1.27 to get the gross square footage, which is used to calculate costs in

Section 3 and Section 6.

Page 14: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - 8 - June 2015 2015

RECOMMENDATIONS - EPS SECTION 2

This section contains recommendations for new construction, remodeling,

renovation and site improvements on a facility-by-facility basis. The

recommendations are based on the scope of work for projects that could be

constructed utilizing “state” funds. Eligible sales surtax projects are listed in the

EPS because these projects may not be fully funded by the sales surtax revenue or

may need to be completed before the sales surtax revenue is available. By including

the eligible sales surtax funded projects in the EPS, Brevard Public Schools has the

flexibility to start and complete many facility renewal projects as the need arises

and without interruption of the educational calendar.

Based on development data from the local governments, Brevard Public Schools has

identified the need for two new elementary schools within the next six years. The

recommendations in the 2015 EPS do not include the construction of two new

elementary schools because “state” funds cannot be utilized for the construction of

this new capacity. The FDOE will not approve “state” funds for these new schools

because they look at total capacity (permanent and relocatable) on a district-wide

basis. While the FDOE deems that there is sufficient capacity in the Brevard

School District, due to the large geographic size and configuration of Brevard

County, the available capacity is located too far from the areas in need of capacity to

reasonably transport the students. Because the sales surtax funds are limited to

critical infrastructure renewal, the new elementary schools will be funded with

educational impact fees.

COFTE - EPS SECTION 4

Capital Outlay Full-Time Equivalent (COFTE) projections are student projections

developed by the Public Schools PK-12 Education Estimating Conferences each year

and are distributed by the FDOE. Section 1013.64(3)(a), F.S., requires the

Department of Education to compute the COFTE student membership, and that

“each district school board shall receive an amount from the Public Education

Capital Outlay and Debt Service Trust Fund to be calculated by computing the

capital outlay full-time equivalent membership as determined by the department”

for needed projects as shown in the EPS. The Department calculation includes in

the COFTE student membership all students receiving instruction at educational

facilities provided by the school district.

COFTE for a given year is determined, as prescribed by the referenced statute,

“… by averaging the unweighted full-time equivalent student membership for the

second and third surveys and comparing the results on a school-by-school basis with

the Florida Inventory for School Houses (FISH).” Actual COFTE and COFTE

projections provided by the FDOE must be used for the District’s student

projections in the EPS.

Page 15: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - 9 - June 2015 2015

The FDOE’s COFTE projections for Brevard have been lower than the actual

enrollments for every year since 2006 (see Figure 3). Consequently they should be

considered as conservative forecasts of future capital needs. The "actual" COFTE for

the school years from 2006-07 to 2013-14 averaged 3,411 less than the actual

enrollment in Brevard Public Schools.

The 2013 COFTE projections indicate declining student enrollment for the School

District that will continue through the 2018-19 school year. By school type, the

FDOE projects the elementary school enrollment falling each year between 2014-15

and 2018-19; the middle school enrollment exhibits a decrease through 2017-18;

and the high school enrollment will increase by 447 and then decrease from years

2016-17 through the year 2020-21. The total COFTE projections show a decrease of

3,628 from 2013-14 to 2020-21 (Source: Brevard 2014-15 to 2024-25 Adopted Capital

Outlay FTE Student Membership Forecast, June 25, 2014)

There are two student projections, which are used for different purposes:

1. COFTE is calculated by FDOE and must be used to complete the

Educational Plant Survey and the annual Five Year District Facilities

Work Plan.

2. Brevard Public School Projections, represent a unified set of numbers developed

through the BPS Enrollment Projection Management Conference and analyzed by

the Facilities Services and Financial Services Department. The BPS Projections

are used in the Student Accommodation Plan and serve as the basis for the

school concurrency program. These projections are utilized by the District

Finance group in the formulas that determine funding that the District

receives from the State and for school staffing plans.

Figure 3 compares the actuals and the projections for both standards over the last

several years, with projections out to 2019-20 for each.

Figure 3

Page 16: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - 10 - June 2015 2015

STUDENT MEMBERSHIP - EPS SECTION 5

This section distributes the COFTE projections by school. The capacity shown for

each school includes relocatable classrooms. The column showing “Negative

Remodeled Stations” totals -712 and represents the elimination of all relocatable

classrooms that exceed 20 years of age by the end of the EPS. It is important to

note that the projected COFTE at a school cannot exceed 100% of its capacity. As a

result, it is assumed that attendance boundaries will be changed as necessary to

achieve a balanced enrollment at those schools.

FINANCIAL SUMMARY - EPS SECTION 6

This section is a summary of the individual recommendations in Section 3. The cost

estimates for new construction, remodeling and renovation are determined by the

FDOE using the formula shown below. The cost estimates for new sites, additions

to sites and site improvements are determined by District personnel. Cost

estimates of district-wide recommendations for maintenance and operations of

educational plants, safety and sanitation deficiencies are not included in this

section.

The cost per student station is set in State Statute (F.S. 1013.64), and is adjusted

annually by the Consumer Price Index. Costs are based upon the estimated cost

midway through the five-year projection period. Actual costs will be determined

when a project is designed and bid, but may not exceed the FDOE estimates.

Cost per student station includes contract costs, legal and administrative costs, fees

of architects and engineers, furniture and equipment, and site improvement costs.

Cost per student station does not include the cost of purchasing the site,

extraordinary costs to develop the site, the cost of related off-site improvements, or

costs for Enhanced Hurricane Protection Areas (EHPA) required by the Florida

Building Code.

Variations on the costs of remodeling or renovating similar spaces will occur due to

the existing environment’s date of last renovation. For instance, the total cost for

renovating a classroom that recently had a roof, ceiling and lighting upgrade will

naturally be less than a classroom that has not been improved in 20 years. No

allowance for these differences is considered in the calculation formula provided by

FDOE.

Effective Construction Costs for the 2015 Educational Plant Survey

The cost of new construction for an individual Facility List is determined

multiplying the FDOE student station cost at a time that is 31 months from the

date of the EPS (halfway through the five-year survey period) by the total student

stations in the Facility List, then dividing by the gross square footage of the facility.

The cost of Remodeling is one-half of the cost of new construction and the cost of

Page 17: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - 11 - June 2015 2015

Renovation is one-third of the cost of new construction. Ancillary costs are 70% of

the averages of the costs for K-6, 7-8, and 9-12. Effective Construction Costs are

shown in Chart 1.

Chart 1

Grade

Level

Student

Station

Cost

Stations Total Cost Gross

Area

(from

Facility

Lists)

Allowed

Sq. Ft.

Cost

Remodeling

(1/2 New)

Renovation

(1/3 New)

K-6 $22,643 970 $21,963,710 137,285 160 80 53

7-8 $24,452 1,264 $30,907,328 179,109 173 87 58

9-12 $31,761 2,859 $90,804,699 403,780 225 113 75

Ancillary 130 65 43

LONG RANGE PLANNING SUMMARY - EPS SECTION 7

This section is developed to show the projections for Capacity, Infrastructure,

Maintenance Cost and Utilization for the Year 6 – Year 10 planning period and

the Year 11 – Year 20 planning period.

BOARD PRIORITIES FOR CAPITAL OUTLAY

In 1994, the School Board adopted priorities for facility capital investment. These

priorities, their definitions and criteria are as follows:

Priority 1: Health and Safety

Definition: Removing or correcting structural and environmental conditions that

threaten or imperil occupants to include mandated improvements required by

regulatory agencies.

Criterion A: The condition has been responsible for accident/injury

documented by district reporting systems.

Criterion B: The condition has been noted in the district’s annual

Comprehensive Safety Inspection Report as a fire or life/safety hazard or has

been otherwise reported as a hazard and a subsequent investigation has

verified the report.

Criterion C: The condition has been documented by test results, acquired via

generally accepted professional practice, reporting inappropriate

environmental conditions for occupants.

Page 18: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

2015 SBBC Educational Plant Survey - 12 - June 2015 2015

Priority 2: Maintenance and Repair

Definition: Correcting conditions due to deteriorating components or materials that

do not represent health or safety threats.

Criterion A: The condition directly affects educational quality or the

continuation of instruction.

Criterion B: The condition will become a threat to health or safety.

Criterion C: The condition is progressively leading to significantly increased

costs.

Criterion D: The condition detracts from the appearance of the facility.

Priority 3: Renewal

Definition: Rebuilding, replacing, or adding to existing environments by bringing

them up to current standards.

Criterion A: The existing environment(s) is(are) inadequate compared to

current standards.

Criterion B: The age of the existing environment(s).

Criterion C: The existing environment(s) date of last renovation.

Priority 4: New Construction

Definition: Providing additional space to address growth.

Criterion A: The current student population is in excess of the permanent

capacity of the school.

Criterion B: The projected student population is sufficient to maintain a

membership within plus or minus ten percent of the new capacity over the

next five years.

Criterion C: The relative ranking of the school compared to other schools in

need of additional space using the projected rate of student growth over the

next five years.

Criterion D: The current facility is less than the Board-established student

population capacity parameter for the grades/programs served.

END OF GUIDE

Page 19: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

PAGE:1 of 234 Report Date: 6/15/2015 11:49:17 AM

BREVARD COUNTY SCHOOL DISTRICTSurvey: Number 4 - Version 1

District:

Survey Status: Active Approved

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Page 20: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:2 of 234 Report Date: 6/15/2015 11:49:17 AM

Section 1: Survey

Page 21: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:3 of 234 Report Date: 6/15/2015 11:49:17 AM

BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

District:

2015 Survey

Survey Open Date: 3/12/2015 11:56:55 AM

Description:

6/9/2015

DVE768 Approval Date: 4/1/2015

Board Approval Date:

Contact Phone Number:

Dane Theodore

321 633 1000

Contact Name:

Contact Email:

Survey Notes:

[email protected]

Active Approved 6/11/2015 4:34:16 PM Dane Theodore

Survey Status Status Time User

Survey Expiration Date: 6/30/2020

Page 22: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:4 of 234 Report Date: 6/15/2015 11:49:17 AM

PREFACE

Report of an educational plant survey, hereinafter also referenced as “survey,” conducted in accordance with the requirements of, and pursuant to specifications in, Article IX and Article XII of the Florida Constitution; Chapters 1001, 1011, and 1013, Florida Statutes (F.S.); State Requirements for Educational Facilities (SREF); and the Florida Building Code (FBC). This survey report describes the current educational plants and the estimated capital outlay needs resulting from a systematic study of present educational and ancillary plants. This study also addresses the future needs, including long range planning, to provide an appropriate educational program and services for each student based on projected capital outlay FTE’s (COFTE) approved or authorized for use by the Department of Education.

NOTE: All educational plant surveys are valid for five full years and expire on June 30 of the fifth full year from the beginning date of the survey. For example, a survey approved in October will be valid through the remaining fiscal year and for five full years beginning on the following July 1; effectively, this makes the survey approved in October valid for five years and eight months. By the same scenario, a survey approved in May will be valid through the remaining fiscal year and for five full years beginning on the following July 1; effectively, this makes the survey approved in May valid for five years and one month.

Page 23: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:5 of 234 Report Date: 6/15/2015 11:49:17 AM

INTRODUCTION TO THE EDUCATIONAL PLANT SURVEY

Definition of an Educational Plant Survey

The educational plant survey is a systematic study of present educational and ancillary plants and the determination of future needs. The survey is not directly concerned with the instructional program but the relationship of educational plants to the instructional program is such that judgments regarding the instructional program are necessarily a part of an educational plant survey.

Page 24: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:6 of 234 Report Date: 6/15/2015 11:49:17 AM

Purpose of an Educational Plant Survey

A formal educational plant survey is required by §1013.31, F.S., to be conducted every five years, but may be conducted as often as necessary. It is sometimes necessary to make changes to the survey recommendations in the interim. Local school administrators are responsible for a regular auditing of survey recommendations and for the initiation of the request for any necessary changes.

The construction of new educational facilities is a major undertaking even in school systems where such construction is a continuous process. If a 50-year capital investment is to be protected, the location, size, type of materials, arrangement of spaces, and other considerations, regarding each new facility or addition to an existing facility must be determined on the basis of reliable, factual data. To do otherwise would violate the trust of present and future generations of children and of taxpayers.

The purpose of an educational plant survey is to aid in formulating plans for housing the educational activities of students and staff of the school district for the next several years and the survey must consider the local comprehensive plan in its forecast strategies. The development of this plan must be based on a careful study of all available data regarding the current status of educational and ancillary facilities in relation to capital outlay full-time equivalency (COFTE) student membership and the projected changes in COFTE student membership. The intent of a regular, formal educational plant survey is to encourage the thoughtful, orderly development of a program for providing educational and ancillary plants to adequately house the educational and academic support activities of the district.

Page 25: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:7 of 234 Report Date: 6/15/2015 11:49:17 AM

In 1957, the Florida Legislature established the School Construction Fund which annually authorized an increase of $200 per student in average daily attendance, subject to matching by local funds. School Construction Fund monies also had to be expended in accordance with the recommendations of a school plant survey. The program was continued with modifications by subsequent legislatures until 1972.

In 1952, the Florida Constitution §9(d), Article XII, was amended to authorize the issuance of State Board of Education (SBE) bonds guaranteed by the Minimum Foundation Program CO&DS allocation. The SBE bond program led to major school construction activities and further strengthened the school plant survey program by requiring that bond proceeds be expended in accordance with survey recommendations.

Legal Basis for Educational Plant Surveys

When the Florida School Code of 1939 was developed, the importance of having a valid basis for a school building program was recognized by inclusion of the requirement that district school boards have periodic school plant surveys of building needs in the districts. The 1939 Code directed the district school superintendent to "recommend plans and procedures for having a survey made" and instructed the district boards to "approve and adopt a district-wide school building program...based on the recommendations of the survey."

The provisions in the 1939 Code for periodic school plant surveys were, for the most part, ineffective. No state financing program for school plants was in effect at that time. Further, the coming of World War II, and the resulting cessation of school plant construction, made any statutory provision relating to school plants meaningless.

The 1972 Legislature enacted the School District Supplemental Capital Outlay Act as an interim measure pending the outcome of the proposed amendment to §9, Article XII of the Constitution. The amendment, which was ratified in the November 1972 general election, increased the CO&DS annual allotment from $400 to $600 per instruction unit in the school districts for the school fiscal year 1967-1968 plus $800 for each “growth unit” since 1967-1968.

The 1973 Legislature established the Florida Educational Finance Act which provided funds for comprehensive school construction and debt service. The amount allocated to each school district was determined by formulas prescribed by the Legislature.

In 1974, the Florida Constitution, §9(a) (2), Article XII, was amended to authorize the issuance of state bonds guaranteed by revenues derived from gross receipts utility taxes for the state system of public education, including, but not limited to, institutions of higher learning, junior colleges, vocational-technical schools, and public schools, as defined by law.

Since 1974, regular changes have been made to statutory provisions and the Florida Constitution in regards to educational facilities, including the establishment of a state lottery where funding is specifically earmarked for education as a supplement to other state funding, and the capping of class sizes. The continual changes to educational laws and funding mechanisms are due, in part, to Florida’s unrelenting effort to maintain and provide state-of-the art facilities to meet the demands of change for our schools programs and the expectations of our citizenry.

When the Minimum Foundation Program law was enacted in 1947, the requirement for periodic school plant surveys was included. The law established that a Capital Outlay and Debt Service (CO&DS) annual allotment of $400 per instruction unit had to be expended in accordance with a planned building program based on a school plant survey. It was at this point that Florida’s school plant survey program became a meaningful and established operation.

Page 26: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:8 of 234 Report Date: 6/15/2015 11:49:17 AM

Method For Making Educational Plant Surveys

The survey is limited to the study of educational and ancillary plants owned or under long-term lease agreement by the school board. No comprehensive study is made of the instructional program and recommendations made for the improvement of the educational and ancillary plants of the district are not an evaluation of the instructional program. Recommendations, however, must be clearly associated with the relationship between educational facilities and instructional programs.

The board must arrange for an educational plant survey to be conducted either by district staff, through contractual agreement, or a combination of district staff and private vendors. A survey conducted by the Office of Educational Facilities is a cooperative process with staff from the Office of Educational Facilities and staff from school districts outside of the district being surveyed. Typically, the survey process will include, as a minimum:

Spot or grid maps showing the residence of all elementary, middle or junior high, and senior high school students, the school attended by each student, and the location of each school.

COFTE student membership trends of each school center for the past five years.

A floor plan for each building at each educational plant identifying each building and each room (space) by number as they appear in the Florida Inventory of School Houses (FISH).

A list of the construction projects under contract.

A statement of the policies of the board with respect to grade organization and the types and sizes of facilities to be provided for new elementary, middle or junior high, and senior high schools (facilities lists).

Other information that may affect building costs, population trends, and other related matters that may influence the district educational facilities building needs program.

The survey team members visit and evaluate each educational plant; student capacities are carefully evaluated at each school center.

The districtwide projection of students is distributed among the various existing school centers and any new school centers are recommended on the basis of past trends and the best judgment of both the District and the County Growth Management Office as to where growth is most likely to occur.

The survey team should make logical recommendations based on all relevant information available.

*

*

*

*

*

*

*

*

*

The broad, general state-level conditions that give directions to a survey are established as guidelines only insofar as feasible for application within a given district.

The survey report must include a recommended pattern for housing the student projection for a five-year period, including changes in utilization of existing school centers, phasing out of unsatisfactory facilities and/or school centers, additions at existing school centers, and construction of new school centers. Ancillary facilities should also be considered in the recommendations.

State-level Requirements

Page 27: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:9 of 234 Report Date: 6/15/2015 11:49:17 AM

School Size:* Any school that is not large enough to justify a full-time principal, a media specialist, food service staff, and special instructional and clerical staff are economically inefficient and restrictive in program offering; simply stated, minimally sized schools are too expensive to operate if a district lacks sufficient financial resources to make such facilities a viable option. Generally, new school centers are not recommended for fewer than 400 students in elementary schools or 100 students per grade level in secondary schools. Where practical, existing schools that are below these sizes should be consolidated.

Generally, all wooden exterior buildings (other than relocatables) are considered unsatisfactory and are not assigned student capacity.

* Wooden Buildings:

Generally, all wooden exterior buildings (other than relocatables) are considered unsatisfactory and are not assigned student capacity.

* Unsatisfactory Space:

NOTE: Unsatisfactory space is typically designated as such due to compromising effects on the structural integrity, safety, or excessive physical deterioration of a building. Space condition should be the same, either satisfactory or unsatisfactory, for all rooms in a building with the exception of rooms reported in relocatable buildings that represent individual units. A space may be structurally unsound (unsatisfactory) and still be adequate in size.

Generally means that the size of space is not appropriate, sufficient, suitable, or lacks ability to meet the fitting requirements for instruction or instructional support, such as small classrooms or insufficient acreage for a school site. Inadequacy may be a condition brought on by changing standards, or increased enrollment causing overuse thereby resulting in undersized or unsuitable circumstances.

* Inadequate Space:

NOTE: Inadequate space is typically designated as such by the capital outlay classifications (COC) C-3 and C-7. Inadequate is a designation for an entire facility, not just a building or room. A space or building may be structurally sound (satisfactory) and still be inadequate.

Facilities designed and built to be moved from one school to another are recognized as providing valuable flexibility.

* Relocatable Building:

A student station is the area necessary for a student to engage with a teacher in appropriate subject matter educational (learning) activities. The size of this area will vary with the particular type of activity and by grade level. A laboratory or shop in which the student must move about requires more area per student than a regular classroom where the student remains seated at a desk. The total student stations at a school center are used to determine the capacity of the school.

* Student Station:

The maximum number of students that should be housed in a facility. In an elementary school, students are typically assigned to one classroom throughout the day and student capacity for elementary schools equals the student stations. However, in middle and secondary schools, students usually move from classroom to classroom to participate in different instructional subject matter, which interjects scheduling as a factor in calculating capacity. Experience has shown that the number of students in a secondary school is a major factor for determining the efficiency of space utilization that may be expected at a school.

* Student Capacity:

Page 28: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:10 of 234 Report Date: 6/15/2015 11:49:17 AM

Used to determine “capacity” which is the number of students that may be housed in a facility at any given time based on a utilization percentage of the total number of existing satisfactory student stations:

* Utilization Factor:

Type School

Utilization Factor Percentage x

Satisfactory Student Stations

allall300 or less301-600601-900901-12001201-15001501 - and aboveallallallallall

100%90%70%75%80%85%90%95%90%100%100%120%150%

ElementaryMiddle & Junior HighSenior High

Combination SchoolsExceptional Student CentersAlternative Education CentersDesignated Area Vocational CentersDesignated Adult Centers

In the recommendations for building a new school center, the initial capacity assigned is the capacity necessary to house the students anticipated to enroll at the school by the end of the survey projection period. The ultimate capacity is usually the maximum capacity school of that type based on applicable district policies (facilities lists). The establishment of an ultimate desirable capacity makes it possible to plan the initial construction within the framework of the ultimate size school–meaning, building core facilities such as media, cafeteria, administration, circulation, and other auxiliary spaces to the full school size and then adding classrooms as the student population projections increase to a level that warrants additional classroom space.

* Initial and Ultimate Student Capacity:

NOTE: Educational plant survey COFTE student projections are determined by the Office of Economic and Demographic Research (EDR). Each five-year survey is based on COFTE projections that are five (5) full years from the official beginning of the survey period, which is July 1 of the first full year of the survey.

The recommendations made in the survey report are intended, in total, to provide adequate facilities for all of the students projected to be enrolled within the 5-year survey period. The priority systems established in statutes and rules define the eligibility for the expenditure of funds.

* Use of State and Local Funds for Recommended Facilities:

Page 29: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:11 of 234 Report Date: 6/15/2015 11:49:17 AM

NOTE: Educational plant survey costs for student stations are determined by the Office of Economic and Demographic Research (EDR). Each five-year survey is based on cost factors that are 31 months (January, the midway point of the five-year survey period) from the official beginning of the survey period, which is July 1 of the first full year of the survey. All new capacity construction uses the appropriate grade level student station cost factors; the cost per square foot for new construction, remodeling, and renovation is based on actual statewide average construction cost data with the EDR cost index increase applied to use the same 31 months mid-point of the survey costs for planning purposes. This cost estimate process is applied uniformly to all surveys in all districts so that consistent estimates can be made. Actual costs are reported yearly in the 5-year district facilities work program annual budget.

District School Board Policies and Prerogatives

State funds alone usually are not enough to complete the recommended school plant construction program that will be identified in an educational plant survey. To ensure that all capital outlay funds are used for the best and most efficient purposes, the educational plant survey team should collaborate with the professional and instructional staff of the district on a plan for meeting the projected school plant needs for the next several years.

Some of the specific local board policies and prerogatives that generally apply to the survey report are:

Actual assignment of students to school centers in the county as authorized and directed by §1003.02, F.S.;*

Facilities comprising a standard school plant for each grade grouping;*

Square footage and special features of each instructional component (state minimums must be met);*

Special facilities at a school center;*

Level of custodial service;*

Level of maintenance service;*

Level of service indicators for local comprehensive planning;*

Type of climatic control.*

Guide to Capital Outlay Classification (COC)

Educational plants are identified by recommended type of facility for capital outlay expenditures. The COC of educational plants determines the extent to which certain funds may be used for capital improvements, subject to applicable Florida Statutes and SREF standards dealing with budgeting and in some cases priority ratings. The COC of an educational plant can only be assigned or changed by an educational plant survey recommendation made in compliance with all applicable laws, rules, and policies.

The COC is grouped into categories with applicable standards to guide the assignment of the appropriate classification:

Adequate site,*

An educational plant that is recommended for continued use. Generally, this includes:C-1:

Satisfactory building(s),*

Projected membership within desired size range for the type of school,*

Page 30: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:12 of 234 Report Date: 6/15/2015 11:49:17 AM

Recommended new educational plant.*

An educational plant that is in a period of transition with evidence insufficient to recommend replacement or consolidation, and typically new construction is not recommended for this COC. Generally, this includes:

C-2:

Inadequate site and/or inadequate building(s),*

Declining or static enrollment,*

An educational plant that probably would be recommended for consolidation if not for excessive distance required for student transportation.

*

An educational plant that is substandard in one or more major aspects. Generally, this includes:C-3:

Inadequate site and/or unsatisfactory building(s),*

Declining or static enrollment to a level indicating that the needs of students can better and more economically be served at other educational plants,

*

Abandoned educational plants not currently housing students.*

NOTE: Educational plants assigned a C-3 COC and used to house students should be closed when adequate facilities are available elsewhere. Facilities assigned a C-3 COC do not generate PECO maintenance funds even when the facility contains satisfactory space.

Ancillary facility recommended for continued use. Generally, this includes:C-6:

Adequate site,*

Satisfactory building(s),*

Recommended new site and/or facilities.*

Ancillary facility is substandard. Generally, this includes:C-7:

Inadequate site and/or unsatisfactory building(s),*

Abandoned facilities not currently being used.*

NOTE: Facilities assigned a C-7 COC that are in current use should be closed when adequate facilities are available elsewhere. Facilities assigned a C-7 COC do not generate PECO maintenance funds even when the facility contains satisfactory space.

Any district owned facility leased to an entity for use by the lessee for any purpose, including educational, but is not used by the district during the normal school hours of operation.

C-9:

NOTE 1: Facilities assigned a C-9 COC do not generate PECO maintenance funds.

NOTE 2: Facilities assigned a C-9 COC are to be counted in the district’s inventory ofavailable space and may be considered in the determination of new construction needs.

Page 31: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:13 of 234 Report Date: 6/15/2015 11:49:17 AM

School centers are usually classified by standard grade groupings (K-5, 6-8, and 9-12), even though a school may have only one or two of the grades present. A school center may be classified as a combination school and recommended to house more than one grade grouping, e.g. grade group K-8, grade group 6-12, or grade group K-12.

Whenever it is feasible, the survey should contain recommendations to upgrade and/or remodel/renovate existing educational plants that are classified as C-1 to meet the district’s educational facilities standards for spaces and school size based on the districts adopted facilities lists for each grade grouping.

School Plant Planning

Planning a school plant, either a complete new school or an addition to an existing school, is a long and complex process when properly done. Remodeling and renovation of existing space can also be very time consuming to plan when all potential options for upgrading or replacement considerations are made. Suggestions made in this section are intended to provide useful, basic information and are not an exhaustive description of all available options for planning or meeting the facilities needs of a district school board.

School Size

Generally, new school centers are not recommended for fewer than 400 students in elementary schools or 100 students per grade level in secondary schools. Any school that is not large enough to justify a full-time principal, a media specialist, food service staff, and special instructional and clerical staff are economically inefficient and restrictive in program offerings. Schools that are minimally sized are very expensive to operate.

The number of students in a school is a major factor in determining the efficiency of space utilization; schools that are too small do not offer optimal instructional standards or provide economically advantageous structures. Just like small schools are not economical, very large schools are not frugal to build, maintain, or staff. The logistics of managing and maintaining an overly large school can outweigh the reasons for building mega structures (such as more extensive program offerings in science or performing arts–these functions may be offered through magnet schools, thereby meeting a districtwide or area need without the burden of managing an overly large school reconfigured to offer such services).

Optimally, elementary schools should be planned for about 800 students, middle schools should be planned for about 1,200 students, and senior high schools should be planned for about 2,000 students. Flexibility and program offerings that allow schools to offer a more educationally diverse program or structural configurations that can provide significant economic rewards should always be considered when planning new schools. However, experience has shown that by modifying elementary schools sizes by more than 25% above or below the 800 student mark is not usually cost effective nor educationally practical. Secondary schools can sometimes be subjected to 25% to 50% modifications from the recommended median point and still be practical and efficient for both educational offerings and cost savings. Neither small or large schools provide cost saving benefits for construction nor for day-to-day operations; therefore, limiting the size of schools to near average size is usually preferable and more practical.

GUIDELINES FOR SCHOOL PLANT DEVELOPMENT

Page 32: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:14 of 234 Report Date: 6/15/2015 11:49:17 AM

Educational Facilities Planning

The basic concept behind educational facilities planning is a simple one. A school building is primarily a school and secondarily a building. If the “school” is not planned in terms of its purposes, its scope, and its programs, the resulting structure will almost certainly just be a “building.” No architect, regardless of talent or experience in school plant design, can plan a school without guidance from the educators who will use it.

The educational facilities planning process is slow and difficult; planning that does not consider school needs beyond the immediate future places an undue burden on the present and future generations of students and taxpayers. Equally as important as long-range planning, no board should commit local and state revenues for a new educational plant that has not been planned by educators. Although the detailed procedures for educational facilities planning will vary considerably from school to school, the ultimate responsibility for the future rests with those professionals who plan today.

School Plant Design

An architect is responsible for designing the building to house the school program developed through the educational facilities planning process. Usually, the architect participates in that process so that educational planning and design do not constitute separate and distinct steps.

The architect uses other specialists in designing the building and the system(s) it will contain; for example, structural engineers, heating and cooling specialists, electrical engineers, and environmental specialists should be involved in the total process. Some broad guidelines appropriate to school building design are:

A site (plot) plan should be developed to show the most effective use of the site for present needs and to guide future expansion. The site design and orientation should show awareness of the principles of “Crime Prevention Through Environmental Design” (CPTED) including natural access control, natural surveillance, and territorial reinforcement;

*

A building should be functional in design; it should meet the needs of and facilitate the attainment of the designed or planned program of the school;

*

The building must be made safe and healthful for all students and school staff personnel by observing all safety and sanitary regulations appropriate to school plants;

*

A balance should be achieved between quality and economy in construction and the anticipated maintenance and operation of the plant;

*

A building should be designed to permit economical expansion both in terms of additional classrooms and special facilities which will eventually serve the ultimate capacity of the school; e.g., media centers, cafeterias, circulation, sanitation, utilities, and administration should be built to their ultimate maximum sizes if additional classrooms are going to be needed for future expansion;

*

Adequate lighting, natural and artificial, should be provided for all instructional spaces;*

A building should be designed to control the transient noise level; the objective in sonic design of instructional spaces is to secure the best hearing and speaking conditions without adversely affecting the surrounding or adjacent instructional programs;

*

Thermal conditioning of school spaces should be provided by economically designed systems that also render long-term cost savings in maintenance and operations.

*

Page 33: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:15 of 234 Report Date: 6/15/2015 11:49:17 AM

Florida Inventory of School Houses (FISH)

The district’s educational plant survey extracts facilities data from FISH; therefore, if FISH is not current and accurate, the educational plant survey cannot be a valid assessment of needs. The district’s facilities inventory may be corrected at any time when new additions or remodeling occurs, during a validation study conducted by the district or OEF, or as the result of an educational plant survey. FISH is the official inventory of the district’s educational facilities. It is the responsibility of the district to maintain an updated inventory. Changes to FISH are subject to review by OEF for compliance with statutory and rule provisions as well as compliance with educational plant survey recommendations.

NOTE: FISH data is imported into the educational plant survey as it exists the moment the survey is created. When a complete new survey is started, the FISH data is imported and does not change even if FISH changes are subsequently made. When a supplemental/spot survey is created, FISH data is imported into the spot survey as it exists for only the selected facilities as of the moment the spot survey is created; this process allows districts to update FISH and then do an updated survey using current FISH data.

School Sites

Before a site is purchased or funds are encumbered for a site, it must meet the criteria established by §1013.36, F.S. Notably, the law requires a school board to coordinate site planning and selection with affected county and city governments to ensure consistency with local land-use plans. This coordination process is detailed in the interlocal agreement between the school board and the general-purpose local governments pursuant to §1013.33(2), F.S.

The choice of sites for new schools is critical to the overall development of a school plant program. In general, new sites should:

Provide adequate space for school buildings;*

Provide adequate off-street parking and off-street loading/unloading;*

Provide adequate playground area.*

In addition, new sites should generally be located to:

Minimize transportation costs and provide safe access from neighborhoods to the school;*

Avoid sites where adjacent land uses may allow the location of undesirable commercial enterprises or industrial activities near the school;

*

Prevent the location of a site adjacent to, or near, high voltage power transmission lines or in an airport approach flight path;

*

Maximize proximity to residential areas and seek to collocate district educational facilities with other public facilities, such as parks, libraries, and community centers.

*

Page 34: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:16 of 234 Report Date: 6/15/2015 11:49:17 AM

Section 2: Facility Lists

Page 35: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:17 of 234 Report Date: 6/15/2015 11:49:17 AM

FACILITIES LISTS

Minimum Space Requirements

The Facility Lists component identifies the standard schools programs by grouping and listing the classrooms and support spaces that districts normally consider the most ideal for meeting the districts needs. These lists usually are a combination of elementary, middle, senior high, ancillary, and other special school centers such as exceptional students, alternative, and various types of combination schools, e.g. K-8, K-12, 6-12, etc.

All board approved and adopted facilities lists must conform to standards established in SREF. The facilities lists in EFIS are based on net square footage per space; the gross square footage in a facilities list for new construction is determined by adding a standardized percentage of the net square footage for all auxiliary and support spaces. Elementary schools have 27 percent added for net-to-gross conversions; middle schools have 32 percent added for net-to-gross conversions; and high schools have 34 percent added for net-to-gross conversions. An additional 6 percent is added to each type school for mechanical spaces.

Educational plant survey costs for student stations are determined by the Office of Economic and Demographic Research (EDR). Each five-year survey is based on cost factors that are 31 months (January, the midway point of the five-year survey period) from the official beginning of the survey period, which is July 1 of the first full year of the survey. All new capacity construction uses the appropriate grade level student station cost factors; the cost per square foot for new construction, remodeling, and renovation is based on actual statewide average construction cost data with the EDR cost index increase applied to use the same 31 months mid-point of the survey costs for planning purposes. This cost estimate process is applied uniformly to all surveys in all districts so that consistent estimates can be made. Actual costs are reported yearly in the 5-year district facilities work program annual budget.

Costs for remodeling recommendations are typically based on one-half the cost of new construction, but may vary significantly based on the type of remodeling. Costs for renovation recommendations are typically based on one-third the cost of new construction, and like remodeling costs, may vary significantly based on the renovation project. All cost estimates are best judgment approximations and may vary significantly between projects. Before entering into the planning phase on projects, the district should have a professional review of the estimated cost and assure that the current Uniform Building Code standards are applied when the cost estimates are made.

