DNV Presentation
Introduction to Pipelines in DNV
Asle Vens Director Offshore Pipelines
Poland Dec, 2011
GLOBAL PIPELINE AWARD
2009 WINNER
Det Norske Veritas AS. All rights reserved. Slide 2 05 December 2011
Agenda
Det Norske Veritas (DNV) a short introduction
Introduction to Pipelines in DNV
Introduction to Offshore Pipelines in DNV
Summary of Main DNV Offshore Pipeline Services
Some recent project references Offshore Pipelines
Det Norske Veritas AS. All rights reserved. Slide 3 05 December 2011
DNV an autonomous independent foundation
Det Norske Veritas AS. All rights reserved. Slide 4 05 December 2011
More than 140 years of managing risk
Det Norske Veritas (DNV) is an independent and autonomous
foundation and spend the major part of the profit on research and
development to the benefit of our clients
DNV was established in 1864 in Norway
The main scope of work was to identify, assess and manage risk
initially for maritime insurance companies
Det Norske Veritas AS. All rights reserved. Slide 5 05 December 2011
DNV IT Risk Management
A world leading service
provider of services for
managing IT Risk
DNVs four main business areas
DNV Energy
A world leading service
provider to the energy
industry in safeguarding
and improving business
performance
DNV Maritime
A world leading
classification society
DNV Industry
A world leading provider of
certification, verification,
assessment, training and
solutions for managing risk
Det Norske Veritas AS. All rights reserved. Slide 6 05 December 2011
Highly skilled people across the world
9,000 employees, of which 82% have
university degree
300 offices
100 countries
2,000 employees serving the energy industry from more than 40 locations worldwide
Det Norske Veritas AS. All rights reserved. Slide 7 05 December 2011
Our people a vital resource
People are the core of DNV 85 nationalities
Competency chart DNV staff around the world
9000 employees
Det Norske Veritas AS. All rights reserved. Slide 8 05 December 2011
Expert role in the oil and gas industry
30% DNV is involved in 30% of the worlds LNG terminal projects
38% 38% of the worlds classed Floating Production, Storage and Offloading
vessels (FPSOs) are to DNV class
65% 65% of the worlds offshore pipelines are designed and installed to DNVs pipeline standard
Det Norske Veritas AS. All rights reserved. Slide 9 05 December 2011
The business lifecycle
DNV - assisting Energy Companies along the entire value chain for
pipelines to safeguard and improve business perfomance
Det Norske Veritas AS. All rights reserved. Slide 10 05 December 2011
Our services & solutions
SHE Risk Management
We develop, implement,
maintain and continually
improve best practices in
SHE management
Enterprise Risk Management
We provide a complete
view of your organisations
total risk exposure and
manage these risks in an
integrated way
Verification
We ensure your projects are
properly managed through
transparent risk
based verification and
certification
Technology Qualification
We provide you with the
confidence that technology
will function reliably
Det Norske Veritas AS. All rights reserved. Slide 11 05 December 2011
Our services & solutions, continued
Certification & Training
We provide certification &
training services to build
trust and competence
within your organisation
and with your stakeholders
IT Risk Management
We safely and
responsibly manage risks
related to ICT systems
and software
Operations Excellence
We safeguard integrity and
maintain optimal production
safely and cost-efficiently
Offshore Classification
We assist you to comply
with classification and
statutory requirements for
MOUs and FPSOs
Det Norske Veritas AS. All rights reserved. Slide 12 05 December 2011
DNV Energy Market Target Areas
Managing
risk
Natural Gas/LNG
Utilities Cleaner energy and
renewables
Arctic Operations &
Technology
Deep and ultra-deep
water field
development
Refining &
petrochemicals
MOUs and FPSOs
Onshore
pipelines
Operations
excellence
Offshore
pipelines
Det Norske Veritas AS. All rights reserved.
