Upload
manal-ali-ghanem
View
213
Download
0
Embed Size (px)
Citation preview
7/31/2019 11 Project Management l11
1/29
PROJECT MANAGEMENT
Risk management part 2
1
7/31/2019 11 Project Management l11
2/29
Today outline2
Quantitative Risk analysis
Risk Response Planning
Risk Monitoring and Control
7/31/2019 11 Project Management l11
3/29
Quantitative Risk analysis3
The Quantitative Risk Analysis process analyzes the
effect of those risk events and assigns a numerical
rating to those risks
This process uses techniques such as Monte Carlosimulation and decision tree
7/31/2019 11 Project Management l11
4/29
Quantitative Risk Analysis: Inputs, Tools & Techniques,and Outputs
4
7/31/2019 11 Project Management l11
5/29
Inputs5
Organizational Process Assets
Project Scope Statement
Risk Management Plan
Risk Register
Project Management Plan
7/31/2019 11 Project Management l11
6/29
Tools and Techniques6
1. Data Gathering and Representation Techniques:
Interviewing.
Interviewing techniques are used to quantify the probability
and impact of risks on project objectives Examples of three-point estimates for a cost estimate are shown
in figure. Documenting the rationale of the risk ranges is an
important component of the risk interview, because it can provide
information on reliability and credibility of the analysis.
7/31/2019 11 Project Management l11
7/29
Range of Project Cost Estimates Collected During theRisk Interview
7
7/31/2019 11 Project Management l11
8/29
8
Probability distributions
Continuous probability distributions represent the uncertainty
in values, such as durations of schedule activities and costs
of project components
Two examples of widely used continuous distributions are shown
in figure . These asymmetrical distributions depict shapes that are
compatible with the data typically developed during the project
risk analysis. Uniform distributions can be used if there is no
obvious value that is more likely than any other between
specified high and low bounds, such as in the early concept stageof design.
7/31/2019 11 Project Management l11
9/29
9
7/31/2019 11 Project Management l11
10/29
10
Expert judgment
2. Quantitative Risk Analysis and Modeling Techniques
Sensitivity analysis
Sensitivity analysis helps to determine which risks have the most potential impact onthe project. It examines the extent to which the uncertainty of each project elementaffects the objective being examined when all other uncertain elements are held at
their baseline values. Expected monetary value analysis
Expected monetary value (EMV) analysis is a statistical concept that calculates theaverage outcome when the future includes scenarios that may or may not happen
The EMV of opportunities will generally be expressed as positive values, while thoseof risks will be negative
EMV is calculated by multiplying the value of each possible outcome by itsprobability of occurrence
and adding them together
A common use of this type of analysis is in decision tree analysis
7/31/2019 11 Project Management l11
11/29
11
Decision tree analysis
Decision tree analysis is usually structured using a decision
tree diagram
that describes a situation under consideration, and the
implications of each of the available choices and possible
scenarios
Modeling and simulation
A project simulation uses a model that translates the
uncertainties specified at a detailed level of the project into
their potential impact on project objectives. Simulations are
typically performed using the Monte Carlo technique
7/31/2019 11 Project Management l11
12/29
Outputs12
Risk Register (Updates)
Probabilistic analysis of the project.
Estimates are made of potential project schedule and cost outcomes,listing the possible completion dates and costs with their associatedconfidence levels
Probability of achieving cost and time objectives. With the risksfacing the project, the probability of achieving project objectivesunder the current plan can be estimated using quantitative riskanalysis results
Prioritized list of quantified risks. This list of risks includes those
that pose the greatest threat or present the greatest opportunityto the project
Trends in quantitative risk analysis results. As the analysis isrepeated, a trend may become apparent that leads toconclusions affecting risk responses.
7/31/2019 11 Project Management l11
13/29
Risk Response Planning13
Risk Response Planning is the process of developing options,and determining actions to enhance opportunities andreduce threats to the project's objectives
Risk Response Planning addresses the risks by their priority,
inserting resources and activities into the budget, schedule,and project management plan, as needed.
Contingency plan or Primary and backup strategies may beselected
A fallback plan can be developed for implementation if the
selected strategy turns out not to be fully effective, or if anaccepted risk occurs
Often, a contingency reserve is allocated for time or cost.Finally
7/31/2019 11 Project Management l11
14/29
Risk Response Planning: Inputs, Tools & Techniques, andOutputs
14
7/31/2019 11 Project Management l11
15/29
Inputs15
Risk Management Plan
Risk Register
7/31/2019 11 Project Management l11
16/29
7/31/2019 11 Project Management l11
17/29
17
Strategies for Positive Risks or Opportunities
Three responses are suggested to deal with risks with potentially positiveimpacts on project objectives. These strategies are to exploit, share, orenhance: Exploit. This strategy may be selected for risks with positive impacts where
the organization wishes to ensure that the opportunity is realized. Thisstrategy seeks to eliminate the uncertainty associated with a particularupside risk by making the opportunity definitely happen.
