170730001 e 13

Embed Size (px)

Citation preview

  • 8/11/2019 170730001 e 13

    1/66

    Alcatel-Lucent GSM

    Install 9100 Outdoor BTS

    BTS Document

    Installation & Dismantling Manual

    3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    2/66

    Status RELEASED

    Short title INS

    All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel-Lucent.

    BLANK PAGE BREAK

    2 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    3/66

    Contents

    Contents

    Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

    1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

    1.1.1 Hardware Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.2 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101.1.3 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101.1.4 Initial State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.1.5 Final State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.1.6 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.1.7 Group Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

    1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141.2.2 Site Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151.2.3 External Tasks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

    1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161.4 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

    1.4.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 171.4.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211.4.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

    2 Scenario . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232.1 Before Going Onsite . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 242.2 Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

    2.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 242.2.2 Required Knowledge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

    2.3 Install at Final Location . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 252.3.1 Unpack Racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 252.3.2 Dismantle Racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 262.3.3 Transport Racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 322.3.4 Position and Fix Racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 342.3.5 Install Batteries (If Necessary) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37

    2.4 Install Power Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 382.4.1 Run Power Cables at BTS Side . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 382.4.2 Connect Power Cables at BTS Side . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41

    2.5 Connect PCM Power Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 432.5.1 Run PCM Cables at BTS Side . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 432.5.2 Connect PCM Cables at BTS Side . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45

    2.6 Connect Antenna Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 492.6.1 Install Jumpers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 492.6.2 Connect Jumper to Antenna Coaxial . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51

    2.6.3 Connect and Label Antenna Jumpers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 522.7 Install Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 552.7.1 Connect External Alarm Cables (Optional) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 552.7.2 Install Synchronization Cables (Optional) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61

    2.8 Fit CAD Terminal Block (120 Ohm Cable) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 632.9 Finish Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65

    3BK 17073 0001 RJZZA Ed.13 3 / 66

  • 8/11/2019 170730001 e 13

    4/66

    Contents

    4 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    5/66

    Preface

    Preface

    Purpose This document describes how to install a 9100 outdoor BTS in theAlcatel-Lucent BSS subsystem.

    Whats New In Edition 13Overall document quality was improved following an editorial review.

    In Edition 12New equipment names were updated.

    In Edition 11The system title was updated.

    In Edition 10The document structure was updated.

    In Edition 09The new logo and system title were updated.

    In Edition 08The type, category and mnemonic were updated.

    In Edition 07The DDF label reference was changed.

    In Edition 06The naming rules were updated.

    In Edition 05Information concerning the new generic CCL was added.

    In Edition 04ITL 260 and ITL 265 were applied.

    3BK 17073 0001 RJZZA Ed.13 5 / 66

  • 8/11/2019 170730001 e 13

    6/66

    Preface

    In Edition 03The following information was added or modified:

    New installation kits

    Alarm cabling

    PCM cabling

    Synchronization cabling

    The TMA section was removed.

    In Edition 02The microwave section was removed.

    In Edition 01First official release of the document.

    Audience This document is intended for:Alcatel-Lucent qualified installers

    Site administrators

    Supervisors

    Project managers

    Field service technicians

    Occasional users.

    Assumed Knowledge You must have a basic understanding of the following:Basic knowledge of Alcatel-Lucent BSS equipment

    Experience of electrical mounting cabling.

    6 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    7/66

    1 Overview

    1 OverviewThis Overview gives information needed by project managers and foremen, forpresentation to the customer and for site planning.

    3BK 17073 0001 RJZZA Ed.13 7 / 66

  • 8/11/2019 170730001 e 13

    8/66

    1 Overview

    1.1 Presentation

    1.1.1 Hardware Description

    1.1.1.1 Rack ConfigurationThe following figure shows the 9100 BTS Medi Layout in an example 3x4configuration.

    2

    3

    4

    1

    BTS 2

    Subrack 2/ 3

    BTS 1Side compartment

    OPTIONS

    DCDPACRI

    Subrack 2/ 2

    AIR

    TRE

    TRE

    TRE

    T

    RE

    FANU FANU FANU

    BACO ACIN

    PM08

    PM08

    PM08

    PM08

    PM08

    FANU FANUFANU

    BCU 1

    SBS 40FANU FANUFANU

    TRE

    TRE

    TRE

    TRE

    AIR

    AIR

    SU

    MP

    ANy

    ANy

    ANx

    ANx

    ANx

    FANU FANUFANUAIR

    AIR

    ANy

    T

    RE

    TRE

    T

    RE

    T

    RE

    Subrack 2/ 1

    1 : Plinth cover2 : Connection area (COAR) between the racks3 : Electricity meter location

    4 : AC switch board

    Figure 1: 9100 BTS Medi Layout (Example: 3x4 Configuration)

    8 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    9/66

    1 Overview

    1.1.1.2 Weight and Dimensions

    Average weight equipment Equipped without battery = 295 kg

    Equipped with 1 battery BU41 = 345 kg

    Equipped with 2 battery BU41 = 395 kg

    Dimensions Height = 1500 mm

    Width = 1200 mm

    Depth = 700 mm

    Table 1: Mini Characteristics

    Average weight equipment Equipped without battery = 495 kg

    Equipped with 1 battery BU41 = 545 kg

    Equipped with 2 battery BU41 = 595 kg

    Dimensions Height = 1500 mm

    Width = 1800 mm

    Depth = 700 mm

    Table 2: Medi Characteristics

    Weight 50 kg

    Dimensions H 235 mm, W 250 mm, L 400 mm

    Table 3: Battery BU41

    Weight 160 kg

    Dimension Height = 1.50 m

    Width = 0.60 m

    Depth = 0.70 m

    Table 4: BTS Compartment Alone (with TRX)