Cost estimates and recommendations for maintenance and operations of educational plants safety and sanitation deficiencies are not included in this survey. Boards should follow the requirements of §1013.12, F.S., to meet the needs in these areas.

Facilities recommended in accordance with the approved facilities lists at existing or recommended new schools may need to be changed as programs change.

Page 36: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:18 of 234 Report Date: 6/15/2015 11:49:17 AM

Building New Schools Or Additions To Existing Schools Relative To Approved Facility Lists

All facility lists are developed and approved by a district school board to establish the district’s standard schools by type and for the ideal size of schools. These lists, once approved by the board and by the Department, are used in the educational plant survey process to identify the space needs of existing schools (comparing FISH and COFTE to the facility lists) and for building new schools. Any new schools constructed or the expansion of existing schools must be relative to the approved facility list and the classroom capacity must not exceed the projected COFTE for that/those schools. When building a new school center or adding classroom capacity to an existing school, the capacity of the instructional spaces (classrooms) for the school may not exceed the projected COFTE planned for the school in the out-year of the survey even though the facility list may be for a larger number of students. The school’s core facilities should be built to the full size of the facility list if it is reasonably anticipated that the school will eventually serve the number of students in the facility list; however, the classrooms must initially only be built to serve the projected COFTE; to do otherwise would violate the public trust and abuse tax-payer money.

Page 37: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:19 of 234 Report Date: 6/15/2015 11:49:17 AM

970

Total Stations: 970 Acres Required: 12

Total Capacity:

808 MATERIAL STORAGE 100 200 0 0 254

2 61 PK - 12 E S E PART-TIME 975 1,950 15 30 2,476

813 STUDENT STORAGE 40 80 0 0 101

815 STUDENT RESTROOM (MALE) 35 70 0 0 88

2 55 PK - 05 MUSIC - ELEMENTARY 1,000 2,000 22 0 2,540

812 PROJECT STORAGE 150 300 0 0 381

806 REFERENCE 100 200 0 0 254

831 MUSIC PRACTICE ROOM 70 140 0 0 177

808 MATERIAL STORAGE 100 200 0 0 254

14 2 04 - 08 INTERMEDIATE/MIDDLE CLASSROOM (4-8) 858 12,012 22 308 15,255

814 STUDENT RESTROOM (BOTH SEXES) 60 2,040 0 0 2,590

808 MATERIAL STORAGE 100 1,400 0 0 1,778

815 STUDENT RESTROOM (MALE) 35 490 0 0 622

811 OUTSIDE STORAGE 50 700 0 0 889

34 1 PK - 03 PRIMARY CLASSROOM (K-3) 882 29,988 18 612 38,084

808 MATERIAL STORAGE 100 200 0 0 254

808 MATERIAL STORAGE 100 3,400 0 0 4,318

813 STUDENT STORAGE 40 1,360 0 0 1,727

811 OUTSIDE STORAGE 50 1,700 0 0 2,159

1 14 PK - 05 ELEMENTARY COVERED PLAY AREA 3,492 3,492 97 0 4,434

1 13 PK - 05 ELEMENTARY P E STORAGE 315 315 1 0 400

7 40 PK - 12 RESOURCE ROOM 290 2,030 10 0 2,578

2 50 PK - 05 ART - ELEMENTARY 1,000 2,000 22 0 2,540

808 MATERIAL STORAGE 100 700 0 0 889

3 10 PK - 03 PRIMARY SKILLS LAB (K-3) 882 2,646 18 0 3,360

816 STUDENT RESTROOM (FEMALE) 35 490 0 0 622

808 MATERIAL STORAGE 100 300 0 0 381

814 STUDENT RESTROOM (BOTH SEXES) 60 180 0 0 228

813 STUDENT STORAGE 40 120 0 0 152

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

ELEMENTARY (KG - 06)

970

Gross Sq. Feet:

Utilization:

137,285

1.000

Level:

Page 38: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:20 of 234 Report Date: 6/15/2015 11:49:17 AM

1 313 PK - VE CAREERS ROOM 288 288 48 0 365

1 311 PK - VE STUDENT ACTIVITIES 480 480 48 0 609

1 315 PK - VE TEACHER PLANNING OFFICE 1,940 1,940 97 0 2,463

3 314 PK - VE ITINERANT OFFICE 125 375 0 0 476

1 309 PK - VE VAULT/STUDENT RECORDS 288 288 48 0 365

1 305 PK - VE PRODUCTION WORKROOM 384 384 48 0 487

1 304 PK - VE RECEPTION AREA 816 816 48 0 1,036

1 307 PK - VE CLINIC 288 288 48 0 365

1 306 PK - VE CONFERENCE ROOM 672 672 48 0 853

1 349 PK - VE KITCHEN CHAIR STORAGE 192 192 48 0 243

1 341 PK - VE KITCHEN & SERVING AREA 4,268 4,268 97 0 5,420

1 340 PK - VE DINING AREA 3,880 3,880 97 0 4,927

1 330 PK - VE CUSTODIAL RECEIVING 1,455 1,455 97 0 1,847

1 316 PK - VE TEACHER LOUNGE/DINING 388 388 97 0 492

1 334 PK - VE CUSTODIAL EQUIPMENT STORAGE 500 500 0 0 635

1 333 PK - VE FLAMMABLE STORAGE 155 155 0 0 196

816 STUDENT RESTROOM (FEMALE) 35 70 0 0 88

815 STUDENT RESTROOM (MALE) 35 70 0 0 88

3 65 PK - 12 E S E RESOURCE 380 1,140 4 0 1,447

817 STUDENT RESTROOM & BATH 110 220 0 0 279

813 STUDENT STORAGE 40 80 0 0 101

816 STUDENT RESTROOM (FEMALE) 35 70 0 0 88

2 303 PK - VE SECRETARIAL SPACE 158 316 0 0 401

808 MATERIAL STORAGE 100 200 0 0 254

2 62 PK - 12 E S E FULL-TIME 950 1,900 10 20 2,413

1 300 PK - VE PRINCIPAL/DIRECTOR OFFICE 250 250 0 0 317

808 MATERIAL STORAGE 100 200 0 0 254

1 302 PK - VE BOOKKEEPING OFFICE 125 125 0 0 158

4 301 PK - VE ASSISTANT PRINCIPAL/OTHER OFFICE 175 700 0 0 889

2 70 PK - 12 E S E ITINERANT 200 400 4 0 508

813 STUDENT STORAGE 40 120 0 0 152

808 MATERIAL STORAGE 100 300 0 0 381

808 MATERIAL STORAGE 100 200 0 0 254

2 66 PK - 12 E S E SUPPLEMENTARY INSTRUCTION 100 200 2 0 254

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 39: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:21 of 234 Report Date: 6/15/2015 11:49:17 AM

1 384 PK - VE PERIODICAL STORAGE 194 194 97 0 246

1 385 PK - VE CLOSED CIRCUIT TV LAB 679 679 97 0 862

14 816 06 - 12 STUDENT RESTROOM (FEMALE) 96 1,344 48 0 1,706

1 383 PK - VE AUDIO VISUAL STORAGE 582 582 97 0 739

1 391 PK - VE MEDIA MAINTENANCE/REPAIR 96 96 48 0 121

14 815 06 - 12 STUDENT RESTROOM (MALE) 96 1,344 48 0 1,706

1 386 PK - VE CLOSED CIRCUIT STORAGE 485 485 97 0 615

1 390 PK - VE MEDIA GROUP PROJECTS/INSTRUCTION 485 485 97 0 615

1 363 PK - VE STAGE 990 990 1 0 1,257

1 364 PK - VE STAGE STORAGE 485 485 97 0 615

1 382 PK - VE PROFESSIONAL LIBRARY 388 388 97 0 492

1 361 PK - VE MULTIPURPOSE ROOM (DINING) 3,007 3,007 97 0 3,818

1 380 PK - VE LIBRARY (READING ROOM/STACKS) 3,589 3,589 97 0 4,558

1 381 PK - VE MEDIA TECHNICAL PROCESSING 388 388 97 0 492

1 367 PK - VE CONTROL BOOTH/PROJECTION ROOM 100 100 1 0 127

1 368 PK - VE TEXTBOOK STORAGE 336 336 48 0 426

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 40: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:22 of 234 Report Date: 6/15/2015 11:49:17 AM

975

Total Stations: 975 Acres Required: 12

Total Capacity:

806 REFERENCE 100 200 0 0 254

2 55 PK - 05 MUSIC - ELEMENTARY 1,000 2,000 22 0 2,540

831 MUSIC PRACTICE ROOM 70 140 0 0 177

808 MATERIAL STORAGE 100 200 0 0 254

2 50 PK - 05 ART - ELEMENTARY 1,000 2,000 22 0 2,540

808 MATERIAL STORAGE 100 700 0 0 889

812 PROJECT STORAGE 150 300 0 0 381

808 MATERIAL STORAGE 100 200 0 0 254

1 60 PK - PK E S E PRE-K 475 475 5 5 603

813 STUDENT STORAGE 40 40 0 0 50

808 MATERIAL STORAGE 100 100 0 0 127

817 STUDENT RESTROOM & BATH 110 110 0 0 139

814 STUDENT RESTROOM (BOTH SEXES) 60 2,040 0 0 2,590

813 STUDENT STORAGE 40 1,360 0 0 1,727

808 MATERIAL STORAGE 100 1,400 0 0 1,778

14 2 04 - 08 INTERMEDIATE/MIDDLE CLASSROOM (4-8) 858 12,012 22 308 15,255

34 1 PK - 03 PRIMARY CLASSROOM (K-3) 882 29,988 18 612 38,084

7 40 PK - 12 RESOURCE ROOM 290 2,030 10 0 2,578

811 OUTSIDE STORAGE 50 1,700 0 0 2,159

808 MATERIAL STORAGE 100 3,400 0 0 4,318

811 OUTSIDE STORAGE 50 700 0 0 889

814 STUDENT RESTROOM (BOTH SEXES) 60 180 0 0 228

813 STUDENT STORAGE 40 120 0 0 152

1 14 PK - 05 ELEMENTARY COVERED PLAY AREA 3,492 3,492 97 0 4,434

1 13 PK - 05 ELEMENTARY P E STORAGE 315 315 1 0 400

816 STUDENT RESTROOM (FEMALE) 35 490 0 0 622

815 STUDENT RESTROOM (MALE) 35 490 0 0 622

808 MATERIAL STORAGE 100 300 0 0 381

3 10 PK - 03 PRIMARY SKILLS LAB (K-3) 882 2,646 18 0 3,360

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

ELEMENTARY (PK - 06)

975

Gross Sq. Feet:

Utilization:

140,109

1.000

Level:

Page 41: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:23 of 234 Report Date: 6/15/2015 11:49:17 AM

1 307 PK - VE CLINIC 288 288 48 0 365

1 306 PK - VE CONFERENCE ROOM 672 672 48 0 853

1 311 PK - VE STUDENT ACTIVITIES 480 480 48 0 609

1 309 PK - VE VAULT/STUDENT RECORDS 288 288 48 0 365

1 305 PK - VE PRODUCTION WORKROOM 384 384 48 0 487

1 302 PK - VE BOOKKEEPING OFFICE 125 125 0 0 158

14 301 PK - VE ASSISTANT PRINCIPAL/OTHER OFFICE 175 2,450 0 0 3,111

1 304 PK - VE RECEPTION AREA 816 816 48 0 1,036

2 303 PK - VE SECRETARIAL SPACE 158 316 0 0 401

1 334 PK - VE CUSTODIAL EQUIPMENT STORAGE 500 500 0 0 635

1 333 PK - VE FLAMMABLE STORAGE 155 155 0 0 196

1 330 PK - VE CUSTODIAL RECEIVING 1,455 1,455 97 0 1,847

3 314 PK - VE ITINERANT OFFICE 125 375 0 0 476

1 313 PK - VE CAREERS ROOM 288 288 48 0 365

1 316 PK - VE TEACHER LOUNGE/DINING 388 388 97 0 492

1 315 PK - VE TEACHER PLANNING OFFICE 1,940 1,940 97 0 2,463

2 62 PK - 12 E S E FULL-TIME 950 1,900 10 20 2,413

816 STUDENT RESTROOM (FEMALE) 35 70 0 0 88

813 STUDENT STORAGE 40 80 0 0 101

808 MATERIAL STORAGE 100 200 0 0 254

815 STUDENT RESTROOM (MALE) 35 70 0 0 88

2 61 PK - 12 E S E PART-TIME 975 1,950 15 30 2,476

808 MATERIAL STORAGE 100 200 0 0 254

813 STUDENT STORAGE 40 80 0 0 101

808 MATERIAL STORAGE 100 200 0 0 254

2 66 PK - 12 E S E SUPPLEMENTARY INSTRUCTION 100 200 2 0 254

813 STUDENT STORAGE 40 120 0 0 152

2 70 PK - 12 E S E ITINERANT 200 400 4 0 508

808 MATERIAL STORAGE 100 200 0 0 254

808 MATERIAL STORAGE 100 300 0 0 381

816 STUDENT RESTROOM (FEMALE) 35 70 0 0 88

815 STUDENT RESTROOM (MALE) 35 70 0 0 88

3 65 PK - 12 E S E RESOURCE 380 1,140 4 0 1,447

817 STUDENT RESTROOM & BATH 110 220 0 0 279

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 42: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:24 of 234 Report Date: 6/15/2015 11:49:17 AM

1 383 PK - VE AUDIO VISUAL STORAGE 582 582 97 0 739

1 384 PK - VE PERIODICAL STORAGE 194 194 97 0 246

1 381 PK - VE MEDIA TECHNICAL PROCESSING 388 388 97 0 492

1 382 PK - VE PROFESSIONAL LIBRARY 388 388 97 0 492

1 385 PK - VE CLOSED CIRCUIT TV LAB 679 679 97 0 862

1 391 PK - VE MEDIA MAINTENANCE/REPAIR 96 96 48 0 121

14 815 06 - 12 STUDENT RESTROOM (MALE) 96 1,344 48 0 1,706

1 386 PK - VE CLOSED CIRCUIT STORAGE 485 485 97 0 615

1 390 PK - VE MEDIA GROUP PROJECTS/INSTRUCTION 485 485 97 0 615

14 816 06 - 12 STUDENT RESTROOM (FEMALE) 96 1,344 48 0 1,706

1 341 PK - VE KITCHEN & SERVING AREA 4,268 4,268 97 0 5,420

1 349 PK - VE KITCHEN CHAIR STORAGE 192 192 48 0 243

1 380 PK - VE LIBRARY (READING ROOM/STACKS) 3,589 3,589 97 0 4,558

1 340 PK - VE DINING AREA 3,880 3,880 97 0 4,927

1 361 PK - VE MULTIPURPOSE ROOM (DINING) 3,007 3,007 97 0 3,818

1 367 PK - VE CONTROL BOOTH/PROJECTION ROOM 100 100 1 0 127

1 368 PK - VE TEXTBOOK STORAGE 336 336 48 0 426

1 363 PK - VE STAGE 990 990 1 0 1,257

1 364 PK - VE STAGE STORAGE 485 485 97 0 615

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 43: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:25 of 234 Report Date: 6/15/2015 11:49:17 AM

842

Total Stations: 842 Acres Required: 11

Total Capacity:

813 STUDENT STORAGE 40 80 0 0 101

808 MATERIAL STORAGE 100 200 0 0 254

816 STUDENT RESTROOM (FEMALE) 35 70 0 0 88

815 STUDENT RESTROOM (MALE) 35 70 0 0 88

808 MATERIAL STORAGE 100 200 0 0 254

806 REFERENCE 100 200 0 0 254

2 61 PK - 12 E S E PART-TIME 975 1,950 15 30 2,476

831 MUSIC PRACTICE ROOM 70 140 0 0 177

2 62 PK - 12 E S E FULL-TIME 950 1,900 10 20 2,413

813 STUDENT STORAGE 40 80 0 0 101

808 MATERIAL STORAGE 100 200 0 0 254

815 STUDENT RESTROOM (MALE) 35 70 0 0 88

814 STUDENT RESTROOM (BOTH SEXES) 60 2,640 0 0 3,352

813 STUDENT STORAGE 40 1,760 0 0 2,235

808 MATERIAL STORAGE 100 300 0 0 381

3 10 PK - 03 PRIMARY SKILLS LAB (K-3) 882 2,646 18 0 3,360

44 1 PK - 03 PRIMARY CLASSROOM (K-3) 882 38,808 18 792 49,286

2 55 PK - 05 MUSIC - ELEMENTARY 1,000 2,000 22 0 2,540

811 OUTSIDE STORAGE 50 2,200 0 0 2,794

808 MATERIAL STORAGE 100 4,400 0 0 5,588

813 STUDENT STORAGE 40 120 0 0 152

2 50 PK - 05 ART - ELEMENTARY 1,000 2,000 22 0 2,540

808 MATERIAL STORAGE 100 600 0 0 762

812 PROJECT STORAGE 150 300 0 0 381

808 MATERIAL STORAGE 100 200 0 0 254

1 13 PK - 05 ELEMENTARY P E STORAGE 315 315 1 0 400

814 STUDENT RESTROOM (BOTH SEXES) 60 180 0 0 228

6 40 PK - 12 RESOURCE ROOM 290 1,740 10 0 2,209

1 14 PK - 05 ELEMENTARY COVERED PLAY AREA 3,024 3,024 84 0 3,840

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

ELEMENTARY (KG - 03)

842

Gross Sq. Feet:

Utilization:

123,450

1.000

Level:

Page 44: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:26 of 234 Report Date: 6/15/2015 11:49:17 AM

1 333 PK - VE FLAMMABLE STORAGE 155 155 0 0 196

1 330 PK - VE CUSTODIAL RECEIVING 1,260 1,260 84 0 1,600

1 340 PK - VE DINING AREA 3,360 3,360 84 0 4,267

1 334 PK - VE CUSTODIAL EQUIPMENT STORAGE 500 500 0 0 635

1 316 PK - VE TEACHER LOUNGE/DINING 336 336 84 0 426

1 313 PK - VE CAREERS ROOM 252 252 42 0 320

1 311 PK - VE STUDENT ACTIVITIES 420 420 42 0 533

1 315 PK - VE TEACHER PLANNING OFFICE 1,680 1,680 84 0 2,133

2 314 PK - VE ITINERANT OFFICE 125 250 0 0 317

1 368 PK - VE TEXTBOOK STORAGE 294 294 42 0 373

1 367 PK - VE CONTROL BOOTH/PROJECTION ROOM 100 100 1 0 127

1 364 PK - VE STAGE STORAGE 420 420 84 0 533

1 349 PK - VE KITCHEN CHAIR STORAGE 168 168 42 0 213

1 341 PK - VE KITCHEN & SERVING AREA 3,696 3,696 84 0 4,693

1 363 PK - VE STAGE 990 990 1 0 1,257

1 361 PK - VE MULTIPURPOSE ROOM (DINING) 2,604 2,604 84 0 3,307

2 66 PK - 12 E S E SUPPLEMENTARY INSTRUCTION 100 200 2 0 254

813 STUDENT STORAGE 40 120 0 0 152

2 70 PK - 12 E S E ITINERANT 200 400 4 0 508

808 MATERIAL STORAGE 100 200 0 0 254

808 MATERIAL STORAGE 100 300 0 0 381

816 STUDENT RESTROOM (FEMALE) 35 70 0 0 88

1 309 PK - VE VAULT/STUDENT RECORDS 252 252 42 0 320

3 65 PK - 12 E S E RESOURCE 380 1,140 4 0 1,447

817 STUDENT RESTROOM & BATH 110 220 0 0 279

1 305 PK - VE PRODUCTION WORKROOM 336 336 42 0 426

1 304 PK - VE RECEPTION AREA 714 714 42 0 906

1 307 PK - VE CLINIC 252 252 42 0 320

1 306 PK - VE CONFERENCE ROOM 588 588 42 0 746

2 303 PK - VE SECRETARIAL SPACE 158 316 0 0 401

1 300 PK - VE PRINCIPAL/DIRECTOR OFFICE 250 250 0 0 317

808 MATERIAL STORAGE 100 200 0 0 254

1 302 PK - VE BOOKKEEPING OFFICE 125 125 0 0 158

4 301 PK - VE ASSISTANT PRINCIPAL/OTHER OFFICE 175 700 0 0 889

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 45: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:27 of 234 Report Date: 6/15/2015 11:49:17 AM

1 385 PK - VE CLOSED CIRCUIT TV LAB 588 588 84 0 746

1 384 PK - VE PERIODICAL STORAGE 168 168 84 0 213

1 390 PK - VE MEDIA GROUP PROJECTS/INSTRUCTION 420 420 84 0 533

1 386 PK - VE CLOSED CIRCUIT STORAGE 420 420 84 0 533

1 391 PK - VE MEDIA MAINTENANCE/REPAIR 84 84 42 0 106

1 380 PK - VE LIBRARY (READING ROOM/STACKS) 3,108 3,108 84 0 3,947

1 383 PK - VE AUDIO VISUAL STORAGE 504 504 84 0 640

1 382 PK - VE PROFESSIONAL LIBRARY 336 336 84 0 426

1 381 PK - VE MEDIA TECHNICAL PROCESSING 336 336 84 0 426

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 46: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:28 of 234 Report Date: 6/15/2015 11:49:17 AM

908

Total Stations: 908 Acres Required: 12

Total Capacity:

808 MATERIAL STORAGE 100 200 0 0 254

2 62 PK - 12 E S E FULL-TIME 950 1,900 10 20 2,413

815 STUDENT RESTROOM (MALE) 35 70 0 0 88

813 STUDENT STORAGE 40 80 0 0 101

813 STUDENT STORAGE 40 80 0 0 101

808 MATERIAL STORAGE 100 200 0 0 254

816 STUDENT RESTROOM (FEMALE) 35 70 0 0 88

815 STUDENT RESTROOM (MALE) 35 70 0 0 88

816 STUDENT RESTROOM (FEMALE) 35 70 0 0 88

3 65 PK - 12 E S E RESOURCE 380 1,140 4 0 1,447

817 STUDENT RESTROOM & BATH 110 220 0 0 279

808 MATERIAL STORAGE 100 300 0 0 381

816 STUDENT RESTROOM (FEMALE) 35 1,365 0 0 1,733

815 STUDENT RESTROOM (MALE) 35 1,365 0 0 1,733

1 14 PK - 05 ELEMENTARY COVERED PLAY AREA 3,240 3,240 90 0 4,114

1 13 PK - 05 ELEMENTARY P E STORAGE 315 315 1 0 400

39 2 04 - 08 INTERMEDIATE/MIDDLE CLASSROOM (4-8) 858 33,462 22 858 42,496

2 61 PK - 12 E S E PART-TIME 975 1,950 15 30 2,476

811 OUTSIDE STORAGE 50 1,950 0 0 2,476

808 MATERIAL STORAGE 100 3,900 0 0 4,953

6 40 PK - 12 RESOURCE ROOM 290 1,740 10 0 2,209

806 REFERENCE 100 200 0 0 254

2 55 PK - 05 MUSIC - ELEMENTARY 1,000 2,000 22 0 2,540

831 MUSIC PRACTICE ROOM 70 140 0 0 177

808 MATERIAL STORAGE 100 200 0 0 254

2 50 PK - 05 ART - ELEMENTARY 1,000 2,000 22 0 2,540

808 MATERIAL STORAGE 100 600 0 0 762

812 PROJECT STORAGE 150 300 0 0 381

808 MATERIAL STORAGE 100 200 0 0 254

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

ELEMENTARY (03 - 06)

908

Gross Sq. Feet:

Utilization:

115,943

1.000

Level:

Page 47: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:29 of 234 Report Date: 6/15/2015 11:49:17 AM

1 349 PK - VE KITCHEN CHAIR STORAGE 180 180 45 0 228

1 341 PK - VE KITCHEN & SERVING AREA 3,960 3,960 90 0 5,029

1 363 PK - VE STAGE 990 990 1 0 1,257

1 361 PK - VE MULTIPURPOSE ROOM (DINING) 2,790 2,790 90 0 3,543

1 340 PK - VE DINING AREA 3,600 3,600 90 0 4,572

1 330 PK - VE CUSTODIAL RECEIVING 1,350 1,350 90 0 1,714

1 316 PK - VE TEACHER LOUNGE/DINING 360 360 90 0 457

1 334 PK - VE CUSTODIAL EQUIPMENT STORAGE 500 500 0 0 635

1 333 PK - VE FLAMMABLE STORAGE 155 155 0 0 196

1 383 PK - VE AUDIO VISUAL STORAGE 540 540 90 0 685

1 382 PK - VE PROFESSIONAL LIBRARY 360 360 90 0 457

1 381 PK - VE MEDIA TECHNICAL PROCESSING 360 360 90 0 457

1 367 PK - VE CONTROL BOOTH/PROJECTION ROOM 100 100 1 0 127

1 364 PK - VE STAGE STORAGE 450 450 90 0 571

1 380 PK - VE LIBRARY (READING ROOM/STACKS) 3,330 3,330 90 0 4,229

1 368 PK - VE TEXTBOOK STORAGE 315 315 45 0 400

1 300 PK - VE PRINCIPAL/DIRECTOR OFFICE 250 250 0 0 317

808 MATERIAL STORAGE 100 200 0 0 254

1 302 PK - VE BOOKKEEPING OFFICE 125 125 0 0 158

4 301 PK - VE ASSISTANT PRINCIPAL/OTHER OFFICE 175 700 0 0 889

2 70 PK - 12 E S E ITINERANT 200 400 4 0 508

813 STUDENT STORAGE 40 120 0 0 152

1 315 PK - VE TEACHER PLANNING OFFICE 1,800 1,800 90 0 2,286

808 MATERIAL STORAGE 100 200 0 0 254

2 66 PK - 12 E S E SUPPLEMENTARY INSTRUCTION 50 100 2 0 127

1 311 PK - VE STUDENT ACTIVITIES 450 450 45 0 571

1 309 PK - VE VAULT/STUDENT RECORDS 270 270 45 0 342

3 314 PK - VE ITINERANT OFFICE 125 375 0 0 476

1 313 PK - VE CAREERS ROOM 270 270 45 0 342

1 307 PK - VE CLINIC 270 270 45 0 342

1 304 PK - VE RECEPTION AREA 765 765 45 0 971

2 303 PK - VE SECRETARIAL SPACE 158 316 0 0 401

1 306 PK - VE CONFERENCE ROOM 630 630 45 0 800

1 305 PK - VE PRODUCTION WORKROOM 360 360 45 0 457

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 48: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:30 of 234 Report Date: 6/15/2015 11:49:17 AM

3 10 PK - 03 PRIMARY SKILLS LAB (K-3) 882 2,646 18 0 3,360

1 391 PK - VE MEDIA MAINTENANCE/REPAIR 90 90 45 0 114

813 STUDENT STORAGE 40 120 0 0 152

808 MATERIAL STORAGE 100 300 0 0 381

814 STUDENT RESTROOM (BOTH SEXES) 60 180 0 0 228

1 384 PK - VE PERIODICAL STORAGE 180 180 90 0 228

1 390 PK - VE MEDIA GROUP PROJECTS/INSTRUCTION 450 450 90 0 571

1 386 PK - VE CLOSED CIRCUIT STORAGE 450 450 90 0 571

1 385 PK - VE CLOSED CIRCUIT TV LAB 630 630 90 0 800

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 49: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:31 of 234 Report Date: 6/15/2015 11:49:17 AM

115

Total Stations: 115 Acres Required: 7

Total Capacity:

812 PROJECT STORAGE 150 150 0 0 201

808 MATERIAL STORAGE 100 100 0 0 134

806 REFERENCE 100 100 0 0 134

1 55 PK - 05 MUSIC - ELEMENTARY 1,000 1,000 22 0 1,340

1 40 PK - 12 RESOURCE ROOM 290 290 10 0 388

1 14 PK - 05 ELEMENTARY COVERED PLAY AREA 396 396 11 0 530

1 50 PK - 05 ART - ELEMENTARY 1,000 1,000 22 0 1,340

808 MATERIAL STORAGE 100 100 0 0 134

808 MATERIAL STORAGE 100 100 0 0 134

1 61 PK - 12 E S E PART-TIME 975 975 15 15 1,306

831 MUSIC PRACTICE ROOM 70 70 0 0 93

808 MATERIAL STORAGE 100 100 0 0 134

814 STUDENT RESTROOM (BOTH SEXES) 60 60 0 0 80

813 STUDENT STORAGE 40 40 0 0 53

808 MATERIAL STORAGE 100 100 0 0 134

1 2 04 - 08 INTERMEDIATE/MIDDLE CLASSROOM (4-8) 858 858 22 22 1,149

1 1 PK - 03 PRIMARY CLASSROOM (K-3) 882 882 18 18 1,181

1 13 PK - 05 ELEMENTARY P E STORAGE 315 315 1 0 422

811 OUTSIDE STORAGE 50 50 0 0 67

808 MATERIAL STORAGE 100 100 0 0 134

811 OUTSIDE STORAGE 50 50 0 0 67

808 MATERIAL STORAGE 100 100 0 0 134

1 10 PK - 03 PRIMARY SKILLS LAB (K-3) 882 882 18 0 1,181

814 STUDENT RESTROOM (BOTH SEXES) 60 60 0 0 80

813 STUDENT STORAGE 40 40 0 0 53

816 STUDENT RESTROOM (FEMALE) 35 35 0 0 46

815 STUDENT RESTROOM (MALE) 35 35 0 0 46

808 MATERIAL STORAGE 100 200 0 0 268

2 3 09 - 12 SENIOR HIGH CLASSROOM (9-12) 800 1,600 25 50 2,144

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

ALTERNATIVE EDUCATION (KG - 12)

115

Gross Sq. Feet:

Utilization:

26,074

1.000

Level:

Page 50: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:32 of 234 Report Date: 6/15/2015 11:49:17 AM

4 301 PK - VE ASSISTANT PRINCIPAL/OTHER OFFICE 175 700 0 0 938

1 300 PK - VE PRINCIPAL/DIRECTOR OFFICE 250 250 0 0 335

1 303 PK - VE SECRETARIAL SPACE 158 158 0 0 211

1 302 PK - VE BOOKKEEPING OFFICE 125 125 0 0 167

853 VOCATIONAL TESTING 250 250 0 0 335

808 MATERIAL STORAGE 100 100 0 0 134

802 INSTRUCTIONAL CONFERENCE ROOM 225 225 0 0 301

846 RECEPTION (VOC ED INSTRUCTION) 90 90 0 0 120

840 VOCATIONAL RELATED CLASSROOM 680 680 20 0 911

1 310 PK - VE SCHOOL STORE 10 10 5 0 13

1 309 PK - VE VAULT/STUDENT RECORDS 30 30 5 0 40

1 308 PK - VE GENERAL SCHOOL STORAGE 50 50 5 0 67

1 305 PK - VE PRODUCTION WORKROOM 40 40 5 0 53

1 304 PK - VE RECEPTION AREA 85 85 5 0 113

1 307 PK - VE CLINIC 30 30 5 0 40

1 306 PK - VE CONFERENCE ROOM 70 70 5 0 93

813 STUDENT STORAGE 40 40 0 0 53

808 MATERIAL STORAGE 100 100 0 0 134

816 STUDENT RESTROOM (FEMALE) 35 35 0 0 46

815 STUDENT RESTROOM (MALE) 35 35 0 0 46

1 62 PK - 12 E S E FULL-TIME 950 950 10 10 1,273

813 STUDENT STORAGE 40 40 0 0 53

1 271 09 - VE VPI LAB 705 705 15 0 944

816 STUDENT RESTROOM (FEMALE) 35 35 0 0 46

815 STUDENT RESTROOM (MALE) 35 35 0 0 46

1 270 09 - VE WORK EVALUATION LAB 1,110 1,110 15 0 1,487

808 MATERIAL STORAGE 100 100 0 0 134

853 VOCATIONAL TESTING 250 250 0 0 335

810 MATERIAL STORAGE (LARGE) 395 395 0 0 529

1 66 PK - 12 E S E SUPPLEMENTARY INSTRUCTION 100 100 2 0 134

1 65 PK - 12 E S E RESOURCE 380 380 4 0 509

817 STUDENT RESTROOM & BATH 110 110 0 0 147

813 STUDENT STORAGE 40 40 0 0 53

808 MATERIAL STORAGE 100 100 0 0 134

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 51: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:33 of 234 Report Date: 6/15/2015 11:49:17 AM

1 340 PK - VE DINING AREA 440 440 11 0 589

1 334 PK - VE CUSTODIAL EQUIPMENT STORAGE 500 500 0 0 670

1 333 PK - VE FLAMMABLE STORAGE 155 155 0 0 207

1 815 06 - 12 STUDENT RESTROOM (MALE) 10 10 5 0 13

1 349 PK - VE KITCHEN CHAIR STORAGE 20 20 5 0 26

1 341 PK - VE KITCHEN & SERVING AREA 484 484 11 0 648

1 816 06 - 12 STUDENT RESTROOM (FEMALE) 10 10 5 0 13

1 312 PK - VE COMPUTER AREA 15 15 5 0 20

1 311 PK - VE STUDENT ACTIVITIES 50 50 5 0 67

1 330 PK - VE CUSTODIAL RECEIVING 165 165 11 0 221

1 316 PK - VE TEACHER LOUNGE/DINING 44 44 11 0 58

1 315 PK - VE TEACHER PLANNING OFFICE 220 220 11 0 294

1 314 PK - VE ITINERANT OFFICE 125 125 0 0 167

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 52: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:34 of 234 Report Date: 6/15/2015 11:49:17 AM

1,137

Total Stations: 1,264 Acres Required: 15

Total Capacity:

