12 Uncertainty in Future Events

Embed Size (px)

Citation preview

  • 7/30/2019 12 Uncertainty in Future Events

    1/54

    Kuliah Ekonomi Teknik Kimia

    JTK FT UGM 2012

  • 7/30/2019 12 Uncertainty in Future Events

    2/54

  • 7/30/2019 12 Uncertainty in Future Events

    3/54

    Introduction

    Probability estimation assumed that allvalues of costs, expenses, revenues,economic lives, and acceptable rates of

    return were known with certainty. Sensitivity analysis is used to determine

    the effect of technical and economicparameters on the profitability of a

    project. The potential error of eachparametric variable is examined, as wellas its effect on the project.

  • 7/30/2019 12 Uncertainty in Future Events

    4/54

    Sensitivity analysis

    Break even analysis

    The Strauss Plot

    Relative profitability plot

    Tornado plot

  • 7/30/2019 12 Uncertainty in Future Events

    5/54

    Break even analysis

  • 7/30/2019 12 Uncertainty in Future Events

    6/54

    Break-even plot for

    pricing alternatives.

  • 7/30/2019 12 Uncertainty in Future Events

    7/54

    A realistic break-even plot.

  • 7/30/2019 12 Uncertainty in Future Events

    8/54

    The Strauss Plot

  • 7/30/2019 12 Uncertainty in Future Events

    9/54

    Example: the Strauss plot

  • 7/30/2019 12 Uncertainty in Future Events

    10/54

    TheStrauss

    plot

  • 7/30/2019 12 Uncertainty in Future Events

    11/54

    Relative probability plot

  • 7/30/2019 12 Uncertainty in Future Events

    12/54

    Tornado plot

  • 7/30/2019 12 Uncertainty in Future Events

    13/54

    Discussion of SensitivityAnalyses Only one variable at a time can be studied.

    Interrelated variables such as fixed capitalinvestment, maintenance, and other

    investment items in operating expensesand their effect upon one another cannotbe represented correctly.

    Synergistic effects particularly with respect

    to marketing variables such as salevolume, selling price, market share cannotbe taken onto account.

  • 7/30/2019 12 Uncertainty in Future Events

    14/54

  • 7/30/2019 12 Uncertainty in Future Events

    15/54

    Uncertainty analysis

    To estimate the probability of a venture,one needs to take some assumptions.

    Each assumption has its own degree of

    uncertainty, and when taken togetherthese uncertainties can result in largepotential errors.

  • 7/30/2019 12 Uncertainty in Future Events

    16/54

    Estimates and Their Use inEconomic AnalysisExample 10-1.Two alternatives are being considered. The best

    estimates for the various consequences are asfollows:

    A BCost $1000 $2000Net annual benefit $150 $250Useful life, in years 10 10End-of-useful-life-salvage value $100 $400

    If interest is 3.5%,which alternative has the better netpresent worth (NPW)?

  • 7/30/2019 12 Uncertainty in Future Events

    17/54

    Example 10-1.

    Alternative ANPW = -1000+ 150(P/A, 3.5%,10) + 100(P/F, 3.5%,10)

    = -1000 + 150(8.317) + 100(0.7089)= -1000 + 1248+ 71

    =+$319Alternative BNPW = -2000 + 250(P/A, 3.5%, 10) + 400(P/F, 3.5%,

    10)= -2000 + 250(8.317) + 400(0.7089)

    = -2000 + 2079 + 284= +$363

    Alternative B, with its larger NPW, would be selected.

  • 7/30/2019 12 Uncertainty in Future Events

    18/54

    Example 10-2.

    Suppose that at the end of 10years, the actual salvagevalue forB were $300 instead of the $400bestestimate. If all the other estimates were correct, is Bstill the preferred alternative?

    Revised BNPW = -2000 + 250(P/A, 3.5%, 10) + 300(P/F, 3.5%,

    10)= -2000 + 250(8.317) + 300(0.7089)= -2000 + 2079 + 213=+$292A is now the preferred alternative.

  • 7/30/2019 12 Uncertainty in Future Events

    19/54

    A Range of Estimates

    an optimistic estimate,

    the most likely estimate

    a pessimistic estimate

  • 7/30/2019 12 Uncertainty in Future Events

    20/54

    Example 10-3

    A firm is considering an investment. The most likelydata values were found during the feasibility study.

    Analyzing past data of similar projects shows thatoptimistic values for the first cost and the annual

    benefit are 5% better than most likely values.Pessimistic values are 15% worse. The firm's mostexperienced project analyst has estimated thevalues for the useful life and salvage value.