    3BK 17073 0001 RJZZA Ed.13 9 / 66

  • 8/11/2019 170730001 e 13

    10/66

    1 Overview

    Weight 100 Kg

    Dimension Height = 1.50 m

    Width = 0.60 m

    Depth = 0.70 m

    Table 5: Empty Side Compartment

    1.1.2 Cases

    None.

    1.1.3 Options

    None.

    10 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    11/66

    1 Overview

    1.1.4 Initial State

    Before beginning the installation, ensure that the AC 220V cable is fitted butthe tension is not present.

    The following figures show examples of steel and concrete foundations.

    Figure 2: Steel Construction

    Figure 3: Concrete Foundation

    3BK 17073 0001 RJZZA Ed.13 11 / 66

  • 8/11/2019 170730001 e 13

    12/66

    1 Overview

    1.1.5 Final State

    After the installation:

    The rack is ready for commissioning

    The rack is not powered up.

    The following figures provide examples of finalized building and fieldinstallations.

    Figure 4: Building Installation

    Figure 5: Field Installation

    1.1.6 Restrictions

    None.

    12 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    13/66

    1 Overview

    1.1.7 Group Task Sequence

    The following figure shows the grouped task sequence for this scenario.

    Before Going Onsite

    Before You Start

    Install at Final Location

    Instal Power Cables

    Connect PCM Power Cables

    Connect Antenna Cables

    Install Options

    Fit CAD Terminal Block

    Finish Installation

    3BK 17073 0001 RJZZA Ed.13 13 / 66

  • 8/11/2019 170730001 e 13

    14/66

    1 Overview

    1.2 Preparation

    1.2.1 Prerequisites

    The following prerequisites apply:

    The site is ready to receive the racks, according to the SPP33: Particular Specification GSM and DCS for Alcatel-Lucent Base Station for Mini/Medi Outdoor BTS Site Preparation .

    Ensure that the following equipment is installed:

    Cable tray

    Antenna feeders

    AC power cable ( maximum 25 mm)

    Earth cable and ground plate

    Differential AC circuit breakers

    2 Mbits cables or Microwave feeders

    DDF for 2 Mbits cables

    Steel or concrete foundation.

    Ambient light and overhead lighting is available

    Power is available

    Check the necessity of the alarm cables (optional installation).

    If this equipment is not installed before the beginning the installation, contact

    the Alcatel-Lucent person responsible of the installation and indicate themissing equipment in the Completion Check List (CCL).

    14 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    15/66

    1 Overview

    1.2.2 Site Specific Information

    You must have the following site specific information:

    Site

    Address and access to the site (key holder)

    Location of grounding plate

    Location of power supply cabinet

    Location of breakers in power box

    Antenna feeder connections and information (AZIMUTH, Sectors, etc.)

    Precise location of BTS rack

    Number of alarms to be connected (if the case)

    Alarm terminal block location (if the case)

    Number of alarms to be connected

    BTS Rack

    Type of BTS rack to be installed (Mini, Medi)

    Type of batteries (BU41, BU100)

    Rack fixing (steel construction, concrete foundation).

    Kits

    PCM connection type

    PCM cable impedance (120 ohm, 75 ohm)

    Synchronization configuration.

    1.2.3 External Tasks

    None.

    3BK 17073 0001 RJZZA Ed.13 15 / 66

  • 8/11/2019 170730001 e 13

    16/66

    1 Overview

    1.3 Scheduling

    Time based on technical constraintsThe number of resources in the following table does not take into accountindividual customer or safety requirements.

    This schedule does not take into account the time required to install cables inthe cable way and to connect to the site equipment (DDF, power cabinet).The total time does not include optional tasks.

    Grouped Task Time / Task

    Before Going Onsite 1h

    Before You Start 1h 1

    Install at Final Location:

    With rack disassembly

    Without rack disassembly. 2

    30 min.

    15 min.

    Install Power Cables 25 min.

    Connect PCM Power Cables 25 min.

    Connect Antenna Cables 50 min.

    Install Options:

    Connect external alarm cables (optional)

    Install synchronization cables (optional)

    15 min.

    15 min.

    Fit CAD Terminal Block -

    Finish Installation 15 min.

    Total Time 4h 25 min. - 4h 10 min.

    (1) : This time is an average value. The real time depends on the site configuration.(2) : If the 9100 BTS is disassembled, it must be transported manually by four people.

    16 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    17/66

    1 Overview

    1.4 ResourcesThe following tables describe the necessary hardware tools, software tools,and forms.

    1.4.1 Tools

    1.4.1.1 Package Labelling ReferencesFor each site, the delivery depends on the options required by the customer.

    Each kit is referenced and labelled either on packages or onthe equipment.

    Note: Each package contains a paper part-list.The reference labelled on the package contains:

    A mnemonic referenceExample: BKBOThis is the Mnemonic reference of the standard installation kit for the

    Mini or Medi Outdoor BTS.An industrial referenceExample: 3BK 05360 DAThis is the industrial reference of the antenna jumper 3m cable.

