136326901 Planning Construction and Environmental

Embed Size (px)

Citation preview

  • 7/28/2019 136326901 Planning Construction and Environmental

    1/214

    PLANNING,CONSTRUCTION AND

    ENVIRONMENTAL

  • 7/28/2019 136326901 Planning Construction and Environmental

    2/214

    2011

    Fourth Edition@All Rights Reserved

    American Association of Airport ExecutivesBy Jeffrey C. Price Leading Edge Strategies and the Metropolitan State College of

    Denver, and Dr. Jeffrey S. Forrest, Metropolitan State College of Denver

    Stephen Quilty, A.A.E., wrote the original version of the modules with periodic updates by theAAAE Board of Examiners, AAAE staff, and industry experts. Revised Fall 2011.

  • 7/28/2019 136326901 Planning Construction and Environmental

    3/214

    Planning, Construction and

    EnvironmentalTable of Contents

    ModuleObjectives................................................................................................................ 1AirportSystemPlanning.................................................................................................... 3

    National Plan of Integrated Airport Systems (NPIAS) ..................................................... 4TheAirportsCapitalImprovementPlan(ACIP)..................................................... 11StateandMetropolitanAirportSystemPlanning.................................................. 13AirportMasterPlans........................................................................................................ 15

    Purpose of the Master Plan and Airport Layout Plan .................................................... 15Phase 1: PrePlanning.................................................................................................................. 18Phase 2: Elements of the Master Plan Studies .................................................................. 22

    Airside................................................................................................................................... 41

    Safety Areas ..................................................................................................................................... 42Markings, Signs and Lighting ................................................................................................... 43NAVAIDS and Air Traffic Control ............................................................................................ 55Airspace ............................................................................................................................................. 75

    TerminalandLandsidePlanning................................................................................ 81Terminal Layouts .......................................................................................................................... 81Terminal Design Considerations ............................................................................................ 85

    Common-useFacilities(CUF)/Common-useTerminalEquipment...............97Miscellaneous Design Considerations .................................................................................. 99Americans with Disability Act ............................................................................................... 105AirportDesignGuidance.............................................................................................. 110Runway and Taxiway System ............................................................................................... 112Design of Other Landing Facilities ...................................................................................... 119

    EnvironmentalRegulationsandIssues................................................................... 123Environmental Requirements for Airport Development Projects ........................ 124Environment Assessment and Audit .................................................................................. 128Environmental Regulations ................................................................................................... 134Environmental Enforcement ................................................................................................. 151Sustainable Development (SD) and the Green Airport Initiative .......................... 153

    AirportCapacityandDelay.......................................................................................... 159Impact of Capacity Restraints ............................................................................................... 160Managing Capacity ..................................................................................................................... 162Demand Management ............................................. ............................................. ..................... 166

    AirportNoiseandLandUseCompatibility............................................................. 169Legislative Acts ............................................................................................................................ 170Factors in Airport Noise Mitigation .................................................................................... 173FAR Part 150 ................................................................................................................................ 180Part 150 Standards of Review .............................................................................................. 184

  • 7/28/2019 136326901 Planning Construction and Environmental

    4/214

    FAR Part 161 Notice and Approval of Airport Noise Access Restrictions ......... 200AirportConstructionManagement........................................................................... 204References......................................................................................................................... 209

  • 7/28/2019 136326901 Planning Construction and Environmental

    5/214

    1

    ModuleObjectives

    Your objective in reading this material is to be able to:

    1. Explain the NPIAS and the ACIP process;2. Describe the roles of States and Metropolitan areas in airport planning;3. Explain the role of the Airport Master Plan, and describe the elements included in

    a Master Plan Study;

    4. Recognize airfield markings, signs and lighting configurations, look and function;5. Construct the Part 77 surfaces;6. Describe terminal design considerations and key factors, such as passenger flow

    and services, and explain ADA, FTZ, ARFF and SRE requirements;

    7. Identify key issues and characteristics of the airports runway and taxiway systemand other landing facilities;

    8. Determine which environmental regulations contribute to the requirements ofairport operators;

    9.

    Explain the environmental review process, including categorical exclusions,environmental assessments and environmental impact statements, as well as the

    exceptions to this process;

    10.Recognize key capacity and delay issues, including those elements that contributeto delays in the system;

    11.Describe the legislative acts relevant to airport noise and their resultant impact onairport operators;

    12.Compare and contrast the Part 150 and Part 161 studies, and know the keyelements of the Part 150 study; and

    13. Explain the airport construction management process.

  • 7/28/2019 136326901 Planning Construction and Environmental

    6/214

    2

    Introduction

    The airport generally consists of three primary areas: landside, terminal and airside. The

    landside area consists of intermodal and ground access areas, such as ingress and egress

    routes to the terminal building, parking garages, rental car facilities, public transportation,

    and other airport support areas. Functional areas within a commercial service airport

    typically include passenger terminal ticketing counters, baggage claim areas, concessions,

    restrooms, public assembly areas, airline clubs, mechanical space, ground transportation,

    security screening, and administrative areas for the airport operator, airlines and other

    tenants. Passenger terminals also include intermodal transportation, vendor storage,

    employee daycare and workout facilities, pet areas, and business centers. Often, a general

    aviation terminal is co-located with an FBO and includes administrative areas, flight

    planning, pilot lounges, and meeting and training rooms. Airside includes the runways,

    taxiways and aircraft parking areas within the perimeter fence.

    Each area of the airport requires detailed planning efforts to maximize the long-term

    growth of the airport. Demands on the facility, as well as needs of the community and

    various local, regional, state, and federal requirements, must be understood and

    incorporated into the planning studies. The applicable requirements and associated

    standards should be incorporated into the planning effort so as to account for demand and

    capacity changes, stakeholder and community needs, financing, safety, security and

    environmental, to name a few. The planning function is a critical component of airport

    management. Large sums of money are involved, and long-term binding agreements and

    large parcels of land are often affected during the planning process. Once its built, it

    must also be maintained, making the planning process an integrated part of the entire

    airport system. Plans, once implemented, affect the airports revenue and expenses and

    may impact air carriers, tenants, vendors and the community.

    The planning process is comprised of several elements. Airport Master Plans are the

    primary document used at airports for long-range planning. Master plans represent the

    vision of the airport operator, the stakeholders, the local community, government

    agencies, planners and airport sponsors, up to 20 years out. Master plan updates, Airport

    Layout Plan updates and Capital Improvement Plans address shorter-term needs.

    Regardless of the short or long term nature, airport operators must address several

    elements in the planning and development of airport projects, including noise abatement,

    environmental and the demand the airport can expect in terms of aeronautical service and

    customer expectations.

    This module addresses the many elements involved in planning developments and

    handling environmental issues at airports.

  • 7/28/2019 136326901 Planning Construction and Environmental

    7/214

    3

    stem plans identify theation facilities required to

    eet the needs at eachanning level. They arermulated on the basis oferall transportationmands and are coordinatedth other transportation

    anning and comprehensivend-use organizations.

    rport Master Plans detaile specific, long-range plansthe individual airportthin the framework oftewide and

    gional/metropolitan systemans.

    AirportSystemPlanning

    Airport planning is performed at national, state, regional and local levels and

    involves a number of factors, including the availability of funds, the role of the

    airport within the national airport system planning structure, whether the airport is

    part of a formal regional system of airports, and the needs and desires of the local

    community.

    System plans identify the aviation facilities required to meet the needs at each

    planning level. They are formulated on the basis of overall transportation

    demands and are coordinated with other transportation planning and

    comprehensive land-use organizations. In the U.S., airport planning is performed

    at several levels:

    1. TheNational Plan of I ntegrated Airport Systems (NPIAS),an l0-yearplan continually updated and published by the FAA, lists public use

    airports and their development programs. The needs identified are

    considered to be in the national interest and are eligible for federal

    financial planning and development assistance.

    2. Statewide integrated airport systems planning identifies the generallocation and characteristics of new airports and the general expansion

    needs of existing facilities to meet statewide air transportation goals. This

    planning is performed or sponsored by state transportation or aviationplanning agencies.

    3. Regional/metropolitan integrated airport systemsplanning identifiesairport needs for large regional/metropolitan areas. Needs are stated in

    general terms and incorporated into statewide system plans. This planning

    is done by regional/metropolitan planning agencies.