    Optimistic Most Likely Pessimistic

    Cost $950 $1000 $1150

    Net annual benefit $210 $200 $175

    Useful life, in years 12 10 8

    Salvage value $100 $0 $0

  • 7/30/2019 12 Uncertainty in Future Events

    21/54

    Example 10-3

    Compute the rate of return for each estimate. If a10% before-tax minimum attractive rate of return isrequired, is the investment justified under all threeestimates? If it is only justified under some

    estimates, how can these results be used.

  • 7/30/2019 12 Uncertainty in Future Events

    22/54

    Example 10-3

    Optimistic Estimate

    PW of cost = PW of benefit

    $950 = 21O(P/A, IRRopt,12) + 100(P/F,IRRopt, 12)

    IRRopt = 19.8%

    Most Likely Estimate

    $1000 = 200(P / A, IRRmostlikely,10)

    (P / A, IRRmostlikely,10) = 1000/200 = 5 IRRmostlikely =15.1%

    Pessimistic Estimate

    $1150 - 170(P/A, IRRpess,8)

    (P / A, IRRpess,8) = 1150/170 = 6.76 IRRpess= 3.9%

  • 7/30/2019 12 Uncertainty in Future Events

    23/54

    Example 10-3

    From the calculations we conclude that the rate ofreturn for this investment is most likely to be15.1%, but might range from 3.9%to 19.8%.Theinvestment meets the 10%MARRcriterion for two

    of the estimates. These estimates can beconsidered to be scenarios of what may happenwith this project. Since one scenario indicates thatthe project is not attractive, we need to have a

    method of weighting the scenarios or consideringhow likely each is.

  • 7/30/2019 12 Uncertainty in Future Events

    24/54

    Example 10-4

    Compute the mean for each parameter:

    Mean cost = [950 + 4 x 1000+ 1150]/6 = 1016.7

    Mean net annual benefit = [210 + 4 x 200 + 170]/6 = 196.7

    Mean useful life = [12 + 4 x 10+ 8]/6 = 10.0

    Mean salvage life = 100/6 = 16.7

    Compute the mean rate of return:

    PW of cost = PW of benefit

    $1016.7 = 196.7(P/A, IRRbeta,10) + 16.7(P/F,IRRbeta, 10)

    IRRbeta= 14.2%

  • 7/30/2019 12 Uncertainty in Future Events

    25/54

    Probability

  • 7/30/2019 12 Uncertainty in Future Events

    26/54

    Example 10-5

    What are the probability distributions for the annualbenefit and life for the following project? Theannual benefit's most likely value is $8000 with aprobability of 60%. There is a 30% probability that

    it will be $5000, and the highest value that is likelyis $10,000. A life of 6 years is twice as likely as alife of 9 years.

  • 7/30/2019 12 Uncertainty in Future Events

    27/54

    Example 10-5

    Probabilities are given for only two of the possibleoutcomes for the annual benefit. The third value isfound using the fact that the probabilities for thethree outcomes must sum to 1,

    1 = P(Benefit is $5000) + P(Benefit is $8000) +P(Benefit is $10,000)

    P(Benefit is $10,000) = 1 - 0.6 - 0.3 = 0.1

    The probability distribution can then be summarizedin a table.Annual benefit $5000 $8000 $10,000

    Probability 0.3 0.6 0.1

  • 7/30/2019 12 Uncertainty in Future Events

    28/54

    Example 10-5

    The problem statement tells us:

    P(life is 6 years) = 2P(life is 9 years)

    P(6) + P(9)= 1

    Combining these, we write2P(9) + P(9) = 1

    P(9) = 1/3

    P(6) = 2/3

    The probability distribution for the life is P(6) = 66.7%and P(9) = 33.3%.

  • 7/30/2019 12 Uncertainty in Future Events

    29/54

  • 7/30/2019 12 Uncertainty in Future Events

    30/54

    Joint ProbabilityDistributionsThe project described in the previous example has a

    first cost of $25,000. The firm uses an interest rateof 10%. Assume that the probability distributionsfor annual benefit and life are unrelated or

    statistically independent. Calculate the probabilitydistribution for the PW.

  • 7/30/2019 12 Uncertainty in Future Events

    31/54

    Example 10-6

    Since there are three outcomes for the annual benefit andtwo outcomes for the life, there are six combinations.The first four columns of the following table show thesix combinations of life and annual benefit. Theprobabilities in columns 2 and 4 are multiplied to

    calculate the joint probabilities in column 5. Forexample, the probability of a low annual benefit and ashort life is 0.3 x 2/3, which equals 0.2 or 20%.