    An Alcatel Lucent ordering referenceExample: G3INS**OO801This is the service kit; refer to Alcatel-Lucent Ordering Reference (for 9100 BTS Mini Outdoor Only) ( Section 1.4.1.2 ).

    1.4.1.2 Alcatel-Lucent Ordering Reference (for 9100 BTS Mini Outdoor Only)Example: reference G3INS**OO803

    The meaning of this reference is as follows:

    G3 refers to the generation of the 9100 BTS

    INS is the installation reference

    ** digits not used in 9100 BTS

    OO refers to the configuration OO of the BTS

    8 refers to the service kit

    03 indicates edition 3 of the kit.

    3BK 17073 0001 RJZZA Ed.13 17 / 66

  • 8/11/2019 170730001 e 13

    18/66

    1 Overview

    1.4.1.3 Hardware KitsUse the following table to check, onsite, the mandatory or optional deliveryitem kits.

    The symbols used are:

    mandatory kit, technical choice kit,

    customer option kit.

    Mandatory Kits OrderingReference

    Mnemonic IndustrialReference

    Quantity

    Basic kit for Mini or Medi INS**OOF BKG3O 3BK 08107 AA

    Antenna jumper cables -

    INS**OOUINS**OOJ

    INS**OOA

    INSTALBOOK

    -

    BLF1BLF2

    BLF3

    BLF5

    -

    3BK 05360 BA3BK 05360 CA

    3BK 05360 DA

    3BK 05360 EL

    -

    2/s2/s

    2/s

    2/s

    Optional Kits OrderingReference

    Mnemonic Industrial Reference Quantity

    Service kit (*1)

    BTS terminal cable

    Monitoring trace cable

    Alarm disable connector

    Calibration cable

    Special mounting tool key

    INS**OO8 -

    CBTE

    MT2C

    ADCO

    CALC

    OMTL

    -

    3BK 07951 AB

    3BK 07952 AA

    3BK 07953 AA

    3BK 08066 AB

    3BK 08244 AA

    -

    1

    1

    1

    1

    1

    2 Mbits cables (roll 100 m or 250 m)

    120 Ohm (4 pairs)

    75 Ohm (4 coax)

    -

    L907/4

    FLEX3/4

    -

    1AC 01328 0004

    1AC 00110 0011

    Power cables (roll 100 m)

    Y/G ground cable

    Shielded power cable 5 x 6 mm2

    -

    YG50

    BK5x6

    -

    1AC 00106 0061

    1AC 00468 0003

    -

    1

    1

    Cable for synchronization

    9100 BTS/9100 BTS (10 m)

    9100 BTS/BTS-G2o) (10 m)

    -

    OCC33

    OCC23

    -

    3BK 08304 AA

    3BK 08303 AA

    -

    1

    2

    Alarm cable 8 pairs (roll 100 m or250 m)

    L907/8 1AC 01328 0001 1

    18 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    19/66

    1 Overview

    Optional Kits OrderingReference

    Mnemonic Industrial Reference Quantity

    Mechanical part for 24 Terminal block MP24 1AD 02843 0001 1

    Label for 24 terminal block LAB 1AD 02853 0001 1

    CAD Terminal block 120/75 ohm(Alcatel)

    JS10 1AD 06634 0011 4

    Fixing kit for wall FKW 1AD 02844 0001 1

    Fixing kit for rack FKR 1AD 02845 0001

    Load 50 Ohm (*1) CH716 3BK 06827 AA 1/S

    (*1) : This kit is delivered with the other equipment but is used by commissioning teams.

    3BK 17073 0001 RJZZA Ed.13 19 / 66

  • 8/11/2019 170730001 e 13

    20/66

    1 Overview

    1.4.1.4 Hardware ToolsRefer to the Tools Catalogue for Field Activity for more information.

    Screwdriver flat head

    3 - 4 - 5 mm

    Tightening tool for antenna jumpers

    ref. 3BK 25050 AA

    Screwdrivers for Torx heads Screwdriver for Pozidriv head

    Screwdriver for hexagon socket heads M5 - M6 Hot air blower

    with cable buses

    Cutting plier Marking pen

    Open-end wrenches

    8 to 19 and 27

    Electricians knife

    Percussion drilling (with depth stop)for 18 masonry drill bits

    Tape labelling machineBlack tape: 12 mm

    Masonry drill bits for percussion tools

    8 - 12 - 18 mm

    Alcatel-Lucent insertion tool for terminalblock reference:

    1AD 01604 0001

    Standard drill bits

    8 to 16 mm

    Tape rule (2 m)

    Mounting key

    Reference: 3BK 08144 AA

    Level

    Hacksaw Stepladder

    Wire stripers Nibblers

    Crimping pliers for lug up to 50 mm2 Sleeving plier

    Bar for craning

    Reference: 3BK 08804 AAAA

    Tent for 9100 BTS outdoor

    Reference: 3BK 08 470 AAAA

    20 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    21/66

    1 Overview

    1.4.2 Supplies

    Item Quantity

    Indelible marker 1

    Rubber sleeves for cables 50

    Tie wraps 100

    Lugs 20

    Blank labels for cables 20

    Adhesive tape 2

    1.4.3 Applicable DocumentsYou must have the following documents or have electronic access to thefollowing documents:

    Catalogue of Instruction Operation (IO)