Share. Sharing a positive risk involves allocating ownership to a third partywho is best able to capture the opportunity for the benefit of the project.Examples of sharing actions include forming risk-sharing partnerships, teams,special-purpose companies, or joint ventures, which can be established withthe express purpose of managing opportunities.
Enhance. This strategy modifies the 'size' of an opportunity by increasingprobability and/or positive impacts, and by identifying and maximizing keydrivers of these positive-impact risks
7/31/2019 11 Project Management l11
18/29
18
Strategy for Both Threats and Opportunities
Acceptance: A strategy that is adopted because it is seldompossible to eliminate all risk from a project. This strategyindicates that the project team has decided not to change
the project management plan to deal with a risk, or isunable to identify any other suitable response strategy.
This strategy can be either passive or active Passive acceptance requires no action, leaving the project team to
deal with the threats or opportunities as they occur
The most common active acceptance strategy is to establish acontingency reserve, including amounts of time, money, orresources to handle known-or even sometimes potential, unknown-threats or opportunities.
7/31/2019 11 Project Management l11
19/29
19
Contingent Response Strategy
Some responses are designed for use only if certain
events occur. For some risks, it is appropriate for the
project team to make a response plan that will only beexecuted under certain predefined conditions, if it is
believed that there will be sufficient warning to
implement the plan. Events that trigger the contingency
response, such as missing intermediate milestones orgaining higher priority with a supplier, should be
defined and tracked.
7/31/2019 11 Project Management l11
20/29
Outputs20
Risk Register (Updates) with:
Identified risks, their descriptions, area(s) of the project (e.g.,WBS element) affected, their causes (e.g., RBS element),and how they may affect project objectives
Risk owners and assigned responsibilities Outputs from the Qualitative and Quantitative Risk Analysis
processes, including prioritized lists of project risks andprobabilistic analysis of the project
Agreed-upon response strategies Specific actions to implement the chosen response strategy
Symptoms and warning signs of risks' occurrence
7/31/2019 11 Project Management l11
21/29
21
Budget and schedule activities required to implement the chosenresponses
Contingency reserves of time and cost designed to provide forstakeholders' risk tolerances
Contingency plans and triggers that call for their execution
Fallback plans for use as a reaction to a risk that has occurred, and theprimary response proves to be inadequate
Residual risks that are expected to remain after planned responses havebeen taken, as well as those that have been deliberately accepted
Secondary risks that arise as a direct outcome of implementing a riskresponse
Contingency reserves that are calculated based on the quantitativeanalysis of the project and the organization's risk thresholds.
7/31/2019 11 Project Management l11
22/29
22
Project Management Plan (Updates)
Risk-Related Contractual Agreements
7/31/2019 11 Project Management l11
23/29
Risk Monitoring and Control23
Risk Monitoring and Control is the process of
identifying, analyzing, and planning for newly
arising risks, keeping track of the identified risks
and those on the watchlist, reanalyzing existingrisks, monitoring trigger conditions for contingency
plans, monitoring residual risks, and reviewing the
execution of risk responses while evaluating their
effectiveness
7/31/2019 11 Project Management l11
24/29
Risk Monitoring and Control: Inputs, Tools & Techniques,and Outputs
24
7/31/2019 11 Project Management l11
25/29
Inputs25
Risk Management Plan
Risk Register
Approved Change Requests
Work Performance Information
Performance Reports
7/31/2019 11 Project Management l11
26/29
Tools and Techniques26
Risk Reassessment
Risk Audits
Risk audits examine and document the effectiveness of
risk responses in dealing with identified risks and theirroot causes, as well as the effectiveness of the riskmanagement process.
Variance and Trend Analysis
Technical Performance Measurement Reserve Analysis
Status Meetings
7/31/2019 11 Project Management l11
27/29
Outputs27
Risk Register (Updates)
Requested Changes
Recommended Corrective Actions
Recommended Preventive Actions
Organizational Process Assets (Updates)
Project Management Plan (Updates)
7/31/2019 11 Project Management l11
28/29
Exercise28
You are planning the installation of hardware and softwarethroughout your company. After your risk managementefforts to eliminate and reduce risks, you are left with thefollowing risks that remain on the project. How much reservewould be needed for time on the project?A. A 25 percent probability of a 4-day delay in receiving
customer approval
B. A 10 percent probability that the equipment installation willtake 40 days less than planned
C. A 50 percent probability that two computers will need to be
returned for poor quality, causing a 20 day delayD. A 30 percent probability that a certain expert will become
available to work on the project, resulting in a 9-day savingsdue to increased productivity
7/31/2019 11 Project Management l11
29/29
Solution29
A. This is a risk, so we add 25 percent X 4 days (+ 1day)
B. This is an opportunity, so we subtract 10 percent X
40 days (- 4 days)C. This is a risk, so we add 50 percent X 20 days (+
10 days)
D. This is an opportunity, so we subtract 30 percent X
9 days (- 3 days) The reserve is therefore +1 4 + 10 3, or 4
days.