815 STUDENT RESTROOM (MALE) 35 105 0 0 138

813 STUDENT STORAGE 40 120 0 0 158

3 62 PK - 12 E S E FULL-TIME 950 2,850 10 30 3,762

816 STUDENT RESTROOM (FEMALE) 35 105 0 0 138

812 PROJECT STORAGE 150 300 0 0 396

808 MATERIAL STORAGE 100 200 0 0 264

808 MATERIAL STORAGE 100 300 0 0 396

3 61 PK - 12 E S E PART-TIME 975 2,925 15 45 3,861

808 MATERIAL STORAGE 100 300 0 0 396

815 STUDENT RESTROOM (MALE) 35 105 0 0 138

813 STUDENT STORAGE 40 120 0 0 158

816 STUDENT RESTROOM (FEMALE) 35 105 0 0 138

816 STUDENT RESTROOM (FEMALE) 35 875 0 0 1,155

815 STUDENT RESTROOM (MALE) 35 875 0 0 1,155

808 MATERIAL STORAGE 100 400 0 0 528

4 11 04 - 08 INTERMEDIATE/MIDDLE SKILLS LAB (4-8) 858 3,432 22 88 4,530

25 2 04 - 08 INTERMEDIATE/MIDDLE CLASSROOM (4-8) 858 21,450 22 550 28,314

805 KILN 60 120 0 0 158

811 OUTSIDE STORAGE 50 1,250 0 0 1,650

808 MATERIAL STORAGE 100 2,500 0 0 3,300

815 STUDENT RESTROOM (MALE) 35 140 0 0 184

808 MATERIAL STORAGE 100 500 0 0 660

5 40 PK - 12 RESOURCE ROOM 290 1,450 10 0 1,914

803 INSTRUCTIONAL DARKROOM 100 200 0 0 264

2 51 04 - 08 ART - MIDDLE 1,260 2,520 30 60 3,326

9 21 04 - 08 INTERMEDIATE/MIDDLE SCIENCE LAB (4-8) 1,122 10,098 22 198 13,329

816 STUDENT RESTROOM (FEMALE) 35 140 0 0 184

812 PROJECT STORAGE 150 1,350 0 0 1,782

808 MATERIAL STORAGE 100 900 0 0 1,188

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

MIDDLE (07 - 08)

1,264

Gross Sq. Feet:

Utilization:

179,109

1.000

Level:

Page 53: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:35 of 234 Report Date: 6/15/2015 11:49:17 AM

831 MUSIC PRACTICE ROOM 70 70 0 0 92

830 MUSIC ENSEMBLE 300 300 0 0 396

834 UNIFORM STORAGE 300 300 0 0 396

832 INSTRUMENT STORAGE 600 600 0 0 792

808 MATERIAL STORAGE 100 100 0 0 132

837 MUSIC EQUIPMENT STORAGE 400 400 0 0 528

836 SHEET MUSIC STORAGE 150 150 0 0 198

806 REFERENCE 100 100 0 0 132

1 76 06 - 12 BAND CLASS (MIDDLE-SR HIGH) 2,000 2,000 45 45 2,640

830 MUSIC ENSEMBLE 300 300 0 0 396

808 MATERIAL STORAGE 100 100 0 0 132

806 REFERENCE 100 100 0 0 132

836 SHEET MUSIC STORAGE 150 150 0 0 198

835 MUSIC STUDIO 180 180 0 0 237

1 77 06 - 12 ORCHESTRA CLASS (MIDDLE-SR HIGH) 1,425 1,425 25 25 1,881

837 MUSIC EQUIPMENT STORAGE 400 400 0 0 528

3 65 PK - 12 E S E RESOURCE 380 1,140 4 0 1,504

816 STUDENT RESTROOM (FEMALE) 35 35 0 0 46

813 STUDENT STORAGE 40 120 0 0 158

808 MATERIAL STORAGE 100 300 0 0 396

815 STUDENT RESTROOM (MALE) 35 35 0 0 46

817 STUDENT RESTROOM & BATH 110 330 0 0 435

833 ROBE STORAGE 150 150 0 0 198

808 MATERIAL STORAGE 100 100 0 0 132

1 63 PK - 12 E S E VOCATIONAL 1,140 1,140 12 12 1,504

808 MATERIAL STORAGE 100 100 0 0 132

806 REFERENCE 100 100 0 0 132

831 MUSIC PRACTICE ROOM 70 70 0 0 92

830 MUSIC ENSEMBLE 300 300 0 0 396

1 75 06 - 12 VOCAL MUSIC CLASS (MIDDLE-SR HIGH) 1,425 1,425 25 25 1,881

808 MATERIAL STORAGE 100 300 0 0 396

3 66 PK - 12 E S E SUPPLEMENTARY INSTRUCTION 100 300 2 0 396

808 MATERIAL STORAGE 100 100 0 0 132

1 70 PK - 12 E S E ITINERANT 200 200 4 0 264

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 54: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:36 of 234 Report Date: 6/15/2015 11:49:17 AM

808 MATERIAL STORAGE 100 100 0 0 132

1 230 06 - 09 HOME ECONOMICS EXPLORATION LAB 1,540 1,540 22 22 2,032

842 KITCHEN (HOME ECONOMICS) 125 125 0 0 165

812 PROJECT STORAGE 150 150 0 0 198

808 MATERIAL STORAGE 100 100 0 0 132

1 119 06 - 12 P E GYMNASTICS & DANCE 1,050 1,050 1 0 1,386

1 117 06 - 12 P E WEIGHT ROOM 1,000 1,000 1 0 1,320

1 210 06 - 09 BUSINESS EXPLORATION LAB 1,210 1,210 22 22 1,597

1 120 06 - 12 GYMNASIUM STORAGE 168 168 56 0 221

852 VOCATIONAL TECHNOLOGY RESOURCE CENTER 800 800 0 0 1,056

851 VOCATIONAL TOOL STORAGE (LARGE) 310 310 0 0 409

849 VOCATIONAL PROJECT STORAGE 310 310 0 0 409

852 VOCATIONAL TECHNOLOGY RESOURCE CENTER 800 800 0 0 1,056

843 LAUNDRY (HOME ECONOMICS) 50 50 0 0 66

808 MATERIAL STORAGE 100 100 0 0 132

1 240 06 - 09 TECHNOLOGY/INDUSTRY EXPLORATION LAB 2,090 2,090 22 22 2,758

1 91 06 - 12 P E DRESSING ROOM (FEMALE) 672 672 56 0 887

1 90 06 - 12 P E DRESSING ROOM (MALE) 672 672 56 0 887

1 93 06 - 12 P E LOCKER ROOM (FEMALE) 112 112 56 0 147

1 92 06 - 12 P E LOCKER ROOM (MALE) 112 112 56 0 147

837 MUSIC EQUIPMENT STORAGE 400 400 0 0 528

831 MUSIC PRACTICE ROOM 70 70 0 0 92

1 115 06 - 12 P E FIRST AID 112 112 56 0 147

836 SHEET MUSIC STORAGE 150 150 0 0 198

832 INSTRUMENT STORAGE 600 600 0 0 792

1 110 06 - 12 P E MULTIPURPOSE ROOM (MIDDLE-SR HIGH) 1,050 1,050 1 0 1,386

1 99 06 - 12 P E TEACHERS SHOWER (MALE) 22 22 1 0 29

1 113 06 - 12 GYMNASIUM SEATING 3,616 3,616 113 0 4,773

1 111 06 - 09 JR HIGH GYMNASIUM 5,800 5,800 120 120 7,656

1 98 06 - 12 P E STORAGE (MIDDLE-SR HIGH) 504 504 56 0 665

1 95 06 - 12 P E SHOWER (FEMALE) 112 112 56 0 147

1 94 06 - 12 P E SHOWER (MALE) 112 112 56 0 147

1 97 06 - 12 P E DRYING AREA (FEMALE) 112 112 56 0 147

1 96 06 - 12 P E DRYING AREA (MALE) 112 112 56 0 147

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 55: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:37 of 234 Report Date: 6/15/2015 11:49:17 AM

1 362 PK - VE MULTIPURPOSE ROOM CHAIR STORAGE 226 226 113 0 298

1 361 PK - VE MULTIPURPOSE ROOM (DINING) 3,503 3,503 113 0 4,623

1 364 PK - VE STAGE STORAGE 565 565 113 0 745

1 363 PK - VE STAGE 990 990 1 0 1,306

1 349 PK - VE KITCHEN CHAIR STORAGE 224 224 56 0 295

1 334 PK - VE CUSTODIAL EQUIPMENT STORAGE 500 500 0 0 660

1 333 PK - VE FLAMMABLE STORAGE 155 155 0 0 204

1 341 PK - VE KITCHEN & SERVING AREA 4,972 4,972 113 0 6,563

1 340 PK - VE DINING AREA 4,520 4,520 113 0 5,966

1 382 PK - VE PROFESSIONAL LIBRARY 452 452 113 0 596

1 381 PK - VE MEDIA TECHNICAL PROCESSING 452 452 113 0 596

1 380 PK - VE LIBRARY (READING ROOM/STACKS) 4,181 4,181 113 0 5,518

1 366 PK - VE STAGE DRESSING ROOM (FEMALE) 280 280 56 0 369

1 365 PK - VE STAGE DRESSING ROOM (MALE) 280 280 56 0 369

1 368 PK - VE TEXTBOOK STORAGE 392 392 56 0 517

1 367 PK - VE CONTROL BOOTH/PROJECTION ROOM 100 100 1 0 132

1 305 PK - VE PRODUCTION WORKROOM 448 448 56 0 591

1 304 PK - VE RECEPTION AREA 952 952 56 0 1,256

1 307 PK - VE CLINIC 336 336 56 0 443

1 306 PK - VE CONFERENCE ROOM 784 784 56 0 1,034

2 303 PK - VE SECRETARIAL SPACE 158 316 0 0 417

1 300 PK - VE PRINCIPAL/DIRECTOR OFFICE 250 250 0 0 330

1 330 PK - VE CUSTODIAL RECEIVING 1,695 1,695 113 0 2,237

2 302 PK - VE BOOKKEEPING OFFICE 125 250 0 0 330

8 301 PK - VE ASSISTANT PRINCIPAL/OTHER OFFICE 175 1,400 0 0 1,848

3 314 PK - VE ITINERANT OFFICE 125 375 0 0 495

1 313 PK - VE CAREERS ROOM 336 336 56 0 443

1 316 PK - VE TEACHER LOUNGE/DINING 452 452 113 0 596

1 315 PK - VE TEACHER PLANNING OFFICE 2,260 2,260 113 0 2,983

1 312 PK - VE COMPUTER AREA 168 168 56 0 221

1 309 PK - VE VAULT/STUDENT RECORDS 336 336 56 0 443

1 308 PK - VE GENERAL SCHOOL STORAGE 560 560 56 0 739

1 311 PK - VE STUDENT ACTIVITIES 560 560 56 0 739

1 310 PK - VE SCHOOL STORE 112 112 56 0 147

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 56: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:38 of 234 Report Date: 6/15/2015 11:49:17 AM

1 389 PK - VE MEDIA SMALL GROUP ROOM 112 112 56 0 147

1 388 PK - VE MEDIA COPYING ROOM 226 226 113 0 298

1 390 PK - VE MEDIA GROUP PROJECTS/INSTRUCTION 565 565 113 0 745

25 815 06 - 12 STUDENT RESTROOM (MALE) 112 2,800 56 0 3,696

1 391 PK - VE MEDIA MAINTENANCE/REPAIR 112 112 56 0 147

25 816 06 - 12 STUDENT RESTROOM (FEMALE) 112 2,800 56 0 3,696

1 383 PK - VE AUDIO VISUAL STORAGE 678 678 113 0 894

1 387 PK - VE MEDIA PRODUCTION LAB 565 565 113 0 745

1 384 PK - VE PERIODICAL STORAGE 226 226 113 0 298

1 386 PK - VE CLOSED CIRCUIT STORAGE 565 565 113 0 745

1 385 PK - VE CLOSED CIRCUIT TV LAB 791 791 113 0 1,044

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 57: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:39 of 234 Report Date: 6/15/2015 11:49:17 AM

1,758

Total Stations: 1,954 Acres Required: 29

Total Capacity:

803 INSTRUCTIONAL DARKROOM 100 100 0 0 134

1 51 04 - 08 ART - MIDDLE 1,260 1,260 30 30 1,688

808 MATERIAL STORAGE 100 100 0 0 134

805 KILN 60 60 0 0 80

812 PROJECT STORAGE 150 1,350 0 0 1,809

808 MATERIAL STORAGE 100 900 0 0 1,206

808 MATERIAL STORAGE 100 700 0 0 938

7 40 PK - 12 RESOURCE ROOM 290 2,030 10 0 2,720

812 PROJECT STORAGE 150 150 0 0 201

803 INSTRUCTIONAL DARKROOM 100 100 0 0 134

1 52 09 - 12 ART - SENIOR HIGH 1,590 1,590 30 30 2,130

805 KILN 60 60 0 0 80

816 STUDENT RESTROOM (FEMALE) 35 525 0 0 703

815 STUDENT RESTROOM (MALE) 35 525 0 0 703

808 MATERIAL STORAGE 100 2,200 0 0 2,948

22 3 09 - 12 SENIOR HIGH CLASSROOM (9-12) 800 17,600 25 550 23,584

15 2 04 - 08 INTERMEDIATE/MIDDLE CLASSROOM (4-8) 858 12,870 22 330 17,245

9 23 09 - 12 SENIOR HIGH SCIENCE LAB (9-12) 1,275 11,475 25 225 15,376

811 OUTSIDE STORAGE 50 750 0 0 1,005

808 MATERIAL STORAGE 100 1,500 0 0 2,010

1 11 04 - 08 INTERMEDIATE/MIDDLE SKILLS LAB (4-8) 858 858 22 22 1,149

6 21 04 - 08 INTERMEDIATE/MIDDLE SCIENCE LAB (4-8) 1,122 6,732 22 132 9,020

808 MATERIAL STORAGE 100 300 0 0 402

812 PROJECT STORAGE 150 900 0 0 1,206

808 MATERIAL STORAGE 100 600 0 0 804

815 STUDENT RESTROOM (MALE) 35 35 0 0 46

808 MATERIAL STORAGE 100 100 0 0 134

3 12 09 - 12 SENIOR HIGH SKILLS LAB (9-12) 800 2,400 25 75 3,216

816 STUDENT RESTROOM (FEMALE) 35 35 0 0 46

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

COMBINATION (07 - 12)

1,954

Gross Sq. Feet:

Utilization:

299,881

1.000

Level:

Page 58: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:40 of 234 Report Date: 6/15/2015 11:49:17 AM

836 SHEET MUSIC STORAGE 150 300 0 0 402

833 ROBE STORAGE 150 300 0 0 402

1 76 06 - 12 BAND CLASS (MIDDLE-SR HIGH) 2,000 2,000 50 50 2,680

837 MUSIC EQUIPMENT STORAGE 400 800 0 0 1,072

831 MUSIC PRACTICE ROOM 70 140 0 0 187

806 REFERENCE 100 200 0 0 268

2 75 06 - 12 VOCAL MUSIC CLASS (MIDDLE-SR HIGH) 1,425 2,850 25 50 3,819

830 MUSIC ENSEMBLE 300 600 0 0 804

808 MATERIAL STORAGE 100 200 0 0 268

835 MUSIC STUDIO 180 180 0 0 241

834 UNIFORM STORAGE 300 300 0 0 402

832 INSTRUMENT STORAGE 600 600 0 0 804

808 MATERIAL STORAGE 100 100 0 0 134

806 REFERENCE 100 100 0 0 134

831 MUSIC PRACTICE ROOM 70 70 0 0 93

830 MUSIC ENSEMBLE 300 300 0 0 402

815 STUDENT RESTROOM (MALE) 35 140 0 0 187

813 STUDENT STORAGE 40 160 0 0 214

4 62 PK - 12 E S E FULL-TIME 950 3,800 10 40 5,092

816 STUDENT RESTROOM (FEMALE) 35 140 0 0 187

808 MATERIAL STORAGE 100 400 0 0 536

808 MATERIAL STORAGE 100 100 0 0 134

808 MATERIAL STORAGE 100 400 0 0 536

4 61 PK - 12 E S E PART-TIME 975 3,900 15 60 5,226

812 PROJECT STORAGE 150 150 0 0 201

808 MATERIAL STORAGE 100 500 0 0 670

5 65 PK - 12 E S E RESOURCE 380 1,900 4 0 2,546

4 66 PK - 12 E S E SUPPLEMENTARY INSTRUCTION 100 400 2 0 536

813 STUDENT STORAGE 40 200 0 0 268

817 STUDENT RESTROOM & BATH 110 440 0 0 589

813 STUDENT STORAGE 40 160 0 0 214

808 MATERIAL STORAGE 100 400 0 0 536

816 STUDENT RESTROOM (FEMALE) 35 140 0 0 187

815 STUDENT RESTROOM (MALE) 35 140 0 0 187

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 59: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:41 of 234 Report Date: 6/15/2015 11:49:17 AM

1 114 06 - 12 P E LAUNDRY 174 174 87 0 233

1 113 06 - 12 GYMNASIUM SEATING 5,600 5,600 175 0 7,504

1 116 06 - 12 P E TRAINING ROOM 250 250 1 0 335

1 115 06 - 12 P E FIRST AID 174 174 87 0 233

1 112 09 - 12 SR HIGH GYMNASIUM 6,500 6,500 70 70 8,710

1 99 06 - 12 P E TEACHERS SHOWER (MALE) 22 22 1 0 29

1 98 06 - 12 P E STORAGE (MIDDLE-SR HIGH) 783 783 87 0 1,049

1 110 06 - 12 P E MULTIPURPOSE ROOM (MIDDLE-SR HIGH) 1,050 1,050 1 0 1,407

1 100 06 - 12 P E TEACHERS SHOWER (FEMALE) 22 22 1 0 29

1 212 09 - VE BUSINESS EDUCATION LAB 1,460 1,460 20 20 1,956

808 MATERIAL STORAGE 100 200 0 0 268

2 210 06 - 09 BUSINESS EXPLORATION LAB 1,210 2,420 22 44 3,242

1 118 06 - 12 P E WRESTLING ROOM 1,680 1,680 1 0 2,251

1 117 06 - 12 P E WEIGHT ROOM 1,000 1,000 1 0 1,340

1 120 06 - 12 GYMNASIUM STORAGE 261 261 87 0 349

1 119 06 - 12 P E GYMNASTICS & DANCE 1,050 1,050 1 0 1,407

830 MUSIC ENSEMBLE 300 300 0 0 402

808 MATERIAL STORAGE 100 100 0 0 134

832 INSTRUMENT STORAGE 600 600 0 0 804

831 MUSIC PRACTICE ROOM 70 70 0 0 93

806 REFERENCE 100 100 0 0 134

836 SHEET MUSIC STORAGE 150 150 0 0 201

1 97 06 - 12 P E DRYING AREA (FEMALE) 174 174 87 0 233

1 77 06 - 12 ORCHESTRA CLASS (MIDDLE-SR HIGH) 1,425 1,425 25 25 1,909

837 MUSIC EQUIPMENT STORAGE 400 400 0 0 536

1 94 06 - 12 P E SHOWER (MALE) 174 174 87 0 233

1 93 06 - 12 P E LOCKER ROOM (FEMALE) 174 174 87 0 233

1 96 06 - 12 P E DRYING AREA (MALE) 174 174 87 0 233

1 95 06 - 12 P E SHOWER (FEMALE) 174 174 87 0 233

1 92 06 - 12 P E LOCKER ROOM (MALE) 174 174 87 0 233

837 MUSIC EQUIPMENT STORAGE 400 400 0 0 536

836 SHEET MUSIC STORAGE 150 150 0 0 201

1 91 06 - 12 P E DRESSING ROOM (FEMALE) 1,044 1,044 87 0 1,398

1 90 06 - 12 P E DRESSING ROOM (MALE) 1,044 1,044 87 0 1,398

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 60: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:42 of 234 Report Date: 6/15/2015 11:49:17 AM

808 MATERIAL STORAGE 100 100 0 0 134

1 246 09 - VE LARGE INDUSTRIAL LAB 4,000 4,000 20 20 5,360

840 VOCATIONAL RELATED CLASSROOM 680 680 20 0 911

810 MATERIAL STORAGE (LARGE) 395 395 0 0 529

852 VOCATIONAL TECHNOLOGY RESOURCE CENTER 800 800 0 0 1,072

852 VOCATIONAL TECHNOLOGY RESOURCE CENTER 800 1,600 0 0 2,144

851 VOCATIONAL TOOL STORAGE (LARGE) 310 620 0 0 830

810 MATERIAL STORAGE (LARGE) 395 395 0 0 529

1 242 09 - 12 MEDIUM TECHNOLOGY LAB 2,375 2,375 25 25 3,182

812 PROJECT STORAGE 150 150 0 0 201

808 MATERIAL STORAGE 100 100 0 0 134

804 DISPENSARY 135 135 0 0 180

849 VOCATIONAL PROJECT STORAGE 310 310 0 0 415

847 VOCATIONAL FLAMMABLE STORAGE 125 125 0 0 167

1 252 09 - VE SMALL HEALTH LAB 1,200 1,200 20 20 1,608

850 VOCATIONAL TOOL STORAGE (SMALL) 195 195 0 0 261

808 MATERIAL STORAGE 100 100 0 0 134

1 230 06 - 09 HOME ECONOMICS EXPLORATION LAB 1,540 1,540 22 22 2,063

842 KITCHEN (HOME ECONOMICS) 125 125 0 0 167

812 PROJECT STORAGE 150 150 0 0 201

840 VOCATIONAL RELATED CLASSROOM 680 680 20 0 911

808 MATERIAL STORAGE 100 100 0 0 134

849 VOCATIONAL PROJECT STORAGE 310 620 0 0 830

812 PROJECT STORAGE 150 150 0 0 201

1 222 09 - VE SMALL DISTRIBUTIVE/DIVERSIFIED LAB 1,100 1,100 20 20 1,474

852 VOCATIONAL TECHNOLOGY RESOURCE CENTER 800 800 0 0 1,072

843 LAUNDRY (HOME ECONOMICS) 50 50 0 0 67

808 MATERIAL STORAGE 100 200 0 0 268

2 240 06 - 09 TECHNOLOGY/INDUSTRY EXPLORATION LAB 2,090 4,180 22 44 5,601

842 KITCHEN (HOME ECONOMICS) 125 125 0 0 167

852 VOCATIONAL TECHNOLOGY RESOURCE CENTER 800 800 0 0 1,072

843 LAUNDRY (HOME ECONOMICS) 50 50 0 0 67

808 MATERIAL STORAGE 100 100 0 0 134

1 233 09 - VE MEDIUM HOME ECONOMICS LAB 1,380 1,380 20 20 1,849

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 61: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:43 of 234 Report Date: 6/15/2015 11:49:17 AM

5 314 PK - VE ITINERANT OFFICE 125 625 0 0 837

1 313 PK - VE CAREERS ROOM 522 522 87 0 699

1 316 PK - VE TEACHER LOUNGE/DINING 700 700 175 0 938

1 315 PK - VE TEACHER PLANNING OFFICE 3,500 3,500 175 0 4,690

1 312 PK - VE COMPUTER AREA 261 261 87 0 349

1 309 PK - VE VAULT/STUDENT RECORDS 522 522 87 0 699

1 308 PK - VE GENERAL SCHOOL STORAGE 870 870 87 0 1,165

1 311 PK - VE STUDENT ACTIVITIES 870 870 87 0 1,165

1 310 PK - VE SCHOOL STORE 174 174 87 0 233

1 351 06 - 12 MIDDLE/SR HIGH COVERED PATIO 6,300 6,300 175 0 8,442

1 349 PK - VE KITCHEN CHAIR STORAGE 348 348 87 0 466

1 341 PK - VE KITCHEN & SERVING AREA 7,700 7,700 175 0 10,318

1 333 PK - VE FLAMMABLE STORAGE 155 155 0 0 207

1 330 PK - VE CUSTODIAL RECEIVING 2,625 2,625 175 0 3,517

1 340 PK - VE DINING AREA 7,000 7,000 175 0 9,380

1 334 PK - VE CUSTODIAL EQUIPMENT STORAGE 500 500 0 0 670

802 INSTRUCTIONAL CONFERENCE ROOM 225 225 0 0 301

1 271 09 - VE VPI LAB 705 705 15 0 944

840 VOCATIONAL RELATED CLASSROOM 680 680 20 0 911

808 MATERIAL STORAGE 100 100 0 0 134

853 VOCATIONAL TESTING 250 250 0 0 335

840 VOCATIONAL RELATED CLASSROOM 680 680 20 0 911

1 307 PK - VE CLINIC 522 522 87 0 699

810 MATERIAL STORAGE (LARGE) 395 395 0 0 529

1 270 09 - VE WORK EVALUATION LAB 1,110 1,110 15 0 1,487

1 304 PK - VE RECEPTION AREA 1,479 1,479 87 0 1,981

2 303 PK - VE SECRETARIAL SPACE 158 316 0 0 423

1 306 PK - VE CONFERENCE ROOM 1,218 1,218 87 0 1,632

1 305 PK - VE PRODUCTION WORKROOM 696 696 87 0 932

5 302 PK - VE BOOKKEEPING OFFICE 125 625 0 0 837

853 VOCATIONAL TESTING 250 250 0 0 335

846 RECEPTION (VOC ED INSTRUCTION) 90 90 0 0 120

13 301 PK - VE ASSISTANT PRINCIPAL/OTHER OFFICE 175 2,275 0 0 3,048

1 300 PK - VE PRINCIPAL/DIRECTOR OFFICE 250 250 0 0 335

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 62: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:44 of 234 Report Date: 6/15/2015 11:49:17 AM

1 388 PK - VE MEDIA COPYING ROOM 350 350 175 0 469

1 389 PK - VE MEDIA SMALL GROUP ROOM 174 174 87 0 233

1 390 PK - VE MEDIA GROUP PROJECTS/INSTRUCTION 875 875 175 0 1,172

1 387 PK - VE MEDIA PRODUCTION LAB 875 875 175 0 1,172

1 384 PK - VE PERIODICAL STORAGE 350 350 175 0 469

1 385 PK - VE CLOSED CIRCUIT TV LAB 1,225 1,225 175 0 1,641

1 386 PK - VE CLOSED CIRCUIT STORAGE 875 875 175 0 1,172

802 INSTRUCTIONAL CONFERENCE ROOM 225 225 0 0 301

808 MATERIAL STORAGE 100 100 0 0 134

15 815 06 - 12 STUDENT RESTROOM (MALE) 174 2,610 87 0 3,497

801 FIRING RANGE (INDOOR) 2,400 2,400 0 0 3,216

1 391 PK - VE MEDIA MAINTENANCE/REPAIR 174 174 87 0 233

1 708 09 - 12 JROTC 1,260 1,260 30 30 1,688

800 ARMS ROOM 150 150 0 0 201

15 816 06 - 12 STUDENT RESTROOM (FEMALE) 174 2,610 87 0 3,497

1 365 PK - VE STAGE DRESSING ROOM (MALE) 435 435 87 0 582

1 366 PK - VE STAGE DRESSING ROOM (FEMALE) 435 435 87 0 582

1 367 PK - VE CONTROL BOOTH/PROJECTION ROOM 100 100 1 0 134

1 364 PK - VE STAGE STORAGE 875 875 175 0 1,172

1 383 PK - VE AUDIO VISUAL STORAGE 1,050 1,050 175 0 1,407

1 360 06 - VE AUDITORIUM 5,250 5,250 175 0 7,035

1 363 PK - VE STAGE 990 990 1 0 1,326

1 380 PK - VE LIBRARY (READING ROOM/STACKS) 6,475 6,475 175 0 8,676

1 381 PK - VE MEDIA TECHNICAL PROCESSING 700 700 175 0 938

1 382 PK - VE PROFESSIONAL LIBRARY 700 700 175 0 938

2 372 06 - VE TICKET BOOTH 30 60 1 0 80

1 368 PK - VE TEXTBOOK STORAGE 609 609 87 0 816

2 370 06 - VE LOBBY 870 1,740 87 0 2,331

2 371 06 - VE CONCESSIONS 200 400 1 0 536

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 63: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:45 of 234 Report Date: 6/15/2015 11:49:17 AM

2,716

Total Stations: 2,859 Acres Required: 39

Total Capacity:

6 62 PK - 12 E S E FULL-TIME 950 5,700 10 60 7,638

816 STUDENT RESTROOM (FEMALE) 35 210 0 0 281

813 STUDENT STORAGE 40 240 0 0 321

808 MATERIAL STORAGE 100 600 0 0 804

808 MATERIAL STORAGE 100 600 0 0 804

6 61 PK - 12 E S E PART-TIME 975 5,850 15 90 7,839

815 STUDENT RESTROOM (MALE) 35 210 0 0 281

813 STUDENT STORAGE 40 240 0 0 321

815 STUDENT RESTROOM (MALE) 35 210 0 0 281

817 STUDENT RESTROOM & BATH 110 660 0 0 884

816 STUDENT RESTROOM (FEMALE) 35 210 0 0 281

2 63 PK - 12 E S E VOCATIONAL 1,140 2,280 12 24 3,055

1 22 09 - 12 SENIOR HIGH SCIENCE DEMO (9-12) 925 925 25 25 1,239

808 MATERIAL STORAGE 100 400 0 0 536

812 PROJECT STORAGE 150 150 0 0 201

808 MATERIAL STORAGE 100 100 0 0 134

63 3 09 - 12 SENIOR HIGH CLASSROOM (9-12) 800 50,400 25 1,575 67,536

812 PROJECT STORAGE 150 300 0 0 402

4 12 09 - 12 SENIOR HIGH SKILLS LAB (9-12) 800 3,200 25 100 4,288

808 MATERIAL STORAGE 100 6,300 0 0 8,442

11 23 09 - 12 SENIOR HIGH SCIENCE LAB (9-12) 1,275 14,025 25 275 18,793

803 INSTRUCTIONAL DARKROOM 100 200 0 0 268

2 52 09 - 12 ART - SENIOR HIGH 1,590 3,180 30 60 4,261

808 MATERIAL STORAGE 100 200 0 0 268

805 KILN 60 120 0 0 160

812 PROJECT STORAGE 150 1,650 0 0 2,211

808 MATERIAL STORAGE 100 1,100 0 0 1,474

808 MATERIAL STORAGE 100 1,100 0 0 1,474

11 40 PK - 12 RESOURCE ROOM 290 3,190 10 0 4,274

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

SENIOR HIGH (09 - 12)

2,859

Gross Sq. Feet:

Utilization:

403,780

1.000

Level:

Page 64: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:46 of 234 Report Date: 6/15/2015 11:49:17 AM

834 UNIFORM STORAGE 300 300 0 0 402

832 INSTRUMENT STORAGE 600 600 0 0 804

836 SHEET MUSIC STORAGE 150 150 0 0 201

835 MUSIC STUDIO 180 180 0 0 241

831 MUSIC PRACTICE ROOM 70 70 0 0 93

806 REFERENCE 100 100 0 0 134

1 76 06 - 12 BAND CLASS (MIDDLE-SR HIGH) 2,000 2,000 50 50 2,680

830 MUSIC ENSEMBLE 300 300 0 0 402

808 MATERIAL STORAGE 100 100 0 0 134

832 INSTRUMENT STORAGE 600 600 0 0 804

831 MUSIC PRACTICE ROOM 70 70 0 0 93

830 MUSIC ENSEMBLE 300 300 0 0 402

1 77 06 - 12 ORCHESTRA CLASS (MIDDLE-SR HIGH) 1,425 1,425 25 25 1,909

837 MUSIC EQUIPMENT STORAGE 400 400 0 0 536

808 MATERIAL STORAGE 100 100 0 0 134

806 REFERENCE 100 100 0 0 134

813 STUDENT STORAGE 40 320 0 0 428

808 MATERIAL STORAGE 100 800 0 0 1,072

808 MATERIAL STORAGE 100 600 0 0 804

6 66 PK - 12 E S E SUPPLEMENTARY INSTRUCTION 50 300 2 0 402

8 65 PK - 12 E S E RESOURCE 380 3,040 4 0 4,073

808 MATERIAL STORAGE 100 200 0 0 268

837 MUSIC EQUIPMENT STORAGE 400 400 0 0 536

816 STUDENT RESTROOM (FEMALE) 35 70 0 0 93

815 STUDENT RESTROOM (MALE) 35 70 0 0 93

831 MUSIC PRACTICE ROOM 70 70 0 0 93

830 MUSIC ENSEMBLE 300 300 0 0 402

836 SHEET MUSIC STORAGE 150 150 0 0 201

833 ROBE STORAGE 150 150 0 0 201

808 MATERIAL STORAGE 100 100 0 0 134

808 MATERIAL STORAGE 100 100 0 0 134

1 70 PK - 12 E S E ITINERANT 200 200 4 0 268

806 REFERENCE 100 100 0 0 134

1 75 06 - 12 VOCAL MUSIC CLASS (MIDDLE-SR HIGH) 1,425 1,425 25 25 1,909

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 65: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:47 of 234 Report Date: 6/15/2015 11:49:17 AM

806 REFERENCE 100 100 0 0 134

1 202 09 - VE SMALL AGRICULTURE LAB 1,100 1,100 20 20 1,474

818 LOCKERS/RESTROOM/SHOWER (ESE/VOC ED) 225 225 0 0 301

810 MATERIAL STORAGE (LARGE) 395 395 0 0 529

1 120 06 - 12 GYMNASIUM STORAGE 405 405 135 0 542

1 117 06 - 12 P E WEIGHT ROOM 1,000 1,000 1 0 1,340

1 116 06 - 12 P E TRAINING ROOM 250 250 1 0 335

1 119 06 - 12 P E GYMNASTICS & DANCE 1,050 1,050 1 0 1,407

1 118 06 - 12 P E WRESTLING ROOM 1,680 1,680 1 0 2,251

808 MATERIAL STORAGE 100 600 0 0 804

6 212 09 - VE BUSINESS EDUCATION LAB 1,460 8,760 20 120 11,738

850 VOCATIONAL TOOL STORAGE (SMALL) 195 195 0 0 261

841 GREENHOUSE 800 800 0 0 1,072

840 VOCATIONAL RELATED CLASSROOM 680 680 20 0 911

848 VOCATIONAL MACHINERY STORAGE 1,100 1,100 0 0 1,474

847 VOCATIONAL FLAMMABLE STORAGE 125 125 0 0 167

1 93 06 - 12 P E LOCKER ROOM (FEMALE) 270 270 135 0 361

1 92 06 - 12 P E LOCKER ROOM (MALE) 270 270 135 0 361

1 95 06 - 12 P E SHOWER (FEMALE) 270 270 135 0 361

1 94 06 - 12 P E SHOWER (MALE) 270 270 135 0 361

1 91 06 - 12 P E DRESSING ROOM (FEMALE) 1,620 1,620 135 0 2,170

836 SHEET MUSIC STORAGE 150 150 0 0 201

1 115 06 - 12 P E FIRST AID 270 270 135 0 361

1 90 06 - 12 P E DRESSING ROOM (MALE) 1,620 1,620 135 0 2,170

837 MUSIC EQUIPMENT STORAGE 400 400 0 0 536

1 112 09 - 12 SR HIGH GYMNASIUM 6,500 6,500 70 70 8,710

1 110 06 - 12 P E MULTIPURPOSE ROOM (MIDDLE-SR HIGH) 1,050 1,050 1 0 1,407

1 114 06 - 12 P E LAUNDRY 270 270 135 0 361

1 113 06 - 12 GYMNASIUM SEATING 8,672 8,672 271 0 11,620

1 100 06 - 12 P E TEACHERS SHOWER (FEMALE) 22 22 1 0 29

1 97 06 - 12 P E DRYING AREA (FEMALE) 270 270 135 0 361

1 96 06 - 12 P E DRYING AREA (MALE) 270 270 135 0 361

1 99 06 - 12 P E TEACHERS SHOWER (MALE) 22 22 1 0 29

1 98 06 - 12 P E STORAGE (MIDDLE-SR HIGH) 1,215 1,215 135 0 1,628

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 66: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:48 of 234 Report Date: 6/15/2015 11:49:17 AM