    Catalogue of Technical and Logistic Information (ITLPRO)

    General Wiring Handbook

    Tools Catalogue for Field Activity

    CI-08 Site Equipment Inventory

    Site Premises Inspection Form (CEL)

    B11 BSS Methods Handbook

    Completion Check List (CCL)

    SPP-33 Particular Specification GSM and DCS for Alcatel-Lucent 9100 Base Station for Mini/Medi Outdoor BTS Site Preparation

    Part Volume T17/V18 3DF 00424 0022 ADBRQ

    Part Volume T17/V03 (G2-BTSO)

    3DF 00424 0009 ADBRQ

    3BK 17073 0001 RJZZA Ed.13 21 / 66

  • 8/11/2019 170730001 e 13

    22/66

    1 Overview

    22 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    23/66

    2 Scenario

    2 Scenario

    This Scenario presents all checks needed before beginning the scenario, andall detailed tasks to be performed onsite.

    3BK 17073 0001 RJZZA Ed.13 23 / 66

  • 8/11/2019 170730001 e 13

    24/66

    2 Scenario

    2.1 Before Going OnsiteBefore going onsite, check that the following information and supplies areavailable:

    All Prerequisites (Section 1.2.1) are met

    The customer is informed of the:

    Date and time

    Site name and address

    Purpose of the operation.

    Personnel are available; refer to Scheduling (Section 1.3)

    Site Specific Information (Section 1.2.2) is available

    Tools (Section 1.4.1) are available and ready for operation

    Supplies (Section 1.4.2) are available and ready for operationApplicable Documents (Section 1.4.3) are available.

    2.2 Before You Start

    2.2.1 Checks

    Perform the following operations:

    Check that all Prerequisites (Section 1.2.1) are met

    Check applicable notifications and operating instructions (refer to theCatalogue of Instruction Operation (IO) and Catalogue of Technical and Logistic Information (ITLPRO) )

    Check the availability of all necessary Tools (Section 1.4.1) and Supplies ( Section 1.4.2)

    Refer to the BSS Site Premises Inspection, Post Handover and completethe Site Premises Inspection Form (CEL)

    Check that the safety precautions are taken in accordance with the safetyinstructions described in the B11 BSS Methods Handbook

    Complete the header field of the CCL. Complete the CCL as each instructionis carried out.

    Among the cases described in Cases (Section 1.1.2) and the options describedin Options (Section 1.1.3) , identify which cases and options apply to you.

    24 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    25/66

    2 Scenario

    2.2.2 Required Knowledge

    You must be familiar with the following:

    Safety Rules and Precautions

    How to document Faults and Anomalies .

    2.3 Install at Final Location

    2.3.1 Unpack Racks

    Unpack the racks:

    1. Complete the Site Premises Inspection Form (CEL) .

    2. Unpack the equipment as shown below.

    3. Check the packages.

    4. Locate the final site location.

    3BK 17073 0001 RJZZA Ed.13 25 / 66

  • 8/11/2019 170730001 e 13

    26/66

    2 Scenario

    2.3.2 Dismantle Racks

    2.3.2.1 Disconnect CablesDisconnect Cables From Side Compartment to BTS1

    Before disconnecting all interconnecting cables, put temporary marks (orlabels).

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    Figure 6: Side Compartment (Internal Lateral View)

    X1

    X6

    A

    B

    Figure 7: BTS1 (Front View)

    26 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    27/66

    2 Scenario

    Side Compartment Connection Cable Reference BTS1 Connection

    Figure 6 / 1 3-pin connector - - Light

    Figure 6 / 2 Alarm BTS1 (male) 3BK 08090 AAAA - Alarm

    Figure 6 / 4 HEX POWER (female) 3BK 08092 AAAA DCDP/X6

    Figure 6 / 5 Stud with screw - - GND (y/ g)

    Figure 6 / 6 Filter (red) - - 0 Volt

    Figure 6 / 7 Filter (blue) - - -48 Volts

    Figure 6 / 8 3-pin connector - - Fan

    Figure 6 / 9 2-pin connector 3BK 08087 AAAA DCDP/X1 -

    Figure 6 / 10 Abis1/ 2 (male) 3BK 07922 ABAA Figure 7 / A Abis 1/ 2

    Figure 6 / 11 Sum 37-pin connect - Figure 7 / B -

    Table 6: Interconnection Between Side Compartment and BTS1

    Disconnect Cables From BTS2 to BTS1 and BTS2 to Side Compartment

    The following tables give the position and reference of the cables to be removed.

    BTS1 Cable Reference BTS2 Connection

    DCDP/X8 3BK 08077 ABAA Door

    DCDP/X12 3BK 08079 ABAA Subrack 2/1

    DCDP/X13 3BK 08079 ABAA Subrack 2/2

    DCDP/X14 3BK 08079 ABAA Subrack 2/3

    Figure 8 / C - Heater

    Figure 8 / D - Logic flat loom

    Table 7: Cabling from BTS2 to BTS1

    3BK 17073 0001 RJZZA Ed.13 27 / 66

  • 8/11/2019 170730001 e 13

    28/66

    2 Scenario

    The following figure shows the BTS1 front view.