Pipelines in DNV
Pipeline services are DNVs largest
activity within the Energy Market
DNV is involved in all phases for both
Onshore and Offshore pipelines
45% of our pipeline revenue comes
from onshore projects
55% of our pipeline revenue come
from offshore projects
Det Norske
Veritas
AS. All
rights
reserved
Slide 13 05 December 2011
Slide 14 05
Decembe
r 2011
In-house Multidiscipline Capabilities
DNV has all necessary core competencies to cover the entire pipeline value
chain from planning through to de-commission
DNV Pipeline Resources DNV has in the order of 250-300 people globally that are mainy occupied with
pipeline related work. Resources are located:
Offshore Pipelines:
- Norway (Hvik, Stavanger)
- UK (Aberdeen, London)
- Denmark (Copenhagen)
- Russia (Moscow)
- USA (Houston, Columbus)
- Brazil (Rio)
- South Africa (Durban)
- MiddleEast (AbuDhabi)
- India (Bombay)
- Singapore
- Malaysia (KL)
- Taiwan (Kaohsiung)
- Vietnam (Vongtau)
- China (Shanghai)
- Australia (Perth)
Det Norske Veritas AS. All rights reserved Slide 15 05 December 2011
Onshore Pipelines:
- Norway (Hvik)
- UK (Aberdeen, London)
- USA (Houston, Columbus)
- Canada (Calgary)
- Singapore
- Vietnam (Vongtau)
- China (Shanghai, Beijing)
- Australia (Brisbane)
Det Norske Veritas AS. All rights reserved. Slide 16 05 December 2011
DNV serving the energy industry
Offshore pipelines
Det Norske Veritas AS. All rights reserved.
Tuesday, 02 February 2010
17
DNV Pipeline Codes History and Background DNV Rules for Submarine Pipeline Systems, 1976
- The first complete pipeline code for offshore pipelines
- Based on allowable stress format.
DNV Rules for Submarine Pipeline Systems, 1981 - Update of 1976 version and became a wide spread code
DNV Rules for Submarine Pipeline Systems, 1996 - A completely new version, incorporating the limit state format with calibrated safety factors
based on the SUPERB JIP work
DNV-OS-F101-2000 - Converted to pure technical standard
- Hearing process resulted in more than 3 500 comments from industry (more than 20 companies)
- DNV interprets this as massive interest instead of critics
Last issue 2007
Global Pipeline Award 2009
GLOBAL PIPELINE AWARD
2009 WINNER
Det Norske Veritas AS. All rights reserved. Slide 18 05 December 2011
The Offshore Pipeline Standard
Enables the operators to reduce CAPEX without compromising safety
Technical requirements harmonized with ISO
Limit state based design criteria with calibrated safety factors
Used for 60-70% of the subsea pipelines in the world !
Only code with an organized feed-back system
Supported by large portfolio of RPs - DNV-RP-F101 Corroded Pipelines
- DNV-RP-F102 Pipeline Field Joint Coating
- DNV-RP-F103 Cathodic Protection
- DNV-RP-F105 Free Spanning Pipelines
- DNV-RP-F106 Pipeline Coatings
- DNV-RP-F107 Pipeline Protection
- DNV-RP-F108 Fracture Control
- DNV-RP-F109 On-Bottom Stability
- DNV-RP-F110 Global Buckling
- DNV-RP-F111 Trawling
- DNV-RP-F113 Pipeline Subsea Repair
- DNV-RP-F116 Subsea Pipeline System Integrity Management (will be issued soon)
Det Norske Veritas AS. All rights reserved. Slide 19 05 December 2011
Recommended
Practices
DNV-RP
Offshore Standard
DNV-OS
Offshore Service
Specification
DNV-OSS
DNV Offshore Codes
F A B C D E
RECOMMENDED PRACTICE
RP-F102
PIPELINE FIELD JOINT COATING
AND FIELD REPAIR OF
LINEPIPE EXTERNAL COATING
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F102
PIPELINE FIELD JOINT COATING
AND FIELD REPAIR OF
LINEPIPE EXTERNAL COATING
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F103
CATHODIC PROTECTION
OF SUBMARINE PIPELINES
BY GALVANIC ANODES
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F103
CATHODIC PROTECTION
OF SUBMARINE PIPELINES
BY GALVANIC ANODES
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F10X
STRUCTURAL DESIGN OF
HIGH PRESSURE/HIGH TEMPERATURE
PIPELINES
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F10X
STRUCTURAL DESIGN OF
HIGH PRESSURE/HIGH TEMPERATURE
PIPELINES
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F203
COUPLED ANALYSES
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F203
COUPLED ANALYSES
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F204
RISER FATIGUE
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F204
RISER FATIGUE
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F205
RISER COLLISION
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F205
RISER COLLISION
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F1XX
On Bottom Stability
of pipelines
DET NORSKE VERITAS
RECOMMENDED PRACTICE
RP-F1XX
On Bottom Stability
of pipelines
DET NORSKE VERITAS
R ECOMMENDED P RACTICE
RP - F1XX
On Bottom Stability
of pipelines
D ET N ORSKE V ERITAS
R ECOMMENDED P RACTICE
RP - F1XX
Installation calculation
Procedures of pipelines
D ET N ORSKE V ERITAS
R ECOMMENDED P RACTICE
RP - F1XX
On Bottom Stability
of pipelines
D ET N ORSKE V ERITAS
R ECOMMENDED P RACTICE
RP - F1XX
Interference between
Trawl gear and pipelines
D ET N ORSKE V ERITAS
Det Norske Veritas AS. All rights reserved.
