11 Project Management l11

Embed Size (px)

Citation preview

  • 7/31/2019 11 Project Management l11

    1/29

    PROJECT MANAGEMENT

    Risk management part 2

    1

  • 7/31/2019 11 Project Management l11

    2/29

    Today outline2

    Quantitative Risk analysis

    Risk Response Planning

    Risk Monitoring and Control

  • 7/31/2019 11 Project Management l11

    3/29

    Quantitative Risk analysis3

    The Quantitative Risk Analysis process analyzes the

    effect of those risk events and assigns a numerical

    rating to those risks

    This process uses techniques such as Monte Carlosimulation and decision tree

  • 7/31/2019 11 Project Management l11

    4/29

    Quantitative Risk Analysis: Inputs, Tools & Techniques,and Outputs

    4

  • 7/31/2019 11 Project Management l11

    5/29

    Inputs5

    Organizational Process Assets

    Project Scope Statement

    Risk Management Plan

    Risk Register

    Project Management Plan

  • 7/31/2019 11 Project Management l11

    6/29

    Tools and Techniques6

    1. Data Gathering and Representation Techniques:

    Interviewing.

    Interviewing techniques are used to quantify the probability

    and impact of risks on project objectives Examples of three-point estimates for a cost estimate are shown

    in figure. Documenting the rationale of the risk ranges is an

    important component of the risk interview, because it can provide

    information on reliability and credibility of the analysis.

  • 7/31/2019 11 Project Management l11

    7/29

    Range of Project Cost Estimates Collected During theRisk Interview

    7

  • 7/31/2019 11 Project Management l11

    8/29

    8

    Probability distributions

    Continuous probability distributions represent the uncertainty

    in values, such as durations of schedule activities and costs

    of project components

    Two examples of widely used continuous distributions are shown

    in figure . These asymmetrical distributions depict shapes that are

    compatible with the data typically developed during the project

    risk analysis. Uniform distributions can be used if there is no

    obvious value that is more likely than any other between

    specified high and low bounds, such as in the early concept stageof design.

  • 7/31/2019 11 Project Management l11

    9/29

    9

  • 7/31/2019 11 Project Management l11

    10/29

    10

    Expert judgment

    2. Quantitative Risk Analysis and Modeling Techniques

    Sensitivity analysis

    Sensitivity analysis helps to determine which risks have the most potential impact onthe project. It examines the extent to which the uncertainty of each project elementaffects the objective being examined when all other uncertain elements are held at

    their baseline values. Expected monetary value analysis

    Expected monetary value (EMV) analysis is a statistical concept that calculates theaverage outcome when the future includes scenarios that may or may not happen

    The EMV of opportunities will generally be expressed as positive values, while thoseof risks will be negative

    EMV is calculated by multiplying the value of each possible outcome by itsprobability of occurrence

    and adding them together

    A common use of this type of analysis is in decision tree analysis

  • 7/31/2019 11 Project Management l11

    11/29

    11

    Decision tree analysis

    Decision tree analysis is usually structured using a decision

    tree diagram

    that describes a situation under consideration, and the

    implications of each of the available choices and possible

    scenarios

    Modeling and simulation

    A project simulation uses a model that translates the

    uncertainties specified at a detailed level of the project into

    their potential impact on project objectives. Simulations are

    typically performed using the Monte Carlo technique

  • 7/31/2019 11 Project Management l11

    12/29

    Outputs12

    Risk Register (Updates)

    Probabilistic analysis of the project.

    Estimates are made of potential project schedule and cost outcomes,listing the possible completion dates and costs with their associatedconfidence levels

    Probability of achieving cost and time objectives. With the risksfacing the project, the probability of achieving project objectivesunder the current plan can be estimated using quantitative riskanalysis results

    Prioritized list of quantified risks. This list of risks includes those

    that pose the greatest threat or present the greatest opportunityto the project

    Trends in quantitative risk analysis results. As the analysis isrepeated, a trend may become apparent that leads toconclusions affecting risk responses.

  • 7/31/2019 11 Project Management l11

    13/29

    Risk Response Planning13

    Risk Response Planning is the process of developing options,and determining actions to enhance opportunities andreduce threats to the project's objectives

    Risk Response Planning addresses the risks by their priority,

    inserting resources and activities into the budget, schedule,and project management plan, as needed.

    Contingency plan or Primary and backup strategies may beselected

    A fallback plan can be developed for implementation if the

    selected strategy turns out not to be fully effective, or if anaccepted risk occurs

    Often, a contingency reserve is allocated for time or cost.Finally

  • 7/31/2019 11 Project Management l11

    14/29

    Risk Response Planning: Inputs, Tools & Techniques, andOutputs

    14

  • 7/31/2019 11 Project Management l11

    15/29

    Inputs15

    Risk Management Plan

    Risk Register

  • 7/31/2019 11 Project Management l11

    16/29

  • 7/31/2019 11 Project Management l11

    17/29

    17

    Strategies for Positive Risks or Opportunities

    Three responses are suggested to deal with risks with potentially positiveimpacts on project objectives. These strategies are to exploit, share, orenhance: Exploit. This strategy may be selected for risks with positive impacts where

    the organization wishes to ensure that the opportunity is realized. Thisstrategy seeks to eliminate the uncertainty associated with a particularupside risk by making the opportunity definitely happen.

