17
10/27/2017 1 Owner Project Requirements How to get what you need From an Owner’s Perspective Learning Objectives What is an OPR Case Study (CHC) Looking to the Future Closing Arguments Crafton Hills College

17 Owner Project Requirements Final · 10/27/2017 1 Owner Project Requirements How to get what you need From an Owner’s Perspective Learning Objectives What is an OPR Case Study

Embed Size (px)

Citation preview

10/27/2017

1

Owner Project Requirements

How to get what you need

From an Owner’s Perspective

Learning Objectives

What is an OPR

Case Study (CHC)

Looking to the Future

Closing Arguments

Crafton Hills College

10/27/2017

2

What is an OPR?Origin, definition and purpose

Definition

The Owner’s Project Requirements (OPR) is a written document that details the functional requirements of a project and the expectations of how it will be used and operated.

Guideline 0 - 2013Standard 202 - 2013

10/27/2017

3

Purpose

The OPR provides the basis from which all design, construction, acceptance, and operational decisions are made. An effective Cx Process depends upon a clear, concise, and comprehensive OPR document, which includes information to help the project team properly plan, design, construct, operate, and maintain systems and assemblies.

Commissioning

The OPR are considered the heart and soul of the Commissioning Process

OPR

Design

Construction

Turnover

Programming

10/27/2017

4

Without an OPR…

When the OPR is not developed, the owner, designer, contractors, and operation and maintenance (O&M) personnel each interpret the project requirements, including their individual responsibilities, from the standpoint of their own specific needs

Without an OPR…

10/27/2017

5

Issues Discussed in the OPR

Purpose of the Project (Functional Uses)

Comfort.

Occupancy.

Sustainability & Energy Goals.

Security.

Durability.

Operation and Maintenance.

Criteria for Success.

Case StudyCrafton Hills College

10/27/2017

6

Crafton Hills College

Bond Program

6 Major New Construction & Modernization Projects

Crafton Center

Central Complex

Public Safety/Allied Health

PE Complex

Clock Tower Building

Canyon Hall

Different Architects

Same MEP Engineer

Same Controls Contractor

Same Commissioning Authority

Challenges

Same MEP Design Firm = Same Design?

Same Control Contractor = Same Installation?

Think again…

10/27/2017

7

What was common…

The Owner Project Requirements & Campus Standards

College Facilities Personnel

The Commissioning Authority

What we achieved…

Standardized the Building Automation System

Standardized the Air Handlers Quality and Configuration

Standardized Connections to the central plant

Standardized VAV terminal box installation details

10/27/2017

8

Building Automation System

Operates the HVAC systems

Responsible for Occupants Comfort

Manages Energy use

How we did it…

We specified…

Same Controllers

Same Valves

Same Sensors

Same Actuators

Selected only quality devices

Used fastest and most capable DC controllers

Used same sequences to operate similar systems

10/27/2017

9

Same Look and Feel

Custom Screens

10/27/2017

10

Benefits

Quality Control

Less vendors to deal with

Familiarity of the M&O personnel with the systems

Less Training Required

Ease of use

Looking to the FutureWhat will the next version of the OPR include

10/27/2017

11

HVAC

Require a maximum of 12” for flexible pipe connections or none.

Use specific HVAC equipment identification scheme

Specify piping flushing and cleaning procedures specially when connecting to a campus loop.

Use Chilled Water and Hot Water supply water temperature at point if use as basis of design.

Specify chemical treatment type and quantities to be provided for new building

Standalone controls of HVAC equipment is prohibited. Everything connected to BAS.

TAB contractor to be contracted to the District and overseen by the CxA

Electrical

Electrical meters installed at the Factory by switchgear manufacturer

Connect all the meters to the BAS.

Use of single use quick wire connections are prohibited

Water proof for underground connectors

Connect vending machine power to BAS for switching OFF

Use LED lighting throughout

Design and submittals must include manufacturer seismic bracing details and requirements

Standardize electrical systems identification.

10/27/2017

12

Plumbing

Do not provide hot water for lavatories.

Do not specify refrigeration units for drinking water faucets or fill stations.

Provided bottle fill stations at all drinking fountains.

Require that all paper and soap dispensers to be compatible with campus vendor products.

Specify point of use water heaters as required.

Exterior plumbing access doors to be non-keyed.

Connect water heaters and recirculating hot water pumps to the BAS for control and monitoring

Lighting Controls

Specify the System you want (Standards)

Make sure the system is accessible through internet.

Specify schedules and zone identification scheme to be used by system programmer.

Include in construction contract additional programing and training at 60 days and 11 month mark after initial training.

Include 3-5 years service contract with construction funding.

10/27/2017

13

Envelope

Use PVC dual ply roofing system on all new roofs.

Require 25 year warranty minimum on roof system.

Do not use asphalt roofing materials when possible.

Use only Low VOC cold application asphalt materials and systems.

Incorporate fall protection anchor points into building design.

Incorporate windows cleaning equipment access in civil design.

Landscaping

Use same arborist for all filed reports

Require the use of native plants only

Specify irrigation system and specific system requirements.

Connect irrigation system for remote access and monitoring.

Define “restoration” of areas impacted by construction.

Establish and require the use of campus identification scheme

10/27/2017

14

Elevators

Avoid if possible…

Do not let the Architect design a glass elevator.

Standardize manufacturer

Specify traction elevators only.

Require remote scheduling capabilities for exterior elevators

Exclude proprietary controls or parts.

Include one year of monthly services in contract.

Include re-permitting/testing at the one year mark in contract.

Closing ArgumentsLessons Learned, Project Management & Recommendations

10/27/2017

15

Lessons Learned

1. Engage a Commissioning Authority at the inception of the project(s)

2. Include the OPR in the solicitation for Bids from Design Teams.

3. Use your Cx Authority to verify compliance.

4. Stay engaged. Support the Cx process…

5. Customize OPR for each project.

6. Require the CM be involved in the Cx process and tie their success to successful functional completion.

7. Secure Board approval for Campus Standards

Board Approval

1. Secure Board approval for all Campus Standard Systems as required by public contract code.

Building Automation System

Fire Alarm System

Irrigation System

Card readers

Door locks

10/27/2017

16

Closing Thoughts

The OPR is the opportunity for the Owner to set a quality assurance process, standards and expectation for the project.

The OPR is used to convey these expectations to the Design and Construction teams.

The OPR serves as the basis for evaluating whether the Design and Construction has been completed to the Owner’s satisfaction.

You get what you spec…

Owner Project Requirements

Questions?

10/27/2017

17

Owner Project Requirements

Rick Lasser, QCxP, CEM, CMVP, LEED AP Commissioning Authority, ARUP 12777 W. Jefferson. Building D, Los Angeles, CA 900661 310 578 [email protected]

Larry CookDirector, Facilities Maintenance & Operation, 11711 Sand Canyon Rd, Yucaipa, CA 92399 1 [email protected]

Hussain Agah, MSCE, PMP, CCM, LEED AP BD+C, Director, Facilities Planning & Construction114 S. Del Rosa Drive, San Bernardino, CA 92408909.382.4094 / Cell [email protected]