Cooperation with the industry
DNV cooperate extensiveley with the pipeline industry, through JIPs,
standardisation organisations, Universities, Committees, etc.
DNV is an active member in several pipeline standardisation and R&D
organisations like ISO, ASME, API, NORSOK, NACE, PRCI, EPRG, etc
DNV has presently the President of NACE (Oliver Moghassi)
DNV runs an International Technical Offshore Pipeline Commitee
Det Norske
Veritas
AS. All
rights
reserved
Slide 20 05 December 2011
21
External DNV Pipeline Committee
Chairman: Colin McKinon (J.P.Kenny)
Operators:
- BP
- ChevronTexaco
- Dong
- ExxonMobil
- Gasprom
- Gassco
- Mrsk
- Petrobras
- Shell
- Statoil
- Total
- Woodside
Manufacturer: - JFE-steel
- Tenaris
- VM tubes
- Tata-group
- Europipe
Contractors - Allseas
- Saipem
- Subsea 7
- Technip
- Heerema
Universities:
NUS
Regulators. - PTIL
- HSE GSI
Designers:
J. P. Kenny
Atkins Boreas
IntecSea
Det Norske Veritas AS. All rights reserved. Slide 23 05 December 2011
Pipeline Software
FATFREE - A professional engineering analysis software for free spanning pipelines
- Based on the state of the art principles of the DNV RP-F105 for Free Spanning Pipelines
StableLines - A professional engineering analysis software for pipelines on-bottom stability
- Based on the state of the art principles of DNV RP DNV-RP-F109
- Making safe decisions on necessary weight simpler.
PET (Pipeline Engineering Tool) - A professional engineering calculation tool for early phase pipeline assessment
- Contains the following modules: DNV-OS-F101 Design Checks, Weight and Volume, End Expansion, Upheaval Buckling, On-Bottom Stability, Fatigue Screening, Reel Straining, Reel Packing, J-Lay, S-Lay, Cathodic Protection
SilverPipe - A professional web based software for Pipeline Integrity Management
- Pipeline Data Management
- Risk Assessment
- Inspection planning
- Integrity Assessment
- Condition & Change Assessment
- Response and Mitigation activities
- Organization and System effectiveness
- Report generator
Det Norske Veritas AS. All rights reserved. Slide 25 05 December 2011
Main Offshore Pipeline Service Areas
Early Phase Support
Verification & Certification
Pipeline Design & Engineering support
Technology Qualification, Advisory and Specialist Services
Project Management and Consultancy Services
Technical Development & Research
Pipeline Integrity Management inc. RBI
Re-qualification and re-assessment
Risk analysis and environmental impact analysis
Supervision during Fabrication, Installation and Commissioning
Material Testing & Consultancy
Pipeline Control Systems (control software)
Marine Warranty Surveys
Pipeline Training
Design and PIM Software
Det Norske Veritas AS. All rights reserved. Slide 32 05 December 2011
Pipeline Research & Development
Maintenance/update of state-of-the art Pipeline codes; Offshore Pipeline Standard OS-
F101 and associated Recommended Practices
DNVs R&D services are used to customise pipeline theory into safe and cost effective solutions. Managing/performing Joint Industry Projects Development of Recommended Practices
Development of analytical tools and methods
Knowledge development & transfer
Some recent JIP projects:
High Pressure / High Temperature
Trawling
Stability
Free Spanning Pipelines
Strain concentration due to concrete coating
Deep pipe (s-lay in deep water)
Laying Criteria
Pipeline Integrity Management
Corroded Pipelines
Coatings & CP design
Clad and lined pipes (Phase 1/2/3)
Det Norske Veritas AS. All rights reserved Slide 33 05 December 2011
Resent, ongoing and planned Pipeline R & D Projects
Recently completed projects:
- EOIP: Pipelines for the future Pipeline technology for the next 10-15 years
- Residual stress / strain for pipeline girth weld under high strain (measure residual stress)
- Develop method for SENT test method for sour service
- Update of DNV-RP-106 External coating
- Development of RP for AUT System Qualification
Ongoing.