    The PW values include the $25,000 first cost and the

    results of each pair of annual benefit and life. Forexample, the PW for the combination of high benefitand long life is:

  • 7/30/2019 12 Uncertainty in Future Events

    32/54

    Example 10-6

    Annual

    BenefitProbability Life Probability

    Joint

    ProbabilityPW

    $5,000 30% 6 66.70% 20.00% -3,224

    8,000 60 6 66.7 40 9,842

    10,000 10 6 66.7 6.7 18,553

    5,000 30 9 33.3 10 3,795

    8,000 60 9 33.3 20 21,072

    10,000 10 9 33.3 3.3 32,590

    100.00%

  • 7/30/2019 12 Uncertainty in Future Events

    33/54

    Probability distribution function for PW

  • 7/30/2019 12 Uncertainty in Future Events

    34/54

    Expected Value

    The first cost of the project in Example 10-5 is $25,000.

    Use the expected values for annual benefits and life toestimate the present worth. Use an interest rate of 10%.

  • 7/30/2019 12 Uncertainty in Future Events

    35/54

    Example 10-7

    EVbenefit = 5000(0.3) + 8000(0.6) + 10,000(0.1) =$7300

    EVlife = 6(2/3) + 9(1/3) = 7 years

    The PW using these values is

    PW(EV) = -25,000 + 7300(P/A, 10%,7) = -25,000+6500(4.868) =$10,536

    [Note: This is the present worth of the expectedvalues, PW(EV), not the expected value of thepresent worth, EV(PW). It is an easy value tocalculate that approximates the EV(PW), whichwill be computed using the joint probability

  • 7/30/2019 12 Uncertainty in Future Events

    36/54

    Example 10-8

    Use the probability distributionfunction of thePWthatwas derivedin Example 10-6 to calculate theEV(PW). Does this indicate an attractive project?

    The table from Example 10-6 can be reused withone additional column for the weighted values ofthe PW (= PW x probability). Then, the expectedvalue of the PW is calculated by summing the

    column of present worth values that have beenweighted by their probabilities.

  • 7/30/2019 12 Uncertainty in Future Events

    37/54

    Example 10-8

    Annual

    Benefit

    Probabilit

    yLife

    Probabilit

    y

    Joint

    Probabilit

    y

    PW

    PW xJoint

    Probability

    $5,000 30% 6 66.70% 20.00% -3,224 -$ 645

    8,000 60 6 66.7 40 9,842 3,937

    10,000 10 6 66.7 6.7 18,553 1,237

    5,000 30 9 33.3 10 3,795 380

    8,000 60 9 33.3 20 21,072 4,214

    10,000 10 9 33.3 3.3 32,590 1,086100.00% EV(PW) = $ 10,209

  • 7/30/2019 12 Uncertainty in Future Events

    38/54

    Example 10-8

    With an expected PW of $10,209, this is an attractiveproject. While there is a 20% chance of a negative PW,the possible positive outcomes are larger and morelikely. Having analyzed the project under uncertainty,

    we are much more knowledgeable about the potentialresult of the decision to proceed.

    The 10,209 value is more accurate than the approximatevalue calculated in Example10-7. The values differbecause PW is a nonlinear function of the life. The

    more accurate value of $10,209 is lower because theannual benefit values for the longer life are discountedby 1/(1 + i) for more year.

  • 7/30/2019 12 Uncertainty in Future Events

    39/54

    Example 10-9

    A dam is being considered to reduce river flooding.But if a dam is built, what height should it be?Increasing the dam's height will (1) reduce aflood's probability, (2) reduce the damage when

    floods occur, and (3) cost more. Which dam heightminimizes the expected total annual cost? Thestate uses an interest rate of 5% for floodprotection projects, and all the dams should last

    50 years.

  • 7/30/2019 12 Uncertainty in Future Events

    40/54

    Example 10-9

    Dam

    Height (ft)First Cost

    Annual

    P (flood) x Height

    Damages If

    Flood Occurs

    No dam $0 0.25 $800,000

    20 700,000 0.05 500,000

    30 800,000 0.01 300,000

    40 900,000 0.002 200,000

  • 7/30/2019 12 Uncertainty in Future Events

    41/54

    Example 10-9

    The easiest way to solve this problem is to choosethe dam height with the lowest equivalent uniformannual cost (EUAC). Calculating the EUAC of thefirst cost requires multiplying the first cost by (A/P,

    5%, 50). For example, for the dam 20ft high this is700,000(A/P,5%, 50)=$38,344.

    Then the EUAC of the first cost and the expectedannual flood damage are added together to find

    the total EUAC for each height. The 30 ft dam issomewhat cheaper than the 40 ft dam.

