Upload
kirandevi1981
View
220
Download
0
Embed Size (px)
Citation preview
8/13/2019 12 Th HOD Level Presentation Sep 2010
1/15
WELCOMETO THE 12th HOD LEVEL HSEF MEETING
8/13/2019 12 Th HOD Level Presentation Sep 2010
2/15
AGENDA
HSEF PERFORMANCE HIGHLIGHTS: April10 - August10.
ACCIDENT / INCIDENT STATISTICS: Jan.10 - August
10.
KEY POINTS OF THE INTERNAL AUDITS/PLANT LEVEL
SAFETY COMMITTEE MEETINGS/FARs
B. S. C. AUDIT PREPARATION ACTION PLAN
AREAS OF CHALLENGE/CONCERN
8/13/2019 12 Th HOD Level Presentation Sep 2010
3/15
Accident details : APRIL,10 - AUGUST, 10 The complex completed 216 days LTA free man
days by 31stAugust,10. The LTI injury accidentwas on 27.01.2010
Incident Details
26.6.2010- PE bagging- Sweep drum tumbled and fell down hittingperson near eye during trolley pushing job.First aid injury.
14.07.2010- ETP-Sulfuric acid spillage due to failure of tanker from
welding during pressure transfer of the acid.
01.09.2010 Truck lane-Fall& crush by trailer during attempt for free
ride-fatal road accident.
04.09.2010- Injury on feet due to struck by falling radiant tube- LTI
Injury
8/13/2019 12 Th HOD Level Presentation Sep 2010
4/15
8/13/2019 12 Th HOD Level Presentation Sep 2010
5/15
Highlight contd
HAZOP study carried outUnloading H2SO4 from road tanker in ETP.
Modification of logic for off spec. operation in green oil absorber in
olefins.
Provision of new catalyst tank in PE plant.
PSUSR ConductedHeavy slope oil loading facility in off site tank farm.
New chiller unit in PE plant.
Sulphuric acid unloading at ETP done.
8/13/2019 12 Th HOD Level Presentation Sep 2010
6/15
Highlight contdIllumination level survey done in Olefins plant, PP plant , Offsite
tank farm and bagging (New Initiative)-21 location illumination levelswere found less compliance done
SMS Audit of PP, PE, Olefins and PPOU plant done and report
circulated for compliance.
Re-structuring of Safety Committees done.
Safety Ambassadors meeting started.
Document prepared for renewal of license for storage and use of
nucleonic gauges
8/13/2019 12 Th HOD Level Presentation Sep 2010
7/15
Highlight contd
Annual checking and maintenance of all fixed water spray
system of the plants and sprinkler systems of the buildings
completed.
Semi annual maintenance of all fire extinguishers completed.
Licenses received from Federal Ministry of Environment for two
years ( 13thSept. 2010 to 12thSept.2012)
Operation of ETP and discharge of effluent.
Operation for sludge incinerator.
Operation for Polymer incinerator
8/13/2019 12 Th HOD Level Presentation Sep 2010
8/15
TRAINING HIGHLIGHTS
Training
Programs
Targetfor
2010
YTD
(%)Jan Feb March April May June July Aug
First Aid
Training140 20.7 0 0 0 10 0 0 0 19
Fire Fighting 540 45 0 0 0 43 51 23 72 54
Safety Training 540 48 10 0 06 0 54 116 63 10
Safety
Induction
Training(Contractors
/Visitors)
NA NA 10 432 39 110 106 151 40 31
8/13/2019 12 Th HOD Level Presentation Sep 2010
9/15
ACCIDENT / INCIDENT STATISTICS
January 2010- August 2010
8/13/2019 12 Th HOD Level Presentation Sep 2010
10/15
Annual Plan highlights : Jan-August10
Sr.
No
Activities Target Completed Not Done
1 Internal Audit 8 8 0
2 Safety Shower
Maintenance8 8 0
3 Noise/BT/VOC/RadiationMonitoring
8 7 One Radiationsurvey was not done
as meter was sent
for calibration
4 Trip and interlock by
pass
2 2 0
5 Gas Detectors
maintenance2 2 0
6 Safety Committee
Meetings56 49 7-Due to TAM
8/13/2019 12 Th HOD Level Presentation Sep 2010
11/15
Pending Action points of HSE meetings/ Audits
and FAR recommendations
Dept Pending Responsibility Target Date/ Status
ETP Caustic Separator
tank area cable
support is badly
corrodedcables
hanging
Neeraj Gupta PendingFollow up
done- revised date30th
Sept.2010
ETP Caustic separator
tank area flooring
is badly damaged
impervious coating
is needed
Neeraj Gupta Caustic separator tank
area flooring is badly
damaged impervious
coating is needed
Olefins
Plant
Plugging of all LPD
/ HPV in Olefins
Plant
Phool Singh Audit done on
17.09.2010 still un
plugged LPDs found.
8/13/2019 12 Th HOD Level Presentation Sep 2010
12/15
Pending Action points of HSE meetings/ Audits
and FAR recommendations
Dept Pending Responsibility Target Date/
Status
Gate B Road from gate A to Gate
B Material entry security
office is badly damagedand require repair and
asphalting
H. S. Chauhan The repairing of
road is done. The
Asphalting will bedone after road
settlement
PE
ware
house
The Eat side road at the
turning from where all the
trailers are entering to bewidened by providing
concrete slabs on the drain
channels
H S Chauhan Job is over
(curing is in
progress )
8/13/2019 12 Th HOD Level Presentation Sep 2010
13/15
B.S.C. Audit Action planSr.
No
Planning Step Target date
1- B.S.C related additional procedure making 11th-13 th September 10
2- Internal auditor meeting, File list making, audit
checklist segregation.
14thSeptember 10
3- First internal audit of plant and facilities
Scoring of plant and facilities
20th-22thSeptember 10
4- Finding presentation to Management, HODs
and safety ambassadors for compliance
25thSeptember10
5- Risk assessment drive 21st-28thSeptember10
6- First complex level audit and rating by selected
auditors and complex internal rating
4th6th October 10
7- Finding presentation to Management, HODs
and safety ambassadors for compliance
11thOctober10
8- Compliance follow up 15th16thOctober 10
PENDING POINTS OF THE 11TH HOD
8/13/2019 12 Th HOD Level Presentation Sep 2010
14/15
PENDING POINTS OF THE 11THHOD
LEVEL MEETING
Tanker/Trailer condition to be checked with checklist
before it is released from main gate . Leaky sulfuric acid
tanker came in ETP plant (11/09/10)
Many heavy trailers run adjacent to PE plant, newloading bay work to be expedited. ( Job will get
completed in this month. )
Audit by B.S.C .is scheduled on. 6th of December to10th December
8/13/2019 12 Th HOD Level Presentation Sep 2010
15/15
AREAS OF CHALLENGE/ CONCERN
Road traffic Control--- Security to accept ownership.
PPE compliance needs further strengthening.
Risk assessment of all jobs to be done in plants/ facilities
by Mechanical ,Civil, Electrical , instrument and non routine
process job.