    C

    D

    X12 X13 X14

    X8

    Figure 8: BTS1 Front View

    Side Compartment Connection Cable Reference BTS2 Connection

    Figure 6 / 3 (male connector) 3BK 08091 AAAA Alarm

    Table 8: Cabling From BTS2 to Side Compartment

    28 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    29/66

    2 Scenario

    2.3.2.2 Mechanical DismantlingDismantle the BTS mechanically:

    1. Open the door wide.

    2. Unscrew the BTS roofs (M5 Hexagon screwdriver).

    3. Remove the BTS roof, respecting the order indicated in the following figures.4. Use the mounting tool key (3BK 08144 AA) to screw the cabinet together.

    5. Define the inter-cabinet fixing location.

    6. Define the cabinet mechanical assembling process.

    7. Insert the screw

    8. Tight the screw.

    When dismounting, do not remove completely the screws because you canlose the nut inside the profile.

    3BK 17073 0001 RJZZA Ed.13 29 / 66

  • 8/11/2019 170730001 e 13

    30/66

    2 Scenario

    30 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    31/66

    2 Scenario

    3BK 17073 0001 RJZZA Ed.13 31 / 66

  • 8/11/2019 170730001 e 13

    32/66

    2 Scenario

    2.3.3 Transport Racks

    2.3.3.1 Transport Racks by CraneThe following figure shows how to transport the racks by crane.

    Figure 9: Handle by Crane

    The following figure shows how to transport the racks by inserting eyerodsthrough the eyebolts.

    Figure 10: Mini and Medi - Insert Rods Through Eyebolts

    32 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    33/66

    2 Scenario

    2.3.3.2 Transport Racks by PalletThe following figure shows how to transport the racks by pallet.

    Figure 11: Pallet Transportation

    2.3.3.3 Transport Racks ManuallyThe following figure shows how to transport the racks manually.

    Figure 12: Manual Transportation (Very Short Distance Only)

    3BK 17073 0001 RJZZA Ed.13 33 / 66

  • 8/11/2019 170730001 e 13

    34/66

    2 Scenario

    2.3.4 Position and Fix Racks

    2.3.4.1 Steel ConstructionPosition and fix the racks for a steel construction:

    1. Position the racks.

    2. Level the racks.

    Figure 13: Steel Construction Installation

    12

    34 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    35/66

    2 Scenario

    2.3.4.2 Concrete FoundationPosition and fix the racks for a concrete foundation:

    1. Mark the position of the fixation points.

    2. Drill holes (using the depth stop).

    Figure 14: Concrete Construction Installation

    1150 mm

    1748 mm

    500 mm

    500 mm 95 mm

    18 mm

    1 2

    3BK 17073 0001 RJZZA Ed.13 35 / 66

  • 8/11/2019 170730001 e 13

    36/66

    2 Scenario

    2.3.4.3 Connect Protective Earth Cable at BTS SideConnect the protective earth cables at the BTS side:

    1. Position the socle cover with the cable entry holes.

    2. Mount the reduction adapter and cable bushes and sleeve.

    3. Run the earth cable on the side compartment.4. Earth connecting detail:

    1 - External ground cable

    2 - Stud for ground.

    36 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    37/66

    2 Scenario

    2.3.4.4 Connect Inter-Rack CablesConnect the following cables:

    1. From BTS1 to the side compartment; use Table 6 .

    2. From BTS2 to BTS1, use Table 7 .

    3. From BTS2 to side compartment, use Table 8 .

    2.3.5 Install Batteries (If Necessary)

    If required, install the batteries:

    1. Fit the batteries.

    2. Install the exhaustion hoses.

    3. Connect the inlet/outlet cables.

    4. Note the battery connection details.

    5. Connect the 3BK 08119 AA temperature sensor cable:

    Fit the heat shrink sleeve over the sensor

    Connect the cable to the positive contact of the battery 1 (see Step 3 )

    Connect the cable to BACO/X200

    12

    TEMPERATURE+

    + S en s or

    BACO

    12

    3 4

    3BK 17073 0001 RJZZA Ed.13 37 / 66

  • 8/11/2019 170730001 e 13

    38/66

    2 Scenario

    2.4 Install Power CablesThis section describes how to connect the AC power supply cables to theside compartment cabinet.

    According to SPP-33 Particular Specification GSM and DCS for Alcatel-Lucent

    9100 Base Station for Mini/Medi Outdoor BTS Site Preparation , the powercables and earth cables are already supplied and installed before 9100 BTSOutdoor installation.

    Before making any electrical connections to the BTS, ensure that the safetyinstructions are followed.

    It is essential that:

    The protective earth is connected to the equipment earth terminal

    The electrical power supply is disconnected.

    2.4.1 Run Power Cables at BTS Side

    Run the power cables to the BTS side:

    1. Identify an available hole on the socle cover with cable entry holes.

    2. Mount the reduction adapter and cable bushes and sleeve.

    3. Auxiliary compartment bottom plate:

    1 - Entry for cable diameter 16 to 25 mm. Minimum over braiding 13 mm.

    2 - Entry for cable diameter 8 to 14 mm. Minimum over braiding 5 mm.

    4. Mount the cable gland detail:Pass the shrink sleeve over the cable

    Pass the adapter over the cable

    Strip the cable to the braid

    Shrink the sleeve.