    4. Airport Master Plansare prepared by the owner/operators of individualairports, usually with the assistance of consultants. They detail the

    specific, long-range plans of the individual airport within the framework

    of statewide and regional/metropolitan system plans. These plans identify

    the development needs at individual airports on the basis of forecasts of

    aviation activity, the potential environmental effects, community

    compatibility, and financial feasibility.

  • 7/28/2019 136326901 Planning Construction and Environmental

    8/214

  • 7/28/2019 136326901 Planning Construction and Environmental

    9/214

    5

    he NPIAS Report identifiesor Congress and the publichose airports included in theational system, the rolehey serve, and the amountsnd types of airportevelopment eligible forederal funding under the

    AIP over the next five years.

    he NPIAS includesstimates of the amount of

    AIP funding needed to fundnfrastructure developmentrojects that will bring theesign of these airports up tourrent standards and addapacity to congestedirports.

    1. Part of a State Airport System Plan;2. Serving a community more than 30 minutes from the nearest NPIAS

    airport;

    3. Forecast to have 10 or more based aircraft within the next 5 years; and4. There is an eligible public sponsor willing to undertake ownership and

    development of the airport.

    Airports that do not meet any of the aforementioned criteria may still be included

    through special justification, such as:

    1. A determination that the benefits of the airport will exceed itsdevelopment costs;

    2. Written documentation describing isolation;3. Airports serving the needs of American Indian communities;4. Airports needed to support recreation areas; and5. Airports needed to develop or protect important national resources.

    Published every two years, the plan includes the cost of eligible, airport

    development that the Secretary of Transportation considers necessary to provide a

    safe, efficient and integrated system of public-use airports adequate to meet the

    needs of national defense, the U.S. Post Office and civil aeronautics. The NPIAS

    Report identifies for Congress and the public those airports included in the

    national system, the role they serve, and the amounts and types of airport

    development eligible for federal funding under the AIP over the next five years.

    Only AIP-eligible development is included in the NPIAS.

    There are approximately 20,000 airports in the U.S., accounting for an estimated

    40 percent of all commercial aviation and 50 percent of all general aviation

    activity in the world. Twenty-six percent of the airports are classified as public

    use and 74 percent, the majority, are classified as private use. 1,834 public-use

    airports (and approximately 14,000 private-use airports) are not included in the

    NPIAS because they do not meet the minimum entry criteria, are located at

    inadequate sites, or cannot be expanded and improved to provide a safe and

    efficient airport.

    The NPIAS includes estimates of the amount of AIP funding needed to fund

    infrastructure development projects that will bring the design of these airports up

    to current standards and add capacity to congested airports. However, the listing

    of any location, airport, or development item does not legally obligate the federal

  • 7/28/2019 136326901 Planning Construction and Environmental

    10/214

    6

    Airport should be safe anefficient, located at optimsites, and developed andmaintained to appropriatstandards.

    Airports should becompatible with surroucommunities, maintainbalance between the neaviation and therequirements of residenneighboring areas.

    government to provide funds or imply environmental approval of such projects.

    Further, the NPIAS is not really a plan as it does not include a timetable for

    development, assign priorities or propose funding levels.

    Airport Master Plans and state system plans provide the cost estimates that are

    included in the NPIAS. These plans are usually funded in part by the FAA, are

    consistent with FAA forecasts of aeronautical activity, follow FAA guidelines,

    and have been reviewed and accepted by FAA planners who are familiar with

    local conditions. Efforts have been made to obtain realistic estimates of

    development needs that coincide with local and state, capital improvement plans.

    The guiding principles of federal involvement in airports have remained

    unchanged since the Federal Airport Act of 1946. To meet the demand for air

    transportation, the airport system should adhere to the following guidelines:

    1. Airports should be safe and efficient, located at optimum sites, anddeveloped and maintained to appropriate standards;

    2. Airports should be affordable to both users and the government, relyingprimarily on user fees and placing minimal burden on the general revenues

    of local, state, and federal government;

    3. Airports should be flexible, expandable, and able to meet increaseddemand and to accommodate new aircraft types;

    4. Airports should be permanent, with the assurance that they will remainopen for aeronautical use over the long term;

    5. Airports should be compatible with surrounding communities, maintaininga balance between the needs of aviation and the requirements of residents

    of neighboring areas;

    6. Airports should be developed in concert with improvements to the airtraffic control system;

    7. The airport system should support national objectives for defense,emergency readiness, and postal delivery;

    8. The airport system should be extensive, providing as many people aspossible with convenient access to air transportation, typically not more

    than 20 miles travel to the nearest NPIAS airport; and

    9. The airport system should help air transportation contribute to aproductive national economy and international competitiveness.

  • 7/28/2019 136326901 Planning Construction and Environmental

    11/214

    7

    ciding what projects goo the NPIAS is a functionndividual Airport Master

    ans and Airport Layoutns, aviation forecasts,

    sting runway capacity andnual airport capacities,port dimensional standardse. airport design guidance)related to each airportstical aircraft, and othertors, such as landquisition, NAVAIDs andmp space.

    NPIAS developmentcategories include: safety andecurity, reconstruction,tandards, environment,erminal building, surfaceaccess and airfield capacity.

    Items included in the NPIAS are the result of local airport sponsors and their

    planning efforts. The local FAA Airports Division Officeis heavily involved in

    these local planning efforts and in ensuring that applicable projects are included

    in the NPIAS. Regional Airports Division Managers are responsible for making

    decisions with respect to input and revisions to the NPIAS, exceptrecommendations proposed for commercial service airports. Recommendations

    for commercial service airports must be approved by the Director of the Office of

    Airport Planning and Programming before being included in the NPIAS. The

    NPIAS does include unfunded development, as it is designed to focus on needed

    improvements, rather than availability of money.

    FAA Order 5090.3C recommends that the availability of funds not be considered

    a factor in creating the plan, as the allocation of funds occurs at the time of project

    implementation. Nor does the FAA recommend including development in whichsources of funding are secured through PFCs, bonds or other sources; if the

    project is not justified by aviation forecasts; if the project is not feasible for the

    airport or is not supported by the airport sponsor, or if the project is revenue

    producing (unless all other development needs are first met). With these

    considerations in mind, the NPIAS does not reflect all of the needs of a particular

    airport.

    Deciding what projects go into the NPIAS is a function of individual Airport

    Master Plans and Airport Layout Plans, aviation forecasts, existing runway

    capacity and annual airport capacities, airport dimensional standards (i.e. airport

    design guidance), as related to each airports critical aircraft, and other factors,

    such as land acquisition, NAVAIDs and ramp space. Certain landside projects,

    such as projects at air carrier airports that are included as part of the Airport

    Master Plan, can also be included in the NPIAS. For further information on this

    process and regarding which airports maybe included in the NPIAS, refer to FAA

    Order 5090.3C.

    Projects listed in the NPIAS are categorized by the purpose of the development

    and the type of airport. The three general categories of work are: Purpose(safety,

    rehabilitation, capacity, standards),physical component (runway, taxiway,

    apron, equipment acquisition) and thetype of work (construct, expand, improve).

    Examples of development include: lighting, marking, pavement rehabilitation,

    runway and taxiway extension, terminal rehabilitation or expansion, noise

  • 7/28/2019 136326901 Planning Construction and Environmental

    12/214

    8

    Reconstruction includesdevelopment to replace orehabilitate airport facilitprimarily pavement and

    lighting systems that havdeteriorated due to weathuse and which have reacthe end of their useful liv

    Standardsprojects refer tFAA airport design standand include developmentbring existing airports updesign criteria recommenby FAA.

    Standards development ageneral aviation and relieairports is generally justifaccommodate a substantinumber of operations by critical aircraft with sizand operating characteristhat were not foreseen at time of original construct

    The environment category

    includes projects designedachieve an acceptable balabetween airport operationrequirements, environmenrequirements, and theexpectations of residents osurrounding area for a quiand clean environment.

    mitigation, acquisition of ARFF or snow removal equipment, landside access

    roadways, safety areas, runway protection zones, etc.

    NPIASCategories

    NPIAS development categories include: safety and security, reconstruction,

    standards, environment, terminal building, surface access and airfield capacity.

    Safety and security projects include development that is required by federal

    regulation, as well as airport certification procedures or design standards, and are

    intended primarily for the protection of human life. Projects included in the safety

    category are obstruction lighting and removal, acquisition of fire and rescue

    equipment, and improvements to runway safety areas. Security projects include

    perimeter fencing, security devices, and other security enhancements, such as

    modifications to terminals to accommodate explosive detection equipment.