840 VOCATIONAL RELATED CLASSROOM 680 2,040 20 0 2,733

810 MATERIAL STORAGE (LARGE) 395 1,185 0 0 1,587

850 VOCATIONAL TOOL STORAGE (SMALL) 195 585 0 0 783

849 VOCATIONAL PROJECT STORAGE 310 930 0 0 1,246

808 MATERIAL STORAGE 100 300 0 0 402

808 MATERIAL STORAGE 100 200 0 0 268

2 244 09 - VE SMALL INDUSTRIAL LAB 1,100 2,200 20 40 2,948

3 245 09 - VE MEDIUM INDUSTRIAL LAB 1,800 5,400 20 60 7,236

840 VOCATIONAL RELATED CLASSROOM 680 1,360 20 0 1,822

853 VOCATIONAL TESTING 250 250 0 0 335

810 MATERIAL STORAGE (LARGE) 395 395 0 0 529

1 270 09 - VE WORK EVALUATION LAB 1,110 1,110 15 0 1,487

808 MATERIAL STORAGE 100 100 0 0 134

1 251 09 - 12 PRACTICAL HEALTH LAB 1,400 1,400 25 25 1,876

808 MATERIAL STORAGE 100 100 0 0 134

1 261 09 - 12 PRACTICAL PUBLIC SERVICE LAB 1,375 1,375 25 25 1,842

812 PROJECT STORAGE 150 450 0 0 603

3 232 09 - VE SMALL HOME ECONOMICS LAB 1,100 3,300 20 60 4,422

1 234 09 - VE LARGE HOME ECONOMICS LAB 2,250 2,250 25 25 3,015

852 VOCATIONAL TECHNOLOGY RESOURCE CENTER 800 2,400 0 0 3,216

852 VOCATIONAL TECHNOLOGY RESOURCE CENTER 800 800 0 0 1,072

1 231 09 - 12 PRACTICAL HOME ECONOMICS LAB 1,600 1,600 25 25 2,144

852 VOCATIONAL TECHNOLOGY RESOURCE CENTER 800 800 0 0 1,072

843 LAUNDRY (HOME ECONOMICS) 50 50 0 0 67

808 MATERIAL STORAGE 100 100 0 0 134

852 VOCATIONAL TECHNOLOGY RESOURCE CENTER 800 800 0 0 1,072

808 MATERIAL STORAGE 100 100 0 0 134

810 MATERIAL STORAGE (LARGE) 395 395 0 0 529

1 242 09 - 12 MEDIUM TECHNOLOGY LAB 2,375 2,375 25 25 3,182

1 241 09 - 12 SMALL TECHNOLOGY LAB 1,625 1,625 25 25 2,177

842 KITCHEN (HOME ECONOMICS) 125 125 0 0 167

812 PROJECT STORAGE 150 150 0 0 201

852 VOCATIONAL TECHNOLOGY RESOURCE CENTER 800 800 0 0 1,072

843 LAUNDRY (HOME ECONOMICS) 50 50 0 0 67

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 67: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:49 of 234 Report Date: 6/15/2015 11:49:17 AM

1 333 PK - VE FLAMMABLE STORAGE 155 155 0 0 207

1 330 PK - VE CUSTODIAL RECEIVING 4,065 4,065 271 0 5,447

1 340 PK - VE DINING AREA 10,840 10,840 271 0 14,525

1 334 PK - VE CUSTODIAL EQUIPMENT STORAGE 500 500 0 0 670

1 316 PK - VE TEACHER LOUNGE/DINING 1,084 1,084 271 0 1,452

1 313 PK - VE CAREERS ROOM 810 810 135 0 1,085

1 312 PK - VE COMPUTER AREA 405 405 135 0 542

1 315 PK - VE TEACHER PLANNING OFFICE 5,420 5,420 271 0 7,262

7 314 PK - VE ITINERANT OFFICE 125 875 0 0 1,172

1 365 PK - VE STAGE DRESSING ROOM (MALE) 675 675 135 0 904

1 364 PK - VE STAGE STORAGE 1,355 1,355 271 0 1,815

1 363 PK - VE STAGE 990 990 1 0 1,326

1 349 PK - VE KITCHEN CHAIR STORAGE 540 540 135 0 723

1 341 PK - VE KITCHEN & SERVING AREA 11,924 11,924 271 0 15,978

1 360 06 - VE AUDITORIUM 8,130 8,130 271 0 10,894

1 351 06 - 12 MIDDLE/SR HIGH COVERED PATIO 9,756 9,756 271 0 13,073

853 VOCATIONAL TESTING 250 250 0 0 335

846 RECEPTION (VOC ED INSTRUCTION) 90 90 0 0 120

13 301 PK - VE ASSISTANT PRINCIPAL/OTHER OFFICE 175 2,275 0 0 3,048

1 300 PK - VE PRINCIPAL/DIRECTOR OFFICE 250 250 0 0 335

840 VOCATIONAL RELATED CLASSROOM 680 680 20 0 911

1 271 09 - VE VPI LAB 705 705 15 0 944

1 311 PK - VE STUDENT ACTIVITIES 1,350 1,350 135 0 1,809

808 MATERIAL STORAGE 100 100 0 0 134

802 INSTRUCTIONAL CONFERENCE ROOM 225 225 0 0 301

1 308 PK - VE GENERAL SCHOOL STORAGE 1,350 1,350 135 0 1,809

1 307 PK - VE CLINIC 810 810 135 0 1,085

1 310 PK - VE SCHOOL STORE 270 270 135 0 361

1 309 PK - VE VAULT/STUDENT RECORDS 810 810 135 0 1,085

1 306 PK - VE CONFERENCE ROOM 1,890 1,890 135 0 2,532

4 303 PK - VE SECRETARIAL SPACE 158 632 0 0 846

5 302 PK - VE BOOKKEEPING OFFICE 125 625 0 0 837

1 305 PK - VE PRODUCTION WORKROOM 1,080 1,080 135 0 1,447

1 304 PK - VE RECEPTION AREA 2,295 2,295 135 0 3,075

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 68: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:50 of 234 Report Date: 6/15/2015 11:49:17 AM

1 388 PK - VE MEDIA COPYING ROOM 542 542 271 0 726

1 389 PK - VE MEDIA SMALL GROUP ROOM 270 270 135 0 361

1 387 PK - VE MEDIA PRODUCTION LAB 1,355 1,355 271 0 1,815

1 385 PK - VE CLOSED CIRCUIT TV LAB 1,897 1,897 271 0 2,541

1 386 PK - VE CLOSED CIRCUIT STORAGE 1,355 1,355 271 0 1,815

1 390 PK - VE MEDIA GROUP PROJECTS/INSTRUCTION 1,355 1,355 271 0 1,815

801 FIRING RANGE (INDOOR) 2,400 2,400 0 0 3,216

802 INSTRUCTIONAL CONFERENCE ROOM 225 225 0 0 301

800 ARMS ROOM 150 150 0 0 201

1 391 PK - VE MEDIA MAINTENANCE/REPAIR 270 270 135 0 361

1 708 09 - 12 JROTC 1,260 1,260 30 30 1,688

808 MATERIAL STORAGE 100 100 0 0 134

1 368 PK - VE TEXTBOOK STORAGE 945 945 135 0 1,266

2 370 06 - VE LOBBY 1,350 2,700 135 0 3,618

1 367 PK - VE CONTROL BOOTH/PROJECTION ROOM 100 100 1 0 134

1 384 PK - VE PERIODICAL STORAGE 542 542 271 0 726

1 366 PK - VE STAGE DRESSING ROOM (FEMALE) 675 675 135 0 904

2 371 06 - VE CONCESSIONS 200 400 1 0 536

1 382 PK - VE PROFESSIONAL LIBRARY 1,084 1,084 271 0 1,452

1 383 PK - VE AUDIO VISUAL STORAGE 1,626 1,626 271 0 2,178

1 381 PK - VE MEDIA TECHNICAL PROCESSING 1,084 1,084 271 0 1,452

2 372 06 - VE TICKET BOOTH 30 60 1 0 80

1 380 PK - VE LIBRARY (READING ROOM/STACKS) 10,027 10,027 271 0 13,436

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 69: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:51 of 234 Report Date: 6/15/2015 11:49:17 AM

0

Total Stations: 0 Acres Required: 7

Total Capacity:

1 422 CA - DS MAIN LOBBY & SWITCHBOARD 0 0 0 0 0

1 421 CA - DS ANCILLARY STAFF LOUNGE 0 0 0 0 0

1 426 CA - DS GENERAL ANCILLARY OFFICE 0 0 0 0 0

1 424 CA - DS DIRECTORS OFFICE 0 0 0 0 0

1 418 CA - DS ANCILLARY ADMINISTRATIVE STORAGE 0 0 0 0 0

1 417 CA - DS CENTRAL SECURITY OFFICE 0 0 0 0 0

1 420 CA - DS SCHOOL BOARD MEETING ROOM 0 0 0 0 0

1 419 CA - DS ANCILLARY FLAMMABLE STORAGE 0 0 0 0 0

1 427 CA - DS STAFF DEVELOPMENT/INSTRUCTION 0 0 0 0 0

1 500 CA - DS PROGRAMMER ROOM 0 0 0 0 0

1 428 CA - DS OTHER ANCILLARY ADMINISTRATIVE SUPPORT 0 0 0 0 0

1 501 CA - DS DATA PROCESSING TECHNICAL AREA 0 0 0 0 0

1 404 CA - DS ANCILLARY RECEPTION AREA 0 0 0 0 0

1 403 CA - DS ANCILLARY SECRETARIAL/CLERICAL OFFICE 0 0 0 0 0

1 406 CA - DS ASSISTANT SUPERINTENDENTS OFFICE 0 0 0 0 0

1 405 CA - DS VAULT 0 0 0 0 0

1 400 CA - DS SUPERINTENDENTS OFFICE 0 0 0 0 0

1 416 CA - DS ANCILLARY CUSTODIAL SERVICES 0 0 0 0 0

1 402 CA - DS SUPERINTENDENTS SECRETARY 0 0 0 0 0

1 401 CA - DS ANCILLARY CONFERENCE ROOM 0 0 0 0 0

1 407 CA - DS ANCILLARY ADMINISTRATIVE OFFICE 0 0 0 0 0

1 413 CA - DS CENTRAL REPRODUCTION & COPY 0 0 0 0 0

1 412 CA - DS PERSONNEL SERVICES 0 0 0 0 0

1 415 CA - DS MAIL ROOM 0 0 0 0 0

1 414 CA - DS CENTRAL ADMINISTRATIVE SUPPLY 0 0 0 0 0

1 409 CA - DS BUSINESS OPERATIONS STORAGE 0 0 0 0 0

1 408 CA - DS BUSINESS OPERATIONS WORK AREA 0 0 0 0 0

1 411 CA - DS WORD PROCESSING CENTER 0 0 0 0 0

1 410 CA - DS SCHOOL PLANT PLANNING 0 0 0 0 0

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

COUNTY ADMINISTRATION (DS - DS)

0

Gross Sq. Feet:

Utilization:

170,000

0.000

Level:

Page 70: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:52 of 234 Report Date: 6/15/2015 11:49:17 AM

1 590 CA - DS SCHOOL BUS PAINT BAY 0 0 0 0 0

1 589 CA - DS SCHOOL BUS PAINT/FLAMMABLE STORAGE 0 0 0 0 0

1 592 CA - DS SCHOOL BUS WORK BAY 0 0 0 0 0

1 591 CA - DS SCHOOL BUS TIRE STORAGE & MOUNTING 0 0 0 0 0

1 588 CA - DS SCHOOL BUS BODY SHOP 0 0 0 0 0

1 585 CA - DS SCHOOL BUS PARTS ROOM 0 0 0 0 0

1 580 CA - DS LOCKSMITH SHOP 0 0 0 0 0

1 587 CA - DS SCHOOL BUS GLASS/UPHOLSTERY SHOP 0 0 0 0 0

1 586 CA - DS SCHOOL BUS MACHINE SHOP 0 0 0 0 0

1 604 CA - DS ANCILLARY MEDIA PROCESSING 0 0 0 0 0

1 603 CA - DS ANCILLARY PERIODICAL/JOURNAL SERVICES 0 0 0 0 0

1 602 CA - DS ANCILLARY PROFESSIONAL LIBRARY 0 0 0 0 0

1 594 CA - DS ANCILLARY SUPPORT STORAGE 0 0 0 0 0

1 593 CA - DS SCHOOL BUS DRIVERS CLASSROOM 0 0 0 0 0

1 601 CA - DS ANCILLARY LIBRARY REFERENCE 0 0 0 0 0

1 600 CA - DS ANCILLARY LIBRARY WAREHOUSE/STACKS 0 0 0 0 0

1 515 CA - DS CENTRAL KITCHEN 0 0 0 0 0

1 510 CA - DS WAREHOUSE STORAGE 0 0 0 0 0

1 525 CA - DS GLAZING SHOP 0 0 0 0 0

1 520 CA - DS CARPENTRY SHOP 0 0 0 0 0

1 505 CA - DS ANCILLARY COMPUTER STORAGE 0 0 0 0 0

1 502 CA - DS DATA PROCESSING EQUIPMENT 0 0 0 0 0

1 575 CA - DS CARPET SHOP 0 0 0 0 0

1 504 CA - DS OFF-LINE EQUIPMENT 0 0 0 0 0

1 503 CA - DS COMPUTER ROOM (RAISED FLOOR) 0 0 0 0 0

1 560 CA - DS PAINT SHOP 0 0 0 0 0

1 555 CA - DS PLUMBING SHOP 0 0 0 0 0

1 570 CA - DS AIR CONDITIONING SHOP 0 0 0 0 0

1 565 CA - DS WELDING SHOP 0 0 0 0 0

1 550 CA - DS MACHINE SHOP 0 0 0 0 0

1 535 CA - DS SMALL ENGINE SHOP 0 0 0 0 0

1 530 CA - DS MASONRY SHOP 0 0 0 0 0

1 545 CA - DS ELECTRICAL SHOP 0 0 0 0 0

1 540 CA - DS ELECTRONICS SHOP 0 0 0 0 0

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 71: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:53 of 234 Report Date: 6/15/2015 11:49:17 AM

1 609 CA - DS ANCILLARY MEDIA COPYING ROOM 0 0 0 0 0

1 612 CA - DS OTHER ANCILLARY MEDIA SPACE 0 0 0 0 0

1 611 CA - DS ANCILLARY MEDIA STORAGE 0 0 0 0 0

1 610 CA - DS ANCILLARY MEDIA MAINTENANCE/REPAIR 0 0 0 0 0

1 605 CA - DS ANCILLARY AUDIO VISUAL EQUIPMENT 0 0 0 0 0

1 608 CA - DS ANCILLARY MEDIA PRODUCTION LABORATORY 0 0 0 0 0

1 607 CA - DS ANCILLARY CLOSED CIRCUIT TV SUPPORT 0 0 0 0 0

1 606 CA - DS ANCILLARY CLOSED CIRCUIT TV LABORATORY 0 0 0 0 0

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 72: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:54 of 234 Report Date: 6/15/2015 11:49:17 AM

0

Total Stations: 0 Acres Required: 7

Total Capacity:

2 525 CA - DS GLAZING SHOP 0 0 0 0 0

1 535 CA - DS SMALL ENGINE SHOP 0 0 0 0 0

2 520 CA - DS CARPENTRY SHOP 0 0 0 0 0

1 428 CA - DS OTHER ANCILLARY ADMINISTRATIVE SUPPORT 0 0 0 0 0

6 510 CA - DS WAREHOUSE STORAGE 0 0 0 0 0

7 540 CA - DS ELECTRONICS SHOP 0 0 0 0 0

1 575 CA - DS CARPET SHOP 0 0 0 0 0

1 589 CA - DS SCHOOL BUS PAINT/FLAMMABLE STORAGE 0 0 0 0 0

2 555 CA - DS PLUMBING SHOP 0 0 0 0 0

5 545 CA - DS ELECTRICAL SHOP 0 0 0 0 0

1 550 CA - DS MACHINE SHOP 0 0 0 0 0

2 594 CA - DS ANCILLARY SUPPORT STORAGE 0 0 0 0 0

1 404 CA - DS ANCILLARY RECEPTION AREA 0 0 0 0 0

1 405 CA - DS VAULT 0 0 0 0 0

6 403 CA - DS ANCILLARY SECRETARIAL/CLERICAL OFFICE 0 0 0 0 0

2 421 CA - DS ANCILLARY STAFF LOUNGE 0 0 0 0 0

2 401 CA - DS ANCILLARY CONFERENCE ROOM 0 0 0 0 0

24 407 CA - DS ANCILLARY ADMINISTRATIVE OFFICE 0 0 0 0 0

25 418 CA - DS ANCILLARY ADMINISTRATIVE STORAGE 0 0 0 0 0

5 419 CA - DS ANCILLARY FLAMMABLE STORAGE 0 0 0 0 0

2 416 CA - DS ANCILLARY CUSTODIAL SERVICES 0 0 0 0 0

1 408 CA - DS BUSINESS OPERATIONS WORK AREA 0 0 0 0 0

1 410 CA - DS SCHOOL PLANT PLANNING 0 0 0 0 0

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

MAINTENANCE (DS - DS)

0

Gross Sq. Feet:

Utilization:

75,000

0.000

Level:

Page 73: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:55 of 234 Report Date: 6/15/2015 11:49:17 AM

0

Total Stations: 0 Acres Required: 7

Total Capacity:

1 587 CA - DS SCHOOL BUS GLASS/UPHOLSTERY SHOP 0 0 0 0 0

2 585 CA - DS SCHOOL BUS PARTS ROOM 0 0 0 0 0

1 592 CA - DS SCHOOL BUS WORK BAY 0 0 0 0 0

1 589 CA - DS SCHOOL BUS PAINT/FLAMMABLE STORAGE 0 0 0 0 0

1 593 CA - DS SCHOOL BUS DRIVERS CLASSROOM 0 0 0 0 0

1 401 CA - DS ANCILLARY CONFERENCE ROOM 0 0 0 0 0

4 428 CA - DS OTHER ANCILLARY ADMINISTRATIVE SUPPORT 0 0 0 0 0

1 421 CA - DS ANCILLARY STAFF LOUNGE 0 0 0 0 0

2 407 CA - DS ANCILLARY ADMINISTRATIVE OFFICE 0 0 0 0 0

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

TRANSPORTATION (DS - DS)

0

Gross Sq. Feet:

Utilization:

75,000

0.000

Level:

Page 74: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:56 of 234 Report Date: 6/15/2015 11:49:17 AM

0

Total Stations: 0 Acres Required: 7

Total Capacity:

1 588 CA - DS SCHOOL BUS BODY SHOP 0 0 0 0 0

1 589 CA - DS SCHOOL BUS PAINT/FLAMMABLE STORAGE 0 0 0 0 0

1 587 CA - DS SCHOOL BUS GLASS/UPHOLSTERY SHOP 0 0 0 0 0

1 602 CA - DS ANCILLARY PROFESSIONAL LIBRARY 0 0 0 0 0

4 585 CA - DS SCHOOL BUS PARTS ROOM 0 0 0 0 0

4 594 CA - DS ANCILLARY SUPPORT STORAGE 0 0 0 0 0

1 600 CA - DS ANCILLARY LIBRARY WAREHOUSE/STACKS 0 0 0 0 0

1 593 CA - DS SCHOOL BUS DRIVERS CLASSROOM 0 0 0 0 0

2 590 CA - DS SCHOOL BUS PAINT BAY 0 0 0 0 0

2 592 CA - DS SCHOOL BUS WORK BAY 0 0 0 0 0

9 407 CA - DS ANCILLARY ADMINISTRATIVE OFFICE 0 0 0 0 0

4 418 CA - DS ANCILLARY ADMINISTRATIVE STORAGE 0 0 0 0 0

1 404 CA - DS ANCILLARY RECEPTION AREA 0 0 0 0 0

6 510 CA - DS WAREHOUSE STORAGE 0 0 0 0 0

1 401 CA - DS ANCILLARY CONFERENCE ROOM 0 0 0 0 0

4 427 CA - DS STAFF DEVELOPMENT/INSTRUCTION 0 0 0 0 0

9 428 CA - DS OTHER ANCILLARY ADMINISTRATIVE SUPPORT 0 0 0 0 0

3 426 CA - DS GENERAL ANCILLARY OFFICE 0 0 0 0 0

4 421 CA - DS ANCILLARY STAFF LOUNGE 0 0 0 0 0

1 424 CA - DS DIRECTORS OFFICE 0 0 0 0 0

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

WAREHOUSE (DS - DS)

0

Gross Sq. Feet:

Utilization:

25,000

0.000

Level:

Page 75: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:57 of 234 Report Date: 6/15/2015 11:49:17 AM

0

Total Stations: 0 Acres Required: 7

Total Capacity:

1 825 CA - DS ANCILLARY RESTROOM (FEMALE) 0 0 0 0 0

1 824 CA - DS ANCILLARY RESTROOM (MALE) 0 0 0 0 0

4 428 CA - DS OTHER ANCILLARY ADMINISTRATIVE SUPPORT 0 0 0 0 0

1 426 CA - DS GENERAL ANCILLARY OFFICE 0 0 0 0 0

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

MULTIPLE USE SUPPORT (DS - DS)

0

Gross Sq. Feet:

Utilization:

25,000

0.000

Level:

Page 76: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:58 of 234 Report Date: 6/15/2015 11:49:17 AM

100

Total Stations: 100 Acres Required: 4

Total Capacity:

815 STUDENT RESTROOM (MALE) 35 35 0 0 46

813 STUDENT STORAGE 40 40 0 0 53

1 62 PK - 12 E S E FULL-TIME 950 950 10 10 1,273

816 STUDENT RESTROOM (FEMALE) 35 35 0 0 46

817 STUDENT RESTROOM & BATH 110 1,650 0 0 2,211

813 STUDENT STORAGE 40 600 0 0 804

808 MATERIAL STORAGE 100 100 0 0 134

1 61 PK - 12 E S E PART-TIME 975 975 15 15 1,306

808 MATERIAL STORAGE 100 100 0 0 134

815 STUDENT RESTROOM (MALE) 35 35 0 0 46

813 STUDENT STORAGE 40 40 0 0 53

816 STUDENT RESTROOM (FEMALE) 35 35 0 0 46

1 13 PK - 05 ELEMENTARY P E STORAGE 315 315 1 0 422

814 STUDENT RESTROOM (BOTH SEXES) 60 60 0 0 80

1 40 PK - 12 RESOURCE ROOM 290 290 10 0 388

1 14 PK - 05 ELEMENTARY COVERED PLAY AREA 360 360 10 0 482

1 10 PK - 03 PRIMARY SKILLS LAB (K-3) 882 882 18 0 1,181

808 MATERIAL STORAGE 100 1,500 0 0 2,010

813 STUDENT STORAGE 40 40 0 0 53

808 MATERIAL STORAGE 100 100 0 0 134

808 MATERIAL STORAGE 100 100 0 0 134

808 MATERIAL STORAGE 100 100 0 0 134

806 REFERENCE 100 100 0 0 134

15 60 PK - PK E S E PRE-K 475 7,125 5 75 9,547

831 MUSIC PRACTICE ROOM 70 70 0 0 93

808 MATERIAL STORAGE 100 100 0 0 134

1 50 PK - 05 ART - ELEMENTARY 1,000 1,000 22 0 1,340

1 55 PK - 05 MUSIC - ELEMENTARY 1,000 1,000 22 0 1,340

812 PROJECT STORAGE 150 150 0 0 201

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

PRE-K E S E (PK - PK)

100

Gross Sq. Feet:

Utilization:

31,496

1.000

Level:

Page 77: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:59 of 234 Report Date: 6/15/2015 11:49:17 AM

1 315 PK - VE TEACHER PLANNING OFFICE 200 200 10 0 268

1 314 PK - VE ITINERANT OFFICE 125 125 0 0 167

1 330 PK - VE CUSTODIAL RECEIVING 150 150 10 0 201

1 316 PK - VE TEACHER LOUNGE/DINING 40 40 10 0 53

1 307 PK - VE CLINIC 30 30 5 0 40

2 306 PK - VE CONFERENCE ROOM 70 140 5 0 187

1 309 PK - VE VAULT/STUDENT RECORDS 30 30 5 0 40

1 308 PK - VE GENERAL SCHOOL STORAGE 50 50 5 0 67

1 361 PK - VE MULTIPURPOSE ROOM (DINING) 310 310 10 0 415

1 349 PK - VE KITCHEN CHAIR STORAGE 20 20 5 0 26

1 380 PK - VE LIBRARY (READING ROOM/STACKS) 370 370 10 0 495

1 362 PK - VE MULTIPURPOSE ROOM CHAIR STORAGE 20 20 10 0 26

1 334 PK - VE CUSTODIAL EQUIPMENT STORAGE 500 500 0 0 670

1 333 PK - VE FLAMMABLE STORAGE 155 155 0 0 207

1 341 PK - VE KITCHEN & SERVING AREA 440 440 10 0 589

1 340 PK - VE DINING AREA 400 400 10 0 536

1 381 PK - VE MEDIA TECHNICAL PROCESSING 40 40 10 0 53

1 66 PK - 12 E S E SUPPLEMENTARY INSTRUCTION 100 100 2 0 134

813 STUDENT STORAGE 40 40 0 0 53

1 69 PK - 12 E S E AUDIOLOGY LAB 250 250 0 0 335

808 MATERIAL STORAGE 100 100 0 0 134

817 STUDENT RESTROOM & BATH 110 110 0 0 147

1 305 PK - VE PRODUCTION WORKROOM 40 40 5 0 53

808 MATERIAL STORAGE 100 100 0 0 134

1 65 PK - 12 E S E RESOURCE 380 380 4 0 509

1 302 PK - VE BOOKKEEPING OFFICE 125 125 0 0 167

1 301 PK - VE ASSISTANT PRINCIPAL/OTHER OFFICE 175 175 0 0 234

1 304 PK - VE RECEPTION AREA 85 85 5 0 113

1 303 PK - VE SECRETARIAL SPACE 158 158 0 0 211

2 70 PK - 12 E S E ITINERANT 200 400 4 0 536

808 MATERIAL STORAGE 100 100 0 0 134

1 300 PK - VE PRINCIPAL/DIRECTOR OFFICE 250 250 0 0 335

808 MATERIAL STORAGE 100 200 0 0 268

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 78: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:60 of 234 Report Date: 6/15/2015 11:49:17 AM

300

Total Stations: 200 Acres Required: 7

Total Capacity:

849 VOCATIONAL PROJECT STORAGE 310 620 0 0 830

840 VOCATIONAL RELATED CLASSROOM 680 1,360 20 0 1,822

808 MATERIAL STORAGE 100 100 0 0 134

1 262 09 - VE SMALL PUBLIC SERVICE LAB 800 800 20 20 1,072

808 MATERIAL STORAGE 100 200 0 0 268

806 REFERENCE 100 200 0 0 268

812 PROJECT STORAGE 150 300 0 0 402

810 MATERIAL STORAGE (LARGE) 395 790 0 0 1,058

1 270 09 - VE WORK EVALUATION LAB 1,110 1,110 15 0 1,487

853 VOCATIONAL TESTING 250 250 0 0 335

810 MATERIAL STORAGE (LARGE) 395 395 0 0 529

1 271 09 - VE VPI LAB 705 705 15 0 944

842 KITCHEN (HOME ECONOMICS) 125 125 0 0 167

808 MATERIAL STORAGE 100 100 0 0 134

852 VOCATIONAL TECHNOLOGY RESOURCE CENTER 800 800 0 0 1,072

843 LAUNDRY (HOME ECONOMICS) 50 50 0 0 67

4 212 09 - VE BUSINESS EDUCATION LAB 1,460 5,840 20 80 7,825

804 DISPENSARY 135 270 0 0 361

1 233 09 - VE MEDIUM HOME ECONOMICS LAB 1,380 1,380 20 20 1,849

808 MATERIAL STORAGE 100 400 0 0 536

1 244 09 - VE SMALL INDUSTRIAL LAB 1,100 1,100 20 20 1,474

812 PROJECT STORAGE 150 150 0 0 201

808 MATERIAL STORAGE 100 100 0 0 134

2 253 09 - VE MEDIUM HEALTH LAB 2,200 4,400 20 40 5,896

840 VOCATIONAL RELATED CLASSROOM 680 680 20 0 911

840 VOCATIONAL RELATED CLASSROOM 680 680 20 0 911

808 MATERIAL STORAGE 100 100 0 0 134

804 DISPENSARY 135 135 0 0 180

1 252 09 - VE SMALL HEALTH LAB 1,200 1,200 20 20 1,608

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

ADULT EDUCATION (AE - AE)

200

Gross Sq. Feet:

Utilization:

44,161

1.500

Level:

Page 79: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:61 of 234 Report Date: 6/15/2015 11:49:17 AM

1 315 PK - VE TEACHER PLANNING OFFICE 600 600 30 0 804

1 316 PK - VE TEACHER LOUNGE/DINING 120 120 30 0 160

1 330 PK - VE CUSTODIAL RECEIVING 450 450 30 0 603

1 381 PK - VE MEDIA TECHNICAL PROCESSING 120 120 30 0 160

1 309 PK - VE VAULT/STUDENT RECORDS 90 90 15 0 120

1 314 PK - VE ITINERANT OFFICE 125 125 0 0 167

1 341 PK - VE KITCHEN & SERVING AREA 1,320 1,320 30 0 1,768

1 371 06 - VE CONCESSIONS 200 200 1 0 268

1 380 PK - VE LIBRARY (READING ROOM/STACKS) 1,110 1,110 30 0 1,487

1 333 PK - VE FLAMMABLE STORAGE 155 155 0 0 207

1 334 PK - VE CUSTODIAL EQUIPMENT STORAGE 500 500 0 0 670

1 340 PK - VE DINING AREA 1,200 1,200 30 0 1,608

840 VOCATIONAL RELATED CLASSROOM 680 680 20 0 911

846 RECEPTION (VOC ED INSTRUCTION) 90 90 0 0 120

853 VOCATIONAL TESTING 250 250 0 0 335

1 306 PK - VE CONFERENCE ROOM 210 210 15 0 281

802 INSTRUCTIONAL CONFERENCE ROOM 225 225 0 0 301

808 MATERIAL STORAGE 100 100 0 0 134

1 303 PK - VE SECRETARIAL SPACE 158 158 0 0 211

1 304 PK - VE RECEPTION AREA 255 255 15 0 341

1 305 PK - VE PRODUCTION WORKROOM 120 120 15 0 160

1 300 PK - VE PRINCIPAL/DIRECTOR OFFICE 250 250 0 0 335

1 301 PK - VE ASSISTANT PRINCIPAL/OTHER OFFICE 175 175 0 0 234

1 302 PK - VE BOOKKEEPING OFFICE 125 125 0 0 167

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 80: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:62 of 234 Report Date: 6/15/2015 11:49:17 AM

102

Total Stations: 102 Acres Required: 7

Total Capacity:

1 64 PK - 12 E S E PT/OT LAB 475 475 5 0 636

816 STUDENT RESTROOM (FEMALE) 35 35 0 0 46

813 STUDENT STORAGE 40 40 0 0 53

808 MATERIAL STORAGE 100 100 0 0 134

1 63 PK - 12 E S E VOCATIONAL 1,140 1,140 12 12 1,527

817 STUDENT RESTROOM & BATH 110 880 0 0 1,179

815 STUDENT RESTROOM (MALE) 35 35 0 0 46

808 MATERIAL STORAGE 100 100 0 0 134

817 STUDENT RESTROOM & BATH 110 110 0 0 147

808 MATERIAL STORAGE 100 200 0 0 268

2 65 PK - 12 E S E RESOURCE 380 760 4 0 1,018

813 STUDENT STORAGE 40 80 0 0 107

1 55 PK - 05 MUSIC - ELEMENTARY 1,000 1,000 22 0 1,340

812 PROJECT STORAGE 150 150 0 0 201

808 MATERIAL STORAGE 100 100 0 0 134

806 REFERENCE 100 100 0 0 134

1 14 PK - 05 ELEMENTARY COVERED PLAY AREA 360 360 10 0 482

816 STUDENT RESTROOM (FEMALE) 35 280 0 0 375

808 MATERIAL STORAGE 100 100 0 0 134

1 50 PK - 05 ART - ELEMENTARY 1,000 1,000 22 0 1,340

831 MUSIC PRACTICE ROOM 70 70 0 0 93

808 MATERIAL STORAGE 100 800 0 0 1,072

8 62 PK - 12 E S E FULL-TIME 950 7,600 10 80 10,184

815 STUDENT RESTROOM (MALE) 35 280 0 0 375

813 STUDENT STORAGE 40 320 0 0 428

808 MATERIAL STORAGE 100 200 0 0 268

2 60 PK - PK E S E PRE-K 475 950 5 10 1,273

817 STUDENT RESTROOM & BATH 110 220 0 0 294

813 STUDENT STORAGE 40 80 0 0 107

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Target Number of Stations:

EXCEPTIONAL STUDENT (PK - 12)

102

Gross Sq. Feet:

Utilization:

30,718

1.000

Level:

Page 81: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:63 of 234 Report Date: 6/15/2015 11:49:17 AM

1 334 PK - VE CUSTODIAL EQUIPMENT STORAGE 500 500 0 0 670

1 333 PK - VE FLAMMABLE STORAGE 155 155 0 0 207

1 341 PK - VE KITCHEN & SERVING AREA 440 440 10 0 589

1 340 PK - VE DINING AREA 400 400 10 0 536

1 315 PK - VE TEACHER PLANNING OFFICE 200 200 10 0 268

1 388 PK - VE MEDIA COPYING ROOM 20 20 10 0 26

1 330 PK - VE CUSTODIAL RECEIVING 150 150 10 0 201

1 316 PK - VE TEACHER LOUNGE/DINING 40 40 10 0 53

1 385 PK - VE CLOSED CIRCUIT TV LAB 70 70 10 0 93

1 383 PK - VE AUDIO VISUAL STORAGE 60 60 10 0 80

1 387 PK - VE MEDIA PRODUCTION LAB 50 50 10 0 67

1 386 PK - VE CLOSED CIRCUIT STORAGE 50 50 10 0 67

1 368 PK - VE TEXTBOOK STORAGE 35 35 5 0 46

1 351 06 - 12 MIDDLE/SR HIGH COVERED PATIO 360 360 10 0 482

1 381 PK - VE MEDIA TECHNICAL PROCESSING 40 40 10 0 53

1 380 PK - VE LIBRARY (READING ROOM/STACKS) 370 370 10 0 495

2 70 PK - 12 E S E ITINERANT 200 400 4 0 536

808 MATERIAL STORAGE 100 100 0 0 134

1 300 PK - VE PRINCIPAL/DIRECTOR OFFICE 250 250 0 0 335

808 MATERIAL STORAGE 100 200 0 0 268

2 66 PK - 12 E S E SUPPLEMENTARY INSTRUCTION 100 200 2 0 268

1 309 PK - VE VAULT/STUDENT RECORDS 30 30 5 0 40

1 69 PK - 12 E S E AUDIOLOGY LAB 250 250 0 0 335

808 MATERIAL STORAGE 100 200 0 0 268

2 306 PK - VE CONFERENCE ROOM 70 140 5 0 187

1 305 PK - VE PRODUCTION WORKROOM 40 40 5 0 53

1 308 PK - VE GENERAL SCHOOL STORAGE 50 50 5 0 67

1 307 PK - VE CLINIC 30 30 5 0 40

1 302 PK - VE BOOKKEEPING OFFICE 125 125 0 0 167

1 301 PK - VE ASSISTANT PRINCIPAL/OTHER OFFICE 175 175 0 0 234

1 304 PK - VE RECEPTION AREA 85 85 5 0 113

1 303 PK - VE SECRETARIAL SPACE 158 158 0 0 211

Spaces Design Grades Description NSF / Space

Total NSF

Cap. / Space

Total Stns.