    5. Check the mounted cable gland.

    38 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    39/66

    2 Scenario

    6. Run the cables into the side compartment as described in Figure 15 .

    3BK 17073 0001 RJZZA Ed.13 39 / 66

  • 8/11/2019 170730001 e 13

    40/66

    2 Scenario

    Figure 15: Run AC Power Cable at BTS Side

    40 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    41/66

    2 Scenario

    2.4.2 Connect Power Cables at BTS Side

    Connect the power cables at the BTS side:

    1. Remove the AC area protection.

    2. Prepare the head of the AC cable:

    Strip the cable

    Cut the cable shielding

    Apply the 10 cm shrink sleeve (1 Figure 16 Step 2)

    Insert the lug pin on the end cable (2 Figure 16 Step 2)

    Cut a notch in the upper part of the AC area protection (1 Figure16 Step 1).

    3. Connect the power supply cable to the AC switch board.If required by the site documentation, the equipmentcan be cabled in a 1-phase system or 3-phase system.For 1 phase system :

    The two wires from breakers L2 and L3 are not present (1 and 2Figure 17 ) 2.

    The clamp bridge in AC-out is present (3 Figure 17 )

    For 3 phase system :

    The two wires from breakers L2 and L3 are present (1 and 2 Figure 17 )

    The clamp bridge in AC-out is not present (3 Figure 17 )

    4. Fit the AC area protection.

    1

    PE N L3L2L1

    1

    21 AB 05067 0004

    1 2

    Figure 16: Power Cable Connection

    3BK 17073 0001 RJZZA Ed.13 41 / 66

  • 8/11/2019 170730001 e 13

    42/66

  • 8/11/2019 170730001 e 13

    43/66

    2 Scenario

    2.5 Connect PCM Power CablesThis section describes how to connect the PCM cables to the 9100 BTSside compartment.

    According to SPP-33 Particular Specification GSM and DCS for Alcatel-Lucent

    9100 Base Station for Mini/Medi Outdoor BTS Site Preparation , the PCMcables are already supplied and installed before 9100 BTS Outdoor installation.

    2.5.1 Run PCM Cables at BTS Side

    Run the PCM cables at the BTS side:

    1. Remove the insulation.

    2. Mount the reduction adapter and cable bushes and sleeve.

    3. Auxiliary compartment bottom plate:1 - Entry for cables diameter 8 to 14 mm (PG16). (minimum over braiding 5mm).

    4. Mount the cable gland detail:

    Pass the shrink sleeve over the cable

    Pass the adapter over the cable

    Fit the cable through the socle cover

    Strip the cable to the braid

    Shrink the sleeve.

    3BK 17073 0001 RJZZA Ed.13 43 / 66

  • 8/11/2019 170730001 e 13

    44/66

    2 Scenario

    44 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    45/66

  • 8/11/2019 170730001 e 13

    46/66

    2 Scenario

    2.5.2.2 L907/ 4 - 120 Ohm Alcatel-Lucent Cable (1AC 01328 0004)This cable has 2 twisted quads (1 quad = 2 pairs).

    A

    B

    E

    F

    G

    D L9 0 71 AC 0 1 3 2 8 0 0 0 4

    Pair 2

    Pair 1

    Pair 2

    Pair 1

    I

    H

    brown

    violet

    yellow

    grey

    blue

    violet

    white

    grey

    Quad2

    Quad1

    M L

    1AC 01328 0004Figure 19: L907/ 4 -120 Ohm PCM Cable

    Pair COAR Signal Color

    1 ABIS 1 TX

    TX

    grey

    white

    Quad 1

    2 ABIS 1 RX

    RX

    violet

    blue

    1 ABIS 2 TX

    TX

    grey

    yellow

    Quad 2

    2 ABIS 2 RX

    RX

    violet

    brown

    46 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    47/66

    2 Scenario

    12

    34

    56 7

    8

    1

    23

    45

    67

    8

    1 : GND (bread earthing clamp)

    2 : TX3 : TX4 : GND (gather the 2 drain wires)

    5 : RX6 : RX7 : R200 (not used)

    8 : GND (bread earthing clamp)

    Figure 20: L907/ 4 - 120 Ohm PCM Cable Connection

    2.5.2.3 FLEX3/ 4 - 75 Ohm Alcatel Lucent Cable (1AC 00110 0011)This cable has four coaxial cables.

    BG

    D

    K

    A

    F

    H

    E

    I

    C

    J

    Figure 21: FLEX3/ 4 -75 Ohm PCM Cable

    3BK 17073 0001 RJZZA Ed.13 47 / 66

  • 8/11/2019 170730001 e 13

    48/66

    2 Scenario

    Coaxial COAR Signal

    1 ABIS 1 TX

    2 ABIS 1 RX

    3 ABIS 2 TX

    4 ABIS 2 RX

    12

    34

    56

    7 8

    1 : GND (bread earthing clamp)

    2 : TX (wire bridge from pin 1)3 : TX (inner conductor)4 : GND5 : RX (wire bridge from pin 4)6 : RX (inner conductor and wire bridge to pin 7)7 : R200

    8 : GND (bread earthing clamp)Figure 22: FLEX3/ 4 - 75 Ohm PCM Cable Connection

    48 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    49/66

    2 Scenario

    2.6 Connect Antenna CablesThis section describes how to connect the antenna feeder cables to the 9100BTS compartment cabinet.