    Reconstruction includes development to replace or rehabilitate airport facilities,

    primarily pavement and lighting systems that have deteriorated due to weather or

    use and which have reached the end of their useful lives. Reconstruction is

    included in the NPIAS when normal maintenance procedures are no longer

    economical and effective.

    Standardsprojects refer to FAA airport design standards and include

    development to bring existing airports up to design criteria recommended by the

    FAA. This development category remains the largest, accounting for 27 percent

    of the NPIAS. Many commercial service airports were designed more than 50

    years ago to serve relatively small and slow aircraft, but are now being used by

    larger and faster turboprop and jet aircraft, resulting in runway and taxiway

    relocations to provide greater clearance for aircraft with larger wingspans.

    Aircraft parking areas must be adapted to accommodate larger aircraft. Standards

    development at general aviation and reliever airports is generally justified to

    accommodate a substantial number of operations by a critical aircraft with sizes

    and operating characteristics that were not foreseen at the time of original

    construction. If this work is not undertaken, aircraft may be required to limit fuelor passenger loads because of inadequate runway length. The FAA usually

    requires an indication that an aircraft type will account for at least 500 annual

    itinerant operationsat an airport before development is included in the NPIAS

    to accommodate it.

  • 7/28/2019 136326901 Planning Construction and Environmental

    13/214

    9

    rfield Capacity isevelopment to improve anrport for the primaryurpose of reducing delay

    nd/or accommodating moreassengers, cargo, aircraftperations, or based aircraft.

    Theenvironment category includes projects designed to achieve an acceptable

    balance between airport operational requirements, environmental requirements,

    and the expectations of residents of the surrounding area for a quiet and clean

    environment. This development supplements the large noise reductions that have

    been achieved by quieter aircraft and the use of noise abatement procedures.Much of the funding goes to relocating households and providing soundproofing

    of residences and public buildings in underlying aircraft approach and departure

    paths, but the majority of funding (80%) goes to land acquisition or easements to

    compensate property owners for overflights.

    Terminal buildingcosts are incurred for development to accommodate more

    passengers and different aircraft (small regional jets and new, large aircraft). This

    development category is the third largest, accounting for 18 percent of the NPIAS

    costs. The NPIAS only includes the portion of terminals that are eligible forfederal aid (about 50 to 60 percent) and excludes revenue-generating areas used

    exclusively by a single tenant or by concessions, such as gift shops and

    restaurants.

    Surface Accessincludes the portion of airport ground access (highways and

    transit) that is within the airport property line and eligible for grants under the

    AIP. This includes curbside improvements and improving passenger access to the

    airport terminal from surface transportation facilities.B

    Airfield Capacity is development to improve an airport for the primary purposeof reducing delay and/or accommodating more passengers, cargo, aircraft

    operations, or based aircraft. This development category includes new runway,

    taxiway, and apron construction and extensions. Runway development that is

    warranted to relieve congestion but precluded because of political and

    environmental considerations is not included.

    New Airportsare recommended in the NPIAS for communities that generate a

    substantial demand for air transportation and either do not have an airport or have

    an airport that cannot be improved to meet minimum standards of safety andefficiency. In addition, new commercial service and reliever airports are

    recommended for communities where existing airports are congested and cannot

    be expanded to meet the forecast demand for air transportation. This category

    accounts for three percent of all NPIAS development.

    B Note that revenue producing parking lots are not included.

  • 7/28/2019 136326901 Planning Construction and Environmental

    14/214

    10

    Other- This category of development accounts for less than one-half of one

    percent of the total development in the NPIAS. It includes fuel farms, utilities,

    and construction and rehabilitation of parking lots, general aviation and reliever

    airports.

  • 7/28/2019 136326901 Planning Construction and Environmental

    15/214

    11

    he values generated by theational Priority System

    NPS) equation serve only toategorize airportevelopment in accordanceith agency goals andbjectives.

    With the extensive demandsr money, the FAA muststribute funds to the regions

    na way that ensures that theghest priority projects areeing funded.

    TheAirportsCapitalImprovementPlan(ACIP)

    NPIAS priorities are guided by a national priority system, which also guides the

    distribution of funds. Project prioritization is primarily handled throughFAA

    Order 5100.39Airport Capital Improvement Program.The FAA uses a

    numerical system as one tool for prioritizing airport development. The values

    generated by theNational Priority System (NPS) equation serve only to

    categorize airport development in accordance with agency goals and objectives.

    The NPS is the combination of quantitative and qualitative evaluations of airport

    development to establish and justify AIP expenditures.

    While the NPIAS identifies for Congress and the public the composition of a

    national airports system and the development and cost necessary to expand and

    improve the system, the ACIP provides the additional detail, including anticipatedsources of funding and a prioritization of projects. With the extensive demands

    for money, the FAA must distribute funds to the regions in a way that ensures that

    the highest priority projects are being funded. The ACIP is intended to help

    accomplish this objective (see Figure 1). It is a needs-based, three- to five-year

    plan for funding of airport planning and development projects.

    Figure1.AirportCapitalImprovementProcess

  • 7/28/2019 136326901 Planning Construction and Environmental

    16/214

    12

    Statutory emphasis (rungrooving, friction treatmand distance-to-go signsprimary and secondaryrunways at commercialairports; vertical visualguidance systems on allprimary runways at

    commercial service airpand runway lighting, taxlighting, sign systems, amarking for all commerservice airports).

    The ACIP components that are used to determine project priority include the NPS

    Equation, the airport code (used to identify the role and size of the airport), the

    ACIP project code, which includes the purpose, component and type of project,

    and the category definition. There are 8 Category definitions, 17 Components and

    39 Types. The Category Definitions include:

    1. Safety/Security (projects related to Title 14 CFR Part 139 (AirportCertification) or Title 49 CFR Part 1542 (Airport Security);

    2. Statutory emphasis (runway grooving, friction treatment, anddistance-to-go signs on all primary and secondary runways at

    commercial service airports; vertical visual guidance systems on all

    primary runways at commercial service airports; and runway lighting,

    taxiway lighting, sign systems, and marking for all commercial service

    airports);3. Reconstruction/Rehabilitation (development required to preserve,

    repair, or restore the functional integrity of the airside servicing area;

    4. Environment (projects related to the National Environmental PolicyAct NEPA, FAR Part 150, or other laws governing environmental

    matters, such as the Clean Air Act);

    5. Planning(studies that are necessary to define and prioritize airportdevelopment needs);

    6. Capacity (items that improve an airport or system of airports for theprimary purpose of accommodating more passengers, cargo, aircraft

    operations or based aircraft);

    7. Standards(development at existing airports intended to attainrecommended airport design standards based on the current design

    category); and

    8. Other (development items necessary for the safe and efficient airportoperations, such as people movers, ground access projects, parking

    lots, fuel farms and projects converting military airfields to civil use as

    authorized under the Military Airport Program (MAP).

    C

    CProjects funded through MAP are those that are necessary to ensure that military airfields meetcivil standards and are able to meet the needs of the civil aviation users. Aircraft hangars, terminalbuildings, fuel farms, utility system modification, surface parking, and roads can be funded fromthe MAP, development not generally AIP eligible.

  • 7/28/2019 136326901 Planning Construction and Environmental

    17/214

    13

    hen formulating regionalCIP project prioritizationnd funding

    commendations, FAAanners are encouraged toke into account five otherctors including: (1) financialnsiderations, (2) sponsor

    erformance, (3) planningctors, (4) legal andgulatory requirements and) state and local factors.

    Additional factors in the rankings include local innovations, environmental issues,

    and airport growth. The numerical priority rating is intended to be used in

    conjunction with qualitative factors to select airport development projects. Use of

    qualitative factors that supplement a projects numerical rating must be

    documented. When formulating regional ACIP project prioritization and fundingrecommendations, FAA planners are encouraged to take into account five other

    factors including: (1) financial considerations, (2) sponsor performance, (3)

    planning factors, (4) legal and regulatory requirements and (5) state and local

    factors.

    StateandMetropolitanAirportSystemPlanning

    Airport system planning is a tool used by state and regional, metropolitan

    planning agencies. System plans are designed to provide information andguidance on the extent, kind, location and timing for public airports, in order to

    produce a viable, balanced and integrated air transportation system.1

    This strategy provides information to guide detailed planning for comprehensive

    land use, ground transportation, and other metropolitan developmental activities.