Total GSF

Page 82: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:64 of 234 Report Date: 6/15/2015 11:49:17 AM

Section 3: Recommendations

Page 83: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:65 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: 520 BUS COMPOUND

Address: 2091 W KING STREET (SR 50), COCOA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use WAREHOUSE WAREHOUSE

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $1,082,676

$0 $0 $0 $0 $0 $1,082,676 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems to the entire facility 520 BUS COMPOUND.

82,940 0 $1,082,676 $13 $0

520 BUS COMPOUND Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 84: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:66 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: ANDREW JACKSON MIDDLE

Address: 1515 KNOX MCRAE DRIVE, TITUSVILLE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 8 GRADE 8

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use MIDDLE MIDDLE

School Capacity 654 654

Utilization Factor 90% 90%

Survey AnnotationOther = fencing & security $42,013 &Site Improvement – Deferred infrastructure improvements as described in 1013.01(22)$290,966

COFTE Student Membership 541 531

Total Stations 727 0 727

Perm. Stations 727 0 727

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $3,566,238

$0 $0 $0 $412,979 $0 $3,153,259 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility ANDREW JACKSON MIDDLE.

107,661 0 $3,153,259 $29 $0

ANDREW JACKSON MIDDLE

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 85: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:67 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: APOLLO ELEMENTARY

Address: 3085 KNOX MCRAE DRIVE, TITUSVILLE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 902 902

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & securityRemodel to expand multipurpose/diningNew media centerNew Covered Play

COFTE Student Membership 802 702

Total Stations 902 0 902

Perm. Stations 902 0 902

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $5,404,779

$0 $0 $0 $116,404 $905,028 $2,109,611 $2,273,736

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2019 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (3247 NSF)

3,562 0 $751,582 $211 $0

APOLLO ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 86: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:68 of 234 Report Date: 6/15/2015 11:49:17 AM

Remodeling 2020 4 1 Removed NSF (8538), Added NSF (8534), Difference NSF (4), Percent (0.05%), Removed Stations (0), Added Stations (0) Remodeling: Adding 1 unit of DINING AREA (3318 NSF), 1 unit of KITCHEN CHAIR STORAGE (151 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2337 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (151 NSF), 1 unit of STAGE (990 NSF), 1 unit of STAGE STORAGE (377 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (180 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (180 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF), 1 unit of INSIDE CIRCULATION (750 NSF) and Removing Room 001 (1352 NSF), Room 045 (3018 NSF), Room 045A (311 NSF), Room 045B (171 NSF), Room 045C (133 NSF), Room 046 (2990 NSF), Room 046A (36 NSF), Room 046B (527 NSF)

-8,538 0 $905,028 $106 $0

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility APOLLO ELEMENTARY.

96,896 0 $2,109,611 $22 $0

New Construction 2020 New Construction: Adding 1 unit of LIBRARY (READING ROOM/STACKS) (3337 NSF), 1 unit of MEDIA TECHNICAL PROCESSING (361 NSF), 1 unit of PROFESSIONAL LIBRARY (361 NSF), 1 unit of AUDIO VISUAL STORAGE (541 NSF), 1 unit of PERIODICAL STORAGE (180 NSF), 1 unit of CLOSED CIRCUIT TV LAB (631 NSF), 1 unit of CLOSED CIRCUIT STORAGE (451 NSF), 1 unit of MEDIA PRODUCTION LAB (451 NSF), 1 unit of MEDIA COPYING ROOM (180 NSF), 1 unit of MEDIA SMALL GROUP ROOM (180 NSF), 1 unit of MEDIA GROUP PROJECTS/INSTRUCTION (451 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (90 NSF)

7,214 0 $1,522,154 $211 $0

APOLLO ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 87: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:69 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: ASTRONAUT SENIOR HIGH

Address: 800 WAR EAGLE BOULEVARD, TITUSVILLE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 9 GRADE 9

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use SENIOR HIGH SENIOR HIGH

School Capacity 1,445 1445

Utilization Factor 95% 95%

Survey Annotation Other = fencing & security

COFTE Student Membership 1,058 727

Total Stations 1,522 0 1522

Perm. Stations 1,522 0 1522

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $1,437,044

$0 $0 $0 $61,932 $0 $1,375,112 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility ASTRONAUT SENIOR HIGH.

244,150 0 $1,375,112 $6 $0

ASTRONAUT SENIOR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 88: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:70 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: ATLANTIS ELEMENTARY

Address: 7300 BRIGGS AVENUE, COCOA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 703 703

Utilization Factor 100% 100%

Survey Annotation Other = fencing & securityExpand dining/multipurpose

COFTE Student Membership 564 484

Total Stations 703 0 703

Perm. Stations 703 0 703

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $2,539,312

$0 $0 $0 $182,921 $0 $1,932,703 $423,688

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (141 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (1726 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (141 NSF)

2,008 0 $423,688 $211 $0

ATLANTIS ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 89: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:71 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility ATLANTIS ELEMENTARY.

115,456 0 $1,932,703 $17 $0

ATLANTIS ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 90: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:72 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: AUDUBON ELEMENTARY

Address: 1201 N BANANA RIVER DRIVE, MERRITT ISLAND

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 761 761

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & securityExpand multipurpose/diningExpand mediaExpand covered PE/storage

COFTE Student Membership 652 572

Total Stations 761 0 761

Perm. Stations 761 0 761

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $3,851,478

$0 $0 $0 $21,865 $0 $2,119,669 $1,709,944

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2019 New Construction: Adding 1 unit of MULTIPURPOSE ROOM (DINING) (2255 NSF)

2,255 0 $475,805 $211 $0

AUDUBON ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 91: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:73 of 234 Report Date: 6/15/2015 11:49:17 AM

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (1540 NSF)

1,855 0 $391,405 $211 $0

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility AUDUBON ELEMENTARY.

87,512 0 $2,119,669 $24 $0

New Construction 2020 New Construction: Adding 1 unit of LIBRARY (READING ROOM/STACKS) (1033 NSF), 1 unit of MEDIA TECHNICAL PROCESSING (304 NSF), 1 unit of PROFESSIONAL LIBRARY (304 NSF), 1 unit of AUDIO VISUAL STORAGE (297 NSF), 1 unit of PERIODICAL STORAGE (152 NSF), 1 unit of CLOSED CIRCUIT TV LAB (533 NSF), 1 unit of CLOSED CIRCUIT STORAGE (381 NSF), 1 unit of MEDIA PRODUCTION LAB (381 NSF), 1 unit of MEDIA COPYING ROOM (152 NSF), 1 unit of MEDIA GROUP PROJECTS/INSTRUCTION (381 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (76 NSF)

3,994 0 $842,734 $211 $0

AUDUBON ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 92: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:74 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: BAYSIDE SENIOR HIGH

Address: 1901 DEGROODT ROAD SW, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 9 GRADE 9

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use SENIOR HIGH SENIOR HIGH

School Capacity 2,235 2235

Utilization Factor 95% 95%

Survey Annotation Other = fencing & security

COFTE Student Membership 1,304 1,070

Total Stations 2,353 0 2353

Perm. Stations 2,353 0 2353

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $2,567,195

$0 $0 $0 $87,586 $0 $2,479,609 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility BAYSIDE SENIOR HIGH.

355,489 0 $2,479,609 $7 $0

BAYSIDE SENIOR HIGH Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 93: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:75 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: BEACHSIDE OFFICE

Address: 331 RAMP ROAD, COCOA BEACH

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use COUNTY ADMINISTRATION COUNTY ADMINISTRATION

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $0

$0 $0 $0 $0 $0 $0 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

BEACHSIDE OFFICE Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 94: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:76 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: CAMBRIDGE ELEMENTARY MAGNET

Address: 2000 CAMBRIDGE DRIVE, COCOA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 765 765

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & securityExpand AdministrationExpand Multipurpose DiningExpand Media

COFTE Student Membership 559 528

Total Stations 765 0 765

Perm. Stations 649 0 649

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 116 0 116

Estimated Total Project Cost $2,558,147

$0 $0 $0 $224,461 $0 $341,424 $1,992,262

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 95: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:77 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility CAMBRIDGE ELEMENTARY MAGNET.

84,496 0 $341,424 $4 $0

New Construction 2020 New Construction: Adding 1 unit of MEDIA TECHNICAL PROCESSING (306 NSF), 1 unit of PROFESSIONAL LIBRARY (306 NSF), 1 unit of AUDIO VISUAL STORAGE (254 NSF), 1 unit of PERIODICAL STORAGE (153 NSF), 1 unit of CLOSED CIRCUIT TV LAB (536 NSF), 1 unit of CLOSED CIRCUIT STORAGE (383 NSF), 1 unit of MEDIA PRODUCTION LAB (383 NSF), 1 unit of MEDIA COPYING ROOM (153 NSF), 1 unit of MEDIA SMALL GROUP ROOM (153 NSF), 1 unit of MEDIA GROUP PROJECTS/INSTRUCTION (383 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (153 NSF)

3,163 0 $667,393 $211 $0

New Construction 2020 New Construction: Adding 1 unit of DINING AREA (919 NSF), 1 unit of KITCHEN CHAIR STORAGE (153 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2372 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (153 NSF)

3,597 0 $758,967 $211 $0

New Construction 2020 New Construction: Adding 1 unit of BOOKKEEPING OFFICE (125 NSF), 1 unit of SECRETARIAL SPACE (158 NSF), 1 unit of RECEPTION AREA (650 NSF), 1 unit of CONFERENCE ROOM (206 NSF), 1 unit of GENERAL SCHOOL STORAGE (241 NSF), 1 unit of STUDENT ACTIVITIES (383 NSF), 1 unit of COMPUTER AREA (115 NSF), 1 unit of CAREERS ROOM (230 NSF), 1 unit of TEACHER LOUNGE/DINING (306 NSF), 1 unit of TEXTBOOK STORAGE (268 NSF)

2,682 0 $565,902 $211 $0

CAMBRIDGE ELEMENTARY MAGNET

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 96: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:78 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: CAPE VIEW ELEMENTARY

Address: 8440 N ROSALIND AVENUE, CAPE CANAVERAL

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 548 548

Utilization Factor 100% 100%

Survey Annotation Other = fencing & securityAdd music & Covered Play

COFTE Student Membership 328 449

Total Stations 548 0 548

Perm. Stations 548 0 548

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $2,303,348

$0 $0 $0 $15,949 $0 $1,804,631 $482,768

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (1973 NSF)

2,288 0 $482,768 $211 $0

CAPE VIEW ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 97: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:79 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility CAPE VIEW ELEMENTARY.

63,934 0 $1,804,631 $28 $0

CAPE VIEW ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 98: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:80 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: CENTRAL MIDDLE

Address: 2600 WINGATE BOULEVARD, WEST MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 8 GRADE 8

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use MIDDLE MIDDLE

School Capacity 1,524 1524

Utilization Factor 90% 90%

Survey Annotation Other = fencing & security

COFTE Student Membership 1,264 1,147

Total Stations 1,694 0 1694

Perm. Stations 1,694 0 1694

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $1,715,821

$0 $0 $0 $56,797 $0 $1,659,024 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Bell/Fire Alarm Systems to the entire facility CENTRAL MIDDLE.

225,379 0 $1,659,024 $7 $0

CENTRAL MIDDLE Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 99: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:81 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: CHALLENGER 7 ELEMENTARY

Address: 6135 RENA DRIVE, COCOA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 551 551

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 495 410

Total Stations 551 0 551

Perm. Stations 551 0 551

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $638,801

$0 $0 $0 $97,722 $0 $541,079 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility CHALLENGER 7 ELEMENTARY.

107,816 0 $541,079 $5 $0

CHALLENGER 7 ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 100: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:82 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: CHRISTA MCAULIFFE ELEMENTARY

Address: 155 DEL MUNDO AVENUE NW, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 918 864

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & security

Add multipurpose & related spacesExpand administrationAdd covered PE & storage

COFTE Student Membership 736 707

Total Stations 918 -54 864

Perm. Stations 754 0 754

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 164 -54 110

Estimated Total Project Cost $2,704,448

$0 $0 $0 $214,547 $30,000 $1,001,680 $1,458,221

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 101: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:83 of 234 Report Date: 6/15/2015 11:49:17 AM

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (151 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2337 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (151 NSF)

2,639 0 $556,829 $211 $0

Remodeling 2018 43 99 Removed NSF (1923), Added NSF (0), Difference NSF (1923), Percent (100%), Removed Stations (54), Added Stations (0) Remodeling: Removing Room N915 (683 NSF), Room T021 (620 NSF), Room T023 (620 NSF)

-1,923 -54 $30,000 $16 $0

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility CHRISTA MCAULIFFE ELEMENTARY.

128,535 0 $1,001,680 $8 $0

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (2714 NSF)

3,029 0 $639,119 $211 $0

New Construction 2020 New Construction: Adding 1 unit of PRODUCTION WORKROOM (301 NSF), 1 unit of VAULT/STUDENT RECORDS (226 NSF), 1 unit of STUDENT ACTIVITIES (377 NSF), 1 unit of COMPUTER AREA (113 NSF), 1 unit of CAREERS ROOM (226 NSF)

1,243 0 $262,273 $211 $0

CHRISTA MCAULIFFE ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 102: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:84 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: CLEARLAKE EDUCATION CENTER

Address: 1225 CLEARLAKE ROAD, COCOA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade ADULT EDUCATION ADULT EDUCATION

High Grade ADULT EDUCATION ADULT EDUCATION

Comments

Existing Recommended

Capital Outlay Classification

2 - SCHOOL CONDITIONALLY RECOMMENDED FOR CONTINUED USE

2 - SCHOOL CONDITIONALLY RECOMMENDED FOR CONTINUED USE

Facility Use VACANT ADULT EDUCATION

School Capacity 0 1120

Utilization Factor 0% 150%

Survey Annotation Other = fencing & security

COFTE Student Membership 0 0

Total Stations 747 0 747

Perm. Stations 747 0 747

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $1,429,417

$0 $0 $0 $31,165 $0 $1,398,252 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility CLEARLAKE EDUCATION CENTER.

101,611 0 $1,398,252 $14 $0

CLEARLAKE EDUCATION CENTER

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 103: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:85 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: COCOA BEACH JR/SR HIGH

Address: 1500 MINUTEMAN CAUSEWAY, COCOA BEACH

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use COMBINATION COMBINATION

School Capacity 1,465 1442

Utilization Factor 90% 90%

Survey Annotation Other = fencing & securityRemodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.

COFTE Student Membership 1,105 1,105

Total Stations 1,628 -25 1603

Perm. Stations 1,253 0 1253

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 375 -25 350

Estimated Total Project Cost $2,070,796

$0 $0 $0 $409,666 $10,000 $1,651,130 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Remodeling 2018 65 99 Removed NSF (683), Added NSF (0), Difference NSF (683), Percent (100%), Removed Stations (25), Added Stations (0) Remodeling: Removing Room N172 (683 NSF)

-683 -25 $10,000 $15 $0

COCOA BEACH JR/SR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 104: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:86 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility COCOA BEACH JR/SR HIGH.

223,966 0 $1,651,130 $7 $0

COCOA BEACH JR/SR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 105: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:87 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: COCOA JR/SR HIGH

Address: 2000 TIGER TRAIL, COCOA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use COMBINATION COMBINATION

School Capacity 1,737 1737

Utilization Factor 90% 90%

Survey Annotation Other = fencing & security

COFTE Student Membership 1,273 1,647

Total Stations 1,930 0 1930

Perm. Stations 1,730 0 1730

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 200 0 200

Estimated Total Project Cost $5,092,043

$0 $0 $0 $240,299 $0 $4,851,744 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility COCOA JR/SR HIGH.

281,489 0 $4,851,744 $17 $0

COCOA JR/SR HIGH Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 106: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:88 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: COLUMBIA ELEMENTARY

Address: 1225 WACO BOULEVARD SE, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 751 751

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 587 464

Total Stations 751 0 751

Perm. Stations 685 0 685

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 66 0 66

Estimated Total Project Cost $463,042

$0 $0 $0 $199,460 $0 $263,582 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Retrofit for Technology to the entire facility COLUMBIA ELEMENTARY.

116,966 0 $263,582 $2 $0

COLUMBIA ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 107: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:89 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: COQUINA ELEMENTARY

Address: 850 KNOX MCRAE DRIVE, TITUSVILLE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 693 693

Utilization Factor 100% 100%

Survey AnnotationOther = fencing & securityExpand multipurpose/diningExpand covered play and add PE Storage

COFTE Student Membership 558 516

Total Stations 693 0 693

Perm. Stations 627 0 627

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 66 0 66

Estimated Total Project Cost $2,556,853

$0 $0 $0 $87,361 $0 $1,703,351 $766,141

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 108: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:90 of 234 Report Date: 6/15/2015 11:49:17 AM

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (995 NSF)

1,310 0 $276,410 $211 $0

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility COQUINA ELEMENTARY.

80,440 0 $1,703,351 $21 $0

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (139 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (725 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (139 NSF), 1 unit of STAGE (454 NSF), 1 unit of STAGE STORAGE (347 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (139 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (139 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (139 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF)

2,321 0 $489,731 $211 $0

COQUINA ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 109: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:91 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: CROTON ELEMENTARY

Address: 1449 CROTON ROAD, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 795 795

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security $86,395 and Site Improvement – Deferred infrastructure improvements as described in 1013.01(22 $103246

COFTE Student Membership 645 571

Total Stations 795 0 795

Perm. Stations 707 0 707

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 88 0 88

Estimated Total Project Cost $2,023,997

$0 $0 $0 $288,841 $0 $1,735,156 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility CROTON ELEMENTARY.

70,895 0 $1,735,156 $24 $0

CROTON ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 110: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:92 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: CUYLER SCHOOL

Address: 2327 HARRY T MOORE AVENUE, MIMS

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

3 - SCHOOL NOT RECOMMENDED FOR CONTINUED USE

3 - SCHOOL NOT RECOMMENDED FOR CONTINUED USE

Facility Use VACANT EXCEPTIONAL STUDENT

School Capacity 0 98

Utilization Factor 0% 100%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 98 0 98

Perm. Stations 98 0 98

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $0

$0 $0 $0 $0 $0 $0 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

CUYLER SCHOOL Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 111: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:93 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: DELAURA MIDDLE

Address: 300 JACKSON AVENUE, SATELLITE BEACH

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 8 GRADE 8

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use MIDDLE MIDDLE

School Capacity 961 961

Utilization Factor 90% 90%

Survey Annotation Other = fencing & security $68,261, Site Improvement – Deferred infrastructure improvements as described in 1013.01(22) $187,720

COFTE Student Membership 739 682

Total Stations 1,068 0 1068

Perm. Stations 1,068 0 1068

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $3,062,604

$0 $0 $0 $255,981 $0 $2,806,623 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility DELAURA MIDDLE.

111,303 0 $2,806,623 $25 $0

DELAURA MIDDLE Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 112: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:94 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: DISCOVERY ELEMENTARY

Address: 1275 GLENDALE AVENUE NW, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 980 980

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security $67,798 Site Utilities $309,738Expand Multipurpose

COFTE Student Membership 680 603

Total Stations 980 0 980

Perm. Stations 826 0 826

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 154 0 154

Estimated Total Project Cost $3,400,317

$0 $0 $0 $689,536 $0 $2,125,256 $585,525

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (196 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2383 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (196 NSF)

2,775 0 $585,525 $211 $0

DISCOVERY ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 113: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:95 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility DISCOVERY ELEMENTARY.

146,005 0 $2,125,256 $15 $0

DISCOVERY ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 114: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:96 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: DR W J CREEL ELEMENTARY

Address: 2000 GLENWOOD DRIVE, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 1,154 1154

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security $71,449 and site utilities $197106Expand media

COFTE Student Membership 897 922

Total Stations 1,154 0 1154

Perm. Stations 1,088 0 1088

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 66 0 66

Estimated Total Project Cost $2,872,950

$0 $0 $0 $396,555 $0 $1,794,654 $681,741

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 115: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:97 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility DR W J CREEL ELEMENTARY.

113,473 0 $1,794,654 $16 $0

New Construction 2020 New Construction: Adding 1 unit of AUDIO VISUAL STORAGE (692 NSF), 1 unit of PERIODICAL STORAGE (231 NSF), 1 unit of CLOSED CIRCUIT TV LAB (808 NSF), 1 unit of CLOSED CIRCUIT STORAGE (577 NSF), 1 unit of MEDIA PRODUCTION LAB (577 NSF), 1 unit of MEDIA COPYING ROOM (231 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (115 NSF)

3,231 0 $681,741 $211 $0

DR W J CREEL ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 116: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:98 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: EAU GALLIE SENIOR HIGH

Address: 1400 COMMODORE BOULEVARD, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 9 GRADE 9

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use SENIOR HIGH SENIOR HIGH

School Capacity 2,185 2185

Utilization Factor 95% 95%

Survey Annotation Other = fencing & security $82,083Expand dining

COFTE Student Membership 1,539 1,500

Total Stations 2,300 0 2300

Perm. Stations 2,050 0 2050

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 250 0 250

Estimated Total Project Cost $3,021,872

$0 $0 $0 $434,083 $0 $1,860,036 $727,753

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Electrical, Plumbing, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility EAU GALLIE SENIOR HIGH.

309,632 0 $1,860,036 $6 $0

New Construction 2020 New Construction: Adding 1 unit of DINING AREA (3293 NSF)

3,293 0 $727,753 $221 $0

EAU GALLIE SENIOR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 117: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:99 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: EDGEWOOD JR/ SR HIGH

Address: 180 E MERRITT AVENUE, MERRITT ISLAND

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use COMBINATION COMBINATION

School Capacity 1,071 1071

Utilization Factor 90% 90%

Survey Annotation Other = fencing & security

COFTE Student Membership 823 822

Total Stations 1,191 0 1191

Perm. Stations 1,100 0 1100

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 91 0 91

Estimated Total Project Cost $634,404

$0 $0 $0 $369,818 $0 $264,586 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility EDGEWOOD JR/ SR HIGH.

149,359 0 $264,586 $2 $0

EDGEWOOD JR/ SR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 118: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:100 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: EDUCATIONAL SERVICES FACILITY

Address: 2700 JUDGE FRAN JAMIESON WAY, VIERA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use COUNTY ADMINISTRATION COUNTY ADMINISTRATION

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

Recommendation to Surplus and offer for sale:Parcel 93 - Madden Avenue - 16 acresParcel 131 - Huntington Lane - 5 acresBoard resolution dated 6/9/2015 declared these parcels no longer necessary for educationaluse.

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $1,723,069

$0 $0 $0 $0 $0 $1,723,069 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, HVAC Systems to the entire facility EDUCATIONAL SERVICES FACILITY.

168,450 0 $1,723,069 $10 $0

EDUCATIONAL SERVICES FACILITY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 119: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:101 of 234 Report Date: 6/15/2015 11:49:17 AM

Page 120: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:102 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: ENDEAVOUR ELEMENTARY MAGNET

Address: 905 PINEDA STREET, COCOA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 990 968

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & securityRemodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.Expand administration.Expand media.Expand multipurpose/dining

Add Covered Play

COFTE Student Membership 706 829

Total Stations 990 -22 968

Perm. Stations 852 0 852

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 138 -22 116

Estimated Total Project Cost $3,884,495

$0 $0 $0 $205,480 $10,000 $980,031 $2,688,984

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 121: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:103 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Painting, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility ENDEAVOUR ELEMENTARY MAGNET.

92,140 0 $980,031 $11 $0

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (3067 NSF)

3,382 0 $713,602 $211 $0

Remodeling 2018 22 99 Removed NSF (620), Added NSF (0), Difference NSF (620), Percent (100%), Removed Stations (22), Added Stations (0) Remodeling: Removing Room T018 (620 NSF)

-620 -22 $10,000 $16 $0

New Construction 2020 New Construction: Adding 1 unit of LIBRARY (READING ROOM/STACKS) (1595 NSF), 1 unit of MEDIA TECHNICAL PROCESSING (387 NSF), 1 unit of PROFESSIONAL LIBRARY (341 NSF), 1 unit of AUDIO VISUAL STORAGE (175 NSF), 1 unit of PERIODICAL STORAGE (170 NSF), 1 unit of CLOSED CIRCUIT TV LAB (596 NSF), 1 unit of CLOSED CIRCUIT STORAGE (426 NSF), 1 unit of MEDIA PRODUCTION LAB (426 NSF), 1 unit of MEDIA COPYING ROOM (170 NSF), 1 unit of MEDIA SMALL GROUP ROOM (170 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (85 NSF)

4,541 0 $958,151 $211 $0

New Construction 2020 New Construction: Adding 1 unit of RECEPTION AREA (490 NSF), 1 unit of VAULT/STUDENT RECORDS (256 NSF), 1 unit of COMPUTER AREA (127 NSF), 1 unit of CAREERS ROOM (256 NSF), 1 unit of ITINERANT OFFICE (125 NSF)

1,254 0 $264,594 $211 $0

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (170 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2275 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (170 NSF), 1 unit of STAGE STORAGE (426 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (213 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (213 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF)

3,567 0 $752,637 $211 $0

ENDEAVOUR ELEMENTARY MAGNET

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 122: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:104 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: ENTERPRISE ELEMENTARY

Address: 7000 ENTERPRISE ROAD, COCOA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 729 729

Utilization Factor 100% 100%

Survey Annotation Other = fencing & securityExpand multipurpose/dining

COFTE Student Membership 556 374

Total Stations 729 0 729

Perm. Stations 707 0 707

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 22 0 22

Estimated Total Project Cost $1,263,491

$0 $0 $0 $105,196 $0 $703,379 $454,916

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (146 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (1864 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (146 NSF)

2,156 0 $454,916 $211 $0

ENTERPRISE ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 123: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:105 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Retrofit for Technology to the entire facility ENTERPRISE ELEMENTARY.

115,880 0 $703,379 $6 $0

ENTERPRISE ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 124: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:106 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: FAIRGLEN ELEMENTARY

Address: 201 INDIAN TRAIL, COCOA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 753 753

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 685 606

Total Stations 753 0 753

Perm. Stations 753 0 753

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $3,249,654

$0 $0 $0 $30,168 $0 $3,219,486 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Retrofit for Technology to the entire facility FAIRGLEN ELEMENTARY.

99,720 0 $3,219,486 $32 $0

FAIRGLEN ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 125: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:107 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: FREEDOM 7 ELEMENTARY SCHOOL OF INTERNATIONAL STUDIES

Address: 400 4TH STREET, COCOA BEACH

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 475 475

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & securityExpand AdministrationAdd stage & related spacesAdd covered play

COFTE Student Membership 402 402

Total Stations 475 0 475

Perm. Stations 453 0 453

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 22 0 22

Estimated Total Project Cost $1,233,103

$0 $0 $0 $134,341 $0 $197,581 $901,181

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (1710 NSF)

2,025 0 $427,275 $211 $0

FREEDOM 7 ELEMENTARY SCHOOL OF INTERNATIONAL STUDIES

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 126: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:108 of 234 Report Date: 6/15/2015 11:49:17 AM

New Construction 2020 New Construction: Adding 1 unit of STAGE (990 NSF), 1 unit of STAGE STORAGE (238 NSF), 1 unit of STAGE STORAGE (238 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (115 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (115 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF)

1,796 0 $378,956 $211 $0

Renovation 2016 Renovating: Apply Painting, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility FREEDOM 7 ELEMENTARY SCHOOL OF INTERNATIONAL STUDIES.

50,606 0 $197,581 $4 $0

New Construction 2020 New Construction: Adding 1 unit of GENERAL SCHOOL STORAGE (237 NSF), 1 unit of VAULT/STUDENT RECORDS (142 NSF), 1 unit of COMPUTER AREA (71 NSF)

450 0 $94,950 $211 $0

FREEDOM 7 ELEMENTARY SCHOOL OF INTERNATIONAL STUDIES

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 127: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:109 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: GARDENDALE EDUCATION CENTER

Address: 301 GROVE BOULEVARD, MERRITT ISLAND

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

3 - SCHOOL NOT RECOMMENDED FOR CONTINUED USE

3 - SCHOOL NOT RECOMMENDED FOR CONTINUED USE

Facility Use VACANT ELEMENTARY

School Capacity 0 681

Utilization Factor 0% 100%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 681 0 681

Perm. Stations 681 0 681

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $0

$0 $0 $0 $0 $0 $0 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

GARDENDALE EDUCATION CENTER

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 128: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:110 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: GEMINI ELEMENTARY

Address: 2100 S OAK STREET, MELBOURNE BEACH

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 711 711

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 505 393

Total Stations 711 0 711

Perm. Stations 667 0 667

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 44 0 44

Estimated Total Project Cost $927,677

$0 $0 $0 $180,830 $0 $746,847 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility GEMINI ELEMENTARY.

80,054 0 $746,847 $9 $0

GEMINI ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 129: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:111 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: GIBSON PARK

Address: Gibson Field Sycamore St, Titusville

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use MULTIPLE USE SUPPORT MULTIPLE USE SUPPORT

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $0

$0 $0 $0 $0 $0 $0 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

GIBSON PARK Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 130: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:112 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: GOLFVIEW ELEMENTARY MAGNET

Address: 1530 S FISKE BOULEVARD, ROCKLEDGE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 777 777

Utilization Factor 100% 100%

Survey Annotation Other = fencing & securityExpand Administration & Media

COFTE Student Membership 612 659

Total Stations 777 0 777

Perm. Stations 689 0 689

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 88 0 88

Estimated Total Project Cost $1,864,289

$0 $0 $0 $200,055 $0 $747,650 $916,584

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 131: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:113 of 234 Report Date: 6/15/2015 11:49:17 AM

New Construction 2020 New Construction: Adding 1 unit of MEDIA TECHNICAL PROCESSING (164 NSF), 1 unit of PROFESSIONAL LIBRARY (275 NSF), 1 unit of PERIODICAL STORAGE (138 NSF), 1 unit of CLOSED CIRCUIT TV LAB (482 NSF), 1 unit of CLOSED CIRCUIT STORAGE (344 NSF), 1 unit of MEDIA PRODUCTION LAB (344 NSF), 1 unit of MEDIA COPYING ROOM (138 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (68 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (138 NSF)

2,091 0 $441,201 $211 $0

Renovation 2016 Renovating: Apply Painting, HVAC Systems, Retrofit for Technology to the entire facility GOLFVIEW ELEMENTARY MAGNET.

86,805 0 $747,650 $9 $0

New Construction 2020 New Construction: Adding 1 unit of BOOKKEEPING OFFICE (125 NSF), 1 unit of RECEPTION AREA (586 NSF), 1 unit of CLINIC (167 NSF), 1 unit of GENERAL SCHOOL STORAGE (137 NSF), 1 unit of SCHOOL STORE (69 NSF), 1 unit of STUDENT ACTIVITIES (344 NSF), 1 unit of COMPUTER AREA (103 NSF), 1 unit of CAREERS ROOM (206 NSF), 1 unit of TEACHER LOUNGE/DINING (275 NSF), 1 unit of TEXTBOOK STORAGE (241 NSF)

2,253 0 $475,383 $211 $0

GOLFVIEW ELEMENTARY MAGNET

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 132: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:114 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: HANS CHRISTIAN ANDERSEN ELEMENTARY

Address: 3011 S FISKE BOULEVARD, ROCKLEDGE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 884 840

Utilization Factor 100% 100%

Survey Annotation Other = fencing & securityRemodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.