    According to SPP-33 Particular Specification GSM and DCS for Alcatel-Lucent

    9100 Base Station for Mini/Medi Outdoor BTS Site Preparation , these cablesare already supplied and installed before the 9100 BTS installation.

    2.6.1 Install Jumpers

    Install the jumpers:

    1. Identify the appropriate cable bushes for passing the cables.

    2. Mount the cable bushes and reduction adapter.

    Figure 23: BTS Antenna Socket Connectors

    3BK 17073 0001 RJZZA Ed.13 49 / 66

  • 8/11/2019 170730001 e 13

    50/66

    2 Scenario

    To connect 1, 2, 3, 4, 5 and 6 of Figure 23 , refer to the Part Volume (T17/V18)documentation.

    1 : Antenna coaxial cable

    2 : 7/ 16 antenna connector3 : 7/ 16 jumper connector4 : Coaxial jumper

    5 : Adapter6 : Bottom plinth7 : Radius of bending mini 50 mm8 : 7/ 16 coaxial socket9 : 7/ 16 jumper connector

    Figure 24: Antenna Jumper Cable Connection

    50 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    51/66

    2 Scenario

    2.6.2 Connect Jumper to Antenna Coaxial

    1 : Antenna coaxial cable2 : Shrink sleeve 63/19 mm 1AC 00057 01033 : Shrink sleeve 40/13 mm 1AC 00057 01024 : Jumper cable5 : Tape auto-vulcanisant 1AC 01595 0001

    Figure 25: Detail Connection Between Coaxial Cables

    3BK 17073 0001 RJZZA Ed.13 51 / 66

  • 8/11/2019 170730001 e 13

    52/66

  • 8/11/2019 170730001 e 13

    53/66

    2 Scenario

    Figure 27: Help to Find Sector Position of Antenna Connectors at Bottom of BTS Compartments

    3BK 17073 0001 RJZZA Ed.13 53 / 66

  • 8/11/2019 170730001 e 13

    54/66

    2 Scenario

    Figure 28: Help to Find Sector Position of Antenna Connectors at Bottom of BTS Compartments

    54 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    55/66

    2 Scenario

    2.7 Install Options

    2.7.1 Connect External Alarm Cables (Optional)

    2.7.1.1 Install Alarm Cables at BTS SideInstall the alarm cables at the BTS side:

    1. Identify the appropriate cable bushes for passing the cables.

    2. Mount the cable bushes and reduction adapter:

    Pass the shrink sleeve over the cable

    Pass the adapter over the cable

    Fit the cable through the socle cover

    Strip the cable to the braid

    Shrink the sleeve.

    3. Fit the cable gland on the bottom plate

    1

    1 : Alarm cable hole

    Figure 29: Side Compartment Bottom Plate

    3BK 17073 0001 RJZZA Ed.13 55 / 66

  • 8/11/2019 170730001 e 13

    56/66

    2 Scenario

    4. Mount the cable gland.

    Figure 30: Cable Gland Mounting

    56 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    57/66

    2 Scenario

    2.7.1.2 Connect Alarm Cables to Connection Area (COAR)The connection area is located between the side compartment and the BTS 1compartment.

    The alarm cables are connected on screw terminal.

    ABIS 4 ABIS 3 ABIS 2 ABIS 1ALARM

    18181818

    Figure 31: Connection Area (COAR)

    3BK 17073 0001 RJZZA Ed.13 57 / 66

  • 8/11/2019 170730001 e 13

    58/66

    2 Scenario

    Pair 2

    Pair 1

    Pair 2

    Pair 1

    Pair 2

    Pair 1

    Pair 2

    Pair 1

    K

    J

    I

    H

    white

    violet

    greengrey

    red

    violet

    black

    grey

    brown

    violetyellow

    grey

    blue

    violet

    White

    grey

    Quad4

    Quad3

    Quad2

    Quad1

    L 9 0 7

    1 AC 0 1 3 2 8 0 0 0 1

    A

    BC

    E

    F

    G

    D

    d1

    d2

    Figure 32: Alcatel-Lucent 8 Pairs Cable L907/ 8

    Alarm Number Color COAR pin Connector

    Alarm 1 grey

    white

    2

    3

    Quad 1

    Alarm 2 violet

    blue

    4

    5

    Alarm 3 grey

    yellow

    6

    7

    Quad 2

    not used violet

    brown

    not connected

    Quad 3 & 4 not used

    58 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    59/66

    2 Scenario

    1

    23

    45

    67

    8

    1 : GND (braid earthing clamp)

    2 : ALM1 GND3 : ALM 1 (external alarm nr 10)4 : ALM 2 GND

    5 : ALM 2 (external alarm nr 13)6 : ALM 3 GND7 : ALM 3 (external alarm nr 14)

    8 : GND (braid earthing clamp)

    Figure 33: Example of Customer Cables: 3 Cables for 3 Alarms

    12

    34

    56

    78

    1 : GND (braid earthing clamp)

    2 : ALM1 GND3 : ALM 1 (external alarm nr 10)4 : ALM 2 GND5 : ALM 2 (external alarm nr 13)6 : ALM 3 GND7 : ALM 3 (external alarm nr 14)8 : GND (braid earthing clamp)