- EOIP: X-Stream - Deepwater Pipelines Cost effective solution deep-water gas pipelines
- Update of DNV -OS-F101
- Extended development of Silverpipe (Pipeline Integrity Management Software)
- Development of AUT workmanship style acceptance criteria
- Standard for verification and certification Onshore pipelines
In planning stage:
- EOIP - Floating pipelines
12 Internally funded project:
Slide 34 05
Decembe
r 2011
Resent, ongoing and planned Pipeline R & D Projects 19 JIP (DNV management):
- Recently completed:
- HIPPS System Design
- Ice pipe Arctic pipelines - Spiral Welded Pipes for offshore us (Phase 1 completed)
- Ongoing:
- Clad and liner pipe phase 3
- Pre-commissioning of pipelines
- Pipeline Integrity Management (DNV RP-116) Phase 2 - HPHT pipelines (merging of Hotpipe and Safebuck)
- ART ILI tool development
- CO2 pipelines phase 2 - Treatment of residual stress in the ECA of pipeline girth welds under high plastic deformation
- Fatigue of girth welds with defects
- Reeling, ECA and sour service
- Horizontal Directional Drilling
- Pipeline spool design (Planning/ongoing)
- In planning stage:
- High strength steel (x80) & sour service
- Corroded pipes (incl. update of DNV-RP-101)
- Installation design and analysis
- Design of concrete coating
- Assessment of pipeline components
4 Other (not DNV managed): - MTI JIP Corroded pipes with complex shape corrosion (completed) - NORSOK Lifetime extension offshore pipelines (completed)
- Sintef Fracture control Phase 2 (Ongoing)
- Safebuck (ongoing)
- PRCI un-piggable pipelines Planning
Det Norske Veritas AS. All rights reserved. Slide 40 05 December 2011
Pipeline Training
DNV courses with external participants
In-house, tailor-made courses for clients
Knowledge transfer related to pipeline codes and experience from various projects
Wide range of standard pipeline related courses:
- Basic pipeline
- Pipeline Design
- Free span
- On-bottom stability
- Global Buckling
- Trawling
- Corroded pipelines
- Pipeline Integrity Management
- Cathodic protection and coating
- Materials
- Construction and Installation
- Pre-Commissioning and Commissioning
Hydro
Det Norske Veritas AS. All rights reserved. Slide 41 05 December 2011
Pipeline Training - courses
Basic 2 days
Trawling
Interference - 1 day DNV-OS-F111
Design 3 days
DNV-OS-F101
Corroded Pipelines 1 day DNV-OS-F101
Global Buckling 2 days DNV-RP-F110
PIM Offshore 2 days
Free Span - 2 days DNV-RP-F105
Cathodic Protection & Coatings 1 day
On-Bottom Stability 1 day DNV-RP-F109
OS-F101 Updated
Det Norske Veritas AS. All rights reserved. Slide 42 05 December 2011
Some Selected Projects References
Det Norske Veritas AS. All rights reserved. Slide 43 05 December 2011
Some Selected Recent Pipeline Projects
Oman-India (24, 3525m deep, 1400km long) Feasibility study
Blue Stream (24, 2150m deep, 2x380km long) Certification/Advisor
Ormen Lange about 850m Advisor, verification, TQ, inspection, surveillance
Langeled (42/44, 380m deep, 1200km long) Design/Installation verif.