COFTE Student Membership 752 723

Total Stations 884 -44 840

Perm. Stations 840 0 840

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 44 -44 0

Estimated Total Project Cost $3,897,385

$0 $0 $0 $182,389 $20,000 $3,694,996 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Remodeling 2018 30 99 Removed NSF (1366), Added NSF (0), Difference NSF (1366), Percent (100%), Removed Stations (44), Added Stations (0) Remodeling: Removing Room N129 (683 NSF), Room N223 (683 NSF)

-1,366 -44 $20,000 $15 $0

HANS CHRISTIAN ANDERSEN ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 133: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:115 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility HANS CHRISTIAN ANDERSEN ELEMENTARY.

107,083 0 $3,694,996 $35 $0

HANS CHRISTIAN ANDERSEN ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 134: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:116 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: HARBOR CITY ELEMENTARY

Address: 1377 SARNO ROAD, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 629 585

Utilization Factor 100% 100%

Survey Annotation Other = fencing & securityRemodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.

COFTE Student Membership 405 339

Total Stations 629 -44 585

Perm. Stations 453 0 453

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 176 -44 132

Estimated Total Project Cost $1,135,279

$0 $0 $0 $153,721 $20,000 $961,558 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Remodeling 2018 51 99 Removed NSF (1456), Added NSF (0), Difference NSF (1456), Percent (100%), Removed Stations (44), Added Stations (0) Remodeling: Removing Room N902 (665 NSF), Room T109 (735 NSF), Room T109A (56 NSF)

-1,456 -44 $20,000 $14 $0

HARBOR CITY ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 135: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:117 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility HARBOR CITY ELEMENTARY.

62,615 0 $961,558 $15 $0

HARBOR CITY ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 136: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:118 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: HERBERT C HOOVER MIDDLE

Address: 2000 HAWK HAVEN DRIVE, INDIALANTIC

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 8 GRADE 8

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use MIDDLE MIDDLE

School Capacity 658 658

Utilization Factor 90% 90%

Survey Annotation Other = fencing & securityAdd multipurpose & Stage related spaces

COFTE Student Membership 550 491

Total Stations 732 0 732

Perm. Stations 732 0 732

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $4,211,728

$0 $0 $0 $85,625 $0 $3,549,476 $576,627

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 137: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:119 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility HERBERT C HOOVER MIDDLE.

104,230 0 $3,549,476 $34 $0

New Construction 2020 New Construction: Adding 1 unit of MULTIPURPOSE ROOM (DINING) (1961 NSF), 1 unit of STAGE STORAGE (242 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (165 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (165 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF)

2,633 0 $576,627 $219 $0

HERBERT C HOOVER MIDDLE

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 138: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:120 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: HERITAGE HIGH

Address: 2353 WEST MALABAR RD, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 9 GRADE 9

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use SENIOR HIGH SENIOR HIGH

School Capacity 2,314 2314

Utilization Factor 95% 95%

Survey Annotation Other = fencing & security

COFTE Student Membership 1,709 1,275

Total Stations 2,436 0 2436

Perm. Stations 2,436 0 2436

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $665,313

$0 $0 $0 $93,029 $0 $572,284 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply HVAC Systems, Retrofit for Technology to the entire facility HERITAGE HIGH.

370,006 0 $572,284 $2 $0

HERITAGE HIGH Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 139: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:121 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: IMPERIAL ESTATES ELEMENTARY

Address: 900 IMPERIAL ESTATE LANE, TITUSVILLE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 729 729

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security $27,125 Site Utilities $31,840Add multipurpose/chair storage

COFTE Student Membership 638 548

Total Stations 729 0 729

Perm. Stations 729 0 729

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $1,732,949

$0 $0 $0 $58,965 $0 $1,135,512 $538,472

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (146 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2260 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (146 NSF)

2,552 0 $538,472 $211 $0

IMPERIAL ESTATES ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 140: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:122 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility IMPERIAL ESTATES ELEMENTARY.

107,927 0 $1,135,512 $11 $0

IMPERIAL ESTATES ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 141: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:123 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: INDIALANTIC ELEMENTARY

Address: 1050 N PALM AVENUE, INDIALANTIC

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 798 798

Utilization Factor 100% 100%

Survey AnnotationOther = fencing & security $29,317, Site Utilities $43,320

Expand media

COFTE Student Membership 747 631

Total Stations 798 0 798

Perm. Stations 754 0 754

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 44 0 44

Estimated Total Project Cost $1,823,969

$0 $0 $0 $136,637 $0 $1,111,302 $576,030

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 142: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:124 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility INDIALANTIC ELEMENTARY.

97,586 0 $1,111,302 $11 $0

New Construction 2020 New Construction: Adding 1 unit of MEDIA TECHNICAL PROCESSING (320 NSF), 1 unit of PROFESSIONAL LIBRARY (301 NSF), 1 unit of AUDIO VISUAL STORAGE (452 NSF), 1 unit of PERIODICAL STORAGE (151 NSF), 1 unit of CLOSED CIRCUIT STORAGE (377 NSF), 1 unit of MEDIA PRODUCTION LAB (377 NSF), 1 unit of MEDIA COPYING ROOM (150 NSF), 1 unit of MEDIA SMALL GROUP ROOM (150 NSF), 1 unit of MEDIA GROUP PROJECTS/INSTRUCTION (377 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (75 NSF)

2,730 0 $576,030 $211 $0

INDIALANTIC ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 143: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:125 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: JAMES MADISON MIDDLE

Address: 3375 DAIRY ROAD, TITUSVILLE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 8 GRADE 8

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use MIDDLE MIDDLE

School Capacity 742 742

Utilization Factor 90% 90%

Survey AnnotationOther = fencing & securityAdd stage & related spacesExpand administration

COFTE Student Membership 499 451

Total Stations 825 0 825

Perm. Stations 825 0 825

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $2,596,701

$0 $0 $0 $41,044 $0 $1,234,430 $1,321,227

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 144: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:126 of 234 Report Date: 6/15/2015 11:49:17 AM

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (148 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2216 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (148 NSF), 1 unit of STAGE (990 NSF), 1 unit of STAGE STORAGE (371 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (185 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (185 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF)

4,343 0 $951,117 $219 $0

Renovation 2017 Renovating: Apply HVAC Systems, Retrofit for Technology to the entire facility JAMES MADISON MIDDLE.

112,666 0 $1,234,430 $11 $0

New Construction 2020 New Construction: Adding 1 unit of BOOKKEEPING OFFICE (125 NSF), 1 unit of SECRETARIAL SPACE (158 NSF), 1 unit of PRODUCTION WORKROOM (240 NSF), 1 unit of CONFERENCE ROOM (236 NSF), 1 unit of VAULT/STUDENT RECORDS (134 NSF), 1 unit of STUDENT ACTIVITIES (191 NSF), 1 unit of CAREERS ROOM (222 NSF), 1 unit of ITINERANT OFFICE (125 NSF), 1 unit of TEXTBOOK STORAGE (259 NSF)

1,690 0 $370,110 $219 $0

JAMES MADISON MIDDLE

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 145: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:127 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: JOHN F KENNEDY MIDDLE

Address: 2100 S FISKE BOULEVARD, ROCKLEDGE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 8 GRADE 8

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use MIDDLE MIDDLE

School Capacity 819 753

Utilization Factor 90% 90%

Survey Annotation

Other = fencing & securityRemodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.Expand administrationAdd stage & related spaces

COFTE Student Membership 579 591

Total Stations 910 -73 837

Perm. Stations 749 0 749

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 161 -73 88

Estimated Total Project Cost $3,468,166

$0 $0 $0 $269,371 $40,000 $2,522,819 $635,976

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of CLINIC (202 NSF), 1 unit of STUDENT ACTIVITIES (337 NSF), 1 unit of CAREERS ROOM (202 NSF), 1 unit of TEXTBOOK STORAGE (236 NSF)

977 0 $213,963 $219 $0

JOHN F KENNEDY MIDDLE

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 146: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:128 of 234 Report Date: 6/15/2015 11:49:17 AM

Remodeling 2017 26 99 Removed NSF (2831), Added NSF (0), Difference NSF (2831), Percent (100%), Removed Stations (73), Added Stations (0) Remodeling: Removing Room N032 (683 NSF), Room N219 (683 NSF), Room N937 (683 NSF), Room T110 (782 NSF)

-2,831 -73 $40,000 $14 $0

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility JOHN F KENNEDY MIDDLE.

112,052 0 $2,522,819 $23 $0

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (135 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (135 NSF), 1 unit of STAGE (990 NSF), 1 unit of STAGE STORAGE (337 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (115 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (115 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF)

1,927 0 $422,013 $219 $0

JOHN F KENNEDY MIDDLE

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 147: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:129 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: JOHN F TURNER SR ELEMENTARY

Address: 3175 JUPITER BOULEVARD SE, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 874 874

Utilization Factor 100% 100%

Survey AnnotationOther = fencing & securityExpand mediaAdd PE Storage & expand covered play

COFTE Student Membership 658 810

Total Stations 874 0 874

Perm. Stations 830 0 830

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 44 0 44

Estimated Total Project Cost $3,170,412

$0 $0 $0 $146,508 $0 $1,570,958 $1,452,946

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 148: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:130 of 234 Report Date: 6/15/2015 11:49:17 AM

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY COVERED PLAY AREA (3146 NSF)

3,146 0 $663,806 $211 $0

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility JOHN F TURNER SR ELEMENTARY.

96,049 0 $1,570,958 $16 $0

New Construction 2020 New Construction: Adding 1 unit of LIBRARY (READING ROOM/STACKS) (872 NSF), 1 unit of MEDIA TECHNICAL PROCESSING (81 NSF), 1 unit of PROFESSIONAL LIBRARY (120 NSF), 1 unit of AUDIO VISUAL STORAGE (133 NSF), 1 unit of PERIODICAL STORAGE (174 NSF), 1 unit of CLOSED CIRCUIT TV LAB (612 NSF), 1 unit of CLOSED CIRCUIT STORAGE (437 NSF), 1 unit of MEDIA PRODUCTION LAB (437 NSF), 1 unit of MEDIA COPYING ROOM (175 NSF), 1 unit of MEDIA SMALL GROUP ROOM (175 NSF), 1 unit of MEDIA GROUP PROJECTS/INSTRUCTION (437 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (87 NSF)

3,740 0 $789,140 $211 $0

JOHN F TURNER SR ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 149: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:131 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: JUPITER ELEMENTARY

Address: 950 TUPELO ROAD SW, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 930 780

Utilization Factor 100% 100%

Survey Annotation Other = fencing & securityRemodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.

COFTE Student Membership 748 780

Total Stations 930 -150 780

Perm. Stations 780 0 780

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 150 -150 0

Estimated Total Project Cost $1,059,381

$0 $0 $0 $216,764 $70,000 $772,617 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Remodeling 2018 45 99 Removed NSF (4886), Added NSF (0), Difference NSF (4886), Percent (100%), Removed Stations (150), Added Stations (0) Remodeling: Removing Room N014 (683 NSF), Room N015 (683 NSF), Room N033 (683 NSF), Room N047 (683 NSF), Room N079 (683 NSF), Room N205 (683 NSF), Room T210 (788 NSF)

-4,886 -150 $70,000 $14 $0

JUPITER ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 150: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:132 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility JUPITER ELEMENTARY.

125,746 0 $772,617 $6 $0

JUPITER ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 151: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:133 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: LEWIS CARROLL ELEMENTARY

Address: 1 SKYLINE BOULEVARD, MERRITT ISLAND

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 751 751

Utilization Factor 100% 100%

Survey Annotation Other = fencing & securityAdd covered play

COFTE Student Membership 635 562

Total Stations 751 0 751

Perm. Stations 751 0 751

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $2,623,327

$0 $0 $0 $37,607 $0 $1,948,922 $636,798

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Electrical, HVAC Systems, Retrofit for Technology to the entire facility LEWIS CARROLL ELEMENTARY.

100,941 0 $1,948,922 $19 $0

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (2703 NSF)

3,018 0 $636,798 $211 $0

LEWIS CARROLL ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 152: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:134 of 234 Report Date: 6/15/2015 11:49:17 AM

Page 153: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:135 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: LOCKMAR ELEMENTARY

Address: 525 PEPPER STREET NE, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 892 892

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & securityAdd PE storage & expand covered playExpand mediaExpand Administration

COFTE Student Membership 761 697

Total Stations 892 0 892

Perm. Stations 892 0 892

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $3,593,595

$0 $0 $0 $50,557 $0 $2,011,811 $1,531,227

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (2611 NSF)

2,926 0 $617,386 $211 $0

LOCKMAR ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 154: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:136 of 234 Report Date: 6/15/2015 11:49:17 AM

New Construction 2020 New Construction: Adding 1 unit of GENERAL SCHOOL STORAGE (446 NSF), 1 unit of VAULT/STUDENT RECORDS (267 NSF), 1 unit of SCHOOL STORE (89 NSF), 1 unit of STUDENT ACTIVITIES (446 NSF), 1 unit of COMPUTER AREA (113 NSF), 1 unit of CAREERS ROOM (267 NSF), 1 unit of ITINERANT OFFICE (125 NSF)

1,753 0 $369,883 $211 $0

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility LOCKMAR ELEMENTARY.

112,452 0 $2,011,811 $18 $0

New Construction 2020 New Construction: Adding 1 unit of MEDIA TECHNICAL PROCESSING (171 NSF), 1 unit of CLOSED CIRCUIT TV LAB (624 NSF), 1 unit of CLOSED CIRCUIT STORAGE (446 NSF), 1 unit of MEDIA PRODUCTION LAB (446 NSF), 1 unit of MEDIA COPYING ROOM (178 NSF), 1 unit of MEDIA SMALL GROUP ROOM (178 NSF), 1 unit of MEDIA GROUP PROJECTS/INSTRUCTION (446 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (89 NSF)

2,578 0 $543,958 $211 $0

LOCKMAR ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 155: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:137 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: LONGLEAF ELEMENTARY

Address: 4290 N WICKHAM ROAD, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 790 790

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 503 468

Total Stations 790 0 790

Perm. Stations 790 0 790

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $1,706,621

$0 $0 $0 $29,980 $0 $1,676,641 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, Electrical, HVAC Systems, Retrofit for Technology to the entire facility LONGLEAF ELEMENTARY.

105,846 0 $1,676,641 $16 $0

LONGLEAF ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 156: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:138 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: LYNDON B JOHNSON MIDDLE

Address: 2155 CROTON ROAD, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 8 GRADE 8

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use MIDDLE MIDDLE

School Capacity 1,019 1019

Utilization Factor 90% 90%

Survey Annotation

Other = fencing & securityExpand mediaExpand administrationAdd multipurpose/stage

COFTE Student Membership 787 716

Total Stations 1,133 0 1133

Perm. Stations 1,111 0 1111

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 22 0 22

Estimated Total Project Cost $5,941,950

$0 $0 $0 $122,013 $0 $3,444,225 $2,375,712

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 157: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:139 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility LYNDON B JOHNSON MIDDLE.

147,248 0 $3,444,225 $23 $0

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (200 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (3000 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (200 NSF), 1 unit of STAGE (990 NSF), 1 unit of STAGE STORAGE (500 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (250 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (250 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF)

5,490 0 $1,202,310 $219 $0

New Construction 2020 New Construction: Adding 1 unit of PRODUCTION WORKROOM (399 NSF), 1 unit of CONFERENCE ROOM (603 NSF), 1 unit of GENERAL SCHOOL STORAGE (499 NSF), 1 unit of COMPUTER AREA (150 NSF), 1 unit of ITINERANT OFFICE (125 NSF)

1,776 0 $388,944 $219 $0

New Construction 2020 New Construction: Adding 1 unit of MEDIA TECHNICAL PROCESSING (408 NSF), 1 unit of PROFESSIONAL LIBRARY (399 NSF), 1 unit of AUDIO VISUAL STORAGE (278 NSF), 1 unit of CLOSED CIRCUIT TV LAB (699 NSF), 1 unit of CLOSED CIRCUIT STORAGE (499 NSF), 1 unit of MEDIA PRODUCTION LAB (499 NSF), 1 unit of MEDIA COPYING ROOM (199 NSF), 1 unit of MEDIA GROUP PROJECTS/INSTRUCTION (499 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (102 NSF)

3,582 0 $784,458 $219 $0

LYNDON B JOHNSON MIDDLE

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 158: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:140 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: MANATEE BUS COMPOUND

Address: 3425 VIERA BOULEVARD, VIERA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use TRANSPORTATION TRANSPORTATION

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $187,658

$0 $0 $0 $0 $0 $187,658 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2018 Renovating: Apply Painting, HVAC Systems to the entire facility MANATEE BUS COMPOUND.

2,290 0 $187,658 $82 $0

MANATEE BUS COMPOUND

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 159: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:141 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: MANATEE ELEMENTARY

Address: 3425 VIERA BOULEVARD, VIERA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 998 998

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 833 772

Total Stations 998 0 998

Perm. Stations 866 0 866

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 132 0 132

Estimated Total Project Cost $1,108,806

$0 $0 $0 $165,075 $0 $943,731 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, Electrical, HVAC Systems to the entire facility MANATEE ELEMENTARY.

123,001 0 $943,731 $8 $0

MANATEE ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 160: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:142 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: MCLARTY STADIUM

Address: MURRELL ROAD, ROCKLEDGE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use MULTIPLE USE SUPPORT MULTIPLE USE SUPPORT

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $0

$0 $0 $0 $0 $0 $0 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

MCLARTY STADIUM Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 161: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:143 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: MEADOWLANE INTERMEDIATE ELEMENTARY

Address: 2700 WINGATE BLVD, WEST MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 3 GRADE 3

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 1,114 1114

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 887 939

Total Stations 1,114 0 1114

Perm. Stations 894 0 894

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 220 0 220

Estimated Total Project Cost $1,901,598

$0 $0 $0 $279,661 $0 $1,621,937 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply HVAC Systems to the entire facility MEADOWLANE INTERMEDIATE ELEMENTARY.

139,110 0 $1,621,937 $12 $0

MEADOWLANE INTERMEDIATE ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 162: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:144 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: MEADOWLANE PRIMARY ELEMENTARY

Address: 2800 WINGATE BOULEVARD, WEST MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 3 GRADE 3

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 824 824

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 773 600

Total Stations 824 0 824

Perm. Stations 824 0 824

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $2,724,437

$0 $0 $0 $36,195 $0 $2,688,242 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, Electrical, HVAC Systems, Retrofit for Technology to the entire facility MEADOWLANE PRIMARY ELEMENTARY.

144,366 0 $2,688,242 $19 $0

MEADOWLANE PRIMARY ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 163: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:145 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: MELBOURNE BUS COMPOUND

Address: 3200 MONROE STREET, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use TRANSPORTATION TRANSPORTATION

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $17,994

$0 $0 $0 $0 $0 $17,994 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2018 Renovating: Apply Electrical to the entire facility MELBOURNE BUS COMPOUND.

11,037 0 $17,994 $2 $0

MELBOURNE BUS COMPOUND

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 164: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:146 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: MELBOURNE SENIOR HIGH

Address: 74 BULLDOG BOULEVARD, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 9 GRADE 9

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use SENIOR HIGH SENIOR HIGH

School Capacity 2,317 2317

Utilization Factor 95% 95%

Survey Annotation Other = fencing & security

COFTE Student Membership 1,862 1,827

Total Stations 2,439 0 2439

Perm. Stations 2,439 0 2439

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $8,893,982

$0 $0 $0 $88,999 $0 $8,804,983 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems to the entire facility MELBOURNE SENIOR HIGH.

334,439 0 $8,804,983 $26 $0

MELBOURNE SENIOR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 165: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:147 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: MERRITT ISLAND SENIOR HIGH

Address: 100 E MUSTANG WAY, MERRITT ISLAND

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 9 GRADE 9

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use SENIOR HIGH SENIOR HIGH

School Capacity 1,914 1914

Utilization Factor 95% 95%

Survey Annotation Other = fencing & security $80,759 Site Improvement -Deferred Infrastructure Improvements as described in 1013.01(22)$265,696

COFTE Student Membership 1,400 1,180

Total Stations 2,015 0 2015

Perm. Stations 1,965 0 1965

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 50 0 50

Estimated Total Project Cost $2,267,993

$0 $0 $0 $426,455 $0 $1,841,538 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility MERRITT ISLAND SENIOR HIGH.

265,516 0 $1,841,538 $7 $0

MERRITT ISLAND SENIOR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 166: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:148 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: MID-SOUTH AREA SUPPORT SERVICES

Address: 1948 PINEAPPLE AVENUE, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use MULTIPLE USE SUPPORT MULTIPLE USE SUPPORT

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

Building 2 remains in FISH as "unsatisfactory." This building is recommended for demolitionper Castaldi approved by DOE March 26, 2014, with concurrence of the Florida Departmentof State Division of Historical Resources on Nov 14, 2014."Other" = Site Utilities $140,790

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $1,581,604

$0 $0 $0 $140,790 $0 $1,440,814 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2018 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems to the entire facility MID-SOUTH AREA SUPPORT SERVICES.

23,984 0 $1,440,814 $60 $0

MID-SOUTH AREA SUPPORT SERVICES

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 167: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:149 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: MILA ELEMENTARY

Address: 288 W MERRITT AVENUE, MERRITT ISLAND

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 707 707

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & security $51,606, Site Utilities $167,504Expand mediaExpand administrationAdd multipurpose dining

COFTE Student Membership 458 429

Total Stations 707 0 707

Perm. Stations 707 0 707

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $3,413,235

$0 $0 $0 $219,110 $0 $1,514,776 $1,679,349

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 168: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:150 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility MILA ELEMENTARY.

91,174 0 $1,514,776 $17 $0

New Construction 2020 New Construction: Adding 1 unit of CONFERENCE ROOM (494 NSF), 1 unit of GENERAL SCHOOL STORAGE (353 NSF), 1 unit of VAULT/STUDENT RECORDS (212 NSF), 1 unit of SCHOOL STORE (70 NSF), 1 unit of STUDENT ACTIVITIES (353 NSF), 1 unit of COMPUTER AREA (106 NSF), 1 unit of ITINERANT OFFICE (125 NSF), 1 unit of TEXTBOOK STORAGE (247 NSF)

1,960 0 $413,560 $211 $0

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (141 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2192 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (141 NSF), 1 unit of STAGE STORAGE (354 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (175 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (175 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF)

3,278 0 $691,658 $211 $0

New Construction 2020 New Construction: Adding 1 unit of MEDIA TECHNICAL PROCESSING (353 NSF), 1 unit of AUDIO VISUAL STORAGE (322 NSF), 1 unit of PERIODICAL STORAGE (141 NSF), 1 unit of CLOSED CIRCUIT TV LAB (494 NSF), 1 unit of CLOSED CIRCUIT STORAGE (353 NSF), 1 unit of MEDIA PRODUCTION LAB (353 NSF), 1 unit of MEDIA COPYING ROOM (141 NSF), 1 unit of MEDIA SMALL GROUP ROOM (141 NSF), 1 unit of MEDIA GROUP PROJECTS/INSTRUCTION (353 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (70 NSF)

2,721 0 $574,131 $211 $0

MILA ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 169: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:151 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: MIMS ELEMENTARY

Address: 2582 U S HIGHWAY 1, MIMS

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 725 725

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security $55,025 Site Improvement – Deferred infrastructure improvements as described in 1013.01(22) $46,930

COFTE Student Membership 507 433

Total Stations 725 0 725

Perm. Stations 725 0 725

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $607,464

$0 $0 $0 $101,954 $0 $505,510 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility MIMS ELEMENTARY.

85,052 0 $505,510 $6 $0

MIMS ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 170: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:152 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: NORTH AREA TRANSPORTATION SERVICES

Address: 1500 DRAA ROAD, TITUSVILLE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use TRANSPORTATION TRANSPORTATION

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $456,837

$0 $0 $0 $0 $0 $456,837 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, Electrical to the entire facility NORTH AREA TRANSPORTATION SERVICES.

12,756 0 $456,837 $36 $0

NORTH AREA TRANSPORTATION SERVICES

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 171: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:153 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: OAK PARK ELEMENTARY

Address: 3395 DAIRY ROAD, TITUSVILLE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 888 888

Utilization Factor 100% 100%

Survey AnnotationOther = fencing & securityExpand MediaExpand dining/multipurpose

COFTE Student Membership 814 683

Total Stations 888 0 888

Perm. Stations 888 0 888

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $3,181,022

$0 $0 $0 $113,032 $0 $1,596,054 $1,471,936

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 172: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:154 of 234 Report Date: 6/15/2015 11:49:17 AM

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (178 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2122 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (178 NSF), 1 unit of STAGE STORAGE (404 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (222 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (222 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF)

3,426 0 $722,886 $211 $0

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility OAK PARK ELEMENTARY.

106,109 0 $1,596,054 $15 $0

New Construction 2020 New Construction: Adding 1 unit of MEDIA TECHNICAL PROCESSING (273 NSF), 1 unit of PROFESSIONAL LIBRARY (355 NSF), 1 unit of AUDIO VISUAL STORAGE (532 NSF), 1 unit of CLOSED CIRCUIT TV LAB (621 NSF), 1 unit of CLOSED CIRCUIT STORAGE (444 NSF), 1 unit of MEDIA PRODUCTION LAB (444 NSF), 1 unit of MEDIA COPYING ROOM (177 NSF), 1 unit of MEDIA SMALL GROUP ROOM (177 NSF), 1 unit of MEDIA GROUP PROJECTS/INSTRUCTION (444 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (83 NSF)

3,550 0 $749,050 $211 $0

OAK PARK ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 173: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:155 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: OCEAN BREEZE ELEMENTARY

Address: 1101 CHEYENNE DRIVE, INDIAN HARBOUR BEACH

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 654 636

Utilization Factor 100% 100%

Survey Annotation Other = fencing & securityRemodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.

COFTE Student Membership 521 505

Total Stations 654 -18 636

Perm. Stations 498 0 498

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 156 -18 138

Estimated Total Project Cost $1,688,548

$0 $0 $0 $269,790 $10,000 $1,408,758 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Remodeling 2018 74 99 Removed NSF (683), Added NSF (0), Difference NSF (683), Percent (100%), Removed Stations (18), Added Stations (0) Remodeling: Removing Room N057 (683 NSF)

-683 -18 $10,000 $15 $0

OCEAN BREEZE ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 174: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:156 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility OCEAN BREEZE ELEMENTARY.

71,419 0 $1,408,758 $20 $0

OCEAN BREEZE ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 175: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:157 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: OLD CREEL BUS COMPOUND

Address: 815 MATHERS ST, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use TRANSPORTATION TRANSPORTATION

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $0

$0 $0 $0 $0 $0 $0 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

OLD CREEL BUS COMPOUND

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 176: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:158 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: PALM BAY ELEMENTARY

Address: 1200 ALLAMANDA ROAD NE, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 1,005 1005

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 682 817

Total Stations 1,005 0 1005

Perm. Stations 829 0 829

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 176 0 176

Estimated Total Project Cost $2,806,686

$0 $0 $0 $326,607 $0 $1,783,990 $696,089

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Plumbing, HVAC Systems, Bell/Fire Alarm Systems to the entire facility PALM BAY ELEMENTARY.

92,838 0 $1,783,990 $19 $0

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (2984 NSF)

3,299 0 $696,089 $211 $0

PALM BAY ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 177: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:159 of 234 Report Date: 6/15/2015 11:49:17 AM

Page 178: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:160 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: PALM BAY MAGNET SENIOR HIGH

Address: 101 PIRATE LANE, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 9 GRADE 9

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use SENIOR HIGH SENIOR HIGH

School Capacity 2,613 2613

Utilization Factor 95% 95%

Survey Annotation Other = fencing & security

COFTE Student Membership 1,351 1,240

Total Stations 2,751 0 2751

Perm. Stations 2,576 0 2576

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 175 0 175

Estimated Total Project Cost $1,827,747

$0 $0 $0 $242,503 $0 $1,585,244 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Electrical, Plumbing, HVAC Systems to the entire facility PALM BAY MAGNET SENIOR HIGH.

338,476 0 $1,585,244 $5 $0

PALM BAY MAGNET SENIOR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 179: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:161 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: PINEWOOD ELEMENTARY

Address: 3757 OLD DIXIE HIGHWAY, MIMS

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 503 503

Utilization Factor 100% 100%

Survey Annotation Other = fencing & securityAdd stage

COFTE Student Membership 393 375

Total Stations 503 0 503

Perm. Stations 503 0 503

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $1,679,434

$0 $0 $0 $60,000 $0 $1,283,100 $336,334

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of STAGE (990 NSF), 1 unit of STAGE STORAGE (252 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (126 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (126 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF)

1,594 0 $336,334 $211 $0

PINEWOOD ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 180: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:162 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility PINEWOOD ELEMENTARY.

69,637 0 $1,283,100 $18 $0

PINEWOOD ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 181: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:163 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: PLANT OPERATIONS AND MAINTENANCE

Address: 1254 S FLORIDA AVENUE, ROCKLEDGE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use MAINTENANCE MAINTENANCE

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $911,014

$0 $0 $0 $0 $0 $911,014 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply HVAC Systems to the entire facility PLANT OPERATIONS AND MAINTENANCE.

46,468 0 $911,014 $20 $0

PLANT OPERATIONS AND MAINTENANCE

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 182: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:164 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: PORT MALABAR ELEMENTARY

Address: 301 PIONEER AVENUE NE, PORT MALABAR

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 852 834

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & securityRemodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.Add multipurpose & chair storageExpand media

COFTE Student Membership 704 731

Total Stations 852 -18 834

Perm. Stations 768 0 768

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 84 -18 66

Estimated Total Project Cost $2,993,338

$0 $0 $0 $118,418 $10,000 $1,837,561 $1,027,359

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 183: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:165 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Electrical, Plumbing, HVAC Systems to the entire facility PORT MALABAR ELEMENTARY.

105,457 0 $1,837,561 $17 $0

Remodeling 2018 35 99 Removed NSF (683), Added NSF (0), Difference NSF (683), Percent (100%), Removed Stations (18), Added Stations (0) Remodeling: Removing Room N224 (683 NSF)

-683 -18 $10,000 $15 $0

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (154 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2381 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (154 NSF)

2,689 0 $567,379 $211 $0

New Construction 2020 New Construction: Adding 1 unit of MEDIA TECHNICAL PROCESSING (109 NSF), 1 unit of CLOSED CIRCUIT TV LAB (537 NSF), 1 unit of CLOSED CIRCUIT STORAGE (384 NSF), 1 unit of MEDIA PRODUCTION LAB (384 NSF), 1 unit of MEDIA COPYING ROOM (153 NSF), 1 unit of MEDIA SMALL GROUP ROOM (153 NSF), 1 unit of MEDIA GROUP PROJECTS/INSTRUCTION (384 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (76 NSF)

2,180 0 $459,980 $211 $0

PORT MALABAR ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 184: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:166 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: QUEST ELEMENTARY

Address: 8751 TRAFFORD DR, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 928 928

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security $27,903 Site Improvement – Deferred infrastructure improvements as described in 1013.01(22)$103,968

COFTE Student Membership 709 790

Total Stations 928 0 928

Perm. Stations 910 0 910

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 18 0 18

Estimated Total Project Cost $1,160,351

$0 $0 $0 $227,871 $0 $932,480 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, HVAC Systems, Retrofit for Technology to the entire facility QUEST ELEMENTARY.

109,915 0 $932,480 $8 $0

QUEST ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 185: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:167 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: RALPH M WILLIAMS JR ELEMENTARY

Address: 1700 CLUBHOUSE DRIVE, ROCKLEDGE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 715 627

Utilization Factor 100% 100%

Survey AnnotationOther = fencing & securityRemodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.Add PE storage and expand covered play

COFTE Student Membership 537 449

Total Stations 715 -88 627

Perm. Stations 627 0 627

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 88 -88 0

Estimated Total Project Cost $2,604,239

$0 $0 $0 $167,165 $40,000 $1,980,982 $416,092

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (1657 NSF)

1,972 0 $416,092 $211 $0

RALPH M WILLIAMS JR ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 186: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:168 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility RALPH M WILLIAMS JR ELEMENTARY.

98,638 0 $1,980,982 $20 $0

Remodeling 2018 115 99 Removed NSF (2732), Added NSF (0), Difference NSF (2732), Percent (100%), Removed Stations (88), Added Stations (0) Remodeling: Removing Room N056 (683 NSF), Room N163 (683 NSF), Room N181 (683 NSF), Room N245 (683 NSF)

-2,732 -88 $40,000 $15 $0

RALPH M WILLIAMS JR ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 187: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:169 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: RIVERVIEW SCHOOL

Address: 3000 JOLLY STREET, TITUSVILLE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 PRE-K E S E

Comments

Existing Recommended

Capital Outlay Classification

2 - SCHOOL CONDITIONALLY RECOMMENDED FOR CONTINUED USE

2 - SCHOOL CONDITIONALLY RECOMMENDED FOR CONTINUED USE

Facility Use PRE-K E S E PRE-K E S E

School Capacity 576 576

Utilization Factor 100% 100%

Survey Annotation

COFTE Student Membership 21 10

Total Stations 576 0 576

Perm. Stations 576 0 576

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $92,800

$0 $0 $0 $92,800 $0 $0 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

RIVERVIEW SCHOOL Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 188: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:170 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: RIVIERA ELEMENTARY

Address: 351 RIVIERA DRIVE NE, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 777 777

Utilization Factor 100% 100%

Survey AnnotationOther = fencing & securityAdd multipurpose & chair storageAdd covered play

COFTE Student Membership 627 707

Total Stations 777 0 777

Perm. Stations 689 0 689

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 88 0 88

Estimated Total Project Cost $1,966,563

$0 $0 $0 $76,354 $0 $574,202 $1,316,007

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (155 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2409 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (155 NSF)

2,719 0 $573,709 $211 $0

RIVIERA ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 189: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:171 of 234 Report Date: 6/15/2015 11:49:17 AM

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY COVERED PLAY AREA (2197 NSF)

2,197 0 $463,567 $211 $0

Renovation 2017 Renovating: Apply Painting, Electrical, HVAC Systems, Retrofit for Technology to the entire facility RIVIERA ELEMENTARY.