    Figure 34: Example of Customer Cable: 1 Cable for 3 Alarms

    3BK 17073 0001 RJZZA Ed.13 59 / 66

  • 8/11/2019 170730001 e 13

    60/66

    2 Scenario

    2.7.1.3 Example: Prepare Alcatel-Lucent Alarm Cable (L907/ 8 ref: 1AC 01328 0001)Prepare the Alcatel-Lucent alarm cable:

    1. Remove the plastic insulation.

    2. Pull out the wire of the braid.

    3. Cut the braid (ensure that you DO NOT cut the DRAIN wire).4. Cut the aluminum tape.

    5. Cut the plastic film.

    6. Untwist the wires (15 cm).

    7. Twist each pair (1 cm).

    8. Cut the skin of the cable at 3 cm and shift it 1 cm ahead of the cable. It isalso possible to put a rubber sleeve.

    1 2

    3

    4

    5

    6

    7 8

    60 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    61/66

    2 Scenario

    2.7.2 Install Synchronization Cables (Optional)

    2.7.2.1 9100 BTS / G2-BTS Connection

    9100 BTS Master Cable G2 Slave

    COAR/XCLK1out

    COAR/XCLK2in/out

    OCC23

    OCC23

    COB2 (*)

    COB2 (*)

    G2 Master Cable 9100 BTS Slave

    COB2 (*)

    COB2 (*)

    OCC23

    OCC23

    COAR/XCL1in

    COAR/XCL2in/out

    The following figure shows the 9100 BTS/ G2 BTS synchronization cablemounting general view.

    P1C OA R CO B 2

    Figure 35: 9100 BTS/ G2 BTS Synchronization Cable Mounting General View

    The following figure shows the 9100 BTS/ G2 BTS cable.

    1 2 3 4 5

    6 7 8 9

    1 m

    P1 P2

    59

    4

    8

    3

    7

    2

    6

    P1

    59

    4

    8

    3

    7

    2

    6

    P2

    screenscreen

    white

    brown

    green

    yellow

    grey

    pink

    blue

    red

    COAR COB2

    OCC23 3BK 08303 AA

    Figure 36: 9100 BTS / G2 BTS Cable (ref. 3BK 08303 AAAA)

    3BK 17073 0001 RJZZA Ed.13 61 / 66

  • 8/11/2019 170730001 e 13

    62/66

    2 Scenario

    2.7.2.2 9100 BTS/ 9100 BTS Connection

    9100 BTS Master Cable 9100 BTS Slave

    COAR/XCLK1out OCC33 COAR/XCLK1in

    A 9 1 00 B T S A 9 1 00 B T S

    P1 P2COA R

    C OA R

    Figure 37: 9100 BTS / 9100 BTS Synchronization Cable Mounting General View

    1 2 3 4 5

    6 7 8 9

    P1

    1 2 3 4 5

    6 7 8 9

    P2

    59

    4

    8

    3

    7

    2

    6

    P1

    59

    4

    8

    3

    7

    2

    6

    P2

    screenscreen

    white

    brown

    green

    yellow

    grey

    pink

    blue

    red

    COAR 1 COAR 2

    OCC33 3BK 08304 AA

    Figure 38: 9100 BTS / 9100 BTS Cable (Ref. 3BK 08304 AAAA)

    2.7.2.3 Fit Synchronization CablesFit the synchronization cables:

    1. Fit the synchronization cables through the cable gland.

    2. Connect the synchronization cables to the first BTS.

    3. Solder the connector of the second BTS.

    4. Connect the synchronization cables to the second BTS.

    5. Label the cables.(*) For G2-BTS outdoor connection, refer to the Part Volume T17/V03 (G2-BTSO) document.

    62 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    63/66

    2 Scenario

    2.8 Fit CAD Terminal Block (120 Ohm Cable)Fit the CAD terminal block:

    1. Insert the jack strip.

    2. Verify the correct position.

    3. Prepare the end of cable without stripping the wires.

    4. Pass the pair in the lateral hole.

    5. Insert the first wire.

    6. Connect the wire with a specific tool.

    7. Connect the second wire.

    8. Pass the drain wire.

    9. Connect the drain wire with the specific tool

    C LIC K

    C LIC K

    200 mm

    1 2

    3 4

    5 6

    3BK 17073 0001 RJZZA Ed.13 63 / 66

  • 8/11/2019 170730001 e 13

    64/66

    2 Scenario

    7 8

    910

    64 / 66 3BK 17073 0001 RJZZA Ed.13

  • 8/11/2019 170730001 e 13

    65/66

    2 Scenario

    2.9 Finish InstallationFinish the installation:

    1. Fit the caps on the socle cover cable bush.

    2. Label the cabinets.

    3. Give the key to the site responsible.

    Note: The following rules apply:

    One key marked side only opens the side compartment

    One key marked side + BTS opens all doors of the 9100 BTS.

    4. Tidy up the site:

    Clean out the rack

    Remove the packaging from the site

    Leave the site clean

    B TS S T A TIO N 4

    B TS S T A T IO N 4

    3 B K 05368 AAAA 3 B K 05365 AAAA

    1 2

    34

    3BK 17073 0001 RJZZA Ed.13 65 / 66

  • 8/11/2019 170730001 e 13

    66/66

    2 Scenario

    BLANK PAGE BREAK