  • 7/30/2019 12 Uncertainty in Future Events

    42/54

    Example 10-9

    Dam height (ft)EUAC of first

    cost

    Expected

    annual flood

    damages

    Total Expected

    EUAC

    No dam $0 $200,000 $200,000

    20 38,344 25,000 63,344

    30 43,821 3000 46,821

    40 49,299 400 49,699

  • 7/30/2019 12 Uncertainty in Future Events

    43/54

    Risk

    Risk can be thought of as the chance of getting anoutcome other than the expected value with anemphasis on something negative.

    One common measure of risk is the probability of

    a loss (see Example 10-6).

    The other common measureis the standarddeviation (a), which measures the dispersion ofoutcomes about the expected value

  • 7/30/2019 12 Uncertainty in Future Events

    44/54

    Example 10-13

    Using the probability distribution for thePW from Example 10-6, calculate thePW's standard deviation.

  • 7/30/2019 12 Uncertainty in Future Events

    45/54

    Example 10-13

    Annual

    Benefit

    Probab

    ilityLife

    Probabilit

    y

    JointProbabil

    ity

    PWPW x

    Probability

    PW2 xProbability

    $5,000 30% 6 66.70% 20.00% -3,224 -$ 645 $ 2,079,480

    8,000 60 6 66.7 40 9,842 3,937 38,747,954

    10,000 10 6 66.7 6.7 18,553 1,237 22,950,061

    5,000 30 9 33.3 10 3,795 380 1,442,100

    8,000 60 9 33.3 20 21,072 4,214 88,797,408

    10,000 10 9 33.3 3.3 32,590 1,086 35,392,740

    100.00% 10,209 189,409,745

  • 7/30/2019 12 Uncertainty in Future Events

    46/54

    Risk Versus Return

    Example 10-14

    A large firm is discontinuing an older product, so somefacilities are becoming available for other uses. Thefollowing table summarizes eight new projects that

    would use the facilities. Considering expected returnand risk, which projects are good candidates? The firmbelieves it can earn 4% on a risk-free investmentinggovernment securities (labeed as project F).

  • 7/30/2019 12 Uncertainty in Future Events

    47/54

    Example 10-14

    Project IRR Standard Deviation1 13.10% 6.50%

    2 12 3.9

    3 7.5 1.5

    4 6.5 3.55 9.4 8

    6 16.3 10

    7 15.1 7

    8 15.3 9.4F 4 0

  • 7/30/2019 12 Uncertainty in Future Events

    48/54

    Example 10-14

    Answering the question is far easier ifwe use Figure 10-7.Since a largerexpected return is better, we want to

    select projects that are as "high up" aspossible. Since a lower risk is better, wewant to select project that are as "farleft" as possible. The graph lets usexamine the trade-off of accepting morerisk for a higher return.

  • 7/30/2019 12 Uncertainty in Future Events

    49/54

    Example 10-14

    dominated projects.

    efficient frontier.

  • 7/30/2019 12 Uncertainty in Future Events

    50/54

    Simulation

    Example 10-15 ShipM4U is considering installing a new, more

    accurate scale, which will reduce the error incomputing postage charges and save $250 a year.

    The scale's useful life is believed to be uniformlydistributed over 12, 13, 14, 15,and 16 years. Theinitial cost of the scale is estimated to be normallydistributed with a mean of $1500 and a standarddeviation of $150.

    Use Excel to simulate 25 random samples of theproblem and compute the rate of return for eachsample. Construct a graph of rate of return versusfrequency of occurrence

  • 7/30/2019 12 Uncertainty in Future Events

    51/54

    Example 10-15

    250 Annual savings

    Life First Cost

    Min 12 1500 Mean

    Max 16 150 Std dev

    Iteration IRR

    1 15 1510 14%

    2 13 1217 18%

    3 12 1391 14%

    4 14 1297 17%

    5 13 1621 12%

    25 14 1408 15%

  • 7/30/2019 12 Uncertainty in Future Events

    52/54

    Example 10-15

    0

    1

    1

    2

    2

    3

    3

    4

    4

    5

    8% 9% 10% 11% 12% 13% 14% 15% 16% 17% 18% 19%

    Frequency

    IRR

    IRR vs Frequency

  • 7/30/2019 12 Uncertainty in Future Events

    53/54

    Example 10-16

    Consider the scale described inExample 10-15. Generate 10,000iterations and construct a frequency

    distribution for the scale's rate of return.

  • 7/30/2019 12 Uncertainty in Future Events

    54/54

    10-16