109,711 0 $574,202 $5 $0

New Construction 2020 New Construction: Adding 1 unit of GENERAL SCHOOL STORAGE (274 NSF), 1 unit of VAULT/STUDENT RECORDS (233 NSF), 1 unit of SCHOOL STORE (77 NSF), 1 unit of STUDENT ACTIVITIES (388 NSF), 1 unit of COMPUTER AREA (116 NSF), 1 unit of CAREERS ROOM (233 NSF)

1,321 0 $278,731 $211 $0

RIVIERA ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 190: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:172 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: ROBERT LOUIS STEVENSON ELEMENTARY SCHOOL OF THE ARTS

Address: 1450 MARTIN BOULEVARD, MERRITT ISLAND

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 569 569

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security $20,915 Site Improvement – Deferred infrastructure improvements as described in 1013.01(22) $86,640

COFTE Student Membership 439 440

Total Stations 569 0 569

Perm. Stations 569 0 569

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $1,201,229

$0 $0 $0 $107,555 $0 $1,093,674 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Electrical, Plumbing, HVAC Systems to the entire facility ROBERT LOUIS STEVENSON ELEMENTARY SCHOOL OF THE ARTS.

60,758 0 $1,093,674 $18 $0

ROBERT LOUIS STEVENSON ELEMENTARY SCHOOL OF THE ARTS

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 191: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:173 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: ROCKLEDGE SENIOR HIGH

Address: 220 ROCKLEDGE AVE, ROCKLEDGE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 9 GRADE 9

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use SENIOR HIGH SENIOR HIGH

School Capacity 1,677 1606

Utilization Factor 95% 95%

Survey Annotation Other = fencing & security $67,171 Site Improvement – Deferred infrastructure improvements as described in 1013.01(22) $368,220

COFTE Student Membership 1,293 1,322

Total Stations 1,766 -75 1691

Perm. Stations 1,691 0 1691

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 75 -75 0

Estimated Total Project Cost $5,578,953

$0 $0 $0 $520,191 $30,000 $5,028,762 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Remodeling 2018 17 99 Removed NSF (2049), Added NSF (0), Difference NSF (2049), Percent (100%), Removed Stations (75), Added Stations (0) Remodeling: Removing Room N165 (683 NSF), Room N168 (683 NSF), Room N241 (683 NSF)

-2,049 -75 $30,000 $15 $0

ROCKLEDGE SENIOR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 192: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:174 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility ROCKLEDGE SENIOR HIGH.

255,846 0 $5,028,762 $20 $0

ROCKLEDGE SENIOR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 193: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:175 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: RONALD MCNAIR MIDDLE

Address: 1 CHALLENGER DRIVE, COCOA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 8 GRADE 8

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use MIDDLE MIDDLE

School Capacity 611 611

Utilization Factor 90% 90%

Survey Annotation Other = fencing & securityExpand administration

COFTE Student Membership 486 446

Total Stations 679 0 679

Perm. Stations 679 0 679

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $1,191,942

$0 $0 $0 $64,056 $0 $710,034 $417,852

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 194: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:176 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Painting, Electrical, HVAC Systems to the entire facility RONALD MCNAIR MIDDLE .

96,188 0 $710,034 $7 $0

New Construction 2020 New Construction: Adding 1 unit of RECEPTION AREA (411 NSF), 1 unit of GENERAL SCHOOL STORAGE (305 NSF), 1 unit of VAULT/STUDENT RECORDS (183 NSF), 1 unit of SCHOOL STORE (61 NSF), 1 unit of STUDENT ACTIVITIES (305 NSF), 1 unit of COMPUTER AREA (91 NSF), 1 unit of CAREERS ROOM (183 NSF), 1 unit of ITINERANT OFFICE (125 NSF), 1 unit of TEACHER LOUNGE/DINING (244 NSF)

1,908 0 $417,852 $219 $0

RONALD MCNAIR MIDDLE

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 195: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:177 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: ROY ALLEN ELEMENTARY

Address: 2601 FOUNTAINHEAD BOULEVARD, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 729 729

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 556 580

Total Stations 729 0 729

Perm. Stations 663 0 663

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 66 0 66

Estimated Total Project Cost $1,146,761

$0 $0 $0 $145,051 $0 $1,001,710 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility ROY ALLEN ELEMENTARY.

95,398 0 $1,001,710 $11 $0

ROY ALLEN ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 196: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:178 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SABAL ELEMENTARY

Address: 1401 N WICKHAM ROAD, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 785 745

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & security $136,776, Site Utilities $319,124Remodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.Add covered play & expand PE storageAdd multipurpose & chair storage

COFTE Student Membership 591 533

Total Stations 785 -40 745

Perm. Stations 679 0 679

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 106 -40 66

Estimated Total Project Cost $3,309,092

$0 $0 $0 $558,300 $20,000 $1,806,612 $924,180

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (1688 NSF)

2,003 0 $422,633 $211 $0

SABAL ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 197: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:179 of 234 Report Date: 6/15/2015 11:49:17 AM

Remodeling 2018 52 99 Removed NSF (1366), Added NSF (0), Difference NSF (1366), Percent (100%), Removed Stations (40), Added Stations (0) Remodeling: Removing Room N074 (683 NSF), Room N939 (683 NSF)

-1,366 -40 $20,000 $15 $0

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility SABAL ELEMENTARY.

76,025 0 $1,806,612 $24 $0

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (136 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2105 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (136 NSF)

2,377 0 $501,547 $211 $0

SABAL ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 198: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:180 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SATELLITE BUS COMPOUND

Address: 52 HOLLAND COURT, SATELLITE BEACH

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use TRANSPORTATION TRANSPORTATION

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation "Other" =Site Improvement – Deferred infrastructure improvements as described in 1013.01(22) $79,420

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $460,156

$0 $0 $0 $79,420 $0 $380,736 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2018 Renovating: Apply Painting, Plumbing, HVAC Systems to the entire facility SATELLITE BUS COMPOUND.

6,632 0 $380,736 $57 $0

SATELLITE BUS COMPOUND

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 199: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:181 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SATELLITE SENIOR HIGH

Address: 300 SCORPION COURT, SATELLITE BEACH

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 9 GRADE 9

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use SENIOR HIGH SENIOR HIGH

School Capacity 1,524 1524

Utilization Factor 95% 95%

Survey Annotation Other = fencing & security $127,433 Site Improvement – Deferred infrastructure improvements as described in 1013.01(22) $282,580

COFTE Student Membership 1,188 1,042

Total Stations 1,605 0 1605

Perm. Stations 1,580 0 1580

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 25 0 25

Estimated Total Project Cost $1,479,003

$0 $0 $0 $513,013 $0 $965,990 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility SATELLITE SENIOR HIGH.

262,619 0 $965,990 $4 $0

SATELLITE SENIOR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 200: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:182 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SATURN ELEMENTARY

Address: 880 RANGE ROAD, COCOA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 958 940

Utilization Factor 100% 100%

Survey AnnotationRemodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.Add multipurpose & related spaces"Other"= $75,639 for site utilities

COFTE Student Membership 664 690

Total Stations 958 -18 940

Perm. Stations 830 0 830

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 128 -18 110

Estimated Total Project Cost $5,441,950

$0 $0 $0 $171,639 $10,000 $4,461,043 $799,268

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 201: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:183 of 234 Report Date: 6/15/2015 11:49:17 AM

Remodeling 2018 29 99 Removed NSF (683), Added NSF (0), Difference NSF (683), Percent (100%), Removed Stations (18), Added Stations (0) Remodeling: Removing Room N204 (683 NSF)

-683 -18 $10,000 $15 $0

Renovation 2017 Renovating: Apply Painting, Electrical, HVAC Systems, Retrofit for Technology to the entire facility SATURN ELEMENTARY.

88,964 0 $4,461,043 $50 $0

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (166 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2573 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (166 NSF), 1 unit of STAGE STORAGE (383 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (200 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (200 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF)

3,788 0 $799,268 $211 $0

SATURN ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 202: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:184 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SEA PARK ELEMENTARY

Address: 300 SEA PARK BOULEVARD, SATELLITE BEACH

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 439 439

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security $99,545 Site Improvement – Deferred infrastructure improvements as described in 1013.01(22) $441,864

COFTE Student Membership 311 331

Total Stations 439 0 439

Perm. Stations 439 0 439

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $2,283,910

$0 $0 $0 $541,409 $0 $1,742,501 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility SEA PARK ELEMENTARY.

55,072 0 $1,742,501 $32 $0

SEA PARK ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 203: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:185 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SHERWOOD ELEMENTARY

Address: 2541 POST ROAD, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 609 609

Utilization Factor 100% 100%

Survey AnnotationOther = fencing & securityExpand mediaAdd covered play

COFTE Student Membership 505 541

Total Stations 609 0 609

Perm. Stations 609 0 609

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $2,931,836

$0 $0 $0 $21,889 $0 $2,161,952 $747,995

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 204: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:186 of 234 Report Date: 6/15/2015 11:49:17 AM

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY COVERED PLAY AREA (1592 NSF)

1,592 0 $335,912 $211 $0

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility SHERWOOD ELEMENTARY.

85,471 0 $2,161,952 $25 $0

New Construction 2020 New Construction: Adding 1 unit of MEDIA TECHNICAL PROCESSING (243 NSF), 1 unit of PROFESSIONAL LIBRARY (243 NSF), 1 unit of PERIODICAL STORAGE (121 NSF), 1 unit of CLOSED CIRCUIT TV LAB (426 NSF), 1 unit of CLOSED CIRCUIT STORAGE (304 NSF), 1 unit of MEDIA PRODUCTION LAB (304 NSF), 1 unit of MEDIA COPYING ROOM (121 NSF), 1 unit of MEDIA SMALL GROUP ROOM (121 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (70 NSF)

1,953 0 $412,083 $211 $0

SHERWOOD ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 205: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:187 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SOUTH AREA HEAD START

Address: 1430 Knecht Road, NE, Palm Bay

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade PRE-K E S E PRE-K E S E

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use VACANT PRE-K E S E

School Capacity 0 36

Utilization Factor 0% 100%

Survey Annotation

COFTE Student Membership 0 10

Total Stations 36 0 36

Perm. Stations 36 0 36

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $115,315

$0 $0 $0 $0 $0 $115,315 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply HVAC Systems to the entire facility SOUTH AREA HEAD START.

3,574 0 $115,315 $32 $0

SOUTH AREA HEAD START

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 206: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:188 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SOUTH LAKE EDUCATION CENTER

Address: 3755 GARDEN STREET, TITUSVILLE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade ADULT EDUCATION ADULT EDUCATION

High Grade ADULT EDUCATION ADULT EDUCATION

Comments

Existing Recommended

Capital Outlay Classification

2 - SCHOOL CONDITIONALLY RECOMMENDED FOR CONTINUED USE

2 - SCHOOL CONDITIONALLY RECOMMENDED FOR CONTINUED USE

Facility Use VACANT ADULT EDUCATION

School Capacity 0 793

Utilization Factor 0% 150%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 529 0 529

Perm. Stations 529 0 529

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $1,716,159

$0 $0 $0 $0 $0 $1,716,159 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, Electrical, HVAC Systems to the entire facility SOUTH LAKE EDUCATION CENTER.

66,021 0 $1,716,159 $26 $0

SOUTH LAKE EDUCATION CENTER

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 207: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:189 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SOUTH PINE GROVE SCHOOL

Address: 2175 N WICKHAM ROAD, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN ADULT EDUCATION

High Grade GRADE 12 ADULT EDUCATION

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use VACANT ADULT EDUCATION

School Capacity 0 138

Utilization Factor 0% 150%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 92 0 92

Perm. Stations 92 0 92

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $290,571

$0 $0 $0 $0 $0 $290,571 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility SOUTH PINE GROVE SCHOOL.

15,471 0 $290,571 $19 $0

SOUTH PINE GROVE SCHOOL

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 208: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:190 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SOUTHWEST MIDDLE

Address: 451 ELDRON BOULEVARD SE, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 8 GRADE 8

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use MIDDLE MIDDLE

School Capacity 1,177 1177

Utilization Factor 90% 90%

Survey Annotation Other = fencing & security

COFTE Student Membership 955 860

Total Stations 1,308 0 1308

Perm. Stations 1,308 0 1308

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $3,831,170

$0 $0 $0 $52,353 $0 $3,778,817 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Electrical, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility SOUTHWEST MIDDLE.

210,841 0 $3,778,817 $18 $0

SOUTHWEST MIDDLE Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 209: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:191 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SPACE COAST JR/ SR HIGH

Address: 6150 BANYAN STREET, COCOA

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use COMBINATION COMBINATION

School Capacity 1,811 1811

Utilization Factor 90% 90%

Survey Annotation Other = fencing & security

COFTE Student Membership 1,435 1,117

Total Stations 2,013 0 2013

Perm. Stations 1,975 0 1975

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 38 0 38

Estimated Total Project Cost $1,932,765

$0 $0 $0 $125,513 $0 $1,807,252 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2015 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems to the entire facility SPACE COAST JR/ SR HIGH.

325,163 0 $1,807,252 $6 $0

SPACE COAST JR/ SR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 210: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:192 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SPESSARD L HOLLAND ELEMENTARY

Address: 50 HOLLAND COURT, SATELLITE BEACH

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 605 605

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security $86,730, Site Utilities $187,720Expand administration

COFTE Student Membership 407 436

Total Stations 605 0 605

Perm. Stations 605 0 605

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $4,362,140

$0 $0 $0 $274,450 $0 $3,686,790 $400,900

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 211: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:193 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Painting, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility SPESSARD L HOLLAND ELEMENTARY.

76,327 0 $3,686,790 $48 $0

New Construction 2020 New Construction: Adding 1 unit of BOOKKEEPING OFFICE (125 NSF), 1 unit of PRODUCTION WORKROOM (242 NSF), 1 unit of CLINIC (80 NSF), 1 unit of GENERAL SCHOOL STORAGE (302 NSF), 1 unit of VAULT/STUDENT RECORDS (181 NSF), 1 unit of SCHOOL STORE (60 NSF), 1 unit of STUDENT ACTIVITIES (302 NSF), 1 unit of COMPUTER AREA (90 NSF), 1 unit of CAREERS ROOM (181 NSF), 1 unit of ITINERANT OFFICE (125 NSF), 1 unit of TEXTBOOK STORAGE (212 NSF)

1,900 0 $400,900 $211 $0

SPESSARD L HOLLAND ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 212: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:194 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: STONE MAGNET MIDDLE

Address: 1101 E UNIVERSITY BOULEVARD, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 8 GRADE 8

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use MIDDLE MIDDLE

School Capacity 1,013 1013

Utilization Factor 90% 90%

Survey Annotation Other = fencing & securityAdd multipurpose & chair storage

COFTE Student Membership 807 793

Total Stations 1,126 0 1126

Perm. Stations 1,126 0 1126

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $6,899,687

$0 $0 $0 $74,853 $0 $6,048,260 $776,574

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (203 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (3140 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (203 NSF)

3,546 0 $776,574 $219 $0

STONE MAGNET MIDDLE

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 213: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:195 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility STONE MAGNET MIDDLE.

163,019 0 $6,048,260 $37 $0

STONE MAGNET MIDDLE

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 214: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:196 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SUNRISE ELEMENTARY

Address: 1651 MARA LOMA BLVD, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 895 895

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 729 798

Total Stations 895 0 895

Perm. Stations 895 0 895

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $790,979

$0 $0 $0 $27,917 $0 $763,062 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply HVAC Systems to the entire facility SUNRISE ELEMENTARY.

110,191 0 $763,062 $7 $0

SUNRISE ELEMENTARY Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 215: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:197 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SUNTREE ELEMENTARY

Address: 900 JORDAN BLASS DRIVE, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 755 755

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 617 528

Total Stations 755 0 755

Perm. Stations 689 0 689

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 66 0 66

Estimated Total Project Cost $2,090,231

$0 $0 $0 $219,494 $0 $1,870,737 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility SUNTREE ELEMENTARY.

114,032 0 $1,870,737 $16 $0

SUNTREE ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 216: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:198 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: SURFSIDE ELEMENTARY

Address: 475 CASSIA BOULEVARD, SATELLITE BEACH

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 479 461

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & securityRemodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.Add musicAdd multipurpose & related spacesExpand media

COFTE Student Membership 384 376

Total Stations 479 -18 461

Perm. Stations 439 0 439

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 40 -18 22

Estimated Total Project Cost $2,089,047

$0 $0 $0 $148,975 $10,000 $1,009,268 $920,804

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 217: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:199 of 234 Report Date: 6/15/2015 11:49:17 AM

New Construction 2020 New Construction: Adding 1 unit of MEDIA TECHNICAL PROCESSING (184 NSF), 1 unit of PROFESSIONAL LIBRARY (184 NSF), 1 unit of PERIODICAL STORAGE (92 NSF), 1 unit of CLOSED CIRCUIT TV LAB (323 NSF), 1 unit of CLOSED CIRCUIT STORAGE (230 NSF), 1 unit of MEDIA COPYING ROOM (92 NSF), 1 unit of MEDIA SMALL GROUP ROOM (92 NSF), 1 unit of MEDIA GROUP PROJECTS/INSTRUCTION (300 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (46 NSF)

1,543 0 $325,573 $211 $0

Remodeling 2018 73 99 Removed NSF (708), Added NSF (0), Difference NSF (708), Percent (100%), Removed Stations (18), Added Stations (0) Remodeling: Removing Room N203 (674 NSF), Room N203A (34 NSF)

-708 -18 $10,000 $14 $0

Renovation 2016 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility SURFSIDE ELEMENTARY.

52,953 0 $1,009,268 $19 $0

New Construction 2020 New Construction: Adding 1 unit of KITCHEN CHAIR STORAGE (88 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (1205 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (88 NSF)

1,381 0 $291,391 $211 $0

New Construction 2020 New Construction: Adding 1 unit of MUSIC - ELEMENTARY (900 NSF), 1 unit of REFERENCE (100 NSF), 1 unit of MATERIAL STORAGE (100 NSF), 1 unit of MUSIC PRACTICE ROOM (70 NSF)

1,440 0 $303,840 $211 $0

SURFSIDE ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 218: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:200 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: THEODORE ROOSEVELT ELEMENTARY

Address: 1400 MINUTEMAN CAUSEWAY, COCOA BEACH

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

2 - SCHOOL CONDITIONALLY RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 599 599

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 391 323

Total Stations 599 0 599

Perm. Stations 599 0 599

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $3,197,776

$0 $0 $0 $51,226 $0 $3,146,550 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2015 Renovating: Apply Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility THEODORE ROOSEVELT ELEMENTARY.

103,357 0 $3,146,550 $30 $0

THEODORE ROOSEVELT ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 219: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:201 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: THOMAS JEFFERSON MIDDLE

Address: 1275 S COURTENAY PARKWAY, MERRITT ISLAND

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 8 GRADE 8

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use MIDDLE MIDDLE

School Capacity 847 847

Utilization Factor 90% 90%

Survey Annotation Other = fencing & security

COFTE Student Membership 643 545

Total Stations 942 0 942

Perm. Stations 942 0 942

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $3,732,066

$0 $0 $0 $54,261 $0 $3,677,805 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility THOMAS JEFFERSON MIDDLE.

117,640 0 $3,677,805 $31 $0

THOMAS JEFFERSON MIDDLE

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 220: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:202 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: TITUSVILLE HIGH

Address: 150 TERRIER TRAIL SOUTH, TITUSVILLE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 9 GRADE 9

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use SENIOR HIGH SENIOR HIGH

School Capacity 1,871 1871

Utilization Factor 95% 95%

Survey Annotation Other = fencing & security

COFTE Student Membership 1,227 1,166

Total Stations 1,970 0 1970

Perm. Stations 1,970 0 1970

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $2,350,072

$0 $0 $0 $188,598 $0 $2,161,474 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility TITUSVILLE HIGH.

314,607 0 $2,161,474 $7 $0

TITUSVILLE HIGH Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 221: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:203 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: TROPICAL ELEMENTARY

Address: 885 S COURTENAY PARKWAY, MERRITT ISLAND

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 910 910

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & security $81,879, Site Utilities $11,552Expand multipurpose & diningExpand mediaAdd PE storage

COFTE Student Membership 668 685

Total Stations 910 0 910

Perm. Stations 910 0 910

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $4,778,712

$0 $0 $0 $93,431 $0 $2,934,614 $1,750,667

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 222: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:204 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility TROPICAL ELEMENTARY.

102,754 0 $2,934,614 $29 $0

New Construction 2020 New Construction: Adding 1 unit of MEDIA TECHNICAL PROCESSING (364 NSF), 1 unit of PROFESSIONAL LIBRARY (364 NSF), 1 unit of AUDIO VISUAL STORAGE (267 NSF), 1 unit of PERIODICAL STORAGE (182 NSF), 1 unit of MEDIA PRODUCTION LAB (455 NSF), 1 unit of MEDIA COPYING ROOM (182 NSF), 1 unit of MEDIA GROUP PROJECTS/INSTRUCTION (455 NSF), 1 unit of MEDIA MAINTENANCE/REPAIR (91 NSF)

2,360 0 $497,960 $211 $0

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF)

315 0 $66,465 $211 $0

New Construction 2020 New Construction: Adding 1 unit of DINING AREA (1432 NSF), 1 unit of KITCHEN CHAIR STORAGE (182 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (2821 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (182 NSF), 1 unit of STAGE STORAGE (455 NSF), 1 unit of STAGE DRESSING ROOM (MALE) (225 NSF), 1 unit of STAGE DRESSING ROOM (FEMALE) (225 NSF), 1 unit of CONTROL BOOTH/PROJECTION ROOM (100 NSF)

5,622 0 $1,186,242 $211 $0

TROPICAL ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 223: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:205 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: UNIVERSITY PARK ELEMENTARY

Address: 500 W UNIVERSITY BOULEVARD, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade PRE-K E S E PRE-K E S E

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 811 811

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security $77,472, Site Improvement – Deferred infrastructure improvements as described in 1013.01(22) $122,740

COFTE Student Membership 582 578

Total Stations 811 0 811

Perm. Stations 679 0 679

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 132 0 132

Estimated Total Project Cost $1,732,126

$0 $0 $0 $355,412 $0 $1,376,714 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility UNIVERSITY PARK ELEMENTARY .

85,272 0 $1,376,714 $16 $0

UNIVERSITY PARK ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 224: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:206 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: VIERA HIGH SCHOOL

Address: 6103 STADIUM WAY, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 9 GRADE 9

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use SENIOR HIGH SENIOR HIGH

School Capacity 2,276 2276

Utilization Factor 95% 95%

Survey Annotation Other = fencing & security

COFTE Student Membership 1,776 1,664

Total Stations 2,396 0 2396

Perm. Stations 2,246 0 2246

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 150 0 150

Estimated Total Project Cost $4,121,481

$0 $0 $0 $464,480 $0 $3,657,001 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2017 Renovating: Apply Painting, HVAC Systems, Retrofit for Technology to the entire facility VIERA HIGH SCHOOL.

330,123 0 $3,657,001 $11 $0

VIERA HIGH SCHOOL Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 225: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:207 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: WEST MELBOURNE ELEMENTARY SCHOOL FOR SCIENCE

Address: 2255 MEADOWLANE AVENUE, WEST MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 618 618

Utilization Factor 100% 100%

Survey Annotation

Other = fencing & security $16,869, Site Utilities $112,632Expand AdministrationAdd multipurpose & related spacesAdd covered play & PE storage

COFTE Student Membership 549 550

Total Stations 618 0 618

Perm. Stations 618 0 618

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $2,996,069

$0 $0 $0 $129,501 $0 $1,491,270 $1,375,298

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Page 226: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:208 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Painting, Electrical, Plumbing, HVAC Systems, Retrofit for Technology to the entire facility WEST MELBOURNE ELEMENTARY SCHOOL FOR SCIENCE.

67,378 0 $1,491,270 $22 $0

New Construction 2020 New Construction: Adding 1 unit of ELEMENTARY P E STORAGE (315 NSF), 1 unit of ELEMENTARY COVERED PLAY AREA (2225 NSF)

2,540 0 $535,940 $211 $0

New Construction 2020 New Construction: Adding 1 unit of DINING AREA (224 NSF), 1 unit of KITCHEN CHAIR STORAGE (124 NSF), 1 unit of MULTIPURPOSE ROOM (DINING) (1916 NSF), 1 unit of MULTIPURPOSE ROOM CHAIR STORAGE (124 NSF)

2,388 0 $503,868 $211 $0

New Construction 2020 New Construction: Adding 1 unit of SECRETARIAL SPACE (158 NSF), 1 unit of CONFERENCE ROOM (279 NSF), 1 unit of GENERAL SCHOOL STORAGE (196 NSF), 1 unit of VAULT/STUDENT RECORDS (185 NSF), 1 unit of SCHOOL STORE (62 NSF), 1 unit of STUDENT ACTIVITIES (92 NSF), 1 unit of COMPUTER AREA (92 NSF), 1 unit of CAREERS ROOM (185 NSF), 1 unit of ITINERANT OFFICE (125 NSF), 1 unit of TEXTBOOK STORAGE (216 NSF)

1,590 0 $335,490 $211 $0

WEST MELBOURNE ELEMENTARY SCHOOL FOR SCIENCE

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 227: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:209 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: WEST MELBOURNE MAINT COMPOUND

Address: 2255 MEADOWLANE, WEST MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use MAINTENANCE MAINTENANCE

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $0

$0 $0 $0 $0 $0 $0 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

WEST MELBOURNE MAINT COMPOUND

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 228: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:210 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: WEST SHORE JR/SR HIGH

Address: 250 WILDCAT ALLEY, MELBOURNE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade GRADE 7 GRADE 7

High Grade GRADE 12 GRADE 12

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use COMBINATION COMBINATION

School Capacity 1,263 1241

Utilization Factor 90% 90%

Survey Annotation Other = fencing & securityRemodeling of Building 99 rooms is removal of relocatables in excess of 20 years old.

COFTE Student Membership 905 905

Total Stations 1,404 -25 1379

Perm. Stations 1,232 0 1232

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 172 -25 147

Estimated Total Project Cost $915,134

$0 $0 $0 $285,806 $10,000 $619,328 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Remodeling 2018 47 99 Removed NSF (683), Added NSF (0), Difference NSF (683), Percent (100%), Removed Stations (25), Added Stations (0) Remodeling: Removing Room N016 (683 NSF)

-683 -25 $10,000 $15 $0

WEST SHORE JR/SR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 229: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:211 of 234 Report Date: 6/15/2015 11:49:17 AM

Renovation 2017 Renovating: Apply Painting, Electrical, HVAC Systems, Retrofit for Technology to the entire facility WEST SHORE JR/SR HIGH.

135,325 0 $619,328 $5 $0

WEST SHORE JR/SR HIGH

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 230: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:212 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: WESTSIDE BUS COMPOUND

Address: 2175 DEGROODT SW, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use TRANSPORTATION TRANSPORTATION

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $0

$0 $0 $0 $0 $0 $0 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

WESTSIDE BUS COMPOUND

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 231: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:213 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: WESTSIDE ELEMENTARY

Address: 2175 DEGROODT ROAD SW, PALM BAY

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade KINDERGARTEN KINDERGARTEN

High Grade GRADE 6 GRADE 6

Comments

Existing Recommended

Capital Outlay Classification

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

1 - SCHOOL RECOMMENDED FOR CONTINUED USE

Facility Use ELEMENTARY ELEMENTARY

School Capacity 857 857

Utilization Factor 100% 100%

Survey Annotation Other = fencing & security

COFTE Student Membership 796 767

Total Stations 857 0 857

Perm. Stations 835 0 835

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 22 0 22

Estimated Total Project Cost $1,358,215

$0 $0 $0 $51,749 $0 $1,306,466 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

Renovation 2016 Renovating: Apply Painting, Electrical, HVAC Systems, Bell/Fire Alarm Systems, Retrofit for Technology to the entire facility WESTSIDE ELEMENTARY.

108,780 0 $1,306,466 $12 $0

WESTSIDE ELEMENTARY

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 232: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:214 of 234 Report Date: 6/15/2015 11:49:17 AM

Facility Name: WHISPERING HILLS EDUCATION CENTER

Address: 800 LANE AVENUE, TITUSVILLE

District Name: BREVARD COUNTY SCHOOL DISTRICT

Survey: Number 4 - Version 1

Low Grade DISTRICT SERVICES DISTRICT SERVICES

High Grade DISTRICT SERVICES DISTRICT SERVICES

Comments

Existing Recommended

Capital Outlay Classification

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

6 - ANCILLARY RECOMMENDED FOR CONTINUED USE

Facility Use COUNTY ADMINISTRATION COUNTY ADMINISTRATION

School Capacity 0 0

Utilization Factor 0% 0%

Survey Annotation

COFTE Student Membership 0 0

Total Stations 0 0 0

Perm. Stations 0 0 0

ExistingStudent Stations

Added/Reduced(+ or -) Recommended

Mod. Stations 0 0 0

Reloc. Stations 0 0 0

Estimated Total Project Cost $0

$0 $0 $0 $0 $0 $0 $0

New Site Cost Site Expansion

Site Development

Site Improvement

Remodeling Cost

Renovation Cost

New Construction

Cost

WHISPERING HILLS EDUCATION CENTER

Parcel Building Description Total NSF Change In Station Count

Calculated Cost

Cost Per NSF

Cost Per Station

Page 233: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:215 of 234 Report Date: 6/15/2015 11:49:17 AM

DISTRICTWIDE RECOMMENDATIONS

The following recommendations are made on a districtwide basis and include each school or facility where applicable.

Correct deficiencies relating to safety to life, health, and sanitation as identified in the comprehensive Safety Inspection Report pursuant to §4.4(5), §4.4(6), §5(1), and §5(13), SREF 2007.

1.

Necessary modifications for the physically disabled in existing buildings recommended for continued use as provided for in §255.21, F.S.

2.

Additional, or replacement of, equipment for existing school buildings recommended for continued use as provided in §2.1(9)(e), SREF 2007.

3.

Replacement of roofs at existing facilities as provided in §1.2(55) and §4.1(1)(c), SREF 2007.4.

Provide storage, custodial spaces, and sanitation facilities to serve students, staff, and the general public as provided in §6.1, SREF 2007, and §423.20, FBC.

5.

Provide paved auto parking areas pursuant to §5(f)10, SREF 2007, and §423.10.2.7, FBC.6.

Purchase sites for educational and ancillary facilities for future use beyond the projection period of this survey pursuant to §1.4, SREF 2007.

7.

Retrofit existing schools for technology, which may include the creation, or improvement of, cable distribution points (closets in telephone parlance). Provide “clean power” and convenient access to video, data, and voice signal wiring, the built-in equipment involved in distributing video, data, and voice signals pursuant to §5, SREF 2007. This recommendation does not include new construction, remodeling, or terminal equipment (workstations, terminals, receiving equipment, and similar items).

8.

The cost estimates for these districtwide recommendations are not included in the section on Financing the Proposed Program.

Page 234: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:216 of 234 Report Date: 6/15/2015 11:49:17 AM

Section 4: COFTE

Page 235: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:217 of 234 Report Date: 6/15/2015 11:49:17 AM

ANALYSIS OF STUDENT POPULATIONS

The projection of future student population change is based on empirical evidence of historical trends in the student population; annually, the Office of Economic and Demographic Research (EDR) prepares COFTE enrollment projections. The projections do not include summer school, regular pre-kindergarten, hospital/homebound, or area vocational school adults attending basic and high school classes. The projections are most accurate in counties where growth and migration occur at a reasonably constant and predictable rate and, conversely, are least accurate if major changes in the economy and development of the county occur during the projection period.

Technique for Predicting COFTE Student Membership Trends

Even though the out-year COFTE projections used for a 5-year survey period may be less (or more) than the district anticipates, the annual recalculation of COFTE projections assures that current, accurate data can be inserted into a new survey to guarantee that the most reliable projections are used for facilities planning purposes.

