15.1.2007 / Nygård Magnus

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Page 2: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

215.1.2007 / Nygård Magnus

Contents of presentation

Motorway E18 Muurla - LohjaTraffic management in a DBFM projectMotorway E18 Muurla - Lohja E18 Muurla–Lohja LCC Service Agreement, Tender Invitation

Document 8, Technical Requirements• examples on requirements• functional requirements • technical requirements • method requirements/descriptions

Summary

Page 3: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

315.1.2007 / Nygård Magnus

Motorway E18 Muurla - Lohja

Page 4: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

415.1.2007 / Nygård Magnus

Lahnajärvi intersection

Suomusjärvi intersection

Muurla intersection

Kruusila intersection

E18 Muurla - Lohja moottoritie

Sammatti intersection

Nummi intersection

Karnainen intersection

Lempola intersection

Muurla-Lahnajärviopens 2008

Lahnajärvi-Lohjaopens 2009

Page 5: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

515.1.2007 / Nygård Magnus

TunnelsHepomäki 270 m

Lakiamäki 430 m

Tervakorpi 560 m

Pitkämäki 595 m

Orosmäki 600 m

Karnainen 2200 m

Lehmihaka 300 m

Page 6: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

615.1.2007 / Nygård Magnus

Traffic management in a DBFM project - E18 Muurla-Lohja

Typical ITS equipment will be adequate for example 8 - 12 years, whereas the contract for the motorway is for 21 years• the system must be upgraded at least once within the

contract period • some of the equipment need some kind of upgrading every

3-5 years (computers, software, ...) to fulfill the functional requirements

Technology developing quite rapidly • demanding to describe adequate requirements • development also a possibility - service provider will have

more possible solutions

Operating the traffic management system will be done by road authority

Page 7: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

715.1.2007 / Nygård Magnus

Existing guidelines and material in the traffic management

Some guidelines are not available, however various regulation exist:

• Variable message traffic sings - Part 1 product standard (EN 12966-1) was available as a draft version

• National guidelines for planning of road tunnels was under preparation

defining the national guidelines - starting point for this work was ”EU’s tunnel directive” (2004/54/EY)

• Finnra gives out more detailed requirements on variable traffic signs

color, size, pictogram, ...

• Some of the requirements for fixed signs is valid to variable traffic signs

Page 8: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

815.1.2007 / Nygård Magnus

Lack of guidelines

Guidelines for planning the system not available in 2005 • under preparation

The problem of missing planning guidelines was dealt with ”typical solutions”• for example. guidelines for

planning of road tunnelsFigure D.1.4.6. Example on location of

traffic management equipment near a two-tube tunnel

Page 9: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

915.1.2007 / Nygård Magnus

E18 traffic management system

Variable speed limits, warning signs and information signs

Incident detection system (Karnainen tunnel 2,2 km)

Monitoring of road weatherMonitoring of trafficTelecommunicationElectricity User interfaceTechnical barriers

• between the carriageway • across the carriageway

Continuous surveillance of the state of the system

Page 10: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

10

15.1.2007 / Nygård Magnus

Structure of technical requirements

8.2 Variable traffic management system8.2.1 Description 8.2.2 Guidelines and regulation8.2.3 Functional requirements8.2.4 Technical requirements 8.2.5 Method requirements/descriptions

Page 11: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

11

15.1.2007 / Nygård Magnus

Description / guidelines

Variable traffic management system: • the contents and overall principles of operation described in a

separate document: Highway 1 Turku-Helsinki, Prefeasibility study of traffic telematics - Only in Finnish [Valtatie 1 Turku Helsinki, Liikennetelematiikan esiselvitys, Tiehallinnon selvityksiä 20/2002 ]

Description of the system: • the coverage• objective

Monitoring of road condition and weather: • done accordingly to the Quality system and manual of Finnra’s Road

Weather system (ISO 9001:2000 certified).

Page 12: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

12

15.1.2007 / Nygård Magnus

Functional requirements

The aim was to use functional requirements as much as possible• sometimes demanding to set clear and precise requirements if not possible then technical requirements were set

Distribution of electricity / power supply network • In tunnels, a separate power network is required alongside the

normal power network to ensure the operations of traffic management system.

• The data communications system , including the client stations for traffic management system shall meet the requirements for uninterrupted power supply (UPS). The UPS equipment in remote use and local control rooms is to be designed so that it can feed the system for 30 minutes. This system includes: ....

Page 13: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

13

15.1.2007 / Nygård Magnus

Technical requirements

Monitoring of traffic: • The monitoring equipment must registrate for every vehicle:• time of vehicle passing the cross-section, speed (km/h), length (m),

distance to vehicle ahead (s), direction, lane the vehicle was using and the type of vehicle

Quality: • quality requirements (max measurement error allowed) : • speed +/- 1 km/h• amount of traffic +/- 1 % • distance between vehicles +/- 0,01 s• length +/- 0,02 m• passenger cars and vans, trucks, buses, trailer trucks

Page 14: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

14

15.1.2007 / Nygård Magnus

Method requirements/descriptions

”To be used only if not possible to set requirements otherwise”

Cameras: • The quality of the camera picture must be approved by Finnra.

The quality must at least the same as the camera pictures for existing Turku – Muurla cameras of traffic management system. Examples were available via internet.

• Service provider must show that the requirements are set.

• ... this requirements especially important in Finland due to the dark conditions in winter-time

Page 15: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

15

15.1.2007 / Nygård Magnus

Quality assurance in the Payment mechanism

Time to repair malfunctions of the system are defined: • if service provider fails to restore the functionality of the

system/equipment in the given time, the payment will be lowered (i.e. service provider will be fined)

For example: • Road weather stations are not functioning according to the

requirements: 250 € / time, + 10 € every starting hour• 72 hours to fix the equipment

• Larger malfunctions might demand for lowering the speed limit, the payment mechanism deals with these more severe situations

Page 16: 15.1.2007 / Nygård Magnus Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

Traffic management in a DBFM project - CASE E18 Muurla-Lohja Finland

16

15.1.2007 / Nygård Magnus

... finally on the requirements

Service provider has got possibility to suggest other solutions of the system • Finnra must approve these solutions• Service provider has got the responsibility of maintenance for

more than 20 years • ...

Possibility to make innovations.