Taichung-Tunghsiao-Tatan (36, 110m deep, 145km long) - PMC
Iran- India (24-26, 3700m deep, 1600km long) Feasibility study
Blind Faith (16 and 18, 2134m deep, 2x60km long) Installation verf.
Perido Norte (2x18, 2530m deep, 168 and 120km) Design/Installation verf.
Nord Stream (48, 220m deep, 2x1220km long) Certification
TAP (42, 820m deep, 115km long) FEED verification + various studies
Reliance KG D6 Deep Water Project (up to 2000m) - Certification
South Stream (4x32, 2150m deep, 900km long) FEED verification
IGI Poseidon (32, 1370m deep, 207km long) FEED verification
Det Norske Veritas AS. All rights reserved. Slide 44 05 December 2011
The Blue Stream - Energy needs of Turkey
The industrialisation of Turkey
- Historically energy needs met through
- Gas import from Russia via Balkan pipeline
- LNG from Algeria
- Crude oil import
- Natural gas consumption
- 10BCM in 1998
- Expected to reach 80 BCM in 2020
Challenges:
- Competence, financing, insurance
- Supply reliability
Det Norske Veritas AS. All rights reserved. Slide 45 05 December 2011
The Blue Stream Pipelines
2 lines; 16 BCM capacity
24 diameter (610 mm)
31.8 mm wall thickness
380/390 km long
K.P. 15
Russian
side Abyssal
Plain
Turkish
side -2500
-2000
-1500
-1000
-500 0
2,150 m
Det Norske Veritas AS. All rights reserved. Slide 46 05 December 2011
The challenges
Water depth of 2,150 m
Sediments with high levels of H2S
Seismic activity
Landslides and sediment flow
Difficult topography of the Russian
coastal slope (very steep sloops)
The required technological
innovation
The tight schedule
Development of repair systems
Det Norske Veritas AS. All rights reserved. Slide 47 05 December 2011
Certification of Blue Stream
Certification Verification
Design
Fabrication
Installation &
Testing
Statement of
Compliance Certificate of
Compliance
Blue Stream Pipeline System
Det Norske Veritas AS. All rights reserved. Slide 48 05 December 2011
Ormen Lange and Langeled
Det Norske Veritas AS. All rights reserved. Slide 49 05 December 2011
MULTIPHASE PRODUCTION LINE
MEG LINE
UMBILICAL
In-line
Tees
20 spools
Pigging loop /
HP-RV Module
N
A
B
Ormen Lange Field layout
HUBS for future
hot-tap tees
Det Norske Veritas AS. All rights reserved. Slide 50 05 December 2011
Ormen Lange Pipelines
Det Norske Veritas AS. All rights reserved. Slide 51 05 December 2011
DEVELOPMENT
AREA
WATER DEPTH = 850 m
TOP OF SLIDE EDGE
WATER DEPTH = 250 m
10 KM
N
TO SHORE
Survey coverage of the slide area
Storegga slide area
Det Norske Veritas AS. All rights reserved. Slide 52 05 December 2011
Det Norske Veritas AS. All rights reserved. Slide 53 05 December 2011
DNV pipeline SoW 2004/2005
Pipeline design verification
Project guideline VIV
Hazid
Pre-commisioning/RFO assistance
Trawl protection pipelines/MEG/umbilicals
Fracture arrest
Environmental data verification
Trawl Impact study
Use of Beluga
Environmental data - current
Techn assistance MEG/30 installation contracts
Independent verification analyses
Fatigue testing
Weld defects (ECA)
Det Norske Veritas AS. All rights reserved. Slide 54 05 December 2011
DNV pipeline SoW 2006
Pipeline design verification - continue
Techn assistance MEG/30 installation contracts
Studies:
Environmental data current
Independent verification analyses lateral buckling (abacus)
Verification of pipelay in curves
Fatigue safety factors during installation
MEG verification installation analyses
VIV benchmarking
Det Norske Veritas AS. All rights reserved. Slide 55 05 December 2011
Langeled
Det Norske Veritas AS. All rights reserved. Slide 56 05 December 2011
Langeled 42/44 gas pipeline
DNV Involvement:
- Detailed Design verification
- Risk assessment
- Installation Surveillance
- Various other technical studies and support
for Hydro/Statoil and Contractors
Det Norske Veritas AS. All rights reserved. Slide 57 05 December 2011
Nord Stream Pipeline Routing
Det Norske Veritas AS. All rights reserved. Slide 58 05 December 2011
DNVs Involvement in Nord Stream
Nord Stream AG is building 2 gas pipelines from Vyborg (Russia) to
Greifswald (Germany) across the Baltic Sea.