    Share. Sharing a positive risk involves allocating ownership to a third partywho is best able to capture the opportunity for the benefit of the project.Examples of sharing actions include forming risk-sharing partnerships, teams,special-purpose companies, or joint ventures, which can be established withthe express purpose of managing opportunities.

    Enhance. This strategy modifies the 'size' of an opportunity by increasingprobability and/or positive impacts, and by identifying and maximizing keydrivers of these positive-impact risks

  • 7/31/2019 11 Project Management l11

    18/29

    18

    Strategy for Both Threats and Opportunities

    Acceptance: A strategy that is adopted because it is seldompossible to eliminate all risk from a project. This strategyindicates that the project team has decided not to change

    the project management plan to deal with a risk, or isunable to identify any other suitable response strategy.

    This strategy can be either passive or active Passive acceptance requires no action, leaving the project team to

    deal with the threats or opportunities as they occur

    The most common active acceptance strategy is to establish acontingency reserve, including amounts of time, money, orresources to handle known-or even sometimes potential, unknown-threats or opportunities.

  • 7/31/2019 11 Project Management l11

    19/29

    19

    Contingent Response Strategy

    Some responses are designed for use only if certain

    events occur. For some risks, it is appropriate for the

    project team to make a response plan that will only beexecuted under certain predefined conditions, if it is

    believed that there will be sufficient warning to

    implement the plan. Events that trigger the contingency

    response, such as missing intermediate milestones orgaining higher priority with a supplier, should be

    defined and tracked.

  • 7/31/2019 11 Project Management l11

    20/29

    Outputs20

    Risk Register (Updates) with:

    Identified risks, their descriptions, area(s) of the project (e.g.,WBS element) affected, their causes (e.g., RBS element),and how they may affect project objectives

    Risk owners and assigned responsibilities Outputs from the Qualitative and Quantitative Risk Analysis

    processes, including prioritized lists of project risks andprobabilistic analysis of the project

    Agreed-upon response strategies Specific actions to implement the chosen response strategy

    Symptoms and warning signs of risks' occurrence

  • 7/31/2019 11 Project Management l11

    21/29

    21

    Budget and schedule activities required to implement the chosenresponses

    Contingency reserves of time and cost designed to provide forstakeholders' risk tolerances

    Contingency plans and triggers that call for their execution

    Fallback plans for use as a reaction to a risk that has occurred, and theprimary response proves to be inadequate

    Residual risks that are expected to remain after planned responses havebeen taken, as well as those that have been deliberately accepted

    Secondary risks that arise as a direct outcome of implementing a riskresponse

    Contingency reserves that are calculated based on the quantitativeanalysis of the project and the organization's risk thresholds.

  • 7/31/2019 11 Project Management l11

    22/29

    22

    Project Management Plan (Updates)

    Risk-Related Contractual Agreements

  • 7/31/2019 11 Project Management l11

    23/29

    Risk Monitoring and Control23

    Risk Monitoring and Control is the process of

    identifying, analyzing, and planning for newly

    arising risks, keeping track of the identified risks

    and those on the watchlist, reanalyzing existingrisks, monitoring trigger conditions for contingency

    plans, monitoring residual risks, and reviewing the

    execution of risk responses while evaluating their

    effectiveness

  • 7/31/2019 11 Project Management l11

    24/29

    Risk Monitoring and Control: Inputs, Tools & Techniques,and Outputs

    24

  • 7/31/2019 11 Project Management l11

    25/29

    Inputs25

    Risk Management Plan

    Risk Register

    Approved Change Requests

    Work Performance Information

    Performance Reports

  • 7/31/2019 11 Project Management l11

    26/29

    Tools and Techniques26

    Risk Reassessment

    Risk Audits

    Risk audits examine and document the effectiveness of

    risk responses in dealing with identified risks and theirroot causes, as well as the effectiveness of the riskmanagement process.

    Variance and Trend Analysis

    Technical Performance Measurement Reserve Analysis

    Status Meetings

  • 7/31/2019 11 Project Management l11

    27/29

    Outputs27

    Risk Register (Updates)

    Requested Changes

    Recommended Corrective Actions

    Recommended Preventive Actions

    Organizational Process Assets (Updates)

    Project Management Plan (Updates)

  • 7/31/2019 11 Project Management l11

    28/29

    Exercise28

    You are planning the installation of hardware and softwarethroughout your company. After your risk managementefforts to eliminate and reduce risks, you are left with thefollowing risks that remain on the project. How much reservewould be needed for time on the project?A. A 25 percent probability of a 4-day delay in receiving

    customer approval

    B. A 10 percent probability that the equipment installation willtake 40 days less than planned

    C. A 50 percent probability that two computers will need to be

    returned for poor quality, causing a 20 day delayD. A 30 percent probability that a certain expert will become

    available to work on the project, resulting in a 9-day savingsdue to increased productivity

  • 7/31/2019 11 Project Management l11

    29/29

    Solution29

    A. This is a risk, so we add 25 percent X 4 days (+ 1day)

    B. This is an opportunity, so we subtract 10 percent X

    40 days (- 4 days)C. This is a risk, so we add 50 percent X 20 days (+

    10 days)

    D. This is an opportunity, so we subtract 30 percent X

    9 days (- 3 days) The reserve is therefore +1 4 + 10 3, or 4

    days.