    A Metropolitan Air System Plan (MASP) or a State Aviation System Plan

    recommends the general location and characteristics of new airports and the

    nature of development and expansion for existing ones. It identifies the principal

    role of each airport in the area and estimates proposed activity. The system planfurther shows the timing and the estimated cost of development. It integrates

    airport system planning into the areas policy and coordination efforts,

    particularly for ground transportation, land use, and the urban environment.

    MASP system planning is a process that allows public and political entities to

    provide input on the comprehensive planning efforts at the local, regional, state

    and national levels. Some regional system plans are eligible for FAA funding.

    The primary purpose of airport system planning is to understand the

    interrelationship of the airports within a specific region. The process takes intoaccount the requirements of the aviation community, as well as the demographics,

    economy, and availability of surface transportation within the region. The process

    should be consistent with state or regional transportation goals, land use, and

    environmental sensitivities.The process is similar to the development of an

    Airport Master Plan, in that it usually includes an inventory of the current aviation

  • 7/28/2019 136326901 Planning Construction and Environmental

    18/214

  • 7/28/2019 136326901 Planning Construction and Environmental

    19/214

    15

    he new master plan approachlaces an emphasis on goaletting, doing the right thingn both the master plan andwith respect to environmentalequirements; it identifiesorecasting tools andddresses security issues withespect to the TSA.

    e goal of the master plan isprovide a framework tode future airportvelopment that is cost-ective and satisfies theeds of the airport, therket and the community,ile balancing

    vironmental andcioeconomic impacts.

    AirportMasterPlans

    An airport master plan is a comprehensive study of an airport and usually

    describes the short-, medium-, and long-term development plans to meet futureaviation demand. The category of study that includes master plans and master

    plan updates can, therefore, be thought of as a continuum that varies by level of

    detail and associated effort.2

    In 2007, the FAA updated AC 150/5070-6B Master Plan Advisory Circular to

    reflect several realities. Airports were creating fewer comprehensive master plans,

    and the AC had not kept pace with the changes in planning techniques. The FAA

    determined that the AC was dated but not out-of-date and that the AC continues to

    provide a good approach to the planning process. The FAA also expects that with

    the changes made in this update, the Master Plan should consistently be used to

    establish goals and objectives for the airport, with less planning done in follow-up

    work. The new master plan approach places an emphasis on goal setting, doing

    the right thing in both the master plan and with respect to environmental

    requirements; it identifies forecasting tools and addresses security issues with

    respect to the TSA. The new AC provides a flexible approach that can be applied

    to airports of all sizes.

    Purpose

    of

    the

    Master

    Plan

    and

    Airport

    Layout

    Plan

    Airport Master Plans are prepared to support the modernization of an existing

    airport or the construction of a new airport. The Master Plan is the sponsors

    strategy for the development of the airport. The goal of the master plan is to

    provide a framework to guide future airport development that is cost-effective and

    satisfies the needs of the airport, the market, and the community, while balancing

    environmental and socioeconomic impacts.

    Each master plan should carefully document and justify proposed development,

    taking into consideration the environmental, economic and technical concepts andalternatives. The Master Plan also provides a graphical presentation of the airport

    and the anticipated land uses in its vicinity; establishes a realistic implementation

    schedule, along with an achievable financial plan. Master planning must be

    sensitive to both environmental evaluations and must satisfy local, state and

    federal regulations. As a planning document, the Master Plan can document

    studies for future aeronautical demand to support local spending, debt, land use

  • 7/28/2019 136326901 Planning Construction and Environmental

    20/214

    16

    In a given study, certain mplanning elements may beemphasized, while others mnot be considered at all.

    Master planning studies thaddress major revisions arecommonly referred to asMaster Plans. Those thatchange only parts of theexisting document and reqa relatively low level of efftend to be known as MastPlan Updates.

    An update of the ALPdrawing set will reflect actuor planned modifications tothe airport and significant airport development.

    controls and other policies. Finally, the Master Plan should set the stage for future

    planning processes by monitoring key conditions and permit changes in plan

    recommendations as needed.

    Each master plan study must focus on the specific needs of the airport for which a

    plan is being prepared, and the scope of a study must be tailored to the individual

    airport. Therefore, in a given study, certain master planning elements may be

    emphasized, while others may not be considered at all. Although the FAA does

    not require airports to prepare master plans, it strongly recommends that they do

    so.3

    The master planning process will vary with the size, complexity, and role of the

    study airport and may include a variety of supporting studies. However, all master

    planning studies will fall within one of two basic types: Airport Master Plans or

    Airport Layout Plan (AL P) Updates.4

    Master planning studies that address major revisions are commonly referred to as

    Master Plans. Those that change only parts of the existing document and

    require a relatively low level of effort tend to be known as Master Plan

    Updates. In common usage, however, the distinction refers to the levels of

    effort and detail of master planning studies. In most cases, the master plan will

    include the following elements: (1) pre-planning, (2) public involvement, (3)

    environmental considerations, (4) existing conditions, (5) aviation forecasts, (6)

    facility requirements, (7) alternatives to development and evaluation, (8) AirportLayout Plans (9) a facilities implementation plan, and (10) a financial feasibility

    analysis.

    An update of the ALP drawing is an element of any master plan study. Keeping

    the ALP current is a legal requirement for airports that receive federal assistance.

    An update of the ALP drawing set will reflect actual or planned modifications to

    the airport and significant off-airport development. An accompanying ALP

    Narrative Report should explain and document those changes and should contain

    at least the following elements:

    5

    1. Basic aeronautical forecasts;2. Basis for the proposed items of development;3. Rationale for unusual design features and/or modifications to FAA Airport

    Design Standards; and

  • 7/28/2019 136326901 Planning Construction and Environmental

    21/214

    17

    While each Master Plan

    ust be accepted by theAA that does not constituteeir approval. It does not

    ommit the federalovernment to participate inny proposed development,certify that any

    evelopment isnvironmentally acceptable.

    4. Summary of the various stages of airport development and layout sketchesof the major items of development in each stage.

    Whenever the fundamental assumptions of the previous master plan have not

    changed, an ALP drawing set update is an appropriate alternative to a full masterplan. If there have not been any major changes in airport activity or improvements

    that have had unanticipated consequences, a master plan update is not necessary.

    Another situation in which only an ALP update would be appropriate is the

    examination of a single development item, such as runway, safety area

    improvements. As indicated above, an ALP update typically involves fewer

    elements than a full, master plan study, including only the aviation demand

    forecasts, an assessment of facility requirements, a facility implementation and

    financing plan, and an airport layout plan drawing set. If additional steps are

    required to complete the ALP update, a full, master plan study is probably a better

    choice.6

    Although master plans include the full list of elements previously discussed, the

    complexity of each element is dependent upon the size, function and particular

    issues and problems faced by each airport. The scope of work for the master plan

    update should address the appropriate level of detail for each element. Essentially,

    each master process is intended to produce:

    1. A technical report containing the analyses conducted in thedevelopment of the plan;

    2. A summary report that brings together facts, conclusions andrecommendations for public review;

    3. An updated, ALP plan drawing set;4. A webpage with information about the airport and key elements of

    the master plan; and

    5. A public information kit that can include visual aids, models,brochures or computer presentations to support the airport

    development program.

    While each Master Plan must be accepted by the FAA, it does not constitute their

    approval. It does not commit the federal government to participate in any

    proposed development, or certify that any development is environmentally

    acceptable. The FAA reviews the elements of the master plan to ensure that sound

  • 7/28/2019 136326901 Planning Construction and Environmental

    22/214

    18

    The airport sponsor usu

    identifies the need for aplanning study based onexisting shortcomings iplan or the introductionnew type of aircraft, crenvironmental problemchange in the strategic of the airport.

    The consultant selectioprocess is governed by Brooks Act, which req

    the selection to be basequalifications, and an ato be made according toand open selection proc

    planning techniques have been applied. The FAA only approves the Forecast

    and the Airport Layout Plan.

    Demand forecasts must resolve any inconsistency between forecasted levels and

    theTerminal Area Forecasts (TAF) which are produced by the FAA. The ALP

    must conform to FAA design standards and approval of the ALP suggests that the

    proposed developments are safe and efficient.