- The 48'' pipelines will be the longest offshore pipelines in the world (ca 1220
km each).
DNV has verified the conceptual/FEED study of Nord Stream for
Gazprom (2006).
DNV has been engaged by Nord Stream AG since late 2007 to:
VERIFY that line 1 meets the requirements of DNV OS F-101 for:
- design,
- fabrication, and
- installation
Upon successful completion of these phases, CERTIFY the pipeline
system according to DNV OSS 301.
Det Norske Veritas AS. All rights reserved. Slide 59 05 December 2011
Blue Stream Pipeline Certification -GASPROM
2 lines; 16 BCM capacity
24 diameter (610 mm)
31.8 mm wall thickness
380/390 km long
K.P. 15
Russian
side Abyssal
Plain
Turkish
side -2500
-2000
-1500
-1000
-500 0
2,150 m
Det Norske Veritas AS. All rights reserved. Slide 60 05 December 2011
BS - Challenges
Water depth of 2,150 m
Sediments with high levels of H2S
Seismic activity
Landslides and sediment flow
Difficult topography of the Russian
coastal slope (very steep sloops)
The required technological
innovation
The tight schedule
Development of repair systems
Det Norske Veritas AS. All rights reserved. Slide 61 05 December 2011
Ormen Lange and Langeled Verification/Tech. Services
Det Norske Veritas AS. All rights reserved. Slide 62 05 December 2011
Ormen Lange Pipelines Norway deepest
Det Norske Veritas AS. All rights reserved. Slide 63 05 December 2011
DEVELOPMENT
AREA
WATER DEPTH = 850 m
TOP OF SLIDE EDGE
WATER DEPTH = 250 m
10 KM
N
TO SHORE
Survey coverage of the slide area
Storegga slide area
Det Norske Veritas AS. All rights reserved. Slide 64 05 December 2011
Det Norske Veritas AS. All rights reserved. Slide 65 05 December 2011
DNV pipeline SoW 2004/2005
Pipeline design verification
Project guideline VIV
Hazid
Pre-commisioning/RFO assistance
Trawl protection pipelines/MEG/umbilicals
Fracture arrest
Environmental data verification
Trawl Impact study
Use of Beluga trenshing machine in deep water
Environmental data - current
Technical assistance MEG/30 installation contracts
Independent verification analyses
Fatigue testing
Weld defects (ECA)
Det Norske Veritas AS. All rights reserved. Slide 66 05 December 2011
DNV pipeline SoW 2006
Pipeline design verification - continue
Techn assistance MEG/30 installation contracts
Studies:
Environmental data current
Independent verification analyses lateral buckling (abacus)
Verification of pipelay in curves
Fatigue safety factors during installation
MEG verification installation analyses
VIV benchmarking
Det Norske Veritas AS. All rights reserved. Slide 67 05 December 2011
Langeled World Longest Pipeline
Det Norske Veritas AS. All rights reserved. Slide 68 05 December 2011
Langeled 42/44 gas pipeline
DNV Involvement:
- Detailed Design verification
- Risk assessment
- Installation Surveillance
- Various other technical studies and support
for Hydro/Statoil and Contractors
Det Norske Veritas AS. All rights reserved. Slide 69 05 December 2011
Nord Stream - Certification
Det Norske Veritas AS. All rights reserved. Slide 70 05 December 2011
DNVs Involvement in Nord Stream
Nord Stream AG is building 2 gas pipelines from Vyborg (Russia) to
Greifswald (Germany) across the Baltic Sea.
- The 48'' pipelines will be the longest offshore pipelines in the world (ca 1220
km each).
