  • 8/12/2019 19 319 13-FP _Norfolk Cleaning Cooler

    1/1

    To (Knh gi): Norfolk Date (Ngy): Nov 8th, 2013Attn (ng/B ): Mr. HiuHP: 0908.080677

    Fax:

    Tel:

    Email: [email protected]

    Machine type (Loi my ) PBZ 4750Serial number (S s-ri)

    STT Slng n gi Thnh ti n

    -

    1 1 58,560,000 58,560,000

    2 1 1,280,000 1,280,000

    VND 59,840,000

    VND 5,984,000

    VND 65,824,000

    1. The quotation is valid within 30 days (Bn cho gi c gi trtrong vng 30 ngy )

    2. Price does not include repair & parts replacement (Gi khng bao gm sa cha & phtng thay th)

    5.Warranty: As Atlas Copco's Warranty Policy.(Bo hnh: Theo chnh sch ca Atlas Copco )

    7. Please T/T your payment to (Vui lng chuyn khon cho chng ti theo thng tin nhsau ):

    ATLAS COPCO VIETNAM CO., LTD. - BINH DUONG BRANCH

    L VBo Linh

    Aftermarket Sales Specialist

    Mobile: 0903 918 356

    Fax: 0650 373 8488

    Email: [email protected]

    Amount

    (VND)

    F-PCTS01-03-07/01/13-Rev.00

    Labor : 3 serviceman x 4days

    SERVICE QUOTATION (WITHOUT SPARE PARTS) No. : 19.319.13 FP (1st. Rev)

    BN CHO GI DCH V(KHNG BAO GM PHTNG) S: 19.319.13 FP (1st. Rev)

    Item QtyUnit Price

    (VND)Description

    M t

    10% VAT (GTGT)TOTAL (Tng cng)

    PBZ 4750-Labor to remove cooler and do cleaning :

    4. Working time: 8:00-17:00 from Monday to Friday. If service is required out of this time frame (from 17:00 onwards

    or on weekend, holidays) the additional charges will be applicable as multiplied by 1.5 for overtime, 2 for weekend

    Job description::

    - -shut off water supply to machine and drain out

    - dismantll cover, doors, piping, jointing part make way for

    cooler cleaning

    - remove the front and the back cover from all cooler

    - One by one tubing cooler cleaning by service tool

    - re-cleaning all tubing by clean water

    - Replace all oring of all coolers- Re install back all parts

    - Open water supply and check for leaking, release air logged/

    fix if neccessary

    - Reinstall all doors

    - Test run machine

    - Report

    Amount (Thnh tin )

    Notes

    Transportation

    Sign and stamp (K tn & ng du)

    3. Time of work performance (Thi gian thc hin cng vic ):

    (Xc nhn t hng)

    (Thi gian lm vic: t8:00 n 17:00 tthhai n thsu.Nu cc cng vic c yu cu ngoi thi gian ny (tcl t17:00 tri hoc cc ngy cui tun, ngy l) th AC stnh thm chi ph nhhs1.5 cho

    6. Term of Payment (iu kin thanh ton ): T/T 100%, within 30 days from invoice dateThanh ton 100% trong vng 20 ngy ktngy xut ha n)

    ngoi gi, hs2 cho th7-CN v hs3 cho ngy l.)

    Confirmed by customer

    and 3 for public holidays.