    Phase1:PrePlanning

    In tailoring a study to the needs of an individual airport, planners and airport

    sponsors must make two major decisions: what type of study to conduct and what

    level of detail to develop for the individual elements of the study. The airport

    sponsor usually identifies the need for a planning study based on existing

    shortcomings in the plan or the introduction of a new type of aircraft, critical

    environmental problem or change in the strategic vision of the airport. The

    airlines, tenants, federal, state or regional planning agencies, or the airport

    sponsor may all identify the need for a master plan update.

    The type of study is determined by the elements that need to be included and the

    level of effort involved. Usually, the FAA and the airport sponsor make this

    decision jointly.

    ConsultantSelection

    The current version of FAA AC 150/5100-14, Architectural, Engineering andPlanning Consultant Services for Airport Grant Projects, provides important

    guidance on consultant selection. Another useful reference is Guidelines to

    Selecting Airport Consultants, published by theAirport Consultants Council

    (ACC), an aviation industry trade association.7

    The consultant selection process is governed by theBrooks Act, which requires

    the selection to be based on qualifications and an award to be made according to a

    fair and open selection process. The grant assurance addressing Engineering and

    Design Services, specifically states that the airport sponsor must award eachcontract or sub-contract for program management, construction management,

    planning studies, feasibility studies, architectural services, preliminary

    engineering, design, engineering, surveying, mapping, or related services under

    Title IX of the Federal Property and Administrative Services Act of 1949 (Brooks

    Act), or an equivalent qualification-based requirement.

  • 7/28/2019 136326901 Planning Construction and Environmental

    23/214

    19

    f sponsors anticipate anEnvironmental AssessmentEA) or Environmentalmpact Statement (EIS),hey should consult with theocal FAA Airports office todetermine the appropriateme to begin the consultantelection process.

    As a general rule, airport sponsors hire consultants to prepare planning studies.

    Before solicitingStatements of Qualifications (SOQs), Request for

    Qualifications (RFQs), or Requests for Proposals (RFPs) from consultants, the

    airport sponsor should have a clear understanding of the issues that have defined

    the need for the study. These requests can be distributed by a number of methods,including public announcement, direct requests, and personal discussions.

    The selection process begins with an invitation to submit information via an RFP

    or an RFQ. The invitation should include the project title, the general scope of

    work, a submission deadline, submittal content requirements and an airport

    contact. Interested consultant or engineering firms normally respond with a

    submittal that includes information demonstrating its understanding of the project;

    evidence of the firms ability to perform the work; profiles of the firms

    principals, staff, and facilities; and references. If requested, statements regardingthe firms fiscal stability may also be provided.

    If sponsors anticipate anEnvironmental Assessment (EA) or Environmental

    Impact Statement (EIS), they should consult with the local FAA Airports Office

    to determine the appropriate time to begin the consultant selection process. If a

    sponsor or the local FAA Airports Office anticipates the need for an

    Environmental Assessment, the sponsor should select a qualified, environmental

    contractor to prepare the EA. When the sponsor or the FAA has substantial

    concerns, the EA may suggest that an action may cause significant impacts, the

    appropriate FAA Airports office should select the contractor to prepare the

    EA.8The consultant selection process includes:

    1. Project identification and advertisement;2. Prequalification of firms (optional);3. Request preliminary proposals;4. Preliminary short list selection;5. Formal proposals requested (and qualifications, if not prequalified

    earlier);

    6. Final selection and ranking;7. Negotiation and contract agreement; and8. Obtainment of FAA concurrence.

  • 7/28/2019 136326901 Planning Construction and Environmental

    24/214

  • 7/28/2019 136326901 Planning Construction and Environmental

    25/214

  • 7/28/2019 136326901 Planning Construction and Environmental

    26/214

  • 7/28/2019 136326901 Planning Construction and Environmental

    27/214

    23

    hile the TAC provides inputd insight on technical issuesd is composed of individualsth relevant technicalckgrounds, the CAC serves

    a sounding board andormation exchange groupstakeholders.

    mall group meetings andefings are informal sessions

    ed to discuss planernatives and may coincideth meetings by communityards, elected officials oric organizations.

    planning alternatives, increased study costs, and frustrated participants, who

    struggle to communicate with the study group.10

    Committees that facilitate public involvement usually include aTechnical

    Advisory Committee (TAC) and aCitizens Advisory Committee

    (CAC).While the TAC provides input and insight on technical issues and is

    composed of individuals with relevant technical backgrounds, the CAC serves as

    a sounding board and information exchange group for stakeholders.11

    Traditional public information meetings, those done in a presentation format with

    consultants presenting information and the community listening and providing

    feedback, are less effective than an "open house" format. The open house format,

    with interactive information stations staffed by knowledgeable individuals is a

    very effective method to engagethe public and stakeholders in soliciting their

    opinions.12Small group meetings and briefings are informal sessions used todiscuss plan alternatives and may coincide with meetings by community boards,

    elected officials or civic organizations.

    An effectivePublic Awareness Campaign is essential to a successful master

    plan process. The campaign often includes informational and educational

    materials, such as fact sheets, flyers, press releases, newspaper ads and web pages

    with interactive self-guided presentations. Electronic versions of key documents

    may also be made available online.

    IdentifyingtheStakeholdersandKeyIssues

    While the stakeholders will vary from airport to airport, the following groupsshould be considered as airport stakeholders:

    1. Users and tenants;2. Groups and individuals from within the sponsors organization;3. FAA personnel from the appropriate regional and field offices;4. Resource agencies and other governmental units with regulatory or review

    authority; and

    5. Other interested groups.Individuals from each stakeholder group must be able to represent the interests of

    their groups in discussions with the master plan team. Ideally, they should also

    represent a consensus viewpoint, rather than a special interest, minority opinion.

  • 7/28/2019 136326901 Planning Construction and Environmental

    28/214

  • 7/28/2019 136326901 Planning Construction and Environmental

    29/214

  • 7/28/2019 136326901 Planning Construction and Environmental

    30/214

  • 7/28/2019 136326901 Planning Construction and Environmental

    31/214

    27

    hort-term forecasts, for upo five years, are used toustify near-termevelopment and supportperational planning andnvironmental improvementrograms. Medium-termorecasts, with a six- to ten-ear time frame, are typicallysed in planning capitalmprovements, and long-termorecasts (beyond 10 years)re helpful for generallanning.

    used to justify near-term development and support operational planning and

    environmental improvement programs. Medium-term forecasts, with a six- to ten-

    year timeframe, are typically used in planning capital improvements, and long-

    term forecasts (beyond 10 years) are helpful for general planning. A number of

    forecasts are readily available for use in developing and evaluating the masterplan forecast. These forecasts include the Terminal Area Forecast, state aviation

    system plans, and other planning efforts.19Certain documents also provide

    guidance on conducting forecasts, including ACRP reports on aviation

    forecasting, a specific guidance document titled Forecasting Aviation Activity by

    Airport, published by the FAA, FAA Aerospace Forecasts (which provides U.S.

    economic and aviation outlooks), local data sources (city and county plans) and

    federal and state data sources that provide economic analysis.

    As mentioned previously, forecasts are subject to the approval of the FAA. Theelements used in the demand forecasts are shown in Table 1.

    Required Included Where AppropriateOperations (annual)

    ItinerantAir CarrierAir Taxi and Commuter

    (Regional)General AviationMilitary

    LocalGeneral AviationMilitary

    Domestic vs. InternationalAnnual Instrument ApproachesIFR vs. VFR OperationsAir Cargo Aircraft Operations

    Touch and Go Operations(Training)Helicopter Operations

    Average Load FactorFuel Use

    Passengers (annual)Enplanements

    Air CarrierCommuter

    EnplanementsOriginatingConnecting

    Passenger and Cargo DataDomestic vs. InternationalGeneral Aviation PassengersHelicopterAir TaxiOther

    Number of Student PilotsNumber of Hours Flown

    AircraftBased AircraftAircraft Mix

    Critical Aircraft

    Average Seats/Aircraft

    Table 1. Elements used in aviation demand forecasts for airport planning.

  • 7/28/2019 136326901 Planning Construction and Environmental

    32/214

    28

    Local operations also inclusimulated instrumentapproaches or low passes atairport. A forecast of AnnuInstrument Approaches (AIis needed for planning orupgrading navigational aidsand landing systems.

    A large amount of air carand airmail is moved by tregular air carriers, as wethe all-cargo operators, an

    should be included in theforecasts.