DNV has verified the conceptual/FEED study of Nord Stream for
Gazprom (2006).
DNV has been engaged by Nord Stream AG since late 2007 to:
VERIFY that the NordStream pipelines meets the requirements of DNV OS F-101
for:
- design,
- fabrication
- Installation
- Pre-commissioning
Upon successful completion of these phases, CERTIFY the pipeline
system according to DNV OSS 301.
Det Norske Veritas AS. All rights reserved. Slide 72 05 December 2011
Taichung-Tunghsiao-Tatan 36 Gas Export
Yung-An Terminal
26 onshore trunkline
Tunghsiao
Tatan Power Plant
36 existing offshore pipeline
Taichung
terminal
New 36 offshore pipeline
Two Offshore Pipeline
Four Onshore Pipelines
Onshore Facilities:
Receiving Terminals
Meetering stations
Filtering stations
Mixing and Distribution stations
Project Management and Consultancy Service for CPC
Det Norske Veritas AS. All rights reserved. Slide 73 05 December 2011
Taichung-Tunghsiao-Tatan 36 Gas Export
Scope of Service for PMC Management
includes:
- Pre-EPC Contract Phase
- Pre-EPC Project Management
- Basic Design/Engineering for Offshore
Pipelines
- Detailed Design for Onshore Facilities
- Preparation of Tender Package
- Evaluation of EPC Tender
- Negotiation with potential contractors
- Post-EPC Tender Phase
- Post-EPC Project Management
- Review and verification of detailed design
by EPC Contractor
- Onshore Fabrication Supervision
- Offshore Installation Supervision
- Pre-commissioning Supervision
68.5899(RFE)
68.5899(RFE)
Segment 0-2 & 0-3 Segment 1
Segment 2
Segment 0-1
Segment 0-4
Taichung
Tunghsiao
Det Norske Veritas AS. All rights reserved. Slide 74 05 December 2011
Reliance Industries Ltd KG-DWN-98/3 Project (Krishna Godavari Block KG-D6) - Certification
Subsea structures: - 1 Deepwater PLEM;
- 6 manifolds;
- 9 Subsea Distribution Assemblies/units;
- 1 umbilical distribution hub
- PLETS
Subsea wells
Water depth 400 2700 m
Pipelines / flowlines: - Trunk lines (5), flowlines (21), MEG (3), vent (7).
- Size ranging from 24 to 3.5
Umbilicals (11 nos)
Control & Riser Platform
CRP
Computer
Model
(from DNV
Independent
Analysis)
Det Norske Veritas AS. All rights reserved. Slide 75 05 December 2011
Project Highlights-2: History of DNVs Involvement
Work awarded to DNV on nomination, based on the past relationship
with Reliance. DNV is perceived by RIL as most competent agency for
many of the services related to the project.
DNV has been the certification and verification agency for this project
from Concept to Commissioning and helped Reliance in Quality,
technology and integrity functions.
- Concept and FEED (2002-2004):
- FEED Optimization & Updating (Year 2006-2007):
- Design, Fabrication, Installation, commissioing Phase (Year 2007-2009):
Use the risk based approach in verification according to DNV OSS
300
Certificate of Compliance issued at end of the project.
Det Norske Veritas AS. All rights reserved. Slide 76 05 December 2011
DNV has 7,000 employees
DNV Energy 1,700 employees serving the energy industry from more than 40 locations worldwide
Project Activities- Multiple Locations Globally
Design review
Subsea Control System
Hovik, Norway
Overall Project
Management,
Mumbai, India
Quantitative Risk Assessment & Hazop
Studies
Malaysia
Design review
Main
Singapore
Design review
CRP Design
Houston, USA
Inspection of Line Pipes
Japan
Inspection of Line Pipes
Germany, France
Inspection of Subsea system
Norway
Inspection of
Jacket
Houston, USA
Inspection of Deck & Topsides
United Arab Emirates
Inspection of Subsea
equipment
Malaysia
Survey of Offshore Installations-India
Inspection of other items:
UK
Houston
Los Angeles
Belgium
Italy
Singapore
Det Norske Veritas AS. All rights reserved. Slide 77 05 December 2011
The End
The frustration of bad quality last longer than the irritation of a high price