Page 236: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:218 of 234 Report Date: 6/15/2015 11:49:17 AM

2015 - 2016 19,113 22,892 19,550 61,554

Year PK-3 4-8 9-12 PK-12

HISTORY

2019 - 2020 18,777 22,631 17,611 59,018

Year PK-3 4-8 9-12 PK-12

PROJECTED

-336 -261 -1,939 -2,536

PK-3 4-8 9-12 PK-12

ANALYSIS OF CHANGE PROJECTED

5-BREVARD COUNTY SCHOOL DISTRICTORGANIZATION:

Number 4 - Version 1SURVEY:

Page 237: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:219 of 234 Report Date: 6/15/2015 11:49:17 AM

Section 5: Student Membership

Page 238: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:220 of 234 Report Date: 6/15/2015 11:49:17 AM

MEADOWLANE INTERMEDIATE

250 689 0 0 0 0 0 0 0 250 689 0 939 1,114 0 0 0 1,114 1.00 1,114 1,336

MANATEE ELEMENTARY

433 339 0 0 0 0 0 0 0 433 339 0 772 998 0 0 0 998 1.00 998 1,197

LONGLEAF ELEMENTARY

251 217 0 0 0 0 0 0 0 251 217 0 468 790 0 0 0 790 1.00 790 948

LOCKMAR ELEMENTARY

403 294 0 0 0 0 0 0 0 403 294 0 697 892 0 0 0 892 1.00 892 1,070

LEWIS CARROLL ELEMENTARY

298 264 0 0 0 0 0 0 0 298 264 0 562 751 0 0 0 751 1.00 751 901

JUPITER ELEMENTARY

511 325 0 0 0 0 41 15 0 470 310 0 780 930 0 -150 0 780 1.00 780 936

JOHN F TURNER SR ELEMENTAR

481 329 0 0 0 0 0 0 0 481 329 0 810 874 0 0 0 874 1.00 874 1,048

INDIALANTIC ELEMENTARY

337 294 0 0 0 0 0 0 0 337 294 0 631 798 0 0 0 798 1.00 798 957

IMPERIAL ESTATES ELEME

312 236 0 0 0 0 0 0 0 312 236 0 548 729 0 0 0 729 1.00 729 874

HARBOR CITY ELEMENTARY

205 134 0 0 0 0 0 0 0 205 134 0 339 629 0 -44 0 585 1.00 585 702

HANS CHRISTIAN AND

394 329 0 0 0 0 0 0 0 394 329 0 723 884 0 -44 0 840 1.00 840 1,008

GOLFVIEW ELEMENTARY M

386 273 0 0 0 0 0 0 0 386 273 0 659 777 0 0 0 777 1.00 777 932

GEMINI ELEMENTARY

176 217 0 0 0 0 0 0 0 176 217 0 393 711 0 0 0 711 1.00 711 853

GARDENDALE EDUCATION CEN

0 0 0 0 0 0 0 0 0 0 0 0 0 681 0 0 0 681 1.00 681 817

FREEDOM 7 ELEMENTARY S

206 196 0 0 0 0 0 0 0 206 196 0 402 475 0 0 0 475 1.00 475 570

FAIRGLEN ELEMENTARY

341 265 0 0 0 0 0 0 0 341 265 0 606 753 0 0 0 753 1.00 753 903

ENTERPRISE ELEMENTARY

201 173 0 0 0 0 0 0 0 201 173 0 374 729 0 0 0 729 1.00 729 874

ENDEAVOUR ELEMENTARY M

577 252 0 0 0 0 0 0 0 577 252 0 829 990 0 -22 0 968 1.00 968 1,161

DR W J CREEL ELEMENTARY

534 388 0 0 0 0 0 0 0 534 388 0 922 1,154 0 0 0 1,154 1.00 1,154 1,384

DISCOVERY ELEMENTARY

368 235 0 0 0 0 0 0 0 368 235 0 603 980 0 0 0 980 1.00 980 1,176

CROTON ELEMENTARY

329 242 0 0 0 0 0 0 0 329 242 0 571 795 0 0 0 795 1.00 795 954

COQUINA ELEMENTARY

305 211 0 0 0 0 0 0 0 305 211 0 516 693 0 0 0 693 1.00 693 831

COLUMBIA ELEMENTARY

279 185 0 0 0 0 0 0 0 279 185 0 464 751 0 0 0 751 1.00 751 901

CHRISTA MCAULIFFE ELE

399 252 0 41 15 0 0 0 0 440 267 0 707 918 0 -54 0 864 1.00 864 1,036

CHALLENGER 7 ELEMENTARY

239 171 0 0 0 0 0 0 0 239 171 0 410 551 0 0 0 551 1.00 551 661

CAPE VIEW ELEMENTARY

294 155 0 0 0 0 0 0 0 294 155 0 449 548 0 0 0 548 1.00 548 657

CAMBRIDGE ELEMENTARY M

340 188 0 0 0 0 0 0 0 340 188 0 528 765 0 0 0 765 1.00 765 918

AUDUBON ELEMENTARY

323 249 0 0 0 0 0 0 0 323 249 0 572 761 0 0 0 761 1.00 761 913

ATLANTIS ELEMENTARY

270 214 0 0 0 0 0 0 0 270 214 0 484 703 0 0 0 703 1.00 703 843

APOLLO ELEMENTARY

413 289 0 0 0 0 0 0 0 413 289 0 702 902 0 0 0 902 1.00 902 1,082

Elementary

FACILITY NAME PK-3 Memb. Proj.

4-8 Memb. Proj.

9-12 Memb. Proj.

PK-3 Memb. In

4-8 Memb. In

9-12 Memb. In

PK-3 Memb. Out

4-8 Memb. Out

9-12 Memb. Out

PK-3 Memb. Reco.

4-8 Memb. Reco.

9-12 Memb. Reco.

Total COFTE

Exist. Satis. Stud. Stat.

Pos. Remo. Sta.

Neg. Remo. Sta.

New Const. Sta.

Total Sta.

Util. Factor

Reco. Capac.

Year- Round Capac.

Page 239: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:221 of 234 Report Date: 6/15/2015 11:49:17 AM

ANDREW JACKSON MIDDL

0 531 0 0 0 0 0 0 0 0 531 0 531 727 0 0 0 727 0.90 654 872

Middle & Junior High

WESTSIDE ELEMENTARY

444 323 0 0 0 0 0 0 0 444 323 0 767 857 0 0 0 857 1.00 857 1,028

WEST MELBOURNE EL

283 267 0 0 0 0 0 0 0 283 267 0 550 618 0 0 0 618 1.00 618 741

UNIVERSITY PARK ELEMENT

367 211 0 0 0 0 0 0 0 367 211 0 578 811 0 0 0 811 1.00 811 973

TROPICAL ELEMENTARY

393 292 0 0 0 0 0 0 0 393 292 0 685 910 0 0 0 910 1.00 910 1,092

THEODORE ROOSEVELT ELE

179 144 0 0 0 0 0 0 0 179 144 0 323 599 0 0 0 599 1.00 599 718

SURFSIDE ELEMENTARY

214 162 0 0 0 0 0 0 0 214 162 0 376 479 0 -18 0 461 1.00 461 553

SUNTREE ELEMENTARY

278 250 0 0 0 0 0 0 0 278 250 0 528 755 0 0 0 755 1.00 755 906

SUNRISE ELEMENTARY

467 331 0 0 0 0 0 0 0 467 331 0 798 895 0 0 0 895 1.00 895 1,074

SPESSARD L HOLLAND ELEM

252 184 0 0 0 0 0 0 0 252 184 0 436 605 0 0 0 605 1.00 605 726

SOUTH AREA HEAD START

10 0 0 0 0 0 0 0 0 10 0 0 10 36 0 0 0 36 1.00 36 43

SHERWOOD ELEMENTARY

327 214 0 0 0 0 0 0 0 327 214 0 541 609 0 0 0 609 1.00 609 730

SEA PARK ELEMENTARY

194 137 0 0 0 0 0 0 0 194 137 0 331 439 0 0 0 439 1.00 439 526

SATURN ELEMENTARY

426 264 0 0 0 0 0 0 0 426 264 0 690 958 0 -18 0 940 1.00 940 1,128

SABAL ELEMENTARY

314 219 0 0 0 0 0 0 0 314 219 0 533 785 0 -40 0 745 1.00 745 894

ROY ALLEN ELEMENTARY

350 230 0 0 0 0 0 0 0 350 230 0 580 729 0 0 0 729 1.00 729 874

ROBERT LOUIS STEVENSON EL

224 216 0 0 0 0 0 0 0 224 216 0 440 569 0 0 0 569 1.00 569 682

RIVIERA ELEMENTARY

471 236 0 0 0 0 0 0 0 471 236 0 707 777 0 0 0 777 1.00 777 932

RIVERVIEW SCHOOL

10 0 0 0 0 0 0 0 0 10 0 0 10 576 0 0 0 576 1.00 576 691

RALPH M WILLIAMS JR EL

252 197 0 0 0 0 0 0 0 252 197 0 449 715 0 -88 0 627 1.00 627 752

QUEST ELEMENTARY

451 339 0 0 0 0 0 0 0 451 339 0 790 928 0 0 0 928 1.00 928 1,113

PORT MALABAR ELEMENTARY

445 286 0 0 0 0 0 0 0 445 286 0 731 852 0 -18 0 834 1.00 834 1,000

PINEWOOD ELEMENTARY

240 135 0 0 0 0 0 0 0 240 135 0 375 503 0 0 0 503 1.00 503 603

PALM BAY ELEMENTARY

515 302 0 0 0 0 0 0 0 515 302 0 817 1,005 0 0 0 1,005 1.00 1,005 1,206

OCEAN BREEZE ELEMENTARY

298 207 0 0 0 0 0 0 0 298 207 0 505 654 0 -18 0 636 1.00 636 763

OAK PARK ELEMENTARY

413 270 0 0 0 0 0 0 0 413 270 0 683 888 0 0 0 888 1.00 888 1,065

MIMS ELEMENTARY

245 188 0 0 0 0 0 0 0 245 188 0 433 725 0 0 0 725 1.00 725 870

MILA ELEMENTARY

275 154 0 0 0 0 0 0 0 275 154 0 429 707 0 0 0 707 1.00 707 848

MEADOWLANE PRIMARY ELEME

584 16 0 0 0 0 0 0 0 584 16 0 600 824 0 0 0 824 1.00 824 988

Elementary

FACILITY NAME PK-3 Memb. Proj.

4-8 Memb. Proj.

9-12 Memb. Proj.

PK-3 Memb. In

4-8 Memb. In

9-12 Memb. In

PK-3 Memb. Out

4-8 Memb. Out

9-12 Memb. Out

PK-3 Memb. Reco.

4-8 Memb. Reco.

9-12 Memb. Reco.

Total COFTE

Exist. Satis. Stud. Stat.

Pos. Remo. Sta.

Neg. Remo. Sta.

New Const. Sta.

Total Sta.

Util. Factor

Reco. Capac.

Year- Round Capac.

Page 240: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:222 of 234 Report Date: 6/15/2015 11:49:17 AM

WEST SHORE JR/SR HIGH

0 317 588 0 0 0 0 0 0 0 317 588 905 1,404 0 -25 0 1,379 0.90 1,241 1,654

SPACE COAST JR/ SR HIGH

0 381 736 0 0 0 0 0 0 0 381 736 1,117 2,013 0 0 0 2,013 0.90 1,811 2,415

EDGEWOOD JR/ SR HIGH

0 319 503 0 0 0 0 0 0 0 319 503 822 1,191 0 0 0 1,191 0.90 1,071 1,429

COCOA JR/SR HIGH

0 614 1,033 0 0 0 0 0 0 0 614 1,033 1,647 1,930 0 0 0 1,930 0.90 1,737 2,316

COCOA BEACH JR/SR HIGH

0 365 740 0 0 0 0 0 0 0 365 740 1,105 1,628 0 -25 0 1,603 0.90 1,442 1,923

Combination

VIERA HIGH SCHOOL

0 0 1,664 0 0 0 0 0 0 0 0 1,664 1,664 2,396 0 0 0 2,396 0.95 2,276 2,875

TITUSVILLE HIGH

0 0 1,166 0 0 0 0 0 0 0 0 1,166 1,166 1,970 0 0 0 1,970 0.95 1,871 2,364

SATELLITE SENIOR HIGH

0 0 1,042 0 0 0 0 0 0 0 0 1,042 1,042 1,605 0 0 0 1,605 0.95 1,524 1,926

ROCKLEDGE SENIOR HIGH

0 0 1,322 0 0 0 0 0 0 0 0 1,322 1,322 1,766 0 -75 0 1,691 0.95 1,606 2,029

PALM BAY MAGNET SENIO

0 1 1,239 0 0 0 0 0 0 0 1 1,239 1,240 2,751 0 0 0 2,751 0.95 2,613 3,301

MERRITT ISLAND SENIOR

0 0 1,180 0 0 0 0 0 0 0 0 1,180 1,180 2,015 0 0 0 2,015 0.95 1,914 2,418

MELBOURNE SENIOR HIGH

0 0 1,827 0 0 0 0 0 0 0 0 1,827 1,827 2,439 0 0 0 2,439 0.95 2,317 2,926

HERITAGE HIGH 0 0 1,275 0 0 0 0 0 0 0 0 1,275 1,275 2,436 0 0 0 2,436 0.95 2,314 2,923

EAU GALLIE SENIOR HIGH

0 1 1,499 0 0 0 0 0 0 0 1 1,499 1,500 2,300 0 0 0 2,300 0.95 2,185 2,760

BAYSIDE SENIOR HIGH

0 0 1,070 0 0 0 0 0 0 0 0 1,070 1,070 2,353 0 0 0 2,353 0.95 2,235 2,823

ASTRONAUT SENIOR HIGH

0 1 726 0 0 0 0 0 0 0 1 726 727 1,522 0 0 0 1,522 0.95 1,445 1,826

Senior High

THOMAS JEFFERSON MID

0 545 0 0 0 0 0 0 0 0 545 0 545 942 0 0 0 942 0.90 847 1,130

STONE MAGNET MIDDLE

0 793 0 0 0 0 0 0 0 0 793 0 793 1,126 0 0 0 1,126 0.90 1,013 1,351

SOUTHWEST MIDDLE

0 860 0 0 0 0 0 0 0 0 860 0 860 1,308 0 0 0 1,308 0.90 1,177 1,569

RONALD MCNAIR MIDDLE

0 446 0 0 0 0 0 0 0 0 446 0 446 679 0 0 0 679 0.90 611 814

LYNDON B JOHNSON MIDDL

0 716 0 0 0 0 0 0 0 0 716 0 716 1,133 0 0 0 1,133 0.90 1,019 1,359

JOHN F KENNEDY MIDDL

0 591 0 0 0 0 0 0 0 0 591 0 591 910 0 -73 0 837 0.90 753 1,004

JAMES MADISON MIDDLE

0 451 0 0 0 0 0 0 0 0 451 0 451 825 0 0 0 825 0.90 742 990

HERBERT C HOOVER MIDDL

0 491 0 0 0 0 0 0 0 0 491 0 491 732 0 0 0 732 0.90 658 878

DELAURA MIDDLE

0 682 0 0 0 0 0 0 0 0 682 0 682 1,068 0 0 0 1,068 0.90 961 1,281

CENTRAL MIDDLE

0 1,147 0 0 0 0 0 0 0 0 1,147 0 1,147 1,694 0 0 0 1,694 0.90 1,524 2,032

Middle & Junior High

FACILITY NAME PK-3 Memb. Proj.

4-8 Memb. Proj.

9-12 Memb. Proj.

PK-3 Memb. In

4-8 Memb. In

9-12 Memb. In

PK-3 Memb. Out

4-8 Memb. Out

9-12 Memb. Out

PK-3 Memb. Reco.

4-8 Memb. Reco.

9-12 Memb. Reco.

Total COFTE

Exist. Satis. Stud. Stat.

Pos. Remo. Sta.

Neg. Remo. Sta.

New Const. Sta.

Total Sta.

Util. Factor

Reco. Capac.

Year- Round Capac.

Page 241: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:223 of 234 Report Date: 6/15/2015 11:49:17 AM

WHISPERING HILLS EDUCATIO

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

WESTSIDE BUS COMPOUND

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

WEST MELBOURNE MA

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

SATELLITE BUS COMPOUND

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

PLANT OPERATIONS AN

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

OLD CREEL BUS COMPOUND

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

NORTH AREA TRANSPORTATI

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

MID-SOUTH AREA SUPPORT

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

MELBOURNE BUS COMPOUND

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

MCLARTY STADIUM

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

MANATEE BUS COMPOUND

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

GIBSON PARK 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

EDUCATIONAL SERVICES FACIL

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

BEACHSIDE OFFICE

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

520 BUS COMPOUND

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.00 0 0

Ancillary

SOUTH PINE GROVE SCHOOL

0 0 0 0 0 0 0 0 0 0 0 0 0 92 0 0 0 92 1.50 138 138

SOUTH LAKE EDUCATION CEN

0 0 0 0 0 0 0 0 0 0 0 0 0 529 0 0 0 529 1.50 793 793

CLEARLAKE EDUCATION CEN

0 0 0 0 0 0 0 0 0 0 0 0 0 747 0 0 0 747 1.50 1,120 1,120

Vocational/Adult

CUYLER SCHOOL

0 0 0 0 0 0 0 0 0 0 0 0 0 98 0 0 0 98 1.00 98 117

ESE/Alternative

out of out of out of

18,776 22,631 17,610 41 15 0 41 15 0 18,776 22,631 17,610 59,017 88,163 0 -712 0 87,451 85,030 105,318

18,776 22,631 17,610

FACILITY NAME PK-3 Memb. Proj.

4-8 Memb. Proj.

9-12 Memb. Proj.

PK-3 Memb. In

4-8 Memb. In

9-12 Memb. In

PK-3 Memb. Out

4-8 Memb. Out

9-12 Memb. Out

PK-3 Memb. Reco.

4-8 Memb. Reco.

9-12 Memb. Reco.

Total COFTE

Exist. Satis. Stud. Stat.

Pos. Remo. Sta.

Neg. Remo. Sta.

New Const. Sta.

Total Sta.

Util. Factor

Reco. Capac.

Year- Round Capac.

Page 242: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:224 of 234 Report Date: 6/15/2015 11:49:17 AM

Section 6: Financial Summary

Page 243: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:225 of 234 Report Date: 6/15/2015 11:49:17 AM

JUPITER ELEMENTARY $0 $0 $216,764 $70,000 $772,617 $0 $1,059,381

JOHN F TURNER SR ELEM $0 $0 $146,508 $0 $1,570,958 $1,452,946 $3,170,412 $1,162,357

LEWIS CARROLL ELEMEN $0 $0 $37,607 $0 $1,948,922 $636,798 $2,623,327 $509,438

LONGLEAF ELEMENTARY $0 $0 $29,980 $0 $1,676,641 $0 $1,706,621

LOCKMAR ELEMENTARY $0 $0 $50,557 $0 $2,011,811 $1,531,227 $3,593,595 $1,224,982

HANS CHRISTIAN ANDERS $0 $0 $182,389 $20,000 $3,694,996 $0 $3,897,385

HARBOR CITY ELEMENTA $0 $0 $153,721 $20,000 $961,558 $0 $1,135,279

INDIALANTIC ELEMENTAR $0 $0 $136,637 $0 $1,111,302 $576,030 $1,823,969 $460,824

IMPERIAL ESTATES ELEM $0 $0 $58,965 $0 $1,135,512 $538,472 $1,732,949 $430,778

MEADOWLANE INTERMED $0 $0 $279,661 $0 $1,621,937 $0 $1,901,598

MANATEE ELEMENTARY $0 $0 $165,075 $0 $943,731 $0 $1,108,806

MEADOWLANE PRIMARY $0 $0 $36,195 $0 $2,688,242 $0 $2,724,437

MILA ELEMENTARY $0 $0 $219,110 $0 $1,514,776 $1,679,349 $3,413,235 $1,343,479

CHALLENGER 7 ELEMENT $0 $0 $97,722 $0 $541,079 $0 $638,801

CAPE VIEW ELEMENTARY $0 $0 $15,949 $0 $1,804,631 $482,768 $2,303,348 $386,214

COLUMBIA ELEMENTARY $0 $0 $199,460 $0 $263,582 $0 $463,042

CHRISTA MCAULIFFE ELE $0 $0 $214,547 $30,000 $1,001,680 $1,458,221 $2,704,448 $1,166,577

CAMBRIDGE ELEMENTAR $0 $0 $224,461 $0 $341,424 $1,992,262 $2,558,147 $1,593,810

APOLLO ELEMENTARY $0 $0 $116,404 $905,028 $2,109,611 $2,273,736 $5,404,779 $1,818,989

GOLFVIEW ELEMENTARY $0 $0 $200,055 $0 $747,650 $916,584 $1,864,289 $733,267

AUDUBON ELEMENTARY $0 $0 $21,865 $0 $2,119,669 $1,709,944 $3,851,478 $1,367,955

ATLANTIS ELEMENTARY $0 $0 $182,921 $0 $1,932,703 $423,688 $2,539,312 $338,950

COQUINA ELEMENTARY $0 $0 $87,361 $0 $1,703,351 $766,141 $2,556,853 $612,913

FREEDOM 7 ELEMENTARY $0 $0 $134,341 $0 $197,581 $901,181 $1,233,103 $720,945

FAIRGLEN ELEMENTARY $0 $0 $30,168 $0 $3,219,486 $0 $3,249,654

GEMINI ELEMENTARY $0 $0 $180,830 $0 $746,847 $0 $927,677

GARDENDALE EDUCATIO $0 $0 $0 $0 $0 $0 $0

ENTERPRISE ELEMENTAR $0 $0 $105,196 $0 $703,379 $454,916 $1,263,491 $363,933

DISCOVERY ELEMENTARY $0 $0 $689,536 $0 $2,125,256 $585,525 $3,400,317 $468,420

CROTON ELEMENTARY $0 $0 $288,841 $0 $1,735,156 $0 $2,023,997

ENDEAVOUR ELEMENTAR $0 $0 $205,480 $10,000 $980,031 $2,688,984 $3,884,495 $2,151,187

DR W J CREEL ELEMENTA $0 $0 $396,555 $0 $1,794,654 $681,741 $2,872,950 $545,393

Elementary

Facility Site Expansion Cost

Total Site Development Cost

Total Site Improvement Cost

Total Remodeling Cost

Total Renovation Cost

Total New Construction Cost

Overall Totals

Estimated Cost If Year Round School

Page 244: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:226 of 234 Report Date: 6/15/2015 11:49:17 AM

DELAURA MIDDLE $0 $0 $255,981 $0 $2,806,623 $0 $3,062,604

HERBERT C HOOVER MID $0 $0 $85,625 $0 $3,549,476 $576,627 $4,211,728 $461,302

ANDREW JACKSON MIDDL $0 $0 $412,979 $0 $3,153,259 $0 $3,566,238

CENTRAL MIDDLE $0 $0 $56,797 $0 $1,659,024 $0 $1,715,821

Middle & Junior High

SUNTREE ELEMENTARY $0 $0 $219,494 $0 $1,870,737 $0 $2,090,231

SURFSIDE ELEMENTARY $0 $0 $148,975 $10,000 $1,009,268 $920,804 $2,089,047 $736,643

SPESSARD L HOLLAND EL $0 $0 $274,450 $0 $3,686,790 $400,900 $4,362,140 $320,720

SUNRISE ELEMENTARY $0 $0 $27,917 $0 $763,062 $0 $790,979

THEODORE ROOSEVELT $0 $0 $51,226 $0 $3,146,550 $0 $3,197,776

WEST MELBOURNE ELEM $0 $0 $129,501 $0 $1,491,270 $1,375,298 $2,996,069 $1,100,238

WESTSIDE ELEMENTARY $0 $0 $51,749 $0 $1,306,466 $0 $1,358,215

TROPICAL ELEMENTARY $0 $0 $93,431 $0 $2,934,614 $1,750,667 $4,778,712 $1,400,534

UNIVERSITY PARK ELEME $0 $0 $355,412 $0 $1,376,714 $0 $1,732,126

QUEST ELEMENTARY $0 $0 $227,871 $0 $932,480 $0 $1,160,351

PORT MALABAR ELEMENT $0 $0 $118,418 $10,000 $1,837,561 $1,027,359 $2,993,338 $821,887

MIMS ELEMENTARY $0 $0 $101,954 $0 $505,510 $0 $607,464

RALPH M WILLIAMS JR EL $0 $0 $167,165 $40,000 $1,980,982 $416,092 $2,604,239 $332,874

OCEAN BREEZE ELEMENT $0 $0 $269,790 $10,000 $1,408,758 $0 $1,688,548

OAK PARK ELEMENTARY $0 $0 $113,032 $0 $1,596,054 $1,471,936 $3,181,022 $1,177,549

PINEWOOD ELEMENTARY $0 $0 $60,000 $0 $1,283,100 $336,334 $1,679,434 $269,067

PALM BAY ELEMENTARY $0 $0 $326,607 $0 $1,783,990 $696,089 $2,806,686 $556,871

RIVERVIEW SCHOOL $0 $0 $92,800 $0 $0 $0 $92,800

SEA PARK ELEMENTARY $0 $0 $541,409 $0 $1,742,501 $0 $2,283,910

SATURN ELEMENTARY $0 $0 $171,639 $10,000 $4,461,043 $799,268 $5,441,950 $639,414

SOUTH AREA HEAD STAR $0 $0 $0 $0 $115,315 $0 $115,315

SHERWOOD ELEMENTAR $0 $0 $21,889 $0 $2,161,952 $747,995 $2,931,836 $598,396

ROBERT LOUIS STEVENS $0 $0 $107,555 $0 $1,093,674 $0 $1,201,229

RIVIERA ELEMENTARY $0 $0 $76,354 $0 $574,202 $1,316,007 $1,966,563 $1,052,806

SABAL ELEMENTARY $0 $0 $558,300 $20,000 $1,806,612 $924,180 $3,309,092 $739,344

ROY ALLEN ELEMENTARY $0 $0 $145,051 $0 $1,001,710 $0 $1,146,761

Elementary

Facility Site Expansion Cost

Total Site Development Cost

Total Site Improvement Cost

Total Remodeling Cost

Total Renovation Cost

Total New Construction Cost

Overall Totals

Estimated Cost If Year Round School

Page 245: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:227 of 234 Report Date: 6/15/2015 11:49:17 AM

CUYLER SCHOOL $0 $0 $0 $0 $0 $0 $0

ESE/Alternative

EDGEWOOD JR/ SR HIGH $0 $0 $369,818 $0 $264,586 $0 $634,404

COCOA BEACH JR/SR HIG $0 $0 $409,666 $10,000 $1,651,130 $0 $2,070,796

SPACE COAST JR/ SR HIG $0 $0 $125,513 $0 $1,807,252 $0 $1,932,765

COCOA JR/SR HIGH $0 $0 $240,299 $0 $4,851,744 $0 $5,092,043

WEST SHORE JR/SR HIGH $0 $0 $285,806 $10,000 $619,328 $0 $915,134

Combination

TITUSVILLE HIGH $0 $0 $188,598 $0 $2,161,474 $0 $2,350,072

VIERA HIGH SCHOOL $0 $0 $464,480 $0 $3,657,001 $0 $4,121,481

SATELLITE SENIOR HIGH $0 $0 $513,013 $0 $965,990 $0 $1,479,003

EAU GALLIE SENIOR HIGH $0 $0 $434,083 $0 $1,860,036 $727,753 $3,021,872 $582,202

HERITAGE HIGH $0 $0 $93,029 $0 $572,284 $0 $665,313

ASTRONAUT SENIOR HIG $0 $0 $61,932 $0 $1,375,112 $0 $1,437,044

BAYSIDE SENIOR HIGH $0 $0 $87,586 $0 $2,479,609 $0 $2,567,195

MELBOURNE SENIOR HIG $0 $0 $88,999 $0 $8,804,983 $0 $8,893,982

PALM BAY MAGNET SENIO $0 $0 $242,503 $0 $1,585,244 $0 $1,827,747

ROCKLEDGE SENIOR HIG $0 $0 $520,191 $30,000 $5,028,762 $0 $5,578,953

MERRITT ISLAND SENIOR $0 $0 $426,455 $0 $1,841,538 $0 $2,267,993

Senior High

JAMES MADISON MIDDLE $0 $0 $41,044 $0 $1,234,430 $1,321,227 $2,596,701 $1,056,982

LYNDON B JOHNSON MID $0 $0 $122,013 $0 $3,444,225 $2,375,712 $5,941,950 $1,900,570

JOHN F KENNEDY MIDDLE $0 $0 $269,371 $40,000 $2,522,819 $635,976 $3,468,166 $508,781

SOUTHWEST MIDDLE $0 $0 $52,353 $0 $3,778,817 $0 $3,831,170

RONALD MCNAIR MIDDLE $0 $0 $64,056 $0 $710,034 $417,852 $1,191,942 $334,282

THOMAS JEFFERSON MID $0 $0 $54,261 $0 $3,677,805 $0 $3,732,066

STONE MAGNET MIDDLE $0 $0 $74,853 $0 $6,048,260 $776,574 $6,899,687 $621,259

Middle & Junior High

Facility Site Expansion Cost

Total Site Development Cost

Total Site Improvement Cost

Total Remodeling Cost

Total Renovation Cost

Total New Construction Cost

Overall Totals

Estimated Cost If Year Round School

Page 246: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:228 of 234 Report Date: 6/15/2015 11:49:17 AM

NORTH AREA TRANSPOR $0 $0 $0 $0 $456,837 $0 $456,837

OLD CREEL BUS COMPOU $0 $0 $0 $0 $0 $0 $0

MID-SOUTH AREA SUPPO $0 $0 $140,790 $0 $1,440,814 $0 $1,581,604

MCLARTY STADIUM $0 $0 $0 $0 $0 $0 $0

MELBOURNE BUS COMPO $0 $0 $0 $0 $17,994 $0 $17,994

WESTSIDE BUS COMPOU $0 $0 $0 $0 $0 $0 $0

WHISPERING HILLS EDUC $0 $0 $0 $0 $0 $0 $0

WEST MELBOURNE MAINT $0 $0 $0 $0 $0 $0 $0

PLANT OPERATIONS AND $0 $0 $0 $0 $911,014 $0 $911,014

SATELLITE BUS COMPOU $0 $0 $79,420 $0 $380,736 $0 $460,156

GIBSON PARK $0 $0 $0 $0 $0 $0 $0

BEACHSIDE OFFICE $0 $0 $0 $0 $0 $0 $0

520 BUS COMPOUND $0 $0 $0 $0 $1,082,676 $0 $1,082,676

MANATEE BUS COMPOUN $0 $0 $0 $0 $187,658 $0 $187,658

EDUCATIONAL SERVICES $0 $0 $0 $0 $1,723,069 $0 $1,723,069

Ancillary

CLEARLAKE EDUCATION $0 $0 $31,165 $0 $1,398,252 $0 $1,429,417

SOUTH LAKE EDUCATION $0 $0 $0 $0 $1,716,159 $0 $1,716,159

SOUTH PINE GROVE SCH $0 $0 $0 $0 $290,571 $0 $290,571

Vocational/Adult

Total $0 $0 $15,849,529 $1,245,028 $169,308,313 $40,765,163 $227,168,033 $32,612,130

Facility Site Expansion Cost

Total Site Development Cost

Total Site Improvement Cost

Total Remodeling Cost

Total Renovation Cost

Total New Construction Cost

Overall Totals

Estimated Cost If Year Round School

Page 247: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:229 of 234 Report Date: 6/15/2015 11:49:17 AM

Page 248: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:230 of 234 Report Date: 6/15/2015 11:49:17 AM

Section 7: Long Range Planning Summary

Page 249: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:231 of 234 Report Date: 6/15/2015 11:49:17 AM

No items meet the criteria.

Five Year Survey - Ten Year Capacity

6/15/2015

BREVARD COUNTY SCHOOL DISTRICT

Schedule of capital outlay projects projected to ensure the availability of satisfactory student stations for the projected student enrollment in K - 12 programs for the future 5 years beyond the 5-year district facilities work program.

Proposed Location of Planned New, Remodeled, or New Additions to Facilities in 6 thru 10 out years (Section 28).

Five Year Survey - Ten Year Infrastructure

6/15/2015

BREVARD COUNTY SCHOOL DISTRICT

Plans for closure of any school, including plans for disposition of the facility or usage of facility space, and anticipated revenues in the 6 thru 10 out years (Section 29).

Not Specified

Not Specified

Page 250: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:232 of 234 Report Date: 6/15/2015 11:49:17 AM

No items match the criteria.

Five Year Survey - Ten Year Maintenance

6/15/2015

BREVARD COUNTY SCHOOL DISTRICT

District projects and locations regarding the projected need for major renovation, repair, and maintenance projects within the district in years 6 - 10 beyond the projects plans detailed in the five years covered by the work plan.

Other - ESE, etc 2,183 0 0.00 #Error 0 40 #Error

High - District Totals

24,794 23,551 15,708.33 66.70 % 0 16,179 68.70 %

Middle - District Totals

19,580 17,615 13,390.43 76.02 % 0 13,791 78.29 %

Elementary - District Totals

43,601 43,601 33,470.83 76.77 % 0 34,474 79.07 %

90,158 84,767 62,569.59 73.81 % 0 64,484 76.07 %

Grade Level Projections

FISH Student Stations

Actual FISH Capacity

Actual COFTE

Actual Utilization

Actual new Student

Capacity to be added/remove

d

Projected COFTE

Projected Utilization

Five Year Survey - Ten Year Utilization

6/15/2015

BREVARD COUNTY SCHOOL DISTRICT

Schedule of planned capital outlay projects identifying the standard grade groupings, capacities, and planned utilization rates of future educational facilities of the district for both permanent and relocatable facilities.

Five schools currently are configured for grades 7-12.New schools may be required as growth requires.

Combination schools are included with the middle schools for student stations, capacity, COFTE and utilization purposes because these facilities all have a 90% utilization factor. Use this space to explain or define the grade groupings for combination schools.

Page 251: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:233 of 234 Report Date: 6/15/2015 11:49:17 AM

No items match the criteria.

Five Year Survey - Twenty Year Capacity

6/15/2015

BREVARD COUNTY SCHOOL DISTRICT

Schedule of capital outlay projects projected to ensure the availability of satisfactory student stations for the projected student enrollment in K - 12 programs for the future 11 - 20 years beyond the 5-year district facilities work program.

Proposed Location of Planned New, Remodeled, or New Additions to Facilities in the 11 through 20 out years (Section 28).

Five Year Survey - Twenty Year Infrastructure

6/15/2015

BREVARD COUNTY SCHOOL DISTRICT

Plans for closure of any school, including plans for disposition of the facility or usage of facility space, and anticipated revenues in the 11 through 20 out years (Section 29).

Not Specified

Not Specified

Page 252: 2015 EDUCATIONAL PLANT SURVEY - Brevard Public Schoolsfacilities.sp.brevardschools.org/planning/Planning Reports/Education… · 2015 SBBC Educational Plant JuneSurvey - iii - 2015

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

Status:

Active Approved

Survey:

Survey: 4 - Version: 1

District:

5-BREVARD COUNTY SCHOOL DISTRICT

PAGE:234 of 234 Report Date: 6/15/2015 11:49:17 AM

No items match the criteria.

Five Year Survey - Twenty Year Maintenance

6/15/2015

BREVARD COUNTY SCHOOL DISTRICT

District projects and locations regarding the projected need for major renovation, repair, and maintenance projects within the district in years 11 - 20 beyond the projects plans detailed in the five years covered by the work plan.

Other - ESE, etc 2,183 0 0.00 #Error 0 40 #Error

High - District Totals

24,794 23,551 15,708.33 66.70 % 0 16,517 70.13 %

Middle - District Totals

19,580 17,615 13,390.43 76.02 % 0 14,079 79.93 %

Elementary - District Totals

43,601 43,601 33,470.83 76.77 % 0 35,194 80.72 %

90,158 84,767 62,569.59 73.81 % 0 65,830 77.66 %

Grade Level Projections

FISH Student Stations

Actual FISH Capacity

Actual COFTE

Actual Utilization

Actual new Student

Capacity to be added/removed

Projected COFTE

Projected Utilization

Five Year Survey - Twenty Year Utilization

6/15/2015

BREVARD COUNTY SCHOOL DISTRICT

Schedule of planned capital outlay projects identifying the standard grade groupings, capacities, and planned utilization rates of future educational facilities of the district for both permanent and relocatable facilities.

Combination schools are included with the middle schools for student stations, capacity, COFTE and utilization purposes because these facilities all have a 90% utilization factor. Use this space to explain or define the grade groupings for combination schools.

5 Schools are 7-12New schools may be required as growth requires.