    Anaircraft operation is defined as a takeoff or a landing at an airport. The

    definition includes touch and go operations, which count as two operations

    one landing and one takeoff. An operation is further classified as either local or

    itinerant.

    Local operationsare arrivals and departures of aircraft, which operate in the

    local traffic pattern or within sight of the tower. They are known to be departing

    for, or arriving from, flights in local practice areas within a 20-mile radius of the

    airport and/or control tower. Local operations also include simulated instrument

    approaches or low passes at the airport. A forecast ofAnnual Instrument

    Approaches (AIA) is needed for planning or upgrading navigational aids and

    landing systems.

    Itinerant operationsare arrivals and departures other than the local operations.

    Estimates of the local and itinerant aircraft operations are developed for each ofthe four, major, civil airport user categories: Air Carriers, Commuters, Air Taxi,

    and General Aviation. A fifth category, Military, is estimated for those airports

    having significant levels of that activity. The Airport Traffic Control Tower

    routinely keeps the activity data if one exists on the field.

    Enplaning passengersare the total number of paid passengers departing on

    commercial aircraft. Originating and transfer passengers are included, as are air

    taxi or charter passengers. Not included are non-revenue passengers such as

    airline employees or thru passengers (departing on aircraft with the same flightnumber that they arrived, and not requiring re-boarding). Separate forecasts are

    developed for both domestic and international passengers. Passenger enplanement

    forecasts are made for each of the three, civil user categories: Air Carrier,

    Regional Carrier, and Air Taxi.

    Enplaning air cargo includes the total tonnage of priority, non-priority, and

    foreign mail, express, and freight (property other than baggage accompanying

    passengers) departing on aircraft at an airport, including originations, stopovers,

    and transfer cargo. A large amount of air cargo and airmail is moved by theregular air carriers, as well as the all-cargo operators, and should be included in

    the forecasts. Since the design of an airport is contingent upon the type of aircraft

    using the facility, a forecast identifying the future mix is necessary.Aircraft mix

    refers to the categories of aircraft: less than 12,500 pounds, from 12,500 pounds

    up to 60,000 pounds, and those over 60,000 pounds. An aircrafts weight,

    wingspan, and speed are tied directly to the length, width, and strength of runways

  • 7/28/2019 136326901 Planning Construction and Environmental

    33/214

    29

    n aircrafts weight,ngspan, and speed are tiedrectly to the length, width,nd strength of runways andxiways.

    A airports include forecastsr based aircraft, both theumber and type, and cargorports or airports withgnificant cargo operationsclude forecasts for cargonnage.

    emographic factors

    fluence the level of airportaffic, its composition, and itsowthin terms of bothcoming traffic from otherates, regions, or cities, andaffic generated by the localregional populations.

    and taxiways. Helicopter operationsat the airport also have design

    considerations and should be forecasted.

    Aviation demand forecasts typically identify the airports design, aircraft and fleet

    mix, and for commercial service airports, the number of passenger enplanements.

    GA airports include forecasts for based aircraft, both the number and type, and

    cargo airports or airports with significant cargo operations include forecasts for

    cargo tonnage.

    While forecasts generally provide an average over the course of a year, most

    airports have peak periods during which demand far surpasses those averages.

    These peaks are critical at commercial service airports serving as hubs or having

    substantial international traffic. Master plan forecasts must include appropriately

    defined peak period activity, such aspeak-hour, average-day, peak-month,

    for the planning of facilities such as terminal buildings and ground access

    systems.20

    FactorsAffectingDemandForecasts

    The art of aviation demand forecasting has undergone considerable study and

    advancement in recent years. Found to be of particular significance, the following

    factors are used to forecast the demand for individual airport master plans and to

    update and refine those forecasts:

    1. Economic Characteristics. A communitys economic character affects its airtraffic-generating potential. This factor is particularly important in connection

    with business travel by commercial and general aviation aircraft and with air

    cargo traffic. Manufacturing, service industries, primary and resource businesses,

    agricultural flying, instructional flying, and aircraft sales all generate air transport

    activity both within and outside the airport area.

    2. Demographic Characteristics. The size and composition of an airport

    communitys populationand its potential growth rateare basic ingredients in

    creating demand for air transportation services. These characteristics include anareas population profile and changes in its age, educational, and occupational

    distribution. Demographic factors influence the level of airport traffic, its

    composition, and its growthin terms of both incoming traffic from other states,

    regions, or cities, and traffic generated by the local or regional populations. The

    discretionary purchasing power available to an airports market area residents

  • 7/28/2019 136326901 Planning Construction and Environmental

    34/214

    30

    Aviation Related FactoFuel price fluctuations,changes in items such athe regulatory environmthe levels and types oftaxes, fees, and currencrestrictions, businessactivity, industry trendsmergers, consolidationsnew marketing agreemeare such factors.

    over any period of time is a good indicator of consumers financial ability to

    travel. This is known as the disposable personal income. Distinct, local

    preferences for particular modes of transportation may exist, but in some cases,

    alternative modes of transportation may not be available or economically feasible.

    The higher the levels of disposable, personal income, the more likely the demand

    for air transportation services will exist.

    3. Geographic Attributes. The geographic distribution and distances between

    populations and centers of commerce within the market area served by an airport

    may have a direct bearing on the type and level of transportation services that will

    be demanded. The physical characteristics of the land and local climatic

    differences may also be important, sometimes limiting aviation demand. On the

    other hand, physical and climatic attractions often stimulate holiday traffic and

    tourism. The relationship of the airport undergoing the master plan process toother airports and to the routes and airways in the regional and national systems

    may have a strong bearing on types and levels of aviation services that might be

    demanded at the master plan airport.

    4. Aviation Related Factors. A number of other factors might affect aviation

    demand at an airport. Fuel price fluctuations, changes in items such as the

    regulatory environment, the levels and types of taxes, fees, and currency

    restrictions, business activity, industry trends, mergers, consolidations and new

    marketing agreements are such factors. In addition, local attitudes toward theenvironmental effects of aviation may affect demand and should be considered in

    forecasting or updating forecasts. Similarly, the granting of new routes for

    international air service can induce important changes in the volume of traffic at

    the specific airports receiving the international service.

    (5) Other Factors. There are a number of actions that local airport authorities or

    operators take that have the conscious or unintended effect of either stimulating or

    retarding growth in aviation demand. The types of ground access and support

    services provided, user charges, and plans for future development can each affectfuture growth of aviation demand. Economic fluctuations such as fuel price

    changes, currency and trade restrictions, political developments, international

    tension, changing regulations and environmental impacts should all be Steps in

    the Forecast Process.

  • 7/28/2019 136326901 Planning Construction and Environmental

    35/214

    31

    Steps in this process includehe identification ofparameters and measures toorecast, review of previous

    orecasts, determination ofdata needs, identification ofdata sources, collection of thedata, selection of the forecastmethods, preparation of theorecasts, and evaluation and

    documentation of the results.

    The actual forecast steps vary from airport to airport, depending on the issues to

    be addressed and the level of effort required to develop the forecast. Steps in this

    process include the identification of parameters and measures to forecast, review

    of previous forecasts, determination of data needs, identification of data sources,

    collection of the data, selection of the forecast methods, preparation of theforecasts, and evaluation and documentation of the results. Planners should refer

    to a report prepared by the FAAs Office of Aviation Policy and Plans (APO-

    110), Forecasting Aviation Activity by Airport, dated July, 2001, to help them

    determine which approach to use.21

    The forecast process includes: (1) the identification of aviation activity measures,

    (2) review of previous forecasts, (3) gathering the data and (4) selecting the

    appropriate forecast methods. The most common forecast techniques include:

    1. Regression Analysis a statistical technique tying aviation demand toenplanements, population and income levels.

    2. Trend Analysis and Extrapolation uses the historical pattern ofaviation activity to project future trends.

    3. Market Share Analysis assumes a top-down relationship betweennational, regional and state and local forecasts whereby local forecasts

    represent a market share or percentage of national forecasts.

    4. Smoothing a statistical technique applied to historical data focused moreon the recent trends and conditions at the airport.

    Once these analyses have been completed, the next step is to apply the forecast

    methods and evaluate results. Planners should look for variances between the

    forecast models, particularly significant historical variances between the FAAs

    Terminal Area Forecasts versus actual historical performance and other forecast

    results. Planners should also be sensitive to significant factors, such as the closure

    of an FBO or airline bankruptcy or merger and the impact such closures will have

    on the forecasts. Trends should be identified along with temporary surges or drops

    in activities. Forecasts are then submitted for approval to the FAA.

    FacilityRequirements

    In this element, planners compare the current facilities and services available at

    the airport, compare it to the forecasted demand for facilities and services, and

    then determine what additional facilities will be needed. In some circles, this is

  • 7/28/2019 136326901 Planning Construction and Environmental

    36/214

    32

    Recognize that in some cthe community or stakehmay not want the airportgrow, or grow only in alimited way. In some cascommunities have oppos

    start-up of commercialservice, and therefore, thconstruction would not bconsistent with the demaof the stakeholders toconstruct facilities toaccommodate such oper

    Planners should meet wrepresentatives of the Tearly in the process andfamiliar with the curren

    versions of applicabledocuments, including TTransportations SecuritRegulations (TSRs).

    The peak hour of the avday of the peak month csubstantially understatedemand at peak times,resulting in unacceptablevels of service oroverloading of systems point that may approach

    gridlock.

    known as a gap analysis. Recognize that in some cases the community or

    stakeholders may not want the airport to grow, or to grow only in a limited way.

    In some cases, communities have opposed the start-up of commercial service, and

    therefore, the construction would not be consistent with the demands of the

    stakeholders to construct facilities to accommodate such operations.

    While there are numerous types of facilities and services that an airport can

    provide, planners should, at the very least, look to the following elements:

    1) Capacity shortfalls;2) New TSA security requirements;3) FAA design standards and updated standards;4) Airport sponsors strategic vision for the airport; and5) Outdated condition of existing facilities.

    Emerging trends, such as the implementation ofNextGen, increased use ofGPS,

    the introduction of very light jets and super heavy large commercial jets,

    expanded use of airline kiosks and new security procedures, should also be

    considered. New regulatory changes should also be considered. For example, new

    air cargo security regulations in 2006 may impact the design of cargo facilities at

    airports. Planners should meet with representatives of the TSA early in the

    process and be familiar with the current versions of applicable documents,

    including TSAsRecommended Security Guidelines for Airport Planning, Design,

    and Constructionand relevant sections of theTransportation Security

    Regulations (TSRs).22

    Design hour demand must also be taken into consideration. In the U.S., the

    evaluation of peak hour demand is often based on the peak hour of the average

    day of the peak month. This approach provides sufficient facility capacity for

    most days of the year but recognizes that there will be some very busy days that

    experience congestion, queues, and delays and that it is important that facilities

    are neither under- nor overbuilt. However, for some critical airport systems, the

    peak hour of the average day of the peak month can substantially understate the

    demand at peak times, resulting in unacceptable levels of service or overloading

    of systems to a point that may approach gridlock. Some components of the

    passenger terminal complex, such as baggage handling systems and security

    checkpoints, are particularly sensitive to this issue.23 Specific facility

    requirements include:

  • 7/28/2019 136326901 Planning Construction and Environmental

    37/214

    33

    Airfield and airspace

    1) Airfield Capacity Analysis (annual service volume);2) Runway Requirements (design standard as related to the Airport

    Reference Code; orientation, length, width and pavement design strength);

    3)Taxiway Requirements (design standard as related to the AirportReference Code);

    4) Navaids;5) Airspace Requirements (Terminal Instrument Procedures).

    CommercialServiceTerminal

    1) Gates and Apron Frontage (aircraft parking positions by aircraft group);2) Passenger Terminal Building (including FIS, ticket counter, baggage,

    security checkpoints, departure lounges, concessions, etc);3) Curb fronts (intermodal connections).

    General Aviation Requirements

    1) Hangars (conventional hangars, t-hangars, etc);2)Transient Aircraft Parking;3)Terminal Facilities (may include FBO, administrative offices, conference

    and training rooms, rental car counters, pilots lounges and flight

    planning).

    Air Cargo Requirements

    1)Type of cargo companies (integrated carriers, freight forwarders, bellyfreight, all-cargo or combination carriers);

    2) Aircraft parking with respect to space and tonnage (pavement strength)requirements;

    3) Security needs;4) Access.

    Support Facilities

    1) Aircraft Rescue and Fire Fighting (based on changes to the airports Part139 Index);

    2) Airport Maintenance (snow removal, support vehicles);

  • 7/28/2019 136326901 Planning Construction and Environmental

    38/214

    34

    Long-term acquisitions,environmental issues, such

    those developments thatrequire an EnvironmentalAssessment or EnvironmenImpact Statement, and theavailability of funding throuthe AIP or PFC programshould also be considered.

    Secondary elements, such aARFF stations have greaterplanning flexibility; althousiting of certain facilities suas the ARFF or ATCT is aldependent on meeting FAAresponse-time and line-of scriteria respectively.

    3) Fuel Storage (for commercial and GA operations, and ground vehicleoperations);

    4) Aircraft Maintenance;5) De-icing Facilities and associated de-icing runoff facilities;6) Special areas (snow storage, storm water retention, environmentally

    sensitive areas).

    Ground Access, Circulation and Parking

    1) Regional Transportation Network (coordination with local planners);2) On-Airport Circulation Roadways (passengers, employees, delivery

    vehicles);

    3) Roadway Facilities (taxi/limo/courtesy van, rental car facilities, chartervans and busses, public parking and employee parking).

    AlternativeDevelopmentandEvaluation

    In this element, airports can address numerous development options, including

    alternatives to address facility requirements. At this point, planners should revisit

    the scope of work to verify that all processes conform to the overall intent of the

    study.

    Long-term land acquisitions, environmental issues, such as those developments

    that require an Environmental Assessment or Environmental Impact Statement,

    and the availability of funding through the AIP or PFC program should also be

    considered.

    The Alternatives process identifies the alternatives and ranks the elements in the

    planning hierarchy. Planners determine both primary and secondary elements.

    Primary elements require large amounts of land, such as runways, terminals,

    ground access and support facilities. Secondary elements, such as ARFF

    stations, have greater planning flexibility; although, siting of certain facilities

    such as the ARFF or ATCT is also dependent on meeting FAA response-time

    and line-of sight criteria respectively. The actual method of analyzingalternatives is an exercise in both force prioritization and assessing secondary

    elements that may be able to fit into or in between primary planning projects.

    Once alternatives are identified, each is evaluated based on operational

    performance (capacity, capability and efficiency). In some cases, an alternative is

  • 7/28/2019 136326901 Planning Construction and Environmental

    39/214

    35

    rant assurance number 29equires that the sponsor

    eep the ALP up to date atl times.

    ederal Aviation RegulationAR) Part 157 requiresrport owners and operators

    onotify the FAA 30 days indvance of any construction,teration, deactivation orhanges in use of any airport.

    to construct a new airport, in which case an airport site selection becomes part of

    the list of alternatives.

    TheAirportLayoutPlan

    A major product of the airport master planning process is the airport layout plan

    (ALP). It comprises drawings that include the airfields physical facilities,

    obstruction clearance and approach profiles, land use plans, terminal area and

    ground access plans, and a property map. All development carried out on

    federally obligated airports must be accomplished in accordance with a (FAA)-

    approved airport layout plan. FAA Order 5100.38,Airport Improvement Program

    Handbook, provides supplemental guidance for the preparation of an ALP. Grant

    assurance number 29 requires that the sponsor keep the ALP up-to-date at all

    times. As stated in Order 5100.38, an ALP remains current for a five-year period,

    or longer, unless major changes at the airport are made or planned.

    The functional components of an airport layout plan include everything from the

    airport entrance to the airspace around the airport. The master planning process

    considers these components in their entirety. The airport layout takes the data

    from the master plan and other studies and shows them in graphic form.

    Federal Aviation Regulation (FAR) Part 157, Notice of Construction, Alteration,

    Activation and Deactivation of Airports, requires airport owners and operators to

    notify the FAA 30 days in advance of any construction, alteration, deactivation or

    changes in use of any airport. Notification of construction or alteration on an

    airport is provided onFAA Standard Form SF-7460-1 Notice of Proposed

    Construction or Alteration. Notification of the activation or alteration of a landing

    area is provided on FAA StandardForm SF-7480 -1 Notice of Landing Area

    Proposal. For a new airport site or location, the initial investigation is the

    responsibility of the airport sponsor and not the FAA. The five primary functions

    of the ALP:

    1) It is an approved (by the FAA) plan necessary for the airport to receiveAIP funding and to continue to receive PFC funding;

    2) It is a blueprint for airport development;3) It is a public document that serves as a record of aeronautical requirements

    and community reference;

    4) It enables the FAA and airport sponsor to plan for improvements;

  • 7/28/2019 136326901 Planning Construction and Environmental

    40/214

    36

    The Airport Layout Plan required element and is ascaled graphic representatof the existing and proposairport land, facilities,protection zones, andapproach areas.

    The ALP is approved andsigned by the FAA, therebecoming a legal docume

    5) It is a working tool for airport staff including operations and maintenancepersonnel.

    AirportLayoutPlanDrawingSet

    The airport layout plan is required to include: (1) the Airport Layout Drawing, (2)

    The Airport Airspace Drawing, (3) the Inner Portion of the Approach Surface

    Drawing, (4) the Terminal Area Drawing, (5) the Land Use Drawing, (6) the

    Runway Departure Surfaces Drawing, and (7) the Airport Property Map (usually

    referred to as the Exhibit A). Additional elements can also include a Cover Sheet,

    a Data Sheet, a Facilities Layout Plan, Utility Drawings and Airport Access Plans.

    The ALP also identifies facilities that are no longer needed and includes a plan for

    their removal.

    The cover sheet includes approval signature blocks, airport location maps and

    other data required by the FAA. The Airport Layout Plan is a required element

    and is a scaled, graphic representation of the existing and proposed airport land,

    facilities, protection zones, and approach areas. It includes other environmental

    features that might influence airport operations and those features necessary for

    future airport development or expansion.D The ALP drawing identifies the

    existing and proposed facilities and features, a vicinity map, a wind rose compass,

    a basic runway and taxiway data table, a legend block, a title and revision block, a

    sponsor approval block, and an approved list of modifications to the FAA design

    standards. The ALP is approved and signed by the FAA, thereby becoming alegal document.

    The ALP should reflect any changes that may affect the navigable airspace or the

    ability of the airport to expand, including the physical features on the airport and

    the critical land uses in and around the vicinity of the airport. Grant assurances

    specifically require airport management to keep the following items up-to-date:(1)

    property lines, (2) the location and nature of all existing and proposed facilities

    and structures (i.e., runways, taxiways, aprons, terminal buildings, parking lots,

    hangars, cargo areas, navigational aids, obstructions, and roads), and (3) thelocation of all existing and proposed non-aviation areas and improvements (i.e.,

    parking lots, ground access roads, and water retention ponds).

    DThe FAA recommends that the ALP drawings be prepared on AutoCAD and that all fundingagencies (FAA, states, regional planning agencies, and airport sponsor) maintain the drawings inan electronic file format.

  • 7/28/2019 136326901 Planning Construction and Environmental

    41/214

    37

    wind rose is a diagramhowing the percentage ofme the wind blows from aarticular direction and at aarticular speed.

    e terminal drawing furtherows the ground access toeairport terminal area,ng with the majorhway routes from theport toward a centralsiness district, other pointsdestination, or key arterialstems. If applicable, other

    odes of access, such as railwater are also shown.

    Another component of the airport layout drawing is awind rose. A wind rose is a

    diagram showing the percentage of time the wind blows from a particular

    direction and at a particular speed. Runways are normally aligned with the

    prevailing winds. Crosswind (winds coming from a direction other than the

    runway heading) runways are built to accommodate primarily small aircraft thatare more susceptible to crosswind effects than are larger ones. Information on

    historic wind data can be obtained from the National Oceanic and Atmospheric

    Administration, Environmental Data Service (NOAA-EDS) in Asheville, North

    Carolina.

    1. Thedata sheet contains airport and runway data tables.2. Thefacilities layout plan depicts existing and future facilities.3. Theterminal area plan is provided to show the airport terminal and

    its surrounding facilities. A structures height is usually noted along

    with any obstruction marking or lighting. For small, GA airports, a

    separate terminal drawing may not be necessary if adequate detail is

    available on the airport layout drawing. The terminal drawing further

    shows the ground access to the airport terminal area, along with the

    major highway routes from the airport toward a central business

    district, other points of destination, or key arterial systems. If

    applicable, other modes of access, such as rail or water, are also

    shown.

    4. Theairport airspace drawingsare required elements and areintended to show all imaginary surfaces identified in FAR Part 77,

    Objects Affecting Navigable Airspace.

    5. The inner portions of the approach surface drawingare requiredelements and include a profile view that presents all runway

    approaches and the location of objects as they affect the approach. The

    profiles show the existing and ultimate planned runway length.

    Obstruction data tables and charts are also included on the airspacedrawing that provide information about the disposition of the

    obstructionproposed removal, lighting, marking, etc. The drawing

    may also depict other approach surfaces, including the threshold-siting

    surface and those surfaces associated with U.S. Standards for

    Instrument Procedures.

  • 7/28/2019 136326901 Planning Construction and Environmental

    42/214

    38

    The purpose of the drawito provide airport

    management with a plan leasing revenue-producinareas on the airport, and fproviding guidance indetermining allowablecompatible uses such asfarming, recreational,commercial or industrial.drawing also providesguidance to local plannincommissions for theestablishment of appropriairport-area zoning.

    6. Theon-airport and off-airport land-use drawingsdepict existingand recommended uses of all land within the ultimate airport property

    line and within the vicinity of the airport, at least to the 65 DNL noise

    contour. The purpose of the drawing is to provide airport management

    with a plan for leasing revenue-producing areas on the airport and forproviding guidance in determining allowable, compatible uses, such as

    ones for farming, recreational, commercial or industrial purposes. The

    drawing also provides guidance to local planning commissions for the

    establishment of appropriate airport-area zoning.

    7. Theairport property map is a drawing that depicts how varioustracts of land were acquired. It includes easements outside the airport

    property line. The purpose of the property map, often termed Exhibit

    A on AIP grant applications, is to identify the legal interest andownership of land that make up the airport. The map assists the FAA

    in determining and analyzing the current and future use of land

    acquired with federal funds. The property map and the ALP are

    required to be current at all times and submitted as part of any AIP

    Grant application.

    8. Therunway departure surface drawingdepicts applicable departuresurfaces.

    9. Theutility drawingdepicts the location and capacity of all utilities onand around the airport.

    10.Theairport access plansdepict major routes and modes oftransportation that serve the airport. These plans are normally used if

    access to the airport is a significant issue.

    Both the airport-layout narrative report and the drawings are public documents.

    They are records of the aeronautical requirements of the airport, both present and

    future, and are references for community deliberations on land use proposals, as

    well as budget and resource planning.

    ALP drawings are typically produced with computer-aided design software, and

    many include software that links the features on the map with Geographic

    Information Systems.

  • 7/28/2019 136326901 Planning Construction and Environmental

    43/214

    39

    he FAA recognizes that thean may change from year to

    ear to reflect changingonditions and priorities.hus, the CIP should beeveloped based on demandth specific improvementsentified for implementationhen specific milestonesccur.

    FacilitiesImplementationPlan

    The facilities implementation plan explains how to implement the findings and

    recommendations of the planning effort. This plan is called by many names,

    includingTransportation Improvement Plan (TIP), Capital Improvement

    Plan (CIP) or evenAirport Capital Improvement Plan (ACIP), but we will useCIP for simplicity.

    Regardless of the terms used, the facilities implementation plan must

    address all of the airports planned capital projects (even those projects

    that are not associated with the recommendations of the master plan) to

    ensure that adequate fiscal, staff, scheduling, and other resources are

    available. In addition, all documentation should be prepared so that it will

    be clearly understood by all parties.

    The facilities implementation plan must balance funding constraints;

    project sequencing limitations; environmental processing requirements;

    agency and tenant approvals and coordination processes; business issues,

    such as leases and property acquisition; and sponsor preferences. The

    plan must also be coordinated with the master plan ALP and the airports

    financial plan. (Source FAA)

    The FAA recognizes that the plan may change from year to year to reflect

    changing conditions and priorities. Thus, the CIP should be developed based on

    demand, with specific improvements identified for implementation when specificmilestones occur.

    KeyActivitiesandResponsibilities

    The Facilities Implementation Plan should provide information regarding key

    activities, such as:

    1) Sponsor-specific project approval activities (those activities requiringboard, council or other administrative body approvals and budgetary

    approvals);

    2) Airline and other tenant approvals including lease modifications;3) Project funding activities (FAA grants, PFC and long-term debt

    financing);

    4) Environmental processing activit